issue no. 9 october / november 2012 issue no 7. april 2012 ... · issue no 7. april 2012 grid25 is...

4
GRID25 NEWSLETTER Issue No 7. April 2012 Grid25 is EirGrid’s strategy for the long-term development of Ireland’s transmission system. The strategy aims to support economic growth and job creation, provide a reliable supply of electricity for all consumers, provide the infrastructure to enable Ireland to realise its renewable potential and achieve the challenging target of delivering 40% of electricity generated from renewable sources by 2020. The Government Policy Statement on the Strategic Importance of Transmission and Other Energy Infrastructure 2012 specifically endorses and supports the Grid25 investment programme and reaffirms that it is Government policy and in the national interest. Recent Grid25 project and programme highlights are outlined below. GRID25 Public consultation is underway on two of EirGrid’s largest Grid25 projects, the Grid West and the Grid Link projects. Since the launch of the Grid West project by An Taoiseach, Enda Kenny in May 2012, the project team has engaged in an extensive programme of public consultation as per the EirGrid project development roadmap. The second round of public consultation took place in August/September 2012 involving a series of five open days across the western region. Following this second round of public consultation, the Constraints Report will be finalised and EirGrid will publish an overall Stage 1 Report. This report will present all the information gathered to date as well as the identification of feasible corridors and station sites. The report is expected to be published in early 2013, at which time the public and other stakeholders will be given the opportunity to review the report and provide feedback. The Grid West project will initially consist of a new high capacity power line linking Bellacorick in County Mayo to a strong point on the transmission grid in the West, either to Flagford in Co. Roscommon or Cashla in Co. Galway. The key driver for this investment of 240 million is the integration of renewable energy sources. To ensure future electrical power needs are met in the South and East of Ireland, EirGrid is developing the Grid Link project, a 500 million investment consisting of a new high voltage power line linking Leinster and Munster. The key drivers for this project are security of supply, the integration of renewable energy sources, the facilitation of future interconnection and long-term demand growth. The second stage of public consultation on the Grid Link project took place between August and October 2012 involving a series of thirteen Open Days across the Grid Link Study Area. During early 2013, EirGrid will outline feasible corridor options for the Grid Link Project. The public and all interested parties will be asked to comment on the corridors identified and to provide feedback on the criteria that should be used to determine a least constrained corridor. Detailed information on the Grid West and the Grid Link projects can be found on www.eirgridprojects.com. PUBLIC CONSULTATION ON GRID LINK AND GRID WEST PROJECTS Grid25 - Delivering Ireland’s Electricity Future GRID25 NEWSLETTER Issue No. 9 October / November 2012 EirGrid’s Project Development and Consultation Roadmap STAGE 1 STAGE 2 STAGE 3 STAGE 4 STAGE 5 Public Public and stakeholder consultation on study area and constraints Public and stakeholder consultation on findings of Stage 1 Report Evaluate Options Consideration of all feedback from Stage 1 Identification of EirGrid’s emerging preferred option (route corridor/site) Identification of indicative line within corridor or site boundary Identify and meet landowners of indicative line/site; initial survey Publication of Stage 2 Report Pre-application consultation with An Bord Pleanála Confirm Design Consideration of all feedback from Stage 2 Conduct environmental studies and surveys Confirmation of design of line/site proposal including construction methodology Ongoing engagement with landowners on preferred line route or site Pre-application consultation with An Bord Pleanála Prepare Planning Application Complete reports and prepare planning application Preparation of Environmental Impact Statement (EIS) or EnvironmentalReport as required Conclusion of Pre-application consultation with An Bord Pleanála Submit application to An Bord Pleanála Wayleaving and Construction Preparation of construction plans Serve wayleave notice to landowners and agree access for construction Commence construction Public Public and stakeholder consultation on findings of Stage 2 Report Public Ongoing public information Public Ongoing public information Once application submitted, public can make submissions to An Bord Pleanála including at an oral hearing, if held Public Ongoing public information Evaluation of Public Consultation process Information Gathering Identify Project Study Area Identify environmental & other constraints Identify feasible options (corridor/sites) Publication of Stage 1 Report Pre-application consultation with An Bord Pleanála

