isolde technical report intc 14/2/2007

12
Mats Lindroos ISOLDE Technical report INTC 14/2/2007 Mats Lindroos

Upload: aletha

Post on 06-Jan-2016

38 views

Category:

Documents


3 download

DESCRIPTION

ISOLDE Technical report INTC 14/2/2007. Mats Lindroos. Outline. Shutdown HIE-ISOLDE ATC summary. Shutdown. ISOLDE shutdown coordinator: Erwin Siesling, AB/OP Shutdown planning available on the WEB ISOLDE technical meeting minutes - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

ISOLDETechnical report INTC 14/2/2007

Mats Lindroos

Page 2: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

Outline

• Shutdown• HIE-ISOLDE

• ATC summary

Page 3: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

Shutdown

• ISOLDE shutdown coordinator: Erwin Siesling, AB/OP

• Shutdown planning available on the WEB– ISOLDE technical meeting minutes

• Please let Erwin know when you start work, complete work or of possible delays

• Main tasks 2007: Mini-move, repair of Boris tube(s), RFQ cooler installation

Page 4: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

HIE-ISOLDE

• The ISOLDE upgrade group has proposed a staging of the project with the 5.5 MeV/u upgrade having highest priority– Stage 1 (High priority): 13.5 MCHF+32 FTE– External contributions so far: 3.8 MCHF+4 FTE

• Flemish Research foundation, University of Leuven, Knut and Alice Wallenberg foundation, EPSCR

• Funding for HIE-ISOLDE discussed in CERN white paper– Theme 4, 50% external funding

• Started activities:– Prototyping of linac, RILIS/LARIS, RFQ cooler

Page 5: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

ATC/ABOC review 2006

• Session on ISOLDE– Chaired by Steve Myers– Scientific secretary: Fredrik Wenander

• Five presentations covering:– ISOLDE physics, operation, Targets,

REX and organization

Page 6: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

Physics programme (Luis Fraile)

• ISOLDE is a world leading RIB facility– Delivers a large fraction of RIB-ISOL beams

in Europe• Difficult start-up in 2006

– Four experiments had to leave empty handed

• In spite of the difficult start-up 350 shifts delivered– Almost as many as in 2005 (ISOLDE alone)

• The REX and RILIS systems are in increased demand– Flagship systems at ISOLDE which attracts

new Users and makes new physics possible

Page 7: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

Operation (Tim Giles)

• Problems during start-up – Many but uncorrelated problems– The power cuts were outside the control of the section (department)

• Shutdown/start-up coordination– The cold checkup must not be compromised by testing and delays– We need close hands-on shutdown coordination – We need daily coordination meetings during start-up in addition to weekly status

meetings• Targets must be handed over to operation early enough

– Person to follow target from workshop to experiment?• Machine supervisors need better and more target training

– Closer interaction between ISOLDE and PSB operators– ISOLDE specific training for all PSB operators

• As the complexity of the facility increases the machine supervisors have an increasingly heavy workload

– REX and RILIS operation will add to the workload (beyond possible)– Priorities for 2nd job of supervisors not clear

• The specification procedure for application programs is heavy– Short-cuts possible if done within section?– More use of commercial software?– However, we must stick to AB standards to simplify support (Comment: Steve)

• The inflector zone could ease operation– In particular coordination with PS running and interventions– The zone must re-structured from safety viewpoint

Page 8: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

Targets (Thierry Stora)

• The limited resources in the section demands a limit on the number of UCx targets per year

• The support for the experimental area need a dedicated technician

• The targets should be followed from workshop, through target test and to the experiment– Valuable support from EURISOL staff and MC fellows for target

tests• Consolidation required:

– The tape station is crucial for ISOLDE and in desperate need of consolidation

– The front-ends must be replaced regularly, done on operation budget as there is no consolidation money available

• Radiation protection:– Disposal of targets and work in the class A lab require a RP

technician continuously – Many tasks during the shutdown requires that a Radiation

Protection technician is present

Page 9: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

REX (Fredrik Wenander)

• REX-ISOLDE is the flagship programme of ISOLDE– The machine delivers a high number of shifts reliably

• 18 out of 20 runs successful in 2005 and 2006• The low energy part ticks like a clock

– EBIS cathode change requires complete bake-out• Linac RF power supplies not yet reaching specifications

– Work in progress this shutdown• The pressure on the small specialist team has been extremly

high– Set-up during weekend. On-call: 10 weekends/specialist– Technical support largely done by two machine specialists– OP technician joined team in 2006 and is just completing the

training to become part of piquet team– The support groups still have very limited knowledge of REX– No dedicated superintendent– We should not split the machine in a low energy and linac part.

• The migration of the control system to AB standards has taken a lot of resources for no improvement– Re-specify existing Visual Basic programs

Page 10: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

Organization (Jacques Lettry)

• The ISOLDE operation is too segmented– Need to follow the beam from target to experiment

• The link between the Users and the machine supervisors must be re-established

• There are many external contributors but the contributions are highly fractioned

– External contributions goes to visible projects leaving support groups to support an ever increasing number of activities

• We can only hope to re-distribute manpower– Better coordinate the work to save resources– Make use of 2nd job for operators for ISOLDE maintenance work

• Could we reduce the workload by reducing the number of shifts and do consolidation instead?

– The operational hours are fixed by RB. A reduction must correctly communicated to the Users

• The RILIS project is also a flagship activity at ISOLDE with an ever increasing demand

– The external contributions (such as RILIS/LARIS) grant represents a major consolidation of old systems

• New projects– Mini-move is externally financed but leaves REX with a more complex system– The RFQ cooler can become a new flagship project of ISOLDE but the external

contributions are highly fragmented.

Page 11: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

Conclusions 1 (Steve Myers)Still to be discussed and agreed by ABMB

• In spite of a difficult start-up the number of shifts of physics were maintained

• Flexibility in schedule:– Can the physics coordinator leave more room for

recovery after problems?– Investigate if the inflector zone can be made

operational again (AB)• Safety:

– Audit of safety at ISOLDE e.g. need of INB. (AB)• Consolidation:

– The tape station should be replaced ASAP (AB)– Can we modify the risk analyses so that some limited

resources also becomes available for end-users (low impact factor items) (AB)

Page 12: ISOLDE Technical report INTC 14/2/2007

Mats Lindroos

Conclusions 2 (Steve Myers)Still to be discussed and agreed by ABMB

• Manpower:– The manpower available for radiation protection and

vacuum for ISOLDE is critical• Software:

– ISOLDE should maintain AB standards to ease support. The specification process is demanding but necessary.

• Organization:– The function of daily technical coordination and

technical spokesperson should be separated (AB)– The ATB and OP group will discuss a possible merge/re-

organization of the ISOLDE activities to optimize the use of resources (AB)

– REX support must be assured on the same level as for the rest of the facility (AB)

– The use of the RILIS should be limited to the agreed 1500 hours to free the staff to install the new solid state laser system which represent a major consolidation of the RILIS (AB)