isiolo airport executive summary
TRANSCRIPT
-
8/2/2019 Isiolo Airport Executive Summary
1/16
Airport Pavement Design
Report
Engineering Report No:
ISAT-ES 0211 02
EXECUTIVE SUMMARY
Kensetsu Kaihatsu LtdFebruary 2011
Government of the Republic of Kenya
Kenya Airports Authority [KAA]
-
8/2/2019 Isiolo Airport Executive Summary
2/16
-
8/2/2019 Isiolo Airport Executive Summary
3/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 3
2011KENSETSU
KAIHATSU
EXECUTIVE SUMMARY
ES1 Introduction
The Kenya Airport Authority (KAA)
commissioned Kensetsu Kaihatsu Consultants
in the Rehabilitation and Restoration of Isiolo
Airport Pavement Project in Isiolo County to
carry out a design of the airport pavement
facility using the Boeing 737-800 as the design
aircraft with provision for future expansion.
The existing airstrip was constructed during
the colonial era and what is remaining is a
dilapidated runway. The airport is part of the
LAPSSET Corridor initiative where it will play
a big role in connecting the Lamu Port in Lamu,Coastal Kenya to Ethiopia and South Sudan.
The airport will be constructed in phases;
phase one will involve the terminal buildings
with 1.2km runway and other facilities like
apron, taxiway. The runway will be expanded
later under subsequent phase[s] to cater for
lager planes.
Actual implementation of the project started in
July 2004 with the engagement of a local
contractor to construct an arrival building,control tower, fire and rescue building, a
3.3km runway, access road, car park and apron
up to sub-base level. The government then
requested its development partners to provide
funding for further development.
The Contract for the first phase of the project
was signed in January 2011 between the
Kenya Airport Authority and Kundan Singh
Construction Company. The pavement worksare anticipated to take about 6 months.
A detailed description of the Scope of Worksunder this phase of construction is given in the
Contract Documents of the Construction ofBuildings and Pavements of Isiolo Airport.
Plate ES1.2 Site photo showing the condition
of the pavement
ES.2 Background of Design Review of IsioloAirport Pavement Structure
ES2.1 Necessity for Design Review
Upon signing of the Contract, the Contractor, in
accordance with Clause 8 of The FourthEdition 1987 FIDIC Conditions of Contract (ref.
to Table 1.2.1 of the Main Report), undertook
monitoring, technical evaluation and
geotechnical engineering investigations in
order to confirm, more precisely, the
engineering properties of the existing soils as
well as the behavior of the existing ground andpavement structure.
The preliminary results indicate that theexisting ground and pavement structure
exhibited much higher bearing capacity and
strength responses in comparison to the
values that may have been considered in the
Original Design.
As a consequence, the Contractor made a
decision to embark on further and more
detailed laboratory and in-situ experimental
testing, technical evaluation, geotechnical
engineering investigations and analyses.This was also in consideration of the fact that it
is most likely the Original Design did not take
-
8/2/2019 Isiolo Airport Executive Summary
4/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 4
2011KENSETSU
KAIHATSU
into account the pozzolanic cementetious
nature of the existing Geomaterial and its
immediate response to compaction and the
effects of time related consolidation,
thixotropy and creep (secondary
consolidation).
This would certainly therefore have influencedthe Original Design Concept, selection of
materials and design of the pavement layerconfiguration.
In view of the foregoing facts, and in
consideration of the recent International trend
whereby emphasis is placed on fostering and
enhancing Value Engineering (VE) based
approach in the design and construction of
civil engineering structures (ref. to Sub-Clause
13.2 quoted hereafter), the Contractor made
the engineering judgment to undertake a
Detail Design Review (DDR) of the IsioloAirport Pavement Structure.
Relevant VE Sub-Clause 13.2 of The Bank
Harmonized Edition of the Conditions of
Contract IFCE, FIDIC
Clause 13.2 Value Engineering
The Contractor may, at any time, submit to the
Engineer a written proposal which (in the
Contractors opinion will, if adopted, (i)
accelerate completion, (ii) reduce the cost to
the Employer of executing, maintaining or
operating the Works, (iii) improve theefficiency or value to the Employer of the
completed Works, or (iv) otherwise be of
benefit to the Employer.
The proposal shall be prepared at the cost of the
Contractor and shall include the items listed in
Sub-Clause 13.3 [Variation Procedure].
