![Page 1: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/1.jpg)
Updates on
POSCO SNG Project
![Page 2: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/2.jpg)
A World of Solutions
1
POSCO Gwangyang SNG Project
• 0.7 B NM3/yr SNG production
(500,000 mtpy)
• 5500 mtpd sub-bituminous coal
processed into syngas and
catalytically converted to methane
• 2 + 1 Gasification Trains
• Located adjacent to the POSCO
Gwangyang Steel Mill on reclaimed
land
• Groundbreaking 2Q2011,
Start-Up in 4Q2014
• First Gasifier set April 2013
![Page 3: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/3.jpg)
SNG Process Overview
7 Courtesy of POSCO
![Page 4: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/4.jpg)
• Feedstock Capacity & Specification : 5,500 mtpd (1.8 MM mTPY) Sub-Bituminous Coal
Selected Coals Feedstock
Range
Gross As Received (GAR) Total Moisture (as received) % 20-30
Air Dried Basis (ADB)
Intrinsic Moisture % 18.0
Volatile Matter % 32.0-38.0
Ash % 3-6
Fixed Carbon % 39.0-41.0
S % 0.2-1.0
Cl % 0.01-0.03
Ultimate Analysis Dried
Ash Free (daf)
HGI 40-42
S.E. gar (HHV) kcal/kg 5,150-5,350
S.E. gad (HHV) kcal/kg 5,500-5,735
POSCO SNG Project Feedstock
![Page 5: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/5.jpg)
Client : POSCO
Contractor : POSCO E&C (EPC Turnkey including PDP, FEED, & Commissioning)
Plant Capacity : SNG 500,000 ton/year
Coal Consumption : 2 Million ton/year
Construction Area : 400,000 m2
Project Period : 2009.11 ~ 2014.8 ( 58 months)
Project Cost : 1 Billion USD
Licensor : CB&I (Gasification) / Linde (AGR) / Haldor Topsoe (Methanation)
POSCO SNG Project
2009 2010 2011 2012
EPC
Contracts
(October)
Gasification
PDP Completion
(October)
Detailed Design
Completion
(March)
2013
Ground
Breaking
(June)
FEED
Completion
(July)
Commissioning
(January)
Commercial
Production
(December)
General Information
Project Schedule
-4-
![Page 6: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/6.jpg)
Groundbreaking in June 2011
June 2011
![Page 7: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/7.jpg)
Piling Start in Feb 2012
February 2012
![Page 8: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/8.jpg)
June 11, 2013
Syngas Cooler
![Page 9: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/9.jpg)
April 2, 2013
![Page 10: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/10.jpg)
Coal Storage Silos
April 8, 2013
![Page 11: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/11.jpg)
-10-
500,000 mtpy SNG 2+1 trains sub-bituminous coal
Site Photo
Sept. 30, 2013
![Page 12: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/12.jpg)
POSCO SNG Project
-11-
![Page 13: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/13.jpg)
POSCO SNG Project
-12-
![Page 14: Introduction to POSCO SNG Project - · PDF fileA World of Solutions 1 POSCO Gwangyang SNG Project • 0.7 B NM3/yr SNG production (500,000 mtpy) • 5500 mtpd sub-bituminous coal processed](https://reader034.vdocuments.us/reader034/viewer/2022050902/5ab9006a7f8b9ac1058d5106/html5/thumbnails/14.jpg)