1 Invitation to Bid Date: 29.10.2008 Dear Sir/Madam, Subject: Civil works - construction of 3 family houses, 1 medical/health village unit, and 1 industrial building in Hadareni Village, Mures County Background informat6ion on the “COMMUNITY DEVELOPMENT PROGRAME IN HADARENI VILAGE” Following the Decision no. 1/2005 of the European Court of Human Rights – amiable solution - in the case of Moldovan and others against Romania, the Romanian Government has initiated a community development programe in Hadareni village, Mures county. The aim of the program is to increase community cohesion between Roma, Hungarians and Romanian citizens of the village by creating local organizational capacity, promoting civic education, initiating and developing dialogue between ethnic and religious groups, enhancing economic development . 1. We hereby solicit your bid for civil works regarding the construction of 3 family houses, 1 medical/health village unit, and 1 industrial building in Hadareni Village, Mures County 2. To enable you to submit a bid, please find enclosed: Annex I. Instructions to Bidders Annex II. Bid Data Sheet Annex III. General Terms and Conditions Annex IV. Special Conditions Annex V. Schedule of Requirements Annex VI. Technical Specifications and details Annex VII. Bid Submission Form Annex VIII. Price schedule 3. Interested Bidders may obtain further information at the following address: Contact Person: Cristina Boldur Name of Office: UNDP Romania, Procurement Unit UN House, 48A Primaverii Blvd., Sector 1, Bucharest Telephone & Fax: 0212017872 / 0212017828 E-Mail: proc ure me nt.ro @undp.org All requests for additional information and clarifications must be submitted in writing either by e-mail ([email protected] ) or by fax (0212017828). 4. Bids must be delivered to the above office on or before 19.11.2008, 16:00 hrs. Late bids shall be rejected. 5. Bids will be opened in the presence of Bidders’ Representatives, who chose to attend at UNDP offices in Bucharest, Romania, on 20 November 2008, 12:00 hrs. 6. This letter is not to be construed in any way as an offer to contract with your firm. Sincerely, Formatted: Font color: Auto

Upload: kingbpp

Post on 28-Oct-2015

46 views

Category:

Documents


7 download

DESCRIPTION

Invitation to BID - New constructions

TRANSCRIPT

Page 1: ITB Constructii Noi Rev1

1

Invitation to Bid

Date: 29.10.2008 Dear Sir/Madam,

Subject: Civil works - construction of 3 family houses, 1 medical/health village unit, and 1 industrial building in

Hadareni Village, Mures County

Background informat6ion on the “COMMUNITY DEVELOPMENT PROGRAME IN HADARENI VILAGE” Following the Decision no. 1/2005 of the European Court of Human Rights – amiable solution - in the case of

Moldovan and others against Romania, the Romanian Government has initiated a community development programe in Hadareni village, Mures county. The aim of the program is to increase community cohesion between Roma, Hungarians and Romanian citizens of

the village by creating local organizational capacity, promoting civic education, initiating and developing dialogue

between ethnic and religious groups, enhancing economic development .

1. We hereby solicit your bid for civil works regarding the construction of 3 family houses, 1

medical/health village unit, and 1 industrial building in Hadareni Village, Mures County

2 . To enable you to submit a bid, please find enclosed:

Annex I. Instructions to Bidders Annex II. Bid Data Sheet

Annex III. General Terms and Conditions Annex IV. Special Conditions Annex V. Schedule of Requirements

Annex VI. Technical Specifications and details Annex VII. Bid Submission Form Annex VIII. Price schedule

3. Interested Bidders may obtain further information at the following address:

Contact Person: Cristina Boldur Name of Office: UNDP Romania, Procurement Unit

UN House, 48A Primaverii Blvd., Sector 1, Bucharest

Telephone & Fax: 0212017872 / 0212017828 E-Mail: [email protected]

All requests for additional information and clarifications must be submitted in writing either by e-mail ([email protected]) or by fax (0212017828).

4. Bids must be delivered to the above office on or before 19.11.2008, 16:00 hrs. Late bids shall be rejected.

5. Bids will be opened in the presence of Bidders’ Representatives, who chose to attend at UNDP offices in

Bucharest, Romania, on 20 November 2008, 12:00 hrs.

6 . This letter is not to be construed in any way as an offer to contract with your firm.

Sincerely,

Formatted: Font color: Auto

Page 2: ITB Constructii Noi Rev1

2

Annex I

INSTRUCTIONS TO BIDDERS A. Introduction

General: The Purchaser invites sealed Bids for five (5) lots of civil works, as follows: LOT NO. 1 Construction of family house “Lacatus Ghiolanca”

LOT NO. 2 Construction of family house “Moldovan Adrian”

LOT NO. 3 Construction of family house “Zoltan Florina”

LOT NO. 4 Construction of Medical/Health village unit

LOT NO. 5 Construction of Industrial Building

Bidders may quote for any of the lots or for all lots. In the case of bidding for multiple lots, the bidder must present

separate and distinct quotation for each lot. 1. Eligible Bidders: Bidders should not be associated, or have been associated in the past, directly or indirectly,

with a firm or any of its affiliates which have been engaged by the Purchaser to provide consulting services for

the preparation of the design specifications, and other documents to be used for the procurement of civil works to be purchased under this Invitation to Bids.

2. Cost of Bid: The Bidder shall bear all costs associated with the preparation and submission of the Bid, and the procuring UN entity will in no case be responsible or liable for those costs, regardless of the conduct or outcome of the solicitation.

B. Solicitation Documents

4. Examination of Solicitation Documents: The Bidder is expected to examine all corresponding instructions, forms, terms and specifications contained in the Solicitation Documents. Failure to comply with these documents will be at the Bidder’s risk and may affect the evaluation of the Bid.

5. Clarification of Solicitation Documents: A prospective Bidder requiring any clarification of the Solicitation

Documents may notify the procuring entity in writing. The response will be made in writing to any request for

clarification of the Solicitation Documents that it receives earlier than two weeks prior to the Deadline for the Submission of Bids. Written copies of the response (including an explanation of the query but without identifying the source of inquiry) will be sent to all prospective Bidders that received the Solicitation

Documents. 6. Amendments of Solicitation Documents: No later than two weeks prior to the Deadline for Submission of

Bids, the procuring entity may, for any reason, whether at its own initiative or in response to a clarification requested by a prospective Bidder, amend the Solicitation Documents. All prospective Bidders that have received the Solicitation Documents will be notified in writing of any amendments. In order to afford

prospective Bidders reasonable time in which to take the amendments into account in preparing their offers, the procuring entity may, at its discretion, extend the Deadline for the Submission of Bids.

C. Preparation of Bids

. 7. Language of the Bid: The Bid prepared by the Bidder and all correspondence and documents relating to the

Bid exchanged by the Bidder and the procuring entity shall be written in the language indicated on the Bid Data Sheet.

8. Documents Comprising the Bid:

The Bid must comprise the following documents:

(a) a Bid Submission form; (b) a Price Schedule completed in accordance with the Annexes V, VI and VIII and clause 11 of Instructions to

Bidders; (c) documentary evidence established in accordance with clause 9 of Instructions to Bidders that the Bidder is

eligible to and is qualified to perform the contract if its Bid is accepted,

Page 3: ITB Constructii Noi Rev1

3

(d) documentary evidence established in accordance with clause 10 of Instructions to Bidders that the civil works and ancillary services to be supplied by the Bidder are eligible civil works and services and conform to the Bidding Documents;

Absence of all or part of the above documents in a Bid or submission of a Bid, which is not fully corresponding, to the Bidding Documents’ requirements may lead to rejection of the aforementioned Bid.

9. Documents Establishing Bidder’s Eligibility and Qualifications:

The Bidder shall furnish evidence of its status as qualified construction work company. The documentary evidence of the Bidder’s qualifications to perform the contract if its Bid is accepted shall be established to the Purchaser’s satisfaction:

(a) Copies of original documents defining the constitution or legal status, place of registration and

principal pace of business of the Bidder

(b) that the Bidder is reliable and capable to perform the contract: - annual balance sheet of the company (including income statement) certified by the fiscal authorities; - the documentary evidence of the Bidder’s economic and financial capacity (bank statement of the Bidder’s

economic/financial reliability, auditing report, other relevant documentary evidence of economic and financial reliability);

(c) company profile (company’s profile and a list of the most important contracts )

10. Documents Establishing Civil works’ Conformity to Bidding Documents:

Construction materials and goods shall conform to Romanian standards, Specifications of the manufacturer, other applicable standards and shall combine high quality and functional reliability. Construction materials and goods shall be supplied to the Purchaser properly packed to avoid damage during transportation and storage.

The documentary evidence of conformity to the Bidding Documents may be in the form of literature, drawings, and data, and shall consist of: (a) A detailed description of the essential technical and performance characteristics of the equipment;

(b) A list giving full particulars, including available sources and current prices of spare parts, special tools, etc, necessary for the proper and continuing functioning of the equipment.

11. Bid Currencies/Bid Prices: All prices shall be quoted in Lei (or US Dollars). The Bidder shall indicate on the appropriate Price Schedule the unit prices (where applicable) and total Bid Price of the civil works it proposes to supply under the contract.

12. Period of Validity of Bids: Bids shall remain valid for 120 days after the date of Bid Submission prescribed by

the procuring UN entity pursuant to clause 16 of Instructions to Bidders. A Bid valid for a shorter period may

be rejected as non-responsive pursuant to clause 20 of Instructions to Bidders. In exceptional circumstances, the procuring UN entity may solicit the Bidder’s consent to an extension of the period of validity. The request and the responses thereto shall be made in writing. Bidders granting the request will not be required nor permitted to

modify their Bids.

13. Bid Security: (a) The Bidder shall furnish as part of its Bid a Bid Security to the Purchaser in the amount of 3 % of the Offer

Value. (b) The Bid Security is to protect the Purchaser against the risk of the Bidder’s conduct which would warrant the

security’s forfeiture, pursuant to Clause 13(g) below. (c) The Bid Security shall be denominated in the currency of the Purchase Order or in a freely convertible currency

and shall be in one of the following forms:

i. bank guarantee or irrevocable letter of credit, issued by a reputable bank located in the purchaser’s country or abroad, and in the form provided in these Solicitation Documents, or,

ii. cashier’s cheque, or certified cheque.

(d) Any Bid not secured in accordance with Clauses 13 a) and 13 c) above will be rejected by the Purchaser as non-responsive pursuant to clause 20 of Instructions to Bidders.

(e) Unsuccessful Bidder Bid Security will be discharged or returned as promptly as possible but not later than thirty

(30) days after the expiration of the period of Bid Validity prescribed by the Purchaser pursuant to clause 12 of instructions to Bidders.

Page 4: ITB Constructii Noi Rev1

4

(f) The successful Bidder’s Bid Security will be discharged or returned upon the Bidder signing the Purchase Order, pursuant to clause 26 of Instructions to Bidders, and furnishing the Performance Security, pursuant to clause 27 of Instructions to Bidders.

(g) The Bid Security may be forfeited: 1) If a Bidder withdraws its offer during the period of the Bid Validity specified by the Bidder on the Bid

Submission Form, or,

2) In the case of a successful Bidder, if the Bidder fails: i. to sign the Purchase Order in accordance with Clause 26 of Instructions to Bidders, or, ii. to furnish Performance Security in accordance with Clause 27 of Instructions to Bidders.

D. Submission of Bids

14. Format and Signing of Bid: The Bidder shall prepare two copies of the Bid, clearly marking each “Original Bid” and “Copy of Bid” as appropriate. In the event of any discrepancy between them, the original shall govern. The two copies of the Bid shall be typed or written in indelible ink and shall be signed by the Bidder or a person

or persons duly authorized to bind the Bidder to the contract. A Bid shall contain no interlineations, erasures, or overwriting except, as necessary to correct errors made by the Bidder, in which case such corrections shall be initialed by the person or persons signing the bid.

15. Sealing and Marking of Bids:

15.1 The Bidder shall seal the original and each copy of the Bid in separate envelopes, duly marking the envelopes as “ORIGINAL” and “COPY”. The envelopes shall then be sealed in an outer envelope.

15.2 The inner and outer envelopes shall:

(a) be addressed to the Purchaser at the address given in section I of these Solicitation Documents; and

(b) make reference to the “subject” indicated in section I of these Solicitation Documents, and a statement: “DO NOT OPEN BEFORE…….”, to be completed with the time and the date specified in section I of these Solicitation Documents for Bid Opening pursuant to clause 16 of Instructions to Bidders.

15.3 The inner and outer envelopes shall also indicate the name and address of the Bidder to enable the Bid to be returned unopened in case it is declared “late”.

15.4 If the outer envelope is not sealed and marked as required by clause 15.2 of Instructions to Bidders, the Purchaser will assume no responsibility for the Bid’s misplacement or premature opening.

16. Deadline for Submission of Bids/Late Bids:

16.1 Bids must be delivered to the office on or before the date and time specified in section I of these Solicitation Documents.

16.2 The Purchaser may, at its discretion, extend this deadline for the submission of the bids by amending the Bidding Documents in accordance with clause 6 of Instructions to Bidders, in which case all rights and

obligations of the Purchaser and Bidders previously subject to the deadline will thereafter be subject to the deadline as extended. 16 3 Any Bid received by the Purchaser after the Deadline for Submission of Bids will be rejected and

returned unopened to the Bidder. 17. Modification and Withdrawal of Bids: The Bidder may withdraw its Bid after submission, provided that

written notice of the withdrawal is received by the procuring UN entity prior to the deadline for submission. No Bid may be modified after passing of the Deadline for Submission of Bids. No Bid may be withdrawn in the interval between the Deadline for Submission of Bids and the expiration of the Period of Bid Validity.

E. Opening and Evaluation of Bids

18. Opening of Bids:

Page 5: ITB Constructii Noi Rev1

5

18.1 The Purchaser will open all Bids in the presence of Bidders’ Representatives who choose to attend, at the time, on the date, and at the place specified in section I of this Solicitation Document. The Bidders’ Representatives who are present shall sign a register evidencing their attendance.

18.2 The bidders’ names, Bid Modifications or withdrawals, bid Prices, discounts, and the presence or absence of requisite Bid Security and such other details as the purchaser, at its discretion, may consider appropriate, will

be announced at the opening. No Bid shall be rejected at Bid Opening, except for Late Bids, which shall be returned unopened to the Bidder pursuant to clause 20 of Instructions to Bidders.

18.3 Bids (and modifications sent pursuant to clause 17 of Instructions to Bidders) that are not opened and read out at Bid Opening shall not be considered further for evaluation, irrespective of the circumstances. Withdrawn Bids will be returned unopened to the Bidders.

18.4 The Purchaser will prepare minutes of the Bid Opening.

19. Clarification of Bids: To assist in the examination, evaluation and comparison of Bids the procuring UN entity may at its discretion ask the Bidder for clarification of its Bid. The request for clarification and the response shall be in writing and no change in price or substance of the Bid shall be sought, offered or permitted.

20. Preliminary Examination:

20.1 Prior to the detailed evaluation, the Purchaser will determine the substantial responsiveness of each Bid to the Invitation to Bid (ITB). A substantially responsive Bid is one which conforms to all the terms and conditions of the ITB without material deviations.

20.2 The Purchaser will examine the bids to determine whether they are complete, whether any computational errors have been made, whether the documents have been properly signed, and whether the bids are generally in

order. 20.3 Arithmetical errors will be rectified on the following basis: If there is a discrepancy between the unit price

and the total price that is obtained by multiplying the unit price and quantity, the unit price shall prevail and the total price shall be corrected. If the Bidder does not accept the correction of errors, its Bid will be rejected. If there is a discrepancy between words and figures the amount in words will prevail.

20.4 A Bid determined as not substantially responsive will be rejected by the Purchaser and may not subsequently be made responsive by the Bidder by correction of the non-conformity.

21. Conversion to Single Currency: To facilitate evaluation and comparison, the Purchaser will convert all Bid

Prices expressed in the amounts in various currencies in which the Bid Prices are payable to US dollars at the

official UN exchange rate on the last day for Submission of Bids. 22. Evaluation of Bids: Determination of compliance with the Solicitation Documents is based on the content of

the Bid itself without recourse to extrinsic evidence.

Evaluation Criteria

1.1 Compliance with requirements of technical assignment.

1.2 Price of the construction works.

1.3 Scheduled time for execution of construction works.

1.4 Compliance with Special and General Conditions specified by these Solicitation Documents.

1.5 Experience and quality of executed similar works confirmed by customers’ references.

F. Award of Contract

23. Award Criteria: The procuring UN entity will Issue the Purchase Order to the lowest priced technically

qualified Bidder. The Purchaser reserves the right to accept or reject any Bid, to annul the solicitation process

and reject all Bids at any time prior to award of purchase order, without thereby incurring any liability to the affected Bidder(s) or any obligation to provide information on the grounds for the purchaser’s action.

Page 6: ITB Constructii Noi Rev1

6

24. Purchaser’s Right to Vary Requirements at Time of Award: The Purchaser reserves the right at the time of

making the award of contract to increase or decrease by up to 10 % the quantity of civil works specified in the

Schedule of Requirements without any change in unit price or other terms and conditions. 25. Notification of Award: Prior to the expiration of the period of Bid Validity, the Purchaser will send the

successful Bidder the Purchase Order. The Purchase Order may only be accepted by the Supplier’s signing and returning an acknowledgement copy of it or by timely delivery of the civil works in accordance with the terms of this purchase order, as herein specified. Acceptance of this Purchase Order shall effect a contract between the

parties under which the rights and obligations of the parties shall be governed solely by the terms and conditions of this purchase order.

26. Signing of the Purchase Order : Within 30 days of receipt of the Purchase Order the successful Bidder shall sign, date and return it to the purchaser.

27. Performance Security: The successful Bidder shall provide the Performance Security on the Performance Security Form provided for in these Solicitation Documents, within 30 days of receipt of the Purchase Order from the purchaser.

Failure of the successful Bidder to comply with the requirement of clause 26 or clause 27 of Instructions to Bidders shall constitute sufficient grounds for the annulment of the award and forfeiture of the Bid Security, in

which event the Purchaser may make the award to the next lowest evaluated Bidder or call for new Bids.

Page 7: ITB Constructii Noi Rev1

7

Annex II

BID DATA SHEET

The following specific data for the civil works to be procured shall complement, supplement, or amend the provisions in the Instruction to Bidders. Whenever there is a conflict, the provisions herein shall prevail over those in the Instructions to Bidders.

Relevant clause(s) of Instruction to Bidders

Specific data complementing, supplementing, or amending instructions to Bidders

Language of the Bid

X English

Bid Price

As per cost estimate. The prices quoted shall include all labor, materials,

equipment, supplies, overhead, and other costs to fully furnish and install the works.The price quoted shall be as per Bill of Quantities attached as Annex VI Technical Specifications

Documents Establishing Bidder’s Eligibility &

Qualifications

X Required. � Not required. - Copies of original documents defining the constitution or legal status, place of registration and principal place of business of the Bidder

- that the Bidder is reliable and capable to perform the contract: - annual balance sheet of the company (including income statement)

certified by the fiscal authorities;

- the documentary evidence of the Bidder’s economic and financial capacity (bank statement of the Bidder’s economic/financial reliability, auditing report, other relevant documentary evidence of economic and financial

reliability); - company profile (company’s profile and a list of the most important

contracts performed in the past 3 years )

Bid Validity Period.

X 120 days � If different, please specify………………………

Bid Security

X Required. � Not required. Bid Security in the amount of 3 % of the Offer Value, as per clause 13 of Instructions to Bidders

Preliminary Examination –

completeness of bid.

X Partial bids permitted. � Partial bids not permitted. “Partial bid” means bid for any full LOT out the 5 indicated lots.

Purchaser’s Right to Vary

Requirements at Time of Award

X 15 percent, increase or

decrease.

� Condition waived

� Condition applies but change limit to ………

percent.

Page 8: ITB Constructii Noi Rev1

8

Annex III

General Terms and Conditions

1. ACCEPTANCE OF THE PURCHASE ORDER

This Purchase Order may only be accepted by the Supplier's signing and returning an acknowledgement copy of it or by timely delivery of the civil works in accordance with the terms of this Purchase Order, as herein specified. Acceptance of this Purchase Order shall effect a contract between the Parties under which the rights

and obligations of the Parties shall be governed solely by the terms and conditions of this Purchase Order, including these General Conditions. No additional or inconsistent provisions proposed by the Supplier shall bind UNDP unless agreed to in writing by a duly authorized official of UNDP.

2. PAYMENT

2.1.1 UNDP shall, on fulfilment of the Delivery Terms, unless otherwise provided in this Purchase

Order, make payment within 30 days of receipt of the Supplier's invoice for the civil works and copies of the shipping documents specified in this Purchase Order.

2.1.2 Payment against the invoice referred to above will reflect any discount shown under the payment

terms of this Purchase Order, provided payment is made within the period required by such payment terms.

2.1.3 Unless authorized by UNDP, the Supplier shall submit one invoice in respect of this Purchase

Order, and such invoice must indicate the Purchase Order's identification number. 2.1.4 The prices shown in this Purchase Order may not be increased except by express written

agreement of UNDP.

3. TAX EXEMPTION

3.1 Section 7 of the Convention on the Privileges and Immunities of the United Nations provides, inter alia, that the United Nations, including its subsidiary organs, is exempt from all direct taxes, except charges for utilities services, and is exempt from customs duties and charges of a similar nature in respect

of articles imported or exported for its official use. In the event any governmental authority refuses to recognize UNDP's exemption from such taxes, duties or charges, the Supplier shall immediately consult with UNDP to determine a mutually acceptable procedure.

3 .2 Accordingly, the Supplier authorizes UNDP to deduct from the Supplier's invoice any amount representing such taxes, duties or charges, unless the Supplier has consulted with UNDP before the payment

thereof and UNDP has, in each instance, specifically authorized the Supplier to pay such taxes, duties or charges under protest. In that event, the Supplier shall provide UNDP with written evidence that payment of such taxes, duties or charges has been made and appropriately authorized.

4. RISK OF LOSS

Risk of loss, damage to or destruction of the civil works shall be governed in accordance with DDU Incoterms 2000, unless otherwise agreed upon by the Parties on the front side of this Purchase Order.

5. EXPORT LICENCES Notwithstanding any INCOTERM 2000 used in this Purchase Order, the Supplier shall obtain any export

licences required for the civil works. 6. FITNESS OF CIVIL WORKS/PACKAGING

The Supplier warrants that the civil works, including packaging, conform to the specifications for the civil

works ordered under this Purchase Order and are fit for the purposes for which such civil works are ordinarily

used and for purposes expressly made known to the Supplier by UNDP, and are free from defects in workmanship and materials. The Supplier also warrants that the civil works are contained or packaged adequately to protect the civil works.

Page 9: ITB Constructii Noi Rev1

9

7. INSPECTION

1 . UNDP shall have a reasonable time after delivery of the civil works to inspect them and to reject and refuse acceptance of civil works not conforming to this Purchase Order; payment for civil works pursuant to this Purchase Order shall not be deemed an acceptance of the civil works.

2. Inspection prior to shipment does not relieve the Supplier from any of its contractual obligations.

8. INTELLECTUAL PROPERTY INFRINGEMENT The Supplier warrants that the use or supply by UNDP of the civil works sold under this Purchase Order does

not infringe any patent, design, trade-name or trade-mark. In addition, the Supplier shall, pursuant to this warranty, indemnify, defend and hold UNDP and the United Nations harmless from any actions or claims brought against UNDP or the United Nations pertaining to the alleged infringement of a patent, design, trade-

name or trade-mark arising in connection with the civil works sold under this Purchase Order. 9. RIGHTS OF UNDP

In case of failure by the Supplier to fulfil its obligations under the terms and conditions of this Purchase Order,

including but not limited to failure to obtain necessary export licences, or to make delivery of all or part of the

civil works by the agreed delivery date or dates, UNDP may, after giving the Supplier reasonable notice to perform and without prejudice to any other rights or remedies, exercise one or more of the following rights:

a) Procure all or part of the civil works from other sources, in which event UNDP may hold the Supplier responsible for any excess cost occasioned thereby.

b) Refuse to accept delivery of all or part of the civil works.

c) Cancel this Purchase Order without any liability for termination charges or any other liability of any kind of UNDP.

10. LATE DELIVERY Without limiting any other rights or obligations of the parties hereunder, if the Supplier will be unable to deliver

the civil works by the delivery date(s) stipulated in this Purchase Order, the Supplier shall (i) immediately consult with UNDP to determine the most expeditious means for delivering the civil works and (ii) use an expedited means of delivery, at the Supplier's cost (unless the delay is due to Force Majeure), if reasonably so

requested by UNDP. 11. ASSIGNMENT AND INSOLVENCY

11.1. The Supplier shall not, except after obtaining the written consent of UNDP, assign, transfer, pledge or

make other disposition of this Purchase Order, or any part thereof, or any of the Supplier's rights or

obligations under this Purchase Order. 11.2. Should the Supplier become insolvent or should control of the Supplier change by virtue of insolvency,

UNDP may, without prejudice to any other rights or remedies, immediately terminate this Purchase Order

by giving the Supplier written notice of termination. 12. USE OF UNDP OR UNITED NATIONS NAME OR EMBLEM

The Supplier shall not use the name, emblem or official seal of UNDP or the United Nations for any purpose. 13. PROHIBITION ON ADVERTISING

The Supplier shall not advertise or otherwise make public that it is furnishing civil works or services to UNDP

without specific permission of UNDP in each instance.

14. CHILD LABOUR

The Supplier represents and warrants that neither it nor any of its affiliates is engaged in any practice inconsistent with the rights set forth in the Convention on the Rights of the Child, including Article 32 thereof, which, inter alia, requires that a child shall be protected from performing any work that is likely to be hazardous

Page 10: ITB Constructii Noi Rev1

10

or to interfere with the child's education, or to be harmful to the child's health or physical, mental, spiritual, moral or social development.

Any breach of this representation and warranty shall entitle UNDP to terminate this Purchase Order immediately upon notice to the Supplier, without any liability for termination charges or any other liability of any kind of UNDP.

15. MINES

The Supplier represents and warrants that neither it nor any of its affiliates is actively and directly engaged in patent activities, development, assembly, production, trade or manufacture of mines or in such activities in respect of components primarily utilized in the manufacture of Mines. The term "Mines" means those devices

defined in Article 2, Paragraphs 1, 4 and 5 of Protocol II annexed to the Convention on Prohibitions and Restrictions on the Use of Certain Conventional Weapons Which May Be Deemed to Be Excessively Injurious or to Have Indiscriminate Effects of 1980.

Any breach of this representation and warranty shall entitle UNDP to terminate this Purchase Order

immediately upon notice to the Supplier, without any liability for termination charges or any other liability of

any kind of UNDP. 16. SETTLEMENT OF DISPUTES

16.1 Amicable Settlement

The Parties shall use their best efforts to settle amicably any dispute, controversy or claim arising out of, or relating to this Purchase Order or the breach, termination or invalidity thereof. Where the Parties wish to seek such an amicable settlement through conciliation, the conciliation shall take place in accordance with the

UNCITRAL Conciliation Rules then obtaining, or according to such other procedure as may be agreed between the Parties.

16.2 Arbitration Unless, any such dispute, controversy or claim between the Parties arising out of or relating to this Purchase

Order or the breach, termination or invalidity thereof is settled amicably under the preceding paragraph of this Section within sixty (60) days after receipt by one Party of the other Party's request for such amicable settlement, such dispute, controversy or claim shall be referred by either Party to arbitration in accordance with

the UNCITRAL Arbitration Rules then obtaining, including its provisions on applicable law. The arbitral tribunal shall have no authority to award punitive damages. The Parties shall be bound by any arbitration award rendered as a result of such arbitration as the final adjudication of any such controversy, claim or dispute.

17. PRIVILEGES AND IMMUNITIES

Nothing in or related to these General Terms and Conditions or this Purchase Order shall be deemed a waiver of any of the privileges and immunities of the United Nations, including its subsidiary organs.

Page 11: ITB Constructii Noi Rev1

11

Annex IV

Special Conditions

The following Special Conditions shall complement, supplement, or amend the General Conditions. Whenever there

is a conflict, the provisions herein shall prevail over those in the General Conditions.

Warranty/Guarantee

X Applies 1 Does not apply If, within 12 months after the civil works have been put

into service, any defects are discovered or arise in the normal course of usage, the Supplier shall remedy the defect either by replacement or by repair. The Contractor

shall ensure the guarantee period for the performed works

Liquidated damages

X Applies 1 Does not apply If the Supplier fails to supply the specified civil works within the time period(s) stipulated by the purchase order, the Purchaser shall, without prejudice to its other

remedies under the contract, deduct from the Purchase Order price, as liquidated damages, a sum equivalent to 0.5 percent of the delivered price of the delayed civil works for each week of delay until actual delivery, up to

a maximum deduction of 10 percent of the delayed civil works Purchase Order price. Once the maximum is reached, the Purchaser may consider termination of the

Purchase Order

Performance security

X Applies 1 Does not apply The Performance Security shall amount to 5 % of the

contract price; this percentage shall be withheld from the value of each Statement of Works and shall be deposited in the Contractor’s security account.

Fifty percent (50%) of the security shall be returned upon works final reception and completion, and fifty percent (50%) shall be returned at the end of the 12-month Defects

Liability Period calculated from the date of the completion of the works.

Annex V.

Page 12: ITB Constructii Noi Rev1

12

SCHEDULE OF REQUIREMENTS

Lot No.

Unit Description of works (specific requirements, general requirements are as per Annex VI)

1

Family House

Lacatus Ghiolanca Composed of 3 rooms, sanitary room, kitchen and other annex required spaces (built area 70-80sq.m/building), built only with one level- ground floor, two/four slopes roof; all installations required by the normal standard of housing in the rural area- electrical

installations, water pipes from an individual well , ecological tank for sanitation purposes, heating system with stoves.

2

Family House

Moldovan Adrian

Composed of 3 rooms, sanitary room, kitchen and other annex required spaces (built area

70-80sq.m/building), built only with one level- ground floor, two/four slopes roof; all installations required by the normal standard of housing in the rural area- electrical installations, water pipes from an individual well , ecological tank for sanitation purposes,

heating system with stoves. 3 Family House

Zoltan Florina Composed of 3 rooms, sanitary room, kitchen and other annex required spaces (built area 70-80sq.m/building), built only with one level- ground floor, two/four slopes roof; all

installations required by the normal standard of housing in the rural area- electrical installations, water pipes from an individual well , ecological tank for sanitation purposes, heating system with stoves.

4 Health unit Built only with one level- ground floor; all installations required by the normal standard; ecological tank for sanitation purposes; heating system –gas power central unit

5 Industrial Building For two different activities and office spaces for meetings or coordination of activities (350

sq.m- 200 sq.m for construction activities, 100sq.m for textile field activities, 50sq.m offices)

The schedule of works can be adjusted as agreed by the Parties when signing the Contract.

Page 13: ITB Constructii Noi Rev1

13

Annex VI. BILL OF QUANTITIES & SPECIFICATION CRITERIA

LOT NO.1 Family House Lacatus Ghiolanca

QUANTITY LIST WITH TECHNOLOGICAL EQUIPMENT, INCLUDING UTILITIES OF THE ESTIMATE-OFFER FOR PROCUREMENT

Item Name M.U. Quantity Unitary Price

-lei/M.U.-

Amount (VAT

exclusive)

-Thousand lei-

(col.3 x 4)

Supplier

(name,

address,telep

hone,

facsimile)

0 1 2 3 4 5 6

1 Water meter Qn=1.5 cubic

meters/h

pcs 1

2 Ecological tank for waste

water, capacity 10 cubic

meters

pcs 1

3 Electric Boiler 10l pcs 1

Thousand lei: TOTAL

USD*):

*) Exchange rate =…………………. Lei/USD, of …………………….

Page 14: ITB Constructii Noi Rev1

14

TECHNICAL SHEET No. 1

EQUIPMENT: WATER METER Qn=1.5 cubic meters/h

Item Technical specifications imposed by the Technical Specifications

Comparison between the technical proposal and

the specifications imposed by the

Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters: -Type: multi-jet, and dry dial -Nominal output: 1.5 mc/h

-Nominal diameter: 20 mm - Connection sizing: 3/4˝ -Connection type: coupling -Design pressure Pn 6 bars

2. Performance specs and conditions related to safety in exploitation: - To be granted a Technical Agreement or an

homologation document; - The Technical Book shall be presented in

Romanian wording.

3. Conditions related to compliance with relevant standards: -Accuracy category: B

4. Guarantee and post-guarantee conditions: -3 years guarantee

- 3 days for solving out issues occurred during the

guarantee period

5. Other condition of technical character:

Page 15: ITB Constructii Noi Rev1

15

TECHNICAL SHEET No. 2

EQUIPMENT: ECOLOGICAL TANK FOR WASTE WATER

Item Technical specifications imposed by the Technical

Specifications

Comparison between the

technical proposal and the specifications imposed by

the Technical

Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters: -Material: polyester

-Net volume: 10 cubic meters -Diameter: 1.8 linear meters -Length: 4.15 linear meters -Installing: buried

2. Performance specs and conditions related to safety in exploitation:

• To be granted a Technical Agreement or an homologation document;

3. Conditions related to compliance with relevant standards: -SR EN 12566-1

4. Guarantee and post-guarantee conditions: - 3 years guarantee.

5. Other condition of technical character:

Minimum life cycle: 30 years

Page 16: ITB Constructii Noi Rev1

16

TECHNICAL SHEET No . 3

EQUIPMENT: ELECTRIC BOILER

Item Technical specifications imposed by the Technical

Specifications Comparison between the technical proposal and

the specifications imposed by the

Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• Hot water 800C

• Capacity 10l

• Sizes: 360x254x360

• Maximum pressure: Pn 10 bar

• Wasteful resistance power: 1.2 kW

• Power supply: 220 V

2. Performance specs and conditions related to safety in exploitation:

-Inside the boiler’s surface is covered by a special enamel layer; -It is fitted out by a programmable thermostat,

magnesium anode, insulation, relief pressure valve, “on-off” switch.

3. Performance specs and conditions related to safety in exploitation:

• To be granted a Technical Agreement or an homologation document;

• The Technical Book shall be presented in Romanian wording.

4. Guarantee and post-guarantee conditions:

• 3 days for solving out issues occurred during

the guarantee period;

• 10 days for providing spare parts in the post-guarantee period.

5. Other condition of technical character

Page 17: ITB Constructii Noi Rev1

17

Bill of quantities

Estimate - Tender: ELECTRIC INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 EA02A1 [ 2] M 170.000

PROTECTION INSULATION TUBE,IPEY SEALED

RECESSED WITH D=16/13,4MM

002 EA02A3 [ 2] M 8.000

PROTECTION INSULATION TUBE,IPEY SEALED

RECESSED WITH D=25,8/21,8 MM

003 EA12A1 M 20.000

METALLIC,FLEXIBILE,PROTECTION,UNTIGHT

TUBE, WITH 2 ROWS OF COILS IN

QUADRILATERAL-SHAPE(SPD) 13,5-23 MM

003 7356501 M 20.500

METALIC TUBE FLEX.PROT.NONTIGHT TYPE SPD

-ROMAN D=13,5 MM

004 EB02A1 M 280.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION < 4 MMP

004 4826880 M 288.400

CONDUCTOR FY 1X 1,5 S 6865

005 EB02A1 M 340.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION < 4 MMP

005 4826892 M 350.200

CONDUCTOR FY 1X 2,5 S 6865

006 EB02B1 M 30.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION 6- 10 MMP

006 4826919 M 30.900

CONDUCTOR FY 1X 6 S 6865

007 ED01A1 BUC. 4.000

MANUAL SWITCH BURIED UNIPOLAR NORMAL OR

WATERPROOF CONSTRUCTION *

Page 18: ITB Constructii Noi Rev1

18

007 5500720 BUC. 4.040

CUMPANA SWITCH ST.250V 10A

008 ED03A1 BUC. 5.000

UNIPOLAR SWITCH BURIED,WOODEN NAILS,IN

SERIES,NORM.CONSTR.OF BACHELITA OR

WATERPROOF CONSTR.

008 5520366 BUC. 5.050

CUMPANA SHIFTER ST.250V 10A

009 ED08A1 BUC. 1.000

PLUG BURIED ASSEM.NORMAL CONSTR.

WATERPROOF OR NORMAL PROTECTION CONTACT

009 5536156 BUC. 1.010

BIPOLAR PLUG PROT.PANEL 250/10A RECESSED

010 ED08B1 [ 1] BUC. 9.000

DOUBLE TWIN PLUG WITH PROTECTION

CONTACT RECESSED MOUNTED

010 5535994 BUC. 9.090

DOUBLE BIPOL.PLUG,PROT.CONTACT 250/10A

RECESSED

011 ED01D1 BUC. 1.000

MANUAL SWITCH WOODEN NAILS IN UNIPOLAR

NORMAL CONSTR. MADE OF BACHELITE OR

TIGHT CONSTR.

011 5500677 BUC. 1.010

VISIBLY SET MANUAL SHIFTER 250V 10A

012 ED10A1 [ 1] BUC. 1.000

BELL BUTTON 10A 250V

013 EE04A1 BUC. 2.000

SIMPLE LUMINAIRE (LAMP HOLDER) REGULAR,

WITH NAIL AND RING

014 EE05A1 BUC. 3.000

SIMPLE APPLY ,OBL./RIGHT.GLOB ST.OPAL.

MONT.CEILING./WALLS ON WOOD DOWEL

014 5104071 BUC. 3.036

WALL BRACKET E27,OBLIQUE,60W,BOWL

015 EE08A1 [ 1] BUC. 1.000

CHANDELIER INCANDENSCENCE BULBS WITH 1

ARM

Page 19: ITB Constructii Noi Rev1

19

015 5105311 BUC. 1.003

INCANDENSCENCE BULBS 1 ARM CHANDELIER

016 EE08A1 BUC. 2.000

CHANDELIER INCANDENSCENCE BULBS WITH 2

ARMS

016 5105312 BUC. 2.006

INCANDENSCENCE BULBS 1 ARM CHANDELIER

017 EE08B1 BUC. 1.000

CHANDELIER INCANDENSCENCE BULBS WITH 3

ARMS

017 5105300 BUC. 1.003

INCANDENSCENCE BULBS 3 ARMS CHANDELIER

018 EE12B1 BUC. 1.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

018 5103611 BUC. 1.003

FLUOR.LUMINAIRE FIA 11-2X36 W EQUIPPED,

APPARENT ASSEM.

019 EE12B1 BUC. 2.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

019 5103823 BUC. 2.006

FLUORESCENT LIGHT FIXTURES AB 02-1X18 W

VISIBLY SET

020 EE14A1 BUC. 2.000

ASSEM.LAMP INSIDE.CONSTR.OR ON EXTER.

ELEMENTS INCANDESCENCE UP TO 1000 W.

020 5101029 BUC. 2.100

INCANDESCENTE LAMP CLEAR E27 TIP S 220V

25W S6115

021 EE14A1 BUC. 11.000

ASSEM.LAMP INSIDE.CONSTR.OR ON EXTER.

ELEMENTS INCANDESCENCE UP TO 1000 W.

021 5101251 BUC. 11.550

INCANDES LAMP DOUBLE SPIR.CLEAR E27 AM

220V 60W CS

022 EF05D1 [ 1] BUC. 1.000

PANEL WITH PROTECTION CUT-OUT AND

Page 20: ITB Constructii Noi Rev1

20

DIFER.FAULT CURRENT DEVICE +

BELL AND SWITCH

022 7305451 BUC. 1.000

PANEL WITH 4 PROTECTION CUT-OUTS

PHASE-NULL(1x 6A+2x16A+1x16A WITH DIFFER.

PROT.DIVICE Id=30mA) BELL AND SWITCH

023 EF09A1 BUC. 6.000

COUPLING COPPER PIPE AT DEVICES BORNS ,

MOTORS,ELECTR.COUNTER COND.HAVING SECT.

<10SQMM,EXCLUSIVELY

024 EG08B1 M 10.000

COND.EARTH CONNECTION LIGHTING ROD

UNDERGROUND EARTH CONN.GALVANIZED STEEL

STRIP 40X4MM IN HARD SOIL *

025 W1R06A1 M 3.000

ELECTRODE OF STEEL PIPE OF TWO AND

A HALF INCHES FOR EARTH GROUNDING

IN NORMAL GROUND

026 W1P08A BUC. 1.000

EARTH CONN.TESTING FOR BUILDING WIRING

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT Bill of quantities

Estimate - Tender: VARIABLE ARCHITECTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

Page 21: ITB Constructii Noi Rev1

21

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 20.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1304 ORA 159.000

SELF-LIFTING METALIC SCAFFOLD 2 CASTLES

6MARCH 75KG/M H-31M L=12M 3SHIFTS

003 CI02A1 [10] MP. 20.000

NATURAL LOCAL STONE PLATING

INCL. MESH

003 2202200 SQ.M. 20.400

BANPOTOC 1 QUALITY G=2CM S LIMESTONE SLAB

6035

004 CG06C1 MP. 6.500

MOSAIC FLOOR CAST ON SITE OF 1,5CM

THICKNESS SIMPLE WITHOUT CRIMP ON

SURFACE <5MP WITH MARBLE MOSAIC

005 CH01B1 M 13.500

PLATED SIMPLE CONCRETE TREADS WITH

PREFAB.TREADS AND RISERS WITH MARBLE

MOSAIC

005 2802892 M 13.905

MANUFACT.MARBLE STAIR CASE NAT.COLOUR

005 2802957 M 13.905

MARBLE MOSAIC RISER NATURAL COLOUR

006 CE14A1 M 5.000

GALVANIZED PLATE RAIN PIPE OF 0,5MM MADE

ON SITE SEMIROUND WITH D= 15,4CM

007 CF06A1 MP. 20.000

EXTER.REGULAR PLASTER,FLOATED FOR

DRYWALLS OR INTERIORS IN GARRET,OF 2 CM

007 2101203 M.C. 0.440

PLASTER MORTAR M25T

008 CG07B1 M 8.000

MOSAIC PLINTHS OR GORGES CAST ON SITE

SITE-HORISONTAL PLINTHS H=10CM AT MARBLE

MOSAIC WALLS

009 CH04A1 M 6.000

CURRENT WOODEN HANDRAIL

009 2948144 M 6.300

OAK WOOD HANDRAIL PRECAST SECT. 40X80 MM

Page 22: ITB Constructii Noi Rev1

22

010 CL20B1 KG 52.000

APPARENT METALLIC MANUFACT. ASSEMBLYING:

GRATES BANISTERS,TRAP DOOR,CHECKS, GRILL

010 6306274 KG 52.000

SIMPL.DECORATIVE LATTICE WORK FOR

STAIRCASES,PROFILED STEEL BALCONY

011 CN11B1 MP. 5.500

DYE WORKS AT BANISTERS,GRID,METALLIC

PARAPET WITH ALCHIDICAL ENAMEL

011 6108347 KG 0.385

REDISH BROWN ENAMEL UIC E.735-8 NTR 1703

-80

011 6100943 KG 0.440

ALCHID RED OXID PLASTER ROUGH G 735-3

012 CN09G1 MP. 18.000

PAINTINGS ON WOOD CARPENTERY ,DONE WITH

2 LAYERS ALCHIDIC LAQUER COLORLESS,AT

DOORS,WINDOWS ,SHUTTER.RUL.

