introduction - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in...
TRANSCRIPT
![Page 1: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/1.jpg)
1
INTRODUCTION
Objectors are not against the operation of Eldora Mountain Resort (EMR). We recognize the
value of the recreation and economic benefit its operation provides to the residents of Boulder
County and others. However, from the start, a large group of people coordinated by The Middle
Boulder Creek Coalition (MBCC) have had many concerns about possible impacts from the
proposed expansion of EMR. We submitted scoping comments on August 31, 2012 and detailed
comments on the project’s Draft Environmental Impact Statement (DEIS) on April 10, 2014.
Some objectors also filed separate comments.
In total, we raised a large number of issues of concern. We believed then, as now, that EMR’s
needs can mostly or entirely be met with an alternative that would have much less of an adverse
impact on the natural and human environment. We detailed how that could be done. See DEIS
comments, especially Attachment 1; this entire letter and our scoping comments are hereby
incorporated by reference.
However, the Forest Service has gone out of its way to ignore our comments. In fact, the
proposed action in the Draft Record of Decision (DROD) combines the worst elements of both
action alternatives, and proposes a very bad Forest Plan amendment that was not proposed in the
DEIS. The agency could not have done a better job of effectively saying “we don’t care about
your concerns”.
The FEIS and DROD that the agency is currently leaning toward violates applicable law, fails to
respond to many of concerns raised in public comments, and falls short of adequately analyzing
several important issues. The Conservation Groups respectfully request that the Forest Service
either: 1) issue a new decision that blends components of the Infill Alternative with those
elements of Alternative 3 that minimize environmental impacts while still achieving the goals of
the project; or 2) remand the documents for issuance of a supplemental EIS that redresses the
legal violations and better addresses the intense public controversy set forth below and in other
objections to the current decision.
ARGUMENTS IN SUPPORT OF OBJECTION
I. THE DEIS AND FEIS FAILED TO CONSIDER AN ADEQUATE RANGE OF
ALTERNATIVES.
Objectors addressed this issue beginning on page 3 of our DEIS comments.
![Page 2: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/2.jpg)
2
A. The alternatives section is the heart of the EIS and the NEPA process.
Part of the purpose of NEPA is “to promote efforts which will prevent or eliminate damage to
the environment and biosphere”. 43 U. S. C. 4321.
Alternatives are “the heart of the [EIS]” 40 CFR 1502.14. The CEQ regulations require that, in
the alternatives section of the EIS, agencies shall “[r]igorously explore and objectively evaluate
all reasonable alternatives, and for alternatives which were eliminated from detailed study,
briefly discuss the reasons for their having been eliminated.” Id. at 1502.14(a).
The Conservation Groups’ NEPA claims are informed by our commitment to improving the
decision, consistent with the statutory intent of the nation’s bedrock environmental law as
defined by the Council of Environmental Quality:
The National Environmental Policy Act (NEPA) is our basic national charter for
protection of the environment. It establishes policy, sets goals (section 101), and provides
means (section 102) for carrying out the policy. Section 102(2) contains “action-forcing”
provisions to make sure that federal agencies act according to the letter and spirit of the
Act.
Ultimately, of course, it is not better documents but better decisions that count. NEPA's
purpose is not to generate paperwork—even excellent paperwork—but to foster excellent
action. The NEPA process is intended to help public officials make decisions that are
based on understanding of environmental consequences, and take actions that protect,
restore, and enhance the environment. These regulations provide the direction to achieve
this purpose.
40 CFR §§ 1500.1(a) and (c).
B. The FS decision to eliminate the Infill Alternative from full consideration violates
NEPA and applicable case law.
Many of the NEPA cases litigated in the natural resource agency context, including Forest
Service and Bureau of Land Management decisions in Colorado, involve claims challenging the
agency’s choice and treatment of alternatives. Applying those cases to this case conclusively
establishes that the FEIS violated NEPA by failing to analyze the Infill Alternative. The Forest
Service is not required to select any particular alternative, but precedent clearly provides that the
agency is required to analyze an Infill Alternative as one of four total alternatives and only three
action alternatives.
![Page 3: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/3.jpg)
3
The EMR DIES and FEIS both violated the NEPA range of alternatives requirement. Objectors
stated this issue beginning on p. 3 of our DEIS comments. We recommended consideration of an
“in-fill alternative” more fully described at Attachment 1 to those comments. Middle Boulder
Creek Coalition’s scoping comments of August 31, 2012 also discussed an in-fill alternative that
could meet EMR’s request for additional terrain. Id. at 3-4. This triggered the need for the Forest
Service to include the Infill Alternative to be included in the DEIS, consistent with the agency’s
statement in the scoping notice that issues and input raised during scoping “will be used to focus
the analysis of the EIS and generate additional action alternatives if needed.” Corrected Scoping
Letter, July 13, 2012, at 1. Despite broadly based and deeply rooted support for an infill
approach, our concerns were ignored to the point that the FEIS refused to even analyze the Infill
Alternative.
When courts review the range of alternatives:
Once the objective of the action is established, the agency may proceed to reject or
abandon alternatives that are too remote, speculative, impractical, or ineffective in
achieving the stated objective. The agency may also reject alternatives that are not
“significantly distinguishable from the alternatives already considered” or under
consideration. In reviewing an agency’s handling of alternatives, a court is guided by a
“rule of reason and practicality,” examining whether the discussion of alternatives in the
EIS is sufficient to permit a reasoned choice among options.
Colorado Environmental Coalition v Salazar, 875 F.Supp.2d 1233, 1245 (D. Colo. 2012)
(internal citations omitted).
The need for the FS to analyze the Infill Alternative here is further supported by a Vermont ski
area case, Dubois v. United States Dep't of Agriculture, 102 F.3d 1273, 1301 (1st Cir. 1996).
That decision held that the Forest Service violated NEPA because it had failed to adequately
consider the possibility of building on-site storage ponds as the challenged decision to use a rare
high-altitude pond (Loon Pond) on the White Mountain National Forest as a water source for
snowmaking. Dubois, 102 F.3d at 1289-90. In declining to consider the on-site option, the FS
had dismissed Dubois’ environmentally preferable alternative as a “practical impossibility.”
Another Colorado decision, Colorado Environmental Coalition v Dombeck, 185 F.3d 1162 (10th
Cir. 1999), considered claims challenging the range of alternatives selected by the Forest Service
in considering a proposed “Category III” expansion of Vail Mountain Resort on the White River
National Forest.
