isiolo airport executive summary

Upload: john-ngaya-mukabi

Post on 06-Apr-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 Isiolo Airport Executive Summary

    1/16

    Airport Pavement Design

    Report

    Engineering Report No:

    ISAT-ES 0211 02

    EXECUTIVE SUMMARY

    Kensetsu Kaihatsu LtdFebruary 2011

    Government of the Republic of Kenya

    Kenya Airports Authority [KAA]

  • 8/2/2019 Isiolo Airport Executive Summary

    2/16

  • 8/2/2019 Isiolo Airport Executive Summary

    3/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 3

    2011KENSETSU

    KAIHATSU

    EXECUTIVE SUMMARY

    ES1 Introduction

    The Kenya Airport Authority (KAA)

    commissioned Kensetsu Kaihatsu Consultants

    in the Rehabilitation and Restoration of Isiolo

    Airport Pavement Project in Isiolo County to

    carry out a design of the airport pavement

    facility using the Boeing 737-800 as the design

    aircraft with provision for future expansion.

    The existing airstrip was constructed during

    the colonial era and what is remaining is a

    dilapidated runway. The airport is part of the

    LAPSSET Corridor initiative where it will play

    a big role in connecting the Lamu Port in Lamu,Coastal Kenya to Ethiopia and South Sudan.

    The airport will be constructed in phases;

    phase one will involve the terminal buildings

    with 1.2km runway and other facilities like

    apron, taxiway. The runway will be expanded

    later under subsequent phase[s] to cater for

    lager planes.

    Actual implementation of the project started in

    July 2004 with the engagement of a local

    contractor to construct an arrival building,control tower, fire and rescue building, a

    3.3km runway, access road, car park and apron

    up to sub-base level. The government then

    requested its development partners to provide

    funding for further development.

    The Contract for the first phase of the project

    was signed in January 2011 between the

    Kenya Airport Authority and Kundan Singh

    Construction Company. The pavement worksare anticipated to take about 6 months.

    A detailed description of the Scope of Worksunder this phase of construction is given in the

    Contract Documents of the Construction ofBuildings and Pavements of Isiolo Airport.

    Plate ES1.2 Site photo showing the condition

    of the pavement

    ES.2 Background of Design Review of IsioloAirport Pavement Structure

    ES2.1 Necessity for Design Review

    Upon signing of the Contract, the Contractor, in

    accordance with Clause 8 of The FourthEdition 1987 FIDIC Conditions of Contract (ref.

    to Table 1.2.1 of the Main Report), undertook

    monitoring, technical evaluation and

    geotechnical engineering investigations in

    order to confirm, more precisely, the

    engineering properties of the existing soils as

    well as the behavior of the existing ground andpavement structure.

    The preliminary results indicate that theexisting ground and pavement structure

    exhibited much higher bearing capacity and

    strength responses in comparison to the

    values that may have been considered in the

    Original Design.

    As a consequence, the Contractor made a

    decision to embark on further and more

    detailed laboratory and in-situ experimental

    testing, technical evaluation, geotechnical

    engineering investigations and analyses.This was also in consideration of the fact that it

    is most likely the Original Design did not take

  • 8/2/2019 Isiolo Airport Executive Summary

    4/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 4

    2011KENSETSU

    KAIHATSU

    into account the pozzolanic cementetious

    nature of the existing Geomaterial and its

    immediate response to compaction and the

    effects of time related consolidation,

    thixotropy and creep (secondary

    consolidation).

    This would certainly therefore have influencedthe Original Design Concept, selection of

    materials and design of the pavement layerconfiguration.

    In view of the foregoing facts, and in

    consideration of the recent International trend

    whereby emphasis is placed on fostering and

    enhancing Value Engineering (VE) based

    approach in the design and construction of

    civil engineering structures (ref. to Sub-Clause

    13.2 quoted hereafter), the Contractor made

    the engineering judgment to undertake a

    Detail Design Review (DDR) of the IsioloAirport Pavement Structure.

    Relevant VE Sub-Clause 13.2 of The Bank

    Harmonized Edition of the Conditions of

    Contract IFCE, FIDIC

    Clause 13.2 Value Engineering

    The Contractor may, at any time, submit to the

    Engineer a written proposal which (in the

    Contractors opinion will, if adopted, (i)

    accelerate completion, (ii) reduce the cost to

    the Employer of executing, maintaining or

    operating the Works, (iii) improve theefficiency or value to the Employer of the

    completed Works, or (iv) otherwise be of

    benefit to the Employer.

    The proposal shall be prepared at the cost of the

    Contractor and shall include the items listed in

    Sub-Clause 13.3 [Variation Procedure].

