ISACASystems Implementation Assurance – Lessons Learned
February 2009
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Agenda – Lessons Learned
1. Project Phase 1- Planning / Mobilization
2. Project Phase 2 – Design / Blueprint
3. Project Phase 3 – Realization / Build & Test
4. Project Phase 4 - Pre Go-live / Deliver Phase
5. Project Phase 5 - Post Go-live / Maintenance Phase
6. Example Project Discussion Document
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 1- Planning/Mobilization
Careful planning, particularly in the early stages of a project, is necessary to coordinate activities and manage project risks effectively. The depth and formality of project plans should be commensurate with the characteristics and risks of a given project.
Outline Project Plan
Define Roles and Responsibilities
Define Project Communication and Reporting Requirements
Define Deliverables and Expectations – Involvement of all Key Players
Outline Risk Acceptance - Manage Internal and External Risks
Define Project oversight activities – Definition of Standards
Define Tollgates and Requirements
Define Budget and estimated Project Costs
Define Project Change Procedures
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 1 Planning/ Mobilization – Lessons Learned
Putting a proper project governance structure in place with sufficient "checks and balances".
Proper Executive and Senior Management buy-in and involvement in project and milestones reached
Projects are often comprised of international teams and must consider both cultural issues and compliance with local laws and regulations
Broader industry and business issues must be taken into consideration
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 1 Planning/Mobilization – Lessons Learned cont.
Underlying Data Model Consideration (e.g. US GAAP versus
IFRS)
Downstream impact on support functions such as internal audit and security administration
Additional Considerations to be aware of during the planning stage:
41% of projects fail to meet management’s objectives
Only 28% of project fulfill management's expectations
Only 16% of IT projects hit all their targets
50% of projects end up late or over budget
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Planning/Mobilization – Lessons Learned cont.
Reasons for project failure in the planning stage: Bad estimates
Scope changes
Change in environment
Insufficient resources
Change in strategy
Imprecise goals/ Insufficient budget
Poor communication
Insufficient support
Wrong project management
Insufficient motivation
Stakeholders not adequately defined
Poor quality of deliverables
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Project Phase 2 - Design/Blueprint
The design phase involves converting the informational, functional, and network requirements identified during the initiation and planning phases into unified design specifications that developers use to script programs during the development phase
Application Control Standards
Designing appropriate security, audit, and automated controls
Standards should be in place to ensure end users, network administrators, auditors, and security personnel are appropriately involved during initial project phases.
Application control standards enhance the security, integrity, and reliability of automated systems by ensuring input, processed, and output information is authorized, accurate, complete, and secure.
Automated input controls help ensure employees accurately input information, systems properly record input, and systems either reject, or accept and record, input errors for later review and correction (e.g. Check Digits, Completeness Checks, Duplication Checks, Validity Checks, Reasonableness Checks, etc.)
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Project Phase 2 - Design/Blueprint cont.
Processing Controls - Automated processing controls help ensure systems accurately process and record information and either reject, or process and record, errors for later review and correction.
• Batch Controls
• Error Reporting
• Transaction Logs
• Run-to Run Totals
• Sequence Checks
Output Controls - Automated output controls help ensure systems securely maintain and properly distribute processed information
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 2 Design/Blueprint – Lessons Learned
Avoid excessive customization - companies desire to "re-invent the wheel"
Many key controls are application driven (e.g. controls which depend on system generated reports, configuration settings such as for the three-way match in the procurement cycle)
Effective process to prioritize all the business "wish-lists”
Decision Making from “Middle Management” – Timely Decisions
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Project Phase 3 - Realization/Build & Test
Development
Development standards should be in place to address the responsibilities of application and system programmers. Application programmers are responsible for developing and maintaining end-user application.
Library Controls - Libraries are collections of stored documentation, programs, and data. Program libraries include reusable program routines or modules stored in source or object code formats.
Automated Password Controls – Management should establish logical access controls for all libraries or objects within libraries
Automated Library Applications – When feasible, management should implement automated library programs, which are available from equipment manufacturers and software vendors
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Project Phase 3 - Realization/Build & Test – cont.
