item - reports · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w...

53
Item ____IPP09_______ - REPORTS -______05/10/2016_________ N O R T H S Y D N E Y C O U N C I L R E P O R T S NSIPP MEETING HELD ON 5/10/2016 Attachments: Site Plan Architectural plans & sections ADDRESS/WARD: 5 McHatton Street, Waverton (W) APPLICATION No: DA207/2016 PROPOSAL: Alterations and additions to dwelling house, demolition of existing tennis court and construct basement garage containing parking for five (5) cars, gym, media room, rainwater tank and on site detention system and reconstruction of tennis court over. PLANS REF: Drawings numbered 1506/DA01A and 1506/DA02, dated May 2016, and 1506/DA03, dated June 2016, drawn by Kenstrom Design Pty Ltd and received by Council on 8 June 2016 OWNER: Richard Elmslie and Leslie Tilly APPLICANT: Kenstrom Design Pty Ltd AUTHOR: Geoff Goodyer, Consultant Town Planner Symons Goodyer Pty Ltd DATE OF REPORT: 13 September 2016 DATE LODGED: 8 June 2015 AMENDED: 1 September 2016 RECOMMENDATION Approval

Upload: others

Post on 25-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Item ____IPP09_______ - REPORTS -______05/10/2016_________

N O R T H S Y D N E Y C O U N C I L R E P O R T S

NSIPP MEETING HELD ON 5/10/2016

Attachments:

Site Plan

Architectural plans & sections

ADDRESS/WARD: 5 McHatton Street, Waverton (W)

APPLICATION No: DA207/2016

PROPOSAL: Alterations and additions to dwelling house, demolition of

existing tennis court and construct basement garage containing

parking for five (5) cars, gym, media room, rainwater tank and

on site detention system and reconstruction of tennis court

over.

PLANS REF: Drawings numbered 1506/DA01A and 1506/DA02, dated May

2016, and 1506/DA03, dated June 2016, drawn by Kenstrom

Design Pty Ltd and received by Council on 8 June 2016

OWNER: Richard Elmslie and Leslie Tilly

APPLICANT: Kenstrom Design Pty Ltd

AUTHOR: Geoff Goodyer, Consultant Town Planner

Symons Goodyer Pty Ltd

DATE OF REPORT: 13 September 2016

DATE LODGED: 8 June 2015

AMENDED: 1 September 2016

RECOMMENDATION Approval

Page 2: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 2

Re: 5 McHatton Street, Waverton

EXECUTIVE SUMMARY

This development application seeks Council’s approval for alterations and additions to

dwelling house, demolition of existing clay base tennis court and construct a new basement

garage containing parking for five (5) cars, gym, media room, rainwater tank and on site

detention system and reconstruction of tennis court over, with the tennis court reinstated in its

current position and level. Existing tennis court lighting poles are proposed to be removed

and replaced as part of this proposal.

The application is reported to NSIPP as the site is opposite the residence of an elected

Councillor.

Council’s notification of the proposal has attracted two (2) neighbour submissions raising

particular concerns about impacts of stormwater runoff, impacts arising from excavation

(noise, dust, debris and damage to properties), and hours of work. The assessment has

considered these concerns as well as the performance of the application against Council’s

planning requirements.

Following this assessment the development application is considered to be reasonable in the

circumstances and is recommended for approval subject to conditions.

Development Services comment:

This application was referred to a consultant planner for assessment to avoid possible conflict

of interest arising from the nearby residence of a serving Councillor. The primary issue turns

on compliance with the applicable site cover, un-built upon and landscape area controls. In

this case the proposal is to remove an existing tennis court, excavate and provide below

ground car parking and media room, and reinstate the above ground tennis court. The end

result will generally be identical to that as existing in this regard. The exceedances of the un-

built upon and landscape area controls are substantial and in the normal course would warrant

refusal. The site is, however, unusual and unique in that it comprises a heritage item with an

annexed site containing a tennis court. The development will provide extra facilities with

minimal impact on the heritage item or its setting. The issue of the additional parking bays

and Council’s code is noted but is considered in itself acceptable given the quality of the

residence and the fact that traffic generation will be governed by the number of occupants in

the dwelling. It is open to the Panel to adopt the consultant’s recommendations should it feel

the merit of the proposal so warrants.

Page 3: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

LOCATION MAP

STRE

ET

HARRIOTT

KING

LANE

HARRIOTT STREET

NEST

WAVERTO

N LANE

BERRY

STREET

ROAD

EDWARD

LANE

DOOHAT AVENUE

BRO

WN

S LA

NE

ROAD

RES ER

VE

PRIORY

BROWNS LANE WEST

HIGHW

AY

BROW

NS

ROAD

HAZELBANK

McHATTON

STREET

LANE

LANE

CHURCH STREET

STREET

CHURCH

ROAD

WES

T(32)

49A

(34)(36)

51

1

5355

5

7

9

1113

1514 17

16

19-21

41-45

13

10

47A

47

51

12

53

55

20

59-61

57

39

37

21

16

14

9

1921

21 23

42

17

25-29

49-51

2-4

6

14-16

1A

15

22

23

22

22A

20

24

18

17

1B

2

25

35

26

16

3

13-15

28

29

1

31

8-10

74

6

30

31

7-94

52

(18)

33

3

70

35

1

29A

37

39

29

66

64

68

39A

1

27A

62

27

41

58

3

2

25

56

32

54

5

1A

23

1

34

52

41A

18

21

7

50

20

1

36

43

2

22

48

19

9

38

45

24

4

26

11

2

17

40

47

5

2A

6

46

8

33

44

15

8

12

53

6

18

11 46

55

9 48

4

2B

57

50

7

5A 59

5

52 154

31

61

54

156-158

7

63

5

9

56

31

11

65 160

11A

58 1517

67

3

166

1

40-42 168

3828

26 170

2422

20

225

15

18 172

1116

12-14

10A 10 8B 8A6

174-180

4

245

3

182

1

810

12

1412

1610

86

18

297

11

190

8295

7-9281

60

58

56

3

54A 273

17

7154

6952

6750

6548

6346

271

6144

59

15

57

55

53

12

51

10A

267

10

188

265 8A8

261

6

49

(32)

42

2

11A

30 255- 259

28

26

253

22

4005438

346199 2

718775 1041055

C

SP 35807 1

961905

192D 7

4029

18982

102

SP 21216

SP 3524

840673

101

SP 3

355

542745

18

SP 12537

69667892

38200310

18982

90274

89

7354

390349 X

1

SP 46122

SP 69516

392635 SP 1253

Sec 3

7544

B

439765

SP 3762Sec

3A

Sec 3

XY

7354

A5

B

B

SP 6786

4

501480

331344

C

3454

411

SP 2885SP 17689

SP 2074

SP 28561

SP 12299

SP 12300

SP 15908

SP 3428815

SP 2258SP 49611

SP 11588

SP 4173

SP 4120

SP 301512

SP 52008

SP 7352

SP 8831

SP 13981

SP 1082

1 772782

SP 472

SP 673

3

16

SP 14195

618A

SP 34511

5SP 362

4492

37

18B

1

SP 15394

SP 118

17

339128

17640SP 1195

SP 241

SP 3067

SP 328

SP 20398

SP 761

7

SP 4743

SP 19781

9

50132

2 3266641

SP 14035

10730

1073

0

306450

SP 3470

8

2

23

SP 64339 1

SP 3275

SP 19191

2

SP 18287

102

CT 18

1

366061

24

875349

22

31

10730

2

20

7

7544

SP 21257

Sec 2

1

3

Sec 2

817407

7544SP 2944

SP 88623 Sec 1

23

7544

8 17

2

9SP 30799 8

3

7544 999946862075

Sec 1

6426

3 17

2 1

1 25

237104973946SP 1331527

8869DRAINAGE

R

ESERVE

5

2 6 Sec 1165897

7544

15 8869

2

SP 7965

SP 87270 8869

310941

14

11 1 9

Sec 37544

7

8SP 12919

SP 136 SP 54872 8

772366

642

17495 166

4849

5051

5253

5455

5657

58

17495 SP 2346

SP 18226

4645

1723344

4342

4140

3938

59

3736

35

1

184559

127

183591

1134

11

SP 76305

996198

1040409

10730

1002384SP 22319

26

11

60

SP 17467

3

10730

2224

28

780423

6

1

628661

72

168106 1

8869

75449

797180SP 12220966223Sec 1

SP 15426

7544 1

21

15

A

SP 340081

7724261168107

25

1

333563

10730

973368Sec 1772373

101

C

120714

5

11

772502

1 3

175453

772367

20

SP 20346

SP 87998

SP 90687

SP 92065

B

10

SP 19533SP 75835

395387

1002607

B

SP 86180

51749576

SP 72629

321904

1714323

1

SP 228702

SP 66868

237104

SP 16134

1195582

8869

4

SP 47053

SP 641861152692

2

SP 54293

100614946

6

101

SP 89685

8869

20744745

18

3264 7319

7212917

12

6162616

1

72870

237104SP 87411

3

13

1

192815

12

14

3

1

6

SP 15475

5

Sec 44038

SP 70609

4

SP 31586

3

SP 14745

Sec 3

4038

1

12

10730

62856616

SP 33792

17495

7816671

11 529352

5107308

62564374141

5538

951

B

Re: Page 3

Property/Applicant Submittors - Properties Notified

5 McHatton Street, Waverton - DA 207/16

Page 4: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 4

Re: 5 McHatton Street, Waverton

DESCRIPTION OF PROPOSAL

Council is in receipt of a proposal to carry out alterations and additions to an existing

dwelling house.

The existing clay base tennis court is to be excavated to provide a subterranean garage for

five (5) cars plus a rainwater tank, gym and media room. The tennis court will then be

reinstated as a new turf court constructed on a concrete base together with re-instatement of

the existing tennis court lights, netting, and a portion of surrounding paving, with all

structures located in the same position and same levels/height as existing. When works are

completed the surface of the site will have exactly the same appearance as existing.

The garage is to be accessed via a ramp through the existing garage to the southern side of the

dwelling. The existing turntable and driveway crossing to McHatton Street, along the western

side of the dwelling will be retained. Air conditioning plant for the garage, gym and media

room will be located in an acoustically treated shed which will replace the existing shed

adjacent to the tennis court behind the front fence.

Excavation will require the removal of part of the existing brick wall and metal palisade

fence to McHatton Street to provide construction vehicle access. Upon completion of works

the wall and palisade fence is to be rebuilt using salvaged material to match existing.

Excavated material will be removed from the site by excavator and loaded into trucks parked

in a construction zone in front of the site on the street.

The proposal includes the installation of a new on-site stormwater detention tank and

connection to the existing stormwater system.

STATUTORY CONTROLS

North Sydney LEP 2013

Zoning – R2 Low Density Residential

Item of Heritage - No

In Vicinity of Item of Heritage – Yes

Conservation Area - Yes (contributory item within the Crows Nest Road

Conservation Area)

FSBL - No

Environmental Planning & Assessment Act 1979

SEPP BASIX

SEPP 55 - Contaminated Lands

Local Development

POLICY CONTROLS

DCP 2013

DESCRIPTION OF LOCALITY

The site is located on the southern side of McHatton Street. The immediate locality is

characterised by 1-storey and 2-storey dwelling houses in landscaped settings. Adjacent to

the site on the eastern side is the North Sydney Demonstration School (the fence and gates of

which are listed as a heritage item of local significance). 100 metres to the east of the site on

Pacific highway the character is quite different, being a mix of commercial and residential

land uses.

Page 5: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 5

Re: 5 McHatton Street, Waverton

Figure 1: Subject Site and lot arrangements

The existing two-storey dwelling house and tennis court on the subject site were constructed

around 1922-1924. They are sited on two separate allotments Lots 27 & 28 in DP 10730. The

dwelling house is constructed of smooth red face-brick with decorative feature brickwork and

a steep, multi-gabelled, glazed terracotta tiled roof. It is identified as a contributory item

within the Crows Nest Road Heritage Conservation Area.

The following photos show the site and general locality:

The front of the subject site, 5

McHatton Street, Waverton.

Page 6: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 6

Re: 5 McHatton Street, Waverton

The existing tennis court on the

subject site, 5 McHatton Street,

Waverton.

The neighbouring house to the

west, 1 McHatton Street.

North Sydney Demonstration

School, to the east of the site on

McHatton Street.

RELEVANT HISTORY

DA 218/2005 was approved on 27 September 2005 for alterations and additions to the

existing dwelling house including a lap pool and tennis court lighting.

On 21 January 2016, a pre-DA lodgement Meeting was held with Council in relation to the

proposed application.

Page 7: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 7

Re: 5 McHatton Street, Waverton

The current development application was lodged on 8 June 2016 and placed on notification

from 24 June to 8 July 2016.

REFERRALS

Engineering

Council’s Development Assessment Engineer has raised no objections and provided

recommended engineering conditions should the application be approved.

Heritage

The application was referred to Council’s conservation Planner who made the following

comments:

1. Heritage Status and Significance

The property is identified as a contributory item within the Crows Nest Road

Conservation Area, ‘a good example of Inter-War Old English style residence and

originally forming part of the Berry Estate 1921. Highly intact. An asymmetrical

broad fronted two storey dwelling with projecting gables with decorative

brickwork, projecting bracketed casement assemblies, leadlight glazing and ogee

copper or lead sheet roofing to bay. Dichromatic face brickwork to gables’

It is located directly adjacent to a heritage item, being North Sydney

Demonstration School.