![Page 4: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/4.jpg)
4
As noted, the National Environmental Policy Act and Council on Environmental Quality
Regulations require the Forest Service to study in detail all "reasonable" alternatives. 42
U.S.C. § 4332(2)(C)(iii) and (E), 40 C.F.R. §§ 1502.1, 1502.14(a). The Seventh Circuit,
and other courts, have interpreted this requirement to preclude agencies from defining the
objectives of their actions in terms so unreasonably narrow they can be accomplished by
only one alternative (i.e., the applicant's proposed project). See, e.g., Simmons, 120 F.3d
at 669; c.f. Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190, 195-96 (D.C. Cir.),
cert. denied, 502 U.S. 994 (1991). Agencies also are precluded from completely ignoring
a private applicant's objectives. [. . . ] We do not perceive these authorities as mutually
exclusive or conflicting. They simply instruct agencies to take responsibility for defining
the objectives of an action and then provide legitimate consideration to alternatives that
fall between the obvious extremes. Beyond this, there are no hard and fast rules to guide
the alternatives analysis. Our task, then, is to determine whether the Forest Service
stepped outside the established parameters by declining to give more attention to the
Conservation Biology Alternative the Appellants prefer, or, stated differently, whether
the alternatives analysis provided satisfies the rule of reason.
185 F.3d at 1174-75 (emphasis added).
The court declined to remand the Category III FEIS for consideration of the environmental
plaintiffs’ Conservation Biology Alternative. That holding does not control here, where the FS is
attempting define and interpret the “purpose and need” so narrowly that only certain expansion
alternatives warrant analysis. Furthermore, the EMR EIS is distinguished by significant factual
differences between this case and the proposed Vail expansion:
The White River Forest Plan, itself subject to National Environmental Policy Act review,
previously prescribed additional winter recreation development on the Forest, and
designated the Category III area for that purpose. We hold the Forest Service was fully
authorized within this decision-making context to limit its consideration to expansion
alternatives designed to substantially meet the recreation development objectives of the
Forest Plan.
Id. at 1175
First, the Forest Service here recognizes that the proposed EMR expansion would violate the
existing ARP Forest Plan, which is why a plan amendment is necessary. Second, the ARP plan
does not prescribe additional development for winter recreation at Eldora. Third, the Infill
Alternative for EMR is markedly different than the Conservation Biology alternative put forward
for Vail. Overall, every skier in the state would agree that Eldora is on the opposite end of the
Colorado ski resort spectrum from Vail, which is one of the biggest and priciest destination
![Page 5: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/5.jpg)
5
resorts in North America, and far and away the biggest employer and economic engine in all of
Eagle County.
Fourth, all of the groups challenging the Vail expansion were either national environmental
groups or Colorado groups or individuals based in Denver or Boulder; none were based in Vail,
Eagle County, or the West slope. Here, the Middle Boulder Creek Coalition and Sierra Club
Indian Peaks Chapter are both based in Nederland and Boulder, respectively; and the leaders of
each group lives in Nederland near the EMR. In other words, Vail pitted outsiders against locals
as well as the local ski area. If any locals belonged to the plaintiff groups, they were not
mentioned in the decision. Here, the MBCC formed to protect the Middle Boulder Creek and
check EMR expansion plans that are largely out of step with local values.
Thus, backdrop, specifics, and context of the proposed EMR expansion are markedly different in
material ways than the Vail Category III case. The two cases share lynx and habitat issues.
Finally, the Vail case lacked both 1) issues involving pristine stream corridors, associated
transportation access or bridges, riparian areas, or adjacent wilderness lands; and 2) any local
government objections to the proposed Category III expansion. Here, all of the factors in 1) are
present; and several local, state, and federal government agencies have raised significant
concerns, and the two most interested local government bodies are expected to file objections.
CEC v Dombeck is not controlling. As argued below, CEC v. Salazar is.
C. The Infill Alternative is reasonable and warrants full analysis under governing law
and court decisions.
In CEC v Dombeck, “The three development alternatives varied primarily in the amount and
type of additional skiable terrain and related amenities to be developed, and, consequently, in the
type and degree of environmental impacts each would impose.” 185 F.3d at 1176. Here, we are
only asking for what the WRNF did in the original Vail Category III DEIS and FEIS: analyze
four total alternatives, including three development alternatives. Here, analysis of a third
development alternative would allow all proposed expansion of parking and on-mountain
amenities while presenting a slightly more modest but still significant increase in new trails and
terrain.
Courts have rejected EISs like this one where the agency unreasonably chooses to consider only
alternatives that involve substantial development of public lands. For instance, in The
Wilderness Society v. Wisely, 524 F. Supp. 2d 1285 (D. Colo. 2007), the Court ruled that a
decision to lease a wilderness-quality area for oil and gas development violated NEPA because
the BLM failed to consider an alternative that would have imposed no surface occupancy
![Page 6: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/6.jpg)
6
stipulations requiring that all drilling occur from outside the area’s boundaries. Id. at 1311-12.
The Court concluded that with a “mix of energy development and conservation characteristics,
the ‘no surface occupancy’ alternative presented a potentially appealing middle-ground
compromise between the absolutism of the outright leasing and no action alternatives.” Id. at
1312.
For the EMR project, the equivalent of the NSO alternative in Wisely (proposed by the
conservation group plaintiffs, and ignored by the agency until the Court ordered BLM to analyze
it on remand) is the Infill Alternative offered by the Conservation Groups. The FS failed here to
consider reasonable alternatives that offered an appealing “middle ground.” If litigated, the
result is likely to be the same as Wisely – remanding the agency decision to comply with NEPA.
Similarly, in NRDC v. U.S. Forest Service, 421 F.3d 797 (9th Cir. 2005), the EIS for a national
forest management plan failed to consider any alternative protecting most of the “currently
roadless areas” in the forest from development. Id. at 814. The Ninth Circuit found the EIS
inadequate because “the range of alternatives … omits the viable alternative of allocating less
unspoiled area to development . . . .” Id. See also California v. Block, 690 F.2d 753, 766-69
(9th Cir. 1982) (agency did not consider a reasonable range of alternatives where none of them
would have protected more than 33 percent of potential wilderness); Friends of the Bitterroot v.
U.S. Forest Serv., 900 F. Supp. 1368, 1373-74 (D. Mont. 1994) (agency violated NEPA by only
considering alternatives that included logging in a roadless area).
