An Introduction to Scrum
• Tim McOwan• KashFlow Software
![Page 2: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/2.jpg)
Overview
• Case study & theory• Scrum principles• Roles, ceremonies & artifacts• Planning• Where next?
![Page 3: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/3.jpg)
Presentation Framework from
– Except:» Motivation theory slides» Salesforce.com» Exercises» Story Point estimating» Lean software development principles» Miscellaneous other slides
![Page 4: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/4.jpg)
We’re losing the relay race
Hirotaka Takeuchi and Ikujiro Nonaka, “The New New Product Development Game”, Harvard Business Review, January 1986.
“The… ‘relay race’ approach to product development…may conflict with the goals of maximum speed and flexibility. Instead a holistic or ‘rugby’ approach—where a team tries to go the distance as a unit, passing the ball back and forth—may better serve today’s competitive requirements.”
![Page 5: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/5.jpg)
• Scrum is an agile process that allows us to focus on delivering the highest business value in the shortest time.
• It allows us to rapidly and repeatedly inspect actual working software (every two weeks to one month).
• The business sets the priorities. Teams self-organize to determine the best way to deliver the highest priority features.
• Every two weeks to a month anyone can see real working software and decide to release it as is or continue to enhance it for another sprint.
Scrum in 100 words
![Page 6: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/6.jpg)
Scrum origins
• Jeff Sutherland
• Initial scrums at Easel Corp in 1993
• IDX and 500+ people doing Scrum
• Ken Schwaber
• ADM
• Scrum presented at OOPSLA 96 with Sutherland
• Author of three books on Scrum
• Mike Beedle
• Scrum patterns in PLOPD4
• Ken Schwaber and Mike Cohn
• Co-founded Scrum Alliance in 2002, initiallywithin the Agile Alliance
![Page 7: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/7.jpg)
Scrum has been used by:
• Microsoft• Yahoo• Google• Electronic Arts• High Moon Studios• Lockheed Martin• Philips• Siemens• Nokia• Capital One• BBC• Intuit
• Nielsen Media• First American Real Estate• BMC Software• Ipswitch• John Deere• Lexis Nexis• Sabre• Salesforce.com• Time Warner• Turner Broadcasting• Oce• KashFlow Software
![Page 8: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/8.jpg)
Case Study:Salesforce.com
• Started 2001– 3 people in R & D– 4 releases per year
• 2006– 200+ in R & D– 1 release per year – late!
![Page 9: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/9.jpg)
2000 2001 2002 2003 2004 2005 2006
Features Delivered per Team
Days between Major Releases
![Page 10: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/10.jpg)
Big Bang Scrum Application
• 1 late release 4 on time releases in 1 year• +94% feature requests delivered (+38% pro
rata)• + 61%reduction in mean time to release• 91% of customers believe quality has
improved / remained the same
![Page 11: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/11.jpg)
2000 2001 2002 2003 2004 2005 2006 2007
Features Delivered per Team
Days between Major Releases
Transformation Results
![Page 12: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/12.jpg)
Salesforce Tips
• Focus on principles over mechanics• Focus on automation• Provide transparency• When the heat is on stick to your guns• Experiment, be patient and expect to
make mistakes
![Page 13: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/13.jpg)
86of respondents are having the “best time” or a
“good time” at Salesforce
%* Improved from 40% 15 months ago
![Page 14: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/14.jpg)
Motivation Theory – Job Design
![Page 15: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/15.jpg)
Motivation Theory – Psychological Contract
![Page 16: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/16.jpg)
Scrum has been used for:
• Commercial software• In-house development
• Contract development
• Fixed-price projects
• Financial applications
• ISO 9001-certified applications
• Embedded systems
• 24x7 systems with 99.999% uptime requirements
• the Joint Strike Fighter
• Video game development
• FDA-approved, life-critical systems
• Satellite-control software
• Websites
• Handheld software
• Mobile phones
• Network switching applications
• ISV applications
• Some of the largest applications in use
![Page 17: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/17.jpg)
Characteristics
• Self-organizing teams
• Product progresses in a series of month-long “sprints”
• Requirements are captured as items in a list of “product backlog”
• No specific engineering practices prescribed
• One of the “agile processes”
![Page 18: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/18.jpg)
The Agile Manifesto – a statement of values
Process and toolsProcess and toolsIndividuals and interactions
Individuals and interactions
over
Following a planFollowing a planResponding to change
Responding to change
over
Source: http://agilemanifesto.org
Comprehensive documentationComprehensive documentationWorking softwareWorking software over
Contract negotiationContract
negotiationCustomer
collaborationCustomer
collaborationover
![Page 19: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/19.jpg)
Project noise level
Simple
ComplexAnarchy
Complicated
Technology
Req
uir
em
en
tsFar from
Agreement
Close toAgreement
Clo
se t
oC
ert
ain
ty
Far
from
Cert
ain
ty
Source: Strategic Management and Organizational Dynamics by Ralph Stacey in Agile Software Development with Scrum by Ken Schwaber and Mike Beedle.