If a proposal, which is approved by the Engineer,
includes a change in the design of part of the
Permanent Works, then unless otherwise agreed
by both Parties:
(a) The Contractor shall design this part,(b) Sub-paragraphs (a) to (d) of Sub-Clause 4.1
[Contractors General Obligations] shallapply, and
(c) If this change results in a reduction in thecontract value of this part, the Engineer shall
proceed in accordance with Sub-Clause 3.5
[Determinations] to agree or determine a fee,
which shall be included in the Contract Price.
This fee shall be half (50%) of the difference
between the following amounts:
(i) Such reduction in contract value, resultingfrom the change, excluding adjustments
under Sub-Clause 13.7 [Adjustments for
Changes in Legislation] and Sub-Clause
13.8 [Adjustments for Changes in Cost],and
(ii) The reduction (if any) in the value to theEmployer of the varied works, taking
account of any reductions in quality,
anticipated life or operational efficiencies.
However, if amount (i) is less than amount (ii),
there shall not be a fee.
Interpretation of Clause 13.2
Value Engineering is basically the development
and application of Advanced Technologies aimed
at realizing cost-effective, durable, sound
engineering and maintenance friendly structures.
The Contractor intends to achieve this goal by
adopting the State of the Art Technologies
developed and widely applied in this region and
introduced in the various sections of the Main
Report.
These Technologies have realized enormous time
savings, whilst further enhancing the
Engineering Properties by at least 150 300%.
Specifically, this mainly culminates in the
enhancement of the Structural Capacity,
Serviceability Level, Bearing Capacity, Strength
and Deformation Resistance of the Pavement
Structure.
ES2.2 Scope of Investigation and Main
Objective of Study
1.2.2 Scope of Works
The consultants, Kensetsu Kaihatsu Limited
were commissioned by the Client, Kenya
Airport Authority, to undertake acomprehensive geotechnical engineering
analysis and review of the Existing design by
employing a Value Engineering (VE) approach
and set up State-of-the-Art International
Standards fostering engineering and
scientific concepts that can be tailored and
applicable in Isiolo, Kenya.
The assignment included but was not limited
to the following tasks:-
i) Review the design using Boeing 737-800as the design aircraft.
ii) Review comprehensively, the ExistingDesign documents.
iii) Study the US Federal Aviation Administration (FAA) Advisory Circular
Airport Pavement Design and
Evaluation AC 150/5320-6D, ICAO
Aerodrome Design Manual, Materials and
Specifications, ICAO recommended
practices as detailed in Annex 14 Volume
1, and any other relevant documents.
iv) Undertake comprehensive Site Surveysand Investigations.
v) Carry out detailed analyses andassessment of the test data obtained fromboth in-situ and laboratory tests
performed in Kenya.
-
8/2/2019 Isiolo Airport Executive Summary
5/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 5
2011KENSETSU
KAIHATSU
vi) Assessment of the laboratory equipmentand capability of the same to carry out
material acceptance and pavement
control testing.
vii)Carry out material investigation,sampling and testing for the proposed
runway.viii) Perform tests on any other suitable
material sites for aggregate sources, later
to be utilized civil works.
ix) Carry out geo-material improvement,mechanical, & chemical stabilization and
testing for any non-compliance materials
and/or for purposes of enhancing the
engineering properties of the compliant
materials.
x) Build capacity in terms of trainingmanpower, and laboratory Technicians
on test methods and quality control.
ES2.2.2 Isiolo Airport Project and
Surrounding Areas
Fig. 1.1 shows the surrounding districts of
Isiolo district
Fig. ES1.1 Lay Out of Isiolo
Fig. 1.2 Satellite Image of Isiolo Airport
ES2.3 Geophysical Details of Isiolo Airport inIsiolo within Isiolo Region of Kenya
The site for the Isiolo Airport located in Isiolo,
Kenya, and its geographical coordinates are
020'17" North and 3735'28" East and its
original name (with diacritics) is Isiolo.
Airports in Isiolo and in the neighbourhood:
Garbatula Airport (distanced
approximately 105.7 km)
Garissa Airport (distanced approximately
247 km)
Hola Airport (distanced approximately
341 km)
Marsabit Airport (distanced
approximately 225 km)
Wajir Airport (distanced approximately
317 km)
Bura Airport (distanced approximately
308 km)ES2.4 Relevant Documents and Records
Reference is made mainly to the following
documents and records.
