investigation of spot treatments for pockets of acidic mine...
TRANSCRIPT
Investigation of Spot Treatments for Pockets of Acidic Mine Water, Fire Road Mine Minto, NB
Atlantic Reclamation Conference NBCC MiramichiOctober 16th, 2018
1
The STOZA Corp. Team• Members
• Troy Dobson, EIT
• Andrew Floyd
• Zach McDougall, Dual MIT
• Otillia McLaughlin
• Spencer Wastle
• Mentors
• Dr. B. Broster, P.Geo
• Dr. J. Day, P.Geo P.Eng
• Gilman Violette, P.Eng
• Steven Rossiter, Dual MIT
• Dr. K. Butler, P.Geo P.Eng
• Dr. N. Susak, P.Geo 2
UNB Geological Engineering Senior Design
Introduction
• Fire Road Mine opened in 1982
• ~50 000 tons of coal produced
• Coal extracted from seam ~0.5m thick
• Mine active for 4 years until pH levels declined to 3 and was subsequently shut down
• At end of operations, mine was ~120 ha and disturbed area totalled ~300 ha
• Currently being treated with a hydrated lime 3
UNB Geological Engineering Senior Design
Introduction• Geological Background
4
UNB Geological Engineering Senior Design
Introduction
• Acid mine drainage
• Acidic water created by the reaction of sulphide minerals when exposed to air and water
• Naturally formed in common sulphide minerals
• The oxidation of pyrite is the most common producer of acid mine drainage due to its high sulphur content
5
UNB Geological Engineering Senior Design
Problem Statement
• The purpose of this design report is to investigate possible in situ solutions for areas of high acidity, and perform a cost analysis of the possible solutions.
6
UNB Geological Engineering Senior Design
• Conduct a site visit to collect
field data and evaluate site
conditions.
• Examine possible in situ
solutions to treat localized
areas of high acidity
• Quantify and incorporate
these solutions with the
current site treatment plan
• No surficial disturbance
• Must be within current solution parameters
• Not interfere with the hydrogeological dynamics
• Work within seasonal constraints on the mine site
• Complete work within the outline of the team schedule
7
Requirements Constraints
UNB Geological Engineering Senior Design
Field Work • November 4th, 2017
• Electromagnetic geophysical survey using an EM31
• Remarked the geophysical survey lines for reproducibility
• Water level, temperature and conductivity measurements
• 4 water samples collected from standing water on site
• 2 soil samples from problematic areas (wells 3 & 17)
• 1 soil sample from non-problematic area (well 27)
• November 17th, 2017
• Slug testing 10 wells chosen based on pH data from GEMTEC reports
• Delineating standing water on site
8
UNB Geological Engineering Senior Design
Field School Spring 2018
UN
B G
eolo
gica
l En
gin
eeri
ng
Sen
ior
Des
ign
9
• Follow up EM-31 and ERI surveys were completed in April 2018
• ERI – Electrical Resistivity Imaging an array of electrodes connected to a central power supply measures voltage drop across electrodes to create a pseudo cross-section.
• Data is subsequently inverted with software and user defined parameters to create a geologically reasonable cross-section
• Very different groundwater conditions with extensive standing water and high volume recharge of clean meteoric water
Geophysical Analysis• The geophysical survey was done using
a Geonics EM-31 Ground Conductivity Meter, a Juniper Systems Data Logger and a Garmin GPS.
• A total of 7 surveys lines were conducted over the anomalous area of high acidity.
• Standing water delineated with Garmin GPS
• Used for comparison of previous geophysical work
10
UNB Geological Engineering Senior Design
Geophysical Analysis Suite
11
• 2014: Peak of 42 mS/m
• 2017: Peak of 40 mS/m, similar anomaly size, smaller maximum
• Site continues to improve over time
STOZA Corp November 4th, 2017 survey area
UNB Geological Engineering Senior Design
Geophysical Analysis Suite
12
• Standing water shows no correlation with areas of high apparent conductivity
• Peak near Well #17
• Soil samples taken from anomalously high apparent conductivity zones
UNB Geological Engineering Senior Design
Field School Spring 2018, EM-31
UN
B G
eolo
gica
l En
gin
eeri
ng
Sen
ior
Des
ign
13
• Results replicated in different environmental conditions across the site.