Located within a row of contributory items from 1 – 5 Crows Nest Road.

2. The property

The property contains a two storey face brick Federation Queen Anne dwelling,

known as ‘Middleton’, with adjacent lawn tennis court on a separate allotment. The

house is largely intact with a later addition and swimming pool at the rear, and a

driveway accessing an existing garage, also at the rear. It is set on established formal

gardens with the tennis court to the east of the house.

3. The proposal

The proposal is for the excavation of a basement garage, media room, gym and OSD

tank, located under the existing tennis court, with car access through the existing

garage. A section of the existing fence will be removed during construction, and then

reinstated. The tennis court will be reinstated above the basement garage, once

construction has been completed.

4. Heritage Impact Assessment and Recommendations

An assessment of the proposed works at No. 5 McHatton Street has been undertaken

in relation to Part 5 Clause 5.10 (Heritage Conservation) of the North Sydney LEP

2013 and Section 13 (Heritage and Conservation) of the North Sydney DCP 2013.

Page 8: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 8

Re: 5 McHatton Street, Waverton

The property is located within the Crows Nest Road Conservation Area and is

identified as being a contributory item. It contains a two storey dwelling, known as

Middleton, built in the Federation Queen Anne Style, which is largely intact, with

some modifications to the rear. It has a lawn tennis court to its east, located on a

separate allotment.

The proposal is for the excavation of a basement garage, media room, gym and OSD

tank, located under the existing tennis court, with car access through the existing

garage. A section of the existing fence will be removed during construction, and then

reinstated. The tennis court will be reinstated above the basement garage, once

construction has been completed.

The proposal involves some demolition and reconfiguration works to the existing

dwelling to allow for access into the basement garage. These works are to a recent

addition and do not impact on original or significant fabric. No objections are raised

to these works, as they will not impact on the building’s contribution to the

significance or character of the Bay Road Conservation Area.

The proposed basement garage will not have an impact on the character or the

significance of the conservation area, or the contributory item, as the works are

located under the tennis court, and not visible from the street. The existing driveway

will be used to access the garage. The tennis court will be reinstated in its current

location during the works, as will the front fence. The presentation of the property to

the street will be largely unaltered at the completion of these works.

The proposed works will not impact adversely on the character or significance of the

existing dwelling, which is a contributory item or the Crows Nest Road Conservation

Area. The works will not impact on the significant fabric or curtilage of the adjacent

heritage listed school.

Accordingly, no objections to the proposal are raised on heritage grounds. Should the

application be approved, it is recommended that the following conditions be placed

on the approval:

Standard Conditions

A4 No demolition of extra fabric

C13 Colours, Finishes and Materials (Conservation Areas)

E11 Removal of extra fabric

Site Specific condition

Front Fence: the front fence is to be reinstated at the completion of the works, to

exactly match the existing fence in terms of materials, height, location and detail.

(Reason: to minimise impact on the conservation area)

SUBMISSIONS

The owners of adjoining properties and the Waverton Precinct were notified of the proposed

development and the application placed on notification from 24 June 2016 to 8 July 2016.

The notification resulted in the following submissions being received raising concern with the

proposal:

Page 9: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 9

Re: 5 McHatton Street, Waverton

Basis of Submissions

Impact of excavation works.

Ensuring the existing hedge is retained for privacy.

Ensuring the existing tennis court level and lighting is retained to prevent

unacceptable lightspill.

Ensuring vents from the garage do not affect the property of the school.

Concern regarding any new stormwater piping off-site.

Preparation of dilapidation reports.

Impacts from stormwater run-off.

Noise related to excavation.

Dust and debris related to excavation.

Damage to adjoining properties arising from excavation.

CONSIDERATION

The relevant matters for consideration under Section 79C of the Environmental Planning and

Assessment Act 1979, are assessed under the following headings:

The application has been assessed against the relevant numeric controls in NSLEP 2013 and

DCP 2013 as indicated in the following compliance tables. More detailed comments with

regard to the major issues are provided later in this report.

NSLEP 2013 Compliance Table

Principal Development Standards – North Sydney Local Environmental Plan 2013

Site Area – 1475.7m² Proposed Control Complies

Clause 4.3(2) – Height of buildings 1.7 metres 8.5 metres YES

DCP 2013 Compliance Table

DEVELOPMENT CONTROL PLAN 2013 – Part B Section 1 - Residential Development

complies Comments

1.2 Social Amenity

Maintaining residential accommodation Yes The proposal will maintain the existing residential

accommodation.

Affordable housing Yes The proposed development will not alter the levels of

affordable housing in the area.

1.3 Environmental Criteria

Topography Yes Finished ground levels match existing ground levels.

Two habitable rooms are located below ground level,

but in this case the rooms are considered to provide

satisfactory amenity for the proposed uses (media

room and gymnasium) and are provided with suitable

ventilation. No excavation is proposed within 1 metre

of any property boundary.

Views Yes The proposal does not obstruct any public or private

views.

Solar access Yes AS proposed ground levels match existing ground

levels all solar access to the site and neighbouring

properties is maintained.

Acoustic privacy Yes Air conditioning plant is to be acoustically housed in

a shed that is located on a part of the site well

separated from neighbouring properties.

Visual privacy Yes The proposal will not result in any overlooking as all

existing ground levels are retained.

Page 10: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 10

Re: 5 McHatton Street, Waverton

1.4 Quality built form

Context Yes The proposal responds positively to the opportunities

and constraints of the site and maintains the character

of the area.

Subdivision pattern Yes The site comprises two allotments, on containing the

dwelling house and the other the tennis court. The

proposal will reinforce his pattern with the tennis

court remaining on a separate allotment.

Streetscape Yes The works will have a temporary impact on the

footpath, kerb, guttering in McHatton Street but these

will be reinstated when works are completed. There is

no impact on existing street trees.

Siting Yes The dwelling house will continue to be sited within a

single form addressing the street.

Setback – front Yes No change is proposed to the front setback, which is

typical of the buildings in McHatton Street.

Setback – side Yes Existing side setbacks are retained, which comply

with the minimum 900mm setback required in the R2

Low Density Residential zone.

Setback - rear Yes The existing rear setback is retained, which is

consistent with that of adjoining dwelling houses in

McHatton Street.

Form massing scale Yes As the work are underground there is no change to the

form, massing and scale of the development.

Built form character Yes The building retains its character as a detached

dwelling house and tennis court in a landscaped

setting.

Dormers Yes The proposal incorporates two dormer windows

facing the street. In the circumstances of the case

these windows are considered to be acceptable as they

present no privacy impacts and do not detract from

the streetscape.

Front fences Yes Part of the existing brick fence will be removed to

permit construction access and will be reinstated

using reclaimed materials when works are completed.

1.5 Quality Urban Environment Vehicle access and parking Yes The DCP provides that parking “must not be provided

underground unless site conditions dictate that this is

the only or most appropriate solution for parking

provision”. In this case, to maintain the character of

the dwelling house and tennis court and their

contribution to the conservation area the provision of

car parking underground is considered to be the most

appropriate solution.

A turntable ensures vehicles are able to enter and

leave the site in a forward direction.

Site coverage

Max 30% permitted

Excludes basements and any parts of the

site otherwise defined as landscape area

(including hard paved surfaces such as on-

slab planting)

Yes

(On merit)

The existing development of the site has a site

coverage of 23.1%. The proposed works will create a

basement garage and basement rooms. Whilst site

coverage includes garages, it excludes basements.

The total parking number exceeds the DCP maximum

by 2 spaces. This is considered acceptable in the

circumstances as the vehicle movements will reflect

that of any large house and not be excessive. Figure

B1.10 identifies that a basement with landscaping

above is considered to be un-built upon area.

Consequently, the proposal will not increase the site

coverage of the development. A maximum site

coverage of 30% applies to sites over 1000m2 and the

proposal complies with this requirement.

Page 11: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 11

Re: 5 McHatton Street, Waverton

Site coverage compliance diagram

Landscape area landscaped area of 50% (min)

un-built upon area of 20% (max)

Yes The DCP requires a minimum landscaped area of

50% and a maximum un-built upon area of 20%. The

existing development complies with this requirement,

with a landscaped area of 52.4% but the un-built upon

area of 24.5% exceeds maximum allowable under the

control.

The proposal will reduce the landscaped area to 23%

and increase the un-built upon area to 53.9%.

Notwithstanding this non-compliance, in the

particular circumstances of this case it is considered

that the objectives of the control are satisfied.

a) The character of the area is maintained.

b) Usable private open space is maintained.

c) The landscaped buffer between properties is

maintained.

d) Surface water is retained on site but after soaking

into the tennis court is directed to the stormwater

system.

e) Obstructions to the underground flow of water

are controlled by the proposed stormwater

system.

f) All existing substantial landscaping is

maintained.

g) There is no increase in site density.

h) There is temporary site disturbance during

construction works but following completion the

site will be stabilised.

i) Streetscape and amenity are maintained.

j) Light continues to penetrate between buildings.

k) Existing space for biodiversity conservation and

ecological processes is maintained.

l) Bushland buffers are not an issue with this

proposal.

Excavation Yes The proposal achieves the objectives of the controls

on excavation in the DCP: Existing vegetation is

retained; impacts on neighbouring properties is

controlled and mitigated; site disturbance is

controlled; structural integrity of adjoining properties

is maintained; there is no transport infrastructure

adjoining the site.

The proposal satisfies the controls relating to

excavation. A detailed Geotechnical Report and

Construction Management Plan form part of the

development proposal.

Page 12: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 12

Re: 5 McHatton Street, Waverton

Control P2 specifically states that consent must not be

granted for basement car parking associated with a

dwelling house. However, the circumstances in this

case are unusual, with the basement proposed not

under the dwelling house but under the tennis court,

which will then be reinstated. In these circumstances,

where the objectives of the control area satisfied, a

variation to permit the basement car parking is

considered to be justified.

Landscaping Yes Existing trees and landscaped areas are to be retained.

Front gardens Yes The existing landscaping within the front setback area

is to be retained.

Private and communal open space Yes The rear yard, swimming pool, and tennis court

provide suitable private open space for the dwelling in

excess of the requirements of the DCP.

Tennis courts Yes No change is proposed to the siting of the tennis court

or its lighting.

1.6 Efficient Use of Resources Energy efficiency Yes A BASIX Certificate has been provided

demonstrating the proposal satisfies the State

Government’s target for energy and water efficiency.

Air conditioning is proposed. A condition of consent

is recommended requiring the air conditioning to have

a minimum energy star rating of 3.5 stars.

Natural ventilation Yes The proposed media room and gymnasium are

provided with fresh air intakes and air conditioning to

provide ventilation. Given the nature of the uses of

these rooms such ventilation is considered to be

satisfactory.

Stormwater management Yes The stormwater plans have been reviewed by

Council’s Engineers who have advised that there are

no objections to the proposal subject to conditions

included in the recommendation of this report.

DEVELOPMENT CONTROL PLAN 2013 – Part B Section 10 – Car Parking and Transport

complies Comments

10.2 Parking Provision

Quantity requirements Yes

(on merit)

The proposal will result in a total of 6 car spaces

being provided for the existing dwelling house where

the DCP permits a maximum of 2 car spaces. The

circumstances are unusual in that the site comprises 2

separate allotments so there is potential for the

allotment containing the dwelling house to be

redeveloped for a dwelling house with 2 car spaces.

However, even making this allowance, the proposal

still provides an excess of 2 car spaces.

The proposal satisfies the first objective of the

control, in that it provides sufficient car parking to

cater for users of the development.

The second objective is to minimise the reliance on

private car usage. In this regard, and in the particular

circumstances of this case, the provision of more than

2 car spaces has little impact on reliance on car usage

as occupants of the dwelling house would equally rely

on using 2 cars as they would on 6 cars as the family

home generally only has 2 drivers so there would only

be 2 cars in use at any time.

The third objective is to facilitate the use of public

and alternative transport modes. In this regard the

garage provides for additional bicycle storage areas

and facilitates greater use of bicycles. The site is well

serviced by public transport due to its proximity to the

Pacific Highway and this proximity will continue to

facilitate the use of public transport.

Page 13: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 13

Re: 5 McHatton Street, Waverton

Design and layout Yes The design of the car parking area complies with

AS2890.1:2004. The turntable ensures that vehicles

are able to enter and leave the site in a forward

direction.

Bicycle parking and associated facilities Yes The DCP requires the provision of a minimum of 2

bicycle spaces (one for occupants and for visitors).

These can be accommodated in the proposed garage.

DEVELOPMENT CONTROL PLAN 2013 – Part B Section 11 – Traffic Guidelines for Development

complies Comments

11.3 Construction Management Plan

Provisions Yes The DCP requires the submission of a Construction

Management Plan prior to the commencement of a

development. However, given the construction traffic

likely to be generated by the development, the

applicant submitted a Construction Traffic

Management Plan and a Construction Management

Plan with the development application to enable an

assessment of impacts arising during construction and

identify how the proposal will mitigate those impacts.