    If a proposal, which is approved by the Engineer,

    includes a change in the design of part of the

    Permanent Works, then unless otherwise agreed

    by both Parties:

    (a) The Contractor shall design this part,(b) Sub-paragraphs (a) to (d) of Sub-Clause 4.1

    [Contractors General Obligations] shallapply, and

    (c) If this change results in a reduction in thecontract value of this part, the Engineer shall

    proceed in accordance with Sub-Clause 3.5

    [Determinations] to agree or determine a fee,

    which shall be included in the Contract Price.

    This fee shall be half (50%) of the difference

    between the following amounts:

    (i) Such reduction in contract value, resultingfrom the change, excluding adjustments

    under Sub-Clause 13.7 [Adjustments for

    Changes in Legislation] and Sub-Clause

    13.8 [Adjustments for Changes in Cost],and

    (ii) The reduction (if any) in the value to theEmployer of the varied works, taking

    account of any reductions in quality,

    anticipated life or operational efficiencies.

    However, if amount (i) is less than amount (ii),

    there shall not be a fee.

    Interpretation of Clause 13.2

    Value Engineering is basically the development

    and application of Advanced Technologies aimed

    at realizing cost-effective, durable, sound

    engineering and maintenance friendly structures.

    The Contractor intends to achieve this goal by

    adopting the State of the Art Technologies

    developed and widely applied in this region and

    introduced in the various sections of the Main

    Report.

    These Technologies have realized enormous time

    savings, whilst further enhancing the

    Engineering Properties by at least 150 300%.

    Specifically, this mainly culminates in the

    enhancement of the Structural Capacity,

    Serviceability Level, Bearing Capacity, Strength

    and Deformation Resistance of the Pavement

    Structure.

    ES2.2 Scope of Investigation and Main

    Objective of Study

    1.2.2 Scope of Works

    The consultants, Kensetsu Kaihatsu Limited

    were commissioned by the Client, Kenya

    Airport Authority, to undertake acomprehensive geotechnical engineering

    analysis and review of the Existing design by

    employing a Value Engineering (VE) approach

    and set up State-of-the-Art International

    Standards fostering engineering and

    scientific concepts that can be tailored and

    applicable in Isiolo, Kenya.

    The assignment included but was not limited

    to the following tasks:-

    i) Review the design using Boeing 737-800as the design aircraft.

    ii) Review comprehensively, the ExistingDesign documents.

    iii) Study the US Federal Aviation Administration (FAA) Advisory Circular

    Airport Pavement Design and

    Evaluation AC 150/5320-6D, ICAO

    Aerodrome Design Manual, Materials and

    Specifications, ICAO recommended

    practices as detailed in Annex 14 Volume

    1, and any other relevant documents.

    iv) Undertake comprehensive Site Surveysand Investigations.

    v) Carry out detailed analyses andassessment of the test data obtained fromboth in-situ and laboratory tests

    performed in Kenya.

  • 8/2/2019 Isiolo Airport Executive Summary

    5/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 5

    2011KENSETSU

    KAIHATSU

    vi) Assessment of the laboratory equipmentand capability of the same to carry out

    material acceptance and pavement

    control testing.

    vii)Carry out material investigation,sampling and testing for the proposed

    runway.viii) Perform tests on any other suitable

    material sites for aggregate sources, later

    to be utilized civil works.

    ix) Carry out geo-material improvement,mechanical, & chemical stabilization and

    testing for any non-compliance materials

    and/or for purposes of enhancing the

    engineering properties of the compliant

    materials.

    x) Build capacity in terms of trainingmanpower, and laboratory Technicians

    on test methods and quality control.

    ES2.2.2 Isiolo Airport Project and

    Surrounding Areas

    Fig. 1.1 shows the surrounding districts of

    Isiolo district

    Fig. ES1.1 Lay Out of Isiolo

    Fig. 1.2 Satellite Image of Isiolo Airport

    ES2.3 Geophysical Details of Isiolo Airport inIsiolo within Isiolo Region of Kenya

    The site for the Isiolo Airport located in Isiolo,

    Kenya, and its geographical coordinates are

    020'17" North and 3735'28" East and its

    original name (with diacritics) is Isiolo.

    Airports in Isiolo and in the neighbourhood:

    Garbatula Airport (distanced

    approximately 105.7 km)

    Garissa Airport (distanced approximately

    247 km)

    Hola Airport (distanced approximately

    341 km)

    Marsabit Airport (distanced

    approximately 225 km)

    Wajir Airport (distanced approximately

    317 km)

    Bura Airport (distanced approximately

    308 km)ES2.4 Relevant Documents and Records

    Reference is made mainly to the following

    documents and records.