• Peak value around 40mS/m
• Maximum conductivity centered around well 17
Field School Spring 2018, ERI
UN
B G
eolo
gica
l En
gin
eeri
ng
Sen
ior
Des
ign
14
Bench Scale Experiment
15
A bench scale testing program was conducted to develop a solution to treat the areas of anomalously high acidity
Choice of solutions based on:• Locally sourced• Economically viable• Previous success with
treating acid mine drainage (AMD)
The proposed treatments included• Biosolids - WWTP• Seafood compost - Envirem Organics Inc.• Hydrated lime sludge
UNB Geological Engineering Senior Design
Bench Scale Experiment
16
• Same volume of soil was used for each column
• Same volume of solution was used for each column
• The experiment ran for 3 weeks
• 140 mL of water weekly
• Water collected on a fixed schedule
UNB Geological Engineering Senior Design
Bench Scale Experiment
17
UNB Geological Engineering Senior Design
Bench Scale TestingThe following tests were performed throughout and at the end of the bench scale experiments:
• pH
• Water chemistry analysis
• Trace element and total dissolved solids analysis outsourced to Research and Productivity Council (RPC)
• Soil chemistry analysis
• Portable X-Ray Fluorescence (PXRF) 18
UNB Geological Engineering Senior Design
Bench Scale - Water Chemistry
19
0
1
2
3
4
5
6
7
8
0 0.5 1 1.5 2 2.5 3 3.5
pH
Time (Weeks)
pH Analysis from Bench Scale Test
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
0 0.5 1 1.5 2 2.5 3 3.5TD
S (M
g/L)
Time (Weeks)
Total Dissolved Solids from Bench Scale Test
UNB Geological Engineering Senior Design
Bench Scale - Water Chemistry
20
Comparing Trace Elements of Problematic Soil to Treatments at Week 3
Element
Problematic Soil -Seafood Compost
Problematic Soil -Hydrated Lime
Problematic Soil -Biosolids
Removed(ppm)
Added(ppm)
Removed(ppm)
Added(ppm)
Removed(ppm)
Added(ppm)
Aluminium - 3.71 - 2.53 0.31 -Boron 0.15 - 0.25 - 0.21 -Cadmium 0.10 - - - - -Calcium 430.00 - 407.00 - - 31.00Copper 73.01 - 73.61 - - 4.50Iron 1653.80 - 1469.00 - 150.00 -Lead 3.70 - 3.73 - - 0.67Lithium - - - - 0.10 -Magnesium 32.30 - 28.50 - - 1.30Manganese 9.10 - 4.74 - 1.20 -Nickel 2.20 - 2.21 - 0.82 -Potassium 63.30 - 63.80 - 18.10 -Sodium - 81.00 38.80 - - -Strontium 0.52 - 0.49 - 0.15 -Zinc 190.93 - 189.07 - - 14.00
Note: Detection limit for analysis was in ppb. To be considered for added and removed columns, the ion's concentration must be greater than ±0.1 ppm to be significant.