The Forest Service reasoning for eliminating the Infill Alternative here (see also subsection E
below) is no different than the arbitrary decision to eliminate the “Community Alternative” in the
Roan Plateau decision:
The Court further finds that the Community Alternative, at least as described in Rock the
Earth’s letter, was indeed a distinct and concrete “alternative” to the other courses of
action being contemplated by the BLM. The Community Alternative was consistent with
the BLM’s statement of the purposes of the action – most significantly, managing the
lands for multiple uses while also complying with the Transfer Act, insofar as the
Community Alternative would have made the top of the Plateau available for leasing
(albeit mostly unavailable for surface occupancy). Moreover, the Community
Alternative was sufficiently distinct from the other alternatives considered by the BLM,
in that none of the other alternatives proposed a combination of nearly full exploitation of
the resources under the Plateau while simultaneously preserving nearly all of the lands
atop the Plateau for environmental protection. Thus, the Community Alternative was
indeed an “alternative” subject to consideration under NEPA.
![Page 7: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/7.jpg)
7
[T]he BLM’s response to such comments never consists of more than a statement that it
did not specifically consider the Community Alternative but that some parts of it (but,
notably, not the most salient feature) appeared in other alternatives.
[. . . ] For this reason, the Court finds that the BLM’s decision did not comply with
NEPA, which in turn renders it “contrary to law” under the APA. For this reason alone,
the BLM’s decision must be vacated and remanded for further consideration.
CEC v Salazar, 875 F.Supp.2d at 1249.
As in the Roan Plateau case, the FS here relied on inaccurate, conclusory statements that the
Infill Alternative was inconsistent with the agency objectives and little different than those
alternatives analyzed in the DEIS. As in that case, the agency is wrong here. Importantly, Roan
Plateau establishes just how much complying with the letter of the law regarding the choice of
alternatives (“the heart of NEPA”) matters: on remand to the agency, a settlement was reached
that is much closer to the Community Alternative that served as the basis for remand than the
original agency decision, which was much more favorable to the oil and gas lessees (the
equivalent of the project proponent in that case). Exhibit *. In Roan Plateau, it took four years
and commanded thousands of hours of attorney and staff time for all parties (environmental
plaintiffs, agencies, and industry proponents) after litigation was filed for the Settlement to be
negotiated – and the new EIS is still pending on remand. Here, the Forest Service still has the
opportunity to get it right before finalizing the ROD.
As detailed above, reviewing courts in Colorado and across the nation have rigorously
interpreted NEPA’s alternatives standard to require agencies to analyze a full range of
alternatives that provide appropriate levels of protection to highly sensitive public lands and
resources. The EMR FEIS failed to do so.
D. Prior Forest Service decisions denying proposed ski area expansions were
influenced by many factors that the ARP has ignored to date for the EMR
expansion proposal
Where public opinion, local government positions, and resource concerns mitigate against ski resort
expansion proposals, there is strong precedent for denying some or all of a given project.
Preliminary research by objectors found four other instances where proposed ski areas or permit
expansions on National Forest lands were denied by the agency. Counting Snodgrass, four of the
five denials were in Colorado: one on the Grand-Mesa-Uncompahgre-Gunnison National Forest
(Crested Butte Mountain Resort), two on the White River NF (Adams Rib and Keystone), and one on
the Arapaho NF (Winter Park Ski Area)
![Page 8: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/8.jpg)
8
A leading recent example in Colorado is the decision of the Grand Mesa, Uncompahgre and
Gunnison National Forests (GMUG) to reject “Crested Butte Mountain Resort’s (CBMR)
Master Development Plan submission which included a proposal to develop Snodgrass
Mountain for lift-served skiing. Exhibit * at 1. Like Eldora and unlike Vail Category III, the
interested environmental stakeholders were two locally based groups who helped organize
local opposition: Friends of Snodgrass Mountain, and Rocky Mountain Biological
Laboratory. Like Middle Boulder Creek Coalition, Friends of Snodgrass Mountain was
founded in response to the expansion proposal. Also like Eldora, there was a diversity of
public opinion on the Snodgrass Mountain proposal.
In 1998, the White River National Forest published a Federal Register Notice of Intent to
prepare an EIS for the proposed Jones Gulch expansion of Keystone Ski Resort. Among
other scoping comments, Summit County and the Colorado Division of Wildlife
(predecessor in interest to Colorado Parks and Wildlife) raised concerns about wildlife
movement corridors – analogous to the elk, moose, lynx, riparian, movement corridor and
other wildlife concerns for the Eldora project described below. The proposed Jones Gulch
expansion did not move forward, and the County eventually purchased private lands in the
area from Vail Resorts (owner of Keystone) to protect as a wildlife migration corridor,
assumedly in cooperative management with the Forest Service regarding adjacent federal
lands.
Lolo Peak, on the Bitterroot National Forest, was allocated by the Forest Plan for downhill
skiing. However, upon further consideration, a Forest Service Needs Assessment indicated
lack of demand and the proposal failed to pass the second level screening at 36 CFR 251.54.
Adams Rib, on the White River National Forest, was approved as a ski area in 1982 and a
ski area permit was issued in 1983. Upon review, subsequent to an MDP submitted in 1993,
numerous issues were raised regarding need, community impacts, wetlands, and “skiability”
of the proposal. The permit was terminated in 1998.
Winter Park Ski Resort, on the Arapaho-Roosevelt National Forest, proposed to expand into
the Zero Creek Basin. During the two-year pre-NEPA process, Zero Creek was removed
from the ski area’s proposal because the Forest Service would not have approved the Zero
Creek component of the proposal.
All of these examples are instructive with regard to factors the Forest Service should consider in
reviewing the Eldora proposal, how the analysis should be conducted, and what outcomes
warrant consideration. The Snodgrass and Jones Gulch decisions are especially relevant due to
striking parallels with the EMR proposal. They are discussed in more detail below.
![Page 9: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/9.jpg)
9
According to the original GMUG decision denying the proposed Snodgrass Mountain expansion
at Crested Butte, relevant factors include a divided community, lukewarm public support, and
local government opposition or lack of support.
In my letter of January 9, 2009, I expressed my view that public support for this proposal did
not exist.
At that time I did not see enough opposition to reject a proposal strictly based upon public
opposition. Since then; however, polarization in the community has increased and organized
opposition to development of Snodgrass has intensified. There is opposition from the Town
of Crested Butte. Gunnison County is unable to submit a letter of support or opposition. [. . .]
I continue to receive numerous letters from people with an interest in the Crested Butte area
who have diverse and heart-felt opinions about this special place where they live and
recreate.
Based on what I have heard and read, I am convinced that the community is deeply divided
over the proposed development of Snodgrass Mountain.
Letter of GMUG Forest Supervisor Charles S. Richmond to Crested Butte Ski Area owners,
November 5, 2009. Exhibit 1 at 1.