1. United States Federal AviationAdministration (US FAA) Advisory Circular
No. 150/5320-6D
2. International Civil Aviation Organization(ICAO) Annex 14 Volume I AerodromeDesign and Operations
3. Aerodrome Design Manual, Part 34. Boeing 747-100 Guide to Aerodrome
Design and Technical Data
5. The Civil Aviation (Aerodromes)Regulations, 2007
6. AASHTO Guide to Pavement Design7. Transport Research Laboratory (TRL)
Overseas Road Note 31, Berkshire, UnitedKingdom
8. Japan Road Association Pavement DesignManual
9. Kenya Roads Design Manuals10.Materials Report and Test Results11.Reconstruction of Airport Pavements at
Isiolo Airport
ES2.5 Brief Background of Project Area
The Study including GeotechnicalInvestigation was carried out for Isiolo Airport
and the site photos are depicted in Plate 1.3
ISIOLO
GARISA
MERU
MARSABIT
-
8/2/2019 Isiolo Airport Executive Summary
6/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 6
2011KENSETSU
KAIHATSU
Plate ES1.3 - Photos Superimposed on
Satellite Imagery showing the Airport
Figure ES1.4 Location map of Isiolo Airport
Kenya is located in Eastern Africa between
longitude 340 and 420 East, Latitude 50 North
and 50 South.
Kenya is the second largest of the East Africa
countries (i.e. Kenya, Uganda, Rwanda,Burundi and Kenya), has a spectacular
landscape of mainly three physiographic
regions namely the coastal plains to the east;the inland plateau; and the highlands. The
Great Rift Valley that runs from north east of
Africa through North western and southwestern Kenya down to Kenya is another
landmark that adds to the scenic view of the
country. The valley is dotted with unique lakes
which include Lakes Turkana, Baringo,
Bogoria, Naivasha, Nakuru, Elementaita, Logipi
and Magadi.
ES3 Determination of PavementStructural Design
Determination of Total Pavement Thickness
Required
Subsequent to determining the Mean-sectionDesign CBR values for the subgrade and the
sub-base (ref. to table 3.1), the weight on the
main landing gear was determined from Fig.
7.2.4 in Chapter 7 of the Main Report. Having
pre-determined the design aircraft and the
number of annual departures of the design
aircraft, the design curves in Fig. 7.2.5
presented in Chapter 7, based on the U.S. ArmyCorps of Engineers Design Method S-77-1 and
the U.S. FAA Design method, the totalpavement thickness required was derived.
ES3.2 Thickness of Sub-base
Refer to Section ES7.1.1 of this Executive
Summary.
ES3.3 Thickness of Surface Course
Refer to Section ES7.1.2 of this Executive
Summary.
ES3.4 Thickness of Base Course
Refer to Section ES7.1.3 of this Executive
Summary.
ES3.5 Thickness of Non-Critical Areas
Refer to Section ES7.1.4 of this Executive
Summary.
ES3.6 Typical Cross-section
Refer to Section ES7.1.5 of this Executive
Summary.
ES4.4 Construction Time Comparative
Analysis
Refer to Section ES7.2.4 of this Executive
Summary.
ES5 Materials Characterization and
Analysis of Test Results
ES5.1 Basic Physical and Mechanical
Parameters
Table ES5.1.1 shows the typical basic physical,mechanical and bearing capacity properties of
existing BCS soils within the Isiolo Airport
Project Area.
Table ES5.1.1 Typical Pre-treatment/Pre-
consolidation Material Test Results
1
2
3
4
5
6
7
8
9
# TESTED PARAMETERSTEST VALUE
REMARKS
Computed UCS (Mpa)
CBR@100%MDD - Soak
MDD - Kg per Cubic meter
OMC
Atterberg - LL
0.05
2.00
1,129.00
34.50
120.00
The subgrade soil has a lot of fines
CBR@100%MDD - Unsoaked 17.00
Atterberg - PI
Atterberg - LS
53.0067.00
23.00
Atterberg - PL
-
8/2/2019 Isiolo Airport Executive Summary
7/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 7
2011KENSETSU
KAIHATSU
ES5.2 Correlation between Physical,
Mechanical and Strength parameters
The typical pre-treatment (pre-
stabilization)/pre-consolidation basic physical,
mechanical and bearing capacity for material
tested from the sub-base material at BP3 Ruiri.