Upload: others

Post on 05-Apr-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Issue No. 9 October / November 2012 Issue No 7. April 2012 ... · Issue No 7. April 2012 Grid25 is EirGrid’s strategy for the long-term development of Ireland’s transmission system

GRId25 NEWSLETTER Issue No 7. April 2012

Grid25 is EirGrid’s strategy for the long-term development of Ireland’s transmission system. The strategy aims to support economic growth and job creation, provide a reliable supply of electricity for all consumers, provide the infrastructure to enable Ireland to realise its renewable potential and achieve the challenging target of delivering 40% of electricity generated from renewable sources by 2020.

The Government Policy Statement on the Strategic Importance of Transmission and Other Energy Infrastructure 2012 specifically endorses and supports the Grid25 investment programme and reaffirms that it is Government policy and in the national interest. Recent Grid25 project and programme highlights are outlined below.

GRId25

Public consultation is underway on two of EirGrid’s largest Grid25 projects, the Grid West and the Grid Link projects.

Since the launch of the Grid West project by An Taoiseach, Enda kenny in may 2012, the project team has engaged in an extensive programme of public consultation as per the EirGrid project development roadmap. The second round of public consultation took place in August/September 2012 involving a series of five open days across the western region.

Following this second round of public consultation, the Constraints Report will be finalised and EirGrid will publish an overall Stage 1 Report. This report will present all the information gathered to date as well as the identification of feasible corridors and station sites. The report is expected to be published in early 2013, at which time the public and other stakeholders will be given the opportunity to review the report and provide feedback.

The Grid West project will initially consist of a new high capacity power line linking Bellacorick in County mayo to a strong point on the transmission grid in the West, either to Flagford in Co. Roscommon or Cashla in Co. Galway. The key driver for this investment of €240 million is the integration of renewable energy sources.

To ensure future electrical power needs are met in the South and East of Ireland, EirGrid is developing

the Grid Link project, a €500 million investment consisting of a new high voltage power line linking Leinster and munster. The key drivers for this project are security of supply, the integration of renewable energy sources, the facilitation of future interconnection and long-term demand growth.

The second stage of public consultation on the Grid Link project took place between August and October 2012 involving a series of thirteen Open days across the Grid Link Study Area. during early 2013, EirGrid will outline feasible corridor options for the Grid Link Project. The public and all interested parties will be asked to comment on the corridors identified and to provide feedback on the criteria that should be used to determine a least constrained corridor.

detailed information on the Grid West and the Grid Link projects can be found on www.eirgridprojects.com.

PuBLIC CONSuLTATION ON GRId LINk ANd GRId WEST PROjECTS

Grid25 - Delivering Ireland’s Electricity Future

GRId25 NEWSLETTER Issue No. 9 October / November 2012

EirGrid’s Project Development and Consultation Roadmap

STAGE1

STAGE2

STAGE3

STAGE4

STAGE5

PublicPublic and stakeholder consultation on study area and constraints

Public and stakeholder consultation on findings of Stage 1 Report

Evaluate OptionsConsideration of all feedback from Stage 1

Identification of EirGrid’s emerging preferred option (route corridor/site)

Identification of indicative line within corridor or site boundary

Identify and meet landownersof indicative line/site;initial survey

Publication of Stage 2 Report

Pre-applicationconsultation with An Bord Pleanála

Confirm DesignConsideration of all feedback from Stage 2

Conduct environmental studies and surveys

Confirmation of design of line/site proposal including construction methodology

Ongoing engagement with landowners on preferred line route or site

Pre-application consultation with An Bord Pleanála

Prepare PlanningApplication Complete reports andprepare planning application

Preparation of Environmental Impact Statement (EIS)or EnvironmentalReport as required