The most critical period is during the excavation

phase when up to 12 trucks per day are anticipated to

arrive and leave with excavated material. Truck

movements will be restricted so as not to conflict with

school drop off (8am-9.30am) and pick up (2.30pm-

4pm) times. Trucks will enter and exit the site via

McHatton Street from an easterly direction.

NORTH SYDNEY LEP 2013

Permissibility within the zone:

The subject site is zoned R2 (Low Density) Residential. The proposed alterations and

additions to an existing dwelling house are permissible with consent of Council.

Zone Objectives

The objectives of the R2 Low Density Residential zone are:

To provide for the housing needs of the community within a low density residential

environment.

To enable other land uses that provide facilities or services to meet the day to day needs

of residents.

To encourage development of sites for low density housing, including dual occupancies, if

such development does not compromise the amenity of the surrounding area or the

natural or cultural heritage of the area.

To ensure that a high level of residential amenity is achieved and maintained.

The proposal is considered to be consistent with these objectives. The heritage significance of

the conservation area is maintained. The proposal maintains the amenity of neighbouring

dwellings whilst providing improved amenity and services for the residents of the subject

site.

Page 14: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 14

Re: 5 McHatton Street, Waverton

Building Heights

The proposal, with a maximum height of 1.7 metres (for the proposed shed housing the air

conditioning plant) complies with the provisions of Clause 4.3(2) of NSLEP 2013 which

limits building height to 8.5m and the provisions of clause 4.3(2A) which limits street

elevation height to 5.5 metres in conservation areas.

Suspensions of Covenants, agreements and similar instruments

The author of this report is unaware of any covenants, agreements or similar instruments that

would prevent the proposed development.

Preservation of trees and vegetation

An arborist’s report was submitted with the development application that assessed the impact

of the proposal on 13 trees on and adjacent to the site. No trees are to be removed. The report

makes recommendations to ensure that the trees are not harmed during construction.

Heritage Conservation

The site does not contain a heritage item. However, it is identified as a contributory building

within the Crows Nest Road Conservation Area. The site is adjacent to the North Sydney

Demonstration School and the fence and gates of the former Crows Nest House on that site

are identified as a heritage item of local significance.

A Heritage Impact Statement has been submitted with the development application. The HIS

has been reviewed by Council’s Conservation Planner and found to be satisfactory. The

proposal will maintain the heritage significance of the conservation area because, once the

development is completed, there will be no perceptible difference to the presentation of the

development to the street or local area.

Earthworks

The proposal involves excavation to a depth of approximately 4 metres below the existing

level of the tennis court. A total of approximately 1,980m3 of soil will be excavated.

Clause 6.10 of NSLEP 2013 contains a number of matters for consideration when assessing

the impact of proposal involving earthworks:

(a) the likely disruption of, or any detrimental effect on:

(i) drainage patterns and soil stability in the locality of the development, and

(ii) natural features of, and vegetation on, the site and adjoining land,

Comment: Drainage patterns and soil stability will be managed in accordance with the

documentation submitted with the development application. Contiguous piering will maintain

soil stability. Ground water seepage will be collected and directed to the stormwater system.

There is no impact on natural features or vegetation.

(b) the effect of the development on the likely future use or redevelopment of the land,

Page 15: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 15

Re: 5 McHatton Street, Waverton

Comment: The earthworks are necessary for the proposed future use of the land as a garage,

media room, gymnasium whilst continuing the use as a tennis court.

(c) the quality of the fill or the soil to be excavated, or both,

Comment: The excavated material will comprise clean soil. No fill is proposed.

(d) the effect of the development on the existing and likely amenity of adjoining properties,

Comment: There will be interim amenity impacts during construction but these can be

mitigated in a satisfactory manner. There will be no impacts on the neighbours’ amenity

when the works are compete.

(e) the source of any fill material and the destination of any excavated material,

Comment: No fill is proposed. Excavated material will be exported and used elsewhere as

engineered fill.

(f) the likelihood of disturbing Aboriginal objects or relics,

Comment: There are no known aboriginal objects on site and it is unlikely that any would be

disturbed by the proposed works.

(g) the proximity to, and potential for adverse impacts on, any waterway, drinking water

catchment or environmentally sensitive area,

Comment: The site is not within an environmentally sensitive area. Subject to appropriate

management in accordance with the documentation submitted with the development

application there will be no adverse impacts on any waterway or drinking water catchment.

(h) any appropriate measures proposed to avoid, minimise or mitigate the impacts of the

development.

Comment: During excavation and construction there will be impacts in terms of traffic, noise,

vibration and dust but these can be mitigated in a satisfactory manner in accordance with the

documentation submitted with the development application and standard conditions.

SEPP 55 and Contaminated Land Management Issues

The subject site has been considered in light of the Contaminated Lands Management Act

and it is considered that as the site has been used for residential purposes for many years,

contamination is unlikely.

DEVELOPMENT CONTROL PLAN 2013

Relevant Planning Area (Waverton / Wollstonecraft)

The application has been assessed against the relevant controls in DCP 2013 as indicated in

the earlier compliance table. The proposal is also considered below in terms of the

requirements of the character statements in NSDCP 2013.

Page 16: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 16

Re: 5 McHatton Street, Waverton

Character Statements – Crows Nest Road Conservation Area

Significant elements

The proposal maintains the characteristic subdivision pattern. The front fence is low and

characteristic of the area and the portion removed during construction will be reconstructed

afterwards. There is no impact on slot views to the harbour along McHatton Street.

Characteristic buildings

The site is on the later subdivided part of the conservation area which is characterized by

single and two storey houses. This character will be maintained.

Characteristic built elements

The proposal is consistent with the characteristic built elements for this neighbourhood. The

existing dwelling house is retained in an unaltered form as is the tennis court.

SECTION 94 CONTRIBUTIONS

Council’s Section 94 Contributions Plan states that contributions will not be levied on

alterations and additions to a single dwelling even if that development results in an increase

in the number of bedrooms. Consequently, no Section 94 Contributions are payable for the

proposed development.

APPLICABLE REGULATIONS

Demolition

Clause 92(1)(b) of the EPA Regulation 2000 require that council take into consideration

Australian Standard AS 2601-1991: The Demolition of Structures, as in force at 1 July 1993.

As demolition is proposed a suitable condition is included in the recommendation of this

report.

ALL LIKELY IMPACTS OF THE DEVELOPMENT

All likely impacts of the proposed development have been considered within the context of

this report.

ENVIRONMENTAL APPRAISAL CONSIDERED

1. Statutory Controls Yes

2. Policy Controls Yes

3. Design in relation to existing building and Yes

natural environment

4. Landscaping/Open Space Provision Yes

5. Traffic generation and Carparking provision Yes

Page 17: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 17

Re: 5 McHatton Street, Waverton

6. Loading and Servicing facilities NA

7. Physical relationship to and impact upon adjoining Yes

development (Views, privacy, overshadowing, etc.)

8. Site Management Issues Yes

9. All relevant S79C considerations of Yes

Environmental Planning and Assessment (Amendment) Act 1979

SUBMITTERS CONCERNS

Issue: Impact during excavation works

Concern is raised that the excavation works will result in unreasonable noise,

vibration and dust.

Planning Comment: The proposal involves excavation of approximately 1,980m3 of

rock and soil. The excavation work occurs over two stages, with the first stage

involving excavation to enable piering and soil stability works to be installed – this

stage lasts for 4 weeks removing approximately 260m3 of material. The second stage

is for bulk earthworks – this stage lasts for 9 weeks removing approximately 1,720m3

of material.

The submitted geotechnical report indicates that most excavation can be done by

excavators or tractor mounted backhoe, although in some locations it may be

necessary to use equipment such as breakers to assist in removing the more rocky

material.

Conditions are included in the recommendation of this report to address the potential

amenity impacts (Conditions C7, E6, E8 and E9).

Issue: Limit the height of and existing hedge

An existing hedge provides privacy but it is requested to limit the height of the hedge

to prevent overshadowing.

Planning Comment: The proposal has no impacts on the hedge and no impacts are

created that are relevant to the hedge so there is no justification for a condition

limiting the height of the hedge. The hedge will be retained in accordance with the

landscape plan and will continue to maintain privacy.

Issue: Lightspill

Concern that the proposal will increase lightspill from tennis court lighting.

Planning Comment: The proposal is to reinstate the existing tennis court lighting in

an identical position and height as currently approved so there will be no increase in

lightspill.

Page 18: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 18

Re: 5 McHatton Street, Waverton

Issue: Impact from exhaust vents

Concern that vents not create impacts for neighbouring properties or the neighbouring

school.

Planning Comment: One exhaust vent is proposed immediately south-east of the

tennis court. The amount and quality of the air being exhausted is unlikely to create

impacts on the school or neighbouring property given the size and nature of use of the

area being vented (ie: 5 car domestic garage, media room and gymnasium).

Issue: Stormwater pipes off-site

Concern regarding the impacts of any new stormwater pipes being installed

downstream from the site.

Planning Comment: No new pipes are proposed downstream from the site. All

works are contained on the site. The proposed drainage works incorporate an on-site

detention system which has been assessed as adequate by Council’s engineer.

Issue: Dilapidation reports

A request that dilapidation reports be prepared for neighbouring properties.

Planning Comment: Given the nature of the works and the scale of excavation

proposed it is appropriate that a dilapidation report be prepared for sites immediately

adjacent to the proposed works (ie: all sites within the zone of influence of the

proposed excavation – see Condition C3).

Issue: Hours of excavation

A request that excavation be limited to four days per week, 8am to 4pm, with no work

on weekends.

Planning Comment: The proposed hours of construction are 7am – 5pm weekdays

and 8am – 1pm Saturdays.

No truck movements will be permitted during school pick-up and drop-off times

(8am-9.30am and 2.30pm-4pm) to prevent traffic congestion. Pedestrian access will

be maintained in front of the site but will be supervised by the onsite traffic

controllers in accordance with the Construction Traffic Management Plan.

It is considered that the proposal, involving extensive excavation immediately

adjacent to residential properties for a domestic garage, is unusual and in the

particular circumstances of the case limiting excavation work to 8am-4pm is

reasonable to maintain neighbour amenity (see Condition E1). However, the

circumstances do not justify limiting works to only 4 days per week, which would

have the unintended consequence of lengthening the construction period.

Issue: Downstream impacts from stormwater

Concern is raised that the proposal will increase stormwater in downstream

infrastructure.

Page 19: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 19

Re: 5 McHatton Street, Waverton

Planning Comment: the proposed hydraulic management plans include a new on-site

stormwater detention tank to ensure that there is no increase in the rate at which

stormwater is disposed of off-site so there will be no impact on downstream

stormwater infrastructure.

CONCLUSION

The proposal involves alterations and additions to an existing dwelling house within a

conservation area.

The development application has been assessed against the North Sydney Local

Environmental Plan 2013 and the North Sydney Development Control Plan 2013.

The proposed basement car park is located below McHatton Street and to the east of the

dwelling on a separate allotment. The removal and replacement of the existing tennis court

with a basement car park and new tennis court over would not impact on the character of the

Conservation area and would not adversely impact the heritage contribution of the existing

dwelling which will continue to be sited within a landscape setting.

The proposed additional parking would exceed the maximum parking provision by 3 parking

spaces, as outlined in the DCP. However the parking demand and traffic generation is limited

by the existing accommodation provided within the dwelling, that is the parking demand and

car use is consistent with that generated by any large dwelling. The basement also provides

new bike storage and the site is well located to regular public transport services including rail

and bus. The proposal is therefore deemed to satisfy the objectives of Council’s DCP with

regard to management of parking.

The assessment has also considered the issues raised in the submissions which have been

addressed throughout this report. Conditions have been recommended to ensure appropriate

management of noise and disturbance created by construction activity and to ensure the

appropriate management of stormwater.

The development application is considered to be a reasonable response to the opportunities

and constraints of the site and is recommended for approval subject to conditions.

