investing in reliability - northwesternenergy.com sky upgrade: northwestern is in the homestretch of...

2
Big Sky is one of the fastest growing areas of Montana. Commercial and residential growth in Big Sky is under way and the demand for electricity to serve businesses, residents and visitors is increasing significantly. NorthWestern Energy is working to keep abreast of the growth and anticipate future needs in this scenic portion of Montana. The Big Sky Community: NorthWestern currently serves about 4,200 electric customers in the Big Sky area. Customers include single residential and multi-unit housing, light commercial, the Big Sky and Moonlight Basin ski resorts, and several large, private residential and ski areas, including the Yellowstone Club and Spanish Peaks developments. Based on current growth patterns and plans announced by a number of these entities, NorthWestern expects to see higher-than-average load growth in this area in the next decade. The Big Sky area is currently served by two 69 kV transmission lines, one stretching from the Jackrabbit substation west of Bozeman to the Meadow Village area, the other reaching Big Sky from Ennis. During times of heavy demand for electricity, typically in the winter months, an outage on either transmission line can leave the other unable to fully provide the electricity that Big Sky needs. In some conditions, extended outages, blackouts, safety issues and customer inconvenience could be the result. Jackrabbit-Big Sky Upgrade: NorthWestern is in the homestretch of a $45 million transmission upgrade focused on the 69 kV line from Four Corners to Meadow Village. The line is being upgraded to a 161 kV line, which more than doubles its capacity and will allow us to more reliably serve existing customers and allow for future demand growth. The line, which largely follows an existing route through the Gallatin Canyon, is scheduled to be complete in the fall of 2016. Investing in Reliability Big Sky Master Plan 2016 Photo by Chris Kamman

Upload: lykhuong

Post on 23-May-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

Big Sky is one of the fastest growing areas of Montana.

Commercial and residential growth in Big Sky is under

way and the demand for electricity to serve businesses,

residents and visitors is increasing significantly.

NorthWestern Energy is working to keep abreast of the

growth and anticipate future needs in this scenic portion

of Montana.

The Big Sky Community: NorthWestern currently

serves about 4,200 electric customers in the Big Sky

area. Customers include single residential and multi-unit

housing, light commercial, the Big Sky and Moonlight Basin

ski resorts, and several large, private residential and ski

areas, including the Yellowstone Club and Spanish Peaks

developments. Based on current growth patterns and plans

announced by a number of these entities, NorthWestern

expects to see higher-than-average load growth in this area

in the next decade.

The Big Sky area is currently served by two 69 kV

transmission lines, one stretching from the Jackrabbit

substation west of Bozeman to the Meadow Village area,

the other reaching Big Sky from Ennis. During times of

heavy demand for electricity, typically in the winter months,

an outage on either transmission line can leave the other

unable to fully provide the electricity that Big Sky needs.

In some conditions, extended outages, blackouts, safety

issues and customer inconvenience could be the result.

Jackrabbit-Big Sky Upgrade: NorthWestern is in the

homestretch of a $45 million transmission upgrade focused

on the 69 kV line from Four Corners to Meadow Village. The

line is being upgraded to a 161 kV line, which more than

doubles its capacity and will allow us to more reliably serve

existing customers and allow for future demand growth.

The line, which largely follows an existing route through

the Gallatin Canyon, is scheduled to be complete in the

fall of 2016.

Investing in ReliabilityBig Sky Master Plan 2016

Photo by Chris Kamman

November 2015

Assessing future needs: While increasing the amount of

electricity available in the area is straightforward, developing

a distribution system capable of reliably delivering it

to customers is not. The area is now served by two

substations, one in the Lone Mountain area and the other

in Meadow Village, along with a network of distributions

lines that provide power from the substations to homes

and businesses. To keep up with the growth of Big Sky,

NorthWestern’s electrical infrastructure in the area will need

to grow as well. We are currently assessing our existing

infrastructure in the Big Sky area and developing plans for

upgrades and additional new electrical infrastructure to

serve the area. As we do in all of the communities we serve,

NorthWestern Energy regularly performs short term and

long term engineering studies to determine our ability to

reliably serve our existing customers and meet the needs of

the community. We also work closely with elected officials,

community leaders and others to develop growth plans.

The short-range plan:

In addition to the completion of the JackRabbit-Big Sky

transmission line upgrade in 2016, NorthWestern Energy

has plans to upgrade the existing substations at Meadow

Village and Lone Mountain to provide additional capacity to

serve the area. These upgrades are expected to begin in

2016 and be complete in 2017.

A long-range plan:

Northwestern has developed an extensive

list of possible upgrades to its electric

transmission and distribution system in Big

Sky. The timeline for projects on the list

stretches from 2016 through 2030. During

this time frame, the demand for electricity

is expected to grow to nearly four times its

current level. The list of upgrades includes:

• The need for a third substation in the

mid-mountain area

• Upgrades to the transmission line from

Ennis to Big Sky

• Upgrades and additions to the distribution

network

• Upgrades to the transmission line between Lone Mountain

and Meadow Village

For more information about the Big Sky project,

please contact:

Community Contact:

Heather Bellamy

Manager, Community Relations

(406) 570-2092

[email protected]

Project Contact:

Tom Pankratz

Director, Major Projects

(406) 443-8950

[email protected]

Operations Contact:

Pat Patterson

Manager, Operations-Bozeman Division

(406) 582-4687

[email protected]