Conclusion of Pre-application consultation withAn Bord Pleanála

Submit application toAn Bord Pleanála

Wayleaving and ConstructionPreparation ofconstruction plans

Serve wayleave notice to landowners and agree access for construction

Commence construction

PublicPublic and stakeholder consultation on findings of Stage 2 Report

PublicOngoing public information

PublicOngoing public information

Once application submitted, public can make submissions to An Bord Pleanála including at an oral hearing, if held

PublicOngoing public information

Evaluation of Public Consultation process

InformationGatheringIdentify Project Study Area

Identify environmental &other constraints

Identify feasible options (corridor/sites)

Publication of Stage 1 Report

Pre-application consultation with An Bord Pleanála

Page 2: Issue No. 9 October / November 2012 Issue No 7. April 2012 ... · Issue No 7. April 2012 Grid25 is EirGrid’s strategy for the long-term development of Ireland’s transmission system

RECENT INVESTMENT DECISIONS 1 CuNGhILL - GLENREE 110kV LINE

uPRATE 2 kILOTERAN - WATERFORd 110kV LINE

uPRATE3 INChICORE 220kV STATION BuSBAR

uPRATE4 FINGLAS 220kV STATION BuSBAR

uPRATE5 kILBARRy - kNOCkRAhA NO.1 110kV

LINE uPRATE6 SLIGO 110kV STATION BuSBAR uPRATE

RECENT PLANNING LODGEMENTS 7 kINNEGAd - muLLINGAR 110kV NEW

CIRCuIT 8 duBLIN NORTh FRINGE 220kV NEW

STATION

RECENT CPPS 9 duNmANWAy 110kV STATION uPGRAdE

RECENT PROJECT AGREEMENTS 10 FINGLAS 110kV STATION

REdEVELOPmENT11 mOuNTLuCAS 110kV STATION

ShALLOW WORkS12 kILPAddOGE 220/110kV STATION –

NEW STATION13 ShELTON ABBEy 110kV STATION

PROTECTION uPGRAdE 14 LImERICk 110kV STATION WORkS 15 ShANNONBRIdGE 220kV STATION

CIVIL WORkS16 CLONkEEN 110kV STATION

RECONFIGuRATION

RECENT ENERGISATIONS* 17 BALLydINE - CuLLENAGh 110kV LINE

uPRATE18 CORduFF - RyEBROOk 110kV LINE

uPRATE19 kILLONAN - TARBERT 220kV LINE

REFuRBIShmENT20 CAThALEEN’S FALL - GOLAGh T 110kV

LINE uPRATE21 CARLOW 110kV STATION WORkS22 TARBERT 220kV STATION WORkS23 FLAGFORd - SRANANAGh 220kV

CIRCuIT – NEW CIRCuIT24 CORdERRy 110kV STATION BuSBAR

uPRATE25 PORTAN 400kV STATION 26 CRANE 110kV STATION BuSBAR

uPRATE 27 NCC REmOTE OPERATION ThROuGh

SCAdA - PhASE 2

GH

COOKSTOWN

MACETOWNRB

KILTOY

CATHALEEN'SFALL CLIFF

SLIGO

TAWNAGHMORE

MOY

CASTLEBAR

RICHMOND

PLA

BALTRASNA

TIN

NAVAN

KNOCKUMBER

MULLINGAR

ATHLONE

CASHLA

GALWAY

ENNIS

DALLOW

PORTLAOISE

DUNSTOWN

TURLOUGHHILL

ARKLOWSHELTONABBEY

CRANE

WEXFORD

CARLOW

KILKENNY

THURLES

CAHIRDOON

ANNERBALLYDINE

GREAT ISLAND

BARRYMORE

MALLOW

CHARLEVILLE

BANDON

DUNMANWAY

MACROOM

KNOCKEARAGH

CLAHANE

RATHKEALE

MONEYPOINT

TARBERT

CARRICK-ON-

SHANNON

LANESBORO

BINBANE

BRINNY

THORNSBERRY

KELLIS

BUTLERSTOWN

DUNGARVAN

DRYBRIDGE

BLAKE

