SELLER/FABRICATOR DATE OF MEETING JOB/P.O.NO. REPORT REF. PAGE NO.
IMECO September 20-21, 2013 11647,11667,1167611677
001 1 of 2ACTION BY
MINUTES OF MEETING
SELLER REFERENCE No. CONTACT PERSON TELEPHONE & FAX No. STATUS
Mr. Trung ; Mr. Son
PRODUCTION LOCATION (FABRICATOR) AUTHOR P.O. DEL. DATE CURRENT PROM. DATE
15/1/2014
MATERIALS/EQUIPMENT
Project Descriptions
ParticipantsMr. Son – Technical QA Director.Tuan DA – Production Director.Tuan HA – Technical Manager.HanhDV – QC Manager.Lam – QC Engineer.
Hussein Adly - NEM-PS – Technical advisor
PO 11647 SamSun PJT
Drawings: all Drawings have been received at IMECO.
QC: QC Document Status as attached.
Materials: outstanding of FIM has been arrived at HCMC port on 18/9/2013, Customs is ongoing.
Fabrication:
Blades, shafts have been assembled into the damper. Actuator supports, stuffing boxes, bearing supports have been welded into the damper casing.Sealing ledges has been welded into the casing.Blades will be dismantled and release for painting tomorrow 24/9/2013.
Inspection: function inspection 1/10/2013, Packing inspection 8/10/2013
Delivery: 10/10/2013.
---------------------------------------------------------------------------------------------------------------------------------------------------
PO 11667 Temple II
Drawings: all Drawings have been received at IMECO.
QC: QC Document Status as attached
Materials: No FIM has been received yet.
Fabrication:Fit-up and Welding of casing has been done already.
Fit-up and welding the blades with attached stiffeners have been done.NDT has been done.
Inspection: function inspection 5/11/2013, Packing inspection 12/11/2013
Delivery: 18/11/2013
8/14/2019 ISO 20-9-2013.pdf
http://slidepdf.com/reader/full/iso-20-9-2013pdf 2/2
SELLER/FABRICATOR DATE OF MEETING JOB/P.O.NO. REPORT REF. PAGE NO.
IMECO September 20-21, 2013 11647,11667,1167611677
001 2 of 2ACTION BY
MINUTES OF MEETING
PO 11676 Intergen
Drawings: all Drawing have been received at IMECO
QC: QC Document Status as attached
Materials: no FIM has been received yet
Fabrication:
Fit-up and welding the casing has been done.NDT on the casing has been performed.Cutting the blades is ongoing.
Inspection: function inspection 25/11/2013, Packing inspection 30/11/2013
Delivery: 2/12/2013
---------------------------------------------------------------------------------------------------------------------------------------------------
PO 11677 Woclawek
Drawings: all Drawing have been received at IMECO
QC: Project was announce on HOLD due to IMECO submit wrong QC Documents, IMECO re-submitted thecorrect QC documents acc.to EN on16/9/2013.
Materials: no FIM has been received yet.
Fabrication:
Fit-up and welding the casing has been done.NDT on the casing has been performed.Cutting the blades is ongoing.
Inspection: function inspection 15/11/2013, Packing inspection 22/11/2013
Delivery: 25/11/2013