ion source and lebt performance and plans08'stockli.pdf · electron suppressor...
TRANSCRIPT
![Page 1: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/1.jpg)
Managed by UT-Battellefor the Department of Energy
Ion Source and LEBT Performance
and Plans
Martin P. Stockli
Ion Source Group Leader
![Page 2: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/2.jpg)
2 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Content
Overview
Milestone Diagnostic Problems & Solutions
The 2007 LEBT Sparkfest
The LBNL Cs System and its Operation
The Beam Current Challenge
The Plans
![Page 3: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/3.jpg)
3 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
• Over the years many low-cost improvements were made to achieve 100% availability for low duty-factor runs.
•The source and LEBT are currently delivering the required 25 mA MEBT beam current with ~100% availability.
Gas inlet
Window
Cusp magnets
Dumping magnets
Cesium collarPlasma
Extractor
E-dump Lens 2RFQ entrance flange
Ground electrode
Lens 1
Outlet electrode
Filter magnets
RF antenna
Gas inlet
Window
Cusp magnets
Dumping magnets
Cesium collarPlasma
Extractor
E-dump Lens 2RFQ entrance flange
Ground electrode
Lens 1
Outlet electrode
Filter magnets
RF antenna
LBNL developed the SNS baseline ion source, a cesium-enhanced, multicusp RF ion source, and the 12 cm long, two-lens electro-static LEBT. Lens-2 is split into four quadrants to steer, chop, and blank the beam.
Commissioning Availability
FE @ ORNL 85.6 %DTL-1 92.4 %DTL-2/3 97.8 %CCL1-3 98.6 %SCL 99.8 %Ring 99.7 %Target 100.0 %Run 2006 99.9 %Run 2007-1 (0.2%) 99.98 %Run 2007-2 (0.8%) 70.6 %Run 2007-3 (1.8%) 97.2 %Run 2008-1 (3.0%)
The SNS Baseline Ion Source and LEBT
•Raising the duty factor to ~0.8 % heated the LEBT, which started to arc and break the chopper HV switches. Minor modifications fixed the problem.•Minor modifications were needed to increased the beam current output.
![Page 4: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/4.jpg)
4 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Content
Overview
Milestone Diagnostic Problems & Solutions
The 2007 LEBT Sparkfest
The LBNL Cs System and its Operation
The Beam Current Challenge
The Plans
![Page 5: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/5.jpg)
5 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
-10
0
10
20
30
40
0 100 200 300 400 500 600Suppression voltage
Ap
pare
nt
cu
rren
t [m
A]
Ion collector
-10
0
10
20
30
40
0 100 200 300 400 500 600Suppression voltage
Ap
pare
nt
cu
rren
t [m
A]
Ion collector
-10
0
10
20
30
40
0 100 200 300 400 500 600Suppression voltage
Ap
pare
nt
cu
rren
t [m
A]
Ion collector
Electron suppressor
Collector-Suppressor
-10
0
10
20
30
40
0 100 200 300 400 500 600Suppression voltage
Ap
pare
nt
cu
rren
t [m
A]
Ion collector
Electron suppressor
Collector-Suppressor
Concerns about accurate beam measurements
drove LBNL to design a special Faraday cup. Its
water cooled Co-Sm magnets generate 0.07 T that
sweep any 65 kV electrons into a suppressor while
the H- beam is collected on a plate.
The required high suppression voltage raised
concerns. Eventually we realized the the beam was
multiplied by partly striking the suppressor.
Early Beam Current Diagnostics
on Ion Source Test Stand
AA
supply
eH
Beam
A
LEBT
exit
Electron
suppressor
Ion c
olle
cto
r
Asupply
eH
Beam
Multiplication could be
optimized with lens 2!
The required high suppression voltage raised
concerns.
(From ASAC’04F)
![Page 6: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/6.jpg)
6 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
5-7-04
A large, deep
Faraday cup was loaned
from KSU and installed.
0
10
20
30
0 100 200 300 400 500Suppression Voltage
Ap
pare
nt
cu
rren
t [m
A]
BCMFC-2
4-26-04
Measurements agree within a few %! A bit larger, less-distant, water-cooled
Faraday cup is being designed. LEBT steerers need to be installed!
LEBT
exitAsupply
2.37”
~8”~12”
H
BCM
FC-2supply
Suppressor
Recent Beam Current Diagnostics
on Ion Source Test Stand
2007: Before 5-2004 test stand current measurements are over-
optimistic. Today, the BCM remains our most trusted measure!
Controls is still planning to install the steerers!
(From ASAC’04F)
![Page 7: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/7.jpg)
7 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
LBNL delivered the 2 MHz amplifier with a rather unique look-up table.