013 CO02B1 MP. 30.000

CONCRETE PLATES WALK SIDE FOR SAND

PAVEMENTS,JOINTS FILLED WITH MASTIC

013 2800488 MP. 30.600

CONCRETE MANUFACT. FLAGSTONE 70X70X8CM

014 IZF10F1 [ 3] MP. 20.000

50MM EXTRUDED POLYSTYRENE LAYER TO

EXTERIOR WALLS GLUED BY BITUMINOUS CEMENT

015 RPCO56A1 [ 3] M 18.000

OAK WOOD BANISTERS AT PLATFORMS WITH

SIZES OF 30 X 125MM AT 3 ROWS

016 CH01D1 M 9.000

SIMPLE CONCRETE TREADS TITIVATED OR

ROLLED WITH CEMENT MORTAR M100-T

CAREFULLY FINISHED

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION, NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

Page 23: ITB Constructii Noi Rev1

23

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

BILL OF QUANTITIES

Estimate - Tender: CONSTANT ARCHITECTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 132.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1302 ORA 390.000

METAL AUTO-LIFTING SCAFFOLD 3 CAST. 3.

5TF H=31M L=29M 3 SHIFTS

003 MDTC5517 BUC. 2.000

EQUIPMENT TRANSPORT KM 90100043

SELF-LIFTING METALLIC SCAFFOLDING WITH 2

CASTLES

004 CD04E1 M.C. 0.100

MASONRY FROM PRESSED BRICK 240X115X63MM

AT BATHROOM TUB CLOSING, CAL.1

005 CD04C1 M.C. 2.000

RESSED BRICK MASONRY 240X115X63MM AT

INSULATED CHIMNEY STACKS IN GARRET,QAL.1

005 2101171 M.C. 0.340

MASONRY MORTAR M 50 S 1030

006 CD05A1 M.C. 32.000

BRICK MASONRY TYPE GVP AT BUILDINGS H

<35M, SHAPE 240X115X 88MM,Q.A

006 2101169 M.C. 6.720

MASONRY MORTAR M 25 S 1030

007 CD04H1 M.C. 6.000

MASONRY FROM PRESSED BRICK 240X115X63M M

AT BUILDING.H<35M, 12,5CM THICKNESS, Q.

A,WITH VOIDS <50 %

007 2101169 M.C. 1.080

MASONRY MORTAR M 25 S 1030

008 CE15B2 [ 1] M 8.000

ALUMINIM WINDOW BOARDS

009 CF01K1 MP. 246.000

FLOATED INT.PLASTERS,AT COLUMNS,WALLS

Page 24: ITB Constructii Noi Rev1

24

WITH SPRINKLER AND PLASTER ROUGH CAST

MECHANICALLY PERFORMED,OF 2CM

009 2101202 M.C. 4.428

PLASTER MORTAR M10T

010 CF06K1 MP. 123.000

FLOATED EXTERNAL PLASTER ON BRICK AND

BLOCKS WALLS WITH CRUND.MECH.LAYER VIZ.

MANUALLY MORTAR M25-T THICK.2,5 CM

010 2101204 M.C. 2.829

MORTAR M50T

011 CF06C1 [ 6] MP. 123.000

OUTER DECORATIVE PLASTER OR

SIMILAR

012 CF10C1 MP. 316.000

PLASTER POLISHING APPLIED ON FLOATED

INTERIOR PLASTERS

013 CG01E1 [ 5] MP. 70.000

CEMENT SLAB FINISH FOR FLOORS

014 RPCK07D1 MP. 52.000

RESINOUS WOODEN FLOORING OF 24MM

THICK. NAILED ON OAK LATHS OF

50X80MM

015 CG06C1 MP. 9.500

MOSAIC FLOOR CAST ON SITE OF 1,5CM

THICKNESS SIMPLE WITHOUT CRIMP ON

SURFACE <5MP WITH MARBLE MOSAIC

016 CG06D1 MP. 8.500

MOSAIC FLOOR POURED ON SITE OF 1,5CM

THICK.SIMPLE WITHOUT CRIMP ON SURF.>5MP

WITH MARBLE MOSAIC

017 CG07B1 M 37.500

MOSAIC PLINTHS OR GORGES CAST ON SITE

SITE-HORISONTAL PLINTHS H=10CM AT MARBLE

MOSAIC WALLS

018 CG28B1 MP. 70.000

5MM DIFFERENCE SUPP.LAYER FOR CEMENT

MORTAR FLOOR

018 2101200 M.C. 0.350

PLASTER MORTAR M 100 (LIME PASTE ) S

1030

019 CG26A1 MP. 18.000

POLISHING,INCLUDING MARBLE OR MARBLE

MOSAIC GRAVEL WAXING FLOORS

020 CG26B1 M 37.500

POLISHING INCLUDING PLINTH AND GORGES

WAXING

Page 25: ITB Constructii Noi Rev1

25

021 CN04D1 MP. 44.000

DYE WORKS FOR INTERIOR AND EXTERIOR

MANUALLY EXEC.WITH OIL PAINTS

IN 2 LAYERS ON SMOOTH PLASTERS

021 6103309 KG 10.648

CREAM PAINT (FP) V.401-1 NTR 90-80

022 CK11G1 [ 3] MP. 11.000

PVC DOUBLED-GLASSED WINDOWS

023 CK14A1 [ 2] MP. 5.300

WHITE COLOR PVC DOORS WITH THERMO

INSULATING GLASS 4+ 16+4MM

024 CK03A1 MP. 9.800

INTERIOR SIMPLE WOOD DOORS ONE LEAF ON

LINING

024 2933300 MP. 9.800

ONE LEAF TIMBER DOOR ON LINING FINISHED

BY MANUFACTURER

025 CK03C1 MP. 3.300

INTERNAL SIMPLE WOOD DOORS IN 2 LEAFS ON

LINING

025 2932150 MP. 3.300

2 LEAFS WOOD DOORS ON LININGS PAINTED AT

PRODUCER

026 CK25C1 BUC. 2.000

CARPENTRY ACCESSORY WORKS APPLIED LOCK

TO A YALE SYSTEM

026 6310380 BUC. 2.000

SAFETY LOCK IN YALLE

SYSTEM WITH DOOR BOLT

027 CK08A1 MP. 0.350

EXTRA DIFFERENCE AT LINING FOR DOORS

WIDER THAN 19,5 CM.

028 CK09A1 [ 1] M 8.000

20CM WIDE PVC WINDOW BOARDS SET TO THE

INTERIOR

029 CM02E1 MP. 4.000

DRAWN WINDOWS SIMPLE MEASURE FREE ON

WOOD CARPENTERY 4-8MM THICK.WITH PUTTY

AND WANG AT VITRI

029 2500327 MP. 4.360

CLEAR DRAWN GLASS Q.3 4MM. PACKED FREE

Page 26: ITB Constructii Noi Rev1

26

SIZES S 853

030 CN06B1 [ 3] MP. 316.000

3 LAYER WHITE COLOR WASHABLE PAINTING FOR

INTERIOR FOR WALLS

031 RPCK72A1 MP. 52.000

PALUX LAKE PARQUET LAQUERING IN THREE

LAYERS

032 IZF10C1 [10] MP. 123.000

THERMINSULATING LAYER FOR WALLS OF

EXPANDED POLYSTYRENE FOR FACADE OF 10CM

THICK.INCLUDING MORTAR ADHESIVE AND

SECURING NAILS

032 2602797 MP. 124.230

PEX C EXPANDED POLYSTYRENE SLAB OF

2000X500X 100MM S7461

033 CO12A1 BUC. 470.000

TERACOTTA ENAMEL STOVES,INCLUDING

METALLIC SEALS

033 2436887 BUC. 484.100

COLORED TILES FOR STOVES OF 240X220 1ST Q.

S1798

033 7323475 BUC. 4.700

METALLIC SET TERRACOTTA STOVE (EG .GRILL)

FROM NES CAST IRON

033 7323580 BUC. 4.700

CAST IRON GRILL MAR ,1 105 X128X8

034 TRA06A TONA 37.500

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. = KM

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

Page 27: ITB Constructii Noi Rev1

27

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: CONSTANT ARCHITECTURE GARRET

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 25.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1302 ORA 170.000

METAL AUTO-LIFTING SCAFFOLD 3 CAST. 3.

5TF H=31M L=29M 3 SHIFTS

003 CD05E1 M.C. 5.000

BRICK MASONRY GVP TYPE FOR

CONSTR.H<35M, FORMAT 365X180X138MM,A Q.

003 2101169 M.C. 0.650

MASONRY MORTAR M 25 S 1030

004 CD04C1 M.C. 1.850

RESSED BRICK MASONRY 240X115X63MM AT

INSULATED CHIMNEY STACKS IN GARRET,QAL.1

004 2101171 M.C. 0.315

MASONRY MORTAR M 50 S 1030

005 CE01A1 MP. 160.000

BURNT CLAY SHAPED TILE COVER

005 2302983 BUC. 2560.000

DRAIN TILE WITH 1 BEAK Q1 390X230X11

S515

006 CE13A1 M 39.000

GALVANIZED PLATE DRAIN OF 0,5MM, MADE ON

SITE SEMIROUND WITH D=15CM

Page 28: ITB Constructii Noi Rev1

28

007 CE14A1 M 21.000

GALVANIZED PLATE RAIN PIPE OF 0,5MM MADE

ON SITE SEMIROUND WITH D= 15,4CM

008 CE15B2 [ 1] M 1.200

ALUMINIM WINDOW BOARDS

009 CE19D1 [ 1] M 55.000

TOOTHING EAVES FROM ONE SIDE

PLANE BOARD AND RABBETED

OF 70CM WIDE

009 2903830 M.C. 0.083

LONG RESIN BOARD SELVEDGED CLASS C THICK

=24MM L=3,00M S 942

010 CF06A1 MP. 6.000

EXTER.REGULAR PLASTER,FLOATED FOR

DRYWALLS OR INTERIORS IN GARRET,OF 2 CM

010 2101203 M.C. 0.132

PLASTER MORTAR M25T

011 CF06C1 [ 6] MP. 25.000

OUTER DECORATIVE PLASTER OR

SIMILAR

012 CF06K1 MP. 25.000

FLOATED EXTERNAL PLASTER ON BRICK AND

BLOCKS WALLS WITH CRUND.MECH.LAYER VIZ.

MANUALLY MORTAR M25-T THICK.2,5 CM

012 2101203 M.C. 0.575

PLASTER MORTAR M25T

013 CK01A1 MP. 0.500

BUILDINGS WOODEN WINDOWS WITH H= 0- 35M

WITH FRAME SURFACE < 1,00MP.

013 2938811 MP. 0.500

EXTERNAL SIMPLE RESIN WINDOWS OAK FRAME

<0,50 SQM

014 VB34C1 BUC. 3.000

PROTECTION CAP FOR CIRCULAR SEWERS WITH

PERIM. OF 701-1600 MM MADE.ON SITE DET.

TYPE 61/0

015 CK09A1 M 1.000

RESINOUS TIMBER LINTELS

015 2947800 M 1.000

RESINOUS WINDOW BOARD OF 30MM WIDE UP

TO 120MM

016 CM02B1 MP. 0.500

DRAWN GLASSES SIMPLE FREE MEASURE ON

WOOD CARPENTERY 2-3MM THICK. WITH

PUTTYAND EYES NAILS>0,25MP

016 2500195 MP. 0.565

Page 29: ITB Constructii Noi Rev1

29

CLEAR DRAWN WINDOW Q.3 3MM. PACKED FREE

SIZES S 853

017 CN09B1 MP. 0.250

DYE WORKS ON WOOD CARPENTRY,OIL PAINT IN

3 LAYERS AT DOORS AND WINDOWS

017 6103270 KG 0.090

RED PAINT V.231-1 NTR 90-80

018 CN15B1 [ 4] MP. 300.000

PAINTING THE TIMBER BY FIREPROOF

SOLUTIONS

019 CN15D1 MP. 75.000

PAINTING OF WOOD WORK WITH SPECIAL

SOLUTIONS,WITH ANTISEPTIC PAINTS,

WATERPROOF ON IMPREGNATE WOOD

020 CN01A1 MP. 6.000

TWO LAYERS LIME MILK PAINTINGS

(PAINTINGS)

021 CO15B1 BUC. 5.000

CLEANING WICHET AT DOUBLE CHIMNEY STACKS

022 CO02B1 [ 2] MP. 3.000

CONCRETE PRECAST SLABS 70 X70 X8CM LAID

ON THE CLEANING DOOR AREA FOR THE

CHIMNEY STACKS

022 2800488 MP. 3.060

CONCRETE MANUFACT. FLAGSTONE 70X70X8CM

023 CO17A1 BUC. 1.000

HATCH TO NON-CIRCULATING TERRACE EXITS

0,8 X0.8M BEECH WOOD INSULATED WITH

INSULATING MATERIAL OF 30MIN FIRE

RESISTANT

024 CO23A1 MP. 81.000

BEECH BOARD WOOD FLOOR BOARDING OF 20MM

THICKNESS

025 IZF10F1 [18] MP. 81.000

INSULATING MINERAL WOOL LAYER G80 TYPE

150MM THICK. COATED,AND ^=0.040 W/MK AND

0 KG/CUBIC METER TO THE FLOORING

026 IZF10C1 [ 5] MP. 25.000

THERMO-INSULATING LAYER FOR FLOOR WITH

EXPANDED POLYSTYRENE

026 2602797 MP. 25.250

PEX C EXPANDED POLYSTYRENE SLAB OF

2000X500X 100MM S7461

027 IZF03B2 MP. 25.000

BARRIER AGAINST VAPOURS ON VERTICAL

SURFACE WITH 1STR IMPISLIT BIT TYPE /A

SAU TSA2000 LIP WITH BITUM TYPE

Page 30: ITB Constructii Noi Rev1

30

027 2600048 KG 37.500

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

027 2602060 MP. 27.500

BIT.2F.NIS. TSA FIBER GLASS

2000 100CM S 10126

028 IZF02A1 MP. 25.000

ROOF VAPOUR DIFFUSION LAYER,TERRACCE

WITH GLASS FIBRE KNITTING HORISONTAL

SURFACE BITUMEN

028 2600048 KG 12.500

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

029 IZF01A1 MP. 25.000

SURFACE MILDING APPLY.VAPOURS DIFUSION

LAYER WITH CUT BITUMEN IN 2 LAYERS

HORIS.AND VERT.SURFACE

029 2600048 KG 3.750

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

030 IZF04J2 MP. 25.000

BOUNDARY LAYER RELATED TO THE INSULATION

WORK EXEC WITH FIBER GLASS FELTING

AND NON GLUED BREAKDOWN

030 2602060 MP. 27.000

BIT.2F.NIS. TSA FIBER GLASS

2000 100CM S 10126

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

Page 31: ITB Constructii Noi Rev1

31

TOTAL with VAT

List with work quantities

Estimate - Tender: RESISTANCE INFRASTRUCTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA04C1 M.C. 18.700

MAN.DIGG.IN LIMIT.SPACES UNDER 1M

SUPPOR.AND MAN.EVAC.IN SOIL WITH NAT.

MOIST AT DEPTH 0,0-1,5M HARD SOIL

002 TSC02D1 100 MC. 0.290

DIGGING WITH EXCAVATOR ON TYRES 0,21-0,

39 MC SOIL NATURAL MOISTURE OPEN AUT.

FILED CATEGORY 2

003 TSC02C1 100 MC. 0.390

EXCAVAT.DIGGING ON TYRES 0,21-0,39 MC

NATUR MOIST SOIL LOAD.DEP.SOIL CAT.1

004 TSD01C1 M.C. 35.000

LOOSE SOIL SHOVEL SPREADING,UNIFORM

LAYER 10-30CM.THICK WITH BREAKBLE CLODS

HARD SOIL

005 TSD05A1 100 MC. 0.350

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

006 TRA06A05 TONA 129.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

007 TSC35B31 100 MC. 0.490

AUTOLOADER ON TYRES WITH BUCKET 2,6-3,9

CM LAND CATEG 2 AT DIST. 11-20 M

008 TSF01B1 MP. 52.000

BANKS SUPPORT BY BEECH BOARDS

HORIZ.LAID WIDTH<1.5M, DEPTH 0,0-

2M;0,21-0,6M BETWEEN BOARDS

009 CG32D1 [ 5] M.C. 8.000

FILLINGS IN LAYERS, EXECUTED BY

MECHANICALLY COMPACTED GRAVEL

010 CA01B1 M.C. 35.300

SIMPLE CONCRETE MOULDING IN FOUNDATIONS

(CONTINUOUS,ISOLATED)AND SOCLES WITH

VOLUME > 3MC,AND IN RETAINIG WALLS

Page 32: ITB Constructii Noi Rev1

32

010 2100945 M.C. 35.582

CEMENT CONCRETE B 150(C8/10) STAS 3622

011 CA01D1 M.C. 12.200

SIMPLE CONCRETE MOULDING IN LAYERS OF 3-

20CM THICKNESS AT CONSTRUCTIONS WITH H

<35M

011 2100945 M.C. 9.374

CEMENT CONCRETE B 150(C8/10) STAS 3622

011 2100919 M.C. 2.923

CEMENT CONCRETE B50 (C2.8/3.5) STAS 3622

012 CB11A1 MP. 139.000

SHUTTERINGS FOR CONCRETE IN ELEV.FROM

PANELS TO STRAIGHT WALL WITH H<3M,WITH

PLYWOOD OF 8MM THICK.

013 CC01C1 KG 710.000

CONCRETE STEEL REINFORCEMENTS ASSEMBLING

IN CONTINUOUS FOUNDATIONS,SLABS OF

PLATES,WITH DIST FROM PLASTICS

014 CZ0301A1 KG 340.000

MANUFAC.REINFOR.SHAPED BARS FOR

FOUNDATION ISOL.CONTINUOUS AND PLATES

IN.CENT.WORKSHOPS OB 37 D=6-8MM

015 CZ0301D1 KG 370.000

REINFORCED MANUFACTURED SHAPING BARS FOR

CONTINOUS ISOLATED FOUNDATION AND PLATE

FOUNDATION IN ATEL CENT.PC 52 D=6-8MM

016 TRA06A05 TONA 119.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

017 TRA02A05 TONA 0.710

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= 5 KM.

018 IZF10F1 [14] MP. 63.300

EXTRUDED POLYSTYRENE INSULATION

LAYER OF 100MM WITH λ= 0.03 W/MK δ> 35 KG

UNDER THE REINFORCED CONCRETE SLAB

019 IZF04J1 [ 1] MP. 81.000

BOUNDARY LAYER EXEC BY POLYETHYLENE

FOIL OF 0.2MM

020 CF12A1 [ 1] MP. 19.000

RIGID WATERPROOFING ON M100T WALLS WITH

APAPSTOP APPLIED IN 3 LAYERS ON HORIZ

SURFACES UNDER WALLS ACC. TO TECHNICAL

SPECIFICATIONS

Direct expensive from items:

Page 33: ITB Constructii Noi Rev1

33

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: RESISTANCE SUPER-STRUCTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CA02J1 M.C. 18.000

MOULDING REINFOR.CONCRETE TO CONSTR.WITH

H<35M,IN FLOORS(BEAMS,COLUMNS,PLATES)

WITH SLAB THICKN.>10CM

001 2100957 M.C. 18.144

Page 34: ITB Constructii Noi Rev1

34

CEMENT CONCRETE B 200(C12/15) STAS 3622

002 CB13A1 MP. 116.000

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTRUCTIONS WITH H<20M TO SLABS AND

BEAMS,WITH PLYWOOD OF 8MM

003 CB13B1 MP. 25.000

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTR.WITH H<20M,AT COLUMNS AND FRAMES,

WITH PLYWOOD OF 8MM

004 CB44A1 BUC. 62.000

SUST.WITH STUDS EXTENS PER3100R FOR

ASSEMBLING FLOORS,PRESLAB TURN FLOORS

MONOL WITH GR OR GR MONOL PL PREFAB.

005 CB45B1 BUC. 31.000

SUSTAIN. FROM METALIC BEAMS EXTENSIBLE

TO CONSTR.WITH H<20M BEAMS SUPPORT.ON

METALIC STUDS

006 RPCH38A1 [ 2] BUC. 30.000

ROUND WOODEN PROP SUPPORT D= 12CM

AT LINTELS OVER DOOR AND WINDOW OPENINGS

007 CC01C1 KG 1610.000

CONCRETE STEEL REINFORCEMENTS ASSEMBLING

IN CONTINUOUS FOUNDATIONS,SLABS OF

PLATES,WITH DIST FROM PLASTICS

008 CZ0302A1 KG 275.000

MANUFAC. REINFORC. FOR WALLS BEAMS

COLUMNS DIAPHRAGMS TO REGULAR CONST IN

CENTRALIZED WORKSHOPS OB 37 D=6-

009 CZ0302E1 KG 590.000

MADE REINFORCED FOR WALLS BEAMS PILLARS

MIDRIFF AT BUILDG. REGULAR IN WORKSHOP

CENTRALIZED PC 52 D=10-

010 CZ0302M1 KG 55.000

MANUFCT. REINFORC. FOR PLATES INCLUD.

STAIRS TO REGULAR CONST. IN CENTRALIZED

WORKSHOPS OB 37 D=6-8MM

011 CZ0302O1 KG 690.000

MANUFCT.REINFORC.FOR PLATES INCLUD.

STAIRS TO REGULAR CONST.IN CENTRALIZED

WORKSHOPS PC 52 D= 6-8MM

012 CP12A1 BUC. 7.000

ASSEMBL.PREFAB.TO HOUSING WITH STRUCT.

MONOL.MIXED AND BRICKWORK.SUST.WITH.VOL.

0,2 MC.AND H<20 M

013 6433209 M.C. 0.300

CONCRETE PRECAST C16/20(B250) II A-

S32.5 0-16MM

014 6433376 KG 18.000

Page 35: ITB Constructii Noi Rev1

35

CONCRETE PREFABR.REINFOR. OB 37 D=6-10MM

STANDARD

015 6433754 KG 10.000

REINFOR.IN CONCRETE PREFABR. PC52 O6-10

MM STANDARD

016 6433754 KG 63.000

REINFOR.IN CONCRETE PREFABR. PC52 O6-10

MM STANDARD

017 AUT1301 ORA 5952.000

EXPANDING METAL GIRDER L=3-5M TYPE GE1 3

SHIFTS

018 AUT1325 ORA 11904.000

EXPANDING METAL PROP PE3100 INCLUDING

PIPE 051X3,5MM

019 TRA06A TONA 45.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. = KM

020 TRA02A TONA 1.610

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= KM.

021 AUT1140 ORA 30.000

TELESCOPIC JIB CRANE ON TYRES TELEMAC HT

125.5 TF 1 SHIFT

022 MDTC4623 BUC. 6.000

EQUIP.TRANSPORT 10 KM-65121002-TYRE

CRANE OF 0,10-0,149 MN(10-14,9TF

023 MDTC5575 BUC. 62.000

EQUIPMENT TRANSPORTATION 10 KM-90100106

EXTENSIBLE METALLIC BEAM WITHL=4-8M TYPE

CE-2

024 MDTC5552 BUC. 124.000

EQUIPMENT TRANSPORTATION 10 KM-90100079

METALLIC POP TYPE PE-3100

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

Page 36: ITB Constructii Noi Rev1

36

- HEALTH

- OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Page 37: ITB Constructii Noi Rev1

37

List with work quantities

Estimate - Tender: REZISTENCE FRAMEWORK

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CE17B1 MP. 125.000

WOODEN FRAMEWORK FOR HEAVY COVERS

002 2900980 M.C. 5.500

FRAMEWORK SQUARED WOOD

003 7335349 ORA 38.000

TIMBER MANUFACT. AT CARPENTRY MACHINES

004 CE23A1 MP. 50.000

SAFETY NET REUSED FOR CONSTRUCTION

COVERS

005 CN15D1 MP. 35.000

PAINTING OF WOOD WORK WITH SPECIAL

SOLUTIONS,WITH ANTISEPTIC PAINTS,

WATERPROOF ON IMPREGNATE WOOD

006 6310159 KG 16.000

JOIN.FRAMEWORK ELEM.LIGHT METALIC

MANUFACT.

007 RPCR41B1 MP. 140.000

FIREPROOF WOODWORK ON PROTECTED SURFAC.

ANT.CONTR.INCE.*

008 CA02M1 M.C. 1.000

REINFOR. CONCRETE MOULDING FOR CONSTR

WITH H<35M IN ELEMENTS SHAPED ISOLATED

WITH VOLUME>0,5MC

008 2100957 M.C. 1.008

CEMENT CONCRETE B 200(C12/15) STAS 3622

009 CB13B1 MP. 8.500

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTR.WITH H<20M,AT COLUMNS AND FRAMES,

WITH PLYWOOD OF 8MM

010 CC02C1 KG 150.000

ASSEMBL.REINFOR.FOR CONSTR H<35M FROM

BARS IN BEAMS AND COLUMNS D<18MM PLATES

D<10MM WITH DIST FROM PLASTIC

011 CZ0302A1 KG 27.000

MANUFAC. REINFORC. FOR WALLS BEAMS

COLUMNS DIAPHRAGMS TO REGULAR CONST IN

CENTRALIZED WORKSHOPS OB 37 D=6-

Page 38: ITB Constructii Noi Rev1

38

012 CZ0302E1 KG 123.000

MADE REINFORCED FOR WALLS BEAMS PILLARS

MIDRIFF AT BUILDG. REGULAR IN WORKSHOP

CENTRALIZED PC 52 D=10-

013 TRA06A05 TONA 2.500

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

014 TRA02A05 TONA 0.200

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= 5 KM.

015 TRA02A10 TONA 2.750

ROAD TRANSPORT OF MATERIALS,SEMIFABS

WITH TRUCK ON DIST.= 10 KM.

016 CF12A1 [ 1] MP. 2.750

RIGID WATERPROOFING ON M100T WALLS WITH

APAPSTOP APPLIED IN 3 LAYERS ON HORIZ

SURFACES UNDER WALLS ACC. TO TECHNICAL

SPECIFICATIONS

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: PAVEMENT

Work category:

=================================================================

Page 39: ITB Constructii Noi Rev1

39

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA01G1 M.C. 18.000

MAN. DIGGINGS IN SPREAD SPACES IN SOIL

WITH NAT.MOISTURE THROWED IN VEHICLE ATH

OF 0,61-2M HARD SOIL

002 TSC35B31 100 MC. 0.180

AUTOLOADER ON TYRES WITH BUCKET 2,6-3,9

CM LAND CATEG 2 AT DIST. 11-20 M

003 TRA01A TONA 33.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= KM

004 TSE06B1 100 MP. 0.900

SOIL PLATF.PREPARING ISOLATING LAYER AND

SAND REPARTION OR GRAVEL IN COHESIVE

SOIL

005 DA06A1 M.C. 14.000

NAT.AGREGG.LAYER(GRAVEL)ROLLED OVER WITH

FILTRING RESISTANCE FUNCTION ISOL.AERING

ANTICAP.MANUAL LAYING

006 TRA01A05 TONA 40.000

MATERIAL,SEMIPREFAB ROAD TRANSPORT BY

TIP LORRY ON A 5 KM DIST.

007 DD02A1 MP. 90.000

PAVMENT MADE OF NORM PAVING 1ST Q. ON

SAND SUB BASE

008 TRA01A10 TONA 16.000

MATERIAL,SEMIPREFAB ROAD TRANSPORT BY

TIP LORRY ON A 10 KM.DIST.

009 DE11A1 M 76.000

SMALL CRIMPS MANUF.CONCRETE 10X15 CM FOR

FRAMING SPACES WALK ROAD ,GREEN ALLEY

FOUND. CONCRETE10 X 20 C

009 2100933 M.C. 2.000

CEMENT CONCRETE B 100(C6/7.5) STAS 3622

010 TRA06A TONA 5.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. = KM

011 RPCT09F1 M.C. 50.000

DEMOLITION BY MECHANICAL MEANS OF PLAIN

Page 40: ITB Constructii Noi Rev1

40

CONCRETE FROM FOUNDATIONS AND ELEVATIONS

012 TRA01A TONA 120.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= KM

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

- HEALTH

- OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

LOT NO. 2 Family House Moldovan Adrian

Page 41: ITB Constructii Noi Rev1

41

QUANTITY LIST WITH TECHNOLOGICAL EQUIPMENT, INCLUDING UTILITIES OF THE ESTIMATE-OFFER FOR PROCUREMENT

Item Name M.U. Quantity Unitary Price

-lei/M.U.-

Amount (VAT

exclusive)

-Thousand lei-

(col.3 x 4)

Supplier

(name,

address,teleph

one,

facsimile)

0 1 2 3 4 5 6

1 Water meter Qn=1.5 cubic

meters/h

pcs 1

2 Ecological tank for waste

water, capacity 10 cubic

meters

pcs 1

3 Electric Boiler 10l pcs 1

Thousand lei: TOTAL

USD*):

*) Exchange rate =…………………. Lei/USD, of …………………….

TECHNICAL SHEET No. 1

EQUIPMENT: WATER METER Qn=1.5 cubic meters/h

Item Technical specifications imposed by the Technical

Specifications

Comparison between the

technical proposal and the specifications imposed by the

Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters: -Type: multi-jet, and dry dial -Nominal output: 1.5 mc/h

-Nominal diameter: 20 mm - Connection sizing: 3/4˝ -Connection type: coupling

-Design pressure Pn 6 bars

2. Performance specs and conditions related to safety in

exploitation: - To be granted a Technical Agreement or an

homologation document;

- The Technical Book shall be presented in Romanian wording.

3. Conditions related to compliance with relevant standards:

-Accuracy category: B

4. Guarantee and post-guarantee conditions: -3 years guarantee

- 3 days for solving out issues occurred during the guarantee period

Page 42: ITB Constructii Noi Rev1

42

5. Other condition of technical character:

TECHNICAL SHEET No. 2

EQUIPMENT: ECOLOGICAL TANK FOR WASTE WATER

Item Technical specifications imposed by the Technical Specifications

Comparison between the technical proposal and the specifications imposed by

the Technical

Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters: -Material: polyester -Net volume: 10 cubic meters

-Diameter: 1.8 linear meters -Length: 4.15 linear meters -Installing: buried

2. Performance specs and conditions related to safety in exploitation:

• To be granted a Technical Agreement or an homologation document;

3. Conditions related to compliance with relevant standards: -SR EN 12566-1

4. Guarantee and post-guarantee conditions: - 3 years guarantee.

5. Other condition of technical character: Minimum life cycle: 30 years

TECHNICAL SHEET No . 3 EQUIPMENT: ELECTRIC BOILER

Item Technical specifications imposed by the Technical

Specifications Comparison between the technical proposal and

the specifications

imposed by the Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• Hot water 800C

• Capacity 10l

• Sizes: 360x254x360

• Maximum pressure: Pn 10 bar

• Wasteful resistance power: 1.2 kW

• Power supply: 220 V

2. Performance specs and conditions related to safety in exploitation: -Inside the boiler’s surface is covered by a special

enamel layer; -It is fitted out by a programmable thermostat, magnesium anode, insulation, relief pressure valve,

“on-off” switch.

3. Performance specs and conditions related to safety in exploitation:

Page 43: ITB Constructii Noi Rev1

43

• To be granted a Technical Agreement or an homologation document;

• The Technical Book shall be presented in Romanian wording.

4. Guarantee and post-guarantee conditions:

• 3 days for solving out issues occurred during the guarantee period;

• 10 days for providing spare parts in the post-

guarantee period.

5. Other condition of technical character

Bill of quantities

Estimate - Tender: ELECTRIC INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 EA02A1 [ 2] M 170.000

PROTECTION INSULATION TUBE,IPEY SEALED

RECESSED WITH D=16/13,4MM

002 EA02A3 [ 2] M 8.000

PROTECTION INSULATION TUBE,IPEY SEALED

RECESSED WITH D=25,8/21,8 MM

003 EA12A1 M 20.000

METALLIC,FLEXIBILE,PROTECTION,UNTIGHT

TUBE, WITH 2 ROWS OF COILS IN

QUADRILATERAL-SHAPE(SPD) 13,5-23 MM

003 7356501 M 20.500

METALIC TUBE FLEX.PROT.NONTIGHT TYPE SPD

-ROMAN D=13,5 MM

004 EB02A1 M 280.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION < 4 MMP

004 4826880 M 288.400

CONDUCTOR FY 1X 1,5 S 6865

005 EB02A1 M 340.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION < 4 MMP

005 4826892 M 350.200

CONDUCTOR FY 1X 2,5 S 6865

006 EB02B1 M 30.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION 6- 10 MMP

Page 44: ITB Constructii Noi Rev1

44

006 4826919 M 30.900

CONDUCTOR FY 1X 6 S 6865

007 ED01A1 BUC. 4.000

MANUAL SWITCH BURIED UNIPOLAR NORMAL OR

WATERPROOF CONSTRUCTION *

007 5500720 BUC. 4.040

CUMPANA SWITCH ST.250V 10A

008 ED03A1 BUC. 5.000

UNIPOLAR SWITCH BURIED,WOODEN NAILS,IN

SERIES,NORM.CONSTR.OF BACHELITA OR

WATERPROOF CONSTR.

008 5520366 BUC. 5.050

CUMPANA SHIFTER ST.250V 10A

009 ED08A1 BUC. 1.000

PLUG BURIED ASSEM.NORMAL CONSTR.

WATERPROOF OR NORMAL PROTECTION CONTACT

009 5536156 BUC. 1.010

BIPOLAR PLUG PROT.PANEL 250/10A RECESSED

010 ED08B1 [ 1] BUC. 9.000

DOUBLE TWIN PLUG WITH PROTECTION

CONTACT RECESSED MOUNTED

010 5535994 BUC. 9.090

DOUBLE BIPOL.PLUG,PROT.CONTACT 250/10A

RECESSED

011 ED01D1 BUC. 1.000

MANUAL SWITCH WOODEN NAILS IN UNIPOLAR

NORMAL CONSTR. MADE OF BACHELITE OR

TIGHT CONSTR.

011 5500677 BUC. 1.010

VISIBLY SET MANUAL SHIFTER 250V 10A

012 ED10A1 [ 1] BUC. 1.000

BELL BUTTON 10A 250V

013 EE04A1 BUC. 2.000

SIMPLE LUMINAIRE (LAMP HOLDER) REGULAR,

WITH NAIL AND RING

014 EE05A1 BUC. 3.000

Page 45: ITB Constructii Noi Rev1

45

SIMPLE APPLY ,OBL./RIGHT.GLOB ST.OPAL.

MONT.CEILING./WALLS ON WOOD DOWEL

014 5104071 BUC. 3.036

WALL BRACKET E27,OBLIQUE,60W,BOWL

015 EE08A1 [ 1] BUC. 1.000

CHANDELIER INCANDENSCENCE BULBS WITH 1

ARM

015 5105311 BUC. 1.003

INCANDENSCENCE BULBS 1 ARM CHANDELIER

016 EE08A1 BUC. 2.000

CHANDELIER INCANDENSCENCE BULBS WITH 2

ARMS

016 5105312 BUC. 2.006

INCANDENSCENCE BULBS 1 ARM CHANDELIER

017 EE08B1 BUC. 1.000

CHANDELIER INCANDENSCENCE BULBS WITH 3

ARMS

017 5105300 BUC. 1.003

INCANDENSCENCE BULBS 3 ARMS CHANDELIER

018 EE12B1 BUC. 1.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

018 5103611 BUC. 1.003

FLUOR.LUMINAIRE FIA 11-2X36 W EQUIPPED,

APPARENT ASSEM.

019 EE12B1 BUC. 2.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

019 5103823 BUC. 2.006

FLUORESCENT LIGHT FIXTURES AB 02-1X18 W

VISIBLY SET

020 EE14A1 BUC. 2.000

ASSEM.LAMP INSIDE.CONSTR.OR ON EXTER.

ELEMENTS INCANDESCENCE UP TO 1000 W.

020 5101029 BUC. 2.100

INCANDESCENTE LAMP CLEAR E27 TIP S 220V

25W S6115

021 EE14A1 BUC. 11.000

Page 46: ITB Constructii Noi Rev1

46

ASSEM.LAMP INSIDE.CONSTR.OR ON EXTER.

ELEMENTS INCANDESCENCE UP TO 1000 W.

021 5101251 BUC. 11.550

INCANDES LAMP DOUBLE SPIR.CLEAR E27 AM

220V 60W CS

022 EF05D1 [ 1] BUC. 1.000

PANEL WITH PROTECTION CUT-OUT AND

DIFER.FAULT CURRENT DEVICE +

BELL AND SWITCH

022 7305451 BUC. 1.000

PANEL WITH 4 PROTECTION CUT-OUTS

PHASE-NULL(1x 6A+2x16A+1x16A WITH DIFFER.

PROT.DIVICE Id=30mA) BELL AND SWITCH

023 EF09A1 BUC. 6.000

COUPLING COPPER PIPE AT DEVICES BORNS ,

MOTORS,ELECTR.COUNTER COND.HAVING SECT.

<10SQMM,EXCLUSIVELY

024 EG08B1 M 10.000

COND.EARTH CONNECTION LIGHTING ROD

UNDERGROUND EARTH CONN.GALVANIZED STEEL

STRIP 40X4MM IN HARD SOIL *

025 W1R06A1 M 3.000

ELECTRODE OF STEEL PIPE OF TWO AND

A HALF INCHES FOR EARTH GROUNDING

IN NORMAL GROUND

026 W1P08A BUC. 1.000

EARTH CONN.TESTING FOR BUILDING WIRING

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

Page 47: ITB Constructii Noi Rev1

47

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: SANITARY INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 SA04B1 M 18.000

STEEL PIPE LONGIT.WELDED GALVAN.INSTAL.

THREAD+COUPLING SET HOUSES+SOC.CULT.