Whereas the EMR FEIS and DROD ignored local sentiment regarding land use issues raised by
the public, NGOs, and local government, the GMUG Snodgrass denial acknowledged that “shifts
in land use would generally be undesired by land owners or those who frequent these areas.” The
discussion of geologic hazards (id. at 3) reveals issues similar to those raised about the portion of the
proposed EMR Placer Lift that would extend beyond the current SUP boundary, raising concerns
from infrastructure and grading on resources including sensitive soils, wetlands, and riparian values.
See section V below.
Excerpts of the Forest Service decision denying the CBMR appeal of Mr. Richmond’s decision
provide that:
[T]he record clearly indicates that Forest Supervisor Richmond understood the issues of
public opinion and the role of local government as part and parcel of determining the
public interest. [. . .]
Also, while 36 CFR 251.54(e)(5) does not require Forest Supervisor Richmond to base
his Decision on the position of local government, the appeal record indicates he
considered the position of the Town of Crested Butte, the Town of Mt. Crested Butte, and
Gunnison County when making his Decision.
Exhibit 2 at 14.
Among the factors relied on by Supervisor Richmond in denying the Snodgrass Mountain
proposal were several that are present here, including community/social/economic, recreation, land
![Page 10: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/10.jpg)
10
use Issues, suitability in light of “geologic hazard, slope/terrain, avalanche, boundary management”
concerns, roadless, and lynx. Id. at 15-16.
Objectors and CPW expert comments detailed the significant concerns and threats to wildlife and
habitat from the proposed Eldora expansion.
According to CPW, ungulates such as the resident elk herd could be hard hit by the northern
Placer pod expansion.
There is no description or analysis of how increased noise pollution will affect wildlife
that use the MBC corridor and adjacent areas during fall and winter EMR operations.
Many wildlife species including terrestrial and avian fauna do not respond well to noise
pollution. This could potentially further displace wildlife from their habitats and
migration corridors. MBC drainage in this vicinity is designated as an elk summer
concentration area in the CPW Species Activity Mapping data base. Elk begin migrating
east from the MBC watershed in mid to late October when snow begins to accumulate at
higher elevations and snowmaking operations begin at EMR. The primary elk movement
corridors originate from the upper reaches of the MBC watershed and Chittenden
Mountain and progress east along Mineral Mountain and east along the slopes south of
MBC and along the MBC corridor. This could potentially interfere with or eliminate a
migration corridor due to the sensitivity of elk to artificial noise and human activity, not
to mention other new construction activities related to alternative 2 that could potentially
displace elk for many years.
CPW Comments at 4 (emphasis added).
Responses to Comments had little to say regarding the highly valued elk herd, beyond referring to the
DEIS (pp. 3-216 and 3-240) and acknowledging that “Alternative 2 would result in a loss of
approximately 64.8 acres of potential elk and mule deer habitat (DEIS p. 2-64).” However, the ROD
does not appear to address the concern stated by CPW expert biologists that the migration corridor
could be “eliminated” or “displace[d] for many years.”
On reconsideration, the Forest Service should explore the potential for an Eldora resolution
modeled on Jones Gulch and Keystone in Summit County, where private lands implicated by the
expansion were eventually conserved for wildlife purposes. This could involve lands both within
and outside EMR’s current permit boundary which many stakeholders consider more valuable
for habitat and migration corridor purposes than downhill skiing. These stakeholders would
include Boulder County, Nederland Parks, Recreation, and Open Space Advisory Board, MBBC,
other environmental and land protection NGOs, and numerous residents of Eldora and other
nearby communities. The Town of Nederland is also expected to submit and objection to the
proposed decision. Boulder County’s has earned an international reputation as a pioneer in Open
Space and land conservation for habitat and other purposes, and environmental ethic of its
citizens is unrivaled in Colorado.
![Page 11: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/11.jpg)
11
When hundreds of commenters and several key stakeholders request reconsideration of an
expansion request, the Forest Service has a duty to the public and other governmental bodies to
rigorously consider alternatives to the plans of a private party seeking to expand operations
beyond current permitted boundaries. That has not happened yet. Now is the time to seriously
explore viable options that might better reconcile EMR’s preferences with local values and
sentiment, and better meet the goals of NEPA, NFMA, and other governing law.
E. The Forest Service Organic Act, Multiple Use Sustained Yield Act, and NFMA all
support the need to analyze the Infill Alternative under relevant case law
In the Roan case, the District Court recognized BLM’s obligation to “manag[e] the lands for
multiple uses[.]” Of course, the multiple-use, sustained-yield is equally applicable to our
National Forests, often termed the “Lands of Many Uses”. Pursuant to the Multiple Use
Sustained Yield Act of 1960, 16 U.S.C. § 528, “It is the policy of the Congress that the national
forests are established and shall be administered for outdoor recreation, range, timber, watershed,
and wildlife and fish purposes.”
Three points must be considered in regard to the multiple-use, sustained-yield mandate.
First, the mandate in the Multiple Use Sustained Yield Act explicitly provides that the purposes
of national forest management include outdoor recreation, watershed, and wildlife and fish
purposes. 16 U. S. C. 528. The current decision has not analyzed how various alternatives would
achieve these purposes in this context; and certainly failed to evaluate whether the Infill
Alternative might best meet the Congressionally established purposes.
Second, the multiple-use sustained-yield mandate is reflected in the National Forest Management
Act (NFMA) of 1976. For instance, “(3) to serve the national interest, the renewable resource
program must be based on a comprehensive assessment of present and anticipated uses, demand
for, and supply of renewable resources from the Nation’s public and private forests and
rangelands, through analysis of environmental and economic impacts, coordination of multiple
use and sustained yield opportunities as provided in the Multiple-Use Sustained-Yield Act of
1960.” 16 U.S.C. § 1600(2). NMFA focuses on renewable resources, and it must be
acknowledged that unchecked ski area expansions conflict with healthy renewable resource
conditions.
Third, going back to the language of the Multiple Use Sustained Yield Act, the Infill Alternative
is almost surely superior to the current proposed decision for at least two of the five enumerated
resources: watershed, and wildlife and fish. Comments from the City of Boulder, Nederland
PROSAB, Boulder County, Colorado Parks and Wildlife, and the U.S. Environmental Protection
Agency all raise water quality concerns regarding the Middle Boulder Creek component of
![Page 12: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/12.jpg)
12
Alternative 2. Comments from Boulder County, CPW, and EPA all raise fish, wildlife, and
habitat concerns. Range and timber resources are not at issue. To the extent NFMA directs the
FS to assess renewable resources management “in cooperation with other agencies,” 16 U.S.C. §
1600(2), the Forest Service must recognize that most or all other agency comments oppose most
of the proposed expansion elements of the DROD.