ES 5.3 Development of test regimes
To attain Optimum and a value engineered
design, several Test Regimes were developedto help us achieve the optimum designs. It
involves the comparison of various designs
options and modeling the different structuresin the Lab.
Table ES5.2.1 Summary of Stabilization
Test Results
A. Neat Material
B. OBRM SUBBASE MATERIAL
C. OPMC SUBBASE MATERIAL
D. SUMMARY OF THE TEST RESULTS-
COMPARATIVE ANALYSIS
E. SUMMARY AND COMPARISON OF
GRANULAR SUB-BASE MATERIAL FOUND IN
THE VICINITY
From the tables above the following can beinferred:
The gravel at BP3 is of good sub-base quality.
It has natural intrinsic cementetious
behaviour. This makes it posses high
engineering properties in comparison to
other materials within the location [see table
above].
The grading of BP3 is satisfactory but we will
be required to add 20% Quarry Dust to
improve on the densities.
Neat 1 1 1 1 1 1 1
1 1 1 1 1 1 2
1 1 1 1 1 1 21 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 2
1 1 1 1 1 1 4
Granular Material-
Gravel
Stabilization
RateM ode of c uring M DD O MC
1d c/s
PL LL PI GRADING
1d/c
UCS
3d/c7d/c
1d/c
1d c/s
3d c/s
3d/c
7d/c
3d c/s
1d/c
3d c/s
1d/c
3d/c
7d/c
1d c/s
3d c/s
BP3
3d/c
7d/c
1d c/s
3d c/s
1%
2%
3%
4%
6%
1d/c
3d/c
7d/c
1d c/s
REMARKS
BP3-NEAT SUBBASE BASE
1 1.23
2 52.00 Not
-
8/2/2019 Isiolo Airport Executive Summary
8/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 8
2011KENSETSU
KAIHATSU
The strength properties, densities and
particle of the neat BP3 material is
enhanced by the inclusion of the 20%
quarry dust and 2% cement.
The cement used is Bamburi PowerPlus. It
is reported that PowerPlus type of cementgains strength immediate/sporadically
after stabilization and after about 28 days
the strength normalizes; PowerMax gains
strength with time and its expected to
yield maximum strength after 28 days.
Laboratory tests and monitoring are
ongoing to confirm this.
The OPMC batched material evidently
shows improved properties. We have an
increase of more than 150% in strengthsafter 3 day cure. Further tests are still on-going to ascertain the behaviour with time
and at different conditions as described in
5.2
From the 1 day cure results we can
tentatively decide that our design will be
BP3+20% Quarry Dust + Tensar TX170Geogrids + 2% cement is the optimum
design
ES5.3 Dynamic Cone Penetration Test ResultsThe ground and Geomaterials characteristics
under dynamic loading as simulated by the
Dynamic Cone Penetration determined in this
Study, are summarized in the Tables below,
while their behavior is graphically
characterized in the corresponding Figures.
The fact that the existing pavement is very
sound can be derived from the very highbearing capacity and strength magnitudes that
it exhibits.
Series 5.4.1 Tables and Figures for DynamicCone Penetration Results for Isiolo Airport
The following derivations can further be made
from these tables and figures.
1. Most of the locations on thecarriageway of the existing
pavement structure exhibit high
bearing strengths under
conditions tested with averages of
CBR 62%.
2. The average CBR mean results isabout 62% for dry in situ
conditions while the soaked
conditions gives average CBR
mean of less than 5%. From the
two CBR figures, it is prudent that
the subgrade/foundation Design
considers options for moisture
control in its design. We are
proposing the GI-MC method for
the design and construction of the
improved subgrade. This because
when the foundation is dry i.e.
when moisture is controlled, the
in-situ strengths are very high
compared when it is partially orcompletely soaked.