• Water chemistry tested by RPC using Inductively Coupled Plasma Mass Spectrometry (ICP-MS)
• Columns are a comparison of elements in the problematic soil sample minus the elements in each of the solutions
UNB Geological Engineering Senior Design
Bench Scale - Water Chemistry
21
• Absolute concentration of metal ions reported in each solution at Week 3
0 100 200 300 400 500 600 700 800 900 1000
Al
Fe
K
Ca
Pb
Mg
Mn
Zn
Concentrations (ppm)
Effluent Water Chemistry Comparison
Seafood Compost Hydrated Lime Sludge Control
Fe ≈ 1680 ppm
Problematic Soil
UNB Geological Engineering Senior Design
Bench Scale - Soil Chemistry
22
0
10000
20000
30000
40000
50000
60000
70000
80000
Al Fe K S Si
Co
nce
ntr
atio
n (
pp
m)
Problematic Soil Pre and Post Leaching
Pre Leach Post Leach
• PXRF data from the problematic soil pre- and post-leaching• Post-leaching shows lower concentrations of elements as they have been
mobilized and carried out by the waterUNB Geological Engineering Senior Design
Bench Scale - Soil Chemistry
• PXRF data comparing the soil columns of the solutions to the problematic soil
• Post-leaching shows an improvement in soil chemistry as a higher concentration of elements remained in the soil with treatment
23
0
10000
20000
30000
40000
50000
60000
70000
80000
Al Fe K S Si
Co
nce
ntr
atio
n (
pp
m)
Problematic Soil and Solutions Post Leach
Problematic Soil Pre Leach Problematic Soil Post Leach Hydrated Lime Sludge Post Leach
Biosolid Soil Post Leach Seafood Compost Soil Post Leach
UNB Geological Engineering Senior Design
Hydrogeology Models
• 3D Surface Topography
• Water table topography (unconstrained)
• Vector plots
• 1st Derivative water table plots
24
UNB Geological Engineering Senior Design
3D Surface Topography Map
1:6400
250m 100m 200m 300m
Water table elevation set at 125m above CGVD2013 (Geodetic Sea level)
UNB Geological Engineering Senior Design
Water Table Topography
Contours marked at 1m elevation change.
26
N
EUTM NAD 83 NB Stereographic
UNB Geological Engineering Senior Design
125m
Flow Direction
Water table slopes assuming homogeneous site conditions.Significant shallowing in troubled regions.
UTM NAD 83 NB Stereographic
27Em/m
N
UNB Geological Engineering Senior Design
1st Derivative Water Table
Visualizes the change of the water table slope. Colour variation showing greatest rate of change in slope.
UTM NAD 83 NB Stereographic
28E
N
UNB Geological Engineering Senior Design
Conclusions • The goal of the project was to find a viable
solution that is economically feasible and can be locally sourced.
• Seafood compost is the best practical spot treatment based on its results in the bench scale tests and the analysis of the data collected in the field.
• Slope of the water table is relatively flat at the two hotspots, allowing direct application of solution to soil.
• The application method assumes vertical infiltration for spot treatment through permeable soil.
29
UNB Geological Engineering Senior Design
Cost Analysis
Costs Associated with Applying Seafood Compost Treatment to Problem Areas on Site
Apparent Conductivity
Cut-off for Area Calculation
(mS/m)
Area(m2)
Cost of Compost $10/ton
($)
Cost of Hauling
$21.08/ton($)
Cost of Equipment
($)
Total Cost($)
12 24800 $37,855 $79,798 $1,118 $118,770
20 9427 $14,390 $30,334 $732 $45,456
26 1796 $2,741 $5,778 $539 $9,057
30
UNB Geological Engineering Senior Design
Solution Source Locations
31
Fire Road Mine
Envirem Compost
Bio-solids
UNB Geological Engineering Senior Design
Environmental Considerations • In terms of the addition of seafood compost.
• Pros:
1. Aids vegetation growth
2. Create a stable organic soil horizon
3. Prevention of future soil erosion
4. Reduce the amount of water infiltrating in the ground
• Cons:
1. Slight odour
2. Increased presence of rodents, birds, and deer to the site
32
UNB Geological Engineering Senior Design
Recommendations
• Conduct a hydrogeological investigation to assess the possible water escape along the hanging wall
• Assess the drainage ditch to ensure its efficiency to prevent possible groundwater stagnation in problem areas on site
• Further geochemistry and vertical permeability assessments to confirm the viability of the proposed seafood compost solution
33
UNB Geological Engineering Senior Design
ReferencesMonenco Consultants Limited . (1991). Stabilization Plan for the Fire Road
Site . Fredericton, NB: Monenco Consultants Limited .