Outdoor recreation cuts two ways. Expanding downhill skiing outside current permitted EMR
boundaries will significantly impact other forms of forest recreation, including: 1) the wilderness
experience in the adjacent Indian Peaks Wilderness; 2) non-EMR recreation in the vicinity of the
proposed Placer lift; and 3) Nordic skiing and backcountry winter sports use in the vicinity of the
proposed Jolly Jug lift in the Jenny Creek area and neighboring backcountry. From an objective
perspective, it can be argued that outdoor recreation is a wash when impacts to non-ski area users
are compared to the asserted benefits of expanding the Resort footprint at the expense of
backcountry and wilderness recreation.
While wilderness recreation and values are specifically referenced in NFMA, downhill skiing at
NF resorts are not. See 16 U.S.C. §1604(g)(3)(A) “(to provide for outdoor recreation (including
wilderness), range, timber, watershed, wildlife, and fish”)(emphasis added). In addition, the
Annual Evaluation Report section provides that “[p]rogram benefits shall include, but not be
limited to, environmental quality factors such as esthetics, public access, wildlife habitat,
recreational and wilderness use, and economic factors such as the excess of cost savings over the
value of foregoing benefits and the rate of return on renewable resources.” Id. at § 1606(d).
The forest planning section of NFMA requires additional assurances and coordination, which the
FS has not satisfactorily acknowledged or addressed:
(e) Required assurances In developing, maintaining, and revising plans for units of the
National Forest System pursuant to this section, the Secretary shall assure that such
plans— (1) provide for multiple use and sustained yield of the products and services
obtained therefrom in accordance with the Multiple-Use Sustained-Yield Act of 1960 [16
U.S.C. 528-531], and, in particular, include coordination of outdoor recreation, range,
timber, watershed, wildlife and fish, and wilderness[.]
Id. at § 1604(e).
The proposed decision appears inconsistent with the emphasis on multiple-use and sustained-
yield policies, renewable resources emphasis, and explicit references to watershed, wildlife, fish,
and wilderness resources and uses in the three main laws enacted by Congress in regard to the
National Forest System: the Organic Act, the Multiple Use and Sustained Yield Act, and NFMA.
![Page 13: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/13.jpg)
13
In Roan, the Lessee-Interveners relinquished and BLM cancelled 17 of 19 leases on the Upper
Plateau in the settlement, while increasing environmentally protective stipulations on the leases
at the Lower Plateau. See Exhibit 3, Roan Plateau Settlement. This outcome is highly analogous
to an ultimate resolution of the current case where a final decision would much more closely
track the Infill Alternative (allowing additional development subject to stronger environmental
protections and directing that development to appropriate, less environmentally sensitive
locations.)
NEPA does matter. That is why it is so important to reconsider the Eldora EIS and DROD.
F. The Forest Service rationale for eliminating the Infill Alternative does not pass
muster from either a legal or common-sense perspective.
The Forest Service inexplicably insisted on only analyzing action alternatives that would expand
the Resort’s footprints to new, environmentally sensitive lands outside the current permit
boundary and in violation of the existing Forest Plan. That is unreasonable and violates NEPA
because an Infill Alternative should have, but was not, analyzed. The lands, habitat, wildlife,
riparian areas, and other renewable resources that would be impacted by the expansion
alternatives are the equivalent of the roadless areas or potential wilderness in the cases cited
above.
The agency defends its choice not to consider the Infill Alternative in part by the following
response to comments:
[R]esource concerns related to the Placer Express chairlift and the Middle Boulder
Creek corridor (including wildlife impacts, slope stability, and water quality in
Middle Boulder Creek) were addressed through the creation of Alternative 3, which
does not include additional development to the north of the current SUP boundary.
Alternative 3 includes additional trails on the back-side of EMR within the current
SUP boundary.
FEIS at D-19, and see FEIS at 2-40.
However, the FS combined Alternatives 2 and 3 in the draft decision proposed for the first time
in the DROD. Alternative 3 addresses the issues concerning MBC only insofar as it does not
approach the Creek. In an effort to address issues, “Alternative 3 does not include the Placer
Express chairlift and terrain and the associated SUP boundary adjustment to Middle Boulder
Creek at the north side of EMR”. FEIS at 2-11, And as stated on FEIS p. 2-1, “the boundary
adjustment associated with each action alternative is a key point of contrast between Alternatives
2 and 3”.
![Page 14: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/14.jpg)
14
The DROD would combine Alternative 3 with Alternative 2’s authorization of the intensely
controversial expansion to Middle Boulder Creek. Nor did Alternative 3 provide a suitable
analysis of the potential for the Infill Alternative to meet the vast majority of the goals and
objectives reflected in the Purpose and Need while avoiding expansions outside the current
permit boundary. Analyzing Alternative 3 cannot excuse the agency’s decision to eliminate the
Infill Alternative from those carried forward for full analysis.
Another reason for rejecting the Infill Alternative was the assertion that an alternate location for
the Placer Chairlift, i.e., one further from MBC that would not cause strongly adverse impacts,
could not be found. FEIS at 2-40. The Infill Alternative did not contemplate installing a chairlift
in the Placer area. Rather, it proposed to upgrade the Corona and Indian Peak chairlifts and
creating new ski terrain within the area served by these lifts as a way of meting at least some of
the purported need for new terrain. See the objectors’ DEIS comments at Attachment 1.
In any case, Infill recognizes the need for a modern, better functioning chairlift to serve this part
of the mountain. The question of what to call it, and further questions going to design, location,
and configuration – are exactly what the EIS should be analyzing.
Replacing the Indian Peak chairlift could be readily accomplished and could avoid concerns
regarding impacts to Middle Boulder Creek. Upgrading Indian Peaks is worthy of analysis
because of the significant benefits including 1) avoiding the significant adverse environmental
impacts associated with extending the Placer Chairlift through old growth forest and vital habitat
to MBC; and 2) improving the user experience by providing modern chairlift facilities.
The Economic Impact Assessment annual compounded rates of skier-visit increases of 0.30% for
Alternative 1, 3.37% for Alternative 2, and 2.19% for Alternative 3 over ten years.
The Economics Impact Alternative 1 (No Action) – this Alternative will result in a
relatively low annual level of visitation increase. As a true “no action alternative,”
Alternative 1 (No Action) does not include any projects that would address the Purpose
and Need. Skier-visits are projected to increase at an annual compounded rate of 0.45
percent over the first five years and at an overall annual compounded rate of 0.30 percent
over ten years.