3. The Subgrade BCS soil has PIvalues of 67%. This indicates a
very high value of fines and clay
minerals in its composition. The
design needs to cater on how to
prevent the contamination of the
Base/sub-base layers through
infiltration/ingress of fines into
the upper pavement layers
[base/sub-base]. The presence of
fines into these layers will be very
-
8/2/2019 Isiolo Airport Executive Summary
9/16
-
8/2/2019 Isiolo Airport Executive Summary
10/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 10
2011KENSETSU
KAIHATSU
Laboratory UCS Tests of Cement Stabilized
[Chemical stabilization]
Table ES5.7.1(b) Summary of Consolidation
Stress Parameters Derived from
Laboratory UCS test of Cement- Geogrid
Stabilized OPMC-[Chemical - Mechanical
stabilization]
ES5.8 Shearing Strength Test Results
The shearing strength parameters aresummarized in Tables ES5.2.1 Series present
the UCS laboratory test results for specimens
tested at 1%, 2% and 3% cement treatmentlevels, while the graphical characteristics of
the loading to failure are shown in the
corresponding figures. Table ES5.8.1 is asummary of these results in comparison with
values that are computed adopting empirical
equations defined in Chapter 4 of the Main
Report.
On the other hand, a summary of the shear
parameters derived from in-situ tests is given
in Table ES5.2.3.
This Table presents the results computed by
adopting Eqns. 4.18 in sub-section 4.3.1 and4.33 ~ 4.38 in sub-section 4.5.1 of Chapter 4 of
the Main Report.
The derivations from these results are briefly
presented after Table ES5.8.2.
Table ES5.8.2 Summary of Shear Stress
Parameters Derived from In-situ Tests
The following observations can be made from
the foregoing Tables ES5.8.1 ~ 5.8.2 and the
corresponding Figures.
The laboratory test results indicate enhanced
intrinsic shearing properties of the pozzolanic
material even at very low cement treatment
ratios (ref. to results of 1% additive tocomparative parameters presented in Chapter7 from various International Agencies).
1) The in-situ test results show that theshearing strength is immensely enhanced
as a result of the coupled effects of long
term consolidation and cementetious
agglomeration.
2) From Table ES5.8.1, it can be observed thatthere is a very good agreement between
the tested and computed values. Thisconfirms the precision of the test results
accordingly.
3) On the average, the in-situ values arehigher that the laboratory test results
{UCSlab = 7.75 MPa compared to UCSin-situ =
8.95 MPa(average)}.
However, as can be observed from the results
summarized in Tables ES5.5.1 in the preceding
section ES5.5, the results tend to be very
similar when corrected for the effects of Long
Term Consolidation by applying the following
equation.
STCn
STC
STCSTCLTC
CSRAttK
qKq
'/100
max0
max
Where,
Superscript LTC and STC denote long term and
short term consolidation respectively whereas t
: LTC time and to : STC time., for OC conditions
( a/ t)fcSTC=1.
MIX
Sample (MPa) (MPa) (MPa) (MPa) ( MP a) ( MP a)
1 P o zz o lan ic 0 .6 6 0. 33 1. 06 4 8. 06 0 1. 291 1 5. 787 0 .3 28 1 .01 0 0 .93 8 0. 42 3 0. 38 0 1 .31 0. 26 1. 06 1. 48
3 P ow er Ma x 0 .6 0. 30 0. 96 4 7. 95 2 1. 290 1 5. 770 0 .3 29 1 .01 1 0 .93 6 0. 42 4 0. 38 1 1 .19 0. 23 0. 96 1. 35
4 P o wer Pl u s 0 .9 6 0. 48 1. 54 4 8. 60 2 1. 295 1 5. 875 0 .3 27 1 .00 8 0 .94 9 0. 41 9 0. 37 9 1 .90 0. 37 1. 54 2. 15
Notethatthe cementcontectis 3% andthe curingmode3days soak
qC pC
SerialNo. UCSqu (MPa)Cu
CSR
maxq
CSR CSR/1
CSR OK
CK
1
ac
1
rc
MIX
Sample (MPa) (MPa) (MPa) (MPa) ( MP a) ( M
1 Pozzolanic 0 .792 0.40 1.27 48.2 99 1.2 92 15.8 26 0.3 28 1.0 10 0.94 3 0.42 1 0.3 80 1.5 7 0.3 1 1.2 7
0 P o we rM ax 0 . 9 62 0.48 1.54 48.6 06 1.2 95 15.8 76 0.3 27 1.0 08 0.94 9 0.41 9 0.3 79 1.9 1 0.3 7 1.5 4
4 P o we rP l us 1 .1 48 0.57 1.84 48.9 42 1.2 97 15.9 31 0.3 26 1.0 07 0.95 6 0.41 6 0.3 77 2.2 7 0.4 4 1.8 4
Notethatthe cementcontectis 3% andthe curingmode3days soak
pqCSerialNo. UCS qu (MPa)
CuCSR
CSR CSR/1
CSR OK
CK1
ac
1
rc
-
8/2/2019 Isiolo Airport Executive Summary
11/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 11
2011KENSETSU
KAIHATSU
ES5.9 Modulus of Deformation, Elastic
Modulus and Linear Elastic Range
A summary of the derived modulus of
deformation, elastic and shear modulus and
elastic limit strain, which is defined as the
range of linear elastic and recoverablebehavior, given in Tables ES5.9.1 and 5.9.2,
were computed by applying Equations 4.48 ~
4.52 of the Main Report.
