IRP Presentation. Advisor / Clients: Dr. James McCalley Venkat Krishnan Joseph Slegers Team Members: Michael Healy (EE), Deogratius Mpinge (CprE), Spenser Mussmann (EE), and Abdelmagid Yousif (EE) Team ID: Dec11_06. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/1.jpg)
IRP Presentation
Modeling Energy System Investment Planning Infrastructure for the State of Iowa
Advisor / Clients: Dr. James McCalley Venkat Krishnan Joseph Slegers
Team Members: Michael Healy (EE), Deogratius Mpinge (CprE), Spenser Mussmann (EE), and Abdelmagid Yousif (EE)
Team ID: Dec11_06
![Page 2: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/2.jpg)
Problem Statement
The energy and transportation demands continue to rise across the state of Iowa. An investment plan will need to be created for the next several decades to meet these demands and remain economical.
The goal of this project is to accurately describe, in a data set, the current energy and transportation sectors within the state of Iowa. This data set will be analyzed by NETPLAN, Iowa State University software, and the results will describe investment strategies as well as emission, un-served demands, capacities, arc flows, and system resiliency.
These results will be displayed on a public website. The current system as well as other scenarios will be available to the user to demonstrate different investment strategies available.
2
![Page 3: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/3.jpg)
Project PlanSoftware analysis:
o NEMS – Electric infrastructure
o MARKAL/TIMES – Electric infrastructure
o CARVER2 – Transportation infrastructure
o TRAGIS – Transportation infrastructure
o NETPLAN – Relationship between electric and transportation
3
![Page 4: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/4.jpg)
Project Plan1. Collect Required Data for NETPLANo Generation
- Type- Capacity- Specifications
o Transmission- Size- Capacity- Specifications
o Transportation- Passenger- Commodity
4
![Page 5: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/5.jpg)
Project Plan2. Develop Website
o Google Earth- Provide infrastructure information- Visual depiction of current infrastructure
o Results/Documentation - Dynamic- Easy to access- Easy to understand- Easy to navigate
5
![Page 6: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/6.jpg)
Project Plan3. Base Case and Scenario Creation
o Base Case- Describes current infrastructure- Benchmark for all other scenarios
o Alternative Cases- Accounts for potential technological improvements or government intervention
6
![Page 7: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/7.jpg)
Project Plan4. Create a guide and improve NETPLAN user manual
o Guide- Step-by-step description of our data set- Provides guidance for next research team
o User manual updates- Description of all files- Hints/tips we learned along the way
7
![Page 8: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/8.jpg)
Project PlanSchedule
o Task Breakdown
o Task Schedule
8
![Page 9: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/9.jpg)
Project Design1. Data Set
o Node system- Generation
At least 95% of total generation Cut off limit
- Demand Locations Compensation
9
![Page 10: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/10.jpg)
Project Design1. Data Set (cont.)
o Arc system- Transmission Lines
Size Routes
- Transportation Routes Type Emissions
- Fuel Routes Natural gas pipelines Fuel by rail Fuel by vehicle
10
![Page 11: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/11.jpg)
Project Design2. Developing the Websiteo Google Earth Map
- Contains node map
- Generation sites
- Transmission lines
- Transportation routes
- Wind maps
- Natural gas pipelines/storage sites
11
![Page 12: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/12.jpg)
Project Design2. Developing the Website (Cont.)o All project documentation
o Interactive NETPLAN results
- Tables
- Charts
- Downloadable content
o References/contact information
o Instructions on running NETPLAN from home
12
![Page 13: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/13.jpg)
Project Implementation1. Investment Strategies
Data Set
o Formulation of base case
o Formulation of alternative scenarios
NETPLAN
o Interface Results
o Result files
o Results displayed on website
13
![Page 14: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/14.jpg)
Project Implementation
Data Set to NETPLAN
NETPLAN results stored as tables and charts
Results to website
14
1. Investment Strategies (Cont.)
![Page 15: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/15.jpg)
Project Implementation2. Google Earth Map
I. Acquire all needed infrastructures data for electric and transportation sectors
II. Use the geographical coordination to build KML files ( Keyhole Markup
Language) in Google Earth
III. Add the basic information (owner, size, length,…etc) for each unit to KML files
IV. Implement the KML files on the website using HTML and Java script languages
HTML & Java Script
Coordinate
Owner, size, length…etc
Data KML file Website15
![Page 16: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/16.jpg)
Project Implementation2. Google Earth Map (Cont.)
16
![Page 17: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/17.jpg)
Project Implementation
Google Earth Interface Java script and HTML code Allows user to specify which
infrastructure component to view
User can view multiple components at a time (Wind speed maps and wind farm locations)
NETPLAN Results Interface Java script and HTML code 21 different scenarios available User can view the results on
the website or download them
3. User Interface
17
![Page 18: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/18.jpg)
Testing and Evaluation
18
• Test the functionality of the website to ensure all the
requirements are met
• Analyze and evaluate the base case result to ensure it is
reasonable and accurate
• Develop scenarios to compare with base case on the future
energy and transportation needs
• Evaluate each scenario for violations
![Page 19: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/19.jpg)
Base CaseAssumptions
o Generation Investment Costs
o Transportation Investment Costs
o Lifespan
o Current Fuel Price
o Average Annual Demand
o Annual Peak Demand
o Emission Rates
o Investment Limits
o Investment Locations 19
![Page 20: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/20.jpg)
Base CaseResults
o High wind and natural gas generation investmentso High wind potential led to feasibility of hybrid vehicleso Emissions per GW dropped significantlyo The total capacity of Iowa increased from approximately
12 GW to 30 GW
20
![Page 21: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/21.jpg)
Base Case
21
Results (Cont.)
![Page 22: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/22.jpg)
High Wind Investment ScenarioClarification: The total wind capacity we found was for use in Iowa only. If we consider the potential export of energy this number will be much higher.
This scenario represents a possible investment strategy Iowa could undertake. There have been many improvements to wind turbine technology, and this case accounts for increased capacity factor.
We found similar results to that of the base case, however wind investments now covered the capacity of the initial coal investments.
Hybrid vehicles became more feasible since more energy was being generated without an increase in generation sites. We assumed existing and new capacity factors would increase by approximately 15%.
22
![Page 23: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/23.jpg)
High Wind Investment Scenario
23
![Page 24: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/24.jpg)
Conclusion
24
• Wind is able to provide the most needed energy for the future
with the best economical and environmental solution
• Increase the wind turbine efficiency considered as the best
solution than other wind scenarios
• Investment in wind will also require investment in natural gas
• According to our analysis, hybrid vehicles should become
economically feasible sometime during the next 40 years
![Page 25: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/25.jpg)
Future Work
• Develop and Improve NETPLAN software
• Simulation time
• End of lifespan function
• Running NETPLAN from the website
• Simulation time
• Access to CPLEX
25
![Page 26: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/26.jpg)
Special Thanks
• Dr. James McCalley, advisor
• Venkat Krishnan, PhD graduate student
• Joseph Slegers, MS graduates student
• Eduardo Eibanez, ISU PhD graduate
• NETSCORE21 Team
26
![Page 27: IRP Presentation](https://reader036.vdocuments.us/reader036/viewer/2022062314/56814435550346895db0ce62/html5/thumbnails/27.jpg)
Questions ?