NEWBRIDGE

SHANKILL

LISDRUM

RATRUSSAN

LOUTH

DUNDALK

MEATHHILL

BELLACORICK

TULLABRACK

MUNGRET

MONETEEN

LIMERICK

MAYNOOTH

FASSAROE

INCHICORE

AUGHINISH

POLLAPHUCA

CLOON

KNOCKRAHA

KILBARRY

SOMERSET

RAFFEENAGHADA

GOLAGH

WATERFORD

GILRA

IKERRIN

NORTH WALLPOOLBEG

SHELLYBANKS

KILTEEL

LISHEEN

GORTAWEE

OUGHTRAGH

CUSHALING

ARVA

MULLAGHARLIN

SHANNONBRIDGE

LETTERKENNY

ARIGNA

FLAGFORD

TRILLICK

IRISHTOWN

CARRIGADROHID

COOLROETRABEG

INNISCARRAMARINA

DUNFIRTH

STRATFORD

MONREAD

KINNEGAD

BALLYLICKEY

DALTON

CORRACLASSY

OLDSTREET

CLASHAVOON

BALLYBEG

CUNGHILL

KILLOTERANCULLENAGH

TIPPERARY

TONROE

HUNTSTOWN

GLENLARA

GARROW

ARDNACRUSHA

RINAWADE

MEENTYCATDRUMKEEN

DERRYIRON

TRALEE

TRIEN

PROSPECT

DRUMLINE

GLASMORE

KILLONAN

AHANE

CORDUFF

CASTLEFARM

SEALROCK

CORDERRY

BALLYWATER

GORMAN

DERRYBRIEN

AGANNYGAL

TYNAGH

CLONKEEN

COOMAGEARLAHY

GLANLEE

BOOLTIAGH

BARODA

ATHY

SINGLAND

SRANANAGH

GLANAGOW

DROMADA

BOGGERAGH

RYEBROOKFINGLAS

CARRICKMINES

WOODLAND

SALTHILL

GARVAGH

MIDLETON

CARROWBEG

CASTLEDOCKRELL

LODGEWOOD

TLONG POIN

CRORY

GLENREE

BALLYMENA

LOGUESTOWN

COLERAINE

LIMAVADY

COOLKEERAGH

KILLYMALLAGHT

SLIEVE KIRK

LISAGHMORE

SPRINGTOWN

STRABANE

OMAGH

ENNISKILLEN

AGHYOULE

MAGHERAFELT

TAMNAMOREDUNGANNON

DRUMNAKELLY

NEWRY

BANBRIDGE

WARINGSTOWN

LISBURN

BALLYNAHINCH

CREAGH

ANTRIM

KELLSLARNE

MOYLEINTERCONNECTOR

KILROOT

CASTLEREAGH

HANNAHSTOWN

BALLYLUMFORD

B

R

ECR

GPSWBCCE

FDG

K

NEWTOWNARDS

RATHGAEL

POWER STATION

CAUTEEN

SORNEHILL

GRId25 PROGRAmmE mILESTONES AChIEVEd The map shows recent milestones achieved in Q3 2012:

400kV Stations

275kV Stations

220kV Stations

110kV Stations

400kV Lines

275kV Lines

220kV Lines

110kV Lines

220kV Cables

110kV Cables

Phase Shifting Transformer

Hydro Generation

Thermal Generation

Pumped Storage Generation

Wind Generation

Transmission Connected Generation

* Please note that the energisation of a project, or an element of a project, does not imply that all works of a particular project are complete.

10

16

4

3

1

2

5

6

7 8

9

13

14

15

18

19

21

20

22

24

26

11

12

17

23

27

25

Page 3: Issue No. 9 October / November 2012 Issue No 7. April 2012 ... · Issue No 7. April 2012 Grid25 is EirGrid’s strategy for the long-term development of Ireland’s transmission system

Planning permission in relation to the proposed overhead 110kV line between the existing Clashavoon 220/110kV substation and the existing dunmanway 110kV substation was granted by An Bord Pleanála in October 2012. The new development is required to reinforce the transmission network in south west Cork, thus increasing the security of supply in the area and also facilitating the connection of renewable generation.