CONNECTIONS D= 1/2I

001 3306625 M 18.180

ZINCKED INSTLL. PIPE THREAD+COUPLING

M - 15( 1/2) OL 32 1 S 7656

002 SA04C1 M 24.000

STEEL PIPE LONGIT.WELDED FOR ZINCKED

INSTAL.WITH THREAD+COUPLING ASSEM.LOC.+

CULT.IN LEGATURI D= 3/4T

002 3306649 M 24.240

ZINCKED INSTLL. PIPE THREAD+COUPLING

M - 20( 3/4) OL 32 1 S 7656

003 SA43C1 BUC. 10.000

CLAMP STEEL PIPE FIXING+PVC WATER+GAS

SUPPLY,TOOTHING SET,PIPE HAVING D= 1/2

INCHES

004 SA43D1 BUC. 10.000

CLAMP STEEL PIPE FIXING+PVC WATER+GAS

SUPPLY,TOOTHING SET,PIPE HAVING D= 3/4

INCHES

005 SA46A1 BUC. 6.000

MANUF.ASSEM.AND CEMENTATION OF

PROTECTION PIPE PASSING PIPE THROUGH

WALL,PIPE HAVING D=1 INCHES

006 SA46B1 BUC. 4.000

MANUFACT,SET AND ASSEMBLY OF PIPE

PROTECTION AT PASSING OF PIPES THROUGH

WALL,PIPE HAVING D=1 1/4 INCHES

007 SA46D1 BUC. 2.000

MANUFACT,SET AND ASSEMBLY OF PIPE

PROTECTION AT PASSING OF PIPES THROUGH

WALL,PIPE HAVING D=2 INCHES

Page 48: ITB Constructii Noi Rev1

48

008 SB16A1 [ 1] M 6.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 32 MM

009 SB16B1 [ 1] M 4.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 40 MM

010 SB16C1 [ 1] M 12.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 50 MM

011 SB16E1 [ 1] M 14.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D=110 MM

012 SB17A1 [ 1] BUC. 6.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D= 32MM

012 6712226 BUC. 6.000

@HTB POLYPROPYLENE ELBOW AT 45 DGR DN 32

CODE 62504011

013 SB17C1 [ 1] BUC. 6.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D= 50MM

013 6712243 BUC. 6.000

@HTB POLYPROPYLENE ELBOW AT 45 DGR DN 50

COD 62504029

014 SB17E1 [ 1] BUC. 10.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D=110 MM

014 6712408 BUC. 6.000

@POLYPROPILENE ELBOW HTD LA 87GR 30MIN

DN 110 COD 62504059

014 6712264 BUC. 4.000

@HTD POLYPROPYLENE ELBOW AT 45 DGR DN

110 COD 62504053

015 SB19A1 [ 5] BUC. 2.000

FIREPROOF POLYPROP. SIMPLE LOW BRANCH

RUBBER SEAL JOINING D=50/40 MM

015 6712811 BUC. 2.000

Page 49: ITB Constructii Noi Rev1

49

@HTEA POLIPROP REDUCED BRANCK 45GR DN50/

40 COD 62510007

016 SB19C1 [ 2] BUC. 2.000

FIREPROOF POLYPROP. SIMPLE LOW BRANCH

RUBBER SEAL JOINING D=110/ 50 MM

016 6712848 BUC. 2.000

@HTEA POLIPROP SIMPLE REDUCED BRANCH 45

DGR DN110/50 COD 62510031

017 SB19C1 [ 1] BUC. 2.000

SEWAGE FIREPROOF POLYPROP.SIMPLE UNIFORM

BRANCH RUBBER SEAL JOINING D=110 MM

017 6712862 BUC. 2.000

@HTEA POLIPROP SIMPLE EQUAL BRANCH 45

DGR DN 110 COD 62508025

018 SB21C1 [ 1] BUC. 2.000

SEWAGE FIREPROOF POLYPROP.INTERVENTION

PART RUBBER SEAL JOINING D=110 MM

019 SB22A1 [ 1] BUC. 2.000

SEWAGE FIREPROOF POLYPROP.REDUCING PIECE

RUBBER SEAL JOINING DN 40- 32 MM

020 SB22B1 [ 1] BUC. 2.000

FIREPROOF POLYPROP.REDUCING COUPLING FOR

SEWERAGE RUBBER SEAL DN 50- 32 MM

021 SB22E1 [ 1] BUC. 1.000

FIREPROOF POLYPROP.REDUCING COUPLING FOR

SEWERAGE RUBBER SEAL D=110- 50 MM

022 SB44C2 [ 1] BUC. 2.000

HDPE GULLY TRAP D= 50 MM WITH 1

CONNECTION AND VERTICAL EXIT

023 SB49A3 [ 1] BUC. 2.000

FIREPROOF POLYPROP.PIPES VENT CAP D=110

MM

024 SC01D3 [ 2] BUC. 1.000

FIBRE GLASS BATH TUB FLAT BOTTOM

IST Q. WHITE WITH L=1700MM

025 SC07E1 [ 1] BUC. 2.000

SANIT.PORCELAIN LAVATORY L2 600 ON STAND

INCLD.FLOOR TRAP AND DELIVERY VALVE

Page 50: ITB Constructii Noi Rev1

50

026 SC10A1 BUC. 1.000

DISH WASHER OF ENAMEL COATING CAST IRON

WITH SUPPORT SET BY WOODEN DOWELS ON WALL

027 SC13B1 BUC. 2.000

SANITARY PORCELAIN WATER CLOSET WITH

SIPHON TRAP P COL2-A TYPE WHITE

PORCELAIN C.1

027 2442757 BUC. 2.020

WATER CLOSET COL2-A WHITE PORCELAIN C.1

S 2066

028 SC16D1 [ 1] BUC. 2.000

RESERVOIR FOR WASHING WC BASIN FROM

POLYPROPYLENE SET MIDHEIGHT ON

BRICK WALL

029 SC18A5 BUC. 2.000

WC BASIN FRAME,OF POLYPROPYLENE WITH LID

030 SC25A1 BUC. 2.000

SANITARY PORCELAIN SHELF TYPE

030 2451849 BUC. 2.020

PORCELAIN SHELF TYPE E2.60 WHITE Q.1 NI

567

031 SC24A1 BUC. 2.000

BRASS TOWEL SUPPORT MOUNTED ON WALLS

TYPE U,WITH 1 ARM, OPENING 450MM

032 SC26A2 BUC. 2.000

SEMICRYST.SANIT.MIRROR POLISH.EDGES

SIZES 500X600MM

033 SC28B1 BUC. 1.000

SANITARY PORCELAIN SOAP BOX

SA2-15 TYPE,VISIBLE,SIMPLE

034 SC29A1 BUC. 2.000

LAUNDRY HANGER OF ENAMELLED CAST IRON ,

SANITARY PORCELAIN OR PLASTIC MATERIAL

TYPE

034 6719536 BUC. 2.000

BATHROOM PEG AMINOPLAST 3 HANGERS NI

2199

035 SC30A1 BUC. 2.000

SANITARY PORCELAIN 1 Q. PAPER HOLDER,HA1

Page 51: ITB Constructii Noi Rev1

51

NI 545/63

036 SC34A1 BUC. 1.000

BOILER WITH PRESSURE BREAKING VESSEL

CAPACITY 100L

037 SD03A1 BUC. 1.000

BATH MIXING BATTERY,WITH FLEXIBLE

SHOWER,OF 1/2 INCH TYPE...ASSEM. WITH

WOODEN DOWELS ON BRICKWALL

037 4201523 BUC. 1.000

BRASS MIXER BATTERY FLEXIBLE TUBE PEAR

SHOWER A 1/2 NI 4309

038 SD06A1 BUC. 2.000

LAVATORY COCK SYSTEM D=1/2"

038 4201341 BUC. 2.000

BATH MIXING BATTERY CAST IRON WASH BASIN

1/2" ENAMEL S8732

039 SD06A1 [ 1] BUC. 1.000

LAVATORY COCK SYSTEM FOR WASHER D=1/2"

039 4201444 BUC. 1.000

BATH MIXING BATTERY CAST IRON WASH BASIN

ENAMEL 1/2" S8732

040 SD12A1 BUC. 6.000

CORNER ADJUSTMENT FAUCET,OF NICHELLED

BRASS,HAVING D=3/8 OR D=1/2 INCHES

040 4201779 BUC. 6.000

NICKEL PLATED GRASS ANGLE CONTROL COCK 1

/2 " S 751/I

041 SA21A1 [ 1] BUC. 6.000

FLEXIBLE REINFORCED RUBBER CONNECTION 1/

2"X1/2"

042 SD13A1 [ 1] BUC. 2.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

042 7344032 BUC. 2.000

SPHERE TAP FI X FE "MINI" DN 1/2" CODE

40MI4272

043 SA21B1 [ 1] BUC. 2.000

FLEXIBLE REINFORCED RUBBER CONNECTION

Page 52: ITB Constructii Noi Rev1

52

1/2"X 3/8"

044 SD13A1 [ 1] BUC. 2.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

044 7344045 BUC. 2.000

@SPHERE FAUCET EVAC+LID+PORTHOSE DN 1/2"

CODE 40814762

045 SD13A1 [ 1] BUC. 2.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

045 7344030 BUC. 2.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 1/2" CODE 40430425

046 SD13B1 [ 1] BUC. 5.000

SPHERE FAUCET WITH COUPLING,FOR STEEL

PIPES D=3/4''

046 7344059 BUC. 5.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

047 SE48A1 [ 1] BUC. 1.000

WATER ELECTRICAL HEATER,10L CAPACITY

048 SF01A1 M 42.000

TIGHTENESS TEST AT PRES. OF INST. INTER.

OF WATER,IN PIPES STEEL ZN. OR LEAD

PRES. INCLUDING REINFORCED

049 SF04A1 [ 1] M 42.000

WATER PIPES CLEANING AND PUTTING

INTO OPERATION

050 CN13A1 M 42.000

INSTALLATIONS REGULAR PAINTINGS WITH OIL

PAINT ON PIPES EXT.D<34MM INCLUDED

050 6103220 KG 0.714

WHITE PAINT (FP) V.101-1 NTR 90-80

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Page 53: ITB Constructii Noi Rev1

53

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: WATER AND SEWAGE SERVICES

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA02F1 M.C. 21.000

MAN.DIGGIN.IN LIMIT.SPACES UNDER 1M WITH

R.O.W.VERT.UNSUPPORT.IN SOIL AVER.COHEZ.

AND VERY COHEZ.DEPTH<1,5M HARD S.

002 TSA12C1 M.C. 4.500

MAN.DIGG.IN EXCAVATIONS 1-1,5M WIDE WITH

SUPP.MAN.EVAC.IN SOIL WITH NAT.MOIST AT

DEPTH 0,0-1,5M,HARD SOIL

003 TSC02B1 100 MC. 0.480

DIGGING WITH TYRE EXCAVAT.0,21-0,

39 MC NAT.MOIST.DISCHARGE GROUND

CAT.2

004 TSA18E2 M.C. 4.500

MAN.EXCAV. FOLLOWING MECHANICAL EXCAVATION

HOLES.FOUND. ELEM.NAT.MOIST.SOIL WITH

SUPPORT DEPTH< 4 M HARD SOIL

005 TSF01A1 MP. 70.000

SUPPORT.BY EDGES WITH BEECH SUPPRT.

PLACED HORIZ.EDG.BETWEEN <1,5M,DEEP.0,0-

2M,0,0 -0,2M BETWEEN EDGE

006 TSD01C1 M.C. 52.000

LOOSE SOIL SHOVEL SPREADING,UNIFORM

LAYER 10-30CM.THICK WITH BREAKBLE CLODS

HARD SOIL

Page 54: ITB Constructii Noi Rev1

54

007 TSD05A1 100 MC. 0.520

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

008 ACA10A1 [ 2] M 12.000

UNDERGROUND SETTING AT WATER SUPPLY HDPE

PIPES JOINED WITH FITTINGS THROUGH

COMPRESSION,WITH DN 20-25 MM

008 6701146 M 12.240

@TV HDPE80 312UNI7611.7615 PN10 DN

25X2.3 COD 64000109

009 ACA17A2 BUC. 2.000

POLYETHILEN CONNECTION PIECES JOINED BY

COMPRESSION FOR HDPE WATER SUPPLY PIPES

009 6790049 BUC. 2.000

@HDPE FEMALE QUICK JOINING80 DN25X1"

COD WAVIN 704026

010 ACA12A1 [ 2] M 14.000

INSTALLING PVC PIPE IN GROUND 100

COMPACT SN 4 FOR EXTERIOR SEWAGE

RUBBER TIGTH ELASTOM.RING D=110 MM

011 SD13A1 [ 1] BUC. 1.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

011 7344045 BUC. 1.000

@SPHERE FAUCET EVAC+LID+PORTHOSE DN 1/2"

CODE 40814762

012 SD13B1 [ 1] BUC. 2.000

SPHERE FAUCET WITH COUPLING,FOR STEEL

PIPES D=3/4''

012 7344059 BUC. 2.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

013 ACE12B1 BUC. 1.000

WATER METER SETTING WITH BLADES OF D 20

MM

014 M1A01B1 [ 1] BUC. 1.000

INSTALLING WASTE WATER ECOLOGICAL TANK

015 ACD01J1 BUC. 2.000

STAS 2308-81 FRAME AND CAP FOR SEWERS

WITH CARRIAGEWAY SUPPORT PIECE III A

Page 55: ITB Constructii Noi Rev1

55

TYPE

016 ACD09G1 BUC. 1.000

CONCRETE MANHOLES SET SECT. CIRC. PR.TIP

1785-2 DI 1,5 M. H 1,5 WITHOUT

UNDERGROUND WATER CARRIAGEWAY

017 ACD04A1 [ 3] BUC. 1.000

MANHOLE STAS 2448-73 WITH INSPECTING

CHAMBER HC=1M OF CONCRETE PIPE WITH LIP

AND NOSE FOR SEWERS WITH DN 110

017 2101195 M.C. 0.038

MORTAR M100 T WITH LIME HYDRATING

017 2100933 M.C. 1.010

CEMENT CONCRETE B 100 (C6/7,5) STAS 3622

018 ACD07A1 M 1.000

ELEMENTS AT MANHOLES STAS WITH H>2 M

INCLUDES: CONCRETE TUBE ACCESS DN 800 L=

1 M WITH FANCET AND OPENING

018 2101183 M.C. 0.019

MANSONRY MORTAR M 100 S 1030

019 ACD03A1 M 2.500

STRINGER LADDED OL 50X10 AND STEPS

OB D=20MM ACCESS IN SEWERS OF CONCRETE

PIPES

020 ACE05A1 [ 1] BUC. 4.000

PVC PIECE FOR PIPING TIGHT PASSAGE

THROUGH CONCRETE SEWERS WALLS

020 6311601 BUC. 2.000

@PASSAGE THROUGH PIECE INCLUDED IN PVC

32 MM WITH WATERPROOFING

020 6311607 BUC. 2.000

@PASSAGE THROUGH PIECE INCLUDED IN PVC

110 MM WITH WATERPROOFING

021 ACE07A1 100 M. 0.120

WATER PIPES WASHING AND DESINFECTION

WITH DN 50

022 ACE08A1 M.C. 12.000

DITCH FILLING FOR WATER PIPE SUPPLY AND

SEWERAGE WITH: SAND

Page 56: ITB Constructii Noi Rev1

56

023 W2H07A1 [ 1] M 12.000

POLYETHYLENE WARNING STRIP

023 TRA01A05 TONA 24.000

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH DUMP TRUCK DISTANCE= 5 KM

024 TRA01A05P TONA 48.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= 5 KM

025 TRI1AA03C2 TONA 48.000

MATERIAL LOADING,GROUP A-HEAVY IN DUST,

BY THROWING FROM PLATFORMS OR SOIL-CAR

CATEG.2

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: VARIABLE ARCHITECTURE Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

Page 57: ITB Constructii Noi Rev1

57

001 CB48A1 MP. 24.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1304 ORA 168.000

SELF-LIFTING METALIC SCAFFOLD 2 CASTLES

6MARCH 75KG/M H-31M L=12M 3SHIFTS

003 CI02A1 [10] MP. 24.000

NATURAL LOCAL STONE PLATING

INCL. MESH

003 2202200 SQ.M. 24.766

BANPOTOC 1 QUALITY G=2CM S LIMESTONE SLAB

6035

004 CG06C1 MP. 6.500

MOSAIC FLOOR CAST ON SITE OF 1,5CM

THICKNESS SIMPLE WITHOUT CRIMP ON

SURFACE <5MP WITH MARBLE MOSAIC

005 CH01B1 M 11.500

PLATED SIMPLE CONCRETE TREADS WITH

PREFAB.TREADS AND RISERS WITH MARBLE

MOSAIC

005 2802892 M 11.845

MANUFACT.MARBLE STAIR CASE NAT.COLOUR

005 2802957 M 11.845

MARBLE MOSAIC RISER NATURAL COLOUR

006 CE14A1 M 6.000

GALVANIZED PLATE RAIN PIPE OF 0,5MM MADE

ON SITE SEMIROUND WITH D= 15,4CM

007 CF06A1 MP. 24.000

EXTER.REGULAR PLASTER,FLOATED FOR

DRYWALLS OR INTERIORS IN GARRET,OF 2 CM

007 2101203 M.C. 0.528

PLASTER MORTAR M25T

008 CG07B1 M 8.000

MOSAIC PLINTHS OR GORGES CAST ON SITE

SITE-HORISONTAL PLINTHS H=10CM AT MARBLE

MOSAIC WALLS

009 CH04A1 M 6.000

CURRENT WOODEN HANDRAIL

009 2948144 M 6.300

OAK WOOD HANDRAIL PRECAST SECT. 40X80 MM

010 CL20B1 KG 52.000

APPARENT METALLIC MANUFACT. ASSEMBLYING:

GRATES BANISTERS,TRAP DOOR,CHECKS, GRILL

010 6306274 KG 52.000

SIMPL.DECORATIVE LATTICE WORK FOR

STAIRCASES,PROFILED STEEL BALCONY

Page 58: ITB Constructii Noi Rev1

58

011 CN11B1 MP. 5.500

DYE WORKS AT BANISTERS,GRID,METALLIC

PARAPET WITH ALCHIDICAL ENAMEL

011 6108347 KG 0.385

REDISH BROWN ENAMEL UIC E.735-8 NTR 1703

-80

011 6100943 KG 0.440

ALCHID RED OXID PLASTER ROUGH G 735-3

012 CN09G1 MP. 18.000

PAINTINGS ON WOOD CARPENTERY ,DONE WITH

2 LAYERS ALCHIDIC LAQUER COLORLESS,AT

DOORS,WINDOWS ,SHUTTER.RUL.

013 CO02B1 MP. 30.000

CONCRETE PLATES WALK SIDE FOR SAND

PAVEMENTS,JOINTS FILLED WITH MASTIC

013 2800488 MP. 30.600

CONCRETE MANUFACT. FLAGSTONE 70X70X8CM

014 IZF10F1 [ 3] MP. 24.000

50MM EXTRUDED POLYSTYRENE LAYER TO

EXTERIOR WALLS GLUED BY BITUMINOUS CEMENT

015 RPCO56A1 [ 3] M 18.000

OAK WOOD BANISTERS AT PLATFORMS WITH

SIZES OF 30 X 125MM AT 3 ROWS

016 CH01D1 M 9.000

SIMPLE CONCRETE TREADS TITIVATED OR

ROLLED WITH CEMENT MORTAR M100-T

CAREFULLY FINISHED

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

Page 59: ITB Constructii Noi Rev1

59

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

BILL OF QUANTITIES

Estimate - Tender: CONSTANT ARCHITECTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 132.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1302 ORA 390.000

METAL AUTO-LIFTING SCAFFOLD 3 CAST. 3.

5TF H=31M L=29M 3 SHIFTS

003 MDTC5517010 BUC. 2.000

EQUIPMENT TRANSPORT 10 KM 90100043

SELF-LIFTING METALLIC SCAFFOLDING WITH 2

CASTLES

004 CD04E1 M.C. 0.100

MASONRY FROM PRESSED BRICK 240X115X63MM

AT BATHROOM TUB CLOSING, CAL.1

005 CD04C1 M.C. 2.000

RESSED BRICK MASONRY 240X115X63MM AT

INSULATED CHIMNEY STACKS IN GARRET,QAL.1

005 2101171 M.C. 0.340

MASONRY MORTAR M 50 S 1030

006 CD05A1 M.C. 32.000

BRICK MASONRY TYPE GVP AT BUILDINGS H

<35M, SHAPE 240X115X 88MM,Q.A

006 2101169 M.C. 6.720

MASONRY MORTAR M 25 S 1030

Page 60: ITB Constructii Noi Rev1

60

007 CD04H1 M.C. 6.000

MASONRY FROM PRESSED BRICK 240X115X63M M

AT BUILDING.H<35M, 12,5CM THICKNESS, Q.

A,WITH VOIDS <50 %

007 2101169 M.C. 1.080

MASONRY MORTAR M 25 S 1030

008 CE15B2 [ 1] M 8.000

ALUMINIM WINDOW BOARDS

009 CF01K1 MP. 246.000

FLOATED INT.PLASTERS,AT COLUMNS,WALLS

WITH SPRINKLER AND PLASTER ROUGH CAST

MECHANICALLY PERFORMED,OF 2CM

009 2101202 M.C. 4.428

PLASTER MORTAR M10T

010 CF06K1 MP. 123.000

FLOATED EXTERNAL PLASTER ON BRICK AND

BLOCKS WALLS WITH CRUND.MECH.LAYER VIZ.

MANUALLY MORTAR M25-T THICK.2,5 CM

010 2101204 M.C. 2.829

MORTAR M50T

011 CF06C1 [ 6] MP. 123.000

OUTER DECORATIVE PLASTER OR

SIMILAR

012 CF10C1 MP. 316.000

PLASTER POLISHING APPLIED ON FLOATED

INTERIOR PLASTERS

013 CG01E1 [ 5] MP. 70.000

CEMENT SLAB FINISH FOR FLOORS

014 RPCK07D1 MP. 52.000

RESINOUS WOODEN FLOORING OF 24MM

THICK. NAILED ON OAK LATHS OF

50X80MM

015 CG06C1 MP. 9.500

MOSAIC FLOOR CAST ON SITE OF 1,5CM

THICKNESS SIMPLE WITHOUT CRIMP ON

SURFACE <5MP WITH MARBLE MOSAIC

016 CG06D1 MP. 8.500

MOSAIC FLOOR POURED ON SITE OF 1,5CM

THICK.SIMPLE WITHOUT CRIMP ON SURF.>5MP

WITH MARBLE MOSAIC

017 CG07B1 M 37.500

MOSAIC PLINTHS OR GORGES CAST ON SITE

Page 61: ITB Constructii Noi Rev1

61

SITE-HORISONTAL PLINTHS H=10CM AT MARBLE

MOSAIC WALLS

018 CG28B1 MP. 70.000

5MM DIFFERENCE SUPP.LAYER FOR CEMENT

MORTAR FLOOR

018 2101200 M.C. 0.350

PLASTER MORTAR M 100 (LIME PASTE ) S

1030

019 CG26A1 MP. 18.000

POLISHING,INCLUDING MARBLE OR MARBLE

MOSAIC GRAVEL WAXING FLOORS

020 CG26B1 M 37.500

POLISHING INCLUDING PLINTH AND GORGES

WAXING

021 CN04D1 MP. 44.000

DYE WORKS FOR INTERIOR AND EXTERIOR

MANUALLY EXEC.WITH OIL PAINTS

IN 2 LAYERS ON SMOOTH PLASTERS

021 6103309 KG 10.648

CREAM PAINT (FP) V.401-1 NTR 90-80

022 CK11G1 [ 3] MP. 11.000

PVC DOUBLED-GLASSED WINDOWS

023 CK14A1 [ 2] MP. 5.300

WHITE COLOR PVC DOORS WITH THERMO

INSULATING GLASS 4+ 16+4MM

024 CK03A1 MP. 9.800

INTERIOR SIMPLE WOOD DOORS ONE LEAF ON

LINING

024 2933300 MP. 9.800

ONE LEAF TIMBER DOOR ON

LINING FINISHED BY

MANUFACTURER

025 CK03C1 MP. 3.300

INTERNAL SIMPLE WOOD DOORS IN 2 LEAFS ON

LINING

025 2932150 MP. 3.300

2 LEAFS WOOD DOORS ON LININGS PAINTED AT

PRODUCER

026 CK25C1 BUC. 2.000

CARPENTRY ACCESSORY WORKS APPLIED LOCK

TO A YALE SYSTEM

Page 62: ITB Constructii Noi Rev1

62

026 6310380 BUC. 2.000

SAFETY LOCK IN YALLE

SYSTEM WITH DOOR BOLT

027 CK08A1 MP. 0.350

EXTRA DIFFERENCE AT LINING FOR DOORS

WIDER THAN 19,5 CM.

028 CK09A1 [ 1] M 8.000

20CM WIDE PVC WINDOW BOARDS SET TO THE

INTERIOR

029 CM02E1 MP. 4.000

DRAWN WINDOWS SIMPLE MEASURE FREE ON

WOOD CARPENTERY 4-8MM THICK.WITH PUTTY

AND WANG AT VITRI

029 2500327 MP. 4.360

CLEAR DRAWN GLASS Q.3 4MM. PACKED FREE

SIZES S 853

030 CN06B1 [ 3] MP. 316.000

3 LAYER WHITE COLOR WASHABLE PAINTING FOR

INTERIOR FOR WALLS

031 RPCK72A1 MP. 52.000

PALUX LAKE PARQUET LAQUERING IN THREE

LAYERS

032 IZF10C1 [10] MP. 123.000

THERMINSULATING LAYER FOR WALLS OF

EXPANDED POLYSTYRENE FOR FACADE OF 10CM

THICK.INCLUDING MORTAR ADHESIVE AND

SECURING NAILS

032 2602797 MP. 124.230

PEX C EXPANDED POLYSTYRENE SLAB OF

2000X500X 100MM S7461

033 CO12A1 BUC. 470.000

TERACOTTA ENAMEL STOVES,INCLUDING

METALLIC SEALS

033 2436887 BUC. 484.100

COLORED TILES FOR STOVES OF 240X220 1ST Q.

S1798

033 7323475 BUC. 4.700

METALLIC SET TERRACOTTA STOVE (EG .GRILL)

Page 63: ITB Constructii Noi Rev1

63

FROM NES CAST IRON

033 7323580 BUC. 4.700

CAST IRON GRILL MAR ,1 105 X128X8

034 TRA06A TONA 37.500

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: CONSTANT ARCHITECTURE GARRET

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 25.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1302 ORA 170.000

METAL AUTO-LIFTING SCAFFOLD 3 CAST. 3.

5TF H=31M L=29M 3 SHIFTS

Page 64: ITB Constructii Noi Rev1

64

003 CD05E1 M.C. 5.000

BRICK MASONRY GVP TYPE FOR

CONSTR.H<35M, FORMAT 365X180X138MM,A Q.

003 2101169 M.C. 0.650

MASONRY MORTAR M 25 S 1030

004 CD04C1 M.C. 1.850

RESSED BRICK MASONRY 240X115X63MM AT

INSULATED CHIMNEY STACKS IN GARRET,QAL.1

004 2101171 M.C. 0.315

MASONRY MORTAR M 50 S 1030

005 CE01A1 MP. 160.000

BURNT CLAY SHAPED TILE COVER

005 2302983 BUC. 2560.000

DRAIN TILE WITH 1 BEAK Q1 390X230X11

S515

006 CE13A1 M 39.000

GALVANIZED PLATE DRAIN OF 0,5MM, MADE ON

SITE SEMIROUND WITH D=15CM

007 CE14A1 M 21.000

GALVANIZED PLATE RAIN PIPE OF 0,5MM MADE

ON SITE SEMIROUND WITH D= 15,4CM

008 CE15B2 [ 1] M 1.200

ALUMINIM WINDOW BOARDS

009 CE19D1 [ 1] M 55.000

TOOTHING EAVES FROM ONE SIDE

PLANE BOARD AND RABBETED

OF 70CM WIDE

009 2903830 M.C. 0.083

LONG RESIN BOARD SELVEDGED CLASS C THICK

=24MM L=3,00M S 942

010 CF06A1 MP. 6.000

EXTER.REGULAR PLASTER,FLOATED FOR

DRYWALLS OR INTERIORS IN GARRET,OF 2 CM

010 2101203 M.C. 0.132

PLASTER MORTAR M25T

011 CF06C1 [ 6] MP. 25.000

OUTER DECORATIVE PLASTER OR

SIMILAR

012 CF06K1 MP. 25.000

FLOATED EXTERNAL PLASTER ON BRICK AND

BLOCKS WALLS WITH CRUND.MECH.LAYER VIZ.

MANUALLY MORTAR M25-T THICK.2,5 CM

012 2101203 M.C. 0.575

PLASTER MORTAR M25T

Page 65: ITB Constructii Noi Rev1

65

013 CK01A1 MP. 0.500

BUILDINGS WOODEN WINDOWS WITH H= 0- 35M

WITH FRAME SURFACE < 1,00MP.

013 2938811 MP. 0.500

EXTERNAL SIMPLE RESIN WINDOWS OAK FRAME

<0,50 SQM

014 VB34C1 BUC. 3.000

PROTECTION CAP FOR CIRCULAR SEWERS WITH

PERIM. OF 701-1600 MM MADE.ON SITE DET.

TYPE 61/0

015 CK09A1 M 1.000

RESINOUS TIMBER LINTELS

015 2947800 M 1.000

RESINOUS WINDOW BOARD OF 30MM WIDE UP

TO 120MM

016 CM02B1 MP. 0.500

DRAWN GLASSES SIMPLE FREE MEASURE ON

WOOD CARPENTERY 2-3MM THICK. WITH

PUTTYAND EYES NAILS>0,25MP

016 2500195 MP. 0.565

CLEAR DRAWN WINDOW Q.3 3MM. PACKED FREE

SIZES S 853

017 CN09B1 MP. 0.250

DYE WORKS ON WOOD CARPENTRY,OIL PAINT IN

3 LAYERS AT DOORS AND WINDOWS

017 6103270 KG 0.090

RED PAINT V.231-1 NTR 90-80

018 CN15B1 [ 4] MP. 300.000

PAINTING THE TIMBER BY FIREPROOF

SOLUTIONS

019 CN15D1 MP. 75.000

PAINTING OF WOOD WORK WITH SPECIAL

SOLUTIONS,WITH ANTISEPTIC PAINTS,

WATERPROOF ON IMPREGNATE WOOD

020 CN01A1 MP. 6.000

TWO LAYERS LIME MILK PAINTINGS

(PAINTINGS)

021 CO15B1 BUC. 5.000

CLEANING WICHET AT DOUBLE CHIMNEY STACKS

022 CO02B1 [ 2] MP. 3.000

CONCRETE PRECAST SLABS 70 X70 X8CM LAID

ON THE CLEANING DOOR AREA FOR THE

CHIMNEY STACKS

022 2800488 MP. 3.060

CONCRETE MANUFACT. FLAGSTONE 70X70X8CM

Page 66: ITB Constructii Noi Rev1

66

023 CO17A1 BUC. 1.000

HATCH TO NON-CIRCULATING TERRACE EXITS

0,8 X0.8M BEECH WOOD INSULATED WITH

INSULATING MATERIAL OF 30MIN FIRE

RESISTANT

024 CO23A1 MP. 81.000

BEECH BOARD WOOD FLOOR BOARDING OF 20MM

THICKNESS

025 IZF10F1 [18] MP. 81.000

INSULATING MINERAL WOOL LAYER G80 TYPE

150MM THICK. COATED,AND ^=0.040 W/MK AND

0 KG/CUBIC METER TO THE FLOORING

026 IZF10C1 [ 5] MP. 25.000

THERMO-INSULATING LAYER FOR FLOOR WITH

EXPANDED POLYSTYRENE

026 2602797 MP. 25.250

PEX C EXPANDED POLYSTYRENE SLAB OF

2000X500X 100MM S7461

027 IZF03B2 MP. 25.000

BARRIER AGAINST VAPOURS ON VERTICAL

SURFACE WITH 1STR IMPISLIT BIT TYPE /A

SAU TSA2000 LIP WITH BITUM TYPE

027 2600048 KG 37.500

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

027 2602060 MP. 27.500

BIT.2F.NIS. TSA FIBER GLASS

2000 100CM S 10126

028 IZF02A1 MP. 25.000

ROOF VAPOUR DIFFUSION LAYER,TERRACCE

WITH GLASS FIBRE KNITTING HORISONTAL

SURFACE BITUMEN

028 2600048 KG 12.500

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

029 IZF01A1 MP. 25.000

SURFACE MILDING APPLY.VAPOURS DIFUSION

LAYER WITH CUT BITUMEN IN 2 LAYERS

HORIS.AND VERT.SURFACE

029 2600048 KG 3.750

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

030 IZF04J2 MP. 25.000

Page 67: ITB Constructii Noi Rev1

67

BOUNDARY LAYER RELATED TO THE INSULATION

WORK EXEC WITH FIBER GLASS FELTING

AND NON GLUED BREAKDOWN

030 2602060 MP. 27.000

BIT.2F.NIS. TSA FIBER GLASS

2000 100CM S 10126

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

- HEALTH

- OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: RESISTANCE SUPER-STRUCTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CA02J1 M.C. 18.000

MOULDING REINFOR.CONCRETE TO CONSTR.WITH

H<35M,IN FLOORS(BEAMS,COLUMNS,PLATES)

WITH SLAB THICKN.>10CM

001 2100957 M.C. 18.144

CEMENT CONCRETE B 200(C12/15) STAS 3622

002 CB13A1 MP. 116.000

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTRUCTIONS WITH H<20M TO SLABS AND

BEAMS,WITH PLYWOOD OF 8MM

Page 68: ITB Constructii Noi Rev1

68

003 CB13B1 MP. 25.000

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTR.WITH H<20M,AT COLUMNS AND FRAMES,

WITH PLYWOOD OF 8MM

004 CB44A1 BUC. 62.000

SUST.WITH STUDS EXTENS PER3100R FOR

ASSEMBLING FLOORS,PRESLAB TURN FLOORS

MONOL WITH GR OR GR MONOL PL PREFAB.

005 CB45B1 BUC. 31.000

SUSTAIN. FROM METALIC BEAMS EXTENSIBLE

TO CONSTR.WITH H<20M BEAMS SUPPORT.ON

METALIC STUDS

006 RPCH38A1 [ 2] BUC. 30.000

ROUND WOODEN PROP SUPPORT D= 12CM

AT LINTELS OVER DOOR AND WINDOW OPENINGS

007 CC01C1 KG 1610.000

CONCRETE STEEL REINFORCEMENTS ASSEMBLING

IN CONTINUOUS FOUNDATIONS,SLABS OF

PLATES,WITH DIST FROM PLASTICS

008 CZ0302A1 KG 275.000

MANUFAC. REINFORC. FOR WALLS BEAMS

COLUMNS DIAPHRAGMS TO REGULAR CONST IN

CENTRALIZED WORKSHOPS OB 37 D=6-

009 CZ0302E1 KG 590.000

MADE REINFORCED FOR WALLS BEAMS PILLARS

MIDRIFF AT BUILDG. REGULAR IN WORKSHOP

CENTRALIZED PC 52 D=10-

010 CZ0302M1 KG 55.000

MANUFCT. REINFORC. FOR PLATES INCLUD.

STAIRS TO REGULAR CONST. IN CENTRALIZED

WORKSHOPS OB 37 D=6-8MM

011 CZ0302O1 KG 690.000

MANUFCT.REINFORC.FOR PLATES INCLUD.

STAIRS TO REGULAR CONST.IN CENTRALIZED

WORKSHOPS PC 52 D= 6-8MM

012 CP12A1 BUC. 7.000

ASSEMBL.PREFAB.TO HOUSING WITH STRUCT.

MONOL.MIXED AND BRICKWORK.SUST.WITH.VOL.

0,2 MC.AND H<20 M

013 6433209 M.C. 0.300

CONCRETE PRECAST C16/20(B250) II A-

S32.5 0-16MM

014 6433376 KG 18.000

CONCRETE PREFABR.REINFOR. OB 37 D=6-10MM

STANDARD

015 6433754 KG 10.000

REINFOR.IN CONCRETE PREFABR. PC52 O6-10

MM STANDARD

Page 69: ITB Constructii Noi Rev1

69

016 6433754 KG 63.000

REINFOR.IN CONCRETE PREFABR. PC52 O6-10

MM STANDARD

017 AUT1301 ORA 5952.000

EXPANDING METAL GIRDER L=3-5M TYPE GE1 3

SHIFTS

018 AUT1325 ORA 11904.000

EXPANDING METAL PROP PE3100 INCLUDING

PIPE 051X3,5MM

019 TRA06A TONA 45.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. = KM

020 TRA02A TONA 1.610

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= KM.

021 AUT1140 ORA 30.000

TELESCOPIC JIB CRANE ON TYRES TELEMAC HT

125.5 TF 1 SHIFT

022 MDTC4623 BUC. 6.000

EQUIP.TRANSPORT 10 KM-65121002-TYRE

CRANE OF 0,10-0,149 MN(10-14,9TF

023 MDTC5575 BUC. 62.000

EQUIPMENT TRANSPORTATION 10 KM-90100106

EXTENSIBLE METALLIC BEAM WITHL=4-8M TYPE

CE-2

024 MDTC5552 BUC. 124.000

EQUIPMENT TRANSPORTATION 10 KM-90100079

METALLIC POP TYPE PE-3100

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

- HEALTH

- OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Page 70: ITB Constructii Noi Rev1

70

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: RESISTANCE INFRASTRUCTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSC18A1 100 MC. 0.140

BULDOZER DIGGING ON TRACTOR 65-80CP

INCL.EARTH PUSH. 10M CAT.1 LAND

002 TSA04B1 M.C. 27.500

MAN.DIGGING IN LIMITED SPACES UNDER 1M

SUPPORTS AND MAN.EVAC.IN SOIL WITH NAT.

HUMIDITY DEPTH.0,0-1,5M MEDIUM SOOL

003 TSC02D1 100 MC. 0.340

DIGGING WITH EXCAVATOR ON TYRES 0,21-0,

39 MC SOIL NATURAL MOISTURE OPEN AUT.

FILED CATEGORY 2

004 TSD01C1 M.C. 39.000

LOOSE SOIL SHOVEL SPREADING,UNIFORM

LAYER 10-30CM.THICK WITH BREAKBLE CLODS

HARD SOIL

005 TSD05A1 100 MC. 0.390

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

006 TRA01A05P TONA 66.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= 5 KM

007 TSC35B31 100 MC. 0.650

AUTOLOADER ON TYRES WITH BUCKET 2,6-3,9

CM LAND CATEG 2 AT DIST. 11-20 M

008 TSF01B1 MP. 73.000

BANKS SUPPORT BY BEECH BOARDS

HORIZ.LAID WIDTH<1.5M, DEPTH 0.0-

2M;0,21-0,6M BETWEEN BOARDS

009 CG32D1 [ 5] M.C. 8.000

FILLINGS IN LAYERS, EXECUTED BY

MECHANICALLY COMPACTED GRAVEL

Page 71: ITB Constructii Noi Rev1

71

010 CA01B1 M.C. 48.700

SIMPLE CONCRETE MOULDING IN FOUNDATIONS

(CONTINUOUS,ISOLATED)AND SOCLES WITH

VOLUME > 3MC,AND IN RETAINIG WALLS

010 2100945 M.C. 49.090

CEMENT CONCRETE B 150(C8/10) STAS 3622

011 CA01D1 M.C. 12.200

SIMPLE CONCRETE MOULDING IN LAYERS OF 3-

20CM THICKNESS AT CONSTRUCTIONS WITH H

<35M

011 2100945 M.C. 9.374

CEMENT CONCRETE B 150(C8/10) STAS 3622

012 2100957 M.C. 2.923

CEMENT CONCRETE B 200(C12/15) STAS 3622

013 CB11A1 MP. 186.000

SHUTTERINGS FOR CONCRETE IN ELEV.FROM

PANELS TO STRAIGHT WALL WITH H<3M,WITH

PLYWOOD OF 8MM THICK.

013 CC01C1 KG 710.000

CONCRETE STEEL REINFORCEMENTS ASSEMBLING

IN CONTINUOUS FOUNDATIONS,SLABS OF

PLATES,WITH DIST FROM PLASTICS

014 CZ0301A1 KG 340.000

MANUFAC.REINFOR.SHAPED BARS FOR

FOUNDATION ISOL.CONTINUOUS AND PLATES

IN.CENT.WORKSHOPS OB 37 D=6-8MM

015 CZ0301D1 KG 370.000

REINFORCED MANUFACTURED SHAPING BARS FOR

CONTINOUS ISOLATED FOUNDATION AND PLATE

FOUNDATION IN ATEL CENT.PC 52 D=6-8MM

016 TRA06A05 TONA 153.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

017 TRA02A05 TONA 0.710

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= 5 KM.

018 IZF10F1 [14] MP. 63.300

EXTRUDED POLYSTYRENE INSULATION

LAYER OF 100MM WITH = 0.03 W/MK > 35 KG

UNDER THE REINFORCED CONCRETE SLAB

019 IZF04J1 [ 1] MP. 81.000

BOUNDARY LAYER EXEC BY POLYETHYLENE

FOIL OF 0.2MM

Page 72: ITB Constructii Noi Rev1

72

020 CF12A1 [ 1] MP. 19.000

RIGID WATERPROOFING ON M100T WALLS WITH

APAPSTOP APPLIED IN 3 LAYERS ON HORIZ

SURFACES UNDER WALLS ACC. TO TECHNICAL

SPECIFICATIONS

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

List with work quantities

Estimate - Tender: REZISTENCE FRAMEWORK

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CE17B1 MP. 125.000

WOODEN FRAMEWORK FOR HEAVY COVERS

002 2900980 M.C. 5.500

FRAMEWORK SQUARED WOOD

003 7335349 ORA 38.000

TIMBER MANUFACT. AT CARPENTRY MACHINES

004 CE23A1 MP. 50.000

SAFETY NET REUSED FOR CONSTRUCTION

COVERS

Page 73: ITB Constructii Noi Rev1

73

005 CN15D1 MP. 35.000

PAINTING OF WOOD WORK WITH SPECIAL

SOLUTIONS,WITH ANTISEPTIC PAINTS,

WATERPROOF ON IMPREGNATE WOOD

006 6310159 KG 16.000

JOIN.FRAMEWORK ELEM.LIGHT METALIC

MANUFACT.

007 RPCR41B1 MP. 140.000

FIREPROOF WOODWORK ON PROTECTED SURFAC.

ANT.CONTR.INCE.*

008 CA02M1 M.C. 1.000

REINFOR. CONCRETE MOULDING FOR CONSTR

WITH H<35M IN ELEMENTS SHAPED ISOLATED

WITH VOLUME>0,5MC

008 2100957 M.C. 1.008

CEMENT CONCRETE B 200(C12/15) STAS 3622

009 CB13B1 MP. 8.500

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTR.WITH H<20M,AT COLUMNS AND FRAMES,

WITH PLYWOOD OF 8MM

010 CC02C1 KG 150.000

ASSEMBL.REINFOR.FOR CONSTR H<35M FROM

BARS IN BEAMS AND COLUMNS D<18MM PLATES

D<10MM WITH DIST FROM PLASTIC

011 CZ0302A1 KG 27.000

MANUFAC. REINFORC. FOR WALLS BEAMS

COLUMNS DIAPHRAGMS TO REGULAR CONST IN

CENTRALIZED WORKSHOPS OB 37 D=6-

012 CZ0302E1 KG 123.000

MADE REINFORCED FOR WALLS BEAMS PILLARS

MIDRIFF AT BUILDG. REGULAR IN WORKSHOP

CENTRALIZED PC 52 D=10-

013 TRA06A05 TONA 2.500

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

014 TRA02A05 TONA 0.200

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= 5 KM.

015 TRA02A10 TONA 2.750

ROAD TRANSPORT OF MATERIALS,SEMIFABS

WITH TRUCK ON DIST.= 10 KM.

016 CF12A1 [ 1] MP. 2.750

RIGID WATERPROOFING ON M100T WALLS WITH

APAPSTOP APPLIED IN 3 LAYERS ON HORIZ

SURFACES UNDER WALLS ACC. TO TECHNICAL

SPECIFICATIONS

Page 74: ITB Constructii Noi Rev1

74

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: PAVEMENT

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA01G1 M.C. 12.000

MAN. DIGGINGS IN SPREAD SPACES IN SOIL

WITH NAT.MOISTURE THROWED IN VEHICLE ATH

OF 0,61-2M HARD SOIL

002 TSC35B31 100 MC. 0.120

AUTOLOADER ON TYRES WITH BUCKET 2,6-3,9

CM LAND CATEG 2 AT DIST. 11-20 M

003 TRA01A05P TONA 22.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= 5 KM

004 TSE06B1 100 MP. 0.600

SOIL PLATF.PREPARING ISOLATING LAYER AND

SAND REPARTION OR GRAVEL IN COHESIVE

SOIL

Page 75: ITB Constructii Noi Rev1

75

005 DA06A1 M.C. 9.000

NAT.AGREGG.LAYER(GRAVEL)ROLLED OVER WITH

FILTRING RESISTANCE FUNCTION ISOL.AERING

ANTICAP.MANUAL LAYING

006 TRA01A05 TONA 9.000

MATERIAL,SEMIPREFAB ROAD TRANSPORT BY

TIP LORRY ON A 5 KM DIST.

