1 INTRODUCTION AND OVERVIEW OF MANAGING ENVIRONMENTAL REGULATOR ASPECTS OF AIRPORT PROJECTS Darren Betters, Lehigh- Northampton Airport Authority Eric H. Buncher, Allegheny County Airport Authority Nicholas M. Clabbers, Kaplan Kirsch & Rockwell

Upload: others

Post on 26-Mar-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

1

INTRODUCTION AND OVERVIEW OF MANAGING ENVIRONMENTAL REGULATOR ASPECTS OF AIRPORT PROJECTS

Darren Betters, Lehigh-

Northampton Airport Authority

Eric H. Buncher, Allegheny

County Airport Authority

Nicholas M. Clabbers,

Kaplan Kirsch & Rockwell

Page 2: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

Airport planning basics – why does it matter and how does it

affect environmental review?

Federal environmental review for airport projects

New way to potentially avoid federal environmental review

2

TODAY’S SESSION

Questions, please!

Page 3: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

The sponsor’s strategy for the development of the airport

Usually a 20 (or more)-year look ahead

Master Plan is basis for Airport Layout Plan (ALP)

-- Airport Master Planning Guidance - FAA Advisory

Circular 150/5070-6BA

3

AIRPORT MASTER PLANS

Page 4: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

Graphic representation of future airport development

Opportunity to address relevant issues

Air service capacity and forecasting

Realistic schedule for project implementation

Financial plan

Framework for continuous planning process

Opportunity to engage public and stakeholders

4

MASTER PLAN – KEY COMPONENTS

Page 5: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

An Airport Layout Plan is a scaled drawing of existing and proposed land and facilities necessary for the operation and development of the airport

ALPs must be maintained in accordance with FAA requirements

-- FAA Order 5190.6B, FAA Airport Compliance Manual, Appendix R

5

AIRPORT LAYOUT PLANS

Page 6: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

ALPs may be conditionally or unconditionally approved by the FAA

The distinction between these approvals is important Approval is a federal action!

FAA funding of projects and approval for implementation

require unconditional ALP approval

6

AIRPORT LAYOUT PLANS, CONTINUED

Page 7: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

Definition of “airport property”

Federally obligated

Subject to regulation

Changes trigger FAA review or approval (in some instances)

and thus environmental review

More on that in a moment

Both a hammer and a shield

7

SIGNIFICANCE OF ALP IN ENVIRONMENTAL CONTEXT

Page 8: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

Establishes environmental policies and goals for the country

When the federal government takes an action that may have

environmental impacts, it must:

Take a hard look at the impacts

Provide information about environmental effects to decision-

makers and the public

Intent is to improve decision making

8

NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) OVERVIEW

Page 9: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

9

NEPA: THREE FORMS

Categorical Exclusion (CATEX)

Environmental Assessment (EA)

EIS

Page 10: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

Sponsor Planning

1

Notice of Intent

2

Scoping

3

Draft EIS/ EA

4

Final EIS/ EA and Record of Decision

5

10

NEPA PROCESS

Page 11: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

11

A SPONSOR’S ROLE

• Coordinate with

state and local

processes

• Watch for other

environmental

requirements –

especially state law

• Contracting with

consultant preparing

the EA/EIS

• Pre-NEPA strategy

• Scrutinize

purpose and

need

• Protect sponsor’s

objectives

• Coordinate

environmental review

with planning

Page 12: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

NEPA process is not a good place to be doing fundamental

planning

Alternatives need to be defined (and eliminated) in the

planning process (to consider cost, for example)

Use planning to set limits for the NEPA review (to identify

what you cannot do)

LESSONS LEARNED

Page 13: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

Not starting the NEPA process with unanswered planning

questions

Overlapping the NEPA and planning process

Developing a supportable purpose and need during the planning

process

Complete alternatives analysis during the planning process

Integrating environmental issues in the planning process

13

SMOOTH PLANNING/NEPA INTEGRATION

Page 14: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

FAA Reauthorization Act of 2018

14

POTENTIALLY AVOIDING NEPA: A NEW LEGAL FRAMEWORK

Pub. L. 115-254, 131 Stat. 1129

Page 15: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

FAA may not directly or indirectly regulate—

(1) the acquisition, use, lease, encumbrance, transfer, or

disposal of land by an airport owner or operator;

(2) any facility upon such land; or

(3) any portion of such land or facility.

15

NEW PROHIBITION ON REGULATING AIRPORT PROPERTY

EXCEPT…

Page 16: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

This prohibition does not apply to:

(1) any regulation ensuring –

(A) the safe and efficient operation of aircraft or safety of people and property

on the ground related to aircraft operations;

(B) that an airport owner or operator receives not less than fair market value …; or

(C) that the airport pays not more than fair market value … .

(2) Any regulation imposed with respect to land or a facility acquired or

modified using Federal funding; or

(3) Any authority contained in –

(A) A Surplus Property Act instrument of transfer, or

(B) Section 40117 of title 49, United States Code [PFCs]

16

EXCEPTIONS

Page 17: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

(c) Rule of Construction –

Nothing in this section shall be construed to affect the

applicability of [revenue use restrictions in] sections 47107(b)

and 47133 …

17

SECTION 163(c): RULES OF CONSTRUCTION

Page 18: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

FAA now only has authority to review and approve ALP changes that:

materially impact the safe and efficient operation of aircraft at,

to, or from the airport or

would adversely affect the safety of people or property on the

ground adjacent to the airport as a result of aircraft operations, or

adversely affect the value of prior Federal investments to a

significant extent;

18

LIMITS ON ALP APPROVALS

Page 19: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

ALP amendments now require examination of the impact on the FAA’s three

“zones of interest.” Does the change:

• materially impact the safe and efficient operation of aircraft at, to, or from the

airport?

• adversely affect the safety of people or property on the ground adjacent to the

airport as a result of aircraft operations?

• adversely affect the value of prior Federal investments to a significant extent.

If not, FAA has no jurisdiction or authority to approve the ALP change.

FAA required to review and approve ALPs that implicate any of these.

Now, certain projects – and their corresponding ALP changes – may not

trigger NEPA.

19

SO WHAT?

Page 20: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

FAA still working out the kinks

Currently, all requests run through FAA HQ via ADOs

Sponsors can submit request to FAA to show that the project

is eligible for Section 163

Ask for forgiveness or permission?

20

HOW DOES THIS WORK?

Page 21: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

Raleigh-Durham, NC (RDU)

21

EARLY ILLUSTRATIVE EXAMPLE

Page 22: INTRODUCTION AND OVERVIEW OF MANAGING … · The sponsor’s strategy for the development of the airport Usually a 20 (or more)-year look ahead Master Plan is basis for Airport Layout

QUESTIONS?