The normalized relations are also presented in
the same Tables.
Table 5.9.1 Summary of Modulus ofDeformation Parameters from Lab Test
Results
Table ES5.9.2 Summary of Modulus of
Deformation Parameters - In-situ Test
Results
The results of deformation properties and the
linear elastic range are presented in Table
5.10.1 below.
The results basically indicate that as the
shearing strength increases with the
deformation resistance, the linear elastic rangeis immensely enhanced.
ES5.10 Deformation Properties and Linear
Elastic Range
The results of deformation properties and the
linear elastic range are presented in Table
5.10.1 below.
The results basically indicate that as the
shearing strength increases with the
deformation resistance, the linear elastic rangeis immensely enhanced.
Table ES5.10.1 Summary of Modulus of
Deformation Parameters - in-situ Test
Results
ES5.11 Summary of the effects of curing
period on soil particle agglomeration and
unconfined strength.
From the laboratory test results OPMC
Stabilized + Geogrid samples yields UCS values
of 3.32 after 3day cure with 2% cement
content [PowerPlus]. After extrapolation from
the relation that is explained in chapter 4, the
following table gives the expected calculated
properties after several days of curing.
Table ES5.11.1 Table: Effects of curing
period on OPMC Level 3
Table 5.11.2 Effects of curing period on
Resulting, ER Composite Pavement
7. PAVEMENT STRUCTURAL DESIGN
7.1 Scope
1 BCS subgrade 12 1 07 4 35 7. 85 5 .2 3 0 .3 8 0 .1 02 78 2 0. 16 98 85 1 37 13
2 BP1 LMD gravel 347 3 83 4 1 27 8. 04 4 1. 76 0 .6 3 0 .2 50 79 4 0 .3 98 41 0 1 71 8
3 BP2 78 Tank Batt 389 4 00 7 1 33 5. 55 4 4. 87 0 .6 7 0 .2 69 63 2 0 .4 26 03 3 1 59 9
5 BP5 Murero 173 2 94 6 98 2. 10 2 7. 17 0 .5 0 0 .1 74 09 7 0. 28 22 99 2 64 1
6 BP6 LMD Sandy 49 1 81 8 60 6. 02 1 2. 36 0 .4 1 0 .1 18 92 9 0. 19 55 80 5 80 6
Specimen
MIXE50
(MPa)
Emax
(MPa)
Gmax
(MPa)ELS
(a)max
(calculated)
(%)
(a)50
(calculated) (%)
(a)ELS
(10-3) (%)
Emax /
qmax
Effects of curing period on OPMC Level 3 & Geogrid, PowerPlus 2% for 3 days Cure/soa
1 24 2.28 4,621.72 95.00
3 72 3.31 5,327.08 138.06
7 168 5.51 6,463.93 229.68
14 336 11.09 8,431.71 462.23
28 672 26.11 11,673.06 1,087.98
56 1344 66.30 16,632.49 2,762.40
112 2688 173.09 23,951.49 7,212.12
Curing Periods,
CP[hours]UCS, qu
f[Mpa]Days Emax CBR [%]
Effects of curing period on Resulting Er (composite pavement)
UCS, QurFCB
1 24 2.11 0.80 1,414.00 1,317.00 87.92
3 72 3.76 1.64 5,589.87 4,073.88 156.71
7 168 5.77 1.89 6,576.69 4,305.93 240.38
14 336 8.23 2.10 7,527.62 4,481.61 342.95
28 672 11.44 2.31 8,530.34 4,646.73 476.60
56 1344 15.59 2.52 9,595.18 4,802.78 649.52
112 2688 20.93 2.73 10,731.70 4,950.97 872.02
224 5376 27.77 2.94 11,949.16 5,092.26 1,157.02
448 10752 36.50 3.15 13,256.83 5,227.42 1,520.65
896 21504 47.59 3.36 14,664.18 5,357.11 1,983.08
1792 43008 61.67 3.57 16,181.03 5,481.88 2,569.43
Days Curing Periods,
CP[hours]UCS, qur
FCA[Mpa] EmaxER
CACBR [%]EmaxER
-
8/2/2019 Isiolo Airport Executive Summary
12/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 12
2011KENSETSU
KAIHATSU
This chapter reviews the EXISTING pavement
design, determines the design based on the US
FAA/ ICAO method of Design, analyzes various
options and recommends the VE based design
for the Isiolo Airport aimed at serving aircraft
with gross weights of up to 79,016kgs for
B737-800 series.