007 DD02A1 MP. 60.000

PAVMENT MADE OF NORM PAVING 1ST Q. ON

SAND SUB BASE

008 TRA01A05 TONA 12.000

MATERIAL,SEMIPREFAB ROAD TRANSPORT BY

TIP LORRY ON A 5 KM DIST.

009 DE11A1 M 70.000

SMALL CRIMPS MANUF.CONCRETE 10X15 CM FOR

FRAMING SPACES WALK ROAD ,GREEN ALLEY

FOUND. CONCRETE10 X 20 C

009 2100933 M.C. 1.400

CEMENT CONCRETE B 100(C6/7.5) STAS 3622

010 TRA06A05 TONA 5.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

Page 76: ITB Constructii Noi Rev1

76

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

LOT NO. 3 Family House Zoltan Florina

QUANTITY LIST WITH TECHNOLOGICAL EQUIPMENT, INCLUDING UTILITIES OF THE ESTIMATE-OFFER FOR PROCUREMENT

Item Name M.U. Quantity Unitary Price

-lei/M.U.-

Amount (VAT

exclusive)

-Thousand lei-

(col.3 x 4)

Supplier

(name,

address,teleph

one, facsimile)

0 1 2 3 4 5 6

1 Water meter Qn=1.5 cubic

meters/h

pcs 1

2 Ecological tank for waste water, capacity 10 cubic

meters

pcs 1

3 Electric Boiler 10l pcs 1

Thousand lei: TOTAL

USD*):

*) Exchange rate =…………………. Lei/USD, of …………………….

TECHNICAL SHEET No. 1

EQUIPMENT: WATER METER Qn=1.5 cubic meters/h

Item Technical specifications imposed by the Technical Specifications

Comparison between the technical proposal and

the specifications

Supplier

Page 77: ITB Constructii Noi Rev1

77

imposed by the

Technical Specifications

0 1 2 3

1. Technical and Functional Parameters: -Type: multi-jet, and dry dial -Nominal output: 1.5 mc/h

-Nominal diameter: 20 mm - Connection sizing: 3/4˝ -Connection type: coupling

-Design pressure Pn 6 bars

2. Performance specs and conditions related to safety in exploitation:

- To be granted a Technical Agreement or an homologation document;

- The Technical Book shall be presented in

Romanian wording.

3. Conditions related to compliance with relevant standards:

-Accuracy category: B

4. Guarantee and post-guarantee conditions: -3 years guarantee

- 3 days for solving out issues occurred during the guarantee period

5. Other condition of technical character:

TECHNICAL SHEET No. 2

EQUIPMENT: ECOLOGICAL TANK FOR WASTE WATER

Item Technical specifications imposed by the Technical

Specifications

Comparison between the

technical proposal and the specifications imposed by

the Technical

Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters: -Material: polyester

-Net volume: 10 cubic meters -Diameter: 1.8 linear meters -Length: 4.15 linear meters -Installing: buried

2. Performance specs and conditions related to safety in exploitation:

• To be granted a Technical Agreement or an homologation document;

3. Conditions related to compliance with relevant standards: -SR EN 12566-1

4. Guarantee and post-guarantee conditions: - 3 years guarantee.

5. Other condition of technical character:

Minimum life cycle: 30 years

Page 78: ITB Constructii Noi Rev1

78

TECHNICAL SHEET No . 3 EQUIPMENT: ELECTRIC BOILER

Item Technical specifications imposed by the Technical

Specifications

Comparison between the

technical proposal and the specifications imposed by the

Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• Hot water 800C

• Capacity 10l

• Sizes: 360x254x360

• Maximum pressure: Pn 10 bar

• Wasteful resistance power: 1.2 kW

• Power supply: 220 V

2. Performance specs and conditions related to safety

in exploitation: -Inside the boiler’s surface is covered by a special enamel layer;

-It is fitted out by a programmable thermostat, magnesium anode, insulation, relief pressure valve, “on-off” switch.

3. Performance specs and conditions related to safety

in exploitation:

• To be granted a Technical Agreement or an homologation document;

• The Technical Book shall be presented in

Romanian wording.

4. Guarantee and post-guarantee conditions:

• 3 days for solving out issues occurred during the guarantee period;

• 10 days for providing spare parts in the post-guarantee period.

5. Other condition of technical character

Bill of quantities

Estimate - Tender: ELECTRIC INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 EA02A1 [ 2] M 170.000

PROTECTION INSULATION TUBE,IPEY SEALED

RECESSED WITH D=16/13,4MM

002 EA02A3 [ 2] M 8.000

PROTECTION INSULATION TUBE,IPEY SEALED

RECESSED WITH D=25,8/21,8 MM

003 EA12A1 M 20.000

METALLIC,FLEXIBILE,PROTECTION,UNTIGHT

TUBE, WITH 2 ROWS OF COILS IN

QUADRILATERAL-SHAPE(SPD) 13,5-23 MM

003 7356501 M 20.500

Page 79: ITB Constructii Noi Rev1

79

METALIC TUBE FLEX.PROT.NONTIGHT TYPE SPD

-ROMAN D=13,5 MM

004 EB02A1 M 280.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION < 4 MMP

004 4826880 M 288.400

CONDUCTOR FY 1X 1,5 S 6865

005 EB02A1 M 340.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION < 4 MMP

005 4826892 M 350.200

CONDUCTOR FY 1X 2,5 S 6865

006 EB02B1 M 30.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION 6- 10 MMP

006 4826919 M 30.900

CONDUCTOR FY 1X 6 S 6865

007 ED01A1 BUC. 4.000

MANUAL SWITCH BURIED UNIPOLAR NORMAL OR

WATERPROOF CONSTRUCTION *

007 5500720 BUC. 4.040

CUMPANA SWITCH ST.250V 10A

008 ED03A1 BUC. 5.000

UNIPOLAR SWITCH BURIED,WOODEN NAILS,IN

SERIES,NORM.CONSTR.OF BACHELITA OR

WATERPROOF CONSTR.

008 5520366 BUC. 5.050

CUMPANA SHIFTER ST.250V 10A

009 ED08A1 BUC. 1.000

PLUG BURIED ASSEM.NORMAL CONSTR.

WATERPROOF OR NORMAL PROTECTION CONTACT

009 5536156 BUC. 1.010

BIPOLAR PLUG PROT.PANEL 250/10A RECESSED

010 ED08B1 [ 1] BUC. 9.000

DOUBLE TWIN PLUG WITH PROTECTION

CONTACT RECESSED MOUNTED

Page 80: ITB Constructii Noi Rev1

80

010 5535994 BUC. 9.090

DOUBLE BIPOL.PLUG,PROT.CONTACT 250/10A

RECESSED

011 ED01D1 BUC. 1.000

MANUAL SWITCH WOODEN NAILS IN UNIPOLAR

NORMAL CONSTR. MADE OF BACHELITE OR

TIGHT CONSTR.

011 5500677 BUC. 1.010

VISIBLY SET MANUAL SHIFTER 250V 10A

012 ED10A1 [ 1] BUC. 1.000

BELL BUTTON 10A 250V

013 EE04A1 BUC. 2.000

SIMPLE LUMINAIRE (LAMP HOLDER) REGULAR,

WITH NAIL AND RING

014 EE05A1 BUC. 3.000

SIMPLE APPLY ,OBL./RIGHT.GLOB ST.OPAL.

MONT.CEILING./WALLS ON WOOD DOWEL

014 5104071 BUC. 3.036

WALL BRACKET E27,OBLIQUE,60W,BOWL

015 EE08A1 [ 1] BUC. 1.000

CHANDELIER INCANDENSCENCE BULBS WITH 1

ARM

015 5105311 BUC. 1.003

INCANDENSCENCE BULBS 1 ARM CHANDELIER

016 EE08A1 BUC. 2.000

CHANDELIER INCANDENSCENCE BULBS WITH 2

ARMS

016 5105312 BUC. 2.006

INCANDENSCENCE BULBS 1 ARM CHANDELIER

017 EE08B1 BUC. 1.000

CHANDELIER INCANDENSCENCE BULBS WITH 3

ARMS

017 5105300 BUC. 1.003

INCANDENSCENCE BULBS 3 ARMS CHANDELIER

018 EE12B1 BUC. 1.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

018 5103611 BUC. 1.003

Page 81: ITB Constructii Noi Rev1

81

FLUOR.LUMINAIRE FIA 11-2X36 W EQUIPPED,

APPARENT ASSEM.

019 EE12B1 BUC. 2.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

019 5103823 BUC. 2.006

FLUORESCENT LIGHT FIXTURES AB 02-1X18 W

VISIBLY SET

020 EE14A1 BUC. 2.000

ASSEM.LAMP INSIDE.CONSTR.OR ON EXTER.

ELEMENTS INCANDESCENCE UP TO 1000 W.

020 5101029 BUC. 2.100

INCANDESCENTE LAMP CLEAR E27 TIP S 220V

25W S6115

021 EE14A1 BUC. 11.000

ASSEM.LAMP INSIDE.CONSTR.OR ON EXTER.

ELEMENTS INCANDESCENCE UP TO 1000 W.

021 5101251 BUC. 11.550

INCANDES LAMP DOUBLE SPIR.CLEAR E27 AM

220V 60W CS

022 EF05D1 [ 1] BUC. 1.000

PANEL WITH PROTECTION CUT-OUT AND

DIFER.FAULT CURRENT DEVICE +

BELL AND SWITCH

022 7305451 BUC. 1.000

PANEL WITH 4 PROTECTION CUT-OUTS

PHASE-NULL(1x 6A+2x16A+1x16A WITH DIFFER.

PROT.DIVICE Id=30mA) BELL AND SWITCH

023 EF09A1 BUC. 6.000

COUPLING COPPER PIPE AT DEVICES BORNS ,

MOTORS,ELECTR.COUNTER COND.HAVING SECT.

<10SQMM,EXCLUSIVELY

024 EG08B1 M 10.000

COND.EARTH CONNECTION LIGHTING ROD

UNDERGROUND EARTH CONN.GALVANIZED STEEL

STRIP 40X4MM IN HARD SOIL *

025 W1R06A1 M 3.000

ELECTRODE OF STEEL PIPE OF TWO AND

A HALF INCHES FOR EARTH GROUNDING

IN NORMAL GROUND

026 W1P08A BUC. 1.000

Page 82: ITB Constructii Noi Rev1

82

EARTH CONN.TESTING FOR BUILDING WIRING

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: SANITARY INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 SA04B1 M 18.000

STEEL PIPE LONGIT.WELDED GALVAN.INSTAL.

THREAD+COUPLING SET HOUSES+SOC.CULT.

CONNECTIONS D= 1/2I

001 3306625 M 18.180

ZINCKED INSTLL. PIPE THREAD+COUPLING

M - 15( 1/2) OL 32 1 S 7656

002 SA04C1 M 24.000

STEEL PIPE LONGIT.WELDED FOR ZINCKED

INSTAL.WITH THREAD+COUPLING ASSEM.LOC.+

CULT.IN LEGATURI D= 3/4T

002 3306649 M 24.240

ZINCKED INSTLL. PIPE THREAD+COUPLING

M - 20( 3/4) OL 32 1 S 7656

003 SA43C1 BUC. 10.000

CLAMP STEEL PIPE FIXING+PVC WATER+GAS

Page 83: ITB Constructii Noi Rev1

83

SUPPLY,TOOTHING SET,PIPE HAVING D= 1/2

INCHES

004 SA43D1 BUC. 10.000

CLAMP STEEL PIPE FIXING+PVC WATER+GAS

SUPPLY,TOOTHING SET,PIPE HAVING D= 3/4

INCHES

005 SA46A1 BUC. 6.000

MANUF.ASSEM.AND CEMENTATION OF

PROTECTION PIPE PASSING PIPE THROUGH

WALL,PIPE HAVING D=1 INCHES

006 SA46B1 BUC. 4.000

MANUFACT,SET AND ASSEMBLY OF PIPE

PROTECTION AT PASSING OF PIPES THROUGH

WALL,PIPE HAVING D=1 1/4 INCHES

007 SA46D1 BUC. 2.000

MANUFACT,SET AND ASSEMBLY OF PIPE

PROTECTION AT PASSING OF PIPES THROUGH

WALL,PIPE HAVING D=2 INCHES

008 SB16A1 [ 1] M 6.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 32 MM

009 SB16B1 [ 1] M 4.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 40 MM

010 SB16C1 [ 1] M 12.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 50 MM

011 SB16E1 [ 1] M 14.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D=110 MM

012 SB17A1 [ 1] BUC. 6.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D= 32MM

012 6712226 BUC. 6.000

@HTB POLYPROPYLENE ELBOW AT 45 DGR DN 32

CODE 62504011

013 SB17C1 [ 1] BUC. 6.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D= 50MM

013 6712243 BUC. 6.000

Page 84: ITB Constructii Noi Rev1

84

@HTB POLYPROPYLENE ELBOW AT 45 DGR DN 50

COD 62504029

014 SB17E1 [ 1] BUC. 10.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D=110 MM

014 6712408 BUC. 6.000

@POLYPROPILENE ELBOW HTD LA 87GR 30MIN

DN 110 COD 62504059

014 6712264 BUC. 4.000

@HTD POLYPROPYLENE ELBOW AT 45 DGR DN

110 COD 62504053

015 SB19A1 [ 5] BUC. 2.000

FIREPROOF POLYPROP. SIMPLE LOW BRANCH

RUBBER SEAL JOINING D=50/40 MM

015 6712811 BUC. 2.000

@HTEA POLIPROP REDUCED BRANCK 45GR DN50/

40 COD 62510007

016 SB19C1 [ 2] BUC. 2.000

FIREPROOF POLYPROP. SIMPLE LOW BRANCH

RUBBER SEAL JOINING D=110/ 50 MM

016 6712848 BUC. 2.000

@HTEA POLIPROP SIMPLE REDUCED BRANCH 45

DGR DN110/50 COD 62510031

017 SB19C1 [ 1] BUC. 2.000

SEWAGE FIREPROOF POLYPROP.SIMPLE UNIFORM

BRANCH RUBBER SEAL JOINING D=110 MM

017 6712862 BUC. 2.000

@HTEA POLIPROP SIMPLE EQUAL BRANCH 45

DGR DN 110 COD 62508025

018 SB21C1 [ 1] BUC. 2.000

SEWAGE FIREPROOF POLYPROP.INTERVENTION

PART RUBBER SEAL JOINING D=110 MM

019 SB22A1 [ 1] BUC. 2.000

SEWAGE FIREPROOF POLYPROP.REDUCING PIECE

RUBBER SEAL JOINING DN 40- 32 MM

020 SB22B1 [ 1] BUC. 2.000

FIREPROOF POLYPROP.REDUCING COUPLING FOR

SEWERAGE RUBBER SEAL DN 50- 32 MM

Page 85: ITB Constructii Noi Rev1

85

021 SB22E1 [ 1] BUC. 1.000

FIREPROOF POLYPROP.REDUCING COUPLING FOR

SEWERAGE RUBBER SEAL D=110- 50 MM

022 SB44C2 [ 1] BUC. 2.000

HDPE GULLY TRAP D= 50 MM WITH 1

CONNECTION AND VERTICAL EXIT

023 SB49A3 [ 1] BUC. 2.000

FIREPROOF POLYPROP.PIPES VENT CAP D=110

MM

024 SC01D3 [ 2] BUC. 1.000

FIBRE GLASS BATH TUB FLAT BOTTOM

IST Q. WHITE WITH L=1700MM

025 SC07E1 [ 1] BUC. 2.000

SANIT.PORCELAIN LAVATORY L2 600 ON STAND

INCLD.FLOOR TRAP AND DELIVERY VALVE

026 SC10A1 BUC. 1.000

DISH WASHER OF ENAMEL COATING CAST IRON

WITH SUPPORT SET BY WOODEN DOWELS ON WALL

027 SC13B1 BUC. 2.000

SANITARY PORCELAIN WATER CLOSET WITH

SIPHON TRAP P COL2-A TYPE WHITE

PORCELAIN C.1

027 2442757 BUC. 2.020

WATER CLOSET COL2-A WHITE PORCELAIN C.1

S 2066

028 SC16D1 [ 1] BUC. 2.000

RESERVOIR FOR WASHING WC BASIN FROM

POLYPROPYLENE SET MIDHEIGHT ON

BRICK WALL

029 SC18A5 BUC. 2.000

WC BASIN FRAME,OF POLYPROPYLENE WITH LID

030 SC25A1 BUC. 2.000

SANITARY PORCELAIN SHELF TYPE

030 2451849 BUC. 2.020

PORCELAIN SHELF TYPE E2.60 WHITE Q.1 NI

567

031 SC24A1 BUC. 2.000

BRASS TOWEL SUPPORT MOUNTED ON WALLS

Page 86: ITB Constructii Noi Rev1

86

TYPE U,WITH 1 ARM, OPENING 450MM

032 SC26A2 BUC. 2.000

SEMICRYST.SANIT.MIRROR POLISH.EDGES

SIZES 500X600MM

033 SC28B1 BUC. 1.000

SANITARY PORCELAIN SOAP BOX

SA2-15 TYPE,VISIBLE,SIMPLE

034 SC29A1 BUC. 2.000

LAUNDRY HANGER OF ENAMELLED CAST IRON ,

SANITARY PORCELAIN OR PLASTIC MATERIAL

TYPE

034 6719536 BUC. 2.000

BATHROOM PEG AMINOPLAST 3 HANGERS NI

2199

035 SC30A1 BUC. 2.000

SANITARY PORCELAIN 1 Q. PAPER HOLDER,HA1

NI 545/63

036 SC34A1 BUC. 1.000

BOILER WITH PRESSURE BREAKING VESSEL

CAPACITY 100L

037 SD03A1 BUC. 1.000

BATH MIXING BATTERY,WITH FLEXIBLE

SHOWER,OF 1/2 INCH TYPE...ASSEM. WITH

WOODEN DOWELS ON BRICKWALL

037 4201523 BUC. 1.000

BRASS MIXER BATTERY FLEXIBLE TUBE PEAR

SHOWER A 1/2 NI 4309

038 SD06A1 BUC. 2.000

LAVATORY COCK SYSTEM D=1/2"

038 4201341 BUC. 2.000

BATH MIXING BATTERY CAST IRON WASH BASIN

1/2" ENAMEL S8732

039 SD06A1 [ 1] BUC. 1.000

LAVATORY COCK SYSTEM FOR WASHER D=1/2"

039 4201444 BUC. 1.000

BATH MIXING BATTERY CAST IRON WASH BASIN

ENAMEL 1/2" S8732

040 SD12A1 BUC. 6.000

CORNER ADJUSTMENT FAUCET,OF NICHELLED

Page 87: ITB Constructii Noi Rev1

87

BRASS,HAVING D=3/8 OR D=1/2 INCHES

040 4201779 BUC. 6.000

NICKEL PLATED GRASS ANGLE CONTROL COCK 1

/2 " S 751/I

041 SA21A1 [ 1] BUC. 6.000

FLEXIBLE REINFORCED RUBBER CONNECTION 1/

2"X1/2"

042 SD13A1 [ 1] BUC. 2.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

042 7344032 BUC. 2.000

SPHERE TAP FI X FE "MINI" DN 1/2" CODE

40MI4272

043 SA21B1 [ 1] BUC. 2.000

FLEXIBLE REINFORCED RUBBER CONNECTION

1/2"X 3/8"

044 SD13A1 [ 1] BUC. 2.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

044 7344045 BUC. 2.000

@SPHERE FAUCET EVAC+LID+PORTHOSE DN 1/2"

CODE 40814762

045 SD13A1 [ 1] BUC. 2.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

045 7344030 BUC. 2.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 1/2" CODE 40430425

046 SD13B1 [ 1] BUC. 5.000

SPHERE FAUCET WITH COUPLING,FOR STEEL

PIPES D=3/4''

046 7344059 BUC. 5.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

047 SE48A1 [ 1] BUC. 1.000

WATER ELECTRICAL HEATER,10L CAPACITY

Page 88: ITB Constructii Noi Rev1

88

048 SF01A1 M 42.000

TIGHTENESS TEST AT PRES. OF INST. INTER.

OF WATER,IN PIPES STEEL ZN. OR LEAD

PRES. INCLUDING REINFORCED

049 SF04A1 [ 1] M 42.000

WATER PIPES CLEANING AND PUTTING

INTO OPERATION

050 CN13A1 M 42.000

INSTALLATIONS REGULAR PAINTINGS WITH OIL

PAINT ON PIPES EXT.D<34MM INCLUDED

050 6103220 KG 0.714

WHITE PAINT (FP) V.101-1 NTR 90-80

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: WATER AND SEWAGE SERVICES

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA02F1 M.C. 86.000

MAN.DIGGIN.IN LIMIT.SPACES UNDER 1M WITH

R.O.W.VERT.UNSUPPORT.IN SOIL AVER.COHEZ.

AND VERY COHEZ.DEPTH<1,5M HARD S.

Page 89: ITB Constructii Noi Rev1

89

002 TSA12C1 M.C. 9.000

MAN.DIGG.IN EXCAVATIONS 1-1,5M WIDE WITH

SUPP.MAN.EVAC.IN SOIL WITH NAT.MOIST AT

DEPTH 0,0-1,5M,HARD SOIL

003 TSC02B1 100 MC. 0.480

DIGGING WITH TYRE EXCAVAT.0,21-0,

39 MC NAT.MOIST.DISCHARGE GROUND

CAT.2

004 TSA18E2 M.C. 4.500

MAN.EXCAV. FOLLOWING MECHANICAL EXCAVATION

HOLES.FOUND. ELEM.NAT.MOIST.SOIL WITH

SUPPORT DEPTH< 4 M HARD SOIL

005 TSF01A1 MP. 88.000

SUPPORT.BY EDGES WITH BEECH SUPPRT.

PLACED HORIZ.EDG.BETWEEN <1,5M,DEEP.0,0-

2M,0,0 -0,2M BETWEEN EDGE

006 TSD01C1 M.C. 90.000

LOOSE SOIL SHOVEL SPREADING,UNIFORM

LAYER 10-30CM.THICK WITH BREAKBLE CLODS

HARD SOIL

007 TSD05A1 100 MC. 0.900

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

008 ACA10A1 [ 2] M 62.000

UNDERGROUND SETTING AT WATER SUPPLY HDPE

PIPES JOINED WITH FITTINGS THROUGH

COMPRESSION,WITH DN 20-25 MM

008 6701146 M 63.240

@TV HDPE80 312UNI7611.7615 PN10 DN

25X2.3 COD 64000109

009 ACA17A2 BUC. 2.000

POLYETHILEN CONNECTION PIECES JOINED BY

COMPRESSION FOR HDPE WATER SUPPLY PIPES

009 6790049 BUC. 2.000

@FEMALE QUICK JOINING HDPE80 DN25X1"

COD WAVIN 704026

010 SB16C1 [ 1] M 6.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 50 MM

011 ACA12A1 [ 2] M 44.000

INSTALLING PVC PIPE IN GROUND 100

COMPACT SN 4 FOR EXTERIOR SEWAGE

RUBBER TIGTH ELASTOM.RING D=110 MM

012 ACA17A1 [ 2] BUC. 4.000

PVC CONNECTING PIECE WITH WEIGTH PER

Page 90: ITB Constructii Noi Rev1

90

PIECE UP TO10 KG INCLUDING

012 6712233 BUC. 4.000

@ PVC-U ELBOW PIPEKGB 45 GR DN 110

013 SD13A1 [ 1] BUC. 1.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

013 7344045 BUC. 1.000

@SPHERE FAUCET EVAC+LID+PORTHOSE DN 1/2"

CODE 40814762

014 SD13B1 [ 1] BUC. 2.000

SPHERE FAUCET WITH COUPLING,FOR STEEL

PIPES D=3/4''

014 7344059 BUC. 2.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

015 ACE12B1 BUC. 1.000

WATER METER SETTING WITH BLADES OF D 20

MM

016 M1A01B1 [ 1] BUC. 1.000

INSTALLING WASTE WATER ECOLOGICAL TANK

017 ACD01J1 BUC. 4.000

STAS 2308-81 FRAME AND CAP FOR SEWERS

WITH CARRIAGEWAY SUPPORT PIECE III A

TYPE

018 ACD09G1 BUC. 1.000

CONCRETE MANHOLES SET SECT. CIRC. PR.TIP

1785-2 DI 1,5 M. H 1,5 WITHOUT

UNDERGROUND WATER CARRIAGEWAY

019 ACD04A1 [ 3] BUC. 3.000

MANHOLE STAS 2448-73 WITH INSPECTING

CHAMBER HC=1M OF CONCRETE PIPE WITH LIP AND NOSE

FOR SEWERS WITH DN 110

019 2101195 M.C. 0.114

MORTAR M100 T WITH LIME HYDRATING

019 2100933 M.C. 3.030

CEMENT CONCRETE B 100 (C6/7,5) STAS 3622

020 ACD07A1 M 1.000

ELEMENTS AT MANHOLES STAS WITH H>2 M

INCLUDES: CONCRETE TUBE ACCESS DN 800 L=

1 M WITH FANCET AND OPENING

Page 91: ITB Constructii Noi Rev1

91

020 2101183 M.C. 0.019

MANSONRY MORTAR M 100 S 1030

021 ACD03A1 M 2.500

STRINGER LADDED OL 50X10 AND STEPS

OB D=20MM ACCESS IN SEWERS OF CONCRETE

PIPES

022 ACE05A1 [ 1] BUC. 8.000

PVC PIECE FOR PIPING TIGHT PASSAGE

THROUGH CONCRETE SEWERS WALLS

022 6311601 BUC. 2.000

@PASSAGE THROUGH PIECE INCLUDED IN PVC

32 MM WITH WATERPROOFING

022 6311607 BUC. 6.000

@PASSAGE THROUGH PIECE INCLUDED IN PVC

110 MM WITH WATERPROOFING

023 ACE07A1 100 M. 0.620

WATER PIPES WASHING AND DESINFECTION

WITH DN 50

024 ACE08A1 M.C. 34.000

DITCH FILLING FOR WATER PIPE SUPPLY AND

SEWERAGE WITH: SAND

025 W2H07A1 [ 1] M 62.000

POLYETHYLENE WARNING STRIP

025 TRA01A05 TONA 68.000

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH DUMP TRUCK DISTANCE= 5 KM

026 TRA01A05P TONA 96.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= 5 KM

027 TRI1AA03C2 TONA 96.000

MATERIAL LOADING,GROUP A-HEAVY IN DUST,

BY THROWING FROM PLATFORMS OR SOIL-CAR

CATEG.2

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Page 92: ITB Constructii Noi Rev1

92

Details transports:

- Items TRA

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: VARIABLE ARCHITECTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 21.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1304 ORA 162.000

SELF-LIFTING METALIC SCAFFOLD 2 CASTLES

6MARCH 75KG/M H-31M L=12M 3SHIFTS

003 CI02A1 [10] MP. 21.000

NATURAL LOCAL STONE PLATING

INCL. MESH

003 2202200 SQ.M. 21.420

BANPOTOC 1 QUALITY G=2CM S LIMESTONE SLAB

6035

004 CG06C1 MP. 6.500

MOSAIC FLOOR CAST ON SITE OF 1,5CM

THICKNESS SIMPLE WITHOUT CRIMP ON

SURFACE <5MP WITH MARBLE MOSAIC

005 CH01B1 M 11.500

PLATED SIMPLE CONCRETE TREADS WITH

PREFAB.TREADS AND RISERS WITH MARBLE

MOSAIC

Page 93: ITB Constructii Noi Rev1

93

005 2802892 M 11.845

MANUFACT.MARBLE STAIR CASE NAT.COLOUR

005 2802957 M 11.845

MARBLE MOSAIC RISER NATURAL COLOUR

006 CE14A1 M 6.000

GALVANIZED PLATE RAIN PIPE OF 0,5MM MADE

ON SITE SEMIROUND WITH D= 15,4CM

007 CF06A1 MP. 21.000

EXTER.REGULAR PLASTER,FLOATED FOR

DRYWALLS OR INTERIORS IN GARRET,OF 2 CM

007 2101203 M.C. 0.462

PLASTER MORTAR M25T

008 CG07B1 M 8.000

MOSAIC PLINTHS OR GORGES CAST ON SITE

SITE-HORISONTAL PLINTHS H=10CM AT MARBLE

MOSAIC WALLS

009 CH04A1 M 6.000

CURRENT WOODEN HANDRAIL

009 2948144 M 6.300

OAK WOOD HANDRAIL PRECAST SECT. 40X80 MM

010 CL20B1 KG 52.000

APPARENT METALLIC MANUFACT. ASSEMBLYING:

GRATES BANISTERS,TRAP DOOR,CHECKS, GRILL

010 6306274 KG 52.000

SIMPL.DECORATIVE LATTICE WORK FOR

STAIRCASES,PROFILED STEEL BALCONY

011 CN11B1 MP. 5.500

DYE WORKS AT BANISTERS,GRID,METALLIC

PARAPET WITH ALCHIDICAL ENAMEL

011 6108347 KG 0.385

REDISH BROWN ENAMEL UIC E.735-8 NTR 1703

-80

011 6100943 KG 0.440

ALCHID RED OXID PLASTER ROUGH G 735-3

012 CN09G1 MP. 18.000

PAINTINGS ON WOOD CARPENTERY ,DONE WITH

2 LAYERS ALCHIDIC LAQUER COLORLESS,AT

DOORS,WINDOWS ,SHUTTER.RUL.

013 CO02B1 MP. 30.000

CONCRETE PLATES WALK SIDE FOR SAND

PAVEMENTS,JOINTS FILLED WITH MASTIC

013 2800488 MP. 30.600

CONCRETE MANUFACT. FLAGSTONE 70X70X8CM

014 IZF10F1 [ 3] MP. 21.000

50MM EXTRUDED POLYSTYRENE LAYER TO

Page 94: ITB Constructii Noi Rev1

94

EXTERIOR WALLS GLUED BY BITUMINOUS CEMENT

015 RPCO56A1 [ 3] M 18.000

OAK WOOD BANISTERS AT PLATFORMS WITH

SIZES OF 30 X 125MM AT 3 ROWS

016 CH01D1 M 9.000

SIMPLE CONCRETE TREADS TITIVATED OR

ROLLED WITH CEMENT MORTAR M100-T

CAREFULLY FINISHED

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

- HEALTH

- OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

BILL OF QUANTITIES

Estimate - Tender: CONSTANT ARCHITECTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 132.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1302 ORA 390.000

METAL AUTO-LIFTING SCAFFOLD 3 CAST. 3.

5TF H=31M L=29M 3 SHIFTS

003 MDTC5517010 BUC. 2.000

EQUIPMENT TRANSPORT 10 KM 90100043

SELF-LIFTING METALLIC SCAFFOLDING WITH 2

Page 95: ITB Constructii Noi Rev1

95

CASTLES

004 CD04E1 M.C. 0.100

MASONRY FROM PRESSED BRICK 240X115X63MM

AT BATHROOM TUB CLOSING, CAL.1

005 CD04C1 M.C. 2.000

RESSED BRICK MASONRY 240X115X63MM AT

INSULATED CHIMNEY STACKS IN GARRET,QAL.1

005 2101171 M.C. 0.340

MASONRY MORTAR M 50 S 1030

006 CD05A1 M.C. 32.000

BRICK MASONRY TYPE GVP AT BUILDINGS H

<35M, SHAPE 240X115X 88MM,Q.A

006 2101169 M.C. 6.720

MASONRY MORTAR M 25 S 1030

007 CD04H1 M.C. 6.000

MASONRY FROM PRESSED BRICK 240X115X63M M

AT BUILDING.H<35M, 12,5CM THICKNESS, Q.

A,WITH VOIDS <50 %

007 2101169 M.C. 1.080

MASONRY MORTAR M 25 S 1030

008 CE15B2 [ 1] M 8.000

ALUMINIM WINDOW BOARDS

009 CF01K1 MP. 246.000

FLOATED INT.PLASTERS,AT COLUMNS,WALLS

WITH SPRINKLER AND PLASTER ROUGH CAST

MECHANICALLY PERFORMED,OF 2CM

009 2101202 M.C. 4.428

PLASTER MORTAR M10T

010 CF06K1 MP. 123.000

FLOATED EXTERNAL PLASTER ON BRICK AND

BLOCKS WALLS WITH CRUND.MECH.LAYER VIZ.

MANUALLY MORTAR M25-T THICK.2,5 CM

010 2101204 M.C. 2.829

MORTAR M50T

011 CF06C1 [ 6] MP. 123.000

OUTER DECORATIVE PLASTER OR

SIMILAR

012 CF10C1 MP. 316.000

Page 96: ITB Constructii Noi Rev1

96

PLASTER POLISHING APPLIED ON FLOATED

INTERIOR PLASTERS

013 CG01E1 [ 5] MP. 70.000

CEMENT SLAB FINISH FOR FLOORS

014 RPCK07D1 MP. 52.000

RESINOUS WOODEN FLOORING OF 24MM

THICK. NAILED ON OAK LATHS OF

50X80MM

015 CG06C1 MP. 9.500

MOSAIC FLOOR CAST ON SITE OF 1,5CM

THICKNESS SIMPLE WITHOUT CRIMP ON

SURFACE <5MP WITH MARBLE MOSAIC

016 CG06D1 MP. 8.500

MOSAIC FLOOR POURED ON SITE OF 1,5CM

THICK.SIMPLE WITHOUT CRIMP ON SURF.>5MP

WITH MARBLE MOSAIC

017 CG07B1 M 37.500

MOSAIC PLINTHS OR GORGES CAST ON SITE

SITE-HORISONTAL PLINTHS H=10CM AT MARBLE

MOSAIC WALLS

018 CG28B1 MP. 70.000

5MM DIFFERENCE SUPP.LAYER FOR CEMENT

MORTAR FLOOR

018 2101200 M.C. 0.350

PLASTER MORTAR M 100 (LIME PASTE ) S

1030

019 CG26A1 MP. 18.000

POLISHING,INCLUDING MARBLE OR MARBLE

MOSAIC GRAVEL WAXING FLOORS

020 CG26B1 M 37.500

POLISHING INCLUDING PLINTH AND GORGES

WAXING

021 CN04D1 MP. 44.000

DYE WORKS FOR INTERIOR AND EXTERIOR

MANUALLY EXEC.WITH OIL PAINTS

IN 2 LAYERS ON SMOOTH PLASTERS

021 6103309 KG 10.648

CREAM PAINT (FP) V.401-1 NTR 90-80

022 CK11G1 [ 3] MP. 11.000

PVC DOUBLED-GLASSED WINDOWS

023 CK14A1 [ 2] MP. 5.300

WHITE COLOR PVC DOORS WITH THERMO

INSULATING GLASS 4+ 16+4MM

Page 97: ITB Constructii Noi Rev1

97

024 CK03A1 MP. 9.800

INTERIOR SIMPLE WOOD DOORS ONE LEAF ON

LINING

024 2933300 MP. 9.800

ONE LEAF TIMBER DOOR ON

LINING FINISHED BY

MANUFACTURER

025 CK03C1 MP. 3.300

INTERNAL SIMPLE WOOD DOORS IN 2 LEAFS ON

LINING

025 2932150 MP. 3.300

2 LEAFS WOOD DOORS ON LININGS PAINTED AT

PRODUCER

026 CK25C1 BUC. 2.000

CARPENTRY ACCESSORY WORKS APPLIED LOCK

TO A YALE SYSTEM

026 6310380 BUC. 2.000

SAFETY LOCK IN YALLE

SYSTEM WITH DOOR BOLT

027 CK08A1 MP. 0.350

EXTRA DIFFERENCE AT LINING FOR DOORS

WIDER THAN 19,5 CM.

028 CK09A1 [ 1] M 8.000

20CM WIDE PVC WINDOW BOARDS SET TO THE

INTERIOR

029 CM02E1 MP. 4.000

DRAWN WINDOWS SIMPLE MEASURE FREE ON

WOOD CARPENTERY 4-8MM THICK.WITH PUTTY

AND WANG AT VITRI

029 2500327 MP. 4.360

CLEAR DRAWN GLASS Q.3 4MM. PACKED FREE

SIZES S 853

030 CN06B1 [ 3] MP. 316.000

3 LAYER WHITE COLOR WASHABLE PAINTING FOR

INTERIOR FOR WALLS

031 RPCK72A1 MP. 52.000

PALUX LAKE PARQUET LAQUERING IN THREE

LAYERS

032 IZF10C1 [10] MP. 123.000

Page 98: ITB Constructii Noi Rev1

98

THERMINSULATING LAYER FOR WALLS OF

EXPANDED POLYSTYRENE FOR FACADE OF 10CM

THICK.INCLUDING MORTAR ADHESIVE AND

SECURING NAILS

032 2602797 MP. 124.230

PEX C EXPANDED POLYSTYRENE SLAB OF

2000X500X 100MM S7461

033 CO12A1 BUC. 470.000

TERACOTTA ENAMEL STOVES,INCLUDING

METALLIC SEALS

033 2436887 BUC. 484.100

COLORED TILES FOR STOVES OF 240X220 1ST Q.

S1798

033 7323475 BUC. 4.700

METALLIC SET TERRACOTTA STOVE (EG .GRILL)

FROM NES CAST IRON

033 7323580 BUC. 4.700

CAST IRON GRILL MAR ,1 105 X128X8

034 TRA06A TONA 37.500

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

Page 99: ITB Constructii Noi Rev1

99

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: CONSTANT ARCHITECTURE GARRET

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 25.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1302 ORA 170.000

METAL AUTO-LIFTING SCAFFOLD 3 CAST. 3.

5TF H=31M L=29M 3 SHIFTS

003 CD05E1 M.C. 5.000

BRICK MASONRY GVP TYPE FOR

CONSTR.H<35M, FORMAT 365X180X138MM,A Q.

003 2101169 M.C. 0.650

MASONRY MORTAR M 25 S 1030

004 CD04C1 M.C. 1.850

RESSED BRICK MASONRY 240X115X63MM AT

INSULATED CHIMNEY STACKS IN GARRET,QAL.1

004 2101171 M.C. 0.315

MASONRY MORTAR M 50 S 1030

005 CE01A1 MP. 160.000

BURNT CLAY SHAPED TILE COVER

005 2302983 BUC. 2560.000

DRAIN TILE WITH 1 BEAK Q1 390X230X11

S515

006 CE13A1 M 39.000

GALVANIZED PLATE DRAIN OF 0,5MM, MADE ON

SITE SEMIROUND WITH D=15CM

007 CE14A1 M 21.000

GALVANIZED PLATE RAIN PIPE OF 0,5MM MADE

ON SITE SEMIROUND WITH D= 15,4CM

008 CE15B2 [ 1] M 1.200

ALUMINIM WINDOW BOARDS

009 CE19D1 [ 1] M 55.000

TOOTHING EAVES FROM ONE SIDE

PLANE BOARD AND RABBETED

OF 70CM WIDE

009 2903830 M.C. 0.083

Page 100: ITB Constructii Noi Rev1

100

LONG RESIN BOARD SELVEDGED CLASS C THICK

=24MM L=3,00M S 942

010 CF06A1 MP. 6.000

EXTER.REGULAR PLASTER,FLOATED FOR

DRYWALLS OR INTERIORS IN GARRET,OF 2 CM

010 2101203 M.C. 0.132

PLASTER MORTAR M25T

011 CF06C1 [ 6] MP. 25.000

OUTER DECORATIVE PLASTER OR

SIMILAR

012 CF06K1 MP. 25.000

FLOATED EXTERNAL PLASTER ON BRICK AND

BLOCKS WALLS WITH CRUND.MECH.LAYER VIZ.

MANUALLY MORTAR M25-T THICK.2,5 CM

012 2101203 M.C. 0.575

PLASTER MORTAR M25T

013 CK01A1 MP. 0.500

BUILDINGS WOODEN WINDOWS WITH H= 0- 35M

WITH FRAME SURFACE < 1,00MP.

013 2938811 MP. 0.500

EXTERNAL SIMPLE RESIN WINDOWS OAK FRAME

<0,50 SQM

014 VB34C1 BUC. 3.000

PROTECTION CAP FOR CIRCULAR SEWERS WITH

PERIM. OF 701-1600 MM MADE.ON SITE DET.

TYPE 61/0

015 CK09A1 M 1.000

RESINOUS TIMBER LINTELS

015 2947800 M 1.000

RESINOUS WINDOW BOARD OF 30MM WIDE UP

TO 120MM

016 CM02B1 MP. 0.500

DRAWN GLASSES SIMPLE FREE MEASURE ON

WOOD CARPENTERY 2-3MM THICK. WITH

PUTTYAND EYES NAILS>0,25MP

016 2500195 MP. 0.565

CLEAR DRAWN WINDOW Q.3 3MM. PACKED FREE

SIZES S 853

017 CN09B1 MP. 0.250

DYE WORKS ON WOOD CARPENTRY,OIL PAINT IN

3 LAYERS AT DOORS AND WINDOWS

017 6103270 KG 0.090

RED PAINT V.231-1 NTR 90-80

018 CN15B1 [ 4] MP. 300.000

PAINTING THE TIMBER BY FIREPROOF

SOLUTIONS

Page 101: ITB Constructii Noi Rev1

101

019 CN15D1 MP. 75.000

PAINTING OF WOOD WORK WITH SPECIAL

SOLUTIONS,WITH ANTISEPTIC PAINTS,

WATERPROOF ON IMPREGNATE WOOD

020 CN01A1 MP. 6.000

TWO LAYERS LIME MILK PAINTINGS

(PAINTINGS)

021 CO15B1 BUC. 5.000

CLEANING WICHET AT DOUBLE CHIMNEY STACKS

022 CO02B1 [ 2] MP. 3.000

CONCRETE PRECAST SLABS 70 X70 X8CM LAID

ON THE CLEANING DOOR AREA FOR THE

CHIMNEY STACKS

022 2800488 MP. 3.060

CONCRETE MANUFACT. FLAGSTONE 70X70X8CM

023 CO17A1 BUC. 1.000

HATCH TO NON-CIRCULATING TERRACE EXITS

0,8 X0.8M BEECH WOOD INSULATED WITH

INSULATING MATERIAL OF 30MIN FIRE

RESISTANT

024 CO23A1 MP. 81.000

BEECH BOARD WOOD FLOOR BOARDING OF 20MM

THICKNESS

025 IZF10F1 [18] MP. 81.000

INSULATING MINERAL WOOL LAYER G80 TYPE

150MM THICK. COATED,AND ^=0.040 W/MK AND

0 KG/CUBIC METER TO THE FLOORING

026 IZF10C1 [ 5] MP. 25.000

THERMO-INSULATING LAYER FOR FLOOR WITH

EXPANDED POLYSTYRENE

026 2602797 MP. 25.250

PEX C EXPANDED POLYSTYRENE SLAB OF

2000X500X 100MM S7461

027 IZF03B2 MP. 25.000

BARRIER AGAINST VAPOURS ON VERTICAL

SURFACE WITH 1STR IMPISLIT BIT TYPE /A

SAU TSA2000 LIP WITH BITUM TYPE

027 2600048 KG 37.500

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

027 2602060 MP. 27.500

BIT.2F.NIS. TSA FIBER GLASS

2000 100CM S 10126

Page 102: ITB Constructii Noi Rev1

102

028 IZF02A1 MP. 25.000

ROOF VAPOUR DIFFUSION LAYER,TERRACCE

WITH GLASS FIBRE KNITTING HORISONTAL

SURFACE BITUMEN

028 2600048 KG 12.500

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

029 IZF01A1 MP. 25.000

SURFACE MILDING APPLY.VAPOURS DIFUSION

LAYER WITH CUT BITUMEN IN 2 LAYERS

HORIS.AND VERT.SURFACE

029 2600048 KG 3.750

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

030 IZF04J2 MP. 25.000

BOUNDARY LAYER RELATED TO THE INSULATION

WORK EXEC WITH FIBER GLASS FELTING

AND NON GLUED BREAKDOWN

030 2602060 MP. 27.000

BIT.2F.NIS. TSA FIBER GLASS

2000 100CM S 10126

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

- HEALTH

- OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Page 103: ITB Constructii Noi Rev1

103

Estimate - Tender: RESISTANCE INFRASTRUCTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSC18A1 100 MC. 0.140

BULDOZER DIGGING ON TRACTOR 65-80CP

INCL.EARTH PUSH. 10M CAT.1 LAND

002 TSA04B1 M.C. 27.500

MAN.DIGGING IN LIMITED SPACES UNDER 1M

SUPPORTS AND MAN.EVAC.IN SOIL WITH NAT.