RECOMMENDATION

PURSUANT TO SECTION 80 OF ENVIRONMENTAL PLANNING AND ASSESSMENT

ACT 1979 (AS AMENDED)

THAT the North Sydney Independent Planning Panel, under the delegation of the General

Manager, as the consent authority, grant consent to Development Application No. 207/16

for alterations and additions to dwelling house, demolition of existing clay base tennis court

and construct a new basement garage containing parking for five (5) cars, gym, media room,

rainwater tank and on site detention system and reconstruction of tennis court and lighting

poles on land at 5 McHatton Street, Waverton subject to the following site specific conditions

and the attached standard conditions:

Stormwater Management and Disposal Design Plan / Construction issue detail

C1. Prior to issue of the Construction Certificate, the applicant shall have a site drainage

management plan prepared by a qualified hydraulic design engineer. The site drainage

management plan must detail the following requirements of North Sydney Council:

Page 20: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 20

Re: 5 McHatton Street, Waverton

a) Compliance with the latest revision of: BCA drainage requirements, Councils

Engineering Performance guide and current Australian Standards and guidelines,

such as AS/NZ 3500.3.2003, National Plumbing and Drainage Code.

b) No works on Council land regarding storm water drainage discharge are proposed or

approved under this consent and no work may be undertaken until approved.

c) Any works on Council’s infrastructure (including rectifying works on: footpath, grass

verge, kerb, gutter and/or driveway crossing) that are reverting to Council care and

control, must be approved from Council prior to commencement of construction. To

obtain the permit, an application must be made to Council on a ‘Permit for Street

Opening’ form with payment of the adopted assessment/inspection fees.

d) Stormwater runoff and subsoil drainage generated by the approved development

must be conveyed in a controlled manner by gravity to existing control pit at the

South /East boundary.

e) The stormwater drainage system shall be designed for an average recurrence interval

(A.R.I.) of 1 in 20 years.

f) Provision is to be made for the collection and disposal in an approved manner of

any overland flow entering the subject property, or concentrated as a result of the

proposed works.

g) Surface inlet pits must be located to catch surface flows, and must be provided at all

pipe junctions, changes in pipe direction exceeding 45 degrees and at the site

boundary (within the property) prior to connection to the public drainage system and

must be of sufficient size to accept the flow.

h) All sub-soil seepage drainage shall be discharged via a suitable silt arrestor pit. Sign

must be installed adjacent to pit stating “This sediment /silt arrestor pit shall be

regularly inspected and cleaned”. Details of all plans certified as being adequate for

their intended purpose and complaint with the provisions of AS 3500.3.2 by an

appropriately qualified and practising civil engineer shall be submitted with the

application for a Construction Certificate.

i) If a car wash bay is established than wastewater collected from the bay drainage

require pre-treatment, such as silt traps and oil separation system, prior to being

discharged into wastewater systems (e.g. sewer or septics).

j) The design and installation of the Rainwater Tank must comply with BASIX and

Sydney Water requirements. Overflow from tank shall be conveyed in a controlled

manner by gravity to the stormwater disposal system.

k) The design and installation of the rainwater reuse system (rainwater tank) must

comply with DCP 2013 requirements. Overflow from the rainwater reuse devise

must be conveyed in a controlled manner by gravity to the stormwater disposal

system. Rainwater Tank must be plumbed to appropriate end uses (i.e. external taps,

toilet flushing, laundry, water features, car washing or garden irrigation) to ensure

sufficient use of tank water so that capacity exists to accommodate rain water from

storm events.

l) Prevent any stormwater egress into adjacent properties by creating physical

barriers and surface drainage interception.

m) The proposed On Site Detention for storm water disposal must be designed to

ensure that the maximum discharge of stormwater collected from the pre-developed

site, which would occur during a 1 in 5 year storm of 1-hour duration for the existing

site conditions, is not exceeded. The OSD system must be regularly maintained and

serviced.

Page 21: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 21

Re: 5 McHatton Street, Waverton

n) The creation of a Positive Covenant (under the provision of the Conveyance Act) on

the property title to ensure the maintenance of OSD and pump system on the

property being developed. Prior to occupation certificate details must be submitted to

Council for approval before registration with the Land Titles Office.

o) Provide subsoil drainage to all necessary areas with pump out facilities as required.

Details demonstrating compliance are to be submitted with the Construction

Certificate.

The Certifying Authority issuing the Construction Certificate must ensure that the

approved drainage plan and specifications, satisfying the requirements of this

condition, is referenced on and accompanies the Construction Certificate. The

measures shown on the approved stormwater management plan, must be implemented

on site prior to issue of the Occupation Certificate.

(Reason: To ensure controlled stormwater management and disposal without

nuisance)

Construction Hours

E1. Building construction and works must be restricted to within the hours of 7.00 am to

5.00 pm Monday to Friday and on Saturday to within the hours of 8.00 am to 1.00 pm

inclusive, with no work on Sundays and Public Holidays.

Demolition works must be restricted to within the hours of 8.00 am to 5.00 pm

Monday to Friday only.

Excavation works must be restricted to within the hours of 8.00 am to 4.00 pm

Monday to Friday only.

For the purposes of this condition:

1) “Building construction” means any physical activity on the site involved in the

erection of a structure, cladding, external finish, formwork, fixture, fitting of

service installation and the unloading of plant, machinery, materials or the

like.

2) “Demolition works” means any physical activity to tear down or break up a

structure (or part thereof) or surface, or the like, and includes the loading of

demolition waste and the unloading of plant or machinery.

3) “Excavation work” means the use of any excavation machinery and the use of

jackhammers, rock breakers, excavators, loaders, or the like, regardless of

whether the activities disturb or alter the natural state of the existing ground

stratum or are breaking up/removing materials from the site and includes the

unloading of plant or machinery associated with excavation work.

All builders, excavators must display, on-site, their twenty-four (24) hour contact

telephone number, which is to be clearly visible and legible from any public place

adjoining the site.

(Reason: To ensure that works do not interfere with reasonable amenity

expectations of residents and the community)

Page 22: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

Report of Symons Goodyer Pty Ltd Page 22

Re: 5 McHatton Street, Waverton

Front Fence

G1. The brick wall and palisade front fence is to be reconstructed to match the form of the

existing fence at the completion of the works. The reinstated wall and fence must

have a matching brick base and palisade fence with the detailing of the fence and

piers to exactly match the existing fence in terms of materials, height, location and

detail.

(Reason: To minimise impact on the conservation area)

Geoff Goodyer David Hoy

CONSULTANT TOWN PLANNER TEAM LEADER ASSESSMENTS

Stephen Beattie

MANAGER DEVELOPMENT SERVICES

Page 23: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

September 2013 v1

NORTH SYDNEY COUNCIL

CONDITIONS OF DEVELOPMENT APPROVAL

5 MCHATTON STREET, WAVERTON

DEVELOPMENT APPLICATION NO. 207/16

A. Conditions that Identify Approved Plans Development in Accordance with Plans/documentation A1. The development must be carried out in accordance with the following drawings and

documentation and endorsed with Council’s approval stamp, except where amended by the following conditions of this consent.

Plan No. Issue Title Drawn by Dated Received

1506/DA01 A Site analysis and sections

Kenstrom design May 2016 08.06.2016

1506/DA02 Plans Kenstrom design May 2016 08.06.2016 1506/DA03 Landscape plan Kenstrom design June 2016 08.06.2016

(Reason: To ensure that the form of the development undertaken is in

accordance with the determination of Council, Public Information) Plans on Site A2. A copy of all stamped approved plans, specifications and documents (including the

plans, specifications and documents submitted and approved with the Construction Certificate) must be kept on site at all times so as to be readily available for perusal by any officer of Council or the Principal Certifying Authority. All documents kept on site in accordance with this condition must be provided to any officer of the Council or the certifying authority upon their request.

(Reason: To ensure that the form of the development undertaken is in

accordance with the determination of Council, Public Information and to ensure ongoing compliance)

No Demolition of Extra Fabric A3. Alterations to, and demolition of the existing building shall be limited to that

documented on the approved plans.

(Reason: To ensure compliance with the approved development)

ATTACHMENT TO IPP09 - 05/10/2016 Page 23

Page 24: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 2 of 29

September 2013 v1

B. ANCILLARY MATTERS TO BE COMPLETED PRIOR TO ISSUE OF A CONSTRUCTION CERTIFICATE

Construction And Traffic Management Plan

B1. Prior to issue of Any Construction Certificate, a Construction and Traffic

Management Plan must be submitted with application form: “To Satisfy DA Consent Condition” and approved in writing from Council. The following matters must be specifically addressed in the Plan:

1. A plan view (min 1:100 scale) of the entire site and frontage roadways indicating:

a) Dedicated construction site entrances and exits, controlled by a certified traffic

controller, to safely manage pedestrians and construction related vehicles in the frontage roadways,

b) RMS approved signage type and location to manage pedestrian in the vicinity, c) Turning areas within the site for construction and spoil removal vehicles,

allowing a forward egress for all construction vehicles on the site, d) The locations of any proposed Work Zones in the frontage roadways (to be

approved by Council’s Traffic Committee), e) Locations and type of hoardings proposed, f) Area of site sheds and the like, g) Location of any proposed crane standing areas, h) Proposed maximum size for construction vehicles/trucks, i) A dedicated unloading and loading point within the site for all construction

vehicles, plant and deliveries, j) Material, plant and spoil bin storage areas within the site, where all materials

are to be dropped off and collected. k) The provision of an on-site parking area for employees, tradesperson and

construction vehicles as far as possible. l) The residents/occupiers are to be updated on a monthly basis and at key

construction stages and be provided with a phone number to contact the site manager.

2. A detailed description and route map of the proposed route for vehicles

involved in spoil removal, material delivery and machine floorage must be provided:

a) Light traffic roads and those subject to a load or height limit must be avoided

at all times. b) Once approved from North Sydney Council, a copy of the route is to be

made available to all contractors, and shall be clearly depicted at a location within the site.

ATTACHMENT TO IPP09 - 05/10/2016 Page 24

Page 25: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 3 of 29

September 2013 v1

3. Traffic Control Plan(s) for the site incorporating following:

a) All Traffic control measures proposed in the road reserve that are in accordance with the RMS publication “Traffic Control Worksite Manual” and designed by a person licensed to do so (minimum RMS ‘red card’ qualification).

b) The main stages of the development requiring specific construction management measures are to be identified and specific traffic control measures identified for each.

4. A Waste Management Plan must be in accordance with the provisions of Part

B Section 19 of the North Sydney DCP 2013 must be provided. The Waste Management Plan must include, but not be limited to, the estimated volume of waste and method of disposal for the construction and operation phases of the development, design of on-site waste storage and recycling area and administrative arrangements for waste and recycling management during the construction process.

5. Evidence of RMS concurrence where construction access is provided directly

or within 20 m of an Arterial and/or Classified Road;

6. A schedule of site inductions to be held on regular occasions and as determined necessary to ensure all new employees are aware of the construction management obligations. These must specify that construction-related vehicles to comply with the approved requirements; and

7. For those construction personnel that drive to the site, the Site Manager shall

attempt to provide on-site parking so that their personnel’s vehicles do not impact on the current parking demand in the area.

A suitably qualified and experienced traffic engineer or consultant shall prepare the Construction and Traffic Management Plan. The construction management measures contained in the approved plan must be implemented in accordance with the plan prior to the commencement of, and during, works on-site. As the plan has a direct impact on the local road network and public amenity, the plan must be submitted to and reviewed by Council prior to the issue of any Construction Certificate. A certificate of compliance with this condition from Council’s Development Engineers as to the result of this review must be obtained and must be submitted as part of the supporting documentation lodged with the Certifying Authority for approval of the application for a Construction Certificate. A copy of the approved Construction and Traffic Management Plan must be kept on the site at all times and be made available to any officer of the Council on request.

ATTACHMENT TO IPP09 - 05/10/2016 Page 25

Page 26: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 4 of 29

September 2013 v1

Notes:

1) North Sydney Council’s adopted fee for certification of compliance with this condition shall be payable on lodgement, or in any event, prior to the issue of the relevant approval.

2) Any use of Council property will require appropriate approvals and demonstration of liability insurances prior to such work commencing.

3) Failure to provide complete and detailed information may result in delays. It is recommended that your Construction Management Plan be lodged with Council as early as possible.

4) Dependent on the circumstances of the site, Council may request additional information to that detailed above.

(Reason: To ensure appropriate measures have been considered for site access,

storage and the operation of the site during all phases of the demolition and construction process in a manner that respects adjoining owner’s property rights and residential amenity in the locality, without unreasonable inconvenience to the community)

C. PRIOR TO THE ISSUE OF A CONSTRUCTION CERTIFICATE (AND

ONGOING, WHERE INDICATED) Stormwater Management and Disposal Design Plan / Construction issue detail C1. Prior to issue of the Construction Certificate, the applicant shall have a site drainage

management plan prepared by a qualified hydraulic design engineer. The site drainage management plan must detail the following requirements of North Sydney Council:

a) Compliance with the latest revision of: BCA drainage requirements, Councils Engineering Performance guide and current Australian Standards and guidelines, such as AS/NZ 3500.3.2003, National Plumbing and Drainage Code.

b) No works on Council land regarding storm water drainage discharge are proposed or approved under this consent and no work may be undertaken until approved.

c) Any works on Council’s infrastructure (including rectifying works on: footpath, grass verge, kerb, gutter and/or driveway crossing) that are reverting to Council care and control, must be approved from Council prior to commencement of construction. To obtain the permit, an application must be made to Council on a ‘Permit for Street Opening’ form with payment of the adopted assessment/inspection fees.

d) Stormwater runoff and subsoil drainage generated by the approved development must be conveyed in a controlled manner by gravity to existing control pit at the South /East boundary.

e) The stormwater drainage system shall be designed for an average recurrence interval (A.R.I.) of 1 in 20 years.

f) Provision is to be made for the collection and disposal in an approved manner of any overland flow entering the subject property, or concentrated as a result of the proposed works.