The design review is limited to the Airport
Pavement and does not include geometric
design or design for any other of the airportfacilities.
7.2 Fundamental Design Philosophy
The design largely adopts the
recommendations made through the Advisory
Circular (AC) No. 150/5320-6D dated April
30th
, 2004, Airport Pavement Design andEvaluation.
Reference is also made to the 737 Airplane
Characteristics Airport Planning D6-58325-6published in May 1984 by Commercial
Airplane Company, which is a Division of the
Boeing Company.
The Design Philosophy is based on the United
States Federal Aviation Administration (FAA)
and the International Civil Aviation
Organization (ICAO) recommended practices.
Table 7.2.1 Summary of Major Design
Considerations
Table 7.2.2 Technical Specifications for
Boeing Aircraft detailing the B737-800
Fig. 7.4 Landing Gear Loading on Pavement
- Model 737-800 Aircraft
-
8/2/2019 Isiolo Airport Executive Summary
13/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 13
2011KENSETSU
KAIHATSU
Fig. 7.5: Pavement Thickness Design as per
the Conventional Design.
Fig. 7.6: Pavement Thickness Design using
the OPMC GI-MC Technique;
Table 7.7.1 Summary of Main Design
Parameters Adopted
Based on the data presented in Table 7.5, the
Total Pavement Thickness required
conventionally is 16 inches or 400mm
Based on the data presented in Table 7.6, the
Total Pavement Thickness required using
OPMC technique in this design is 200mm.
7.7.6 Typical Cross-section A
Table 7.8.1 Summary of the structural
capacity, deformation resistance of thecomposite pavement
The Table above shows the results of the
individual layers and the composite pavementsafter one day cure. The strength as explained
and inferred in Chapter 5 will increase with
time.
The summaries from table 7.8.1 above shows
that our proposed pavement structure is
adequate to perform as a runway that will
handle Boeing 737-800 aircraft with annual
departures of 3000 flights for 20 years.
Cross-
section A
Cross-
section B
TA TA qu,A[Mpa] qu,B[Mpa]
T 1 A sp ha lt co nc re te ACWearing/Binding
Course 1 7 7 4.50 4.50 4,419.00 4,419.00
T2 OPMC Level 3
Subbase
Geomaterial +
Geogrid 0.62 20 20 3.32 3.32 5,331.15 5,331.15
T3
BCS
Ground
Improvement
Subgrade 0.35 20 40 1.38 1.38 2,179.02 2,179.02
where:
ERCA
- resultant ER for cross section A
ERCB
- resultant ER for cross section B
492.32
1414
1317100
1.46
65.13
Composite
pavementERCB
T1+T2+T3+
T4
0.94
0.05
Composite
pavementER
CA100
0.83T4Existing Black
Cotton SoilSubgrade 0.05 53 33
S/No Description Pavement LayerOPMC/GG
CoefficientE
Bmax[Mpa]
qu[Mpa]E
Amax[Mpa]
Determin
ation of
Thickness
for This
-
8/2/2019 Isiolo Airport Executive Summary
14/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 14
2011KENSETSU
KAIHATSU
Conclusion:
The design used in this project realizes a
reduction of the overall thickness of about
125mm as compared to the conventional
designs.