HUMIDITY DEPTH.0,0-1,5M MEDIUM SOOL

003 TSC02D1 100 MC. 0.340

DIGGING WITH EXCAVATOR ON TYRES 0,21-0,

39 MC SOIL NATURAL MOISTURE OPEN AUT.

FILED CATEGORY 2

004 TSD01C1 M.C. 39.000

LOOSE SOIL SHOVEL SPREADING,UNIFORM

LAYER 10-30CM.THICK WITH BREAKBLE CLODS

HARD SOIL

005 TSD05A1 100 MC. 0.390

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

006 TRA01A05P TONA 66.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= 5 KM

007 TSC35B31 100 MC. 0.650

AUTOLOADER ON TYRES WITH BUCKET 2,6-3,9

CM LAND CATEG 2 AT DIST. 11-20 M

008 TSF01B1 MP. 73.000

BANKS SUPPORT BY BEECH BOARDS

HORIZ.LAID WIDTH<1.5M, DEPTH 0.0-

2M;0,21-0,6M BETWEEN BOARDS

009 CG32D1 [ 5] M.C. 8.000

FILLINGS IN LAYERS, EXECUTED BY

MECHANICALLY COMPACTED GRAVEL

010 CA01B1 M.C. 48.700

SIMPLE CONCRETE MOULDING IN FOUNDATIONS

(CONTINUOUS,ISOLATED)AND SOCLES WITH

VOLUME > 3MC,AND IN RETAINIG WALLS

010 2100945 M.C. 49.090

CEMENT CONCRETE B 150(C8/10) STAS 3622

Page 104: ITB Constructii Noi Rev1

104

011 CA01D1 M.C. 12.200

SIMPLE CONCRETE MOULDING IN LAYERS OF 3-

20CM THICKNESS AT CONSTRUCTIONS WITH H

<35M

011 2100945 M.C. 9.374

CEMENT CONCRETE B 150(C8/10) STAS 3622

012 2100957 M.C. 2.923

CEMENT CONCRETE B 200(C12/15) STAS 3622

013 CB11A1 MP. 186.000

SHUTTERINGS FOR CONCRETE IN ELEV.FROM

PANELS TO STRAIGHT WALL WITH H<3M,WITH

PLYWOOD OF 8MM THICK.

013 CC01C1 KG 710.000

CONCRETE STEEL REINFORCEMENTS ASSEMBLING

IN CONTINUOUS FOUNDATIONS,SLABS OF

PLATES,WITH DIST FROM PLASTICS

014 CZ0301A1 KG 340.000

MANUFAC.REINFOR.SHAPED BARS FOR

FOUNDATION ISOL.CONTINUOUS AND PLATES

IN.CENT.WORKSHOPS OB 37 D=6-8MM

015 CZ0301D1 KG 370.000

REINFORCED MANUFACTURED SHAPING BARS FOR

CONTINOUS ISOLATED FOUNDATION AND PLATE

FOUNDATION IN ATEL CENT.PC 52 D=6-8MM

016 TRA06A05 TONA 153.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

017 TRA02A05 TONA 0.710

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= 5 KM.

018 IZF10F1 [14] MP. 63.300

EXTRUDED POLYSTYRENE INSULATION

LAYER OF 100MM WITH = 0.03 W/MK > 35 KG

UNDER THE REINFORCED CONCRETE SLAB

019 IZF04J1 [ 1] MP. 81.000

BOUNDARY LAYER EXEC BY POLYETHYLENE

FOIL OF 0.2MM

020 CF12A1 [ 1] MP. 19.000

RIGID WATERPROOFING ON M100T WALLS WITH

APAPSTOP APPLIED IN 3 LAYERS ON HORIZ

SURFACES UNDER WALLS ACC. TO TECHNICAL

SPECIFICATIONS

Direct expensive from items:

Page 105: ITB Constructii Noi Rev1

105

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: RESISTANCE SUPER-STRUCTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CA02J1 M.C. 18.000

MOULDING REINFOR.CONCRETE TO CONSTR.WITH

H<35M,IN FLOORS(BEAMS,COLUMNS,PLATES)

WITH SLAB THICKN.>10CM

001 2100957 M.C. 18.144

CEMENT CONCRETE B 200(C12/15) STAS 3622

002 CB13A1 MP. 116.000

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTRUCTIONS WITH H<20M TO SLABS AND

BEAMS,WITH PLYWOOD OF 8MM

003 CB13B1 MP. 25.000

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTR.WITH H<20M,AT COLUMNS AND FRAMES,

WITH PLYWOOD OF 8MM

Page 106: ITB Constructii Noi Rev1

106

004 CB44A1 BUC. 62.000

SUST.WITH STUDS EXTENS PER3100R FOR

ASSEMBLING FLOORS,PRESLAB TURN FLOORS

MONOL WITH GR OR GR MONOL PL PREFAB.

005 CB45B1 BUC. 31.000

SUSTAIN. FROM METALIC BEAMS EXTENSIBLE

TO CONSTR.WITH H<20M BEAMS SUPPORT.ON

METALIC STUDS

006 RPCH38A1 [ 2] BUC. 30.000

ROUND WOODEN PROP SUPPORT D= 12CM

AT LINTELS OVER DOOR AND WINDOW OPENINGS

007 CC01C1 KG 1610.000

CONCRETE STEEL REINFORCEMENTS ASSEMBLING

IN CONTINUOUS FOUNDATIONS,SLABS OF

PLATES,WITH DIST FROM PLASTICS

008 CZ0302A1 KG 275.000

MANUFAC. REINFORC. FOR WALLS BEAMS

COLUMNS DIAPHRAGMS TO REGULAR CONST IN

CENTRALIZED WORKSHOPS OB 37 D=6-

009 CZ0302E1 KG 590.000

MADE REINFORCED FOR WALLS BEAMS PILLARS

MIDRIFF AT BUILDG. REGULAR IN WORKSHOP

CENTRALIZED PC 52 D=10-

010 CZ0302M1 KG 55.000

MANUFCT. REINFORC. FOR PLATES INCLUD.

STAIRS TO REGULAR CONST. IN CENTRALIZED

WORKSHOPS OB 37 D=6-8MM

011 CZ0302O1 KG 690.000

MANUFCT.REINFORC.FOR PLATES INCLUD.

STAIRS TO REGULAR CONST.IN CENTRALIZED

WORKSHOPS PC 52 D= 6-8MM

012 CP12A1 BUC. 7.000

ASSEMBL.PREFAB.TO HOUSING WITH STRUCT.

MONOL.MIXED AND BRICKWORK.SUST.WITH.VOL.

0,2 MC.AND H<20 M

013 6433209 M.C. 0.300

CONCRETE PRECAST C16/20(B250) II A-

S32.5 0-16MM

014 6433376 KG 18.000

CONCRETE PREFABR.REINFOR. OB 37 D=6-10MM

STANDARD

015 6433754 KG 10.000

REINFOR.IN CONCRETE PREFABR. PC52 O6-10

MM STANDARD

016 6433754 KG 63.000

REINFOR.IN CONCRETE PREFABR. PC52 O6-10

MM STANDARD

017 AUT1301 ORA 5952.000

Page 107: ITB Constructii Noi Rev1

107

EXPANDING METAL GIRDER L=3-5M TYPE GE1 3

SHIFTS

018 AUT1325 ORA 11904.000

EXPANDING METAL PROP PE3100 INCLUDING

PIPE 051X3,5MM

019 TRA06A TONA 45.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. = KM

020 TRA02A TONA 1.610

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= KM.

021 AUT1140 ORA 30.000

TELESCOPIC JIB CRANE ON TYRES TELEMAC HT

125.5 TF 1 SHIFT

022 MDTC4623 BUC. 6.000

EQUIP.TRANSPORT 10 KM-65121002-TYRE

CRANE OF 0,10-0,149 MN(10-14,9TF

023 MDTC5575 BUC. 62.000

EQUIPMENT TRANSPORTATION 10 KM-90100106

EXTENSIBLE METALLIC BEAM WITHL=4-8M TYPE

CE-2

024 MDTC5552 BUC. 124.000

EQUIPMENT TRANSPORTATION 10 KM-90100079

METALLIC POP TYPE PE-3100

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

- HEALTH

- OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

Page 108: ITB Constructii Noi Rev1

108

VAT

TOTAL with VAT

List with work quantities

Estimate - Tender: REZISTENCE FRAMEWORK

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CE17B1 MP. 125.000

WOODEN FRAMEWORK FOR HEAVY COVERS

002 2900980 M.C. 5.500

FRAMEWORK SQUARED WOOD

003 7335349 ORA 38.000

TIMBER MANUFACT. AT CARPENTRY MACHINES

004 CE23A1 MP. 50.000

SAFETY NET REUSED FOR CONSTRUCTION

COVERS

005 CN15D1 MP. 35.000

PAINTING OF WOOD WORK WITH SPECIAL

SOLUTIONS,WITH ANTISEPTIC PAINTS,

WATERPROOF ON IMPREGNATE WOOD

006 6310159 KG 16.000

JOIN.FRAMEWORK ELEM.LIGHT METALIC

MANUFACT.

007 RPCR41B1 MP. 140.000

FIREPROOF WOODWORK ON PROTECTED SURFAC.

ANT.CONTR.INCE.*

008 CA02M1 M.C. 1.000

REINFOR. CONCRETE MOULDING FOR CONSTR

WITH H<35M IN ELEMENTS SHAPED ISOLATED

WITH VOLUME>0,5MC

008 2100957 M.C. 1.008

CEMENT CONCRETE B 200(C12/15) STAS 3622

009 CB13B1 MP. 8.500

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTR.WITH H<20M,AT COLUMNS AND FRAMES,

WITH PLYWOOD OF 8MM

010 CC02C1 KG 150.000

ASSEMBL.REINFOR.FOR CONSTR H<35M FROM

BARS IN BEAMS AND COLUMNS D<18MM PLATES

D<10MM WITH DIST FROM PLASTIC

011 CZ0302A1 KG 27.000

MANUFAC. REINFORC. FOR WALLS BEAMS

COLUMNS DIAPHRAGMS TO REGULAR CONST IN

CENTRALIZED WORKSHOPS OB 37 D=6-

Page 109: ITB Constructii Noi Rev1

109

012 CZ0302E1 KG 123.000

MADE REINFORCED FOR WALLS BEAMS PILLARS

MIDRIFF AT BUILDG. REGULAR IN WORKSHOP

CENTRALIZED PC 52 D=10-

013 TRA06A05 TONA 2.500

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

014 TRA02A05 TONA 0.200

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= 5 KM.

015 TRA02A10 TONA 2.750

ROAD TRANSPORT OF MATERIALS,SEMIFABS

WITH TRUCK ON DIST.= 10 KM.

016 CF12A1 [ 1] MP. 2.750

RIGID WATERPROOFING ON M100T WALLS WITH

APAPSTOP APPLIED IN 3 LAYERS ON HORIZ

SURFACES UNDER WALLS ACC. TO TECHNICAL

SPECIFICATIONS

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: PAVEMENT-

Work category:

=================================================================

Page 110: ITB Constructii Noi Rev1

110

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA01G1 M.C. 20.000

MAN. DIGGINGS IN SPREAD SPACES IN SOIL

WITH NAT.MOISTURE THROWED IN VEHICLE ATH

OF 0,61-2M HARD SOIL

002 TSC35B31 100 MC. 0.200

AUTOLOADER ON TYRES WITH BUCKET 2,6-3,9

CM LAND CATEG 2 AT DIST. 11-20 M

003 TRA01A05P TONA 36.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= 5 KM

004 TSE06B1 100 MP. 0.850

SOIL PLATF.PREPARING ISOLATING LAYER AND

SAND REPARTION OR GRAVEL IN COHESIVE

SOIL

005 DA06A1 M.C. 13.000

NAT.AGREGG.LAYER(GRAVEL)ROLLED OVER WITH

FILTRING RESISTANCE FUNCTION ISOL.AERING

ANTICAP.MANUAL LAYING

006 TRA01A10 TONA 38.000

MATERIAL,SEMIPREFAB ROAD TRANSPORT BY

TIP LORRY ON A 10 KM.DIST.

007 DD02A1 MP. 85.000

PAVMENT MADE OF NORM PAVING 1ST Q. ON

SAND SUB BASE

008 TRA01A10 TONA 17.000

MATERIAL,SEMIPREFAB ROAD TRANSPORT BY

TIP LORRY ON A 10 KM.DIST.

009 DE11A1 M 115.000

SMALL CRIMPS MANUF.CONCRETE 10X15 CM FOR

FRAMING SPACES WALK ROAD ,GREEN ALLEY

FOUND. CONCRETE10 X 20 C

009 2100933 M.C. 3.000

CEMENT CONCRETE B 100(C6/7.5) STAS 3622

010 TRA06A05 TONA 10.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

011 PB01A1 M.C. 1.000

POURING PLAIN B50 CONCRETE IN

COMPLETIONS TO FILLING LEVELLING AND CONCRETE

Page 111: ITB Constructii Noi Rev1

111

SLOPE EXEC.IN LAYER OF 5-20CM.

011 2100957 M.C. 1.008

CEMENT CONCRETE B 200(C12/15) STAS 3622

012 PC02A1 MP. 6.000

SHUTTERINGS FOR CONCRETE ELEVATION AND

RETAINING WALLS FROM PLYWOOD P PANELS

PLANE SURFACE

013 ACC08B1 M 5.000

INSTALLING CONCRETE CIRC.PIPE PREC.L=5M DN 500

PREMO

013 6418871 BUC. 1.010

PREMO FEED PIE D= 500 P= 4 L=5

B600SBP ISLGC T2027

014 TSG03B1 100 MP. 17.000

MANUAL LAND CLEARING OF AFFORESTATION AREA

WITH BUSHES AND SHRUBS WITH DIAM.<10CM.

MATER.STORAGE,WITH ROOTING OFF

015 TSG01A1 100 MP. 17.000

LEAFS AND BRANCHES LAND CLEANING OFF,

PILING UP AND SUPERVIZED BURNING

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

- HEALTH

- OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Page 112: ITB Constructii Noi Rev1

112

LOT NO. 4 Health Unit

QUANTITY LIST WITH TECHNOLOGICAL EQUIPMENT, INCLUDING UTILITIES OF THE ESTIMATE-OFFER FOR PROCUREMENT

Item Name M.U. Quantity Unitary Price

-lei/M.U.-

Amount (VAT

exclusive)

-Thousand lei-

(col.3 x 4)

Supplier

(name,

address,telephone,

facsimile)

Page 113: ITB Constructii Noi Rev1

113

0 1 2 3 4 5 6

1 Mural Tank on gas fuel, thermo power

of 30kw

pcs 1

2 Gas Regulating filter Dn ¾˝ pcs 1

3 Gas Detector and electro-valve pcs 1

4 Programmable thermostat pcs 1

5 Water meter Qn=1.5 cubic meters/h pcs 1

6 Ecological tank for waste water,

capacity 6 m3 pcs 1

Thousand

lei:

TOTAL

USD*):

*) Exchange rate =…………………. Lei/USD, of …………………….

TECHNICAL SHEET No. 1

EQUIPMENT: TANK FOR HOT WATER

Item Technical specifications imposed by the Technical Specifications

Comparison between the technical proposal and

the specifications imposed by the

Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• Type: mural with forced flow and sealed burning chamber

• Thermic agent: hot water 80 – 600C

• Nominal output Pn 3 bars

• Minimum output 90%

• Net thermic power: 30 KW

• Burnt gas Connection 110/60 mm

• Volume of expansion vessel: 8 liters

• Hot water flow Dt=250. C 13 l/min

• Primary connection 3/4˝ - gas 3/4˝ - water feed pipe - outlet 1/2˝

• gas consumption 3.4 Ncubic meters/h

• Fuel nominal output: 20 mbar

2. Performance specs and conditions related to safety in exploitation:

• The tank shall be fitted out with flame

extinguishing protection system, electric current supply cut off, and pressure building up in installation

• To be granted the I.S.C.I.R. endorsement.

• The Technical Book shall be presented in

Romanian wording.

3. Conditions related to compliance with relevant

standards:

Page 114: ITB Constructii Noi Rev1

114

4. Guarantee and post-guarantee conditions:

• 3 years guarantee;

• 3 days for solving out issues occurred during the guarantee period;

• 10 days for providing spare parts in the post-guarantee period

5. Other condition of technical character: the electro-

pump shall provide the pressure head of water of 2 mH2O to tank’s nominal load.

TECHNICAL SHEET No. 2

EQUIPMENT: GAS REGULATING FILTER

Item Technical specifications imposed by the

Technical Specifications Comparison between the technical proposal and the

specifications imposed by the Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• maximum entrance pressure: 200 mbar

• outlet pressure: 20 mbar

• connection diameter: 3/4˝

2. Performance specs and conditions related to safety in exploitation:

- To be granted a Technical Agreement or an homologation document;

- The Technical Book shall be presented in

Romanian wording.

3. Conditions related to compliance with relevant standards:

4. Guarantee and post-guarantee conditions: - 3 days for solving out issues occurred during

the guarantee period;

- 10 days for providing spare parts in the post-guarantee period.

5. Other condition of technical character:

TECHNICAL SHEET No. 3

EQUIPMENT: GAS DETECTOR AND ELECTRO-VALVE

Item Technical specifications imposed by the Technical Specifications

Comparison between the technical proposal and the

specifications imposed by the Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• Lower sensitivity limit: 2%CH4 in air

• Electro-valve nominal diameter: 3/4″

Page 115: ITB Constructii Noi Rev1

115

• Normal closed electro-valve, with one step

• Pressure: max 200 bar

• Male electro-valve connection

• Power supply: 230 V/50 Hz;

• Location: in the central heating, and the electro-valve to the exterior

2. Performance specs and conditions related to safety in exploitation:

• Closing period: < 1 sec.

• Opening period: < 1 sec.

3. Conditions related to compliance with relevant standards: supplier must be certified according to Standards family ISO 9001

4. Guarantee and post-guarantee conditions:

• 3 years guarantee.

5. Other condition of technical character:

TECHNICAL SHEET No. 4

EQUIPMENT: PROGRAMMABLE ELECTRONIC THERMOSTAT

Item Technical specifications imposed by the

Technical Specifications Comparison between the technical proposal and the

specifications imposed by the Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• Type: single pole, change over contacts, with “on-off” switch Power supply: 230V / 50 Hz.

• Maximum current to thermostat contacts: 6 A

• Control temperature area: 10 – 300C

• Use temperature area: 10 – 50 0C

• Protection degree IP 30

• Dt=0.5 K

2. Performance specs and conditions related to safety in exploitation:

• To be granted a Technical Agreement and

an homologation document;

• The Technical Book shall be presented in Romanian wording.

3. Conditions related to compliance with relevant

Page 116: ITB Constructii Noi Rev1

116

standards:

4. Guarantee and post-guarantee conditions:

• 3 days for solving out issues occurred during the guarantee period;

• 10 days for providing spare parts in the post-guarantee period.

5. Other condition of technical character:

TECHNICAL SHEET No. 5

EQUIPMENT: WATER METER Qn=1.5 cubic meters/h

Item Technical specifications imposed by the Technical Specifications

Comparison between the technical proposal and

the specifications

imposed by the Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters: -Type: multi-jet, and dry dial

-Nominal output: 1,5 mc/h -Nominal diameter: 15 mm - Connection sizing: 1/2˝

-Connection type: coupling -Design pressure Pn 6 bars

2. Performance specs and conditions related to safety in

exploitation: - To be granted a Technical Agreement or an

homologation document;

- The Technical Book shall be presented in Romanian wording.

3. Conditions related to compliance with relevant standards:

-Accuracy category: B

4. Guarantee and post-guarantee conditions:

-3 years guarantee - 3 days for solving out issues occurred during the guarantee period

5. Other condition of technical character:

TECHNICAL SHEET No. 6

EQUIPMENT: ECOLOGICAL TANK FOR WASTE WATER

Item Technical specifications imposed by the Technical Comparison between the Supplier

Page 117: ITB Constructii Noi Rev1

117

Specifications technical proposal and the

specifications imposed by the Technical Specifications

0 1 2 3

1. Technical and Functional Parameters:

-Material: polyester -Net volume: 6 cubic meters -Diameter: 1.6 linear meters

-Length: 3.0 linear meters -Installing: buried

2. Performance specs and conditions related to safety in exploitation:

• To be granted a Technical Agreement or an homologation document;

3. Conditions related to compliance with relevant

standards: -SR EN 12566-1

4. Guarantee and post-guarantee conditions:

- 3 years guarantee.

5. Other condition of technical character: Minimum life cycle: 30 years

Equipment List TE-

- panel for 24 modules 1 PCS

- automatic switch 4P 32A, with differential prot. device Id=100mA, Icn=6kA, curba C 1 PCS

- circuit breaker phase-null 6A, Icn=4,5kA, curba C 3 PCS

- circuit breaker phase-null 16A, Icn=4,5kA, curba C 7 PCS

- copper clamps 10mmp 5 PCS - copper clamps 2,5mmp 30 PCS

- copper conductor 1…4mmp 3 m

- tags 11 PCS

- warning plate 1 PCS

Bill of quantities

Estimate - Tender: HEAT INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 IA07A1 [ 3] BUC. 1.000

INSTALLING MURAL BOILER FOR PREPARING HEAT

CARRIER AND HOT WATER, WITH A HEAT OUTPUT

OF: 25.1-70 KW

002 IB02A01 [ 3] BUC. 13.000

INSTALLING FINISHED STEEL SHEET

RADIATORS H 600 MM

Page 118: ITB Constructii Noi Rev1

118

002 5700860 BUC. 1.000

STEEL RADIATOR TYPE 11 600/600 MM

002 5700864 BUC. 5.000

STEEL RADIATOR TYPE 22 600/500 MM

002 5700866 BUC. 2.000

STEEL RADIATOR TYPE 22 600/700 MM

002 5700868 BUC. 5.000

STEEL RADIATOR TYPE 22 600/1000 MM

003 IC04B1 [ 1] M 34.000

COPPER PIPE MOUNTED BY WELDING IN

BRANCHES OF RADIATORS D=15 MM

004 IC25A1 [ 1] M 25.000

COPPER PIPE MOUNTED BY WELDING IN

CENTR.HEAT.DISTRIB.D=18 MM

005 IC25A1 [ 2] M 35.000

COPPER PIPE MOUNTED BY WELDING IN

CENTR.HEAT.DISTRIB.D=22 MM

006 IC25B1 [ 1] M 16.000

COPPER PIPE MOUNTED BY WELDING IN

CENTR.HEAT.DISTRIB.D=28 MM

007 IC34B1 [ 2] BUC. 68.000

COPPER FITTINGS FOR JOINING PIPE WELDING

PIECES HAVING 2 WELDINGS D=15 MM

007 7300509 BUC. 45.000

@COPPER PIPE ELBOW MM 90 GR DN 15 COD

46900004

007 7300331 BUC. 13.000

@COPPER CURVE FOR GOING OVER PIPE MM

DN 15 COD 46850002

007 3331105 BUC. 10.000

@COPPER MALE COUPLING MM DN 15 COD

46270005

008 IC34B1 [ 3] BUC. 47.000

BRONZE FITTINGS FOR COPPER

- STEEL JOINING D=1/2 INCHES

008 3330697 BUC. 34.000

@BRONZE FE X M PIPE NIPPLE FE X M DN 1/2"

X16 COD 46243078

008 3330694 BUC. 13.000

@BRONZE FE X M SCREWED UNION FE X M DN 1/

2"X15 COD 46341004

009 IC34C1 [ 2] BUC. 22.000

Page 119: ITB Constructii Noi Rev1

119

COPPER FITTINGS FOR JOINING PIPE WELDING

PIECES HAVING 2 WELDINGS D=18 MM

009 7300515 BUC. 2.000

@COPPER PIPE ELBOW MM 90 GR DN 18 COD

46900006

009 3331108 BUC. 6.000

@COPPER MALE COUPLING MM DN 18 COD

46270007

009 3330885 BUC. 14.000

@COPPER REDUCTION MT DN 18X15 COD

46243015

010 IC34C1 [ 3] BUC. 10.000

COPPER FITTINGS FOR JOINING PIPE WELDING

PIECES HAVING 2 WELDINGS D=22 MM

010 7300519 BUC. 2.000

@COPPER PIPE ELBOW MM 90 GR DN 22 COD

46900007

010 3330900 BUC. 8.000

@COPPER REDUCTION MT DN 22X18 COD

46243021

011 IC34D1 [ 2] BUC. 6.000

COPPER FITTINGS FOR JOINING PIPE WELDING

PIECES HAVING 2 WELDINGS D=28 MM

011 7300523 BUC. 2.000

@COPPER PIPE ELBOW MM 90 GR DN 28 COD

46900008

011 3330912 BUC. 4.000

@COPPER REDUCTION MT DN 28X22 COD

46243027

012 IC34D1 [ 4] BUC. 8.000

BRONZE FITTINGS FOR COPPER

- STEEL JOINING D=1 INCH

012 3330725 BUC. 2.000

@BRONZE FE X M SCREWED UNION FEXM DN 1"X28

COD 46341014

012 3330723 BUC. 6.000

@BRONZE FE X M PIPE NIPPLE FEXM DN 1"X28

COD 46243089

Page 120: ITB Constructii Noi Rev1

120

013 IC34L1 [ 2] BUC. 4.000

COPPER FITTINGS FOR JOINING PIPE WELDING

PIECES HAVING 3 WELDINGS D=15 MM

013 3330754 BUC. 4.000

@COPPER TEE PIECE DN 15 COD 46130005

014 IC34M1 [ 2] BUC. 8.000

COPPER FITTINGS FOR JOINING PIPE WELDING

PIECES HAVING 3 WELDINGS D=18 MM

014 3330778 BUC. 8.000

@COPPER REDUCING TEE PIECE DN 18X15X18

015 IC34M1 [ 3] BUC. 10.000

COPPER FITTINGS FOR JOINING PIPE WELDING

PIECES HAVING 3 WELDINGS D=22 MM

015 3330797 BUC. 10.000

@COPPER REDUCING TEE PIECE DN 22X18X22

016 IC34N1 [ 2] BUC. 2.000

COPPER FITTINGS FOR JOINING PIPE WELDING

PIECES HAVING 3 WELDINGS D=28 MM

016 3330761 BUC. 2.000

@COPPER TEE PIECE DN 28 COD 46130009

016 3330816 BUC. 8.000

@COPPER REDUCING TEE PIECE DN 28X22X28

017 IC35C1 [ 1] BUC. 24.000

TUBE CLIPS DN 14-16 MM

018 IC35D1 [ 1] BUC. 62.000

TUBE CLIPS DN 18-22 MM

019 IC35E1 [ 1] BUC. 18.000

TUBE CLIPS DN 26-28 MM

020 IC40A1 BUC. 12.000

MANUF.ASSEMBLY+CEMENTATION OF PROTECTION

PIPE AT PIPES PASSING THROUGH WALLS D=1

INCHES

021 ID01A2 BUC. 26.000

CORNER VENTIL DOUBLED FAUCET ADJUSTM.

FOR CENTRAL HEAT.INSTALLATION WITH D: 1/

2''

021 4507211 BUC. 13.000

@CORNER FAUCET COPPER PIPE DN 1/2" CODE

4O020413

021 4507213 BUC. 13.000

@CORNER FAUCET COPPER PIPE RETURN

ADJUSTMENT DN1/2" COD 4O120414

Page 121: ITB Constructii Noi Rev1

121

022 ID06A1 [ 1] BUC. 6.000

COUPLING SPHERE FAUCET CENT.HEAT.INSTL.

HAVING DN=1/2"

022 7344047 BUC. 6.000

@BALL GAUGE COCK+HOSEBEARING+LEVER MAN

DN 1/2" COD 40740485

023 ID06A2 [ 1] BUC. 2.000

COUPLING SPHERE FAUCET FOR CENT.HEAT.

INSTL.HAVING DN=3/4"

023 7344059 BUC. 2.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

024 ID06A3 [ 1] BUC. 4.000

SPHERE FAUCET WITH COUPLING FOR CENT.

HEAT. INSTL.HAVING DN=1"

024 7344085 BUC. 4.000

@BALL VALVE FIXFI+LEVER MANEV DN 1" COD

40450425

025 ID06A3 [ 3] BUC. 1.000

Y TYPE FILTER FOR IMPURITIES OF D: 1’’

026 ID15A1 [ 1] BUC. 2.000

AUTOMATIC EXHAUSTER CENTR.HEATING INST.

DN 1/2"

027 IE01A1 MP. 48.000

TIGHT.TEST AT PRES.CENTR.HEAT.INSTL.

TOTAL HEAT.BODIES AREA:UP TO 100 M

028 IE02A1 MP. 48.000

DILAT.-CONTRACT.AND FUNCT.TEST CENTR.

HEAT.INSTL.TOTAL HEATING AREA:UP TO

100MP

029 IE07A1 MP. 48.000

DRINCKING WATER WASHING OF INSIDE

INSTALLATION OF CENTRAL HEATING WITH

SUP. BODY UNTIL 100M

030 CN13A1 M 110.000

INSTALLATIONS REGULAR PAINTINGS WITH OIL

PAINT ON PIPES EXT.D<34MM INCLUDED

030 6103220 KG 1.870

WHITE PAINT (FP) V.101-1 NTR 90-80

031 RPCU07B1 BUC. 11.000

MASONRY CHANELLING OF 1 BRICK WITH LIME

Page 122: ITB Constructii Noi Rev1

122

MORTAR AND CEMENT OPENINGS FOR TUBES OF

50-400SQ.CM

032 RPCU20A1 BUC. 11.000

SEALING WITH LIME CEMENT MORTAR OF

BRICKWORK VOIDS

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: GAS INSTALLATION

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA02F1 M.C. 9.000

MAN.DIGGIN.IN LIMIT.SPACES UNDER 1M WITH

R.O.W.VERT.UNSUPPORT.IN SOIL AVER.COHEZ.

AND VERY COHEZ.DEPTH<1,5M HARD S.

002 TSD01C1 M.C. 7.000

LOOSE SOIL SHOVEL SPREADING,UNIFORM

LAYER 10-30CM.THICK WITH BREAKBLE CLODS

HARD SOIL

003 TSD05A1 100 MC. 0.070

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

Page 123: ITB Constructii Noi Rev1

123

004 ACE08A1 M.C. 2.000

DITCH FILLING FOR WATER PIPE SUPPLY AND

SEWERAGE WITH: SAND

005 W2H07A1 [ 1] M 16.000

POLYETHYLENE WARNING STRIP

006 W2G01A01 M 18.000

UNDERGR.CABLE SETTING 1 KV GR.0,050-0,

150 KG/M CU-AL IN DITCH ON SAND LAYER

WITHOUT OBST.WITH MAN.PULLING ASSEM.

006 4801660 M 18.360

POWER CABLE CYY 0.6/ 1KV 1X 1.5 U

S.8778

007 GD02A1 [ 1] M 16.000

POLYETYLENE PIPE FOR GAS CONNECTIONS

WITH DN 32 MM

007 7500156 M 16.320

PE GAS PIPE 100 SDR11 DN=32x3mm

008 GD14A1 [ 2] BUC. 2.000

HDPE/STEEL REISER TYPE PASSAGE THROUGH

PIECE PE 100 DN 32X1"

009 IA41A1 BUC. 1.000

GAS METER MOUNTED ON METER PLATE

EXISTENT AT BRANCHES WITH D: 1''

010 IA45A1 BUC. 1.000

PLATE FOR GAS METER WITH BRANCH OF:

1''

011 IC33C1 M 7.000

PIPE OL.INST.WELD.LONG. NG+THREAD+

COUPLING WITHOUT GAS INSTALLATION

FITTINGS IN BURNING PLACES +COLUMN+

DISTRIBUSTION COL+DISTRIB.D=3/4 T

011 3305683 M 7.070

BLACK INST.PIPE THREAD+COUPLING M - 20(

3/4) OL 32 1 S 7656

012 IC34C1 BUC. 15.000

SOFT CAST IRON FITTINGS SCREWED COUPLING

STEEL PIPES PIECES HAVING 2 SCREWING D=3

/4 INCH

012 4117930 BUC. 10.000

FLEXIBLE CAST IRON ELBOW A1 S474 DN 20 3

/4

012 4123197 BUC. 4.000

Page 124: ITB Constructii Noi Rev1

124

FLEXIBLE CAST IRON NIPPLE PIPE N8 S478

DN 20 3/4 DS

012 4123563 BUC. 1.000

FLEXIBLE CAST IRON CORCK T9 S487 DN 20 3

/4

013 IC34D1 BUC. 2.000

SOFT CAST IRON FITTINGS FOR SCREWED

JOIN.STEEL PIPES PIECES BEING WITH 2

SCREWS FOR D=1 INCHES

013 4113934 BUC. 2.000

FLEXIBLE CAST IRON REDUCTION N4 S 477

25X 20 F1

014 IC35D1 BUC. 3.000

CLAMPS FIXING STEEL PIPES AT HEATING

INST.OR GASES ASSEMBLED IN BRICK OR

CONCRETE WALL D= 3/4 INCHES

015 IC40B1 BUC. 1.000

MANUF.ASSEMBLY+CEMENTATION OF PROTECTION

PIPE AT PIPES PASSING THROUGH WALLS D=1

1/4 INCHES

016 ID20B1 [ 2] BUC. 3.000

BALL GAUGE COCK FOR GAS INSTALLATION

WITH DN: 3/4"

016 7344059 BUC. 3.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

017 ID20B1 [ 3] BUC. 1.000

INSTALLING GAS DETECTOR WITH

ELECTRO-VALVE D: 3/4"

018 GD10A1 BUC. 2.000

AIR HOLE WITH NO CONTROL COVER 1-2

INCHES

019 IE06A1 M 7.000

FINAL VERIFICATION AT PRESSURE OF

ASSEMBLY GAS CONDITIONS TAPS D: UP TO

1''

020 IE06B1 M 16.000

FINAL CHECKING OF PRESSURE OF GAS

MOUNTED GAS PIPES, TAPS , D:

OVER 1''

021 CN13A1 M 7.000

INSTALLATIONS REGULAR PAINTINGS WITH OIL

PAINT ON PIPES EXT.D<34MM INCLUDED

021 6103311 KG 0.119

CREAM-YELLOW COLOUR PAINT V.451-3 NTR 90

Page 125: ITB Constructii Noi Rev1

125

-80

022 TRA01A… TONA 4.000

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH DUMP TRUCK DISTANCE= … KM

023 TRA01A…P TONA 4.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= … KM

023 TRI1AA03C2 TONA 4.000

MATERIAL LOADING,GROUP A-HEAVY IN DUST,

BY THROWING FROM PLATFORMS OR SOIL-CAR

CATEG.2

024 YB01M [ 1] MII LEI. 1.000

RECEPTION OF GAS INSTALLATION

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: SANITARY INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 SA12B1 [ 3] M 45.000

PEXAL PIPE MONT.IN CONNECTION PIPES

OF SANIT.SUNDRIES D= 16 MM

Page 126: ITB Constructii Noi Rev1

126

002 SA12C1 [ 3] M 13.000

PEXAL PIPE MONT.IN CONNECTION PIPES

OF SANIT.SUNDRIES D= 20 MM

003 SA12D1 [ 1] M 10.000

PEXAL PIPE ASSEM.IN PIPES OF CONN.AT

SANIT.OBJECTS DN 26 MM

004 SA04B1 M 10.000

STEEL PIPE LONGIT.WELDED GALVAN.INSTAL.

THREAD+COUPLING SET HOUSES+SOC.CULT.

CONNECTIONS D= 1/2I

004 3306338 M 10.100

GALVANIZED INST.PIPE THREAD C - 15( 1/2)

OL 32 1 S 7656

005 SA06A1 M 36.000

WELDED STEEL PIPE LONGIT.FOR INSTAL.

ZINKED WITH THREAD+COUPLING ASSEM.LOC.+

SOC. SOC. CULT.IN DISTRIB. D= 3/4T

005 3306340 M 36.360

PIPE INST.ZINC THREAD M - 20( 3/4) OL 32

1 S 7656

006 SA06B1 M 17.000

STEEL PIPE LONGIT.WELDED FOR ZINCKED

INSTAL.WITH THREAD+COUPLING ASSEM.LOC.+

SOC. CULT.IN DISTRIB. D=1 T

006 3306352 M 17.170

GALVANIZED INST.PIPE THREAD M - 25(1 ) OL

32 1 S 7656

007 SA43C1 [ 1] BUC. 56.000

FIXING PIPE BRACE DN 16 MM

008 SA43D1 [ 1] BUC. 16.000

FIXING PIPE BRACE DN 20 MM

009 SA43E1 [ 1] BUC. 12.000

FIXING PIPE BRACE DN 26 MM

010 SA43C1 BUC. 12.000

CLAMP STEEL PIPE FIXING+PVC WATER+GAS

SUPPLY,TOOTHING SET,PIPE HAVING D= 1/2

INCHES

011 SA43D1 BUC. 42.000

CLAMP STEEL PIPE FIXING+PVC WATER+GAS

SUPPLY,TOOTHING SET,PIPE HAVING D= 3/4

INCHES

Page 127: ITB Constructii Noi Rev1

127

012 SA43E1 BUC. 19.000

CLAMP FOR FIXING STEEL+PVC PIPE OF WATER

+GAS SUPPLY, ASSEM.BY TOOTHING,PIPE D=1

INCH

013 SA46A1 BUC. 14.000

MANUF.ASSEM.AND CEMENTATION OF

PROTECTION PIPE PASSING PIPE THROUGH

WALL,PIPE HAVING D=1 INCHES

014 SA46B1 BUC. 5.000

MANUFACT,SET AND ASSEMBLY OF PIPE

PROTECTION AT PASSING OF PIPES THROUGH

WALL,PIPE HAVING D=1 1/4 INCHES

015 SA46C1 BUC. 2.000

MANUFACT,SET AND ASSEMBLY OF PIPE

PROTECTION AT PASSING OF PIPES THROUGH

WALL,PIPE HAVING D=1 1/2 INCHES

016 SB16A1 [ 1] M 10.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 32 MM

017 SB16C1 [ 1] M 18.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 50 MM

018 SB16D1 [ 1] M 12.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 75 MM

019 SB16E1 [ 1] M 11.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D=110 MM

020 SB17A1 [ 1] BUC. 12.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D= 32MM

020 6712369 BUC. 5.000

@HTB POLYPROPYLENE ELBOW AT 87 DGR 30

MIN DN 32 COD 62504011

020 6712226 BUC. 7.000

@HTB POLYPROPYLENE ELBOW AT 45 DGR DN 32

CODE 62504011

021 SB17C1 [ 1] BUC. 11.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D= 50MM

021 6712381 BUC. 3.000

@HTD POLYPROPYLENE ELBOW AT 87 DGR 30

MIN DN 50 COD 62504035

Page 128: ITB Constructii Noi Rev1

128

021 6712243 BUC. 8.000

@HTB POLYPROPYLENE ELBOW AT 45 DGR DN 50

COD 62504029

022 SB17D1 [ 1] BUC. 2.000

PP POLYPROPYLENE SEWER.ELBOWS JOIN.