ATTACHMENT TO IPP09 - 05/10/2016 Page 26

Page 27: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 5 of 29

September 2013 v1

g) Surface inlet pits must be located to catch surface flows, and must be provided at all pipe junctions, changes in pipe direction exceeding 45 degrees and at the site boundary (within the property) prior to connection to the public drainage system and must be of sufficient size to accept the flow.

h) All sub-soil seepage drainage shall be discharged via a suitable silt arrestor pit. Sign must be installed adjacent to pit stating “This sediment /silt arrestor pit shall be regularly inspected and cleaned”. Details of all plans certified as being adequate for their intended purpose and complaint with the provisions of AS 3500.3.2 by an appropriately qualified and practising civil engineer shall be submitted with the application for a Construction Certificate.

i) If a car wash bay is established than wastewater collected from the bay drainage require pre-treatment, such as silt traps and oil separation system, prior to being discharged into wastewater systems (e.g. sewer or septics).

j) The design and installation of the Rainwater Tank must comply with BASIX and Sydney Water requirements. Overflow from tank shall be conveyed in a controlled manner by gravity to the stormwater disposal system.

k) The design and installation of the rainwater reuse system (rainwater tank) must comply with DCP 2013 requirements. Overflow from the rainwater reuse devise must be conveyed in a controlled manner by gravity to the stormwater disposal system. Rainwater Tank must be plumbed to appropriate end uses (i.e. external taps, toilet flushing, laundry, water features, car washing or garden irrigation) to ensure sufficient use of tank water so that capacity exists to accommodate rain water from storm events.

l) Prevent any stormwater egress into adjacent properties by creating physical barriers and surface drainage interception.

m) The proposed On Site Detention for storm water disposal must be designed to ensure that the maximum discharge of stormwater collected from the pre-developed site, which would occur during a 1 in 5 year storm of 1-hour duration for the existing site conditions, is not exceeded. The OSD system must be regularly maintained and serviced.

n) The creation of a Positive Covenant (under the provision of the Conveyance Act) on the property title to ensure the maintenance of OSD and pump system on the property being developed. Prior to occupation certificate details must be submitted to Council for approval before registration with the Land Titles Office.

o) Provide subsoil drainage to all necessary areas with pump out facilities as required.

Details demonstrating compliance are to be submitted with the Construction Certificate.

The Certifying Authority issuing the Construction Certificate must ensure that the approved drainage plan and specifications, satisfying the requirements of this condition, is referenced on and accompanies the Construction Certificate. The measures shown on the approved stormwater management plan, must be implemented on site prior to issue of the Occupation Certificate.

(Reason: To ensure controlled stormwater management and disposal without nuisance)

ATTACHMENT TO IPP09 - 05/10/2016 Page 27

Page 28: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 6 of 29

September 2013 v1

Dilapidation Report Damage to Public Infrastructure

C2. A dilapidation survey and report (including photographic record and CCTV electronic

file) must be prepared by a suitably qualified consultant who details the pre-developed condition of the existing public infrastructure in the vicinity of the development site. Particular attention must be paid to accurately recording any pre-developed damaged infrastructure, including the CCTV of drainage within the area, so that Council is fully informed when assessing any damage to public infrastructure caused as a result of the development. A copy of the dilapidation survey with CCTV electronic file and report is to be submitted to Council and to the Certifying Authority for approval prior to the issue of any Construction Certificate.

The developer may be held liable for all damage to public infrastructure in the vicinity of the site, where such damage is not accurately recorded and demonstrated as pre-existing under the requirements of this condition.

The developer shall bear the cost of carrying out works to restore all public infrastructure damaged as a result of the carrying out of the development, and no occupation of the development shall occur until damage caused as a result of the carrying out of the development is rectified.

A copy of the dilapidation survey with CCTV electronic file and report must be lodged with North Sydney Council by the Certifying Authority with submission of the Construction Certificate documentation.

(Reason: To record the condition of public infrastructure prior to the commencement of construction)

Dilapidation Report Private Property (Excavation) C3. A full dilapidation survey and report on the visible and structural condition of all

neighbouring structures within the ‘zone of influence’ of the required excavations must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The zone of influence is to be defined as the horizontal distance from the edge of the excavation face to twice the excavation depth.

The dilapidation report and survey is to be prepared by a consulting structural/geotechnical engineer agreed to by both the applicant and the owner of any affected adjoining property.

All costs incurred in achieving compliance with this condition shall be borne by the person entitled to act on this Consent.

In the event that access for undertaking the dilapidation survey is denied by an adjoining owner, the applicant MUST DEMONSTRATE, in writing, to the satisfaction of Council that all reasonable steps have been taken to obtain access and advise the affected property owner of the reason for the survey and that these steps have failed. Written concurrence must be obtained from Council in such circumstances.

ATTACHMENT TO IPP09 - 05/10/2016 Page 28

Page 29: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 7 of 29

September 2013 v1

Note: This documentation is for record keeping purposes only, and may be used by the developer or affected property owner to assist in any action required to resolve any dispute over damage to adjoining properties arising from the works. It is in the applicant’s and adjoining owner’s interest for it to be as full and detailed as possible.

(Reason: To record the condition of property/ies prior to the commencement of construction)

Structural Adequacy of Adjoining Properties – Excavation Works C4. A report prepared by an appropriately qualified and practising structural engineer

detailing the structural adequacy of adjoining public properties, which certifies their ability to withstand the proposed excavation and outlines any measures required to be implemented to ensure that no damage will occur to adjoining properties during the course of the works, must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The measures outlined in the certified report must be complied with at all times.

(Reason: To ensure the protection and structural integrity of adjoining properties in close proximity during excavation works)

Shoring for Adjoining Property C5. Where any shoring for excavation is to be located on or is supporting Council’s

property, or any adjoining private property, engineering drawings certified as being adequate for their intended purpose by an appropriately qualified and practising structural engineer, showing all details, including the extent of excavation, encroachment and the method of removal and de-stressing of shoring elements, backfilling and compacting of over-excavated cavities on Council’s and/or private property with fill suitable for its purpose, must be first submitted to the Council with “To Satisfy DA Consent Condition”. The temporary tieback anchors shall be at a minimum depth of 1.5 m below the surface levels of the footpath and roadway.

A certificate of compliance with this condition from Council’s Development Engineers as to the result of this review must be obtained. Approved application “To Satisfy DA Consent Condition” must be submitted to the Certifying Authority for approval with Construction Certificate. A copy of this documentation must be provided to the Council for record purposes. Backfilling and compacting of over-excavated cavities must be addressed as the build up is progressing through the basements to ensure that compaction is reliable.

Note: Approval of engineering drawings for shoring works to be located on adjoining property by the Certifying Authority does not authorize a trespass on private or public land. All relevant permissions/ legal rights must be obtained to undertake any works on adjoining land.

(Reason: To ensure the protection of existing public infrastructure and adjoining properties)

ATTACHMENT TO IPP09 - 05/10/2016 Page 29

Page 30: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 8 of 29

September 2013 v1

Structural Adequacy of Existing Building C6. A report prepared by an appropriately qualified and practising structural engineer,

certifying the structural adequacy of the property and its ability to withstand the proposed additional, or altered structural loads during all stages of construction shall be submitted to the Certifying Authority for approval prior to issue of any Construction Certificate. The certified report must also include all details of the methodology to be employed in construction phases to achieve the above requirements. The methodology in the certified report must be complied with at all times.

(Reason: To ensure the structural integrity of the building is maintained)

Geotechnical Report C7. Prior to issue of the Construction Certificate, the recommendation of the

Geotechnical/Civil Engineering report must be prepared to addresses at a minimum (but is not limited to) the following:

a) The type and extent of substrata formations by the provision of a minimum of

four (4) representative bore hole logs which are to provide a full description of all material from ground surface to 1.0 m below the finished basement floor level and include the location and description of any anomalies encountered in the profile. The surface and depth of the bore hole logs shall be related to Australian Height Datum;

b) The appropriate means of excavation/shoring in light of point (a) above and

proximity to adjacent property and structures. Potential vibration caused by method of excavation and potential settlements affecting nearby footings/foundations shall be discussed and ameliorated;

c) The proposed method to temporarily and permanently support the excavation

for the basement adjacent to adjoining property, structures and road reserve if nearby (full support to be provided within the subject site);

d) The existing groundwater levels in relation to the basement structure, where

influenced; e) The drawdown effects on adjacent properties (including road reserve), if any,

the basement excavation will have on groundwater together with the appropriate construction methods to be utilized in controlling groundwater. Where it is considered there is the potential for the development to create a “dam” for natural groundwater flows, a groundwater drainage system must be designed to transfer groundwater through or under the proposed development without a change in the range of the natural groundwater level fluctuations. Where an impediment to the natural flow path is constructed, artificial drains such as perimeter drains and through drainage may be utilized; and

ATTACHMENT TO IPP09 - 05/10/2016 Page 30

Page 31: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 9 of 29

September 2013 v1

f) Recommendations to allow the satisfactory implementation of the works. An implementation program is to be prepared along with a suitable monitoring program (as required) including control levels for vibration, shoring support, ground level and groundwater level movements during construction. The implementation program is to nominate suitable hold points at the various stages of the works for verification of the design intent before sign-off and before proceeding with subsequent stages.

The geotechnical report must be prepared by a consulting geotechnical/ hydrogeological engineer with previous experience in such investigations and reporting. It is the responsibility of the engaged geotechnical specialist to undertake the appropriate investigations, reporting and specialist recommendations to ensure a reasonable level of protection to adjacent property and structures both during and after construction. The report shall contain site-specific geotechnical recommendations and shall specify the necessary hold/inspection points by relevant professionals as appropriate. The design principles for the geotechnical report are as follows:

a) No ground settlement or movement is to be induced which is sufficient

enough to cause an adverse impact to adjoining property and/or infrastructure; b) No changes to the ground water level are to occur as a result of the

development that are sufficient enough to cause an adverse impact to the surrounding property and infrastructure;

c) No changes to the ground water level are to occur during the construction of

the development that are sufficient enough to cause an adverse impact to the surrounding property and infrastructure;

d) Vibration is to be minimized or eliminated to ensure no adverse impact on the

surrounding property and infrastructure occurs, as a result of the construction of the development;

e) Appropriate support and retention systems are to be recommended and

suitable designs prepared to allow the proposed development to comply with these Design Principles; and

f) An adverse impact can be assumed to be crack damage as identified within the

relevant Australian Standard for determining such damage. The report, satisfying the requirements of this condition, must be provided as part of the supporting documentation lodged with the Certifying Authority for approval of the Construction Certificate application. The professional recommendations of the report shall be implemented in full during the relevant stages of excavation and construction.

(Reason: To ensure the structural integrity of the subject site and adjoining sites

ATTACHMENT TO IPP09 - 05/10/2016 Page 31

Page 32: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 10 of 29

September 2013 v1

during the excavation process) Geotechnical Certificate

C8. A certificate prepared by an appropriately qualified Geotechnical Engineer certifying that the existing rock formations and substrate on the site is capable of:

a) Withstanding the proposed loads to be imposed; b) Withstanding the extent of the proposed excavation, including any

recommendations for shoring works that may be required to ensure the stability of the excavation;

c) Providing protection and support of adjoining properties; and d) The provision of appropriate subsoil drainage during and upon completion of

construction works.

The Certifying Authority must ensure that the building plans and specifications submitted by the Applicant referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To ensure the structural integrity of the subject site and adjoining sites during the excavation process)

Waste Management Plan

C9. A Waste Management Plan is to be submitted for approval by the Certifying Authority prior to the issue of any Construction Certificate. The plan must include, but not be limited to: -

a) The estimated volume of waste and method of disposal for the construction and operation phases of the development;

b) The design of the on-site waste storage and recycling area; and c) Administrative arrangements for waste and recycling management during the

construction process.

The approved Waste Management Plan must be complied with at all times in the carrying out of the development.

(Reason: To encourage the minimisation of waste and recycling of building waste)

Colours, Finishes and Materials (Conservation Areas)

C10. The finishes, materials and exterior colours shall be complimentary to the architectural style of the original building and sympathetic to the character of the Conservation Area. A schedule of finishes, materials and external colours shall be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted fully satisfy the requirements of this condition prior to the release of the Construction Certificate.

ATTACHMENT TO IPP09 - 05/10/2016 Page 32

Page 33: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 11 of 29

September 2013 v1

(Reason: To ensure that the completed colours, finishes and materials are complementary to the Conservation Area.)

Work Zone C11. If a Works Zone is proposed, an application must be made to the North Sydney Local

Traffic Committee to install the ‘Work Zone’. Works Zones are provided specifically for the set down and pick up of materials and not for the parking of private vehicles associated with the site. Works Zones will generally not be approved where there is sufficient space on-site for the setting down and picking up of goods being taken to or from a construction site. If the Works Zone is approved by the Committee, the Applicant must obtain a written copy of the related resolution from the North Sydney Local Traffic Committee and submit a copy of this to the Certifying Authority to enable issue of the Construction Certificate. Where approval of the ‘Work Zone’ is resolved by the Committee, the necessary ‘Work Zone’ signage shall be installed (at the cost of the Applicant) and the adopted fee paid prior to commencement of any works on the site. Further, at the expiration of the Works Zone approval, the Applicant is required to remove the Works Zone signs and reinstate any previous signs, all at the Applicant's cost. (Reason: Amenity and convenience during construction)

Maintain Property Boundary Alignment Levels C12. Except where otherwise approved by Council, the property boundary alignment levels

must match existing prior to the commencement of works. Plans and specifications which document existing and proposed levels adjacent to the site boundaries and which comply with the requirements of this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate.

The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate fully satisfy the requirements of this condition. (Reason: To ensure interface between property and public land remains uniform)

Basement Car park to comply with relevant standards C13. The basement layout must comply with all requirements of Australian Standard

AS2890.1. Certification from a suitably qualified and practicing Civil Engineer that the basement design will comply with the requirements of the Australian Standard must be provided to the Certifying Authority for approval prior to issue of any Construction Certificate.