![Page 20: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/20.jpg)
Wasted Effort
Features and Functions Used in a Typical System
Standish Group Study Reported at XP2002 by Jim Johnson, Chairman
Always7%
Often13%
Sometimes16% Rarely
19%
Never45%
Rarely or Never Used: 64%
Often or Always Used: 20%
![Page 21: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/21.jpg)
Exercise
• Possible benefits (negatives) of Scrum to Our organisation
• Post-Its, 5 minutes
![Page 22: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/22.jpg)
Scrum
Cancel
Gift wrap
Return
Sprint2-4 weeks
Return
Sprint goal
Sprint backlog
Potentially shippableproduct increment
Productbacklog
CouponsGift wrap
Coupons
Cancel
24 hours
The Sprint Cycle
![Page 23: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/23.jpg)
Putting it all together
![Page 24: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/24.jpg)
Sprints
•Scrum projects make progress in a series of “sprints”
•Typical duration is 2–4 weeks or a calendar month at most
•A constant duration leads to a better rhythm
•Product is designed, coded, and tested during the sprint
![Page 25: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/25.jpg)
And….
• Regular “of value” releases• Does it really need to be done? What is the value? • Knowing the context
– So, knowing the trade-offs
• Collaborative• Communication
![Page 26: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/26.jpg)
Communication (Typical Model)
Send
![Page 27: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/27.jpg)
Communication (Shannon et al)
![Page 28: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/28.jpg)
Sequential vs. overlapping development
Source: “The New New Product Development Game” by Takeuchi and Nonaka. Harvard Business Review, January 1986.
Rather than doing all of one thing at a time... ...Scrum teams do a
little of everything all the time
Requirements
Design Code Test
![Page 29: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/29.jpg)
No changes during a sprint
•Plan sprint durations around how long you can commit to keeping change out of the sprint
Change
![Page 30: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/30.jpg)
Scrum framework
•Product owner
•ScrumMaster•Team
Roles
•Sprint planning•Sprint review•Sprint retrospective
•Daily scrum meeting
Ceremonies
•Product backlog•Sprint backlog•Burndown charts
Artifacts
![Page 31: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/31.jpg)
Scrum framework
•Sprint planning•Sprint review•Sprint retrospective
•Daily scrum meeting
Ceremonies
•Product backlog•Sprint backlog•Burndown charts
Artifacts
•Product owner
•ScrumMaster•Team
Roles
![Page 32: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/32.jpg)
Product owner
• Define the features of the product
• Decide on release date and content
• Be responsible for the profitability of the product (ROI)
• Prioritize features according to market value
• Adjust features and priority every iteration, as needed
• Accept or reject work results
![Page 33: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/33.jpg)
Product Owner
• What are their responsibilities?
• Post Its, 5 minutes
![Page 34: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/34.jpg)
The ScrumMaster
• Represents management to the project
• Responsible for enacting Scrum values and practices
• Removes impediments
• Ensure that the team is fully functional and productive
• Enable close cooperation across all roles and functions
• Shield the team from external interference
![Page 35: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/35.jpg)
Scrum Master
• What are their responsibilities?
• Post Its, 5 minutes
![Page 36: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/36.jpg)
The team
• Typically 5-9 people
• Cross-functional:
• Programmers, testers, user experience designers, etc.