RUBBER SEAL D= 75 MM

022 6712252 BUC. 2.000

@HTB POLYPROPYLENE ELBOW AT 45 DGR DN 75

CODE 62504041

023 SB17E1 [ 1] BUC. 13.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D=110 MM

023 6712264 BUC. 13.000

@HTD POLYPROPYLENE ELBOW AT 45 DGR DN

110 COD 62504053

024 SB19A1 [ 5] BUC. 3.000

FIREPROOF POLYPROP. SIMPLE LOW BRANCH

RUBBER SEAL JOINING D=50/40 MM

024 6712812 BUC. 3.000

@HTEA POLYPROP.EQUAL BRANCH 45GR DN50/50

CODE 62508013

025 SB19A1 [ 1] BUC. 2.000

SEWAGE FIREPROOF POLYPROP.SIMPLE UNIFORM

BRANCH RUBBER SEAL JOINING D= 50 MM

025 6712812 BUC. 2.000

@HTEA POLYPROP.EQUAL BRANCH 45GR DN50/50

CODE 62508013

026 SB19B1 [ 2] BUC. 1.000

FIREPROOF POLYPROP. SIMPLE LOW BRANCH

FOR SEWAGE AND RUBBER SEALING

JOINING D= 75/40 MM

026 6712824 BUC. 1.000

@HTEA R.S.SMALL POLYPROP 45GR DN75/

40 COD 62510013

027 SB19C1 [ 2] BUC. 1.000

FIREPROOF POLYPROP. SIMPLE LOW BRANCH

RUBBER SEAL JOINING D=110/ 50 MM

027 6712848 BUC. 1.000

@HTEA POLIPROP SIMPLE REDUCED BRANCH 45

DGR DN110/50 COD 62510031

Page 129: ITB Constructii Noi Rev1

129

028 SB19C1 [ 1] BUC. 5.000

SEWAGE FIREPROOF POLYPROP.SIMPLE UNIFORM

BRANCH RUBBER SEAL JOINING D=110 MM

028 6712862 BUC. 5.000

@HTEA POLIPROP SIMPLE EQUAL BRANCH 45

DGR DN 110 COD 62508025

029 SB21A1 [ 1] BUC. 1.000

SEWAGE FIREPROOF POLYPROP.INTERVENTION

PART RUBBER SEAL JOINING D= 50 MM

030 SB21C1 [ 1] BUC. 2.000

SEWAGE FIREPROOF POLYPROP.INTERVENTION

PART RUBBER SEAL JOINING D=110 MM

031 SB22A1 [ 1] BUC. 4.000

SEWAGE FIREPROOF POLYPROP.REDUCING PIECE

RUBBER SEAL JOINING DN 40- 32 MM

032 SB22B1 [ 1] BUC. 1.000

FIREPROOF POLYPROP.REDUCING COUPLING FOR

SEWERAGE RUBBER SEAL DN 50- 32 MM

033 SB22D1 [ 1] BUC. 1.000

SEWAGE FIREPROOF POLYPROP.REDUCING PIECE

RUBBER SEAL JOINING D= 75- 50 MM

034 SB22E1 [ 1] BUC. 1.000

FIREPROOF POLYPROP.REDUCING COUPLING FOR

SEWERAGE RUBBER SEAL D=110- 50 MM

035 SB22F1 [ 1] BUC. 2.000

SEWAGE FIREPROOF POLYPROP.REDUCING PIECE

RUBBER SEAL JOINING D=110- 75 MM

036 SB44C2 [ 1] BUC. 3.000

HDPE GULLY TRAP D= 50 MM WITH 1

CONNECTION AND VERTICAL EXIT

037 SB49A1 [ 1] BUC. 1.000

FIREPROOF POLYPROP.FANNING CAP FOR

VENTILATION COLUMNS D= 50 MM

038 SB49A2 [ 1] BUC. 2.000

VENTILATION CAP FOR FIREPROOF POLYPROP.

AIR COLUMNS D= 75 MM

039 SA43F1 [ 1] BUC. 16.000

Page 130: ITB Constructii Noi Rev1

130

BRACELET FOR FIXING PIPES DN 32 MM

040 SA43H1 [ 1] BUC. 3.000

TUBE CLIP DN 50 MM

041 SA43J1 [ 1] BUC. 2.000

TUBE CLIP DN 75 MM

042 SA43K1 [ 1] BUC. 2.000

TUBE CLIP DN 110 MM

043 SC07E1 [ 1] BUC. 7.000

SANIT.PORCELAIN LAVATORY L2 600 ON STAND

INCLD.FLOOR TRAP AND DELIVERY VALVE

044 SC07A1 [ 1] BUC. 1.000

SANITARY PORCELAIN BASIN FOR DISABLED

PERSONS MOUNTED ON FIXED BASIN STAND,

INCLD.CEILING SINK WATER TRAP AND

DELIVERY VALVE,AND TOWEL SUPPORT

045 SC13A1 BUC. 2.000

SANITARY PORCELAIN WATER CLOSET WITH

SIPHON TRAP S COV-A TYPE WHITE PORCELAIN

C.1

045 2444690 BUC. 2.020

WATER CLOSET BASIN COV2 WHITE PORCELAIN

C. 1 S 2066

046 SC13A1 [ 3] BUC. 1.000

WATER CLOSET BASIN OF SANITARY PORCELAIN

WITH INTERIOR S SIPHON,WITH FRONTAL

OPENING FOR HANDICAP PERSONS

047 SC16D1 [ 1] BUC. 2.000

RESERVOIR FOR WASHING WC BASIN FROM

POLYPROPYLENE SET MIDHEIGHT ON

BRICK WALL

048 SC16G1 BUC. 1.000

PORCELAIN DUOBLOCK CLEANING WC BASIN

RESERVOIR,ASSEMBL.ON BASIN

049 SC18A5 BUC. 2.000

WC BASIN FRAME,OF POLYPROPYLENE WITH LID

050 SC18A5 [ 1] BUC. 1.000

ERGONOMIC FRAME TO WATER CLOSET FOR

HANDICAPPED PERSONS

051 SC24A2 BUC. 7.000

TOWEL SUPPORT MADE OF AM NICKEL SET

ON WALLS U TYPE, 1 ARM, OPENING 600MM

Page 131: ITB Constructii Noi Rev1

131

052 SC25A1 BUC. 7.000

SANITARY PORCELAIN SHELF TYPE

052 2451849 BUC. 7.070

PORCELAIN SHELF TYPE E2.60 WHITE Q.1 NI

567

053 SC26A2 BUC. 7.000

SEMICRYST.SANIT.MIRROR POLISH.EDGES

SIZES 500X600MM

054 SC26A2 [ 1] BUC. 1.000

POLISHED SEMICRYST.SANITARY MIRROR

ADJUSTABLE INCLINE, SIZES 650X650 MM

055 SC27A1 [ 1] BUC. 8.000

LIQUID SOAP DISTRIBUTOR VISIBLY SET ON

WALL

056 SC30A1 BUC. 2.000

SANITARY PORCELAIN 1 Q. PAPER HOLDER,HA1

NI 545/63

057 SC30A1 [ 1] BUC. 1.000

SUPPORTING BRACKET WITH PAPER HOLDER SET

WITH ANCHORAGE SYSTEM TO THE WALL FOR

HANDICAPPED PERSONS

058 SD06A1 BUC. 7.000

LAVATORY COCK SYSTEM D=1/2"

058 4201377 BUC. 7.000

BRASS MIXT.WASH HAND BATTERY 1/2" PEARL

JET S8732

059 SD06A1 [ 2] BUC. 1.000

LAVATORY COCK SYSTEM WITH MEDICAL GRASP

FOR HANDICAPP. D=1/2"

060 SD12A1 BUC. 16.000

CORNER ADJUSTMENT FAUCET,OF NICHELLED

BRASS,HAVING D=3/8 OR D=1/2 INCHES

060 4201779 BUC. 16.000

NICKEL PLATED GRASS ANGLE CONTROL COCK 1

/2 " S 751/I

061 SA21A1 [ 1] BUC. 16.000

FLEXIBLE REINFORCED RUBBER CONNECTION 1/

2"X1/2"

062 SD13A1 [ 1] BUC. 3.000

Page 132: ITB Constructii Noi Rev1

132

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

062 7344032 BUC. 3.000

SPHERE TAP FI X FE "MINI" DN 1/2" CODE

40MI4272

063 SA21B1 [ 1] BUC. 3.000

FLEXIBLE REINFORCED RUBBER CONNECTION

1/2"X 3/8"

064 SD13A1 [ 1] BUC. 1.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

064 7344047 BUC. 1.000

@BALL GAUGE COCK+HOSEBEARING+LEVER MAN DN

1/2" COD 40740485

065 SD13A1 [ 1] BUC. 2.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

065 7344030 BUC. 2.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 1/2" CODE 40430425

066 SD13B1 [ 1] BUC. 3.000

SPHERE FAUCET WITH COUPLING,FOR STEEL

PIPES D=3/4''

066 7344059 BUC. 3.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

067 SD13C1 [ 1] BUC. 1.000

SPHERE FAUCET WITH COUPLING,FOR STEEL

PIPES D=1''

067 7344085 BUC. 1.000

@BALL VALVE FIXFI+LEVER MANEV DN 1" COD

40450425

068 SF01A1 M 131.000

TIGHTENESS TEST AT PRES. OF INST. INTER.

OF WATER,IN PIPES STEEL ZN. OR LEAD

PRES. INCLUDING REINFORCED

069 SF04A1 M 131.000

CLEANING AND SUBMIT FOR FUNCTION OF PVC

WATER PIPES.

070 CN13A1 M 63.000

INSTALLATIONS REGULAR PAINTINGS WITH OIL

PAINT ON PIPES EXT.D<34MM INCLUDED

070 6103220 KG 1.071

WHITE PAINT (FP) V.101-1 NTR 90-80

Page 133: ITB Constructii Noi Rev1

133

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: ELECTRIC INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 EA02A1 [ 2] M 450.000

PROTECTION INSULATION TUBE,IPEY SEALED

RECESSED WITH D=16/13.4MM

002 EA02B1 [ 2] M 2.000

PROTECTION INSULATION TUBE,IPEY SEALED

RECESSED WITH D=32/28.1 MM

003 SA18H2 M 4.000

UN-PLASTIF.PVC PIPES TYPE M.ASSEM.AT

CONSTR.IND+SOC IN DISTRIB.PIPES LOCATED

IN CANALES D=110

004 EA12A1 M 30.000

METALLIC,FLEXIBILE,PROTECTION,UNTIGHT

TUBE, WITH 2 ROWS OF COILS IN

QUADRILATERAL-SHAPE(SPD) 13,5-23 MM

004 7356501 M 30.750

METALIC TUBE FLEX.PROT.NONTIGHT TYPE SPD

Page 134: ITB Constructii Noi Rev1

134

-ROMAN D=13,5 MM

005 EB02A1 M 520.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION < 4 MMP

005 4826880 M 535.600

CONDUCTOR FY 1X 1,5 S 6865

006 EB02A1 M 730.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION < 4 MMP

006 4826892 M 751.900

CONDUCTOR FY 1X 2,5 S 6865

007 EB02B1 M 20.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION 6- 10 MMP

007 4826921 M 20.600

CONDUCTOR FY 1X 10 S 6865

008 EC01B1 M 12.000

ELECTRICAL CABLE LAMP,PLUG SECT.<4MMP

MONTAT BACH.PE DIBLURI MAT.PLASTIC

008 7500271 M 12.360

COPPER FLEXIBLE CABLE MYYM 3x1.5

009 EC12A1 BUC. 4.000

INTERIOR TERMINAL CONNEC.TO CLAMPS WITH

CU.PIPES <2X10MMP

010 ED09A1 [ 2] BUC. 2.000

TWIN PLUG WITH PROTECTION CONTACT

16A 220V

010 5536561 BUC. 2.020

TWIN PLUGS 16A 220V EX.EDIICT5 COD

7055A

011 ATB03A [ 1] BUC. 1.000

INSTALLING PROGRAMMABLE THERMOSTAT

012 ATD13A M 6.000

MEASUREMENT,CDA,SIGNALLING CABLE SET ON

WALL,GARRET,WITH:UP TO 10 WIRES

OF 1,5-2,5 SQMM

012 4812566 M 6.090

CSYY FLEXIBLE CABLE 3 X 1,5 S 8779

013 ATD16A BUC. 2.000

FORMATION OF CABLE END.,LONG UNDER 1 M,

INSULATION AND PVC COVER,UNDER 10 WIRES

NONARMATURE

Page 135: ITB Constructii Noi Rev1

135

014 ED01A1 BUC. 2.000

MANUAL SWITCH BURIED UNIPOLAR NORMAL OR

WATERPROOF CONSTRUCTION *

014 5500720 BUC. 2.020

CUMPANA SWITCH ST.250V 10A

015 ED03A1 BUC. 10.000

UNIPOLAR SWITCH BURIED,WOODEN NAILS,IN

SERIES,NORM.CONSTR.OF BACHELITA OR

WATERPROOF CONSTR.

015 5520366 BUC. 10.100

CUMPANA SHIFTER ST.250V 10A

016 ED08A1 BUC. 2.000

PLUG BURIED ASSEM.NORMAL CONSTR.

WATERPROOF OR NORMAL PROTECTION CONTACT

016 5536156 BUC. 2.020

TWIN PLUG PROT.PANEL 250/10A RECESSED

017 ED08B1 [ 1] BUC. 18.000

DOUBLE TWIN PLUG WITH PROTECTION

CONTACT RECESSED MOUNTED

017 5535994 BUC. 18.180

DOUBLE TWIN PLUG,PROT.CONTACT 250/10A

RECESSED

018 EE12B1 BUC. 3.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

018 5103642 BUC. 3.009

FLUOR.LUMINAIRE FIRA 03-1X36 W DOUBLE

REFL.PARAB.EQUIPPED,VISIBLE SET

019 EE12B1 BUC. 8.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

019 5103656 BUC. 8.024

FIRA FLUORESCENT LIGHT FIXTURES 03-2X36

W DOUBLE REFL.PARAB.

020 EE12B1 BUC. 14.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

020 5103671 BUC. 14.042

FIRA 03-4X18 W FLUOR.FIXTURE DOUBLE

REFL.PARAB.7 PLATES,ASSEMBLED

021 EE12B1 BUC. 2.000

Page 136: ITB Constructii Noi Rev1

136

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

021 5103823 BUC. 2.006

FLUORESCENT LIGHT FIXTURES AB 02-1X18 W

VISIBLY SET

022 EE12G1 BUC. 1.000

FIXTURE FOR TUBE FLUORESCENT LAMPS SEALED

SET ON PLASTIC MATERIAL DOWELS

022 5103836 BUC. 1.030

FIPAD 04-2X36 W FLUOR.FIXTURE PC DISPER.

STARTER,UNASSEMBLED

023 EE14B1 BUC. 2.000

TUBULAR FLUORESCENT LAMP SET INSIDE

CONSTR.OR ON EXTER.ELEM.AT NON TIGHT OR

TIGHT LUMINAIRES

023 5102336 BUC. 2.140

TUBULAR FLUORESCENT LAMP 220V-36W

024 EE11A1 [ 1] BUC. 2.000

TIGHT FIXTURE (PROJECTOR) SET ON SUPPORT

024 5103864 BUC. 2.006

LUXOR PROJECTOR 02-150W SODIUM VAP.

SYMETRIC/ASYMETRIC REFL.

025 EE14C1 [ 2] BUC. 2.000

LAMP MONT.INSIDE CONSTR.OR EXTERIOR

ELEM.WITH SODIUM VAP.FOR FIXTURES

NON SEALED OR SEALED

025 5102368 BUC. 2.100

@SODIUM VAPOR LAMP 220 V 150W

026 EF02A1 [ 1] BUC. 1.000

INSTALLING PANEL FITTED ACCORDING TO

ANNEX

026 YC01M MII LEI.

MATERIAL PRICE DIFFERENCE THOUSAND LEI

027 EF09B1 BUC. 10.000

COPPER PIPE JOINNING AT DEVICE

MARKLANDS,MOTORS,POWER PANNELS HAVING

SECTION 10 OR 16MMP

027 5203059 BUC. 10.000

BRASS PUNCHING SLIPPER FOR COPPER COND.

5X 3,1 MMP

Page 137: ITB Constructii Noi Rev1

137

028 EF10A1 BUC. 68.000

ELECTRIC CONNECTION (CONEC.) BETWEEN

SAFETY CLAMPS AND DEVICES,OR BETWEEN

DEVICES,WITH PIPE L<0,5 M

028 4826919 M 23.800

CONDUCTOR FY 1X 6 S 6865

029 EG07B1 M 4.000

DOWN.PIPES STEEL-ZINK BAND 25X4MM,

APPARENT ASSEMBLED ON WALLS

030 EG08B1 M 50.000

COND.EARTH CONNECTION LIGHTING ROD

UNDERGROUND EARTH CONN.GALVANIZED STEEL

STRIP 40X4MM IN HARD SOIL *

031 W1R06A1 M 9.000

ELECTRODE OF STEEL PIPE OF TWO AND

A HALF INCHES FOR EARTH GROUNDING

IN NORMAL GROUND

032 EG10A1 [ 1] BUC. 1.000

SEPARATION PIECE FOR EARTHING BELT

033 W1P08A BUC. 1.000

EARTH CONN.TESTING FOR BUILDING WIRING

034 RPCU12C1 BUC. 48.000

WALL CHANELLING IN REINFORCED CONCRETE

FLOORING OF 12-13CM THICKNESS AND

SECTION 151-300SQCM

035 RPCB13B1 BUC. 48.000

B150 FILLING OF HOLES AREA OF 020SQM IN

FLOORINGS OVER 10CM THICKNESS

036 EH05A1 [ 1] BUC. 1.000

TESTING ELECTRIC PANELS

037 EH07A1 KWH. 8.000

ELECTRIC POWER FOR TESTS

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

Page 138: ITB Constructii Noi Rev1

138

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities Estimate - Tender: WATER AND SEWAGE SERVICES

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA02F1 M.C. 40.000

MAN.DIGGIN.IN LIMIT.SPACES UNDER 1M WITH

R.O.W.VERT.UNSUPPORT.IN SOIL AVER.COHEZ.

AND VERY COHEZ.DEPTH<1,5M HARD S.

002 TSA12C1 M.C. 16.000

MAN.DIGG.IN EXCAVATIONS 1-1,5M WIDE WITH

SUPP.MAN.EVAC.IN SOIL WITH NAT.MOIST AT

DEPTH 0,0-1,5M,HARD SOIL

003 TSC02B1 100 MC. 0.340

DIGGING WITH TYRE EXCAVAT.0,21-0,

39 MC NAT.MOIST.DISCHARGE GROUND

CAT.2

004 TSA18E2 M.C. 3.500

MAN.EXCAV. FOLLOWING MECHANICAL EXCAVATION

HOLES.FOUND. ELEM.NAT.MOIST.SOIL WITH

SUPPORT DEPTH< 4 M HARD SOIL

005 TSF01A1 MP. 60.000

SUPPORT.BY EDGES WITH BEECH SUPPRT.

PLACED HORIZ.EDG.BETWEEN <1,5M,DEEP.0,0-

2M,0,0 -0,2M BETWEEN EDGE

006 TSD01C1 M.C. 66.000

LOOSE SOIL SHOVEL SPREADING,UNIFORM

LAYER 10-30CM.THICK WITH BREAKBLE CLODS

HARD SOIL

007 TSD05A1 100 MC. 0.330

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

Page 139: ITB Constructii Noi Rev1

139

008 ACA10A2 [ 2] M 20.000

UNDERGROUND SETTING AT WATER SUPPLY HDPE

PIPES JOINED WITH FITTINGS THROUGH

COMPRESSURE,WITH DN 32 MM

008 7500137 M 21.000

PE WATER PIPE 100 SDR 17 PN 10 Dn=32mm

009 ACA17A2 BUC. 3.000

POLYETHILEN CONNECTION PIECES JOINED BY

COMPRESSURE FOR HDPE WATER SUPPLY PIPES

009 7500610 BUC. 1.000

PE ELBOW PIPE 900 COMPRESSION D=32

009 7500155 BUC. 2.000

FE COMPRESSION CONNECTION 32x3/4

010 ACA12C1 [ 3] M 13.000

INSTALLING PVC PIPE IN GROUND 100

COMPACT SN 4 FOR EXTERIOR SEWAGE

RUBBER TIGTH ELASTOM.RING D=160 MM

011 SD13A1 [ 1] BUC. 1.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

011 7344045 BUC. 1.000

@SPHERE FAUCET EVAC+LID+PORTHOSE DN 1/2"

CODE 40814762

012 SD13B1 [ 1] BUC. 2.000

SPHERE FAUCET WITH COUPLING,FOR STEEL

PIPES D=3/4''

012 7344059 BUC. 2.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

013 ACE12B1 BUC. 1.000

WATER METER SETTING WITH BLADES OF D 20

MM

014 M1A01B1 [ 1] BUC. 1.000

INSTALLING WASTE WATER ECOLOGICAL

TANK

015 ACD01G1 BUC. 3.000

LID AND FRAME STAS 2308-81 FOR SEWERS

WITH SUPPORT. PIECE NONCARRIAGEWAY TYPE

I

016 ACD09A1 BUC. 1.000

MON.CONCRETE MAHHOLES CIRC.SECT.TYPE

1785-2 DI 1,5 M. H 1,5 NO UNDERGROUND

WATER NONCARRIAGEWAY

Page 140: ITB Constructii Noi Rev1

140

017 ACD04A1 [ 1] BUC. 1.000

MANHOLE STAS 2448-73 WITH INSPECTION

CHAMBER HC=1M MADE OF CONCRETE TUBE WITH

TAP BOLT AND CHANNEL LIP DN 200

017 2101195 M.C. 0.038

MORTAR M100 T WITH LIME HYDRATING

017 2100933 M.C. 1.010

CEMENT CONCRETE B 100 (C6/7,5) STAS 3622

018 ACD07A1 M 1.000

ELEMENTS AT MANHOLES STAS WITH H>2 M

INCLUDES: CONCRETE TUBE ACCESS DN 800 L=

1 M WITH FANCET AND OPENING

018 2101183 M.C. 0.019

MANSONRY MORTAR M 100 S 1030

019 ACD03A1 M 2.500

STRINGER LADDED OL 50X10 AND STEPS OB

D=20MM ACCESS IN SEWERS OF CONCRETE PIPES

020 ACE05A1 [ 1] BUC. 5.000

PVC PIECE FOR PIPING TIGHT PASSAGE

THROUGH CONCRETE SEWERS WALLS

020 6311601 BUC. 2.000

@PASSAGE THROUGH PIECE INCLUDED IN PVC

32 MM WITH WATERPROOFING

020 6311607 BUC. 2.000

@PASSAGE THROUGH PIECE INCLUDED IN PVC

110 MM WITH WATERPROOFING

020 6311608 BUC. 1.000

@PASSAGE THROUGH PIECE INCLUDED IN PVC

160 MM WITH WATERPROOFING

021 ACE07A1 100 M. 0.200

WATER PIPES WASHING AND DESINFECTION

WITH DN 50

022 ACE08A1 M.C. 10.000

DITCH FILLING FOR WATER PIPE SUPPLY AND

SEWERAGE WITH: SAND

023 W2H07A1 [ 1] M 20.000

POLYETHYLENE WARNING STRIP

023 TRA01A… TONA 20.000

Page 141: ITB Constructii Noi Rev1

141

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH DUMP TRUCK DISTANCE= … KM

024 TRA01A…P TONA 58.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= … KM

025 TRI1AA03C2 TONA 58.000

MATERIAL LOADING,GROUP A-HEAVY IN DUST,

BY THROWING FROM PLATFORMS OR SOIL-CAR

CATEG.2

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: VARIABLE ARCHITECTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 22.500

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

Page 142: ITB Constructii Noi Rev1

142

002 AUT1304 ORA 165.000

SELF-LIFTING METALIC SCAFFOLD 2 CASTLES

6MARCH 75KG/M H-31M L=12M 3SHIFTS

003 CI02A1 [10] MP. 22.500

NATURAL LOCAL STONE PLATING

INCL. MESH

003 2202200 SQ.M. 22.940

BANPOTOC 1 QUALITY G=2CM S LIMESTONE SLAB

6035

004 CG06C1 MP. 6.000

MOSAIC FLOOR CAST ON SITE OF 1,5CM

THICKNESS SIMPLE WITHOUT CRIMP ON

SURFACE <5MP WITH MARBLE MOSAIC

005 CH01B1 M 10.000

PLATED SIMPLE CONCRETE TREADS WITH

PREFAB.TREADS AND RISERS WITH MARBLE

MOSAIC

005 2802892 M 10.30

MANUFACT.MARBLE STAIR CASE NAT.COLOUR

005 2802957 M 10.300

MARBLE MOSAIC RISER NATURAL COLOUR

006 CE14A1 M 3.000

GALVANIZED PLATE RAIN PIPE OF 0,5MM MADE

ON SITE SEMIROUND WITH D= 15,4CM

007 CF06A1 MP. 22.500

EXTER.REGULAR PLASTER,FLOATED FOR

DRYWALLS OR INTERIORS IN GARRET,OF 2 CM

007 2101203 M.C. 0.495

PLASTER MORTAR M25T

008 CG07B1 M 8.000

MOSAIC PLINTHS OR GORGES CAST ON SITE

SITE-HORISONTAL PLINTHS H=10CM AT MARBLE

MOSAIC WALLS

009 CH04A1 M 19.000

CURRENT WOODEN HANDRAIL

009 2948144 M 19.950

OAK WOOD HANDRAIL PRECAST SECT. 40X80 MM

010 CL20B1 KG 396.000

APPARENT METALLIC MANUFACT. ASSEMBLYING:

GRATES BANISTERS,TRAP DOOR,CHECKS, GRILL

010 6306274 KG 396.000

SIMPL.DECORATIVE LATTICE WORK FOR

STAIRCASES,PROFILED STEEL BALCONY

011 CN11B1 MP. 18.000

Page 143: ITB Constructii Noi Rev1

143

DYE WORKS AT BANISTERS,GRID,METALLIC

PARAPET WITH ALCHIDICAL ENAMEL

011 6108347 KG 1.260

REDISH BROWN ENAMEL UIC E.735-8 NTR 1703

-80

011 6100943 KG 1.440

ALCHID RED OXID PLASTER ROUGH G 735-3

012 CN09G1 MP. 57.000

PAINTINGS ON WOOD CARPENTERY ,DONE WITH

2 LAYERS ALCHIDIC LAQUER COLORLESS,AT

DOORS,WINDOWS ,SHUTTER.RUL.

013 CO02B1 MP. 26.000

CONCRETE PLATES WALK SIDE FOR SAND

PAVEMENTS,JOINTS FILLED WITH MASTIC

013 2800488 MP. 30.600

CONCRETE MANUFACT. FLAGSTONE 70X70X8CM

014 IZF10F1 [ 3] MP. 26.520

50MM EXTRUDED POLYSTYRENE LAYER TO

EXTERIOR WALLS GLUED BY BITUMINOUS CEMENT

015 RPCO56A1 [ 3] M 57.000

OAK WOOD BANISTERS AT PLATFORMS WITH

SIZES OF 30 X 125MM AT 3 ROWS

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Page 144: ITB Constructii Noi Rev1

144

Bill of quantities

Estimate - Tender: CONSTANT ARCHITECTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 155.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1302 ORA 435.000

METAL AUTO-LIFTING SCAFFOLD 3 CAST. 3.

5TF H=31M L=29M 3 SHIFTS

003 MDTC5517010 BUC. 2.000

EQUIPMENT TRANSPORT 10 KM 90100043

SELFLIFTING METALLIC SCAFFOLDIING WITH 2

CASTLES

004 CD05A1 M.C. 49.000

BRICK MASONRY TYPE GVP AT BUILDINGS H

<35M, SHAPE 240X115X 88MM,Q.A

004 2101169 M.C. 10.290

MASONRY MORTAR M 25 S 1030

005 CD04H1 M.C. 6.500

MASONRY FROM PRESSED BRICK 240X115X63M M

AT BUILDING.H<35M, 12,5CM THICKNESS, Q.

A,WITH VOIDS <50 %

005 2101169 M.C. 1.170

MASONRY MORTAR M 25 S 1030

006 CE15B2 [ 1] M 13.000

ALUMINIM WINDOW BOARDS

007 CF01K1 MP. 375.000

FLOATED INT.PLASTERS,AT COLUMNS,WALLS

WITH SPRINKLER AND PLASTER ROUGH CAST

MECHANICALLY PERFORMED,OF 2CM

007 2101202 M.C. 6.750

PLASTER MORTAR M10T

008 CF06K1 MP. 155.000

FLOATED EXTERNAL PLASTER ON BRICK AND

BLOCKS WALLS WITH CRUND.MECH.LAYER VIZ.

MANUALLY MORTAR M25-T THICK.2,5 CM

Page 145: ITB Constructii Noi Rev1

145

008 2101204 M.C. 3.565

MORTAR M50T

009 CF06C1 [ 6] MP. 155.000

OUTER DECORATIVE PLASTER OR

SIMILAR

010 CF10C1 MP. 496.000

PLASTER POLISHING APPLIED ON FLOATED

INTERIOR PLASTERS

011 CG01E1 [ 5] MP. 121.000

CEMENT SLAB FINISH FOR FLOORS

012 CG03B1 [ 5] MP. 52.000

PLASTIC MATERIAL FLOORING WITH

PVC CARPET FOR INTERNSE TRAFFIC WITH PVC SILL

012 6715983 MP. 53.300

TARKETT TYPE PVC CARPET

013 CG11A1 [ 2] MP. 31.000

CERAMIC TILE SLAB FLOORING ANCHORED BY

ADHESIVE PASTE

013 2422628 MP. 31.930

BROWN SMOOTH GLAZED SANDSTONE PLATES S

250X 60X12 C1 VRAC

014 RPCK42A1 M 57.000

CERAMICS TILE PLINTHS OF MAX.

15CM HIGH,HORZONTAL FOR WALLS*

014 2434891 M 58.139

UN SMOOTH SANDSTONE JOINNINGS ELEM.

GREEN S 150X100X 8 C1 S5939

015 CG28B1 MP. 121.000

5MM DIFFERENCE SUPP.LAYER FOR CEMENT

MORTAR FLOOR

015 2101200 M.C. 0.605

PLASTER MORTAR M 100 (LIME PASTE ) S

1030

016 CI06E1 MP. 80.000

WHITE TILE PLATING ADHESIVE PASTE FIXED

Page 146: ITB Constructii Noi Rev1

146

016 2401777 MP. 83.999

DECOR WHITE TILE MONOC M.DR 150X150X5,5

Q. 1 S233

017 CK11G1 [ 3] MP. 18.000

PVC DOUBLED-GLASSED WINDOWS

018 CK14A1 [ 2] MP. 31.000

WHITE COLOR PVC DOORS WITH THERMO

INSULATING GLASS 4+ 16+4MM

019 CK25C1 BUC. 10.000

CARPENTRY ACCESSORY WORKS APPLIED LOCK

TO A YALE SYSTEM

019 6310380 BUC. 10.000

SAFETY LOCK IN YALLE

SYSTEM WITH DOOR BOLT

020 CK09A1 [ 1] M 13.000

20CM WIDE PVC WINDOW BOARDS SET TO THE

INTERIOR

021 CM02E1 MP. 8.000

DRAWN WINDOWS SIMPLE MEASURE FREE ON

WOOD CARPENTERY 4-8MM THICK.WITH PUTTY

AND WANG AT VITRI

021 2500327 MP. 8.720

CLEAR DRAWN GLASS Q.3 4MM. PACKED FREE

SIZES S 853

022 CL20B1 [ 3] KG 1.000

VISIBLE METALLIC PLATEWORKS: STAINLESS

HANDRAIL TO SANITARY GROUPS FOR

HANDICAP PERSONS

023 CN06B1 [ 3] MP. 496.000

3 LAYER WHITE COLOR WASHABLE PAINTING FOR

INTERIOR FOR WALLS

024 IZF10C1 [10] MP. 155.000

THERMINSULATING LAYER FOR WALLS OF

EXPANDED POLYSTYRENE FOR FACADE OF 10CM

THICK.INCLUDING MORTAR ADHESIVE AND

SECURING NAILS

024 2602797 MP. 156.550

PEX C EXPANDED POLYSTYRENE SLAB OF

2000X500X 100MM S7461

025 CK14A1 [ 7] MP. 0.640

METALLIC HATCH GARRET ACCESS 30MIN FIRE

RESISTANT

Page 147: ITB Constructii Noi Rev1

147

025 6306458 BUC. 1.000

TRAP DOOR RF30 MINUTES

026 CM06G1 [ 1] MP. 9.000

POLYCARBONATE SUN-BLIND INCLUDING

METALLIC STRUCTURE

027 TRA06A05 TONA 49.500

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: CONSTANT ARCHITECTURE GARRET

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 37.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1302 ORA 195.000

METAL AUTO-LIFTING SCAFFOLD 3 CAST. 3.

Page 148: ITB Constructii Noi Rev1

148

5TF H=31M L=29M 3 SHIFTS

003 CD05E1 M.C. 8.000

BRICK MASONRY GVP TYPE FOR

CONSTR.H<35M, FORMAT 365X180X138MM,A Q.

003 2101169 M.C. 1.040

MASONRY MORTAR M 25 S 1030

004 CE01A1 MP. 210.000

BURNT CLAY SHAPED TILE COVER

004 2302983 BUC. 3360.000

DRAIN TILE WITH 1 BEAK Q1 390X230X11

S515

005 CE13A1 [ 5] M 55.000

STEEL GUTTERS PROTECTED BY PLASTIFOL

OF 0.5MM, SEMI-ROUND OF D=

15CM

006 CE14A1 [ 3] M 15.000

STEEL RAIN PIPES PROTECTED BY PLASTIFOL

OF 0.5MM ROUND WITH D=15.4CM

007 CE19D1 [ 1] M 52.000

TOOTHING EAVES FROM ONE SIDE

PLANE BOARD AND RABBETED

OF 70CM WIDE

007 2903830 M.C. 0.080

LONG RESIN BOARD SELVEDGED CLASS C THICK

=24MM L=3,00M S 942

008 CF06C1 [ 6] MP. 37.000

OUTER DECORATIVE PLASTER OR

SIMILAR

009 CF06K1 MP. 37.000

FLOATED EXTERNAL PLASTER ON BRICK AND

BLOCKS WALLS WITH CRUND.MECH.LAYER VIZ.

MANUALLY MORTAR M25-T THICK.2,5 CM

009 2101203 M.C. 0.851

PLASTER MORTAR M25T

010 CN15B1 [ 4] MP. 400.000

PAINTING THE TIMBER BY FIREPROOF

SOLUTIONS

011 CN15D1 MP. 100.000

PAINTING OF WOOD WORK WITH SPECIAL

SOLUTIONS,WITH ANTISEPTIC PAINTS,

WATERPROOF ON IMPREGNATE WOOD

012 CO23A1 MP. 135.000

Page 149: ITB Constructii Noi Rev1

149

BEECH BOARD WOOD FLOOR BOARDING OF 20MM

THICKNESS

013 IZF10F1 [18] MP. 135.000

INSULATING MINERAL WOOL LAYER G80 TYPE

150MM THICK. COATED,AND ^=0.040 W/MK AND

0 KG/CUBIC METER TO THE FLOORING

014 IZF10C1 [ 5] MP. 37.000

THERMO-INSULATING LAYER FOR FLOOR WITH

EXPANDED POLYSTYRENE

014 2602797 MP. 37.370

PEX C EXPANDED POLYSTYRENE SLAB OF

2000X500X 100MM S7461

015 IZF03B2 MP. 135.000

BARRIER AGAINST VAPOURS ON VERTICAL

SURFACE WITH 1STR IMPISLIT BIT TYPE /A

SAU TSA2000 LIP WITH BITUM TYPE

015 2600048 KG 202.500

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

015 2602060 MP. 148.500

BIT.2F.NIS. TSA FIBER GLASS

2000 100CM S 10126

016 IZF02A1 MP. 135.000

ROOF VAPOUR DIFFUSION LAYER,TERRACCE

WITH GLASS FIBRE KNITTING HORISONTAL

SURFACE BITUMEN

016 2600048 KG 67.500

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

017 IZF01A1 MP. 135.000

SURFACE MILDING APPLY.VAPOURS DIFUSION

LAYER WITH CUT BITUMEN IN 2 LAYERS

HORIS.AND VERT.SURFACE

017 2600048 KG 20.250

MAT.+ WORK D.P.C. BITUMEN TYPE H 80/90

S7064

018 IZF04J2 MP. 135.000

BOUNDARY LAYER RELATED TO THE INSULATION

WORK EXEC WITH FIBER GLASS FELTING

AND NON GLUED BREAKDOWN

018 2602060 MP. 145.799

BIT.2F.NIS. TSA FIBER GLASS

2000 100CM S 10126

Page 150: ITB Constructii Noi Rev1

150

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: RESISTANCE SUPER-STRUCTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CA02J1 M.C. 24.700

MOULDING REINFOR.CONCRETE TO CONSTR.WITH

H<35M,IN FLOORS(BEAMS,COLUMNS,PLATES)

WITH SLAB THICKN.>10CM

001 2100957 M.C. 24.898

CEMENT CONCRETE B 200(C12/15) STAS 3622

002 CB13A1 MP. 158.000

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTRUCTIONS WITH H<20M TO SLABS AND

BEAMS,WITH PLYWOOD OF 8MM

003 CB13B1 MP. 158.000

SHUTTERINGS MADE OF REUSED PANELS FOR

CONSTR.WITH H<20M,AT COLUMNS AND FRAMES,

WITH PLYWOOD OF 8MM

004 CB44A1 BUC. 72.000

SUST.WITH STUDS EXTENS PER3100R FOR

ASSEMBLING FLOORS,PRESLAB TURN FLOORS

MONOL WITH GR OR GR MONOL PL PREFAB.

005 CB45B1 BUC. 40.000

Page 151: ITB Constructii Noi Rev1

151

SUSTAIN. FROM METALIC BEAMS EXTENSIBLE

TO CONSTR.WITH H<20M BEAMS SUPPORT.ON

METALIC STUDS

006 RPCH38A1 [ 2] BUC. 41.000

ROUND WOODEN PROP SUPPORT D= 12 CM

AT LINTELS OVER DOOR AND WINDOW OPENINGS

007 CC01C1 KG 1555.000

CONCRETE STEEL REINFORCEMENTS ASSEMBLING

IN CONTINUOUS FOUNDATIONS,SLABS OF

PLATES,WITH DIST FROM PLASTICS

008 CZ0302A1 KG 335.000

MANUFAC. REINFORC. FOR WALLS BEAMS

COLUMNS DIAPHRAGMS TO REGULAR CONST IN

CENTRALIZED WORKSHOPS OB 37 D=6-

009 CZ0302E1 KG 795.000

MADE REINFORCED FOR WALLS BEAMS PILLARS

MIDRIFF AT BUILDG. REGULAR IN WORKSHOP

CENTRALIZED PC 52 D=10-

010 CZ0302M1 KG 120.000

MANUFCT. REINFORC. FOR PLATES INCLUD.

STAIRS TO REGULAR CONST. IN CENTRALIZED

WORKSHOPS OB 37 D=6-8MM

011 CZ0302O1 KG 840.000

MANUFCT.REINFORC.FOR PLATES INCLUD.

STAIRS TO REGULAR CONST.IN CENTRALIZED

WORKSHOPS PC 52 D= 6-8MM

012 CP12A1 BUC. 10.000

ASSEMBL.PREFAB.TO HOUSING WITH STRUCT.

MONOL.MIXED AND BRICKWORK.SUST.WITH.VOL.

0,2 MC.AND H<20 M

013 6433209 M.C. 0.400

CONCRETE PRECAST C16/20(B250) II A-

S32.5 0-16MM

014 6433376 KG 27.000

CONCRETE PREFABR.REINFOR. OB 37 D=6-10MM

STANDARD

015 6433754 KG 14.000

REINFOR.IN CONCRETE PREFABR. PC52 O6-10

MM STANDARD

016 6433754 KG 90.000

REINFOR.IN CONCRETE PREFABR. PC52 O6-10

MM STANDARD

017 AUT1301 ORA 7680.000

EXPANDING METAL GIRDER L=3-5M TYPE GE1 3

SHIFTS

018 AUT1325 ORA 13824.000

EXPANDING METAL PROP PE3100 INCLUDING

PIPE 051X3,5MM

Page 152: ITB Constructii Noi Rev1

152

019 TRA06A TONA 62.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. = KM

020 TRA02A TONA 1.600

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= KM.

021 AUT1140 ORA 30.000

TELESCOPIC JIB CRANE ON TYRES TELEMAC HT

125.5 TF 1 SHIFT

022 MDTC46230 BUC. 6.000

EQUIP.TRANSPORT KM-65121002-TYRE

CRANE OF 0,10-0,149 MN(10-14,9TF

023 MDTC5575 BUC. 80.000

EQUIPMENT TRANSPORTATION KM-90100106

EXTENSIBLE METALLIC BEAM WITHL=4-8M TYPE

CE-2

024 MDTC5552 BUC. 144.000

EQUIPMENT TRANSPORTATION KM-90100079

METALLIC POP TYPE PE-3100

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: PAVEMENTS AND PARKING

Work category:

=================================================================

Page 153: ITB Constructii Noi Rev1

153

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA01G1 M.C. 40.000

MAN. DIGGINGS IN SPREAD SPACES IN SOIL

WITH NAT.MOISTURE THROWED IN VEHICLE ATH

OF 0,61-2M HARD SOIL

002 TSC35B31 100 MC. 0.400

AUTOLOADER ON TYRES WITH BUCKET 2,6-3,9

CM LAND CATEG 2 AT DIST. 11-20 M

003 TSD01A1 M.C. 40.000

SHOVEL SPREADING OF MELLOW EARTH

UNIFORM LAYER 10-30CM.THICK BY

CLODS CRUSHING,SOFT GROUND

004 TSD05A1 100 MC. 0.400

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

005 TSE06B1 100 MP. 4.000

SOIL PLATF.PREPARING ISOLATING LAYER AND

SAND REPARTION OR GRAVEL IN COHESIVE

SOIL

006 DA06A1 M.C. 60.000

NAT.AGREGG.LAYER(GRAVEL)ROLLED OVER WITH

FILTRING RESISTANCE FUNCTION ISOL.AERING

ANTICAP.MANUAL LAYING

007 TRA01A05 TONA 168.000

MATERIAL,SEMIPREFAB ROAD TRANSPORT BY

TIP LORRY ON A 5 KM DIST.

008 DD02A1 MP. 400.000

PAVMENT MADE OF NORM PAVING 1ST Q. ON

SAND SUB BASE

009 TRA01A10 TONA 140.000

MATERIAL,SEMIPREFAB ROAD TRANSPORT BY

TIP LORRY ON A 10 KM.DIST.