The LBNL 2 MHz
Calibration:
0 0
500 1.2
1000 2.4
1500 7.2
1800 12
2000 19.2
2200 28.8
2300 36
2500 48
2700 26
2900 52
3000 36
3100 86.4
3300 110.4
3500 124.8
3700 132
3900 144
10000 192
0
20
40
60
80
100
120
140
0 1000 2000 3000 4000
Low Level Signal
RF
Ou
pu
t P
ow
er
[kW
]
0
10
20
30
40
50
60
70
80
0 10 20 30 40 50 60 70 80
Control Slide Reading (kW)
Measu
red
RF
Ou
tpu
t P
ow
er
(kW
)
Sliding up
Sliding
down
Yoon Kang’s 2006 measurements yield interesting results:
3 settings are practically correct: 0, 5, and 70 kW.
Most other settings significantly over-deliver, inflating mA/kW efficiencies by 50%.
A hysteresis prevents all values between 26 and 50 kW from being recalculated, but likely were near 70 kW.
All Pre-October-2006 Frontend RF power
values are seriously flawed!
![Page 8: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/8.jpg)
8 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
0
20
40
60
80
100
0 500 1000 1500 2000 2500 3000 3500 4000
Low Level Signal
RF
Ou
tpu
t P
ow
er
[kW
]
LBNL
ORNL-TS-06
ORNL-FE-06
ORNL-FE-07
ORNL-FE-07B
We were unable to reproduce the unique LBNL look-up table.
The Test Stand 2 MHz yielded a different calibration curve. Reason is not understood.
0
20
40
60
80
100
0 500 1000 1500 2000 2500 3000 3500 4000
Low Level Signal
RF
Ou
tpu
t P
ow
er
[kW
]
LBNL
ORNL-TS-06
ORNL-FE-06
ORNL-FE-07
ORNL-FE-07B
The ORNL 2 MHz
Calibration:2 MHz Look-Up Tables
The RF group continues their effort to validate and
improve the calibration of our three 2 MHz amplifiers!
Three calibrations of the Frontend 2 MHz found consistent curves that only differ at the high power end, which are based on extrapolations.
Pre-2006 Test Stand RF power-values are likely far off!
We lack a calibration for the spare 2 MHz.
![Page 9: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/9.jpg)
9 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Tuning the Ion Source and LEBT
A beampulse with
large overshoot
0.33-0.38 ms
Beam
current
RFQ filling
The best invention since sliced bread!
The compactness of the LBNL LEBT allows for no beam current diagnostics before the RFQ.
Therefore source tuning has to be delayed until RFQ is running.
The MEBT beam stop power limit allowed only for the 1st 50s to be measured, which are dominated by the plasma breakdown and initial beam current overshoot.
A time-consuming retune was needed when the entire pulse length could be monitored.
On Halloween 2007 Controls implemented a shift that allows the ion source pulse to be shifted through a 50s window accelerated by the RFQ.
This has eliminated many, many hours of beam tuning with questionable merit.
Beam Current Peak Current –1 mA
![Page 10: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/10.jpg)
10 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Content
Overview
Milestone Diagnostic Problems & Solutions
The 2007 LEBT Sparkfest
The LBNL Cs System and its Operation
The Beam Current Challenge
The Plans
![Page 11: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/11.jpg)
11 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Cesiation
30 mA
4 pm
9 am
Spark-Video
Festival
•Early in run 2007-2, when the duty factor was increased from 0.2 to 0.8%, frequent chopper failures suggested a sparking problem.
•~1week later we had lens-2 spark counters that capacitively picked up high voltage fluctuations. They suggest sparkfest occurring often at random.
The 2007 LEBT problem
![Page 12: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/12.jpg)
12 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
A robuster LEBT
A
A
Courtesy of R. Welton
•Exposure of the insulators is a risk!
![Page 13: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/13.jpg)
13 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Content
Overview
Milestone Diagnostic Problems & Solutions
The 2007 LEBT Sparkfest
The LBNL Cs System and its Operation
The Beam Current Challenge
The Plans
![Page 14: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/14.jpg)
14 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
The LBNL Cs System:
The LBNL H- source features a complex outlet electrode assembly that
1. extracts the ions and forms a beam
2. deflects the co-extracted electrons onto the e-dump
3. adds surface produced H- ions to the volume produced ions
ions
Cs-collar The LBNL Cs collar holds the cesium cartridges and its outlet aperture where the surface-produced ions originate. The entire collar can be heated with an external compressed air heater up to ~400 C.