(Reason: To ensure the basement layout complies with relevant standards)

ATTACHMENT TO IPP09 - 05/10/2016 Page 33

Page 34: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 12 of 29

September 2013 v1

On-Site Stormwater Detention C14. On site detention must be provided to ensure that the maximum discharge of

stormwater collected from the pre-developed site, which would occur during a 1 in 5 year storm of 1-hour duration for the existing site conditions, is not exceeded. All other stormwater run-off from the site for all storms up to a 1 in 100 year storm event is to be retained on the site for gradual release to the piped drainage system. Provision is to be made for satisfactory overland flow should a storm in excess of the above parameters occur. The OSD system shall be regularly maintained and serviced.

Engineering calculations, design and certification complying with this condition must be provided by an appropriately qualified and practicing Civil Engineer and submitted to Certifying Authority for approval prior to the issue of any Construction Certificate.

(Reason: To ensure appropriate provision is made for the disposal and

management of stormwater generated by the development, and to ensure that public infrastructure in Council’s care and control is not overloaded)

Pump-Out System Design for Stormwater Disposal C15. The design of the pump-out system for stormwater disposal will be permitted for

drainage of basement areas only, and must be designed in accordance with the following criteria:

a) The pump system shall consist of two pumps, connected in parallel, with each

pump being capable of emptying the holding tank at the rate equal to the rate of inflow for the one-hour duration storm. The tank shall be designed for capacity of holding an one-hour duration storm which would occur during average recurrence interval (A.R.I.) of 1 in 20 years storm;

b) The pump system shall be regularly maintained and serviced, every six (6)

months;

c) The creation of a Positive Covenant (under the provision of the Convincing Act) on the property title to ensure the maintenance of the Pump System on the property being developed. Prior to Occupation Certificate, details are to be submitted to Council for approval before registration with the Land Titles Office.

Engineering details demonstrating compliance with these criteria, and certified by an appropriately qualified and practicing civil engineer shall be provided to the Certifying Authority for approval prior to the issue of any Construction Certificate.

(Reason: To ensure adequate provision is made for the discharge of sub-surface

stormwater from the excavated parts of the site)

ATTACHMENT TO IPP09 - 05/10/2016 Page 34

Page 35: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 13 of 29

September 2013 v1

Bond for Damage and Completion of Infrastructure Works – Stormwater, Kerb and Gutter, Footpaths, Vehicular Crossing and Road Pavement C16. Prior to the issue of any Construction Certificate, security deposit or bank guarantee

must be provided to Council to the sum of $8,500.00 to be held by Council for the payment of cost for any/all of the following: a. making good any damage caused to any property of the Council as a

consequence of the doing of anything to which this consent relates,

b. completing any public work (such as road work, kerbing and guttering, footway construction, stormwater drainage and environmental controls) required in connection with this consent

c. remedying any defects in any such public work that arise within 6 months

after the work is completed.

The security in accordance with the schedule contained later in these conditions and must be provided by way of a deposit with the Council; or a guarantee satisfactory to Council (such as a satisfactory bank guarantee).

The security will be refundable following the expiration of 6 months from the issue of any final Occupation Certificate or completion of public work required to be completed (whichever is the latest) but only upon inspection and release by Council’s Engineers. Council shall have full authority to make use of the bond for such restoration works as deemed necessary by Council in circumstances including the following: - where the damage constitutes a hazard in which case Council may make use of

the security immediately; the applicant has not repaired or commenced repairing damage within 48

hours of the issue by Council in writing of instructions to undertake such repairs or works;

works in the public road associated with the development are to an unacceptable quality; and

the Certifying Authority must ensure that security bond is provided to North Sydney Council prior to issue of any Construction Certificate.

(Reason: To ensure appropriate security for works on public land and an

appropriate quality for new public infrastructure) Tree Bond for Public Trees C17. Prior to the issue of any construction certificate, security in the sum of $3,000.00

must be provided to Council for the protection of trees in public places, including the making good of any damage caused to such trees. The security is to be provided in accordance with the Schedule below.

ATTACHMENT TO IPP09 - 05/10/2016 Page 35

Page 36: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 14 of 29

September 2013 v1

The security required by this condition and in the schedule contained later in these conditions must be provided by way of a deposit with the Council; or other such guarantee that is satisfactory to Council (such as a bank guarantee). Any guarantee provided as security must name North Sydney Council as the nominated beneficiary and must not be subject to an expiry date.

The security will be refundable following the expiration of 6 months from the issue of any final Occupation Certificate but only upon inspection and release by Council's Landscape Development Officer.

If any tree is removed or damaged Council may deduct from this security the reasonable cost of replacement with a tree of the same species and to a similar stage of growth it would have attained at the completion of the work.

In the case of any tree, which cannot be replaced with a similar specimen, the security for that tree will be forfeited to Council and used to provide replacement street plantings.

SCHEDULE/LOCATION

Brushbox Located on road reserve to McHatton Street.

(Reason: Protection of existing environment public infrastructure, community assets and significant trees)

Air Conditioners in Residential Premises C18. The use of any air conditioner installed on the premises must comply with the

requirements of the Protection of the Environment Operations (Noise Control) Regulations 2008 and State Environmental Planning Policy (Infrastructure) 2007 and must not:

(a) emit a noise that is audible within a habitable room in any affected residence

(regardless of whether any door or window to that room is open);

(i) before 8.00am and after 10.00pm on any Saturday, Sunday or Public Holiday; or

(ii) before 7.00am or after 10.00pm on any other day

(b) cause an LAeq(15min) which exceeds the RBL background noise level by more than 5dB when measured at the boundary of any affected residence. The modifying factor adjustments in Section 4 of the EPA Industrial Noise Policy will be applied.

“affected residence” includes residential premises (including any lot in the strata scheme or another strata scheme), premises for short-term accommodation and hospitals.

“boundary” includes any window or elevated window of an affected residence.

ATTACHMENT TO IPP09 - 05/10/2016 Page 36

Page 37: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 15 of 29

September 2013 v1

Terms in this condition have the same meaning as in the Noise Guide for Local Government and the Industrial Noise Policy published by the NSW Environment Protection Authority. (Reason: To maintain residential amenity)

Security Deposit/ Guarantee Schedule C19. All fees and security deposits/ guarantees in accordance with the schedule below must

be provided to Council prior to the issue of any Construction Certificate:

Security deposit/ guarantee Amount ($) Street Tree Bond (on Council Property) $3,000.00 Footpath Damage Bond $8,500.00 TOTAL BONDS $11,500.00

(Reason: Compliance with the development consent)

BASIX Certificate

C20. Under clause 97A(3) of the Environmental Planning & Assessment Regulation 2000, it is a condition of this development consent that all the commitments listed in BASIX Certificate No. A259480 for the development are fulfilled. Plans and specifications complying with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.

(Reason: To ensure the proposed development will meet the Government’s requirements for sustainability and statutory requirements)

D. PRIOR TO THE COMMENCEMENT OF ANY WORKS (AND CONTINUING

WHERE INDICATED) Protection of Trees

D1. All trees that are specifically nominated to be retained by notation on plans or by condition as a requirement of this consent must be maintained and protected during demolition, excavation and construction on the site in accordance with AS4970-2009 (Protection of trees on development sites). A report containing recommendations, and methods of tree protection prepared by an appropriately qualified person must be provided to the Certifying Authority for approval by an appropriately qualified person prior to commencement of any works on the site. Any recommendations must be undertaken for the duration of works on the site.

(Reason: To ensure compliance with the requirement to retain significant planting on the site)

ATTACHMENT TO IPP09 - 05/10/2016 Page 37

Page 38: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 16 of 29

September 2013 v1

Public Liability Insurance – Works on Public Land D2. Any person or contractor undertaking works on public land must take out Public Risk

Insurance with a minimum cover of $20 million in relation to the occupation of public land and the undertaking of approved works within Council’s road reserve or public land, as approved in this consent. The Policy is to note, and provide protection/full indemnification for North Sydney Council, as an interested party. A copy of the Policy must be submitted to Council prior to commencement of the works. The Policy must be valid for the entire period that the works are being undertaken. Note: Applications for hoarding permits, vehicular crossings etc will require

evidence of insurance upon lodgement of the application. (Reason: To ensure the community is protected from the cost of any claim for

damages arising from works on public land) Sydney Water Approvals D3. Prior to the commencement of any works, the approved plans must be submitted to a

Sydney Water Quick Check agent or Customer Care Centre to determine whether the development application will affect Sydney Water’s sewer and water mains, stormwater drains and/or easements, and if further requirements need to be met. The approved plans will be appropriately stamped. The Certifying Authority must ensure that a Quick Check agent/Sydney Water has appropriately stamped the plans before the commencement of building works.

Note: For Quick Check agent details please refer to “Your Business” section of Sydney Water’s web site at www.sydneywater.com.au then see Building and Renovating under the heading Building and Developing, or telephone 13 20 92.

(Reason: To ensure compliance with Sydney Water requirements)

Commencement of Works Notice

D4. Building work, demolition or excavation in accordance with this development consent must not be commenced until the developer has given at least 2 days notice to North Sydney Council of the person’s intention to commence building work, demolition or excavation in accordance with this development consent.

(Reason: To ensure appropriate safeguarding measures are in place prior to the

commencement of any building work, demolition or excavation)

ATTACHMENT TO IPP09 - 05/10/2016 Page 38

Page 39: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 17 of 29

September 2013 v1

E. DURING DEMOLITION AND BUILDING WORK Construction Hours E1. Building construction and works must be restricted to within the hours of 7.00 am to

5.00 pm Monday to Friday and on Saturday to within the hours of 8.00 am to 1.00 pm inclusive, with no work on Sundays and Public Holidays.

Demolition works must be restricted to within the hours of 8.00 am to 5.00 pm Monday to Friday only. Excavation works must be restricted to within the hours of 8.00 am to 4.00 pm Monday to Friday only. For the purposes of this condition:

i. “Building construction” means any physical activity on the site involved in the erection of a structure, cladding, external finish, formwork, fixture, fitting of service installation and the unloading of plant, machinery, materials or the like.

ii. “Demolition works” means any physical activity to tear down or break up a

structure (or part thereof) or surface, or the like, and includes the loading of demolition waste and the unloading of plant or machinery.

iii. “Excavation work” means the use of any excavation machinery and the use of

jackhammers, rock breakers, excavators, loaders, or the like, regardless of whether the activities disturb or alter the natural state of the existing ground stratum or are breaking up/removing materials from the site and includes the unloading of plant or machinery associated with excavation work.

All builders, excavators must display, on-site, their twenty-four (24) hour contact telephone number, which is to be clearly visible and legible from any public place adjoining the site.

(Reason: To ensure that works do not interfere with reasonable amenity

expectations of residents and the community) Cigarette Butt Receptacle E2. A cigarette butt receptacle is to be provided on the site for the duration of

excavation/demolition/construction process, for convenient use of site workers.

(Reason: To ensure adequate provision is made for builders’ waste)

ATTACHMENT TO IPP09 - 05/10/2016 Page 39

Page 40: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 18 of 29

September 2013 v1

Parking Restrictions

E3. Existing public parking provisions in the vicinity of the site must be maintained at all times during works. The placement of any barriers, traffic cones, obstructions or other device in the road shoulder or kerbside lane is prohibited without the prior written consent of Council. Changes to existing public parking facilities/restrictions must be approved by the North Sydney Local Traffic Committee. The Developer will be held responsible for any breaches of this condition, and will incur any fines associated with enforcement by Council regulatory officers. (Reason: To ensure that existing kerbside parking provisions are not

compromised during works) Road Reserve Safety E4. All public footways and roadways fronting and adjacent to the site must be

maintained in a safe condition at all times during the course of the development works, with no obstructions caused to the said footways and roadways. Construction materials and plant must not be stored in the road reserve without approval of Council. A safe pedestrian circulation route and a pavement/route free of trip hazards must be maintained at all times on or adjacent to any public access ways fronting the construction site. Where public infrastructure is damaged, repair works must be carried out in when and as directed by Council officers (at full Developer cost). Where pedestrian circulation is diverted on to the roadway or verge areas, clear directional signage and protective barricades must be installed in accordance with AS 1742-3 (1996) “Traffic Control Devices for Work on Roads”. If pedestrian circulation is not satisfactorily maintained across the site frontage, and action is not taken promptly to rectify the defects, Council may undertake proceedings to stop work.

(Reason: Public Safety) Temporary Disposal of Stormwater Runoff E5. During construction, stormwater runoff must be disposed in a controlled manner that

is compatible with the erosion and sediment controls on the construction site. Immediately upon completion of any impervious areas on the site (including roofs, driveways, paving) and where the final drainage system is incomplete, the necessary temporary drainage systems must be installed to reasonably manage and control runoff as far as the approved point of stormwater discharge. Such ongoing measures must be to the satisfaction of the Principal Certifying Authority.