    1. United States Federal AviationAdministration (US FAA) Advisory Circular

    No. 150/5320-6D

    2. International Civil Aviation Organization(ICAO) Annex 14 Volume I AerodromeDesign and Operations

    3. Aerodrome Design Manual, Part 34. Boeing 747-100 Guide to Aerodrome

    Design and Technical Data

    5. The Civil Aviation (Aerodromes)Regulations, 2007

    6. AASHTO Guide to Pavement Design7. Transport Research Laboratory (TRL)

    Overseas Road Note 31, Berkshire, UnitedKingdom

    8. Japan Road Association Pavement DesignManual

    9. Kenya Roads Design Manuals10.Materials Report and Test Results11.Reconstruction of Airport Pavements at

    Isiolo Airport

    ES2.5 Brief Background of Project Area

    The Study including GeotechnicalInvestigation was carried out for Isiolo Airport

    and the site photos are depicted in Plate 1.3

    ISIOLO

    GARISA

    MERU

    MARSABIT

  • 8/2/2019 Isiolo Airport Executive Summary

    6/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 6

    2011KENSETSU

    KAIHATSU

    Plate ES1.3 - Photos Superimposed on

    Satellite Imagery showing the Airport

    Figure ES1.4 Location map of Isiolo Airport

    Kenya is located in Eastern Africa between

    longitude 340 and 420 East, Latitude 50 North

    and 50 South.

    Kenya is the second largest of the East Africa

    countries (i.e. Kenya, Uganda, Rwanda,Burundi and Kenya), has a spectacular

    landscape of mainly three physiographic

    regions namely the coastal plains to the east;the inland plateau; and the highlands. The

    Great Rift Valley that runs from north east of

    Africa through North western and southwestern Kenya down to Kenya is another

    landmark that adds to the scenic view of the

    country. The valley is dotted with unique lakes

    which include Lakes Turkana, Baringo,

    Bogoria, Naivasha, Nakuru, Elementaita, Logipi

    and Magadi.

    ES3 Determination of PavementStructural Design

    Determination of Total Pavement Thickness

    Required

    Subsequent to determining the Mean-sectionDesign CBR values for the subgrade and the

    sub-base (ref. to table 3.1), the weight on the

    main landing gear was determined from Fig.

    7.2.4 in Chapter 7 of the Main Report. Having

    pre-determined the design aircraft and the

    number of annual departures of the design

    aircraft, the design curves in Fig. 7.2.5

    presented in Chapter 7, based on the U.S. ArmyCorps of Engineers Design Method S-77-1 and

    the U.S. FAA Design method, the totalpavement thickness required was derived.

    ES3.2 Thickness of Sub-base

    Refer to Section ES7.1.1 of this Executive

    Summary.

    ES3.3 Thickness of Surface Course

    Refer to Section ES7.1.2 of this Executive

    Summary.

    ES3.4 Thickness of Base Course

    Refer to Section ES7.1.3 of this Executive

    Summary.

    ES3.5 Thickness of Non-Critical Areas

    Refer to Section ES7.1.4 of this Executive

    Summary.

    ES3.6 Typical Cross-section

    Refer to Section ES7.1.5 of this Executive

    Summary.

    ES4.4 Construction Time Comparative

    Analysis

    Refer to Section ES7.2.4 of this Executive

    Summary.

    ES5 Materials Characterization and

    Analysis of Test Results

    ES5.1 Basic Physical and Mechanical

    Parameters

    Table ES5.1.1 shows the typical basic physical,mechanical and bearing capacity properties of

    existing BCS soils within the Isiolo Airport

    Project Area.

    Table ES5.1.1 Typical Pre-treatment/Pre-

    consolidation Material Test Results

    1

    2

    3

    4

    5

    6

    7

    8

    9

    # TESTED PARAMETERSTEST VALUE

    REMARKS

    Computed UCS (Mpa)

    CBR@100%MDD - Soak

    MDD - Kg per Cubic meter

    OMC

    Atterberg - LL

    0.05

    2.00

    1,129.00

    34.50

    120.00

    The subgrade soil has a lot of fines

    CBR@100%MDD - Unsoaked 17.00

    Atterberg - PI

    Atterberg - LS

    53.0067.00

    23.00

    Atterberg - PL

  • 8/2/2019 Isiolo Airport Executive Summary

    7/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 7

    2011KENSETSU

    KAIHATSU

    ES5.2 Correlation between Physical,

    Mechanical and Strength parameters

    The typical pre-treatment (pre-

    stabilization)/pre-consolidation basic physical,

    mechanical and bearing capacity for material

    tested from the sub-base material at BP3 Ruiri.