Cs-collar
e-
e-dump
Extr
acto
r
![Page 15: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/15.jpg)
15 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Cs dispensers by SAES Getters
• The LBNL H- source uses eight 12 mm long Cs cartridges from SAES Getters. The nichrome shell contains a mix of Cesium chromate (Cs2CrO4) with reducing agent St101®(84%Zr+16%Al) that also absorbs the active gases that are produced during the reduction reactions:
4 Cs2CrO4 + 5 Zr 8 Cs (g) + 5 ZrO2+2 Cr2O3
6 Cs2CrO4 + 10 Al 12 Cs (g)+ 5 Al2O3+3 Cr2O3
when being heated to 550 – 850C.
A metal wire partially obstructs the slit to eliminate the escape of loose particles.
•The compressed gas heating system is unable to generate temperatures high enough to initiate the release of Cs.
•Accordingly, the release of cesium is initiate by shutting off the air flow and heating the cesium collar with the plasma.
•A thermocouple inserted in to the air duct of the collar measures the temperature of the collar. The temperature of the cartridge is higher due to the thermal resistance between the cartridges and the collar.•After initially exploring a wide range of parameters, we settled on heating the collar to 500 or 550C for 20-30 minutes.
•This was repeated until the desired current was achieved.This worked on the Frontend with limited persistence!
![Page 16: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/16.jpg)
16 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Early Cs R&D
“Unlike …Runs 1-7, in the new technique the source was outgassed at ~7% duty-factor and 50 kW of RF power for ~1 day while maintaining the collar temperature below 150 C. This led to our highest average beam current of any experimental run: 30 mA, suggesting much more Cs was delivered to the source”. From R.F. Welton et al, AIP Conf. Proc. No.763 (2005), pp. 296-314.
• However, for long pulses on the test stand it generated only 20-25 mA, not the ~41 mA required for 1.4 MW ops.
• In 2006 R. Welton tried to increase the yield by optimizing the positions of the antenna, the cesium collar, etc.
• He then started to suspect the getter in the cartridges to be incapacitated by the residual gases in the source.
The initial experiment seemed to confirm the hypothesis!
In addition, the paper calculated that a 0.5
monolayer of Cs is sputtered away in 2.5 s.
![Page 17: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/17.jpg)
17 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Early Cs R&D
0
10
20
30
40
50
9/21/04 9/28/04 10/5/04 10/12/04
Av
era
ge
Pu
lse
Cu
rre
nt
[mA
]
Emittance measurements with 10 Hz
Start Lifetime Test with 60 Hz
Recesiate RF trips shortly before COB
Cannot be restarted quicklyRecesiate
Source fails
pulse length: 1.23 ms
0
10
20
30
40
50
9/21/04 9/28/04 10/5/04 10/12/04
Av
era
ge
Pu
lse
Cu
rre
nt
[mA
]
Emittance measurements with 10 Hz
Start Lifetime Test with 60 Hz
Recesiate RF trips shortly before COB
Cannot be restarted quicklyRecesiate
Source fails
pulse length: 1.23 ms
“these reactions are limited by the
availability of Zr and Al rather than
Cs2CrO4. Computational
thermodynamic analysis reveals that
at temperatures greater than ~250 C,
Zr and Al will spontaneously react
and form stable compounds with
residual gases evolved from the
source during initial out-gassing.
Therefore, it is clear that the Cs
collar must be maintained at
temperatures below 250C, ideally
as cold as possible, until the
source has been conditioned (out-
gassed) to full duty-factor before
heating the Cs collar”. From R.F.
Welton et al, PAC’05, Knoxville, TN (2005)
pp. 472-474.
The next experiment was even
better! Therefore it was concluded:
However, a later repetition yielded 25 mA, no more than the early runs!
But we continued to condition as cold as possible!
![Page 18: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/18.jpg)
18 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Improving our
Cesiation Procedure
•“Repeating 20-30 minutes at 500-
550C until having desired beam”
was very unsatisfactory.
• We learned to precisely control the
temperature at 550C and time
variations showed that 40 minutes
would most frequently produce the
desired results, although sometimes
it would take an hour.
20 min @ 550C
Cesium collar temperature
Cooling air shut off
Fine-tune duty-factor
•The beam always decreased
rapidly during the first shift. Only
cesiation ~10 hours after start up
would yield persistent beam.
Clearly, new ideas
are needed!
•Excess cesiations became an issue
because of excessive sparking
killed the chopper electronics.