• Members should be full-time
• May be exceptions (e.g. database administrator)
• Teams are self-organizing
• Ideally, no titles but rarely a possibility
• Membership should change only between sprints
![Page 37: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/37.jpg)
•Product owner
•ScrumMaster•Team
Roles
Scrum framework
•Product backlog•Sprint backlog•Burndown charts
Artifacts
•Sprint planning•Sprint review•Sprint retrospective
•Daily scrum meeting
Ceremonies
![Page 38: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/38.jpg)
Sprint planning meeting
Sprint prioritization
• Analyze and evaluate product backlog
• Select sprint goal
Sprint planning
• Decide how to achieve sprint goal (design)
• Create sprint backlog (tasks) from product backlog items (user stories / features)
• Estimate sprint backlog in hours
Sprintgoal
Sprintgoal
Sprintbacklo
g
Sprintbacklo
g
Business conditionsBusiness
conditions
Team capacityTeam
capacity
Product backlogProduct backlog
Technology
Technology
Current productCurrent product
![Page 39: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/39.jpg)
Sprint planning
• Team selects items from the product backlog they can commit to completing
• Sprint backlog is created
• Tasks are identified and each is estimated (1-16 hours)
• Collaboratively, not done alone by the ScrumMaster
• High-level design is considered
As a vacation planner, I want to see photos of the hotels.
As a vacation planner, I want to see photos of the hotels.
Code the middle tier (8 hours)Code the user interface (4)Write test fixtures (4)Code the foo class (6)Update performance tests (4)
![Page 40: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/40.jpg)
Sprint Planning
• Who has what responsibilities?
• Post Its, 10 minutes
![Page 41: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/41.jpg)
Sprint planning
• Talk : join in• What is done?• Ownership of estimates• Learning opportunity of context
![Page 42: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/42.jpg)
The daily scrum
•Parameters• Daily
• 15-minutes
• Stand-up
•Not for problem solving• Whole world is invited
• Only team members, ScrumMaster, product owner, can talk
•Helps avoid other unnecessary meetings
![Page 43: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/43.jpg)
Everyone answers 3 questions
•These are not status for the ScrumMaster• They are commitments in front of peers
What did you do yesterday?What did you do yesterday?11
What will you do today?What will you do today?22
Is anything in your way?Is anything in your way?33
![Page 44: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/44.jpg)
Work the board
• Update with real estimates• Highlight issues• Own the estimate if task taken• Whose board?
![Page 45: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/45.jpg)
Daily Scrum
• What are your responsibilities?
• Post Its, 10 minutes
![Page 46: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/46.jpg)
The sprint review
•Team presents what it accomplished during the sprint
•Typically takes the form of a demo of new features or underlying architecture
• Informal• 2-hour prep time rule
• No slides
•Whole team participates
• Invite the world
![Page 47: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/47.jpg)
Sprint retrospective
•Periodically take a look at what is and is not working
•Typically 15–30 minutes
•Done after every sprint
•Whole team participates• ScrumMaster
• Product owner
• Team
• Possibly customers and others
![Page 48: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/48.jpg)
Start / Stop / Continue
•Whole team gathers and discusses what they’d like to:
Start doingStart doing
Stop doingStop doing
Continue doing
Continue doing
This is just one of many ways to do a sprint retrospective.
![Page 49: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/49.jpg)
Retrospectives
• What are your responsibilities?
• Post Its, 5 minutes
![Page 50: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/50.jpg)
•Product owner
•ScrumMaster•Team
Roles
Scrum framework
•Sprint planning•Sprint review•Sprint retrospective
•Daily scrum meeting
Ceremonies
•Product backlog•Sprint backlog•Burndown charts
Artifacts
![Page 51: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/51.jpg)
Product backlog
•The requirements
•A list of all desired work on the project
• Ideally expressed such that each item has value to the users or customers of the product
•Prioritized by the product owner
•Reprioritized at the start of each sprint
This is the product backlog
This is the product backlog
![Page 52: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/52.jpg)
A sample product backlog
Backlog item Estimate
Allow a guest to make a reservation 3
As a guest, I want to cancel a reservation. 5
As a guest, I want to change the dates of a reservation.
3
As a hotel employee, I can run RevPAR reports (revenue-per-available-room)
8
Improve exception handling 8
... 30
... 50
![Page 53: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/53.jpg)
The sprint goal
•A short statement of what the work will be focused on during the sprint
Database Application
Financial services
Life Sciences
Support features necessary for population genetics studies.
Support more technical indicators than company ABC with real-time, streaming data.
Make the application run on SQL Server in addition to Oracle.