    ES 5.3 Development of test regimes

    To attain Optimum and a value engineered

    design, several Test Regimes were developedto help us achieve the optimum designs. It

    involves the comparison of various designs

    options and modeling the different structuresin the Lab.

    Table ES5.2.1 Summary of Stabilization

    Test Results

    A. Neat Material

    B. OBRM SUBBASE MATERIAL

    C. OPMC SUBBASE MATERIAL

    D. SUMMARY OF THE TEST RESULTS-

    COMPARATIVE ANALYSIS

    E. SUMMARY AND COMPARISON OF

    GRANULAR SUB-BASE MATERIAL FOUND IN

    THE VICINITY

    From the tables above the following can beinferred:

    The gravel at BP3 is of good sub-base quality.

    It has natural intrinsic cementetious

    behaviour. This makes it posses high

    engineering properties in comparison to

    other materials within the location [see table

    above].

    The grading of BP3 is satisfactory but we will

    be required to add 20% Quarry Dust to

    improve on the densities.

    Neat 1 1 1 1 1 1 1

    1 1 1 1 1 1 2

    1 1 1 1 1 1 21 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 2

    1 1 1 1 1 1 4

    Granular Material-

    Gravel

    Stabilization

    RateM ode of c uring M DD O MC

    1d c/s

    PL LL PI GRADING

    1d/c

    UCS

    3d/c7d/c

    1d/c

    1d c/s

    3d c/s

    3d/c

    7d/c

    3d c/s

    1d/c

    3d c/s

    1d/c

    3d/c

    7d/c

    1d c/s

    3d c/s

    BP3

    3d/c

    7d/c

    1d c/s

    3d c/s

    1%

    2%

    3%

    4%

    6%

    1d/c

    3d/c

    7d/c

    1d c/s

    REMARKS

    BP3-NEAT SUBBASE BASE

    1 1.23

    2 52.00 Not

  • 8/2/2019 Isiolo Airport Executive Summary

    8/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 8

    2011KENSETSU

    KAIHATSU

    The strength properties, densities and

    particle of the neat BP3 material is

    enhanced by the inclusion of the 20%

    quarry dust and 2% cement.

    The cement used is Bamburi PowerPlus. It

    is reported that PowerPlus type of cementgains strength immediate/sporadically

    after stabilization and after about 28 days

    the strength normalizes; PowerMax gains

    strength with time and its expected to

    yield maximum strength after 28 days.

    Laboratory tests and monitoring are

    ongoing to confirm this.

    The OPMC batched material evidently

    shows improved properties. We have an

    increase of more than 150% in strengthsafter 3 day cure. Further tests are still on-going to ascertain the behaviour with time

    and at different conditions as described in

    5.2

    From the 1 day cure results we can

    tentatively decide that our design will be

    BP3+20% Quarry Dust + Tensar TX170Geogrids + 2% cement is the optimum

    design

    ES5.3 Dynamic Cone Penetration Test ResultsThe ground and Geomaterials characteristics

    under dynamic loading as simulated by the

    Dynamic Cone Penetration determined in this

    Study, are summarized in the Tables below,

    while their behavior is graphically

    characterized in the corresponding Figures.

    The fact that the existing pavement is very

    sound can be derived from the very highbearing capacity and strength magnitudes that

    it exhibits.

    Series 5.4.1 Tables and Figures for DynamicCone Penetration Results for Isiolo Airport

    The following derivations can further be made

    from these tables and figures.

    1. Most of the locations on thecarriageway of the existing

    pavement structure exhibit high

    bearing strengths under

    conditions tested with averages of

    CBR 62%.

    2. The average CBR mean results isabout 62% for dry in situ

    conditions while the soaked

    conditions gives average CBR

    mean of less than 5%. From the

    two CBR figures, it is prudent that

    the subgrade/foundation Design

    considers options for moisture

    control in its design. We are

    proposing the GI-MC method for

    the design and construction of the

    improved subgrade. This because

    when the foundation is dry i.e.

    when moisture is controlled, the

    in-situ strengths are very high

    compared when it is partially orcompletely soaked.