60
40
20
00 5 10 15 hours
Avera
ge C
urr
ent
[mA
] 1st cesiation2nd cesiation
3rd cesiation
32 mA
19 mA
32 mA
11-26-05
10-20-07
![Page 19: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/19.jpg)
19 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
From the “saes getters” manual
830C
770C
•A continuous program of research at SAES Getters S.p.A. into means of controlling the release of alkali metals has led to SAES Alkali Metal Dispensers for the photo-tube industry. ….. •SAES alkali metal dispensers are particularly suitable for … following problems ..:
•Very pure alkali metal films are required•The rate of evaporation of the alkali metal has to be controlled at will•The rate of evaporation of the alkali metal must be reproducible
•All SAES alkali metal dispensers have… low gas emission due to:•The use of excess of ST101 nonevaporable getter alloy as a reducing agent for the alkali alloy which also sorbs, at the source, the gas generated in the reaction.
•The gases released from the SAES dispensers have been measured after having submitted them to a typical bake-out process simulating the conditions in which the photo tubes are normally processed. …. about 1 cc torr/cm, mostly hydrogen.
•SAES alkali metal dispenser are normally current controlled. SAES suggest to ramp up the current by 0.1A/min, or about over ~1 hour period. •The Cs emission threshold is at 4.70.2A (standard deviation) 620 20C
1. Temperature not a major concern as excess ST101 pumps residual gas!
2. Ramping temperature degasses the sintered Cs2CrO4/ST101 powder!
3. Time variations have to be expected! Cs Indicator needed!
![Page 20: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/20.jpg)
20 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
25 sccm H2 started 2 MHz @ 50kW,10 Hz,0.4ms
550C13 MHz @ 250 W
CO2
H2O
N2 & CO
O2
H2
Ar
60C
150C
200C
250C
1. Start Hydrogen flow ASAP!
2. Ramping the Cs collar temperature to ~300C beneficial!
90C
Pump 1 off
300C
2 MHz @ 50kW,30 Hz,0.5ms
2 MHz @ 50kW,60Hz,0.5ms
350CPlasma
out
HV on Start of Cs
evaporation
3. H2O not a good Cs indicator!
The staged conditioning & cesiation test
![Page 21: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/21.jpg)
21 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Cs collar at 250C
Cs collar at 550C
Fine tuning
duty-factor
40
30
20
10
0
Pe
ak
Cu
rre
nt
[mA
]
50 kW
36 kW
65 kV
Lens-1 Current
0 1 2 hrs.
Cs indicators:
12-24-07
The release of Cesium is indicated in order of increasing reliability by
1. Drop in H2O partial pressure
2. Arcing of 65 kV supply
3. Increase of 65 kV load current
4. Arcing of lens 1 5. Increase of load
current of lens-16. Increase in beam
current
What are we observing?
Therefore we cesiate with beam-on whenever possible. This has added invaluable insight into the process!
When RFQ not available, or 65 kV arcing excessively, we resort occasionally to observing the lens 1-current. The lens-1 current is less reliable because it can change for other reasons, and not all
of them are understood.
![Page 22: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/22.jpg)
22 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
First Cesiations:
•The persistence of the first
cesiation is normally poor. It
starts to level off after a few
hours at a much lower level.
Final conditioning temperature
Cesiation tempera-
ture
Cs release after
starting cesiation
~50 C 500 C ~120 min.
~50 C 550 C ~60 min.
250 C 550 C ~10 min.
350 C 550 C ~5 min.
There are some processes and/or work that need to happen at elevated temperature before the cesium cartridges start to release Cs.
Especially when the temperature is not ramped up during conditioning, the Cs release is delayed by some significant time.
The time delay depends on collar temperature during conditioning and the RF power. It exhibits a significant spread.
60
40
20
00 5 10 15 hours
Avera
ge C
urr
ent
[mA
] 1st cesiation2nd cesiation
3rd cesiation
32 mA
19 mA
32 mA
10-20-07
![Page 23: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/23.jpg)
23 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Subsequent Cesiations:
60
40
20
00 5 10 15 hours
Avera
ge C
urr
ent
[mA
] 1st cesiation2nd cesiation
3rd cesiation
32 mA
19 mA
32 mA
10-20-07
Once Cs has been released from the cartridges no more prolonged heating is required. Additional cesium is released by simply increasing the cartridge temperature to ~500C.
Subsequent cesiations reach normally higher peak values but also with a limited persistence.
After a few hours the performance levels out on a higher level than before.
![Page 24: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/24.jpg)
24 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Asymptotic
Cesiations:
To understand the ultimate performance that can be achieved with cesiations, we cesiated almost every day during a 2-week run on the test stand!
Most recesiation consisted of heating the Cs collar to 500and keeping it there for 2-3 minutes.