CHAPTER 9
9. METHOD OF CONSTRUCTION
General Method of Construction:
9.1 Procedure for Construction of Ground
Improved Subgrade
9.2 Procedure for Construction of Sub-
Base/Base Course
9.3 Procedure for Construction of Asphalt
Concrete Wearing Course
10 Conclusions and Recommendations
10.1 Conclusions
Based on the derivations noted in this Report,
the following main conclusions can be made.
1. The subgrade CBR is high when thesubgrade condition is Unsoaked and
the CBR values drops tremendouslywhen the subgrade is wet. The
-
8/2/2019 Isiolo Airport Executive Summary
15/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 15
2011KENSETSU
KAIHATSU
subgrade soil, predominantly Black
Cotton Soil [BCS] have very high
amount of fines [PI of 62%]. The
intrusion of the fines into the well
graded base/sub-base material should
be stopped since the presence of fineswill result to the increase of the
capillary action of the layer making the
base vulnerable to moisture. The
presence of fines will therefore lead to
the drop in strength of the pavement
structure.
2. The subgrade is improved using theGround Improvement Moisture
Control Technique where sand
piles/columns are used to control
moisture.
3. The gravel materials from borrow pitswithin the vicinity of the Project Area
are suitable for the construction of the
Base Course pavement layer. The
existing gravel material is porous and
has relatively low densities. We have
batched the gravel with 0.6mm quarry
dust to improve on its compaction.
4. The gravel exhibit high values ofstrength when stabilized; chemicallyusing cement and mechanically using
Tensar TX 170 TriAx Geogrids. Tensar
TX 170G geogrids are used to
mechanically stabilize the base layer
thereby enhancing the durability,
longevity and versatility of the
pavement. Through the confinement of
the granular material, the geogrid will
maintain and improve the mechanical
stability of the pavement once the
pavement structure starts showing
signs of deterioration due to age and
increased passes of traffic.
5. The pavement structure is expected toexhibit increase in strength with time
as the curing process continues.
6. This pavement design reduces theoverall thickness of pavement from
400mm to 200mm in comparison to
the conventional approach and cuts on
the use of cement from 7-8%conventionally to less than 3%. This
design does not entail the excavation
and subsequent backfilling of the Black
Cotton Subgrade Soil with selected
granular Geomaterial.
7. Due mainly to the nature of thematerial and the existing naturalground, the magnitude of the bearing
capacity, strength and deformation
resistance of the existing sub-base and
subgrade supersedes to a large extent,
values specified as material
requirements for base course layers by
International Agencies and
Researchers.
8. The Cement-Geogrid stabilizedGeomaterials exhibits higher values in
terms of strength, bearing capacity and
deformation resistance as compared to
the Cement stabilized materials.
9. This Design satisfies all theengineering properties and VE aspects.
10.2 Recommendations:
From the foregoing analysis, discussions and
conclusions, the following recommendations
can be made accordingly.
1. The GI-MC technique is meant to controlmoisture levels in the subgrade. It also
incorporates Geotextile/Geofabrics which
will enhance the mobilization of the
stresses within the Black Cotton Soil
subgrade thereby improving further the
strength of the subgrade. The geofabrics
will also act as a filtration/separation
membrane and will act to stop the ingressof fines into the well graded base/sub-base
granular material.
2. The inclusion of the Geogrid is ofimportance as can be inferred from the
material analysis and conclusion.
3. From the effects of curing on the strengthcharacteristics of the cement-geogrid
stabilized Geomaterials, the proposed
pavement structure will depict increase of
strength with time.
-
8/2/2019 Isiolo Airport Executive Summary
16/16
EXECUTIVE SUMMARY
Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 16
2011KENSETSU
KAIHATSU
4. A comprehensive hydrological survey needto be done so as to analyze the effects of
drainage and runoff to the general
operation of the airport and also design
structures that will be able to control therunoff since the proposed airport is
located on a flood plain.
5. From the subgrade analysis, the accessroads in and out of the airport need to be
adequately designed to enable delivery of
material during construction.
6. It is envisaged that the above design[OPMC GI-MC Technique] will realize and
overall saving on material and
construction time of more than 40%. This
savings will come from:
a. Reduction in cement quantitiesfrom 7-8% conventionally to less
than 3%
b. No excavation and subsequentbackfilling of the subgrade Black
Cotton Soil.
c. Reduction in construction time.