    3. The Subgrade BCS soil has PIvalues of 67%. This indicates a

    very high value of fines and clay

    minerals in its composition. The

    design needs to cater on how to

    prevent the contamination of the

    Base/sub-base layers through

    infiltration/ingress of fines into

    the upper pavement layers

    [base/sub-base]. The presence of

    fines into these layers will be very

  • 8/2/2019 Isiolo Airport Executive Summary

    9/16

  • 8/2/2019 Isiolo Airport Executive Summary

    10/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 10

    2011KENSETSU

    KAIHATSU

    Laboratory UCS Tests of Cement Stabilized

    [Chemical stabilization]

    Table ES5.7.1(b) Summary of Consolidation

    Stress Parameters Derived from

    Laboratory UCS test of Cement- Geogrid

    Stabilized OPMC-[Chemical - Mechanical

    stabilization]

    ES5.8 Shearing Strength Test Results

    The shearing strength parameters aresummarized in Tables ES5.2.1 Series present

    the UCS laboratory test results for specimens

    tested at 1%, 2% and 3% cement treatmentlevels, while the graphical characteristics of

    the loading to failure are shown in the

    corresponding figures. Table ES5.8.1 is asummary of these results in comparison with

    values that are computed adopting empirical

    equations defined in Chapter 4 of the Main

    Report.

    On the other hand, a summary of the shear

    parameters derived from in-situ tests is given

    in Table ES5.2.3.

    This Table presents the results computed by

    adopting Eqns. 4.18 in sub-section 4.3.1 and4.33 ~ 4.38 in sub-section 4.5.1 of Chapter 4 of

    the Main Report.

    The derivations from these results are briefly

    presented after Table ES5.8.2.

    Table ES5.8.2 Summary of Shear Stress

    Parameters Derived from In-situ Tests

    The following observations can be made from

    the foregoing Tables ES5.8.1 ~ 5.8.2 and the

    corresponding Figures.

    The laboratory test results indicate enhanced

    intrinsic shearing properties of the pozzolanic

    material even at very low cement treatment

    ratios (ref. to results of 1% additive tocomparative parameters presented in Chapter7 from various International Agencies).

    1) The in-situ test results show that theshearing strength is immensely enhanced

    as a result of the coupled effects of long

    term consolidation and cementetious

    agglomeration.

    2) From Table ES5.8.1, it can be observed thatthere is a very good agreement between

    the tested and computed values. Thisconfirms the precision of the test results

    accordingly.

    3) On the average, the in-situ values arehigher that the laboratory test results

    {UCSlab = 7.75 MPa compared to UCSin-situ =

    8.95 MPa(average)}.

    However, as can be observed from the results

    summarized in Tables ES5.5.1 in the preceding

    section ES5.5, the results tend to be very

    similar when corrected for the effects of Long

    Term Consolidation by applying the following

    equation.

    STCn

    STC

    STCSTCLTC

    CSRAttK

    qKq

    '/100

    max0

    max

    Where,

    Superscript LTC and STC denote long term and

    short term consolidation respectively whereas t

    : LTC time and to : STC time., for OC conditions

    ( a/ t)fcSTC=1.

    MIX

    Sample (MPa) (MPa) (MPa) (MPa) ( MP a) ( MP a)

    1 P o zz o lan ic 0 .6 6 0. 33 1. 06 4 8. 06 0 1. 291 1 5. 787 0 .3 28 1 .01 0 0 .93 8 0. 42 3 0. 38 0 1 .31 0. 26 1. 06 1. 48

    3 P ow er Ma x 0 .6 0. 30 0. 96 4 7. 95 2 1. 290 1 5. 770 0 .3 29 1 .01 1 0 .93 6 0. 42 4 0. 38 1 1 .19 0. 23 0. 96 1. 35

    4 P o wer Pl u s 0 .9 6 0. 48 1. 54 4 8. 60 2 1. 295 1 5. 875 0 .3 27 1 .00 8 0 .94 9 0. 41 9 0. 37 9 1 .90 0. 37 1. 54 2. 15

    Notethatthe cementcontectis 3% andthe curingmode3days soak

    qC pC

    SerialNo. UCSqu (MPa)Cu

    CSR

    maxq

    CSR CSR/1

    CSR OK

    CK

    1

    ac

    1

    rc

    MIX

    Sample (MPa) (MPa) (MPa) (MPa) ( MP a) ( M

    1 Pozzolanic 0 .792 0.40 1.27 48.2 99 1.2 92 15.8 26 0.3 28 1.0 10 0.94 3 0.42 1 0.3 80 1.5 7 0.3 1 1.2 7

    0 P o we rM ax 0 . 9 62 0.48 1.54 48.6 06 1.2 95 15.8 76 0.3 27 1.0 08 0.94 9 0.41 9 0.3 79 1.9 1 0.3 7 1.5 4

    4 P o we rP l us 1 .1 48 0.57 1.84 48.9 42 1.2 97 15.9 31 0.3 26 1.0 07 0.95 6 0.41 6 0.3 77 2.2 7 0.4 4 1.8 4

    Notethatthe cementcontectis 3% andthe curingmode3days soak

    pqCSerialNo. UCS qu (MPa)