Recesiations increased the beam current and, assisted by a reduction of H2 flow, added up to ~30% to the previous 48 mA. Alternatively, we reduced the RF by ~30% to maintain ~50 mA. Over the next few hours the excess current dropped off ~exponentially, or alternatively we restored the RF to maintain the 50 mA. In less than 10 hours, the beam production returned to the previous ~48 mA with ~50 kW. Obviously at least 2 kind of persistences!
0 5 10 15 hours
60
50
40
30
20
10
0Ave
rag
e C
urr
en
t [m
A]
50 kW
40 kW
50 kW
48 mA 48 mA
11-29-07
12th cesiation
on day 13
8.5 hours
![Page 25: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/25.jpg)
25 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
So, what appears to be happening?
There are surface states where the Cs atoms are strongly bound and therefore resist sputtering.
Initially a fraction of those states are occupied by absorbed residual gas and or contaminates. As those are sputtered away and replaced by Cs atoms, the highly persistent beam output increases.
There are other surface states, where the Cs atoms bond with less energy, and therefore easily sputter, showing a poor persistence.
65 kV
Lens-1 Current
34.3 kW
5 10 15 hrs. after Cs
~25 mA
~24 mA
40
30
20
10
0
Peak C
urr
en
t [m
A]
12-25-07
This performance level can be increased by up to 30% if there is a steady flux of Cs replacing the sputtering losses. Such a flux could be established with an external Cs reservoir, a hot Cs-collar, and/or excessive cesiations.
Combining ramping up the collar temperaturewith the typical 1 hour cesiation time yielded a heavy cesiation with very high persistence!
Once fully established, the base performance level requires only rarely re-cesiations.
![Page 26: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/26.jpg)
26 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
So, What is the IDEAL Procedure?
The ideal conditioning procedure
Pump down Add 25 sccm hydrogen when p<10-4 Torr After a while rapidly ramp up RF to desorb residual
gas and sputter clean Cs collar outlet aperture while– Letting Cs collar outlet aperture get as hot as possible– Ramp the cesium cartridges temperature to ~200
XX minutes before cesiation – Ramp the cesium cartridges temperature to 400 C
Cesiation– Turn on cooling air to Cs collar outlet aperture– Shut off cooling air to Cs collar– Raise Cs collar to ~550 C– Use time to dose Cs– Turn on cooling air
Next 10 hours– Maintain Cs collar at XXX C to maintain a small Cs flux
However, we do not have separate temperature controls for the Cs collar and its outlet aperture. A compromise is needed!
![Page 27: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/27.jpg)
27 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Content
Overview
Milestone Diagnostic Problems & Solutions
The 2007 LEBT Sparkfest
The LBNL Cs System and its Operation
The Beam Current Challenge
The Plans
![Page 28: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/28.jpg)
28 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
The SNS Power Ramp Up:
Can the SNS ion source and LEBT provide the required MEBT beam currents at the rep rates and pulse lengths given by the ramp-up plan?
=Average Mini Pulse Current
(Source Pulse Length) = (LINAC Pulse Length) + 0.2 ms
= LINAC Pulse Length
![Page 29: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/29.jpg)
29 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
7-7-06 7-21-06 8-4-06 8-18-06 9-01-06
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
40
30
20
10
0
Avera
ge B
eam
Curr
ent [m
A]
7-7-06 7-21-06 8-4-06 8-18-06 9-01-06
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
40
30
20
10
0
Avera
ge B
eam
Curr
ent [m
A]
40
30
20
10
0
Avera
ge B
eam
Curr
ent [m
A]
The 20 mA Challenge: (=13.6 mA average chopped)
Production Run 2006: Inflated RF and
Short Pulse Length > Plenty Current
1-14-07 1-28-07 2-11-07 2-25-07 3-11-07 3-25-07 4-28-07
80
60
40
20
02
MH
z P
ow
er [k
W]
40
30
20
10
0
Ave
rag
e B
eam
Curr
en
t [m
A]
1-14-07 1-28-07 2-11-07 2-25-07 3-11-07 3-25-07 4-28-07
80
60
40
20
02
MH
z P
ow
er [k
W]
80
60
40
20
02
MH
z P
ow
er [k
W]
40
30
20
10
0
Ave
rag
e B
eam
Curr
en
t [m
A]
40
30
20
10
0
Ave
rag
e B
eam
Curr
en
t [m
A]
6-4-07 6-18-07 7-02-07 7-16-07 7-30-07 8-13-07 8-27-07 9-10-07
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
40
30
20
10
0A
vera
ge B
eam
Curr
ent [m
A]
6-4-07 6-18-07 7-02-07 7-16-07 7-30-07 8-13-07 8-27-07 9-10-07
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
40
30
20
10
0A
vera
ge B
eam
Curr
ent [m
A]
40
30
20
10
0A
vera
ge B
eam
Curr
ent [m
A]Run 2007-2: Sparking LEBT
> Current no issue
Run 2007-3: Learn making 20 mA with
maxed-out RF
With maxed-out RF, the beam power
depends on Ion Source mood swings, etc.