Monenco Consultants limited . (1991). Use of Chatham Coke Ash at the Fire
Road SIte . Fredericton, NB: Monenco Consultants Limited .
NB Coal Limited . (1996 ). Acid Mine Drainage Cover Options and Their
Considerations at the Fire Road Mine . Fredericton, NB : NB Coal Limited .
NB Coal Limited . (1997 ). Investigation of Metal Hydroxide Solubility from
SLudge in Acid Mine Drainage . Minto, NB: NB Coal Limited .
NB Coal Limited. (1996 ). Investigation on the Placement of Lime
Neutralization on Acid Generating Waste Rock . Minto, NB : NB Coal
Limited.
New Brunswick Power Coroporation Development Division . (1993 ).
Review Of Acid Mine Drainage at NB Coal Ltd.'s Fire Road Site .
Fredericton, NB : New Brunswick Power Coroporation Development
Division .
Phinney, K. (1987). Acid Mine Generation at NB Coal Ltd's Fire Road
Operation. Minto, NB.
Phinney, K. (1989). Reclamation Study Fire Road Minesite . Fredericton,
NB: K.D Phinney.
Piercey, S. e. (2014). Analysis of Powdered refrence materials and known
samples with a benchtop, field portable X-ray Fluorescence (pXRF)
spectrometer: evaluation of performance and potential applications for
exploration lithogeochemistry. The Geological Society of LOndon .
Ryan Leblanc, A. S. (2014 ). Environmental Characterization of the Fire
Road Coal Mine Using Hydrological and Geophysical Investogation
Techniques . Fredericton, NB: University Of New Brunswick .
Taylor, J. (1996). The Microbiology of Acid Mine Drainage.
Three - D Geoconsultants Limited . (1984). The Fire Road - Bog Camp
Road 1983-1984 Percussion Drilling Program . Fredericton, NB: Three - D
Geoconsultants Limited .
34
Al, T., & Butler, K. (2001). Environmental Geoscience, Acid mine
drainage in the Minto Coal Fields. Fredericton: Department of Geology.
Al, T., & Butler, K. (2001). Environmental Geoscience, Acid mine
drainage in the MInto Coal Fields. Fredericton: Department of
Geology.
GEMTEC . (1988). Surface and Groundwater Hydrology of the
Fire Road Mine Site . Fredericton: GEMTEC .
GEMTEC. (2014 ). Groundwater Sampling and Analysis June
2013, Former Fire Road Mine SIte . Fredericton : GEMTEC.
GEMTEC Consulting Engineers and Scientists. (2010).
Groundwater Sampling and Analysis June 2010, Fire Road Mine
Site . Fredericton, NB : GEMTEC Consulting Engineers and
Scientists.
Grace Dearbon Inc. . (1996 ). Evaluation of Options for the
Control of AMD Generation at NB Coal Ltd.'s Fire Road Mine
Site . Fredericton, NB : Grace Dearbon Inc. .
Ian Bragdon, K. H. (2014 ). Fire Road Coal Mine, NB AMD
Effects Assessment . Fredericton : University of New Brunswick .
Kawatra, S. K., & Eisele, T. C. (2001). Coal Desulfurization:
High-efficiency Preparation Methods. Taylor & Francis.
Kelsey Cheverie, L. E. (2014 ). 2014 Fire Road Mine Site
Preliminary Geochemical & Geophysical Report . Fredericton,
NB: Univeristy of New Brunsiwck .
LeBLanc, B. R. (2014). Geophysical & Geochemical
Investigation on Fire Road Mine ESCI 3713. Fredericton:
Univeristy of New Brunswick .
UNB Geological Engineering Senior Design
Acknowledgements
STOZA Corp. would like to thank Michele Coleman of NB power for the opportunity to work on this project, and to the mentors who have helped us throughout its duration.
• Dr. Broster
• Dr. Day
• Mr. Gilman Violette
• Dr. Butler
• Dr. Susak
• Steven Rossiter
35
UNB Geological Engineering Senior Design
Questions?
36