Alternative 2 - The Proposed Action (Alternative 2) includes projects that would meet the
Purpose and Need and result in increased skier-visits. Skier-visits are projected to
increase at an annual compounded rate of 4.39 percent over the first five years and at an
overall annual compounded rate of 3.37 percent over ten years.
![Page 15: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/15.jpg)
15
Alternative 3 - Alternative 3 includes projects that would reasonably meet the purpose
and need, but would not address all issues. Skier-visits are projected to increase at an
annual compounded rate of 3.10 percent over the first five years and at an overall annual
compounded rate of 2.19 percent over ten years.
FEIS at 3-12.
However, the FEIS and DROD is uninformed by any estimates of skier-day increases under the
Infill Alternative. The number and rate would be expected to be significantly higher than No
Action because the lift upgrades, additional trails and terrain, on-mountain hospitality services,
and parking would all be significantly improved.
The in-fill alternative is reasonable because it could be implemented; in fact, it can be
accomplished much more easily than either of the action alternatives because extensive tree
removal and glading, and for the most part, expensive mitigation measures, would not have to be
done. See section IV B below. A potentially serious safety problem with the Jenny Creek Trail
would be avoided. See section V below. Making backside lifts more wind resistant would be
accomplished by upgrading the Corona and Indian Peaks Lifts, consistent with the Infill
Alternative, while avoiding the impacts to soils and wildlife that would occur with installation of
the Placer Lift and associated runs and glades.
The FEIS establishes that upgrading lifts will go a long way towards addressing wind-related
concerns:
Detachable chairlifts are heavier and less easily impacted by wind. The existing Indian
Peaks and Corona chairlifts are located in exposed alignments, and the old, lightweight
fixed-grip infrastructure is easily blown around (DEIS p. 3-5). [. . .]
Additionally, the replacement of the Corona and Challenge chairlifts, included in
Alternatives 2 and 3, would improve access and terrain availability during wind events.
The replaced chairlifts would be heavier, detachable chairlifts that would be less
susceptible to wind (DEIS p. 3-16).
FEIS at D-16.
What is missing is a recognition that the upper part of the proposed Placer pod can be configured
to 1) address wind concerns, 2) access new infill trails and terrain, and 3) enhance the visitor
experience without building the controversial lift and associated trails outside the existing
footprint and down to Middle Boulder Creek. In fact, such an alternative would almost surely be
paid off sooner than a more aggressive and expensive expansion alternative, and entirely possible
![Page 16: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/16.jpg)
16
that it could provide a better return on investment in the long run than the current proposal,
notwithstanding the “analysis” in the Economic Impact Assessment.
The FEIS treatment of wind (see section V below) contrasts sharply with the treatment of similar
uncertainty and disagreement regarding avalanche danger in the GMUG decision on Snodgrass
Mountain. “There continues to be uncertainty over the potential for the increase of avalanche
frequency and severity along Gothic Road. Concerns persistently raised by knowledgeable locals
perpetuate the issue. Among three commissioned studies there is little agreement.” Exhibit 1 at 3.
NEPA requires formulating and fully analyzing reasonable alternatives that would minimize
impact consistent with the purpose and need, but the Forest Service is attempting to circumvent
the law by over-emphasizing the proponent’s interest in expansion of the footprint, contrary to
the Forest Plan.
Just because EMR has questions about the Infill Alternative does not mean it was properly
eliminated from analysis. Several of the cases discussed above required consideration of energy
development alternatives that were heatedly opposed by oil and gas operators who asserted legal
rights to develop their leases contrary to the conservation alternatives. Under NEPA
implementing regulations and case law, Infill clearly qualifies as a reasonable alternative
warranting full consideration.
Guidance from the Council on Environmental Quality definitively disposes of the FS rationale
attempting to discount infill simple because EMR is not enamored of an approach that would
achieve the vast majority of its stated goals without expanding the permit boundary or requiring
amendment of the ARP Forest Plan.
Q 2a. Alternatives Outside the Capability of Applicant or Jurisdiction of
Agency. If an EIS is prepared in connection with an application for a permit or other
federal approval, must the EIS rigorously analyze and discuss alternatives that are
outside the capability of the applicant or can it be limited to reasonable alternatives
that can be carried out by the applicant?
A. Section 1502.14 requires the EIS to examine all reasonable alternatives to the
proposal. In determining the scope of alternatives to be considered, the emphasis is
on what is "reasonable" rather than on whether the proponent or applicant likes or is
itself capable of carrying out a particular alternative. Reasonable alternatives include
those that are practical or feasible from the technical and economic standpoint and
using common sense, rather than simply desirable from the standpoint of the
applicant.
![Page 17: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/17.jpg)
17
Questions and Answers about the NEPA Regulations, 46 Fed Reg 18026, March 23, 1981;
emphasis added.
The Infill Alternative must be fully considered in the EIS.
II. THE FOREST SERVICE IGNORED SIGNIFICANT CONCERNS REGARDING
BACKCOUNTRY USE, SENSITIVE ENVIRONMENTAL RESOURCES, AND
USER SAFETY IN REGARD TO THE PROPOSED JOLLY JUG POD.
The Forest Service asserts that it was justified in eliminating the Infill Alternative because it
analyzed Alternative 3, focused on the proposed Jolly Jug expansion. The agency seems to imply
that the so-called “southern expansion” raises no “key issues,” is uncontroversial, and that
analyzing it can somehow make up for dropping the Infill Alternative. None of these assertions
are correct.
Objectors discussed this issue in our DEIS comments at 14-15. MBCC comments (at 4) opposed
the Jolly Jug amendment because it would compromise backcountry recreation management
emphasis prescribed in the Forest Plan:
The amendment for the Jolly Jug portion would change 11 acres of management
prescription 1.3 to 8.22. DEIS at B-3. The 1.3 management area emphasizes backcountry
recreation. Plan at 337. This acreage should remain in management area 1.3.
DEIS comments (at 15) also stated that “The Jolly jug runs would face south to southeast,
making the reliability of this pod very questionable during sunny, warm periods, and in years
where snowfall is below normal.” This calls the justification for Jolly Jug into question, raising
doubts as to whether it makes sense for users, the proponent, or the federal land manager. Why
authorize a controversial expansion of dubious value that would degrade the backcountry
experience, raise safety issues, and impact sensitive environmental resources?
Page 1 of the MBCC Scoping Comments put the Forest Service on notice of serious concerns
associated with the proposed Jolly Jug Lift.