It is better to use less RF for producing
the 25 mA for Run 2008-1.
8-29-07 8-31-07 9-2-07 9-4-07 9-6-07 9-8-07
160
140
120
100
80
60
40
20
0
Beam
Pow
er
[kW
]
8-29-07 8-31-07 9-2-07 9-4-07 9-6-07 9-8-07
160
140
120
100
80
60
40
20
0
Beam
Pow
er
[kW
]
Power on Target for last 2007-3 Production
Need to increase efficiency!
Need to reduce inefficiencies!
9-14-06 10-5-06 10-26-06 11-16-06 12-07-06
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
40
30
20
10
0
Avera
ge B
eam
Curr
ent [m
A]
9-14-06 10-5-06 10-26-06 11-16-06 12-07-06
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
40
30
20
10
0
Avera
ge B
eam
Curr
ent [m
A]
40
30
20
10
0
Avera
ge B
eam
Curr
ent [m
A] Run 2007-1:Longer Pulse Length
> Current marginal
> Test RF
![Page 30: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/30.jpg)
30 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
The p+ac-Man Problem!
0
200
400
600
0 10 20 30Particle energy [eV]
Cro
ss s
ecti
on
[10
-16cm
2]
p++ H¯ = H + H*Electronic detachment:
H + H¯ = H2() + eIn cold plasmas losses are dominated by mutual neutralization ( =70 Gb for Tp+ 0.5eV). After a path length x through a proton density np+, the number of surviving H¯ ions is :NH¯ = N0e
-nx, or for np+= 51013 cm-3, only about ⅓ survive a path length of x=(np+)-1 0.3 cm ⅛”!
Mutual neutralization:
Associative detachment:
e + H¯= 2e + H
The p+ac-Man problem can be reduced by producing the H¯ions as close as possible to the outlet aperture so they can get out before being caught by the hungry p+.
H¯ ions are mainly destroyed by 3 mechanisms:
H- surface production is most effective on a surface surrounding the outlet aperture that is facing the plasma, and that can be kept at optimal temperture!
p+
H¯
From LINAC’06
![Page 31: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/31.jpg)
31 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
1.2 mm
LBL assembly drawing
The LBNL assembly drawing shows a 1.2 mm gap between the cesium collar outlet and the source outlet.
The Cesium Collar Position Issue:
1 mm
ORNL quick fix 9-28-07
The two aperture were brought closer together with 4-mm thick, conical Cs collar outlet apertures.
Pro-B&P
3.2 mm
LBL stacked parts
Correctly fabricated and assembled LBNL parts leave a 3.2 mm gap.
Refabricating the Cs collar takes many weeks and ~5k$/collar.
On test stand, a 304 SS aperture yields 38 mA with 40 kW of 2 MHz; a Mo aperture yields 40 mA with 29 kW, 90% more efficient than any previous LBNL source at 60 Hz.
![Page 32: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/32.jpg)
32 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
The Cs collar position, a hidden variable?
The Cesium collar is mounted to the outlet electrode with four 5-40 screws.
If two neighboring screws would be missing, and the collar is heated to 200 or 500C, the radial distance of the mounting holes grows by 0.06 – 0.2 mm. This causes a slight misalignment.
Hidden Good Source / Bad Source Variable???Unique, but not very robust engineering!
However, if all screws hold all legs in place, heating it to 200, 300, 500, or 550C will move the collar in axial direction by >1.5, >1.8, >2.4, or >2.5.
Depending on the initial, unintentional slight bends of the mounting legs, the Cesium collar moves either away from or towards the outlet aperture.
![Page 33: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/33.jpg)
33 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
The Cesium collar mitigation:
Mitigation include
meandering Cs collar mounting legs
backset mounts and bend legs to assure forward force
Ion Source configuration for run 2008-1
0.5 mm
Pro-B&P Pro-B&P
Design a outlet aperture with ceramic balls (blue) that guarantee a ~0.5 mm gap and centering in the groove of the outlet aperture.
This yielded 40 mA with 27 kW 2 MHz at 0.5 ms and 60 Hz on the test stand, an additional 7% increase in efficiency.
![Page 34: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/34.jpg)
34 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
In the 5 days before run 2008-1 three source configurations were tested on the Frontend before deciding on the ball-centered Cs collar outlet as workhorse for this run.
