IOWA ACCELERATED BRIDGE CONSTRUCTION Norm McDonald, PE 2014 ASCE Transportation Conference November 5, 2014 Ames

Upload: others

Post on 17-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

IOWA ACCELERATED BRIDGE CONSTRUCTION

Norm McDonald, PE2014 ASCE Transportation ConferenceNovember 5, 2014 Ames

Page 2: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

ABC Definition• ABC is bridge construction that uses innovative planning, design, materials and construction methods in a safe and cost-effective manner to reduce the on site construction time that occurs when building new bridges or replacing and rehabilitating existing bridges.

- FHWA Accelerated Bridge Construction Final Manual

Page 3: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Mobility Impact Time

• Tier 5 – Overall project schedule is significantly reduced by months to years.

• Tier 4 – Traffic impacts within 3 months.• Tier 3 – Traffic impacts within 2 weeks.• Tier 2 – Traffic impacts within 3 days.• Tier 1 – Traffic impacts within 1 to 24 hours.

- FHWA Accelerated Bridge Construction Final Manual

Page 4: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

ABC Techniques• Prefabricated Bridge Elements and Systems (PBES)• Precast elements• Self-propelled modular transporters (SPMT)• Slide-In Bridge Construction (SIBC)

• Innovative Contracting• A+B Bidding• I/D Contracts• Lane Rental

Page 5: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Why use ABC?• To deal with schedule constraints

• Limited time-window due to special events• Emergency replacement due to natural disasters, accidents, or intentional acts

• To minimize impact on local traffic • Access to business• Commuters• Essential services

• To deal with the unavailability of suitable detour

Page 6: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

ABC: Benefits

• Reduced public inconvenience • Improved public perception • Improved road users and workers safety• Reduce negative economic impact on local businesses

• Improve the durability of the structure

Page 7: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Iowa’s ABC Experience• 11 Demonstration projects constructed to date

• Focus on a variety of PBES• Focus on I/D contracting• Grants – IBRC, IBRD, SHRP2 R04, HFL

• 5 Projects currently in Final Design

• 2 Projects currently in Preliminary Design

Page 8: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Presentation Overview• Five Key Projects

• Mackey Bridge - 2006• Madison Bridge - 2006• 24th Street Bridge - 2008• Keg Creek Bridge - 2011• Massena Bridge - 2013

• ABC Policy

Page 9: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Mackey Bridge

Page 10: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Mackey BridgeName Mackey BridgeLocation 120th Street over Squaw CreekYear Constructed 2006Owner Boone CountyEngineer Iowa DOTBridge Type PPCBSize 151'‐4 x 30'‐6Spans 47'‐5, 56'‐6, 47'‐5ABC Technologies Precast Abutment Footing

Precast Pier CapsFull‐Depth Precast Deck Panels

Total Project Bid $737,098.11Bridge Unit Cost* $90/SFABC Contract Period NoneGrant IBRC*Traditional unit cost at this time for PPCB = $60/SF

Page 11: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Mackey Bridge

Page 12: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Mackey Bridge

Page 13: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Mackey Bridge

Page 14: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Mackey Bridge

• Lessons Learned• The precast concrete footing/cap to pile

connection is a highlight of the project.• Consider prestressing precast elements.• PPC Beam flange width.• Haunch forming system.• Deck panel post-tensioning:

• Panel casting tolerance.• Stress distribution from pt.

Page 15: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Madison Bridge

Page 16: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Madison BridgeName Madison BridgeLocation 290th Street over Branch Clanton CreekYear Constructed 2006Owner Madison CountyEngineer Iowa DOTBridge Type Precast Box BeamSize 46'‐8 x 24'Span 46'‐8ABC Technologies Precast Abutment Footing

Precast Box BeamsTotal Project Bid $159,937Bridge Unit Cost* $98/SFABC Contract Period NoneGrant IBRC*No traditional unit cost data available for box beam bridges

Page 17: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Madison Bridge

Page 18: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Madison Bridge

Page 19: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Madison Bridge

• Lessons Learned• The contractor’s temporary support method for the

precast footing with flowable mortar fill worked well.• The cast-in-place concrete closure diaphragm added

time to the critical path and was subsequently changed to a precast piece in a future similar project.

Page 20: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Buena Vista County

1'-9"

2'-1"

3'-0" 3'-3"

4 Pile Spaces @ 6'-0" = 24'-0" 2'-1"

2 - 78" Dia. x 5"Studs Ea. Sideof Pile (Typ.)

HP 10 x 57Steel Bearing Pile

1'-9" Ø GalvanizedC.M.P. Pile Sleeve

28'-0"

Steel Post and Guardrail

4'-0" x 1'9"Deck Beam

Grouted Keys

2'-0"

28'-2"

NeopreneBearing Pad

Grout VoidSolid

3'-0" Wide PrecastCap Beam

Page 21: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Buena Vista County

Page 22: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract
Page 23: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

24th Street Bridge

Page 24: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

24th Street BridgeName 24th Street Bridge in Council BluffsLocation 24th Street over I‐29/I‐80Year Constructed 2008Owner Iowa DOTEngineer HDR, Inc.Bridge Type CWGSize 353'‐6 x 82'Spans 178'‐6, 175'‐0ABC Technology Full‐Depth Precast Deck PanelsTotal Project Bid $12,506,262.87Bridge Unit Cost* $140/SFABC Contract Period A+B with 210 days max. @ $1,500/dayGrant HfL