We also have concerns about the proposed Jolly Jug lift, as it will also necessitate an
expansion of the SUP Boundary and could have similar impacts to the environment. In
the text that follows, the wording “expansion” refers to the expansion beyond the Special
Use Permit Boundary, the proposed Placer Lift, bridge and associated ski runs, and the
planned Moose Glade Express Lift and associated ski runs as shown in the accepted
Master Development Plan.
MBCC Scoping Comments continued:
![Page 18: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/18.jpg)
18
The proposed Jolly Jug expansion has some of the same impacts as the proposed
expansion on the backside: habitat fragmentation from top to bottom and potential
impacts to Jenny Creek and its riparian habitat. The proposed Jolly Jug expansion needs
a thorough environmental assessment in the EIS. It may also have impacts on the visitor
experience for those using the Jenny Creek trail.
Id. at 9.
Relevant to the fatal flaw in the EIS range of alternatives, scoping comments stated in bold type
at page 4:
At least one alternative needs to address the ski area meeting its perceived
deficiencies (lack of intermediate terrain, inadequate uphill capacity of lifts and
problems with wind) within their current permit boundary.
It is difficult to understand how the agency could conclude that no key issues were raised or
public controversy was lacking regarding this aspect of the project.
To state it simply: the Infill Alternative was designed to meet the purpose and need without
expanding outside the current SUP, by focusing upgrades, improvements, and additional runs
and terrain within the current permitted boundary. The Infill Alternative is reasonable, it differs
significantly from those alternatives the Forest Service chose to analyze, and it warrants full
consideration.
Contrary to the two action alternatives analyzed in the EIS, or the draft decision, MBCC
specifically called for analyzing an Infill Alternative that would offer additional intermediate
terrain in the Jolly Jug area without expanding beyond the current SUP boundary:
We note that the deficiency of Intermediate terrain can be largely rectified without any
expansion of the backside runs below their current elevation, nor any expansion outside
the current Special Use Permit (SUP) Boundary. Using other runs planned in the
Proposed Action (run 18, which is shown as intermediate in the Master Development
Plan, and run 19), combined with a slight redesign of Jolly Jug as shown in the Master
Development Plan (but staying within the current SUP Boundary) along with some of the
planned intermediate glades shown on the backside (or cutting runs where the glades are
currently planned), would largely meet the deficiency.
Id. at 3.
The Sierra Club Indian Peaks Group comments signed by Bill Ikler commented that the southern
expansion would negatively impact backcountry use in the Jenny Creek area, stating that the
project “should be measured not against the total acreage of the National Forest but its impacts
![Page 19: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/19.jpg)
19
on the quality of the acreage and experience of the Hessie, 4th of July and Jenny Creek areas in
particular.” Id. at 4.
MBCC coordinator Dave Hallock’s DEIS comments (at 2 and 8) raised concerns about 1) “three
trout species found in Middle Boulder Creek and Jenny Creek (Greenback cutthroat hybrid,
brook and brown)”; and wetlands “along Jenny Creek (DEIS at page 3-294).”
The FEIS incorrectly asserts that “No key issues were identified associated with the Jolly Jug
area, and thus these projects, and the associated SUP boundary adjustment, were carried forward
into detailed analysis (DEIS p. 2-41)[,]” and “As discussed above, there were no resource issues
identified regarding the proposed Jolly Jug pod and the southern SUP boundary adjustment
warranting the development of a strictly infill alternative.” FEIS at D-19.
This is incorrect. The Jolly Jug Lift is also controversial and the Conservation Groups and
numerous other commenters identified serious resource concerns, user conflicts, and safety
issues associated with the proposed southern expansion.
The proposed Jolly Jug pod would cross a sizable area now traversed by the Jenny Creek Trail,
which provides backcountry access to the Arestua Hut, Yankee Doodle Lake, and other
destinations. “Under the Proposed Action, users of the Jenny Creek Trail would encounter ski
trails, a chairlift, and tree and gladed skiing terrain while on property owned by EMR.” FEIS at
3-21. DEIS Figure 4 shows the Trail would intersect four ski trails, the Jolly Jug Glades, and the
chairlift corridor. Figure 4 depicts Alternative 3, the full Jolly Jug component which has been
incorporated into the proposed action described in the DROD at 2.
Though most of the area where alpine skiers would cross the trail is on private land (see (D)ROD
Figure 1), the Forest Service proposes to permit the expansion into the Jolly Jug area, which
includes construction of the runs and lift corridor that would intercept the Jenny Creek Trail.
Therefore, the EIS for the expansion of EMR must address this issue.
It is easy to imagine how the intersection of alpine runs with the backcountry trail could present
a potentially serious safety problem. Apparently, all the new terrain in the Jolly Jug pod would
be intermediate. See FEIS at 3-17. Thus at least some of the snowriders in this pod would be
moving fairly fast as they approached the intersection with the Jenny Creek Trail at
approximately a right angle with the Trail, where winter backcountry travelers would be moving
much more slowly. Alpine and backcountry users might not see each other in time to avoid
colliding. Collisions would thus be inevitable.
![Page 20: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/20.jpg)
20
For recreational forest visitors, collisions will ruin one’s day or worse, and “mere” near-misses
would considerably degrade the recreational experience for both backcountry users and downhill
skiers.1 The agency has an obligation to provide for the safety of all users.
The Forest Service refuses to see an obvious issue here: “[t]he ID Team did not identify key
issues associated with the Jolly Jug area.” FEIS at 2-41. Rather, the final documents insist that
the potential safety problem can be addressed through signage and the designation of “uphill
travel corridors” (FEIS at 3-21); or “potentially an ‘uphill lane’ where necessary” (PDC under
Recreation, DROD at A-1). See also FEIS at 2-43 and D-68.
However, the project documents never say what an “uphill lane” or “uphill travel corridor” are,
nor how this type of facility and signage would protect the safety of Trail users. They never say
how or why the proposed measures would be effective. Such conclusory statements, without
supporting rationale, do not comply with NEPA. Agencies must analyze mitigation measures in
detail and explain how effective the measures would be. Northwest Indian Cemetery Protective
Ass'n v. Peterson, 795 F.2d 688, 697 (9th Cir.1986), rev'd on other grounds, Lyng v. Northwest
Indian Cemetery Protective Ass'n, 485 U.S. 439 (1988). “A mere listing of mitigation measures
is insufficient to qualify as the reasoned discussion required by NEPA.” Id. Instead, mitigation
measures should be supported by analytical data, Idaho Sporting Congress v. Thomas, 137 F.3d
1146, 1151 (9th Cir. 1998), even if that data is not based on the best scientific methodology
available. Greenpeace Action v. Franklin, 14 F.3d 1324, 1332-33 (9th Cir.1992).