10-28-07 11-11-07 11-25-07 12-09-07 12-23-07
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
40
30
20
10
0
Avera
ge B
eam
Curr
ent [m
A]
10-28-07 11-11-07 11-25-07 12-09-07 12-23-07
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
80
60
40
20
0
2 M
Hz P
ow
er [k
W]
40
30
20
10
0
Avera
ge B
eam
Curr
ent [m
A]
40
30
20
10
0
Avera
ge B
eam
Curr
ent [m
A]
The 25 mA Challenge: (=17 mA average chopped)
Testing with
30 mA Bad Source
The 2nd source was bad, requiring ~50 kW.
Recent sources make 25 mA with <<40 kW.
12-27-07 12-29-07 12-31-07 1-2-08
180
160
140
120
100
80
60
40
20
0
Be
am
Po
we
r [k
W]
12-27-07 12-29-07 12-31-07 1-2-08
180
160
140
120
100
80
60
40
20
0
Be
am
Po
we
r [k
W]
Power on Target for New-Year Production Run
Operations has now a knob to keep the target power fixed, even when sub-systems struggle.
Broken
E-dump
The e-dump of the 3rd
source shortened out after several hours of stable operation. It was decided to run it with ~50 kW.
Every opportunity is used for testing!
![Page 35: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/35.jpg)
35 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
12-25/26-2007Testing 2008-2 requirements:
Red = Source Rep Rate = 60 Hz Purple = Gate Width = 0.7 msTeal = 2 MHz power = 29.5 -35.2 kWDark Yellow = Collar temp = 187CYellow = H2 flow 29 sccmBlue = BCM02 current Max >30 mABrown = Accel Voltage 69 kVLight green = Foc1 Current < 2 mA
>30 mA at 4.2% duty factor for >20 hours!
30 mA
![Page 36: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/36.jpg)
36 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Testing future requirements: 12-18-07 9:30-10:00
Light Brown = Source Rep Rate 60 Hz Light Green = Gate Width 0.6, 0.7, 1.0 msDark Yellow = 2 MHz power 70 kWTeal = Collar temp 50CBrown = H2 flow 35 sccmBlue = BCM02 current Max 40 mAGreen = BCM02 current Avg = problemPurple = Accel Voltage 69 kVRed = EDmp Voltage 2.3 kVYellow = Foc2 Voltage 58 kV
0.42-0.47 ms
4.2 % 4.2 %6 %
40 mA at 4.2% duty factor but less at 6%!
38 mA
![Page 37: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/37.jpg)
37 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Teal = Source Rep Rate 60 Hz Grey = Gate Width 0.7 msWhite = 2 MHz power 70 kWMagenta = Collar temp 45CGreen = H2 flow 32 sccmBlue = BCM02 current Max 40 mARed = BCM02 current Avg = problem Black = Accel Voltage 69 kVPurple = EDmp Voltage 2.2 kVOrange = Foc2 Voltage 57 kV 0.33-0.38 ms
Retesting future requirements: 12-24-07 00:00-04:00
3.8 hours of 38 mA at 4.2% duty factor!
38 mA
![Page 38: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/38.jpg)
38 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Content
Overview
Milestone Diagnostic Problems & Solutions
The 2007 LEBT Sparkfest
The LBNL Cs System and its Operation
The Beam Current Challenge
The Plans
![Page 39: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/39.jpg)
39 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Cs-Collar Outlet Aperture with heating / cooling air channel
Electrically insulating ceramic Balls
Replaceable Converter Insert
Adaptive Mounting Washer
The R&D Cesium collar outlet aperture
Producing 38 mA with 70 kW is too risky. We need a source configuration that can produce 38 mA MEBT current with 50 kW to allow for operation with not so good or bad sources. Therefore we need to continue our efficiency enhancing R&D!A good R&D source component has
A knob for each individual function that can be fine-tuned during operation for squeezing the last mA out of the source!
Screws, allowing the rapid replacement of configuration critical elements!
We are fabricating a Cs-collar outlet aperture that has replaceable converter inserts, and temperature- and voltage-controls independent of the cesium collar and the source outlet. This will allow for optimal geometry and conditions during conditioning and operations!