Version Controls
Software Documentation
System Descriptions – System descriptions provide narrative explanations of operating environments and the interrelated input, processing, and output functions of integrated application systems
System Documentation – System documentation includes system flowcharts and models that identify the source and type of input information, processing and control actions (automated and manual), and the nature and location of output information.
System File Layouts – System file layouts describe collections of related records generated by individual processing applications
Naming Convention - critical part of program documentation
End-User Instructions – Organizations should establish end-user instructions that describe how to use an application.
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Project Phase 3 - Realization/Build & Test
Build & Test
The testing phase requires organizations to complete various tests to ensure the accuracy of programmed code, the inclusion of expected functionality, and the interoperability of applications and other network components. Thorough testing is critical to ensuring systems meet organizational and end-user requirements.
Acceptance Testing – to assess the overall functionality and interoperability of an application
End-to-End Testing - to assess the interoperability of an application and other system components such as databases, hardware, software, or communication devices
Functional Testing - to assess the operability of a program against predefined requirements
Integration Testing - to assess the interfaces of integrated software components
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Project Phase 3 - Realization/Build & Test – cont.
Parallel Testing - to compare the output of a new application against a similar, often the original, application
Regression Testing - to assess functionality after programmers make code changes to previously tested applications
Stress Testing - to assess the maximum limits of an application
String Testing - to assess the functionality of related code modules
System Testing - to assess the functionality of an entire system
Unit Testing - to assess the functionality of small modules of code
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 3 Realization/Build & Test – Lessons Learned
Project streams reporting 99% completion of tasks which, if subject to deeper analysis, does not hold water
Incomplete testing which can have a devastating post go-live impact when "too lightly" tested configurations fail and disrupt the business
Data conversion is a task which many times are under-estimated
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Project Phase 4 - Pre Go-live/Deliver Phase
The implementation phase involves installing approved applications into production environments.
Primary tasks include…
announcing the implementation schedule,
training end users, and
installing the product.
Additionally, organizations should…
input and verify data,
configure and test system and security parameters
Management should circulate implementation schedules to all affected parties and should notify users of any implementation responsibilities.
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 4 Pre Go-live/Deliver Phase – Lessons Learned
Training is a key area where projects tend to cut corners:
Insufficient training can be disastrous for the morale of users, acceptance of the new application and company productivity which can seriously hamper the pre-go-live promises of more efficient post go-live environment.
Strong personalities, ego's, compensation structures and a mentality of "nothing will stop us from going live on x-date" can mean that pre-determined exit factors for the deliver phase such as successfully completed testing and completed cut-over activities can be compromised
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Project Phase 5 - Post Go-live/ Maintenance Phase
Management should…
conduct post-implementation reviews at the end of a project to validate the completion of project objectives and assess project management activities.
interview all personnel actively involved in the operational use of a product and document and address any identified problems.
analyze the effectiveness of project management activities by comparing, among other things, planned and actual costs, benefits, and development times.
document the results and present them to senior management.
The maintenance phase involves…
making changes to hardware, software, and documentation to support its operational effectiveness.
making changes to improve a system’s performance, correct problems, enhance security, or address user requirements.
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 5 Post Go-live/Maintenance Phase – Lessons Learned
PwC was able to categorize post go-live issues in the following 35 buckets, sorted by number of incidents, highest number first:
Locked user/UID validity date required resetting
Abend related issues
Report generation
Authentication
Batch processing/upload issues
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 5 Post Go-live/Maintenance Phase – Lessons Learned cont.
Interface processing issues
Transaction Processing issues - mostly FI, FI-AP, SD
PO/EBP GR IR Processing issues
Access - General
SAP Mail/Inbox/Workflow Issues
Process Chain Issues
Authorization Issue
Shopping Cart PTP
Master Data issue
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 5 Post Go-live/Maintenance Phase – Lessons Learned cont.
HR Transaction Processing Issue
Non - PROD access issue - to DEV,QA etc
ABAP Error
Miscellaneous
BW/BI/Related Reports Issues
Cannot access ESS
Missing Data/Unable to display issues
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 5 Post Go-live/Maintenance Phase – Lessons Learned cont.