*Traditional unit cost at this time for CWG = $120/SF

Page 25: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

24th Street Bridge

Page 26: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

24th Street Bridge

Page 27: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

24th Street Bridge

• Lessons Learned• Sand blasting is the preferred method for roughening

the concrete surfaces for bonding precast concrete to cast-in-place concrete

• Transverse joint detail

• Incentive/Disincentive amount needs to be commensurate with the project size

Page 28: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Keg Creek Bridge

Page 29: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Keg Creek BridgeName Keg CreekLocation US 6 over Keg CreekYear Constructed 2011Owner Iowa DOTEngineer HNTB CorporationBridge Type Rolled Steel I GirderSize 204'‐6 x 44'‐0Spans 67'‐3, 70'‐0, 67'‐3ABC Technologies Precast Abutment Footing

Precast WingwallsPrecast Pier CapsPrecast Pier ColumnsModular UnitsUHPC JointsGrouted Splice Couplers

Total Project Bid $2,658,823.35Bridge Unit Cost* $161/SFABC Contract Period 14 day critical closure w/ $22,000/day I/DGrant SHRP2 R04

*Traditional unit cost at this time for I Girder = $90/SF

Page 30: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

14-Day ABC Timeline

Actual ABC period: October 17 – November 1

Page 31: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Iowa Bridge Farm

Page 32: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

SuperstructureModules –Structural Steel Assembly

Page 33: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Superstructure Modules – Deck Forming

Page 34: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Deck Concrete Placement

Page 35: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Keg Creek Bridge

Page 36: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Keg Creek Bridge

Page 37: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Cap Beam Assembly

168 kips

Page 38: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Keg Creek Bridge

Page 39: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Keg Creek Bridge

Page 40: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract
Page 41: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Keg Creek Bridge

• Lessons Learned• Grouted splice couplers are promising – template is

critical.• Modular unit deck reinforcing congestion.• Semi-integral abutment overhanging backwall detail

needs improvement.• Survey, survey, survey! Not just an ABC issue.• Inspector training and project demands.

Page 42: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Massena Bridge

Page 43: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Massena Bridge

Page 44: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

BRIDGE CONSTRUCTION VISUALIZATION

Page 45: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Mobility Impacts & ABC Consideration• Original concept: Six months road closure• 7 miles out of distance travel for detour• AADT (2012) – 1,460 w/ 16% trucks• User costs for 180 day detour

• Indirect $437,000• Direct $15,000 (road maintenance & detour signing)

• User costs for a 9 day road closure• $22,000

Page 46: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Massena BridgeName Massena Lateral SlideLocation IA 92 over Small StreamYear Constructed 2013Owner Iowa DOTEngineer Iowa DOTBridge Type PPCBSize 120'‐0 x 44'‐0Span 120'Key ABC Technologies Slide‐In Bridge Construction (SIBC)

Precast WingwallsPrecast Abutment Footing

Total Project Bid $1,346,647.90Bridge Unit Cost* $112/SFABC Contract Period 9 day critical closure w/ $10,000/day I/DGrant HfL

*Traditional unit cost at this time for PPCB = $85/SF

Page 47: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Massena Bridge

Page 48: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Massena Bridge

Page 49: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Massena Bridge

Page 50: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Massena Bridge

Page 51: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Massena Bridge

• Lessons Learned• Let ABC projects in the fall.• I/D time increment – days v. hours.• For the abutment footing let with a C.I.P. and precast concrete alternate.

• Pile size considerations HP14x117.• Pile driving acceptance criteria.• Falsework inspection.

Page 52: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

ABC Policy

•Developed in 2012• First level screening

• Average Annual Daily Traffic• Out of distance travel• Daily road user cost• Economy of scale

Page 53: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Measures Score Weight Factor

Weighted Score

Maximum Score

Weighted Maximum Score

Average Annual Daily Traffic 5 10 50 5 50

Out of Distance Travel 2 10 20 5 50

Daily Road User Costs 4 10 40 5 50

Economy of Scale 2 5 10 3 15

Total Score 120 Max Score 165

ABC Rating Score (Total Score/Max Score)x100= 73

ABC RATING SCORE FACTORS AND WEIGHTS

Page 54: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

ABC Policy

Page 55: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

AHP Analysis Details• AHP (Analytic Hierarchy Process) is a decision- making technique designed to select the best alternative from a set of alternatives evaluated against several criteria.

• The decision maker performs pair-wise comparisons that are used to develop an overall priority ranking for each alternative.

55

Page 56: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

AHP Analysis Details Comparisons are also used to assess the extent to which one alternative satisfies a criteria over another alternative.

Alt B9 8 7 6 5 4 3 2 987654321

9 8 7 6 5 4 3 2 987654321Alt A

Alt A

Alt B

Direct Costs

Indirect Costs

Page 57: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

ABC Policy

• Final concept recommending ABC approach with desired ABC schedule & method.• Tier 1: Traffic Impacts within 1 to 24 hours• Tier 2: Traffic Impacts within 3 days• Tier 3: Traffic Impacts within 2 weeks• Tier 4: Traffic Impacts within 3 months• Tier 5: Traffic Impacts from 3 months to years

Page 58: IOWA ACCELERATED BRIDGE CONSTRUCTION...Precast Pier Columns Modular Units UHPC Joints Grouted Splice Couplers Total Project Bid $2,658,823.35 Bridge Unit Cost* $161/SF ABC Contract

Additional Information

http://www.iowadot.gov/bridge/abc.htm

Google: Iowa DOT ABC

2014 PCI Convention and National Bridge Conference Proceedings