(Reason – Stormwater control during construction)

ATTACHMENT TO IPP09 - 05/10/2016 Page 40

Page 41: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 19 of 29

September 2013 v1

Geotechnical Stability during Works

E6. A contractor with specialist excavation experience must undertake the excavations for

the development and a suitably qualified and consulting geotechnical engineer must oversee the excavation procedure. Geotechnical aspects of the development work, namely appropriate excavation method and vibration control, support and retention of excavated faces, and Hydro geological considerations must be undertaken in accordance with the recommendations of the Geotechnical Report prepared by qualified Geotechnical Engineer, and all subsequent geotechnical inspections carried out during the excavation and construction phase. Approval must be obtained from all affected property owners, including North Sydney Council where rock anchors (both temporary and permanent) are proposed below adjacent private or public property. (Reason: Ensure appropriate professional are engaged at appropriate stages

during construction)

Removal of Extra Fabric E7. Should any portion of the existing building, trees, or curtilage of the site which is

indicated on the approved plans to be retained be damaged for whatever reason, all the works in the area of the damaged portion are to cease and written notification of the damage is to be given to Council forthwith. No work is to resume until the written approval of Council to do so is obtained. Failure to comply with the provisions of this condition may result in the Council taking further action including legal proceedings if necessary.

(Reason: To ensure compliance with the terms of this development consent)

Dust Emission and Air Quality E8. The following must be complied with at all times:

(a) Materials must not be burnt on the site. (b) Vehicles entering and leaving the site with soil or fill material must be

covered. (c) Dust suppression measures must be carried out to minimise wind-borne

emissions in accordance with the NSW Department of Housing’s 1998 guidelines - Managing Urban Stormwater: Soils and Construction.

(d) Odour suppression measures must also be carried out where appropriate so as

ATTACHMENT TO IPP09 - 05/10/2016 Page 41

Page 42: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 20 of 29

September 2013 v1

to prevent nuisance occurring at adjoining properties. (Reason: To ensure residential amenity is maintained in the immediate vicinity)

Noise and Vibration E9. The works must be undertaken in accordance with the “Interim Construction Noise

Guideline” published by the NSW Environment Protection Authority, to ensure excessive levels of noise and vibration do not occur so as to minimise adverse effects experienced on any adjoining land.

(Reason: To ensure residential amenity is maintained in the immediate vicinity) Developer’s Cost of Work on Council Property E10. The developer must bear the cost of all works associated with the development that

occurs on Council’s property, including restoration of damaged areas.

(Reason: To ensure the proper management of public land and funds) No Removal of Trees on Public Property E11. No trees on public property (footpaths, roads, reserves, etc.) unless specifically

approved by this consent shall be removed or damaged during construction including for the erection of any fences, hoardings or other temporary works.

(Reason: Protection of existing environmental infrastructure and community

assets) Benchmarks E12. All permanent survey markers must be retained, undamaged, and not relocated.

(Reason: Protection of existing environmental infrastructure and community assets)

Construction Hours E13. Building construction and works must be restricted to within the hours of 7.00 am to

5.00 pm Monday to Friday and on Saturday to within the hours of 8.00 am to 1.00 pm inclusive, with no work on Sundays and Public Holidays.

Demolition and excavation works must be restricted to within the hours of 8.00 am to 5.00 pm Monday to Friday only. For the purposes of this condition: a) “Building construction” means any physical activity on the site involved in the

erection of a structure, cladding, external finish, formwork, fixture, fitting of

ATTACHMENT TO IPP09 - 05/10/2016 Page 42

Page 43: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 21 of 29

September 2013 v1

service installation and the unloading of plant, machinery, materials or the like.

b) “Demolition works” means any physical activity to tear down or break up a

structure (or part thereof) or surface, or the like, and includes the loading of demolition waste and the unloading of plant or machinery.

c) “Excavation work” means the use of any excavation machinery and the use of

jackhammers, rock breakers, excavators, loaders, or the like, regardless of whether the activities disturb or alter the natural state of the existing ground stratum or are breaking up/removing materials from the site and includes the unloading of plant or machinery associated with excavation work.

All builders, excavators must display, on-site, their twenty-four (24) hour contact telephone number, which is to be clearly visible and legible from any public place adjoining the site.

(Reason: To ensure that works do not interfere with reasonable amenity

expectations of residents and the community) Out of Hours Work Permits E14. Where it is necessary for emergency works to occur outside those hours allowed by

these conditions, an application may be made to Council's Customer Services Centre for a permit to carry out emergency works outside of the approved hours. If a permit is issued the development must be carried out in accordance with any requirements of the permit. A permit and shall only be approved if public safety or convenience is at risk. Any further variation shall require the lodgement and favourable determination of a modification application pursuant to Section 96 of the Environmental Planning and Assessment Act 1979.

Notes: 1) Failure to obtain a permit for work outside of the approved hours will result in

on the spot fines being issued, or Council pursuing any action required (including legal proceedings) to have the out of hours work cease, without prior warning.

2) Further information on permits can be obtained from the Council website at www.northsydney.nsw.gov.au.

3) It is recommended that applications for permits be lodged as early as possible to allow sufficient time for determination by Council and avoid disruption or delay due to conflicting priorities.

4) Permit Emergency for such occurrence shall be limited to two occasions per calendar month

(Reason: To ensure that works do not interfere with reasonable amenity

expectations of residents and the community)

ATTACHMENT TO IPP09 - 05/10/2016 Page 43

Page 44: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 22 of 29

September 2013 v1

Installation and Maintenance of Sediment Control E15. Erosion and sediment controls must be installed and maintained at all times in

accordance with the Sediment and erosion control plan submitted and approved with the Construction Certificate. Erosion and sediment measures must be maintained in accordance with the publication Managing Urban Stormwater: Soils & Construction (4th edition, Landcom, 2004), commonly referred to as the “Blue Book” and can only be removed when development activities have been completed and the site fully stabilised.

(Reason: To protect the environment from the effects of sedimentation and erosion from development sites)

Site Amenities and Facilities E16. Where work involved in the erection and demolition of a building is being carried out,

amenities which satisfy applicable occupational health and safety and construction safety regulations, including any WorkCover Authority requirements, must be provided and maintained at all times. The type of work place determines the type of amenities required.

Further information and details can be obtained from the Internet at www.workcover.nsw.gov.au

(Reason: To ensure the health and safety of the community and workers on the site)

Health and Safety E17. All work undertaken must satisfy applicable occupational health and safety and

construction safety regulations, including any WorkCover Authority requirements to prepare a health and safety plan. Site fencing must be installed sufficient to exclude the public from the site. Safety signs must be erected that warn the public to keep out of the site, and provide a contact telephone number for enquiries.

Further information and details regarding occupational health and safety requirements for construction sites can be obtained from the internet at www.workcover.nsw.gov.au

(Reason: To ensure the health and safety of the community and workers on the site)

Prohibition on Use of Pavements E18. Building materials must not be placed on Council’s footpaths, roadways, parks or

grass verges (unless a permit is obtained from Council beforehand). A suitable sign to this effect must be erected adjacent to the street alignment.

ATTACHMENT TO IPP09 - 05/10/2016 Page 44

Page 45: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 23 of 29

September 2013 v1

(Reason: To ensure public safety and amenity on public land) Waste Disposal E19. All records demonstrating the lawful disposal of waste must be retained and kept

readily accessible for inspection by regulatory authorities such as North Sydney Council and the Environmental Protection Authority. (Reason: To ensure the lawful disposal of construction and demolition waste)

F. PRESCRIBED CONDITIONS IMPOSED UNDER EP&A ACT AND

REGULATIONS AND OTHER RELEVANT LEGISLATION Building Code of Australia F1. All building work must be carried out in accordance with the provisions of the

Building Code of Australia.

(Reason: Prescribed - Statutory) Home Building Act F2. 1) Building work that involves residential building work (within the meaning and

exemptions provided in the Home Building Act 1989) for which the Home Building Act 1989 requires there to be a contract of insurance under Part 6 of that Act must not be carried out unless the Principal Certifying Authority for the development to which the work relates has given North Sydney Council written notice of the contract of insurance being issued and of the following:

a) in the case of work for which a principal contractor is required to be

appointed:

i) the name and licence number of the principal contractor, and ii) the name of the insurer by which the work is insured under Part

6 of that Act, or

(b) in the case of work to be done by an owner-builder:

(i) the name of the owner-builder, and (ii) if the owner-builder is required to hold an owner-builder permit

under that Act, the number of the owner-builder permit.

2) If arrangements for doing residential building work are changed while the work is in progress such that the information submitted to Council in accordance with this conditions is out of date, work must cease and no further work may be carried out unless the Principal Certifying Authority for the development to which the work relates (not being the Council), has given the Council written notice of the updated information.

ATTACHMENT TO IPP09 - 05/10/2016 Page 45

Page 46: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 24 of 29

September 2013 v1

Note: A certificate purporting to be issued by an approved insurer under Part 6 of the

Home Building Act 1989 that states that a person is the holder of an insurance policy issued for the purposes of that Part is, for the purposes of this clause, sufficient evidence that the person has complied with the requirements of that Part.

(Reason: Prescribed - Statutory)

Appointment of a Principal Certifying Authority (PCA) F3. Building work, demolition or excavation in accordance with the development consent

must not be commenced until the developer has appointed a Principal Certifying Authority for the building work in accordance with the provisions of the EP&A Act and its Regulations.

(Reason: Statutory; To ensure appropriate safeguarding measures are in place

prior to the commencement of any building work, demolition or excavation)

Construction Certificate F4. Building work, demolition or excavation in accordance with the development consent

must not be commenced until a Construction Certificate for the relevant part of the building work has been issued in accordance with the provisions of the EP&A Act and its Regulations.

(Reason: Statutory; To ensure appropriate safeguarding measures are in place

prior to the commencement of any building work, demolition or excavation)

Occupation Certificate F5. A person must not commence occupation or use of the whole or any part of a new

building (new building includes an altered portion of, or an extension to, an existing building) unless an Occupation Certificate has been issued in relation to the building or part. Only the Principal Certifying Authority appointed for the building work can issue an Occupation Certificate.

(Reason: Statutory) Critical Stage Inspections F6. Building work must be inspected by the Principal Certifying Authority on the critical

stage occasions prescribed by the EP&A Act and its Regulations, and as directed by the appointed Principal Certifying Authority.

ATTACHMENT TO IPP09 - 05/10/2016 Page 46

Page 47: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 25 of 29

September 2013 v1

(Reason: Statutory) Commencement of Works F7. Building work, demolition or excavation in accordance with this development consent

must not be commenced until the developer has given at least 2 days notice to North Sydney Council of the person’s intention to commence the erection of the building.

(Reason: Statutory; To ensure appropriate safeguarding measures are in place

prior to the commencement of any building work, demolition or excavation)

Excavation/Demolition F8. 1) All excavations and backfilling associated with the erection or demolition of a

building must be executed safely and in accordance with appropriate professional standards.

2) All excavations associated with the erection or demolition of a building must

be properly guarded and protected to prevent them from being dangerous to life or property.

3) Demolition work must be undertaken in accordance with the provisions of

AS2601- Demolition of Structures.

(Reason: To ensure that work is undertaken in a professional and responsible manner and protect adjoining property and persons from potential damage)

Protection of Public Places F9. 1) A hoarding and site fencing must be erected between the work site and

adjoining public place.

2) If necessary, an awning is to be erected, sufficient to prevent any substance from, or in connection with, the work falling into the public place.

3) The work site must be kept lit between sunset and sunrise if it is likely to be

hazardous to persons in the public place.

4) Any such hoarding, fence or awning is to be removed when the work has been completed.

5) No access across public reserves or parks is permitted.

ATTACHMENT TO IPP09 - 05/10/2016 Page 47

Page 48: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 26 of 29

September 2013 v1

Note: Prior to the erection of any temporary fence or hoarding over property owned or managed by Council, written approval must be obtained. Any application needs to be accompanied by plans indicating the type of hoarding and its layout. Fees are assessed and will form part of any approval given. These fees must be paid prior to the approval being given. Approval for hoardings will generally only be given in association with approved building works, maintenance or to ensure protection of the public. An application form for a Hoarding Permit can be downloaded from Council’s website.

(Reason: To ensure public safety and the proper management of public land)

Site Sign F10. 1) A sign must be erected in a prominent position on the site

a) stating that unauthorised entry to the work site is prohibited;

b) showing the name of the principal contractor (or person in charge of the work site), and a telephone number at which that person may be contacted at any time for business purposes and outside working hours; and

c) showing the name, address and telephone number of the Principal

Certifying Authority for the work.

2) Any such sign must be maintained while to building work or demolition work is being carried out, but must be removed when the work has been completed.

(Reason: Prescribed - Statutory) Support for Neighbouring Buildings F11. 1) If an excavation associated with the erection or demolition of a building

extends below the level of the base of the footings of a building on an adjoining allotment of land, the person causing the excavation to be made:

a) Must preserve and protect the building from damage;

b) If necessary, must underpin and support the adjoining building in an approved manner Subject to adjoining owner’s consent); and

c) Must, at least 7 days before excavating below the level of the base of the footings of a building on an adjoining allotment of land, give notice of intention to do so to the owner of the adjoining allotment of land and furnish particulars of the excavation to the owner of the building being erected or demolished.