Backup Issues
Project Systems/WBS Issue
Data Entry / Update / Delete Request
Runtime Error
User error/Training Issue
Extracting/Downloading Data from SAP
SAP GUI Access Issues
Financial Period End Consolidation
Systems Implementation Assurance – Lessons LearnedPricewaterhouseCoopers
Phase 5 Post Go-live/Maintenance Phase – Lessons Learned cont.
File error/File copy requests
Network Issue
Foreign language/Unicode
MSS Data Display Issues
Transport request / issues
Operating System Issue
Draft
SDLC Selection Framework • IT Process Maturity
Independent Project AssuranceFebruary 2009
Draft
SDLC Selection Framework • IT Process Maturity
Realize the tangible and intangible business benefits outlined in the business case with the priority to increase customer satisfaction with billing and an enhanced ability to efficiently and effectively launch new products and services in the future.
Deliver the project on time, within budget, with agreed critical functionality for the business as quickly as possible.
Leverage standard SAP business process design and core infrastructure to reduce risk and cost.
Provide a standard platform to allow for ease of integration and reporting.
Deliver a compliant system that addresses key stakeholder requirements, including financial and regulatory reporting requirements.
The company is making a significant investment to implement a single pricing, billing, invoicing, accounts receivable and cash management and collection system, utilizing SAP as the core technology. With Business Blueprint of Phase II of Project SAP complete, Executive Management would like to gain the appropriate assurance that the project achieves it’s stated objectives:
Understanding Your Objectives
Draft
SDLC Selection Framework • IT Process Maturity
Issue Possible Area of Assurance
Data Quality
• Billing data quality and accuracy
• Customer master conversion/migration
• Customer rate accuracy
• Interfacing of information to legacy systems
• Review controls around data cleansing and conversion for billing and customer master data.
• Share independent perspective on data conversion activities and provide recommendations throughout the process.
• Assess key interfaces identified and controls supporting completeness, accuracy, validity, and restricted access risks.
Customer First Focus
• Invoice Presentation Quality and Accuracy
• Shipment Rating Timeframe
• Review controls and system configurations associated with invoice generation and shipment rating and provide recommendations related to validity, completeness, accuracy, efficiency, and evidence of duplication.
• Share independent perspective on good practices associated with revenue cycle and billing/invoicing.
Financial Reporting
• Inaccurate Bad Debt Provision Calculation
• Excessive Unapplied Cash Balance
• Current system Upgrade
• Share other client experiences regarding security, internal control and risk management associated with SAP upgrade to ECC 6.0.
• Provide independent perspective on technical strategy for cash application.
• Assess process to define key financial and management reporting requirements and assess the effectiveness of the reporting designed to meet these requirements.
Issues on Your Mind
Draft
SDLC Selection Framework • IT Process Maturity
• Ongoing review of the project, control and business outcomes focusing on the stated Project SAP business objectives, risks, and priorities.
• Provide Executive Management with ongoing project assurance reporting.
• We would work along side the project identifying potential issues as early as possible and hence allowing Executive Management adequate time to consider, and if necessary address such issues. This is critical if the independent project assurance role is to add value to the project and help assist in its successful outcome. To this end we believe the independent assurance function should:
– Attend and provide input to key project team meetings
– Provide a rolling progress report on issues identified through our work
– Brief key program stakeholders on the status of our work and issues arising on a regular basis
ProjectOutcomes
ControlsOutcomes
BusinessOutcomes
ImplementationMethodology
Project Management
Project Governance
FunctionalReadiness
TechnicalReadiness
OrganizationalReadiness
BusinessCase
BenefitsRealizationPlan
Project Structure
DataQuality
Interfaces
ITGCs
BusinessProcesses
Project Assurance – A Suggested Approach
Draft
SDLC Selection Framework • IT Process Maturity
• Flexible, tailored approach to focus on management’s priorities for assurance regarding the achievement of Project SAP objectives.