    CuCSR

    CSR CSR/1

    CSR OK

    CK1

    ac

    1

    rc

  • 8/2/2019 Isiolo Airport Executive Summary

    11/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 11

    2011KENSETSU

    KAIHATSU

    ES5.9 Modulus of Deformation, Elastic

    Modulus and Linear Elastic Range

    A summary of the derived modulus of

    deformation, elastic and shear modulus and

    elastic limit strain, which is defined as the

    range of linear elastic and recoverablebehavior, given in Tables ES5.9.1 and 5.9.2,

    were computed by applying Equations 4.48 ~

    4.52 of the Main Report.

    The normalized relations are also presented in

    the same Tables.

    Table 5.9.1 Summary of Modulus ofDeformation Parameters from Lab Test

    Results

    Table ES5.9.2 Summary of Modulus of

    Deformation Parameters - In-situ Test

    Results

    The results of deformation properties and the

    linear elastic range are presented in Table

    5.10.1 below.

    The results basically indicate that as the

    shearing strength increases with the

    deformation resistance, the linear elastic rangeis immensely enhanced.

    ES5.10 Deformation Properties and Linear

    Elastic Range

    The results of deformation properties and the

    linear elastic range are presented in Table

    5.10.1 below.

    The results basically indicate that as the

    shearing strength increases with the

    deformation resistance, the linear elastic rangeis immensely enhanced.

    Table ES5.10.1 Summary of Modulus of

    Deformation Parameters - in-situ Test

    Results

    ES5.11 Summary of the effects of curing

    period on soil particle agglomeration and

    unconfined strength.

    From the laboratory test results OPMC

    Stabilized + Geogrid samples yields UCS values

    of 3.32 after 3day cure with 2% cement

    content [PowerPlus]. After extrapolation from

    the relation that is explained in chapter 4, the

    following table gives the expected calculated

    properties after several days of curing.

    Table ES5.11.1 Table: Effects of curing

    period on OPMC Level 3

    Table 5.11.2 Effects of curing period on

    Resulting, ER Composite Pavement

    7. PAVEMENT STRUCTURAL DESIGN

    7.1 Scope

    1 BCS subgrade 12 1 07 4 35 7. 85 5 .2 3 0 .3 8 0 .1 02 78 2 0. 16 98 85 1 37 13

    2 BP1 LMD gravel 347 3 83 4 1 27 8. 04 4 1. 76 0 .6 3 0 .2 50 79 4 0 .3 98 41 0 1 71 8

    3 BP2 78 Tank Batt 389 4 00 7 1 33 5. 55 4 4. 87 0 .6 7 0 .2 69 63 2 0 .4 26 03 3 1 59 9

    5 BP5 Murero 173 2 94 6 98 2. 10 2 7. 17 0 .5 0 0 .1 74 09 7 0. 28 22 99 2 64 1

    6 BP6 LMD Sandy 49 1 81 8 60 6. 02 1 2. 36 0 .4 1 0 .1 18 92 9 0. 19 55 80 5 80 6

    Specimen

    MIXE50

    (MPa)

    Emax

    (MPa)

    Gmax

    (MPa)ELS

    (a)max

    (calculated)

    (%)

    (a)50

    (calculated) (%)

    (a)ELS

    (10-3) (%)

    Emax /

    qmax

    Effects of curing period on OPMC Level 3 & Geogrid, PowerPlus 2% for 3 days Cure/soa

    1 24 2.28 4,621.72 95.00

    3 72 3.31 5,327.08 138.06

    7 168 5.51 6,463.93 229.68

    14 336 11.09 8,431.71 462.23

    28 672 26.11 11,673.06 1,087.98

    56 1344 66.30 16,632.49 2,762.40

    112 2688 173.09 23,951.49 7,212.12

    Curing Periods,

    CP[hours]UCS, qu

    f[Mpa]Days Emax CBR [%]

    Effects of curing period on Resulting Er (composite pavement)