010 DE11A1 M 230.000

SMALL CRIMPS MANUF.CONCRETE 10X15 CM FOR

FRAMING SPACES WALK ROAD ,GREEN ALLEY

FOUND. CONCRETE10 X 20 C

010 2100933 M.C. 4.600

CEMENT CONCRETE B 100(C6/7.5) STAS 3622

011 TRA06A05 TONA 14.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

Page 154: ITB Constructii Noi Rev1

154

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

LOT NO. 5 Industrial Building

QUANTITY LIST WITH TECHNOLOGICAL EQUIPMENT, INCLUDING UTILITIES OF THE

ESTIMATE-OFFER FOR PROCUREMENT

Item Name M.U. Quantity Unitary Price

-lei/M.U.-

Amount (VAT

exclusive) -Thousand lei-

Supplier

(name, address,telephone,

Page 155: ITB Constructii Noi Rev1

155

(col.3 x 4) facsimile)

0 1 2 3 4 5 6

1 Mural Tank on gas fuel, thermo

power of 30kw

pcs 2

2 Gas Regulating filter Dn ¾˝ pcs 2

3 Gas Detector and electro-valve pcs 1

4 Programmable thermostat pcs 2

5 Water meter Qn=2.5 cubic meters/h pcs 1

6 Ecological tank for waste water,

capacity 20 m3 pcs 1

Thousand lei: TOTAL

USD*):

*) Exchange rate =…………………. Lei/USD, of …………………….

TECHNICAL SHEET No. 1

EQUIPMENT: TANK FOR HOT WATER

Item Technical specifications imposed by the Technical Specifications

Comparison between the technical proposal and

the specifications imposed by the

Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• Type: mural with forced flow and sealed burning chamber

• Thermic agent: hot water 80 – 600C

• Nominal output Pn 3 bars

• Minimum output 90%

• Net thermic power: 30 KW

• Burnt gas Connection 110/60 mm

• Volume of expansion vessel: 8 liters

• Hot water flow Dt=250. C 13 l/min

• Primary connection 3/4˝

- gas 3/4˝ - water feed pipe - outlet 1/2˝

• gas consumption 3.4 Ncubic meters/h

• Fuel nominal output: 20 mbar

2. Performance specs and conditions related to safety in exploitation:

• The tank shall be fitted out with flame extinguishing protection system, electric current

supply cut off, and pressure building up in

Page 156: ITB Constructii Noi Rev1

156

installation

• To be granted the I.S.C.I.R. endorsement.

• The Technical Book shall be presented in Romanian wording.

3. Conditions related to compliance with relevant standards:

4. Guarantee and post-guarantee conditions:

• 3 years guarantee;

• 3 days for solving out issues occurred during the guarantee period;

• 10 days for providing spare parts in the post-

guarantee period

5. Other condition of technical character: the electro-pump shall provide the pressure head of water of 2

mH2O to tank’s nominal load.

TECHNICAL SHEET No. 2

EQUIPMENT: GAS REGULATING FILTER

Item Technical specifications imposed by the

Technical Specifications Comparison between the technical proposal and the

specifications imposed by the Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• maximum entrance pressure: 200 mbar

• outlet pressure: 20 mbar

• connection diameter: 3/4˝

2. Performance specs and conditions related to safety in exploitation:

- To be granted a Technical Agreement or an homologation document;

- The Technical Book shall be presented in

Romanian wording.

3. Conditions related to compliance with relevant standards:

4. Guarantee and post-guarantee conditions: - 3 days for solving out issues occurred during

the guarantee period;

- 10 days for providing spare parts in the post-guarantee period.

5. Other condition of technical character:

TECHNICAL SHEET No. 3

EQUIPMENT: GAS DETECTOR AND ELECTRO-VALVE

Page 157: ITB Constructii Noi Rev1

157

Item Technical specifications imposed by the

Technical Specifications

Comparison between the

technical proposal and the specifications imposed by

the Technical

Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• Lower sensitivity limit: 2%CH4 in air

• Electro-valve nominal diameter: 1″

• Normal closed electro-valve, with one step

• Pressure: max 200 bar

• Male electro-valve connection

• Power supply: 230 V/50 Hz;

• Location: in the central heating, and the

electro-valve to the exterior

2. Performance specs and conditions related to safety in exploitation:

• Closing period: < 1 sec.

• Opening period: < 1 sec.

3. Conditions related to compliance with relevant standards: supplier must be certified according to Standards family ISO 9001

4. Guarantee and post-guarantee conditions:

• 3 years guarantee.

5. Other condition of technical character:

TECHNICAL SHEET No. 4

EQUIPMENT: PROGRAMMABLE ELECTRONIC THERMOSTAT

Item Technical specifications imposed by the

Technical Specifications Comparison between the technical proposal and the specifications imposed by

the Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters:

• Type: single pole, change over contacts, with “on-off” switch Power supply: 230V /

50 Hz.

• Maximum current to thermostat contacts: 6 A

• Control temperature area: 10 – 300C

• Use temperature area: 10 – 50 0C

• Protection degree IP 30

• Dt=0.5 K

2. Performance specs and conditions related to safety in exploitation:

• To be granted a Technical Agreement and

an homologation document;

• The Technical Book shall be presented in Romanian wording.

3. Conditions related to compliance with relevant

Page 158: ITB Constructii Noi Rev1

158

standards:

4. Guarantee and post-guarantee conditions:

• 3 days for solving out issues occurred during the guarantee period;

• 10 days for providing spare parts in the post-guarantee period.

5. Other condition of technical character:

TECHNICAL SHEET No. 5

EQUIPMENT: WATER METER Qn=2.5 cubic meters/h

Item Technical specifications imposed by the Technical Specifications

Comparison between the technical proposal and

the specifications

imposed by the Technical Specifications

Supplier

0 1 2 3

1. Technical and Functional Parameters: -Type: multi-jet, and dry dial

-Nominal output: 2.5 cubic meters/h -Nominal diameter: 20 mm - Connection sizing: 3/4˝

-Connection type: coupling -Design pressure Pn 6 bars

2. Performance specs and conditions related to safety in

exploitation: - To be granted a Technical Agreement or an

homologation document;

- The Technical Book shall be presented in Romanian wording.

3. Conditions related to compliance with relevant standards:

-Accuracy category: B

4. Guarantee and post-guarantee conditions:

-3 years guarantee - 3 days for solving out issues occurred during the guarantee period

5. Other condition of technical character:

TECHNICAL SHEET No. 6

EQUIPMENT: ECOLOGICAL TANK FOR WASTE WATER

Item Technical specifications imposed by the Technical Comparison between the Supplier

Page 159: ITB Constructii Noi Rev1

159

Specifications technical proposal and the

specifications imposed by the Technical Specifications

0 1 2 3

1. Technical and Functional Parameters:

-Material: polyester -Net volume: 20 cubic meters -Diameter: 2.5 linear meters

-Length: 4.15 linear meters -Installing: buried

2. Performance specs and conditions related to safety in exploitation:

• To be granted a Technical Agreement or an homologation document;

3. Conditions related to compliance with relevant

standards: - SR EN 12566-1

4. Guarantee and post-guarantee conditions:

- 3 years guarantee.

5. Other condition of technical character: Minimum life cycle: 30 years

- Equipment List TE-

- enclosed panel 48 modules 1 PCS - automatic switch 4P 63A, with differential prot. device Id=100mA, Icn=9kA, curve C 1 PCS

- circuit breaker phase-null 6A, Icn=4,5kA, curve C 4 PCS - circuit breaker phase-null 16A, Icn=4,5kA, curve C 10 PCS - circuit breaker 4P 10A, Icn=4,5kA, curba C 3 PCS

- circuit breaker 4P 25A, Icn=6kA, curba C 1 PCS - copper clamps 25mmp 5 PCS

- copper clamps 6mmp 5 PCS - copper clamps 2,5mmp 55 PCS - copper conductor 1…4mmp 8 m

- tags 18 PCS - warning plate 1 PCS

Bill of quantities

Estimate - Tender: HEAT INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

Page 160: ITB Constructii Noi Rev1

160

001 IA07A1 [ 3] BUC. 2.000

INSTALLING MURAL BOILER FOR PREPARING HEAT

CARRIER AND HOT WATER, WITH A HEAT OUTPUT

OF: 25.1-70 KW

002 ATB03A [ 1] BUC. 2.000

INSTALLING PROGRAMMABLE THERMOSTAT

003 IB02A01 [ 3] BUC. 28.000

INSTALLING FINISHED STEEL SHEET

RADIATORS H 600 MM

003 5700864 BUC. 4.000

STEEL RADIATOR TYPE22 600/500 MM

003 5700865 BUC. 1.000

STEEL RADIATOR TYPE22 600/600 MM

003 5700866 BUC. 2.000

STEEL RADIATOR TYPE22 600/700 MM

003 5700867 BUC. 2.000

STEEL RADIATOR TYPE22 600/800 MM

003 5700868 BUC. 2.000

STEEL RADIATOR TYPE22 600/1000 MM

003 5700869 BUC. 11.000

STEEL RADIATOR TYPE22 600/1200 MM

003 5700870 BUC. 6.000

STEEL RADIATOR TYPE22 600/1400 MM

004 IC08B1 M 94.000

OL PIPE INST.WELD.LONG.NG+THREAD+

COUPLING HEAT.C.HOUSING+SOC.INS.CONNEC.

HEAT.BODY+AERING D=1/2 I

004 3305671 M 94.000

BLACK INST.PIPE THREAD+COUPLING M - 15(

1/2) OL 32 1 S 7656

005 IC08C1 M 9.000

OL PIPE INST.WELD.LONG.NG+THREAD+

COUPLING HEAT.C.HOUSING+SOC.INS.CONNEC.

HEAT. BODY+ AERING D=3/4 T

005 3305683 M 9.000

BLACK INST.PIPE THREAD+COUPLING M - 20(

3/4) OL 32 1 S 7656

Page 161: ITB Constructii Noi Rev1

161

006 IC10B1 M 65.000

OL PIPE INST.WELD.LONG.NG+THREAD+

COUPLING HEAT.C.HOUSING+SOC.INS.IN

DISTRIBUTION D= 3/4 INCHES

006 3305683 M 65.975

BLACK INST.PIPE THREAD+COUPLING M - 20(

3/4) OL 32 1 S 7656

007 IC10C1 M 85.000

OL PIPE INST.WELD.LONG.NG+THREAD+

COUPLING HEAT.C.HOUSING+SOC.INS.IN

DISTRIBUTION D= 1 INCHES

007 3305695 M 86.275

BLACK INST. PIPE FL+MF M - 25(1 ) OL 321

S 7656

008 IC10D1 M 36.000

OL PIPE INST.WELD.LONG.NG+THREAD+

COUPLING HEAT.C.HOUSING+SOC.INS.IN

DISTRIBUTION D= 1 1/4 INCHES

008 3305700 M 36.540

BLACK INST.PIPE THREAD+COUPLING M - 32(1

1/4) OL 32 1 S 7656

009 IC10E1 M 19.000

OL PIPE INST.WELD.LONG.NG+THREAD+

COUPLING HEAT.C.HOUSING+SOC.INS.IN

DISTRIBUTION D= 1 1/2 INCHES

009 3305712 M 19.285

BLACK THREADED+COUPLINGS PIPE M - 40(1 1

/2) OL 32 1 S 7656

010 IC35C1 BUC. 88.000

CLAMPS FIXING STEEL PIPES AT HEATING

INST.OR GASES ASSEMBLED IN BRICK OR

CONCRETE WALL D= 1/2 INCHES

011 IC35D1 BUC. 24.000

CLAMPS FIXING STEEL PIPES AT HEATING

INST.OR GASES ASSEMBLED IN BRICK OR

CONCRETE WALL D= 3/4 INCHES

012 IC35E1 BUC. 26.000

FIXING STEEL PIPES AT WARMING

INSTALLATION OR GASE ASSEM.IN BRICK WALL

OR CONCRETE D=1 INCHES

013 IC35F1 BUC. 10.000

CLAMPS FIXING STEEL PIPES AT HEATING

INST.OR GASES ASSEMBLED IN BRICK OR

CONCRETE WALL D=1 1/4 INCHES

Page 162: ITB Constructii Noi Rev1

162

014 IC35G1 BUC. 6.000

FIXING CLAMPS FOR STEEL PIPES HEATING

INST.OR GAS SET IN BRICKWORK OR CONCRETE

D=1 1/2 INCHES

015 IC37A1 [ 1] KG 20.000

PIPE SUPPORTS,DIFFERENT TUBES, COLECTOR-

DISTRIB DEVICES, RECIPIENTS DIV.UP TO

2KG.INCL./PIECE

016 IC40A1 BUC. 16.000

MANUF.ASSEMBLY+CEMENTATION OF PROTECTION

PIPE AT PIPES PASSING THROUGH WALLS D=1

INCHES

017 IC40B1 BUC. 18.000

MANUF.ASSEMBLY+CEMENTATION OF PROTECTION

PIPE AT PIPES PASSING THROUGH WALLS D=1

1/4 INCHES

018 IC40D1 BUC. 4.000

PROTECTION PIPE MANUFACTURE ASSEMBLY+

CEMENTED AT PASSING OF PIPES TROUGH

WALLS D=2 INCHES

019 IC40F1 BUC. 2.000

PROTECTION PIPE MANUFACTURE ASSEMBLY+

CEMENTED AT PASSING OF PIPES TROUGH

WALLS D=3 INCHES

020 ID01A2 BUC. 56.000

CORNER VENTIL DOUBLED FAUCET ADJUSTM.FOR

CENTRAL HEAT.INSTALLATION WITH D: 1/2''

020 4507207 BUC. 28.000

@CORNER FAUCET ROUND DN 1/2" CODE

4O020407

020 4507209 BUC. 28.000

CORNER FAUCETV ADJUSTMENT BECK DN 1/2"

CODE 4O120408

021 ID06A1 [ 1] BUC. 6.000

COUPLING SPHERE FAUCET CENT.HEAT.INSTL.

HAVING DN=1/2"

021 7344049 BUC. 6.000

@BALL GAUGE COCK+HOSEBEARING+LEVER MANEV

DN 1/2" COD 40761487

022 ID06A1 [ 1] BUC. 4.000

COUPLING SPHERE FAUCET CENT.HEAT.INSTL.

HAVING DN=1/2"

022 7344030 BUC. 4.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

Page 163: ITB Constructii Noi Rev1

163

DN 1/2" CODE 40430425

023 ID06A2 [ 1] BUC. 4.000

COUPLING SPHERE FAUCET FOR CENT.HEAT.

INSTL.HAVING DN=3/4"

023 7344059 BUC. 4.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

024 ID06B2 [ 1] BUC. 2.000

COUPLING SPHERE FAUCET FOR CENT.HEAT.

INSTL.HAVING DN=1 1/2"

024 7344119 BUC. 2.000

@SPHERE FAUCET MALE+LEVER MANEV DN 1"1/4

COD 46460425

025 ID15A1 [ 1] BUC. 2.000

AUTOMATIC EXHAUSTER CENTR.HEATING INST.

DN 1/2"

026 ID06B2 [ 3] BUC. 1.000

Y TYPE INCLINED FILTER FOR IMPURITIES

WITH D: 1 1/2''

027 IC54B1 BUC. 4.000

SOFT CAST IRON BLACK THREAD INTER-

EXTERIOR U2 UNION D =3/4 INCHES

028 IC54C1 [ 1] BUC. 2.000

U2 BLACK UNION PLASTIC CAST IRON MALE

FEMALE D =1 1/2 INCHES

029 IE01C1 MP. 226.000

TIGHTNESS PRESSURE TEST CENTRAL HEATING,

TOTAL HEAT AREA OF BUILDING IS:201 SQM.

TO 500

030 IE02C1 MP. 226.000

DILAT.-CONTRACT.AND FUNCT.TEST CENTR.

HEAT.INSTL.TOTAL HEATING AREA IS:201 MP.

LA 500

031 IE07C1 MP. 226.000

TAP WATER CLEANING OF THE INTERIOR

INSTALLATION OF CENTRAL HEATING WITH

SUPP. DEVICE 201-500 MP.

032 CN13A1 M 168.000

INSTALLATIONS REGULAR PAINTINGS WITH OIL

PAINT ON PIPES EXT.D<34MM INCLUDED

Page 164: ITB Constructii Noi Rev1

164

032 6103220 KG 2.856

WHITE PAINT (FP) V.101-1 NTR 90-80

033 CN13C1 MP. 16.000

PAINTINGS AT INSTALLATION DONE WITH OIL

PAINTS ON PIPES WITH EXTERNAL D >34MM

INCL.

033 6103220 KG 2.400

WHITE PAINT (FP) V.101-1 NTR 90-80

034 IZJ07B1 MP. 2.000

ROUGH CASTING OF PIPES AND DEVICES,WITH

PLASTER ROUGH CAST LEAD IN TWO LAYERS

035 IZH22A1 [ 2] MP. 4.000

PIPE INSULATION WITH MINERAL WOOL SHELLS

AND ALUMINIUM FOLIATING OF 40 MM.

THICKNESS

035 2609490 M 9.270

@MINERAL COTTON SHELLS VILLAS DN48 G=40

CASER SHEET AL

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: GAS INSTALLATION

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

Page 165: ITB Constructii Noi Rev1

165

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA02F1 M.C. 25.000

MAN.DIGGIN.IN LIMIT.SPACES UNDER 1M WITH

R.O.W.VERT.UNSUPPORT.IN SOIL AVER.COHEZ.

AND VERY COHEZ.DEPTH<1,5M HARD S.

002 TSC02B1 100 MC. 0.850

DIGGING WITH TYRE EXCAVAT.0,21-0,

39 MC NAT.MOIST.DISCHARGE GROUND

CAT.2

003 TSD01C1 M.C. 83.000

LOOSE SOIL SHOVEL SPREADING,UNIFORM

LAYER 10-30CM.THICK WITH BREAKBLE CLODS

HARD SOIL

004 TSD05A1 100 MC. 0.830

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

005 ACE08A1 M.C. 27.000

DITCH FILLING FOR WATER PIPE SUPPLY AND

SEWERAGE WITH: SAND

006 W2H07A1 [ 1] M 170.000

POLYETHYLENE WARNING STRIP

007 W2G01A01 M 174.000

UNDERGR.CABLE SETTING 1 KV GR.0,050-0,

150 KG/M CU-AL IN DITCH ON SAND LAYER

WITHOUT OBST.WITH MAN.PULLING ASSEM.

007 4801660 M 177.478

POWER CABLE CYY 0,6/ 1KV 1X 1,5 U

S.8778

008 GD02E1 [ 1] M 170.000

POLYETYLENE PIPE FOR GAS BRANCHES

WITH DN 65 MM

008 7500115 M 171.700

PE GAS PIPE 100 SDR11 DN=63x5.8mm

009 GD14B1 [ 1] BUC. 2.000

HDPE/STEEL REISER TYPE PASSAGE THROUGH

PIECE PE 100 DN 63X2"

010 IA41B1 BUC. 1.000

GAS METER SET ON EXISTING METER PLATE 1

1/4''CONNECTIONS

Page 166: ITB Constructii Noi Rev1

166

011 IA45A2 BUC. 1.000

GAS METER PLATE WITH 1 1/4''CONNECTION

012 IC30A1 M 1.500

OL.INST.PIPE LONG.WELDED BLACK SMOOTH

GAS INST.HOUSING+SOC.CULT.BUILDINGS WELDING

IN DISTRIBUTION D= 3/4 INCHES

012 3304835 M 1.523

NON THREADED BLACK PIPE M - 20( 3/4) OL

32 1 S 7656

013 IC30B1 M 8.000

OL.INST.PIPE LONG.WELDED BLACK SMOOTH

GAS INST.HOUSING+SOC.CULT.BUILDINGS WELDING

IN DISTRIBUTION D= 1 INCH

013 3304847 M 8.120

NON THREADED BLACK PIPE M - 25(1) OL 32

1 S 7656

014 IC34C1 BUC. 3.000

SOFT CAST IRON FITTINGS SCREWED COUPLING

STEEL PIPES PIECES HAVING 2 SCREWING D=3

/4 INCH

014 4117930 BUC. 1.000

FLEXIBLE CAST IRON ELBOW A1 S474 DN 20 3

/4

014 4123197 BUC. 2.000

FLEXIBLE CAST IRON NIPPLE PIPE N8 S478 DN

20 3/4 DS

015 IC34D1 BUC. 12.000

SOFT CAST IRON FITTINGS FOR SCREWED

JOIN.STEEL PIPES PIECES BEING WITH 2

SCREWS FOR D=1 INCHES

015 4117966 BUC. 8.000

FLEXIBLE CAST IRON ELBOW PIPE A1 S474 DN

25 1

015 4123240 BUC. 2.000

FLEXIBLE CAST IRON NIPPLE PIPE N8 S478 DN

25 1 DS

015 4113934 BUC. 2.000

FLEXIBLE CAST IRON REDUCTION N4 S 477

25X 20 F1

016 IC34G1 BUC. 2.000

IRON CAST FITTINGS PLIANT FOR COUPLING

SCREWED STEEL PIPES THE PIECES BEING

WITH 2 SCREW ON FOR D=2 INCHES

016 4114160 BUC. 2.000

Page 167: ITB Constructii Noi Rev1

167

FLEXIBLE CAST IRON REDUCTION N4 S 477

50X 25 F2

017 IC34N1 BUC. 1.000

SOFT CAST IRON FITTINGS SCREWED

GALVANIZED PIPES HIDRANTS COLUMNS, 3

SCREWS D=1 INCHES

017 4115463 BUC. 1.000

IRON CAST TEE B1 S476 DN= 25 1

018 IC35D1 BUC. 1.000

CLAMPS FIXING STEEL PIPES AT HEATING

INST.OR GASES ASSEMBLED IN BRICK OR

CONCRETE WALL D= 3/4 INCHES

019 IC35E1 BUC. 4.000

FIXING STEEL PIPES AT WARMING

INSTALLATION OR GASE ASSEM.IN BRICK WALL

OR CONCRETE D=1 INCHES

020 IC40C1 BUC. 1.000

MAKING ASSEMBL+CONCRETING PROTECTION

PIPES AT PASSING OF PIPES TROUGH WALLS D

=1 1/2 INCHES

021 ID20B1 [ 2] BUC. 2.000

BALL GAUGE COCK FOR GAS INSTALLATION

WITH DN: 3/4"

021 7344059 BUC. 2.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

022 ID20C1 [ 1] BUC. 2.000

BALL GAUGE COCK FOR GAS INSTALLATION

AVAND DN 1 ''

022 7344085 BUC. 2.000

@BALL VALVE FIXFI+LEVER MANEV DN 1" COD

40450425

023 ID20C1 [ 2] BUC. 1.000

INSTALLING GAS DETECTOR WITH

ELECTRO-VALVE D: 1"

024 GD10A1 BUC. 2.000

AIR HOLE WITH NO CONTROL COVER 1-2

INCHES

025 IE06A1 M 9.500

FINAL VERIFICATION AT PRESSURE OF

ASSEMBLY GAS CONDITIONS TAPS D: UP TO

1''

Page 168: ITB Constructii Noi Rev1

168

026 IE06B1 M 170.000

FINAL CHECKING OF PRESSURE OF GAS

MOUNTED GAS PIPES, TAPS , D:

OVER1''

027 IE06B1 M 16.000

FINAL CHECKING OF PRESSURE OF GAS

MOUNTED GAS PIPES, TAPS , D:

OVER1''

028 CN13A1 M 9.500

INSTALLATIONS REGULAR PAINTINGS WITH OIL

PAINT ON PIPES EXT.D<34MM INCLUDED

028 6103311 KG 0.162

CREAM-YELLOW COLOUR PAINT V.451-3 NTR 90

-80

029 TRA01A… TONA 54.000

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH DUMP TRUCK DISTANCE= … KM

030 TRA01A…P TONA 49.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= … KM

031 TRI1AA03C2 TONA 49.000

MATERIAL LOADING,GROUP A-HEAVY IN DUST,

BY THROWING FROM PLATFORMS OR SOIL-CAR

CATEG.2

032 YB01M [ 1] MII LEI. 1.000

RECEPTION OF GAS INSTALLATION

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Page 169: ITB Constructii Noi Rev1

169

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: SANITARY INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 SA12B1 [ 3] M 44.000

PEXAL PIPE MONT.IN CONNECTION PIPES

OF SANIT.SUNDRIES D= 16 MM

002 SA12C1 [ 3] M 13.000

PEXAL PIPE MONT.IN CONNECTION PIPES

OF SANIT.SUNDRIES D= 20 MM

003 SA12D1 [ 1] M 5.000

PEXAL PIPE ASSEM.IN PIPES OF CONN.AT

SANIT.OBJECTS DN 26 MM

004 SA06B1 M 45.000

STEEL PIPE LONGIT.WELDED FOR ZINCKED

INSTAL.WITH THREAD+COUPLING ASSEM.LOC.+

SOC. CULT.IN DISTRIB. D=1 T

004 3306352 M 45.450

GALVANIZED INST.PIPE THREAD M - 25(1 ) OL

32 1 S 7656

005 SA43C1 [ 1] BUC. 55.000

FIXING PIPE BRACE DN 16 MM

006 SA43D1 [ 1] BUC. 15.000

FIXING PIPE BRACE DN 20 MM

007 SA43E1 [ 1] BUC. 7.000

FIXING PIPE BRACE DN 26 MM

008 SA43E1 BUC. 30.000

CLAMP FOR FIXING STEEL+PVC PIPE OF WATER

+GAS SUPPLY, ASSEM.BY TOOTHING,PIPE D=1

INCH

009 SB16A1 [ 1] M 7.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 32 MM

Page 170: ITB Constructii Noi Rev1

170

010 SB16C1 [ 1] M 12.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 50 MM

011 SB16D1 [ 1] M 12.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D= 75 MM

012 SB16E1 [ 1] M 16.000

SEWAGE FIREPROOF POLYPROP.PIPE RUBBER

SEAL JOINING D=110 MM

013 SB17A1 [ 1] BUC. 12.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D= 32MM

013 6712369 BUC. 6.000

@HTB POLYPROPYLENE ELBOW AT 87 DGR 30

MIN DN 32 COD 62504011

013 6712226 BUC. 6.000

@HTB POLYPROPYLENE ELBOW AT 45 DGR DN 32

CODE 62504011

014 SB17C1 [ 1] BUC. 13.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D= 50MM

014 6712381 BUC. 2.000

@HTD POLYPROPYLENE ELBOW AT 87 DGR 30

MIN DN 50 COD 62504035

014 6712243 BUC. 11.000

@HTB POLYPROPYLENE ELBOW AT 45 DGR DN 50

COD 62504029

015 SB17E1 [ 1] BUC. 20.000

SEWAGE FIREPROOF POLYPROP.ELBOW RUBBER

SEAL JOINING D=110 MM

015 6712264 BUC. 20.000

@HTD POLYPROPYLENE ELBOW AT 45 DGR DN

110 COD 62504053

016 SB19A1 [ 1] BUC. 1.000

SEWAGE FIREPROOF POLYPROP.SIMPLE UNIFORM

BRANCH RUBBER SEAL JOINING D= 50 MM

016 6712812 BUC. 1.000

@HTEA POLYPROP.EQUAL BRANCH 45GR DN50/50

CODE 62508013

Page 171: ITB Constructii Noi Rev1

171

017 SB19C1 [ 2] BUC. 2.000

FIREPROOF POLYPROP. SIMPLE LOW BRANCH

RUBBER SEAL JOINING D=110/ 50 MM

017 6712848 BUC. 2.000

@HTEA POLIPROP SIMPLE REDUCED BRANCH 45

DGR DN110/50 COD 62510031

018 SB19C1 [ 1] BUC. 8.000

SEWAGE FIREPROOF POLYPROP.SIMPLE UNIFORM

BRANCH RUBBER SEAL JOINING D=110 MM

018 6712862 BUC. 8.000

@HTEA POLIPROP SIMPLE EQUAL BRANCH 45

DGR DN 110 COD 62508025

019 SB21C1 [ 1] BUC. 3.000

SEWAGE FIREPROOF POLYPROP.INTERVENTION

PART RUBBER SEAL JOINING D=110 MM

020 SB22E1 [ 1] BUC. 2.000

FIREPROOF POLYPROP.REDUCING COUPLING FOR

SEWERAGE RUBBER SEAL D=110- 50 MM

021 SB22F1 [ 1] BUC. 3.000

SEWAGE FIREPROOF POLYPROP.REDUCING PIECE

RUBBER SEAL JOINING D=110- 75 MM

022 SB24D1 [ 1] BUC. 3.000

AERATION CAP MEMBRANE SET ON PP PIPES DN

75 MM

023 SB44D2 [ 1] BUC. 2.000

HDPE GULLY TRAP D= 50 MM WITH 2

CONNECTIONS AND VERTICAL EXIT

024 SA43H1 [ 1] BUC. 5.000

TUBE CLIP DN 50 MM

025 SA43J1 [ 1] BUC. 9.000

TUBE CLIP DN 75 MM

026 SA43K1 [ 1] BUC. 3.000

TUBE CLIP DN 110 MM

027 SC07A1 [ 2] BUC. 4.000

SANITARY PORCELAIN LAVATORY, SET ON

CONSOLES ANCHORED BY WOODEN DOWELS ON

Page 172: ITB Constructii Noi Rev1

172

BRICKWALL,INCL.SINK WATER TRAP AND VALVE

027 2442288 BUC. 4.040

PORCELAIN BASIN WITHOUT REST L 2-600MM

WHITE C.1 S 1540

027 4203557 BUC. 8.000

ENAMELLED DOUBLE ARM CONSOLE 420MM QAL.1

S 3343

028 SC07E1 [ 1] BUC. 2.000

SANIT.PORCELAIN LAVATORY L2 600 ON STAND

INCLD.FLOOR TRAP AND DELIVERY VALVE

029 SC13A1 BUC. 6.000

SANITARY PORCELAIN WATER CLOSET WITH

SIPHON TRAP S COV-A TYPE WHITE PORCELAIN

C.1

029 2444690 BUC. 6.060

WATER CLOSET BASIN COV2 WHITE PORCELAIN

C. 1 S 2066

030 SC16D1 [ 1] BUC. 6.000

RESERVOIR FOR WASHING WC BASIN FROM

POLYPROPYLENE SET MIDHEIGHT ON

BRICK WALL

031 SC18A5 BUC. 6.000

WC BASIN FRAME,OF POLYPROPYLENE WITH LID

032 SC22A1 [ 1] BUC. 1.000

SANITARY PORCELAIN URINAL WITH DELAY

ACTION VALVE, MOUNTED ON BRICK WALL

032 4201747 BUC. 1.000

URINAL WITH DELAY ACTION VALVE VISIBLY SET

033 SC24A2 BUC. 2.000

TOWEL SUPPORT MADE OF AM NICKEL SET

ON WALLS U TYPE, 1 ARM, OPENING 600MM

034 SC25A1 BUC. 6.000

SANITARY PORCELAIN SHELF TYPE

034 2451849 BUC. 6.060

PORCELAIN SHELF TYPE E2.60 WHITE Q.1 NI

567

035 SC26A2 BUC. 6.000

SEMICRYST.SANIT.MIRROR POLISH.EDGES

SIZES 500X600MM

Page 173: ITB Constructii Noi Rev1

173

036 SC27A1 [ 1] BUC. 6.000

LIQUID SOAP DISTRIBUTOR VISIBLY SET ON

WALL

037 SC30A1 BUC. 6.000

SANITARY PORCELAIN 1 Q. PAPER HOLDER,HA1

NI 545/63

038 SD05A1 [ 1] BUC. 4.000

DELAY ACTION VALVE COLD WATER FOR BASIN,

WITH DN 1/2"

039 SD06A1 BUC. 2.000

LAVATORY COCK SYSTEM D=1/2"

039 4201377 BUC. 2.000

BRASS MIXT.WASH HAND BATTERY 1/2" PEARL

JET S8732

040 SD12A1 BUC. 8.000

CORNER ADJUSTMENT FAUCET,OF NICHELLED

BRASS,HAVING D=3/8 OR D=1/2 INCHES

040 4201779 BUC. 8.000

NICKEL PLATED GRASS ANGLE CONTROL COCK 1

/2 " S 751/I

041 SA21A1 [ 1] BUC. 8.000

FLEXIBLE REINFORCED RUBBER CONNECTION 1/

2"X1/2"

042 SD13A1 [ 1] BUC. 6.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

042 7344032 BUC. 6.000

SPHERE TAP FI X FE "MINI" DN 1/2" CODE

40MI4272

043 SA21B1 [ 1] BUC. 6.000

FLEXIBLE REINFORCED RUBBER CONNECTION

1/2"X 3/8"

044 SD13A1 [ 1] BUC. 1.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

044 7344047 BUC. 1.000

@BALL GAUGE COCK+HOSEBEARING+LEVER MAN

DN 1/2" COD 40740485

Page 174: ITB Constructii Noi Rev1

174

045 SD13A1 [ 1] BUC. 1.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

045 7344030 BUC. 1.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 1/2" CODE 40430425

046 SD13B1 [ 1] BUC. 3.000

SPHERE FAUCET WITH COUPLING,FOR STEEL

PIPES D=3/4''

046 7344059 BUC. 3.000

@SHERE FAUCET FEMALEXFEMALE+LEVER MANEV

DN 3/4" CODE 40440425

047 SD13C1 [ 1] BUC. 2.000

SPHERE FAUCET WITH COUPLING,FOR STEEL

PIPES D=1''

047 7344085 BUC. 2.000

@BALL VALVE FIXFI+LEVER MANEV DN 1" COD

40450425

048 SF01A1 M 107.000

TIGHTENESS TEST AT PRES. OF INST. INTER.

OF WATER,IN PIPES STEEL ZN. OR LEAD

PRES. INCLUDING REINFORCED

049 SF04A1 M 107.000

CLEANING AND SUBMIT FOR FUNCTION OF PVC

WATER PIPES.

050 CN13A1 M 45.000

INSTALLATIONS REGULAR PAINTINGS WITH OIL

PAINT ON PIPES EXT.D<34MM INCLUDED

050 6103220 KG 0.765

WHITE PAINT (FP) V.101-1 NTR 90-80

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

Page 175: ITB Constructii Noi Rev1

175

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: WATER AND SEWAGE SERVICES

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA02F1 M.C. 236.000

MAN.DIGGIN.IN LIMIT.SPACES UNDER 1M WITH

R.O.W.VERT.UNSUPPORT.IN SOIL AVER.COHEZ.

AND VERY COHEZ.DEPTH<1,5M HARD S.

002 TSA12C1 M.C. 24.000

MAN.DIGG.IN EXCAVATIONS 1-1,5M WIDE WITH

SUPP.MAN.EVAC.IN SOIL WITH NAT.MOIST AT

DEPTH 0,0-1,5M,HARD SOIL

003 TSC02B1 100 MC. 0.820

DIGGING WITH TYRE EXCAVAT.0,21-0,

39 MC NAT.MOIST.DISCHARGE GROUND

CAT.2

004 TSA18E2 M.C. 6.000

MAN.EXCAV. FOLLOWING MECHANICAL EXCAVATION

HOLES.FOUND. ELEM.NAT.MOIST.SOIL WITH

SUPPORT DEPTH< 4 M HARD SOIL

005 TSF01A1 MP. 105.000

SUPPORT.BY EDGES WITH BEECH SUPPRT.

PLACED HORIZ.EDG.BETWEEN <1,5M,DEEP.0,0-

2M,0,0 -0,2M BETWEEN EDGE

006 TSD01C1 M.C. 242.000

LOOSE SOIL SHOVEL SPREADING,UNIFORM

LAYER 10-30CM.THICK WITH BREAKBLE CLODS

HARD SOIL

007 TSD05A1 100 MC. 2.420

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

008 ACA10A3 [ 2] M 173.000

Page 176: ITB Constructii Noi Rev1

176

UNDERGROUND SETTING AT WATER SUPPLY HDPE

PIPES JOINED WITH FITTINGS THROUGH

COMPRESSURE,WITH DN 40 MM

008 7500552 M 176.460

PE WATER PIPE 100 SDR 17 PN 10 Dn=40mm

009 ACA17A2 BUC. 3.000

POLYETHILEN CONNECTION PIECES JOINED BY

COMPRESSURE FOR HDPE WATER SUPPLY PIPES

009 7500478 BUC. 1.000

PE ELBOW PIPE 900 COMPRESSION D=40

009 7500474 BUC. 2.000

COMPRESSION HDPE CONNECTION FE 40x1"

010 ACA12C1 [ 3] M 51.000

INSTALLING PVC PIPE IN GROUND 100

COMPACT SN 4 FOR EXTERIOR SEWAGE

RUBBER TIGTH ELASTOM.RING D=160 MM

011 SD13A1 [ 1] BUC. 1.000

BALL VALVE WITH COUPLINGS,FOR STEEL

PIPES OF D= 1/2 "

011 7344045 BUC. 1.000

@SPHERE FAUCET EVAC+LID+PORTHOSE DN 1/2"

CODE 40814762

012 SD13C1 [ 1] BUC. 2.000

SPHERE FAUCET WITH COUPLING,FOR STEEL

PIPES D=1''

012 7344085 BUC. 2.000

@BALL VALVE FIXFI+LEVER MANEV DN 1" COD

40450425

013 ACE12B1 [ 1] BUC. 1.000

INSTALLING WATER GAUGE WITH DN

25 MM

014 M1A01B1 [ 1] BUC. 1.000

INSTALLING WASTE WATER ECOLOGICAL

TANK

015 ACD01J1 BUC. 4.000

STAS 2308-81 FRAME AND CAP FOR SEWERS

WITH CARRIAGEWAY SUPPORT PIECE III A

TYPE

Page 177: ITB Constructii Noi Rev1

177

016 ACD09G1 BUC. 1.000

CONCRETE MANHOLES SET SECT. CIRC. PR.TIP

1785-2 DI 1,5 M. H 1,5 WITHOUT

UNDERGROUND WATER CARRIAGEWAY

017 ACD04A1 BUC. 2.000

MANHOLE STAS 2448-73 WORK SPACE HC=2M

CONCRETE TUBE WITH PLUG AND OPENING WITH

DN 200

017 2101195 M.C. 0.076

MORTAR M100 T WITH LIME HYDRATING

017 2100933 M.C. 2.020

CEMENT CONCRETE B 100 (C6/7,5) STAS 3622

017 2804216 BUC. 1.010

SIMPLE CONCRETE CIRCULAR TUBE WITHOUT

FOOTING COUPLING DRY JOINING 1000X1000

S816

018 ACD07A1 M 1.000

ELEMENTS AT MANHOLES STAS WITH H>2 M

INCLUDES: CONCRETE TUBE ACCESS DN 800 L=

1 M WITH FANCET AND OPENING

018 2101183 M.C. 0.019

MANSONRY MORTAR M 100 S 1030

019 ACD03A1 M 3.000

STRINGER LADDED OL 50X10 AND STEPS

OB D=20MM ACCESS IN SEWERS OF CONCRETE

PIPES

020 ACE05A1 [ 1] BUC. 8.000

PVC PIECE FOR PIPING TIGHT PASSAGE

THROUGH CONCRETE SEWERS WALLS

020 6311602 BUC. 2.000

@PASSAGE THROUGH PIECE INCLUDED IN PVC

40 MM WITH WATERPROOFING

020 6311607 BUC. 3.000

@PASSAGE THROUGH PIECE INCLUDED IN PVC

110 MM WITH WATERPROOFING

020 6311608 BUC. 3.000

@PASSAGE THROUGH PIECE INCLUDED IN PVC

160 MM WITH WATERPROOFING

021 ACE07A1 100 M. 17.300

WATER PIPES WASHING AND DESINFECTION

WITH DN 50

Page 178: ITB Constructii Noi Rev1

178

022 ACE08A1 M.C. 56.000

DITCH FILLING FOR WATER PIPE SUPPLY AND

SEWERAGE WITH: SAND

023 W2H07A1 [ 1] M 173.000

POLYETHYLENE WARNING STRIP

023 TRA01A… TONA 112.000

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH DUMP TRUCK DISTANCE= … KM

024 TRA01A…P TONA 180.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= … KM

025 TRI1AA03C2 TONA 180.000

MATERIAL LOADING,GROUP A-HEAVY IN DUST,

BY THROWING FROM PLATFORMS OR SOIL-CAR

CATEG.2

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Page 179: ITB Constructii Noi Rev1

179

Bill of quantities

Estimate - Tender: ELECTRIC INSTALLATIONS

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 EA02A1 [ 2] M 80.000

PROTECTION INSULATION TUBE,IPEY SEALED

RECESSED WITH D=16/13,4MM

002 EA02B2 [ 2] M 3.000

PROTECTION INSULATION TUBE,IPEY SEALED

RECESSED WITH D=40/35,4MM

003 ATD29C1 [ 2] M 120.000

PVC GUTTER FOR CABLE PROTECTION

003 7111001 M 123.600

PVC GUTTER FOR CABLE PROTECTION 16X25 MM

004 ATD29A KG 180.000

NON-GALVANISED, PREFAB ELEMENTS:

SUPPORTS, METALLIC CONSTR,RACKS

004 6902493 KG 180.000

METALLIC OL37 MANUFACTURED MECHANICAL

GALVANIZED CONSTRUCTIONS

005 EA16C1 BUC. 32.000

DEVIATION DOSE FOR CABLES OR INSTALLATIO

N PIPES -NBU PG 16

005 7318987 BUC. 32.000

DEVIATION DOSE FOR CABLES OR INSTALLATIO

N PIPES TYPE:NBU PG16

006 EB02A1 M 240.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION < 4 MMP

006 4826880 M 247.200

CONDUCTOR FY 1X 1,5 S 6865

007 EB02A1 M 120.000

INSULATION COPPER PIPE INSIDE PROTECTION

TUBES,PIPE HAVING SECTION < 4 MMP

007 4826892 M 123.600

Page 180: ITB Constructii Noi Rev1

180

CONDUCTOR FY 1X 2,5 S 6865

008 EC01B1 M 280.000

ELECTRICAL CABLE LAMP,PLUG SECT.<4MMP

MONTAT BACH.PE DIBLURI MAT.PLASTIC

008 4801830 M 288.400

POWER CABLE CYY 0,6/ 1KV 2X 1,5U S.8778

009 EC01B1 M 120.000

ELECTRICAL CABLE LAMP,PLUG SECT.<4MMP

MONTAT BACH.PE DIBLURI MAT.PLASTIC

009 4801892 M 123.600

POWER CABLE CYY 0,6/ 1KV 3X 1,5U S.8778

010 EC01B1 M 360.000

ELECTRICAL CABLE LAMP,PLUG SECT.<4MMP

MONTAT BACH.PE DIBLURI MAT.PLASTIC

010 4801907 M 370.800

POWER CABLE CYY 0,6/ 1KV 3X 2,5U S.8778

011 EC03A1 M 50.000

POWER CABLE SET WITH SCAFS ON CONSOLES

FIXED WITH METALLIC NAILS COND.<10 SQMM.