ATTACHMENT TO IPP09 - 05/10/2016 Page 48

Page 49: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 27 of 29

September 2013 v1

2) The owner of the adjoining allotment of land is not liable for any part of the cost of work carried out for the purposes of this clause, whether carried out on the allotment of land being excavated or on the adjoining allotment of land.

3) In this clause, allotment of land includes a public road and any other public

place.

(Reason: To ensure adjoining owner’s property rights are protected and protect adjoining properties from potential damage)

G. PRIOR TO THE ISSUE OF AN OCCUPATION CERTIFICATE Front Fence G1. The brick wall and palisade front fence is to be reconstructed to match the form of the

existing fence at the completion of the works. The reinstated wall and fence must have a matching brick base and palisade fence with the detailing of the fence and piers to exactly match the existing fence in terms of materials, height, location and detail.

(Reason: To minimise impact on the conservation area)

Infrastructure Repair and Completion of Works G2. Prior to the issue of any Occupation Certificate any and all works relating to the

development:

a. in the road reserve must be fully completed to the satisfaction of Council Engineers at no cost to Council; and

b. to repair and make good any damaged public infrastructure caused as a result of any works relating to the development (including damage caused by, but not limited to, delivery vehicles, waste collection, contractors, sub contractors, concrete vehicles) must be fully repaired to the satisfaction of Council Engineers at no cost to Council.

(Reason: Maintain quality of Public assets)

Covenant & Restriction (Stormwater Control Systems) G3. An Instrument pursuant to Sections 88B and 88E of the Conveyancing Act 1919 and

one copy must be submitted to Council in registrable form, providing for:

a. a restriction as to user and positive covenant as to user as appropriate in favour of North Sydney Council burdening 5 Mchatton Street requiring the ongoing retention, maintenance and operation of the stormwater facility (on-site detention, pump-out and rainwater tanks);

ATTACHMENT TO IPP09 - 05/10/2016 Page 49

Page 50: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 28 of 29

September 2013 v1

b. North Sydney Council being nominated in the Instrument as the only party

authorised to release, vary or modify the Instrument;

c. the wording on the Instrument making reference to the Council file/s which hold: (a) the Construction plans; and (b) the “Work-as-Executed” (as built) plans;

Upon Council being satisfied as to the terms of the Instrument, North Sydney Council’s official seal will be affixed to these documents, prior to submission to the Land & Property Information Office for registration

The Instrument creating the restriction and/or covenant under ss 88B and 88E required by this condition of consent must be registered on the Title of the development site prior to the issue of an Occupation Certificate or commencement of use of the site, whichever is the earlier. Evidence of the registration of the instrument referred to in this condition is to be provided to Council prior to the issue of an Occupation Certificate. All costs associated with the preparation, approval and registration of the Instrument required by this condition of consent must be borne by the person acting on this consent including the reasonable costs of Council in obtaining advice, negotiating the terms or otherwise facilitating the execution and registration of the required Instrument.

(Reason: Compliance and adequate maintenance of drainage system)

Damage to Adjoining Properties G4. All precautions must be taken to prevent any damage likely to be sustained to

adjoining properties. Adjoining owner property rights and the need for owner’s permission must be observed at all times, including the entering onto land for the purpose of undertaking works.

(Reason: To ensure adjoining owner’s property rights are protected) Utility Services G5. All utility services shall be adjusted, to the correct levels and/or location/s required by

this consent, prior to issue of an occupation certificate. This shall be at no cost to Council.

(Reason: To ensure compliance with the terms of this consent)

ATTACHMENT TO IPP09 - 05/10/2016 Page 50

Page 51: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

5 MCHATTON STREET, WAVERTON DEVELOPMENT APPLICATION NO. 20716 Page 29 of 29

September 2013 v1

Basement Pump-Out Maintenance G6. Prior to issue of an Occupation Certificate a Maintenance Regime must be prepared

for the basement stormwater pump-out system and submitted to the Principal Certifying Authority for approval with the Occupation Certificate documentation. The regime must specify that the system is to be regularly inspected and checked by qualified practitioners. The basement stormwater pump-out system must be maintained in accordance with the approved Maintenance Regime at all times.

(Reason: To ensure future provision for maintenance of the drainage system)

BASIX Completion Certificate G7. In accordance with Clause 154C of the Environmental Planning and Assessment

Regulation 2000, prior to issuing a final occupation certificate the Certifying Authority must apply to the Director-General for a BASIX completion receipt.

(Reason: To ensure compliance with the specified BASIX Certificate) I. ON-GOING / OPERATIONAL CONDITIONS Tennis Court Lighting Illumination Intensity I1. The level of illumination and/or lighting intensity used to illuminate the tennis court

lighting must comply with the requirements of Australian Standard AS4282:1997 Control of the Obtrusive Effects of Outdoor lighting. The lighting poles must be controlled to ensure that excessive light spill or nuisance is not caused to any nearby premises.

(Reason: To ensure that the residential amenity of adjoining properties is not

adversely affected by the nature of the lighting to the tennis court) Hours of Illumination I2. The tennis court shall not be lit between the hours of 8pm and 6am.

(Reason: To ensure that the residential amenity of adjoining properties is not adversely affected by the nature of the lighting to the tennis court)

ATTACHMENT TO IPP09 - 05/10/2016 Page 51

Page 52: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

60

60

70

70

70

60

80

90

80

80

80

7090

80

66.6

67.8 69.7

67.9

67.0

67.6

70.8

66.6

69.2

68.3

65.5

60.4

59.4

62.3

60.3

67.5

64.3

74.1

74.5

71.8

72.2

72.2

69.7

74.7

70.2

78.4

75.2

70.7

76.0

72.8

70.1

72.7

69.2

69.9

66.9

70.4

71.9

78.7

72.7

79.3

79.7

76.8

74.4

78.8

75.6

74.1

75.5

72.2

74.4

68.6

78.2

80.177.7

78.7 82.1

79.6

81.0

81.8

82.1

81.4

79.9

85.4

77.9

77.6

79.4

81.5

87.2

85.8

88.082.5

80.1

53.460.7

75.9

80.5 81.8

80.279.8

61.0

61.6

70.2

70.7 72.0

68.1

71.5

77.4

72.9

70.7

71.0

70.8

68.3

71.0

71.0

69.4

69.8

69.4

80.9

83.4

79.7

89.1

78.6

77.8

73.6

76.7

80.0

77.5

77.3

77.2

81.181.1

80.580.5

81.381.3

80.380.3

79.879.8

79.279.2

76.774.6 80.474.2

80.382.9

80.8

82.0

79.2

81.3

89.5

82.5

81.8

79.6 80.6

80.8

94.1

76.7

78.978.9

82.4

78.578.580.9

81.2 81.5

90.2

82.3

78.6

82.8

93.3

89.689.6

90.590.5

80.480.4

87.1

84.884.8

79.8

83.983.9

79.8

82.7

87.6

88.688.6

82.482.4

82.482.4

84.584.5

88.288.2

86.286.2

87.887.8

85.985.9

96.396.3

85.585.5

85.385.3

81.5

80.6

72.5

70.5

80.7

85.0

85.8

83.9

77.2

76.1

73.9

76.9

78.1

82.5

82.7

80.3

77.0

82.2

81.7

81.3

73.2

74.1

82.9

78.8

73.4

78.8

86.2

81.9

87.2

88.1

86.0

89.9

86.9

82.9

87.588.4

89.5

90.8

94.8

94.8

99.2

83.2

84.8

87.2

88.2

90.0

89.8

95.2

94.6

98.798.6

97.296.9

100.2

100.5100.5

100.7100.7

96.7

97.1

97.297.0

100.1100.1 101.2101.2

100.0100.0

92.0 91.3

94.794.8

84.1

85.6

89.4

86.7

94.1

88.0

96.6

88.6

88.1

89.3

93.7

96.8 95.6

94.494.4

94.294.294.194.1

96.8

92.9

93.8

90.689.6

94.5

97.1

90.790.4

99.799.799.999.9

96.496.4

98.498.4

BAY

LANEHARRIOTT STREET

NEST

WAVERTO

N

AVENUE

WAVERTO

N LANE

OAK STREET

ROAD

EDWARD

PRIORY

BROWNS LANE WEST

TOONGARAH

ROAD ROAD

RESERVE

ROAD

TOO

NGARAH RO

AD

McHATTON

STREET

LANE

STREET

ROAD

ROAD

STREET

SINCLAIR STREET

SINCLAIR STREET PEDESTRIAN LINK

HAZELBANK

43

41

78

39

76

37

2

4A4

1

6

3

5

7

9

11

21

16

1412

108

64

9

2

72A

53

1

91

1

24

631- 37

39- 41

4340

45

3

5

7-17

1921

42

17

49-51

2-4

28

15

(26A )

22

23

26

24

22

22A

20

24

18

17

1B

2

25

35

26

16

3

13-15

28

29

1

31

8-10

74

6

30

31

7-94

52

(18)

33

3

70

35

1

29A

37

6

39

29

66

64

68

39A

1

27A

4

62

27

41

3-9

58

3

2

25

56

32

54

5

1A

23

1

34

52

41A

18

21

7

50

20

1

36

43

2

22

48

19

9

38

45

24

4

26

11

2

17

40

47

5

2A

6

46

20

8

44

15

53

6

11 46

55

9 48

4

2B

57

50

7

5A 59

5

52

31

61

54

7

63

5

9

56

1 1

65 11A

58 15

67

40-4238

2826

2422

20

1518

1116

12-14

10A 10 8B 8A6

4

810

12

14

16

18

28

26

27

25

23

21

297

190

295

281

60

58

19

56

54A

17

7154

6952

6750

6548

63

22

46

6144

59

15

57

55

53

51

188

49

(32)

42

11A

30

28

26

22

1

317

313

418

B

SP 21145

2

8688 20

719092SP 8719

19

Sec 3

7354

1

18SP 32170

SP 3885

SP 62795

17

SP 10677

SP 4172

SP 3510

15

Sec 3

C

7354

144005438 2 1041055

SP 3580

7 1

19 7

4029

18982

SP 21216

SP 3524

840673 SP 3

355

18

SP 12537

6

382003

10

18982

9

7354

X

SP 46122

SP 69516

SP 1253

Sec 3

7544

SP 3762

Sec 3Sec

373545

BSP 6786 4

501480

331344 345441

1

SP 2885

SP 12299

SP 15908

SP 34288

SP 2258SP 4961

SP 11588

SP 4173

SP 4120

SP 30151

SP 52008

SP 8831

SP 13981

SP 1082

SP 472

SP 673

16

SP 14195

6

SP 34511

5SP 362

1

SP 15394

SP 118

17

339128

17640SP 1195

SP 3067SP 761

7

SP 19781

9

5013

22 3266641

10730

10730

306450

8

2

23

SP 64339 1

SP 3275

SP 1919

1

2

SP 18287

102

1

24

875349

22

31

10730

2

Sec 6

9

SP 12116

101

793237100

704487SP 15037

703255 793238

SP 37812

SP 398041

4 192299

1

CB

SP 459195409

82

314839

192299

A 2SP 13862

8

SP 32774 SP 3332

20

7

7544

SP 21257

Sec 2

1

3

Sec 2

817407

7544SP 2944

SP 8862

3 Sec 1

23

7544

8

2

SP 307993

7544 999946862075

Sec 1

6426

3 17

2 1

1 25

973946SP 1331527

8869DRAINAGE

R

ESERVE

5

26 Sec 1165897

7544

1 5 8869

2

SP 7965

SP 87270

310941

14

11 1

Sec 37544

7 SP 12919

SP 136 SP 54872 8

772366

642

17495 166

4849

5051

5253

5455

5657

58

17495 SP 2346

SP 18226

4645

1723344

4342

4140

3938

59

3736

35

1

184559

127

183591

1134

11

SP 76305

996198

1040409

10730

1002384SP 22319

26

11

60

SP 17467

3

10730

2224

28

780423

6

628661

72

168106

8869

75449

797180SP 12220966223Sec 1

SP 15426

7544 1

21

15SP 340081

7724261168107

25

1

10730

973368Sec 1772373

101

12071

45

11

77250213

175453

772367

20

6

5

4038

4

3 SP 171355952212

SP 13400

SP 14122

SP 14745

SP 4888

SP 4723

SP 5318Sec 3

4038

1

57

58

59

SP 3038

12

SP 2358

10730

SP 2873

6285661617495

7816671

11510730

84374141

327421 120178

32

2 1

BCT 52342903

12

SP 17303

137004

1

North Sydney CouncilCopyright:

Copyright © North Sydney Council - No part of this map may be reproducedwithout permission. Commercial decisions should not be made based on information contained in this map without first checking details held by the responsible Government authority.

Further details can be obtained by calling (02) 9936 8100 or e-mail [email protected].

ATTACHMENT TO IPP09 - 05/10/2016 Page 52

Page 53: Item - REPORTS · 6 s treet l a n e l a n e c h u r c h s t r e e t s t r e e t c h u r c h road w e s t (2) 4 9 a (3 4) (3 6) 5 1 1 5 3 5 5 5 7 9 11 13 15 14 1 7 16 19-21 41-45 13

For privacy reasons, the architectural plans have been removed

from this document prior to publishing on the web. The plans

attached to the hard copy report may be viewed at Stanton Library

during opening hours or at the Customer Service Centre in Council

Chambers between 9.00am and 4.00pm Monday to Friday.