Please see the project website for further information: www.eirgridprojects.com/projects/clashavoondunmanway

EirGrid submitted the planning application for the new kinnegad-mullingar 110kV circuit to An Bord Pleanála in july 2012. An Environmental Report (including an Environmental Impact Assessment Screening Report) was prepared in respect of the proposed development. The application and environmental report may be inspected at the following locations:

•The Offices of An Bord Pleanála, 64 marlborough Street, dublin 1;

•The Offices of Westmeath County Council, County Buildings, mullingar, Co. Westmeath;

•The Offices of meath County Council, County hall, Navan, Co. meath.

The application may be viewed on the following website: www.mullingar110kVproject.ie

This new circuit, an investment of €16m in the midlands region, will help secure electricity supply to the area which if lost would affect both residential and business customers.

CLAShAVOON - duNmANWAy 110kV NEW LINE – PLANNING PERmISSION GRANTEd

kINNEGAd - muLLINGAR 110kV NEW LINE – PLANNING APPLICATION LOdGEd

A planning lodgement was recently submitted to An Bord Pleanála for the proposed development of a new 220kV station in dublin. The dublin North Fringe 220kV reinforcement project will consist of a new 220kV station located off the N32 at Belcamp.

The new station will reinforce the electricity supplies for both the North City and County and represents an investment of approximately €70 million in the region. The 220kV station will be connected into Finglas 220kV station by cable.

duBLIN NORTh FRINGE 220kV NEW STATION – PLANNING APPLICATION LOdGEd

Dublin North Fringe 220kV New Station layout

Page 4: Issue No. 9 October / November 2012 Issue No 7. April 2012 ... · Issue No 7. April 2012 Grid25 is EirGrid’s strategy for the long-term development of Ireland’s transmission system

The Flagford to Srananagh 220kV line was energised in August 2012. This new transmission line now provides a much needed 220kV boost for the North West region meeting the requirements of demand growth and security of supply for industry, business and domestic customers.

The project components included:• Construction of a new 220kV station at Srananagh,

in County Sligo • Construction of a new 220kV line from the existing

station at Flagford County Roscommon to the new station at Srananagh

•The looping of two existing 110kV lines into Srananagh requiring 34km of new line build

• The construction of 11km of new 110kV line from Srananagh to Sligo

The new 220kV line is 56km in length and runs in a general northwesterly direction avoiding technical and environmental constraints that were identified during the planning process. In total, 172 new

lattice steel single circuit 220kV towers have been constructed along the route. The steel for the intermediate towers was manufactured using a special process which reduced the quantity of lattice bracing required and achieved a ‘Reduced Visual Impact’ design.

The completion of this project is attributable to a dedicated, hard-working and multi-talented team from EirGrid, ESB Networks and ESB International.

The 2012 National Ploughing Championships were held in New Ross, County Wexford over three days in September. EirGrid’s exhibition area was the largest to date and told the story of transmission infrastructure in Ireland using pictures, videos, web links, artefacts, games, a scale model and a live link to the National Control Centre. The marquee also showcased the Schools Science Programme and the Grid Link project.

Over 12,000 visitors engaged with the 25-strong EirGrid team of staff volunteers over the three days, and many had the opportunity to talk to and listen to a wide variety of stakeholders.

ENERGISATION OF FLAGFORd SRANANAGh 220kV NEW LINE

PLOuGhING ChAmPIONShIPS 2012

CONTACT dETAILS:

Tel: +353 (0)1 23 70000 (EirGrid Main Reception)Tel: +353 (0)1 70 26642 (Customer Relations Team)Fax: +353 (0)1 66 15375Email: [email protected]: www.eirgrid.comAddress: The Oval, 160 Shelbourne Road, Ballsbridge, Dublin 4, Ireland.

© Published by EirGrid October 2012

Minister for Agriculture, Mr. Simon Coveney, TD and Sean Meagher, Grid Development.

End Mast at Srananagh 220kV Station