    UCS, QurFCB

    1 24 2.11 0.80 1,414.00 1,317.00 87.92

    3 72 3.76 1.64 5,589.87 4,073.88 156.71

    7 168 5.77 1.89 6,576.69 4,305.93 240.38

    14 336 8.23 2.10 7,527.62 4,481.61 342.95

    28 672 11.44 2.31 8,530.34 4,646.73 476.60

    56 1344 15.59 2.52 9,595.18 4,802.78 649.52

    112 2688 20.93 2.73 10,731.70 4,950.97 872.02

    224 5376 27.77 2.94 11,949.16 5,092.26 1,157.02

    448 10752 36.50 3.15 13,256.83 5,227.42 1,520.65

    896 21504 47.59 3.36 14,664.18 5,357.11 1,983.08

    1792 43008 61.67 3.57 16,181.03 5,481.88 2,569.43

    Days Curing Periods,

    CP[hours]UCS, qur

    FCA[Mpa] EmaxER

    CACBR [%]EmaxER

  • 8/2/2019 Isiolo Airport Executive Summary

    12/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 12

    2011KENSETSU

    KAIHATSU

    This chapter reviews the EXISTING pavement

    design, determines the design based on the US

    FAA/ ICAO method of Design, analyzes various

    options and recommends the VE based design

    for the Isiolo Airport aimed at serving aircraft

    with gross weights of up to 79,016kgs for

    B737-800 series.

    The design review is limited to the Airport

    Pavement and does not include geometric

    design or design for any other of the airportfacilities.

    7.2 Fundamental Design Philosophy

    The design largely adopts the

    recommendations made through the Advisory

    Circular (AC) No. 150/5320-6D dated April

    30th

    , 2004, Airport Pavement Design andEvaluation.

    Reference is also made to the 737 Airplane

    Characteristics Airport Planning D6-58325-6published in May 1984 by Commercial

    Airplane Company, which is a Division of the

    Boeing Company.

    The Design Philosophy is based on the United

    States Federal Aviation Administration (FAA)

    and the International Civil Aviation

    Organization (ICAO) recommended practices.

    Table 7.2.1 Summary of Major Design

    Considerations

    Table 7.2.2 Technical Specifications for

    Boeing Aircraft detailing the B737-800

    Fig. 7.4 Landing Gear Loading on Pavement

    - Model 737-800 Aircraft

  • 8/2/2019 Isiolo Airport Executive Summary

    13/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 13

    2011KENSETSU

    KAIHATSU

    Fig. 7.5: Pavement Thickness Design as per

    the Conventional Design.

    Fig. 7.6: Pavement Thickness Design using

    the OPMC GI-MC Technique;

    Table 7.7.1 Summary of Main Design

    Parameters Adopted

    Based on the data presented in Table 7.5, the

    Total Pavement Thickness required

    conventionally is 16 inches or 400mm

    Based on the data presented in Table 7.6, the

    Total Pavement Thickness required using

    OPMC technique in this design is 200mm.

    7.7.6 Typical Cross-section A

    Table 7.8.1 Summary of the structural

    capacity, deformation resistance of thecomposite pavement

    The Table above shows the results of the

    individual layers and the composite pavementsafter one day cure. The strength as explained

    and inferred in Chapter 5 will increase with

    time.

    The summaries from table 7.8.1 above shows

    that our proposed pavement structure is

    adequate to perform as a runway that will

    handle Boeing 737-800 aircraft with annual

    departures of 3000 flights for 20 years.

    Cross-

    section A

    Cross-

    section B

    TA TA qu,A[Mpa] qu,B[Mpa]

    T 1 A sp ha lt co nc re te ACWearing/Binding

    Course 1 7 7 4.50 4.50 4,419.00 4,419.00

    T2 OPMC Level 3

    Subbase

    Geomaterial +

    Geogrid 0.62 20 20 3.32 3.32 5,331.15 5,331.15

    T3

    BCS

    Ground

    Improvement

    Subgrade 0.35 20 40 1.38 1.38 2,179.02 2,179.02

    where:

    ERCA

    - resultant ER for cross section A

    ERCB

    - resultant ER for cross section B

    492.32

    1414

    1317100

    1.46

    65.13

    Composite

    pavementERCB

    T1+T2+T3+

    T4

    0.94

    0.05

    Composite

    pavementER

    CA100

    0.83T4Existing Black

    Cotton SoilSubgrade 0.05 53 33

    S/No Description Pavement LayerOPMC/GG

    CoefficientE

    Bmax[Mpa]

    qu[Mpa]E

    Amax[Mpa]

    Determin

    ation of

    Thickness

    for This

  • 8/2/2019 Isiolo Airport Executive Summary

    14/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 14

    2011KENSETSU

    KAIHATSU

    Conclusion:

    The design used in this project realizes a

    reduction of the overall thickness of about

    125mm as compared to the conventional

    designs.