![Page 54: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/54.jpg)
Managing the sprint backlog
• Individuals sign up for work of their own choosing
• Work is never assigned
• Estimated work remaining is updated daily
• Any team member can add, delete or change the sprint backlog
• Work for the sprint emerges
• If work is unclear, define a sprint backlog item with a larger amount of time and break it down later
• Update work remaining as more becomes known
![Page 55: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/55.jpg)
A sprint backlog
TasksTasksCode the user interfaceCode the middle tier
Test the middle tier
Write online help
Write the foo class
MonMon8
16
8
12
8
TuesTues4
12
16
8
WedWed ThurThur
4
11
8
4
FriFri
8
8
Add error logging
8
10
16
8
8
![Page 56: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/56.jpg)
A sprint burndown chartH
ou
rs
![Page 57: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/57.jpg)
Hou
rs
40
30
20
10
0Mon Tue Wed Thu Fri
TasksTasksCode the user interfaceCode the middle tier
Test the middle tier
Write online help
MonMon8
16
8
12
TuesTues WedWed ThurThur FriFri4
12
16
7
11
8
10
16 8
50
![Page 58: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/58.jpg)
Does Scrum do everything?
• What should we be doing in any event?
• 5 minutes, Post Its.
![Page 59: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/59.jpg)
Lean Software Development
• Waiting– Queuing theory, steady state of arrival
• Task switching• Partially done or ‘stored’ completed work• Speed of fixing defects• Options
– Create many– Decide at last responsible moment
• Trade offs
Mary and Tom Poppendieck
![Page 60: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/60.jpg)
Scalability
• Typical individual team is 7 ± 2 people
• Scalability comes from teams of teams
• Factors in scaling
• Type of application
• Team size
• Team dispersion
• Project duration
• Scrum has been used on multiple 500+ person projects
![Page 61: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/61.jpg)
Planning
• Estimating
• Road map!
![Page 62: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/62.jpg)
Epics: A milestone (?) with many stories
User Stories
User Story
Conversations
Acceptance Criteria
![Page 63: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/63.jpg)
Epics
• Think of a recent Epic…• Good:
– 5 minutes, write some stories
• Choose a Story– Write the conversations– Write the acceptance criteria
![Page 64: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/64.jpg)
Estimating using Story Points
• Relative complexity• How long will story x take compared to
story y?• Still an estimate• More thorough than other methods• Takes into account productivity /
efficiency of the team
![Page 65: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/65.jpg)
1 SP
20 SP13 SP
8 SP5 SP3 SP2 SP
?100 SP40 SP
Relative complexity – the Bridge metaphor
![Page 66: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/66.jpg)
Simple Velocity
• 3 simple wooden bridges in 1 sprint– Velocity = 3 story points
• Alternatively:– 1 simple wooden bridge and 1 basic
concrete bridge– 1 covered wooden bridge
• Team velocity increases and decreases– New team members, change in
environment etc.
![Page 67: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/67.jpg)
Scrum Estimating
• Poker cards• Deliberately increases exponentially to take into
account:– More uncertainty with bigger tasks
• Debate and discuss• No back log item > 20• Sufficient estimating
![Page 68: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/68.jpg)
Scrum is not Magic
It is simple...
...but hard work...
...and sometimes painful!
![Page 69: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/69.jpg)
Dilbert’s World
![Page 70: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/70.jpg)
The art of the possible
• The impossible is…
Still impossible
Unless you are Tom Cruise .. and we
aren’t, although we are all taller than him!
![Page 71: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/71.jpg)
The art of the possible
• We do what we can» Not what we cannot
» We cannot do xyz
• OK, What can we do?
![Page 72: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/72.jpg)
Where to go next
• www.mountaingoatsoftware.com/scrum
• www.scrumalliance.org
• www.controlchaos.com
![Page 73: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/73.jpg)
A Scrum reading list
• Agile and Iterative Development: A Manager’s Guide by Craig Larman
• Agile Estimating and Planning by Mike Cohn
• Agile Project Management with Scrum by Ken Schwaber
• Agile Retrospectives by Esther Derby and Diana Larsen
• Agile Software Development Ecosystems by Jim Highsmith
• Agile Software Development with Scrum by Ken Schwaber and Mike Beedle
• Scrum and The Enterprise by Ken Schwaber
• User Stories Applied for Agile Software Development by Mike Cohn
• Lean Software Development by Mary & Tom Poppendieck
• Lots of weekly articles at www.scrumalliance.org
![Page 74: Introduction to Scrum](https://reader036.vdocuments.us/reader036/viewer/2022062703/554f986cb4c9057b298b45e9/html5/thumbnails/74.jpg)
What to take away
• Inspect and adapt!• What will I be doing
differently?• What do I plan to do in:
– Sprint planning?– Daily scrums?– Retrospectives?