– Efforts embedded in and integrated with overall Project SAP approach with a focus on value-add
– “One touch” integration of effort with external audit requirements to minimize disruption to project and avoid surprises
– Evaluate and leverage work performed by others (e.g., Parent Company Internal Audit, SAP, etc.)
• “Hub and Spoke” deployment of world class functional and technical capabilities from PwC to the project:
– SAP Risk Management, Security, and Control
– Transportation & Logistics
– Business Process
– Data Assurance
– Program/Project Management
– Internal Control and Financial Reporting
• Distinguished history of providing independent project assurance services to the company and the parent company.
– Experience navigating the Demand and Supply IT Model
– Invested in relationships throughout the service center and the company.
– Teams deployed alongside of the company in Houston, Scottsdale, and Plantation.
Our Value Proposition to the company
Draft
SDLC Selection Framework • IT Process Maturity
Integrating our Audit into Project SAP
Go-live & supportBlueprint
TIMETABLE
Realization
Business Process/ IT General Controls
Data Conversion/ Cleansing
Management Reporting
Security and Access Control
Testing Framework
Control Design/Gap Analysis
Agreement of expected key controls within the draft
documentation during the Blueprint and Realization
phases of the project allows maximum opportunity to
correct any issues within the design.
Data Conversion and Cleansing
Data integrity is a key risk within any environment;
this risk is increased during periods of
changes such as a system replacement.
Management Reporting
Many key business process controls rely upon system
generated data. The requirement to manipulate this
data as part of its use adds additional risk. Effective design and implementation of system
reports maximises process efficiency and reduces the audit
risk.
Testing Framework
Our experience of large implementations has
found that the proving of the system is complex and
difficult to manage effectively. A key factor are the controls around
the remediation of issues reported during the testing
phase.
Security and Access Control
As greater use of system based controls are built into the control environment, the
reliance upon the proper allocation of access increases. Getting this right from day one both for business and support users reduces the risk that gaps are
found post live that affect our strategy.
Draft
SDLC Selection Framework • IT Process Maturity
Business Process/IT General Controls
Review proposed business process control documentation containing the following types of controls: configurable, reports, manual procedures, automated, and interfaces.
Evaluate key controls over financial reporting (selected by the company) for completeness, accuracy, validity, restricted access, efficiency, resilience, and evidence of duplication.
Review of SAP screens to confirm settings of configurable controls.
Walkthrough of business process controls to confirm existence/operation of the automated and manual controls.
Assess SAP ITGCs
Management Reporting
Assess process to define key financial and management reporting requirements and assess the effectiveness of the reporting designed to meet these requirements.
Baseline key custom reports used to support the operation of manual controls for financial reporting (completeness, accuracy).
Testing Framework
Ensure requirements for unit testing, integration testing, system testing, UAT, interface and performance testing are adequately considered with a focus on testing of key controls.Assess whether an adequate testing monitoring system is in place.
Assess coordination of testing between business and IT.
Review configuration management and change control strategy and plan.
Review sample of testing scenarios and results focusing on consistency in approach and compliance with policy in relation to key controls.
Data Conversion/Cleansing
Review scope, approach, and requirements for data cleansing and conversion.
Assess quality controls within the conversion, setup and cleansing processes to ensure data integrity.
Review controls over the data cleansing and conversion process.
Review sample of data cleansing and conversion results.
Review strategy for master data maintenance.
Security/Access Controls
Review proposed SAP access related controls for sensitive access (SA) and Segregation of Duties (SOD) rule set; role maintenance; and user provisioning.
Assess SAP user roles against SA and SOD rule sets.
Walkthrough user provisioning and role maintenance process.
Assess existence of processes to manage access during implementation and during early stages of live operation.
Example Workplan
Draft
SDLC Selection Framework • IT Process Maturity
Questions
Contact Information
– Peter Harries, Partner 213 – 356 – 6760
– Charles Lewis, Partner 602 – 364 – 8290
– Pablo Hernandez, Senior Manager 602 – 364 – 8064
– JJ Marais, Senior Manager 602 – 364 – 8232