is construction verification the missing link in the bim ... - construction verification.pdf · t h...
TRANSCRIPT
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Is Construction Verification
The missing link in the BIM chain?
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Presenters:-
Michael Johnson
Senior BIM Consultant [email protected]
+44 (0)7802 865554
Shaun Farrell
Associate Director [email protected]
+44 (0)20 7544 4000
Paul Thorpe
BIM/VDC Coordinator [email protected]
+44 (0)7525 805781
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Agenda
• History
• BIM
• Consequences
• Construction Verification
• Benefits
• Construction Verification …… A Contractors Perspective
• Construction Verification ……. A Project Managers Perspective
• Questions
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Plowman Craven…..
■ 50th Anniversary
■ Work across all sectors of AECO Market
■ Technical innovators
■ Delivery capability across multiple platforms
■ 200 plus permanent staff
■ First adopters of laser scanning in the UK
■ 12+ years laser scanning experience
Clear Edge Technical and Application Partner - Europe
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Construction Yesterday
■ Visionary Clients
■ Great Concepts
■ Great Engineering
■ Eventual Delivery
BUT
■ Labour Intensive
■ Dangerous Working Environment
■ High Risk
■ Cost Challenges
■ Supply Chain Challenges
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Construction Today
■ Visionary Clients
■ Great Concepts
■ Great Engineering
■ Eventual Delivery
BUT
■ Labour Intensive
■ Dangerous Working Environment
■ High Risk
■ Cost Challenges
■ Supply Chain Challenges
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Is this what we are trying to achieve?
Structure
CDE
Architect MEP Infrastructure
Federated, clash managed
Digitally Marked up
Issued to CDE
Construction Sequencing
Change Management
Structural Fabrication
Model Manufacturing
MEP Model
Quantity Take Off Estimates &
BOQ’s
Model Review
Construction BIM
Operation
t h e t r u s t e d n a m e i n m e a s u r e m e n t
We are trying to provide better
Healthcare Housing Education
Infrastructure Commercial Leisure
t h e t r u s t e d n a m e i n m e a s u r e m e n t
BIM 4 Design
• EIR
• AIM
• Design BEP
• LOD/LOI
• Federated Design Models
• Clash Managed
• Audited for purpose
t h e t r u s t e d n a m e i n m e a s u r e m e n t
BIM 4 Construction
• EIR
• AIM
• Construction BEP
• LOD/LOI
• Clash Managed
• Audited for purpose
• Federated Sub - contractor Models
• 4D and 5D Activities
t h e t r u s t e d n a m e i n m e a s u r e m e n t
BIM in reality
• Design BIM sorted in a digital environment
• Construction PIM sorted in a digital environment
• Digital environment to construction site is sometimes still a
challenge!
• Do always get what we expected?
• How do we validate work done?
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Possible Consequences of WIP
• Right element in wrong place
• Wrong element in wrong place
• Out of tolerance installation
• Knock on effects to following packages
• Package creep
• RFI’s
• Sub contractor Delays
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Where is the Construction Verification Value ?
In addition to the contractual obligations surrounding the positional
and content verification of an installation, what would be the
commercial value of having “documented independent certification’ of
the positional accuracy and content of installations?
Could Construction Verification play a part in mitigating some of
the ever present costly delays, RFI’s, package creep, re-works,
legal and financial variations that play a part in our current
process?
Could Construction Verification add clarity to stage payments to
Contractors for work successfully carried out?
Could a reduction in contingency influence tender return prices
and impact on work won ratios’
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Benefits
• Validate constructed work delivered against design
• Early recognition of possible re-work
• Apportionment of financial responsibility
• Assistance with site monitoring against program
• Assistance with Site Progress Reports against invoicing
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Case Study
Objective:-
‘The purpose of the project was to verify that the steel work
construction on the Project was within 25mm tolerance of
the design, and that it included the penetrations required
when federated with the steelwork model.’
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Workflow used
• Building was laser scanned and photographed
• Scans processed in Cyclone
• Data converted to Recap (rcs) file format
• Data was aligned to Site Coordinates
• Point Cloud federated into PIM
• Verification carried out within Navis
• Report complied
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Deliverables
Commissioned deliverables:
• RCS file
• Construction Verification Report
• 2D CAD outputs
• Visual presentation
t h e t r u s t e d n a m e i n m e a s u r e m e n t
Financial Value of Construction Verification
• In general, horizontal position of major steel structure
(columns and beams) was within tolerance in the
East/West direction, but deviates in North/South as
illustrated in CAD outputs
• 9 instances of other discrepancies, including penetrations
are illustrated in the report
Discrepancies
Identified
Indicative RFI
Cost
Possible Project
Cost / floor
9 £5000 £45,000
t h e t r u s t e d n a m e i n m e a s u r e m e n t
The challenge ……. adoption
■ Should we do it?
■ Who pays?
