Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r FACILITY LOCATION, CAPACITY AND LAYOUT Chapter Outline Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7-1 Locating Manufacturing Facilities Locating Service Operations Capacity Decisions Facility Layout

Upload: griselda-ball

Post on 14-Dec-2015

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

7C h a p t e r

FACILITY LOCATION, CAPACITY AND LAYOUT

Chapter Outline

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

7-1

• Locating Manufacturing Facilities

• Locating Service Operations• Capacity Decisions• Facility Layout

Page 2: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

7C h a p t e r

FACILITY LOCATION, CAPACITY AND LAYOUT

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

7-2

Chapter Objectives

• Identify the various factors that must be considered in selecting a location for a manufacturing or service operation.

• Introduce a framework for evaluating alternative site locations.

• Present alternative strategies for increasing capacity.

Page 3: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

7C h a p t e r

FACILITY LOCATION, CAPACITY AND LAYOUT

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

7-3

Chapter Objectives continued

• Identify the different types of facility layouts in manufacturing and service operations.

• Define the steps required in balancing an assembly line.

Page 4: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

Locating Manufacturing Facilities(Qualitative Factors)

• Local Infrastructure• Worker Education and Skills• Product Content

Requirements• Political/Economic Stability

7-4

Page 5: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

Locating Manufacturing Facilities(Quantitative Factors)

• Labor Costs• Distribution Costs• Facility Costs• Exchange Rates

7-5

Page 6: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

Plant Location Methods

• Quantitative:· Center of gravity

method• Qualitative:

· factor-rating systems

7-6

Page 7: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

EXHIBIT 7.6 Comparing Capacity and Demand in a Service Operation D

eman

d

Time

Maximum capacity

Optimal capacity

Customers turned away

Poor service

Idle capacity

7-7

Page 8: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

EXHIBIT 7.7 Economies of Scale

Ave

rage

uni

t cos

t

Volume (units)

Economies of scale

Diseconomies of scaleA

B

C

D

VA VB VC VD

7-8

Page 9: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

EXHIBIT 7.8A Proactive Capacity Strategy

Volume(units)

Time

DemandPlant Capacity

Excess/idle capacity

7-9

Page 10: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

EXHIBIT 7.8B Neutral Capacity Strategy

Volume(units)

Time

Demand

Plant Capacity

7-10

Page 11: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

EXHIBIT 7.8C Reactive Capacity Strategy

Volume(units)

Time

Demand

Plant Capacity

Unfilled demand

7-11

Page 12: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

Types of Facility Layouts

• Process layout• Product layout• Group technology

layout • Fixed-position layout

7-12

Page 13: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

Process Layout

Assembly Painting Plating

MachiningWelding

7-13

Page 14: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

Product Layout

Product A

Product B

Product C

Step 1

Step 1

Step 1

Step 2

Step 2

Step 2

Step 3

Step 3

Step 3

Step 4

Step 4

Step 4

7-14

Page 15: Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 7 C h a p t e r F ACILITY L OCATION, C APACITY AND L AYOUT Chapter Outline Irwin/McGraw-Hill

Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999

EXHIBIT 7. 17 Precedence Graph for Model J Wagon

A

E

D

CB

G

F

H

I

J K

12

12

911

45

50

15

12

12

8 9

7-15