    CHAPTER 9

    9. METHOD OF CONSTRUCTION

    General Method of Construction:

    9.1 Procedure for Construction of Ground

    Improved Subgrade

    9.2 Procedure for Construction of Sub-

    Base/Base Course

    9.3 Procedure for Construction of Asphalt

    Concrete Wearing Course

    10 Conclusions and Recommendations

    10.1 Conclusions

    Based on the derivations noted in this Report,

    the following main conclusions can be made.

    1. The subgrade CBR is high when thesubgrade condition is Unsoaked and

    the CBR values drops tremendouslywhen the subgrade is wet. The

  • 8/2/2019 Isiolo Airport Executive Summary

    15/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 15

    2011KENSETSU

    KAIHATSU

    subgrade soil, predominantly Black

    Cotton Soil [BCS] have very high

    amount of fines [PI of 62%]. The

    intrusion of the fines into the well

    graded base/sub-base material should

    be stopped since the presence of fineswill result to the increase of the

    capillary action of the layer making the

    base vulnerable to moisture. The

    presence of fines will therefore lead to

    the drop in strength of the pavement

    structure.

    2. The subgrade is improved using theGround Improvement Moisture

    Control Technique where sand

    piles/columns are used to control

    moisture.

    3. The gravel materials from borrow pitswithin the vicinity of the Project Area

    are suitable for the construction of the

    Base Course pavement layer. The

    existing gravel material is porous and

    has relatively low densities. We have

    batched the gravel with 0.6mm quarry

    dust to improve on its compaction.

    4. The gravel exhibit high values ofstrength when stabilized; chemicallyusing cement and mechanically using

    Tensar TX 170 TriAx Geogrids. Tensar

    TX 170G geogrids are used to

    mechanically stabilize the base layer

    thereby enhancing the durability,

    longevity and versatility of the

    pavement. Through the confinement of

    the granular material, the geogrid will

    maintain and improve the mechanical

    stability of the pavement once the

    pavement structure starts showing

    signs of deterioration due to age and

    increased passes of traffic.

    5. The pavement structure is expected toexhibit increase in strength with time

    as the curing process continues.

    6. This pavement design reduces theoverall thickness of pavement from

    400mm to 200mm in comparison to

    the conventional approach and cuts on

    the use of cement from 7-8%conventionally to less than 3%. This

    design does not entail the excavation

    and subsequent backfilling of the Black

    Cotton Subgrade Soil with selected

    granular Geomaterial.

    7. Due mainly to the nature of thematerial and the existing naturalground, the magnitude of the bearing

    capacity, strength and deformation

    resistance of the existing sub-base and

    subgrade supersedes to a large extent,

    values specified as material

    requirements for base course layers by

    International Agencies and

    Researchers.

    8. The Cement-Geogrid stabilizedGeomaterials exhibits higher values in

    terms of strength, bearing capacity and

    deformation resistance as compared to

    the Cement stabilized materials.

    9. This Design satisfies all theengineering properties and VE aspects.

    10.2 Recommendations:

    From the foregoing analysis, discussions and

    conclusions, the following recommendations

    can be made accordingly.

    1. The GI-MC technique is meant to controlmoisture levels in the subgrade. It also

    incorporates Geotextile/Geofabrics which

    will enhance the mobilization of the

    stresses within the Black Cotton Soil

    subgrade thereby improving further the

    strength of the subgrade. The geofabrics

    will also act as a filtration/separation

    membrane and will act to stop the ingressof fines into the well graded base/sub-base

    granular material.

    2. The inclusion of the Geogrid is ofimportance as can be inferred from the

    material analysis and conclusion.

    3. From the effects of curing on the strengthcharacteristics of the cement-geogrid

    stabilized Geomaterials, the proposed

    pavement structure will depict increase of

    strength with time.

  • 8/2/2019 Isiolo Airport Executive Summary

    16/16

    EXECUTIVE SUMMARY

    Isiolo Airport Pavement Design Engineering Report No: ISAT 0211/01 Page 16

    2011KENSETSU

    KAIHATSU

    4. A comprehensive hydrological survey needto be done so as to analyze the effects of

    drainage and runoff to the general

    operation of the airport and also design

    structures that will be able to control therunoff since the proposed airport is

    located on a flood plain.

    5. From the subgrade analysis, the accessroads in and out of the airport need to be

    adequately designed to enable delivery of

    material during construction.

    6. It is envisaged that the above design[OPMC GI-MC Technique] will realize and

    overall saving on material and

    construction time of more than 40%. This

    savings will come from:

    a. Reduction in cement quantitiesfrom 7-8% conventionally to less

    than 3%

    b. No excavation and subsequentbackfilling of the subgrade Black

    Cotton Soil.

    c. Reduction in construction time.