![Page 40: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/40.jpg)
40 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
The R&D Cesium collar outlet aperture
Pro-B&P
Pro-B&PPro-B&P
Pro-B&P
![Page 41: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/41.jpg)
41 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Slide 5 from the PUP Review September 21-22, 2005:
![Page 42: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/42.jpg)
42 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
0.0
10.0
20.0
30.0
40.0
50.0
60.0
0 20 40 60 80
RF Power (kW)
H-
Cu
rre
nt
(mA
)
uncesiated
cesiated
Alternatives: External Cesium Reservoir
Ionization Cone
Cs injection collar
Outlet Aperture
Air duct
Cs Line
Extractor electrode
ions
• Baseline Cs2CrO4system limits source lifetime or beam current
• Proven Fermilab reservoir (lifetime: 0.5-1 year) & enhanced geometry
• 65 mA,1.2 ms, 10 Hz with internal antenna• 50 mA, 0.75 ms, 30Hz with ext. ant. source
(Tres~110C)
External Cs oven
(Fermilab)
Test stand:
cesiated
1.2 ms, 10 Hz
uncesiated
(Courtesy of R. Welton)
LBNL-TS
60 Hz
No screws!Too many knobs!
![Page 43: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/43.jpg)
43 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Alternatives: Snap-in Cones
• Higher work function materials yield lower
work functions when coated with Cs:
•SS-1.67 eV
•Mo-1.60 eV
•Ni-1.47 eV (also shields magnetic field)
•Pt-1.4 eV
•Re-1.5eV (10x surface area)
• Baseline collar modifications• Allows Cs supply and Cs collection
surface to operate at different temps• Brings ion surface very close to outlet• Centers and fixes position of collar• On FE brief demonstration of 30mA with
33kW and a 15% larger outlet area
(Courtesy of R. Welton)
Comments: -Compare to 30 mA with 29.5 kWwith the ball-centered outlet aperture with original 7 mm outlet . -Temperature cannot be varied
Promising Future Options!
![Page 44: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/44.jpg)
44 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Al2O3 insulator
Anode
Cooling channel
Plasma
stream
Cathode Ions
Prototype External Antenna Source and Plasma Gun Courtesy of R. Welton
Long-Pulse External Antenna Sources
• Multi-year lifetime - DESY (low duty-factor)
• Plasma gun found to enhance H- up to ~50%
• 50 mA – 1.2 ms pulses achieved at 10Hz –unacceptable pulse droop.
Large Volume External Antenna Source
• Excellent pulse shape: 38 mA, 0.750 ms, 30 Hz pulses produced using baseline and external Cs systems.
• ~25mA delivered over a week period at low-Cs flow & ~40 kW (LEBT arc counting) using external Cs system
• Alumina chamber failed at 45 Hz, 1.2 ms, 60 kWTwo layer antenna
Alumina
Water jacket
Space for
confinement
modules
AlN Source
• Heat transfer / thermal stress calculations show this AlNchamber can handle 100kW at 7% duty-factor with a factor of 2 safety margin
• Being tested on test stand1-9-08
45mA
30kW
60Hz85min
![Page 45: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/45.jpg)
45 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
The Helicon H-Ion Source and Test Facility
SNS External
Antenna H-
Source
ions
FED Helicon
Plasma
Generator
Combines the highly developed VASMIR helicon plasma generator (FED) and ORNL-LBNL H- ion source – funded by ORNL-LDRD
Plasma generator proven to produce ~10x higher plasma density using ~10x lower RF power
Restarted helicon test facility in bldg. 7625 in the FED: 1st plasma 2-23-07
Operated plasma generator at densities comparable to earlier operations (~1500 W, 13.56 MHz) - Currently retrofitting SNS H-
source in Bldg. 7625
Courtesy of R. Welton
![Page 46: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/46.jpg)
46 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
The LEBT Upgrade: A 2-solenoid LEBTTo improve robustness, we design a 2-solenoid LEBT that uses mostly existing equipment.
•After moving the ion source with the LEBT vacuum chamber, the chopper can run near ground potential.
•Being a novel combination, it needs to be tested on the test stand!
•Two solenoids yield a robust beam transport.
•Differential pumping and a gate valve help the RFQ.
•Diagnostics allows for full power source testing.
•This combines a working chopper with a proven high-power LEBT design.
RFQ
LEBT chamber with chopper
reentrant ion
source
Existing
Front End
Ground break
RFQ
Existing
chamber
with
source
near ground
chopper & steerers
diagnostics, pumping,
gate-valve,& steering
Exit steerers
Solenoids are currently being designed in-house!
![Page 47: Ion Source and LEBT Performance and Plans08'Stockli.pdf · Electron suppressor Collector-Suppressor Concerns about accurate beam measurements drove LBNL to design a special Faraday](https://reader030.vdocuments.us/reader030/viewer/2022040402/5e7ff9e68f47e851ff077df7/html5/thumbnails/47.jpg)
47 Managed by UT-Battellefor the Department of Energy AAC’07”Stockli
Conclusions