■ When do we do it?
■ Where is the benefit?
■ Should it be a line item within a BEP?
■ Can it help address LOD500?
Let’s ask the experts!
Why would a contractor benefit from
construction verification?
• Present day potential savings
• Why construction verification is becoming more
important
• Where the industry is heading (Level 3 BIM)
Scenario – Trade on Trade Handover
Subcontractor 1 completes work
Subcontractor 1 employs surveyor to validate works
and produce as-builts
Area is handed over to Subcontractor 2
Subcontractor 2 employs surveyor to check works are
within defined tolerances
Subcontractor 2 accepts / refuses area SAME WORK TWICE!
What’s wrong with this picture?
An independent certified project partner
Responsible for
Project surveys,
Construction verification,
Producing the as-built information
How is this paid for?
Part of the project prelims
Subcontractors scope to undertake surveys removed
Possible Solution
How to combat increased design complexity?
Established Understood Delivering benefits
Clash Detection
Tolerances
Deflections
Settlement
What about on site?
importance of construction verification
design
complexity
Point Clouds
How to provide better as-built information
Greater understanding
of the as-built condition
Review in 3D the impact
to follow on trades
Improved accuracy 1:1
Continuous monitoring
How to provide better as-built information
Reliability
Deflections / Settlement throughout project duration
An as-built today is less reliable in 3 months
BIM Level 3 during the construction phase?
An updating digital record
of the project during the
construction phase
Frequent / constant
recording of as-built
conditions
Smart sensors recording
condition data, such as
concrete strength
Allowing all parties to
review real time
Current conditions used to inform up-coming works
Checking construction methodology / programme using real time information
Site personnel safety briefings showing real time working areas and routes
Remote senior staff reviews of progress, safety, quality etc.
How will this information be used?
Extreme 4D
Dr. Ionnis Brilakis –
Laing O Rourke Lecturer in Construction
Engineering Cambridge University
Where will this lead to?
“As-is BIM”
Utilising technology such as:
• Cloud computing
• Scan to BIM
• Big data
• Internet of things
Smart sensors capturing physical and
non-physical data throughout lifecycle of
the asset
Turner & Townsend
Who we are
Turner & Townsend is an independent professional services company specialising in programme management, project management, cost management and consulting across the property, infrastructure and natural resources sectors.
With 90 offices in 38 countries we draw on our extensive global and industry experience to manage risk while maximising value and performance during the construction and operation of our clients’ assets.
Our vision
To be the leading capital programmes professional service provider operating across property, infrastructure and natural resources.
BIMnet - Verification
Turner & Townsend
Our services
Operations
Maximising asset portfolio
performance
Environmental assessment
Facilities management
Health and safety
Legislative compliance
Life cycle costing, carbon and energy management
Operational cost management
Operational performance improvement
Consultancy
Improving programme performance
Asset strategy and planning
Business case development
Change management
Funders advisory services
Organisational design
Performance improvement
Procurement and supply chain strategy
Risk and opportunity management
Delivery
Managing programme delivery
Contract and dispute management
Cost engineering and cost management
Design management
Portfolio management
Procurement
Project controls
Project management
Project monitoring and audit
Planning and scheduling
Risk mitigation
Combining skills, delivering programme results
BIMnet - Verification
Turner & Townsend
Technology Team
Capital Projects
We manage the delivery and integration of Technology Solutions into existing and new builds
■ KPMG
■ PWC
BIM
We work with our clients to define their information requirements and assure these are met though management and validations processes to create a digital asset
■ Battersea Power Station
■ Grosvenor Square
Analytics
We get clients to understand their business better by helping them analyse and use their data in an effective way. We do this using interactive & visualization tools
■ NHS
■ Zurich
Solutions Advisory
We provide consultancy and information management solutions to our clients to support their objectives
■ United Utilities
■ Tramlink
BIMnet - Verification
Turner & Townsend
Gate process - Verified
• The transition from published to archive
• Archived at key project milestones and project completion
• Re-measured and verified as built
Image ©Mervyn Richards
BIMnet - Verification
Turner & Townsend
Gate process - Archived
• Used to record all progress as each project milestone is met
• Hold a record of all transaction and change orders
• Re-measured as built/as constructed and verified information
• Asset data
• Health and safety file
• Operations & maintenance information
BIMnet - Verification
Turner & Townsend Management Solutions Limited One New Change London EC1M 9AF
t: +44 (0)20 7544 4000 e: [email protected] www.turnerandtownsend.com
© Turner & Townsend Project Management Limited. This content is for general information purposes only and does not purport to constitute professional advice. We do not make any representation or give any warranty, express or implied, and shall not be liable for any losses or damages whatsoever, arising from reliance on information contained in this document.
It must not be made available or copied or otherwise quoted or referred to in whole or in part in any way, including orally, to any other party without our express written permission and we accept no liability of whatsoever nature for any use by any other party.