011 4802055 M 51.500

POWER CABLE CYY 0,6/ 1 KV 5X 2,5U S.8778

012 EC03A1 M 15.000

POWER CABLE SET WITH SCAFS ON CONSOLES

FIXED WITH METALLIC NAILS COND.< 10

SQMM.

012 4802079 M 15.450

POWER CABLE CYY 0,6/ 1KV 5X 6 U S.

8778

013 EC03C1 M 5.000

POWER CABLE MONTAT CU SCOABE PE

CONSOLE FIX.CU DIBLURI METAL COND.25 SAU

35 MMP.

013 4802108 M 5.100

CYY POWER CABLE 0,6/ 1KV 5X 25 U S.8778

014 EC12A1 BUC. 236.000

INTERIOR TERMINAL CONNEC.TO CLAMPS WITH

CU.PIPES <2X10MMP

Page 181: ITB Constructii Noi Rev1

181

015 EC12C1 BUC. 6.000

INSIDE FINAL HEAD CONNECT.AT LANDMARKWIT

H PIPE.WITH <4X10MMP

016 EC12D1 [ 2] BUC. 2.000

TERMINAL INTERIOR HEAD AT THROUGH JOINTS

OF COPPER PIPES 5X25SQMM

017 ED01A1 BUC. 4.000

MANUAL SWITCH BURIED UNIPOLAR NORMAL OR

WATERPROOF CONSTRUCTION *

017 5500720 BUC. 4.040

CUMPANA SWITCH ST.250V 10A

018 ED03A1 BUC. 8.000

UNIPOLAR SWITCH BURIED,WOODEN NAILS,IN

SERIES,NORM.CONSTR.OF BACHELITA OR

WATERPROOF CONSTR.

018 5520366 BUC. 8.080

CUMPANA SHIFTER ST.250V 10A

019 ED03F1 BUC. 6.000

UNIPOLAR PLUG APPARENT ,WOOD DOWEL,IN

SERIES,CONSTR.NORM.FROM BACHELITA OR

TIGHT CONSTR.

019 5500689 BUC. 6.060

VISIBLY SET MANUAL SWITCH 250V 10A

020 ED08B1 [ 1] BUC. 12.000

DOUBLE TWIN PLUG WITH PROTECTION

CONTACT RECESSED MOUNTED

020 5535994 BUC. 12.120

DOUBLE BIPOL.PLUG,PROT.CONTACT 250/10A

RECESSED

021 ED08E1 BUC. 38.000

VISIBLE SET PLUG ON WOODEN NAILS NORMAL

CONSTRUCTION OR CAPSULATED CONSTRUCTION

021 5535996 BUC. 38.380

DOUBLE MOUNTED BIPOLAR SOCKET,PROT.

CONTACT 250/10A

022 EB15A1 BUC. 24.000

NUMBERS FOR ELECTRIC BRANCHES OR MAINS

Page 182: ITB Constructii Noi Rev1

182

022 6719689 BUC. 24.000

PVC TUBULAR LABELS

023 EE12B1 BUC. 2.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

023 5103605 BUC. 2.006

FIA FLUORESCENT LIGHT FIXTURES 11-1X36W

VISIBLY SET

024 EE12B1 BUC. 10.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

024 5103763 BUC. 10.030

FIAG FLUORESCENT FIXTURE 11-2X36 W

FITTED,VISIBLY MOUNTED

025 EE12B1 BUC. 3.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

025 5103707 BUC. 3.009

FIRI FLUORESCENT FIXTURE 03-2X18 W

REFL.DOUBLE PARAB.FITTED,RECESSED

026 EE12B1 BUC. 6.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

026 5103723 BUC. 6.018

FIRI FLUORESCENT FIXTURE 03-4X18 W

REFL.DOUBLE PARAB.7 PLATES, RECESSED

027 EE12B1 BUC. 4.000

UNTIGHT HOLLOW FLUORESCENT FIXTURES SET

ON PLASTICS DOWELS

027 5103823 BUC. 4.012

FLUORESCENT LIGHT FIXTURES AB 02-1X18 W

VISIBLY SET

028 EE12G1 BUC. 6.000

FIXTURE FOR TUBE FLUORESCENT LAMPS SEALED

SET ON PLASTIC MATERIAL DOWELS

028 5103835 BUC. 6.180

FIPAD FLUORESCENT FIXTURE 04-2X18 W

DISPER. PC,STARTER,NOT FITTED

Page 183: ITB Constructii Noi Rev1

183

029 EE14B1 BUC. 12.000

TUBULAR FLUORESCENT LAMP SET INSIDE

CONSTR.OR ON EXTER.ELEM.AT NON TIGHT OR

TIGHT LUMINAIRES

029 5102335 BUC. 12.840

220V-18W TUBULAR FLUORESCENT LAMP

030 EE10C1 BUC. 8.000

SPECIAL FIXTURE, DIFS. MOUNTED ON

MET.NAILS FOR MERCURY VAPOUR LAMPS

030 5104746 BUC. 8.024

VAPOUR FIXTURE HG.IHV 1X250W

WATERPROOF FOR INTER.LIGHTING

031 EE14C1 BUC. 8.000

MERCURRY VAPOURS LAMP ASSEM.INSIDE

CONSTRUCTION OR AT EXTERNAL ELEMENTS FOR

TIGHT OR NON TIGHT LUMINAIRES

031 5102384 BUC. 8.400

FL.MERCURY VAPOUR LAMP OF HIGH PRESSURE

LVF E40/45 220V 250W S7832

032 EF04A1 [ 1] BUC. 1.000

CAPSULATED PANEL EQUIPED ACCORDING TO

ANNEX

032 YC01M MII LEI.

MATERIAL PRICE DIFFERENCE THOUSAND LEI

033 EF09A1 BUC. 55.000

COUPLING COPPER PIPE AT DEVICES BORNS ,

MOTORS,ELECTR.COUNTER COND.HAVING SECT.

<10MMP,EXCLUSIV

034 EF09C1 BUC. 10.000

COPPER PIPE BRANCHING AT TERMINALS,

MOTORS,ELECTR.PANEL PIPE HAVING SECT.25

OR 35MMP

034 5203097 BUC. 10.000

BRASS CUT SHOE COPPER PIPE 6X 5,4 MMP

035 EF10A1 BUC. 140.000

ELECTRIC CONNECTION (CONEC.) BETWEEN

SAFETY CLAMPS AND DEVICES,OR BETWEEN

DEVICES,WITH PIPE L<0,5 M

035 4826919 M 49.000

CONDUCTOR FY 1X 6 S 6865

Page 184: ITB Constructii Noi Rev1

184

036 EB09A1 [ 1] BUC. 6.000

COPPER FLEX.PIECE FOR ADDITIONAL B.E.P.

EARTH GROUNDING

036 4826464 M 1.800

CONDUCTOR FCTIFF -750 1X 16 S 526

036 5203372 BUC. 12.000

BRASS PUNCHED CLIP FOR COPPER

PIPES 5X 5.4

037 W1E09V1 [ 1] KG 24.000

ROUND BARS FILLED WITH COPPER 20X 5 MMP

038 EG07B1 M 12.000

DOWN.PIPES STEEL-ZINK BAND 25X4MM,

APPARENT ASSEMBLED ON WALLS

039 EG08C1 M 50.000

EARTH COND.LIGHTING ROD PROT.EARTH CONN.

UNDERGROUND ASSEM.OL GALVANIZED STRIP

40X4MM ASSEM.IN VERY HARD SOIL

040 W1R06A1 M 9.000

ELECTRODE OF STEEL PIPE OF TWO AND A

HALF INCHES FOR EARTH GROUNDING IN

NORMAL GROUND

041 EG10A1 [ 1] BUC. 1.000

SEPARATION PIECE FOR EARTHING BELT

042 EG10A1 [ 2] BUC. 1.000

COVER PLATE BOX FOR B.E.P

043 EG11B1 [ 1] BUC. 6.000

BEP CONNECTING PIECE TO INSTALLATION

PIPES

044 W1R11A [ 1] BUC. 6.000

FLEX.PIECE JOINING BY GALVANIZED SCREWS

TO B.E.P.

045 EG11B1 [ 2] BUC. 1.000

GAS SPARK VALVE TAP FOR NAT GAS INST.

CONN.TO BEP

046 W1P08A BUC. 1.000

EARTH CONN.TESTING FOR BUILDING WIRING

Page 185: ITB Constructii Noi Rev1

185

047 EH05B1 BUC. 2.000

PANEL TESTING MADE OF CAPSULATED BOXES

IN NUMBER OF MAX.10

048 EH07A1 KWH. 25.000

ELECTRIC POWER FOR TESTS

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Other direct expenses:

-SOCIAL ENSURANCE QUOTE - CAS:

-UNEMPLOYMENT:

-RISK FUND

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

BILL OF QUANTITIES

Estimate - Tender: ARCHITECTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CB48A1 MP. 412.000

ASSEMBLY AND DISMANLING OF MECH.LIFTED

SCAFFOLDING 2 CASTLES L=12M FOR FACADE

FINISHING

002 AUT1304 ORA 960.000

SELF-LIFTING METALIC SCAFFOLD 2 CASTLES

6MARCH 75KG/M H-31M L=12M 3SHIFTS

003 MDTC5517005 BUC. 2.000

EQUIPMENT TRANSPORTAT 5 KM 90100043 SELF

LIFTING METALLIC SCAFFOLDING WITH 2

CASTELS

004 CD05A1 M.C. 4.500

Page 186: ITB Constructii Noi Rev1

186

BRICK MASONRY TYPE GVP AT BUILDINGS H

<35M, SHAPE 240X115X 88MM,Q.A

004 2101169 M.C. 0.945

MASONRY MORTAR M 25 S 1030

005 CD24A1 MP. 150.000

PLAIN PARTITIONING WALLS CW 75/100

WITH METALLIC STRUCTURE (RIGIPS)

006 CK17C1 [ 1] MP. 25.000

PVC PARTIONING MADE OF FIXED

PANELS AND DOOR SHEETS

007 CE05C1 [ 1] MP. 415.000

ROOF COVERING OF THERMO-INSULATING PANELS

OF 8 CM (NAVY BLUE)

008 CD14A1 [ 1] MP. 375.000

FACADE METALLIC PANELS SANDWICH

TYPE WITH POLYURETHANE FOAM

THERMO-INSULATION OF 8 CM(NAVY BLUE)

009 CE13A1 M 104.000

GALVANIZED PLATE DRAIN OF 0,5MM, MADE ON

SITE SEMIROUND WITH D=15CM

010 CE14A1 M 18.000

GALVANIZED PLATE RAIN PIPE OF 0,5MM MADE

ON SITE SEMIROUND WITH D= 15,4CM

011 CE15B2 M 24.000

LINTEL,COVER WIDE 15-30CM,LENGHT<2M-FELT

BLANKET

011 2101200 M.C. 0.120

PLASTER MORTAR M 100 (LIME PASTE) S

1030

012 CK20B1 [ 8] MP. 100.000

GYPSOSCARDBOARD SUSPENDED CEILINGS

INCLD.ANCHORAGE SYSTEM

013 CF10C1 [ 2] MP. 312.000

POLISHING PLASTER COAT SUPPORT

014 CN06B1 [ 6] MP. 312.000

2 LAYER WASHABLE PAINTING FOR

INTERIOR, WHITE COLOR

Page 187: ITB Constructii Noi Rev1

187

015 CF01K1 MP. 30.000

FLOATED INT.PLASTERS,AT COLUMNS,WALLS

WITH SPRINKLER AND PLASTER ROUGH CAST

MECHANICALLY PERFORMED,OF 2CM

015 2101202 M.C. 0.540

PLASTER MORTAR M10T

016 CF06K1 MP. 83.000

FLOATED EXTERNAL PLASTER ON BRICK AND

BLOCKS WALLS WITH CRUND.MECH.LAYER VIZ.

MANUALLY MORTAR M25-T THICK.2,5 CM

016 2101203 M.C. 1.909

PLASTER MORTAR M25T

017 CF09A1 [ 4] MP. 83.000

SPECIAL THIN PLASTER FOR

SOCLE AT INTERIOR AND EXTERIOR WITH MOSAIC

PUTZ

018 CF03A1 MP. 16.500

INTERNAL FLOATED PLASTER,AT CEILINGS

PLANE,AVERAGE THICKNESS OF 2CM

018 2101202 M.C. 0.330

PLASTER MORTAR M10T

019 CG19A1 [ 3] MP. 275.000

FLOORING OF TITIVATED CEMENT WITH

QUARTZ

019 2101200 M.C. 5.775

PLASTER MORTAR M 100 (LIME PASTE) S

1030

020 CG01F1 MP. 377.000

CEMENT FINISH SLAB SUPPORT OF LEVELLING PLASTER

UNDER FLOORING OF 3CM THICKNESS

021 CG11A1 MP. 70.000

PLATED FLOORS FROM CERAMICS SQUARED OR

RECTANGULAR OF SAME COLOUR PLACED

SIMETRICALLY

021 2425280 MP. 72.100

NON GLAZED SMOOTH TILING GRI F

100X100X 8 C1 S5939

022 RPCK42A1 M 115.000

CERAMICS TILE PLINTHS OF MAX.

Page 188: ITB Constructii Noi Rev1

188

15CM HIGH,HORZONTAL FOR WALLS*

022 2434891 M 117.299

UN SMOOTH SANDSTONE JOINNINGS ELEM.

GREEN S 150X100X 8 C1 S5939

023 CG02B1 [ 2] MP. 25.000

LAMINATED PARQUET FLOOR FOR INTENSE

TRAFFIC

024 CI06E1 MP. 80.000

WHITE TILE PLATING ADHESIVE PASTE FIXED

024 2401777 MP. 83.999

DECOR WHITE TILE MONOC M.DR 150X150X5,5

Q. 1 S233

025 CK11G1 [ 2] MP. 32.800

P.V.C. WINDOWS WITH 5 ROOMS ,

SEALING, WHITE DOUBLE-GLASSED WINDOW

OF 24 MM

026 CK14A1 [ 1] MP. 1.900

SPECIAL METALLIC DOORS

026 6306454 BUC. 1.000

30 MIN.FIRE RESISTANT METALLIC

DOOR

027 CK14A1 [ 2] MP. 12.000

WHITE COLOR PVC DOORS WITH THERMO

INSULATING GLASS 4+ 16+4MM

028 CK14A1 [ 6] MP. 2.300

PVC DOORS

029 CK14A1 [29] MP. 19.500

PVC DOORS WITH PLAN WINDOW WITH

SURFACE < 5 SQUARE METERS

030 CK14A1 [11] MP. 18.000

ALUMINIUM ROLLING DOORS (GATES) WITH

THERMO-INSULATION

031 CK11G1 MP. 1.200

ALUMINIUM WINDOWS FOR CONSTRUCTIONS

WITH H<10M AND WINDOW FRAME OF < 3SQM

031 6307321 MP. 1.200

ONE LEAF ALUMINUM WINDOW

Page 189: ITB Constructii Noi Rev1

189

Page 190: ITB Constructii Noi Rev1

190

032 CM04B1 MP. 1.100

CLEAR DRAWN WINDOW GLASSES FIXED SIZES

METALLIC JOINERY 2-3MM THICK RED LEAD PUTTY

AND METALLIC RODS >0,2

032 2500327 MP. 1.155

CLEAR DRAWN GLASS Q.3 4MM. PACKED FREE

SIZES S 853

033 CD14A1 [ 2] MP. 31.000

THERMO-INSULATION PANELS OF 4 CM TO

SUN-BLIND

034 CI02A1 [13] MP. 31.000

SPECIAL FINISHING FOR FACADE WITH ALUMINIUM

ALUCOBOND PLATES

035 CO01A1 MP. 170.000

PAVEMENT OF SIMPLE CONCRETE POURED

ON SITE

035 2100933 M.C. 13.770

CEMENT CONCRETE B 100(C6/7.5) STAS 3622

036 CO03A1 M 111.000

PAVEMENT KERBS SET ON M100-T MORTAR OF

5CM THIC.ON CONCRETE FOUNDATION,WITH

CEMENT

036 2202202 M 111.555

PAVEMENT KERBS 12 X25X50CM

036 2100933 M.C. 5.217

CEMENT CONCRETE B 100(C6/7.5) STAS 3622

036 2101200 M.C. 1.221

PLASTER MORTAR M 100 (LIME PASTE) S

1030

037 CL20C1 [18] KG 30.000

INSTALLING VISIBLE PLATEWORKS:

GRATE FOR WIPPING THE FEET

037 6306016 KG 30.000

METALLIC GRID FOR SWEEPING FEET OF

PROFILED STEEL

038 TRA06A05 TONA 34.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

Page 191: ITB Constructii Noi Rev1

191

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

- HEALTH

- OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: RESISTANCE INFRASTRUCTURE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA01B1 M.C. 108.000

MAN.EXCAVATIONS IN LARGE SPACES IN SOIL

WITH NAT. MOISTURE SET IN STORAGE ROOM

OR VEHIC.H<0,6M MEDIUM SOIL*

002 TSA14B1 M.C. 3.820

MAN.EXCAV.IN HOLES OF 1.5-6M WIDE WITH

SUPPORT MAN. EVAC.IN SOIL WITH NAT.MOIST.

0.0-2M DEEP,INTERMEDIATE SOIL

003 TSA04B1 M.C. 19.000

MAN.DIGGING IN LIMITED SPACES UNDER 1M

SUPPORTS AND MAN.EVAC.IN SOIL WITH NAT.

HUMIDITY DEPTH.0,0-1,5M MEDIUM SOOL

004 TSD02D1 100 MC. 1.840

LOOSE SOIL SPREADING RESULTED FROM

1ST OR 2ND C. SOIL WITH BULD. 65-80HP IN

LAYER WITH THICKNESS OF 51-100

005 TSD01B1 M.C. 27.000

Page 192: ITB Constructii Noi Rev1

192

SHOVEL SPREADING OF THE LOOSE LAND,LEVEL

LAYER 10-30CM.THICK WITH CRUSHED CLODS

AVERAGE SOIL

006 TSD05A1 100 MC. 0.270

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

007 TRB01C12 TONA 14.600

MATERIALS TRANSPORT WITH WHEELEBARROW

TYRES LOAD THROW UNLOAD OVERTURN GROUP1-

3 DISTANCE 20M

008 TRA01A05P TONA 18.200

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= 5 KM

009 CG32D1 [ 5] M.C. 45.000

FILLINGS IN LAYERS, EXECUTED BY

MECHANICALLY COMPACTED GRAVEL

010 CA01B1 M.C. 44.000

SIMPLE CONCRETE MOULDING IN FOUNDATIONS

(CONTINUOUS,ISOLATED)AND SOCLES WITH

VOLUME > 3MC,AND IN RETAINIG WALLS

010 2100945 M.C. 44.352

CEMENT CONCRETE B 150(C8/10) STAS 3622

011 CA01D1 [ 8] M.C. 5.000

PLAIN CONCRETE C6/7.5 IN LAYERS OF 3-

20CM THICK. TO EQUALIZING

011 2100933 M.C. 5.040

CEMENT CONCRETE B 100(C6/7.5) STAS 3622

012 CB01A1 MP. 115.000

SHUTTERING IN BUSHING GLASS BOTTOM ,

EQUIPMENT BOTTOM,FROM REUSED PANELS,FROM

RESINE SLATS SC AND SUBSC INCL SPIJIN

013 CB11A1 MP. 132.000

SHUTTERINGS FOR CONCRETE IN ELEV.FROM

PANELS TO STRAIGHT WALL WITH H<3M,WITH

PLYWOOD OF 8MM THICK.

014 CA02A1 M.C. 25.000

REINFORCED CONCRETE MOULDING IN

INSULATED FOUNDATIONS VOLUME <3MC

014 2100969 M.C. 25.200

CEMENT CONCRETE C16/20(B 250) STAS 3622

Page 193: ITB Constructii Noi Rev1

193

015 CA02C1 M.C. 15.000

POURING REINFORCED CONCRETE IN CONTIN.

FOUNDATIONS ,PLATE FOUNDATIONS AND WALLS

UNDER 0 ELEVATION OF BUILD.WITH THICK.

<30CM

015 2100969 M.C. 15.120

CEMENT CONCRETE C16/20(B 250) STAS 3622

016 CC01C1 KG 3830.000

CONCRETE STEEL REINFORCEMENTS ASSEMBLING

IN CONTINUOUS FOUNDATIONS,SLABS OF

PLATES,WITH DIST FROM PLASTICS

017 CZ0301A1 KG 855.000

MANUFAC.REINFOR.SHAPED BARS FOR

FOUNDATION ISOL.CONTINUOUS AND PLATES

IN.CENT.WORKSHOPS OB 37 D=6-8MM

018 CZ0301D1 KG 2975.000

REINFORCED MANUFACTURED SHAPING BARS FOR

CONTINOUS ISOLATED FOUNDATION AND PLATE

FOUNDATION IN ATEL CENT.PC 52 D=6-8MM

019 TRA06A05 TONA 176.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

020 TRA02A05 TONA 5.000

ROAD MATERIALS SEMIPRECAST TRANSPORT

WITH TRUCK ON DISTANCE= 5 KM.

021 CA01D1 M.C. 30.000

SIMPLE CONCRETE MOULDING IN LAYERS OF 3-

20CM THICKNESS AT CONSTRUCTIONS WITH H

<35M

021 2100969 M.C. 30.240

CEMENT CONCRETE C16/20(B 250) STAS 3622

022 IZF04J1 [ 1] MP. 336.000

BOUNDARY LAYER EXEC BY POLYETHYLENE

FOIL OF0.2MM

023 CC02F1 KG 1020.000

REINFORCED ASSEMBLED AT CONSTR.H<35M

FROM NETS WITH G=1-3KG/MPIN MIDRIFF

WALLS WITH PLASTIC DISTAN

024 CZ0302XD1 KG 1020.000

MANUFACTURING OF WELDED MESH IN CENTRALIZED

WORKSHOPS OF CONCRETE STEEL 37 WITH BARS OF

D=4-5MM

025 IZF10F1 [14] MP. 336.000

EXTRUDED POLYSTYRENE INSULATION

LAYER OF 100MM WITH = 0.03 W/MK > 35 KG

Page 194: ITB Constructii Noi Rev1

194

UNDER THE REINFORCED CONCRETE SLAB

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: CONSTANT RESISTANCE

Work category:

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 CL01A1 TONA 5.470

STEEL PILLARS SETTING FOR INDUSTRIAL

HALL COMPLET.SET HAVING<1T INCL.

002 CL04A1 TONA 4.500

STEEL FULL BEAM SETTING COMPL.SETTING

UNDER 1T

003 CL16A1 TONA 4.021

SETTING OF METALLIC TEMPLETS OF 0.1-0.2T

ON CONCRETE FRAMEWORK TO CONSTR WITH H

<35M

004 TRA04A10 TONA 13.500

ROAD TRANSPORT PRECAST MATER.BY

AUTO CARRIER WITH TRAILER UNDER

20T ON DIS.10 KM.*

Page 195: ITB Constructii Noi Rev1

195

005 CA02J1 [ 5] M.C. 1.200

POURING REINFORCED CONCRETE C16/20 IN SLABS

006 CP26A1 [ 1] M.C. 0.650

PUTTING IN OPERATION OF MORTAR M100

FOR SITTING METALLIC PILLARS

007 CC02C1 KG 35.000

ASSEMBL.REINFOR.FOR CONSTR H<35M FROM

BARS IN BEAMS AND COLUMNS D<18MM PLATES

D<10MM WITH DIST FROM PLASTIC

008 CZ0302XE1 KG 35.000

MANUFACTURING OF WELDED MESH IN CENTRALIZED

WORKSHOPS OF CONCRETE STEEL 37 WITH BARS OF

D=6-8MM

009 TRA06A05 TONA 4.300

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Bill of quantities

Estimate - Tender: PLATFORM

Work category:

Page 196: ITB Constructii Noi Rev1

196

=================================================================

= NO.SYMBOL ITEM QUANTITY MEASURE UNIT PU MAT VAL MAT =

= N A M E PU MAN VAL MAN =

= I T E M PU UTI VAL UTI =

= PU TRA VAL TRA =

= SPOR MAT MAN UTI WEIGHT/ADD. TOTAL WEIGHT T O T A L =

=================================================================

001 TSA01G1 M.C. 60.000

MAN. DIGGINGS IN SPREAD SPACES IN SOIL

WITH NAT.MOISTURE THROWED IN VEHICLE ATH

OF 0,61-2M HARD SOIL

002 TSC04G1 100 MC. 4.000

MECH.DIGGING WITH EXC.OF 0,71-1,25CM IN

SOIL WITH NATURAL MOISTURE VEHIC.UNLOAD.

SOIL CAT.3

003 TSC18B1 100 MC. 2.000

DIGG.WITH BULLDOZ.ON TRACT.65-80PH

INCLD.SOIL PUSHING AT 10 M SOIL CAT.2

004 TSC35B31 100 MC. 2.000

AUTOLOADER ON TYRES WITH BUCKET 2,6-3,9

CM LAND CATEG 2 AT DIST. 11-20 M

005 TRA01A05P TONA 1080.000

ROAD TRANSPORT OF SOIL OR DEBRIS WITH

TIP LORRY DIST.= 5 KM

006 TSD01D1 M.C. 60.000

SHOVEL SPREADING OF LOOSE SOIL,LEVEL

LAYER 10-30CM.THICK.CLODS CRUSHING VERY

HARD SOIL

007 TSD05A1 100 MC. 0.600

COMPACTION WITH MEC.RAMMER OF 150-200KG

OF FILLG.IN LAYER OF 20-30CM EXCLUSIVELY

WET LAYER FROM NONCOHEZ. SOIL

008 TSE06B1 100 MP. 22.000

SOIL PLATF.PREPARING ISOLATING LAYER AND

SAND REPARTION OR GRAVEL IN COHESIVE

SOIL

009 DA06A1 M.C. 660.000

NAT.AGREGG.LAYER(GRAVEL)ROLLED OVER WITH

FILTRING RESISTANCE FUNCTION ISOL.AERING

ANTICAP.MANUAL LAYING

010 TRA01A10 TONA 1475.000

MATERIAL,SEMIPREFAB ROAD TRANSPORT BY

TIP LORRY ON A 10 KM.DIST.

011 DC05C1 MP. 2200.000

CEMENT CONCRETE ROAD SURFACING EXEC IN

ONE BASE OF 20 CM THICKNESS

012 DZ30F1 M.C. 444.000

CEMENT CONCRETE FOR ROAD PLATFORM AIRPORT

RUNWAY TRADE 400 WITH GRAVEL AND SAND CONCRETE

Page 197: ITB Constructii Noi Rev1

197

CAPACITY CAP 25-35 CUBIC METERS/H

013 DC04B1 M 500.000

CUTTING BY DIAMOND DISK MACHINE OF SHRINKAGE

AND EXPANSION JOINTS BETON ROAD

WEAR

014 DC03A1 BUC. 240.000

CONCRETE STEEL ANCHORAGE WITH LENGTH BAR 1 M WITH

MOUTH PENANCOR CEMENT CONCRETE SURFACING

VIBRATED TO CONSTRUCTION LONG JOINTS

015 TRA06A05 TONA 1065.000

CONCRETE- MORTAR ROAD TRANSPORTATION

WITH CONCRETE MIXER MOTOR-TRUCK OF 5,5MC

DIST. =5 KM

Direct expensive from items:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

From which:

Afferent amount of thermic equipm. =

Afferent amount of electric equipm.=

Details transports:

- Items TRA

Other direct expenses:

- SOCIAL ENSURANCE QUOTE - CAS:

- UNEMPLOYMENT:

-HEALTH

-OTHER EXPENSIVE ACCORDING TO THE LAW STIPULATION,

NOMINALIZED:

Total direct expenses:

WEIGHT MATERIALS WORK LABOUR EQUIPMENT TRANSPORT TOTAL

Indirect expenses:

Profit:

TOTAL GENERAL ESTIMATE:

VAT

TOTAL with VAT

Annex VII.

BID/PROPOSAL SUBMISSION FORM

Page 198: ITB Constructii Noi Rev1

198

To: The procuring entity

Dear Sir / Madam,

Having examined the Bidding Documents, the receipt of which is hereby duly acknowledged, we, the undersigned, offer to supply and deliver [description of civil works] in conformity with the said bidding documents for the sum of [total bid amount in words and figures] as may be ascertained in accordance with the Price Schedule

attached herewith and made part of this Bid.

We undertake, if our Bid is accepted, to deliver the civil works in accordance with the delivery schedule

specified in the Schedule of Requirements.

We agree to abide by this Bid for a period of [number] days from the date fixed for opening of Bids in the

Invitation to Bid, and it shall remain binding upon us and may be accepted at any time before the expiration of that period.

We understand that you are not bound to accept any Bid you may receive.

Dated this . . . . .day of . . . . .[year].

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Signature [in the capacity of]

Duly authorised to sign the Bid for and on behalf of . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Page 199: ITB Constructii Noi Rev1

199

Annex VIII.

PRICE SCHEDULE

1. The Price Schedule must provide a detailed cost breakdown for each item. 2. Technical descriptions for each proposed item must provide sufficient detail to allow the Purchaser to determine

compliance of Bid with specifications as per Schedule of Requirements and Technical Specifications of this ITB.

3. In addition to the hard copy, if possible please provide also the information on diskette (IBM compatible). 4. Work schedule (Annex).

5. Warranty for performed works. 6. Timeframe for rectification of defects. 7. Payment schedule.

Signature of Bidder ………………………………………..

Financial summary table of work category

----------------------------------------

Estimate-tender of object: LACATUS FAMILY HOUSE

------------------------------------------------------------------------------------------------------------------------------------

| No. | | Amount | from which: |

| Cr. | W o r k c a t e g o r y |(VAT exclusive)-----------------------------------------------------------------|

| | | | contractor | associate | subcontractor |

| | | - RON - | chief | | |

| | | |(association chief) | | |

| | | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| 0 | 1 | 2 | 3 | 4 | 5 |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| I. | Buildings and special constructions,aff. | | | | |

| | installations to constructions and | | | | |

| | facility networks inside building | | | | |

| | | | | | |

| 1 | VARIABLE ARCHITECTURE | | | | |

| | | | | | |

| 2 | CONSTANT ARCHITECTURE | | | | |

| | | | | | |

| 3 | ARHITECTURE ATTIC | | | | |

| | | | | | |

| 4 | RESISTANCE INFRASTRUCTURE | | | | |

| | | | | | | | 5 | RESISTANCE SUPERSTRUCTURE | | | | |

| | | | | | |

| 6 | RESISTANCE FRAMEWORK | | | | |

| | | | | | |

| 7 | ELECTRIC INSTALLATIONS | | | | |

| | | | | | |

| 8 | SANITARY INSTALLATIONS | | | | |

| | | | | | |

| 9 | HEATING INSTALLATIONS | | | | |

| | | | | | |

| 10 | GAS INSTALLATIONS | | | | |

| | | | | | |

| 11 | WATER AND SEWAGE SERVICES | | | | |

| | | | | | |

| 12 | PAVEMENT | | | | |

| | | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL I | | | | | |-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| II. | Supply | | | | |

| | - Technological equipments with assembling| | | | |

| | - Transport equipments | | | | |

| | - Utilities,including independent equipmen| | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------| | | TOTAL II | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | Total amount ( exclusive VAT ) - RON - | | | | |

| | Euro | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | Value added tax - RON - | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------| | | TOTAL (VAT inclusive ) - RON - | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

Page 200: ITB Constructii Noi Rev1

200

Financial summary table of work category

----------------------------------------

Estimate-tender of object: MOLDOVAN FAMILY HOUSE

------------------------------------------------------------------------------------------------------------------------------------

| No. | | Amount | from which: |

| Cr. | W o r k c a t e g o r y |(VAT exclusive)-----------------------------------------------------------------|

| | | | contractor | associate | subcontractor |

| | | - RON - | chief | | |

| | | |(association chief) | | |

| | | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| 0 | 1 | 2 | 3 | 4 | 5 |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| I. | Buildings and special constructions,aff. | | | | | | | installations to constructions and | | | | |

| | facility networks inside building | | | | |

| | | | | | |

| 1 | VARIABLE ARCHITECTURE | | | | |

| | | | | | |

| 2 | CONSTANT ARCHITECTURE | | | | |

| | | | | | |

| 3 | ARHITECTURE ATTIC | | | | |

| | | | | | |

| 4 | RESISTANCE INFRASTRUCTURE | | | | |

| | | | | | |

| 5 | RESISTANCE SUPERSTRUCTURE | | | | |

| | | | | | |

| 6 | RESISTANCE FRAMEWORK | | | | |

| | | | | | |

| 7 | ELECTRIC INSTALLATIONS | | | | |

| | | | | | |

| 8 | SANITARY INSTALLATIONS | | | | |

| | | | | | | | 9 | HEATING INSTALLATIONS | | | | |

| | | | | | |

| 10 | GAS INSTALLATIONS | | | | |

| | | | | | |

| 11 | WATER AND SEWAGE SERVICES | | | | |

| | | | | | |

| 12 | PAVEMENT | | | | |

| | | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL I | | | | | |-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| II. | Supply | | | | |

| | - Technological equipments with assembling| | | | |

| | - Transport equipments | | | | |

| | - Utilities,including independent equipmen| | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL II | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | Total amount ( exclusive VAT ) - RON - | | | | |

| | Euro | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------| | | Value added tax - RON - | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL (VAT inclusive ) - RON - | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

Page 201: ITB Constructii Noi Rev1

201

Financial summary table of work category

----------------------------------------

Estimate-tender of object: ZOLTAN FAMILY HOUSE

------------------------------------------------------------------------------------------------------------------------------------

| No. | | Amount | from which: |

| Cr. | W o r k c a t e g o r y |(VAT exclusive)-----------------------------------------------------------------|

| | | | contractor | associate | subcontractor |

| | | - RON - | chief | | |

| | | |(association chief) | | |

| | | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| 0 | 1 | 2 | 3 | 4 | 5 |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| I. | Buildings and special constructions,aff. | | | | | | | installations to constructions and | | | | |

| | facility networks inside building | | | | |

| | | | | | |

| 1 | VARIABLE ARCHITECTURE | | | | |

| | | | | | |

| 2 | CONSTANT ARCHITECTURE | | | | |

| | | | | | |

| 3 | ARHITECTURE ATTIC | | | | |

| | | | | | |

| 4 | RESISTANCE INFRASTRUCTURE | | | | |

| | | | | | |

| 5 | RESISTANCE SUPERSTRUCTURE | | | | |

| | | | | | |

| 6 | RESISTANCE FRAMEWORK | | | | |

| | | | | | |

| 7 | ELECTRIC INSTALLATIONS | | | | |

| | | | | | |

| 8 | SANITARY INSTALLATIONS | | | | |

| | | | | | | | 9 | HEATING INSTALLATIONS | | | | |

| | | | | | |

| 10 | GAS INSTALLATIONS | | | | |

| | | | | | |

| 11 | WATER AND SEWAGE SERVICES | | | | |

| | | | | | |

| 12 | PAVEMENT | | | | |

| | | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL I | | | | | |-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| II. | Supply | | | | |

| | - Technological equipments with assembling| | | | |

| | - Transport equipments | | | | |

| | - Utilities,including independent equipmen| | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL II | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | Total amount ( exclusive VAT ) - RON - | | | | |

| | Euro | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | Value added tax - RON - | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL (VAT inclusive ) - RON - | | | | |

|-----|-------------------------------------------|-------------- |---------------------|---------------------|---------------------|

Page 202: ITB Constructii Noi Rev1

202

Financial summary table of work category

----------------------------------------

Estimate-tender of object: HEALTH UNIT

------------------------------------------------------------------------------------------------------------------------------------

| No. | | Amount | from which: |

| Cr. | W o r k c a t e g o r y |(VAT exclusive)-----------------------------------------------------------------|

| | | | contractor | associate | subcontractor |

| | | - RON - | chief | | |

| | | |(association chief) | | |

| | | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| 0 | 1 | 2 | 3 | 4 | 5 |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| I. | Buildings and special constructions,aff. | | | | | | | installations to constructions and | | | | |

| | facility networks inside building | | | | |

| | | | | | |

| 1 | VARIABLE ARCHITECTURE | | | | |

| | | | | | |

| 2 | CONSTANT ARCHITECTURE | | | | |

| | | | | | |

| 3 | ARHITECTURE ATTIC | | | | |

| | | | | | |

| 4 | RESISTANCE INFRASTRUCTURE | | | | |

| | | | | | |

| 5 | RESISTANCE SUPERSTRUCTURE | | | | |

| | | | | | |

| 6 | RESISTANCE FRAMEWORK | | | | |

| | | | | | |

| 7 | ELECTRIC INSTALLATIONS | | | | |

| | | | | | |

| 8 | SANITARY INSTALLATIONS | | | | |

| | | | | | | | 9 | HEATING INSTALLATIONS | | | | |

| | | | | | |

| 10 | GAS INSTALLATIONS | | | | |

| | | | | | |

| 11 | WATER AND SEWAGE SERVICES | | | | |

| | | | | | |

| 12 | PAVEMENT AND PARKING | | | | |

| | | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL I | | | | | |-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| II. | Supply | | | | |

| | - Technological equipments with assembling| | | | |

| | - Transport equipments | | | | |

| | - Utilities,including independent equipmen| | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL II | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | Total amount ( exclusive VAT ) - RON - | | | | |

| | Euro | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | Value added tax - RON - | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL (VAT inclusive ) - RON - | | | | |

|-----|-------------------------------------------|-------------- |---------------------|---------------------|---------------------|

Page 203: ITB Constructii Noi Rev1

203

Financial summary table of work category

----------------------------------------

Estimate-tender of object: INDUSTRIAL BUILDIND

------------------------------------------------------------------------------------------------------------------------------------

| No. | | Amount | from which: |

| Cr. | W o r k c a t e g o r y |(VAT exclusive)-----------------------------------------------------------------|

| | | | contractor | associate | subcontractor |

| | | - RON - | chief | | |

| | | |(association chief) | | |

| | | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| 0 | 1 | 2 | 3 | 4 | 5 |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| I. | Buildings and special constructions,aff. | | | | |

| | installations to constructions and | | | | |

| | facility networks inside building | | | | |

| | | | | | |

| 1 | ARCHITECTURE | | | | |

| | | | | | |

| 2 | RESISTANCE INFRASTRUCTURE | | | | |

| | | | | | |

| 3 | RESISTANCE SUPERSTRUCTURE | | | | |

| | | | | | |

| 4 | ELECTRIC INSTALLATIONS | | | | | | | | | | | |

| 5 | SANITARY INSTALLATIONS | | | | |

| | | | | | |

| 6 | HEATING INSTALLATIONS | | | | |

| | | | | | |

| 7 | GAS INSTALLATIONS | | | | |

| | | | | | |

| 8 | WATER AND SEWAGE SERVICES | | | | |

| | | | | | |

| 9 | PLATFORM | | | | |

| | | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL I | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| II. | Supply | | | | |

| | - Technological equipments with assembling| | | | |

| | - Transport equipments | | | | |

| | - Utilities,including independent equipmen| | | | | |-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL II | | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | Total amount ( exclusive VAT ) - RON - | | | | |

| | Euro | | | |

|-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | Value added tax - RON - | | | | | |-----|-------------------------------------------|--------------|---------------------|---------------------|---------------------|

| | TOTAL (VAT inclusive ) - RON - | | | | |

|---- -|-------------------------------------------|-------------- |---------------------|---------------------|---------------------|

Financial summary table of objects

----------------------------------

|--------|------------------------------------------------------------|-----------------------|-----------------------------------------------------------------------|

| No.Cr. | O b j e c t g r o u p | Amount | from which| from which: |

| | O b j e c t n a m e | ( VAT | C + M |-----------------------------------------------------------------------|

| | | exclusive)| | contractor | associate | subcontractor |

| | | - RON - | | leader | | |

| | | | | of the association | | |

| | | | |-----------------------------------------------------------------------|

| | | | | Total | C+M | Total | C+M | Total | C+M |

|--------|------------------------------------------------------------|-----------------------|-----------|-----------|-----------|-----------|-----------|-----------|

| 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |

|--------|------------------------------------------------------------|-----------------------|-----------|-----------|-----------|-----------|-----------|-----------|

| 1. | Basic Investment (work) | | | | | | | | |

| | | | | | | | | | |

| 1.001| 1 LACATUS FAMILY HOUSE | | | | | | | | |

| | | | | | | | | | |

| 1.002| 2 MOLDOVAN FAMILY HOUSE | | | | | | | | |

| | | | | | | | | | |

| 1.003| 3 ZOLTAN FAMILY HOUSE | | | | | | | | |

| | | | | | | | | | |

| 1.004| 4 HEALTH UNIT | | | | | | | | |

| | | | | | | | | | |

| 1.005| 5 INDUSTRIAL BUILDING | | | | | | | | |

| | | | | | | | | | |

|--------|------------------------------------------------------------|-----------------------|-----------|-----------|-----------|-----------|-----------|-----------|

| | | | | | | | | | |

| 2 | Site organization 1.00% | | | | | | | | |

| | | | | | | | | | |

|--------|------------------------------------------------------------|-----------------------|-----------|-----------|-----------|-----------|-----------|-----------|

| | | | | | | | | | |

| | Total Amount ( VAT exclusive ) - RON - | | | | | | | | |

| | Euro | | | | | | | | |

| | | | | | | | | | |

|--------|------------------------------------------------------------|-----------------------|-----------|-----------|-----------|-----------|-----------|-----------|

| | | | | | | | | | |

| | Value added tax - RON - | | | | | | | | |

| | | | | | | | | | |

|--------|------------------------------------------------------------|-----------------------|-----------|-----------|-----------|-----------|-----------|-----------|

| | TOTAL (VAT inclusive) - RON - | | | | | | | | |

| | | | | | | | | | |

|--------|------------------------------------------------------------|-----------------------|-----------|-----------|-----------|-----------|-----------|-----------|