Looking to comparable situations on city streets might be instructive. On icy days, transit
planners recognize that it might be difficult if not impossible for cars to stop at a traffic light at
the bottom of a hill. Accordingly, on such days, these lights are configured to: 1) slow but not
stop downhill traffic, and 2) flash yellow or red to alert drivers on the cross streets to the danger
that downhill traffic is not stopping. For streets in residential neighborhoods that are prone to
unsafe speeds, traffic planners utilize tools such as speed bumps or traffic circles to slow drivers.
For the Jolly Jug danger zone, the Forest Service has not even considered this level of preventive
management, let along required anything beyond standard caution signs that are routinely
ignored or given short shrift by a significant proportion of downhill skiers.
An EIS is not complete unless it contains “a reasonably complete discussion of possible
mitigation measures.” Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 352 (1989).
(“…omission of a reasonably complete discussion of possible mitigation measures would
undermine the “action-forcing” function of NEPA. Without such a discussion, neither the agency
nor other interested groups and individuals can properly evaluate the severity of the adverse
1 FEIS D-68 states that “The presence of ski area infrastructure would detract from the experience of remoteness and
solitude.” This is certainly true, but on busy days, the experience for backcountry travelers would be even worse,
with the possibility of collisions and serious injuries making for a very stressful crossing of the Jolly Jug Pod.
![Page 21: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/21.jpg)
21
effects.”) That requirement is implicit in NEPA's demand that an EIS must discuss “ ‘any
adverse environmental effects which cannot be avoided should the proposal be implemented.’ ”
Id. at 351-52, (quoting NEPA, 42 U.S.C. § 4332(C)(ii)); see also 40 C.F.R. § 1502.16(h) (stating
that an EIS must contain “[m]eans to mitigate adverse environmental impacts”).
One way to address the conflict might be to reroute the Jenny Creek Trail. But the Forest Service
refuses to consider this option:
This design is eliminated from detailed analysis because the user conflict can be
minimized and/or avoided through appropriate signage and specification of an uphill
lane where necessary.
FEIS at 2-43. Two other options for eliminating or reducing the conflict were eliminated for the
same reason. Id. at 2-43, 2-44.
How can safety of backcountry skiers and snowshoers, as well as alpine skiers in the Jolly Jug
pod not be a key issue when part of the purpose and need for the project is to address skier safety
during wind events? (See FEIS at 1-3, 1-4.) Stated another way, how can skier safety during
wind events be addressed, but serious danger to long-time users of a backcountry ski trail from
the southern proposed expansion be ignored?
The southern expansion and proposed Jolly Jug lift presents serious user conflict and safety
issues which the existing analysis has not addressed.
III. THE AGENCY VIOLATED NEPA’S PUBLIC INVOLVEMENT
REQUIREMENTS AND AGENCY DIRECTION BY AMENDING THE PLAN
TO INVALIDATE FOREST PLAN STANDARD 99 IN THE FEIS AND ROD.
The DEIS did not propose to amend or alter standard 99. This decision appeared for the first time
in the DROD and FEIS, after the last opportunity for public comment. Accordingly, qualifying
parties may object on this issue pursuant to 36 CFR § 219.54(c)(7). Additionally, objectors’
comments stated concerns about maintaining the integrity of the wildlife movement corridor
along Middle Boulder Creek (MBC). MBCC DEIS comments at 11-12. See also id. at 5, where
standard 99 is mentioned. Also, Rocky Smith’s scoping comments, dated August 28, 2012,
expressed concern about compliance with standard 99. Id. at 2.
Under the proposed decision, the Forest Plan would be amended to remove standard 99. The
DROD “decision approves the amendment to Forest Plan Standard 99 by removing the
applicability of this standard specifically to the component of the decision at the Middle Boulder
Creek area on the proposed northern SUP boundary.” DROD at ROD-3.
![Page 22: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/22.jpg)
22
Standard 99 states:
In riparian areas, cover that provides wildlife travel corridors will be maintained
along the entire length of riparian zones on at least one side of the drainage. New
corridor interruptions affecting both sides of the drainage will be of minimum
width needed and no more than 60 feet.
Forest Plan at 30.
Amending the Forest Plan to waive this standard is a major decision that is intended to allow
significant environmental impacts that are otherwise prohibited under the Forest Plan pursuant to
Standard 99. It is inappropriate and a violation of NEPA to
A. Requirements for Protecting Riparian Areas.
The Forest Service’s Watershed Conservation Practices Handbook (WCPH) requires the
following:
Allow no action that will cause long-term change away from desired condition in any
riparian or wetland vegetation community. Consider management of stream
temperature and large woody debris recruitment when determining desired
vegetation community.
FSH 2509.25, section 12.1 (Management Measure 2), design criterion 1b.
According to a Forest Plan goal, the desired condition is to maintain riparian areas:
Activities that have the ability to affect the continuity of structure, composition, and
function within riparian ecosystems shall be managed to sustain riparian areas.
Goal 6, Forest Plan at 13.
A Plan guideline states that plan implementation should “[m]aintain the function of key or
unique habitats such as…riparian habitat,…migration corridors,…and riparian areas”. Guideline
103, id. at 30.
Another Plan goal is to “[r]etain the integrity of effective habitat”. Goal 93, id at 30.
B. The project would not maintain the Middle Boulder Creek riparian area as required.
![Page 23: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/23.jpg)
23
It is well known that riparian areas are extremely important for wildlife, which Plan standard 99
recognizes. Standard 99 and various other standards and guidelines in the Forest Plan are
designed to protect the riparian resource and meet the agency’s requirements for protecting them.
However, the current proposed action includes an amendment that would waive standard 99 for
about 200 feet along MBC. FEIS at B-9. Access to this area would be for construction of the
Placer Lift bottom terminal and associated ski runs. This would require a crossing of Middle
Boulder Creek (MBC), and removal of vegetation for the lift and associated ski trails, creating a
sizable breach in the vegetation cover within the riparian corridor along the creek. This would in
turn violate the existing Plan standard 99, which allows interruptions of no more than 60 feet.
And by removing standard 99 for MBC, there would be no standard protecting the riparian areas
associated with the section of MBC through the project area.
The riparian/upland corridor along MBC through the project area, which is now nearly 100
percent effective because there is very little human use (id. at 3-221), would become impaired
under the proposed action. Id. at 3-222. This would be a permanent impact, as vegetation in the
corridor that is removed for access to the bottom terminal of the Placer Lift and its associated
collector trail would not be allowed to regrow. The ecological integrity and continuity of the
riparian area and its habitat would not be maintained. This violates the Forest Plan.
The Colorado Division of Parks and Wildlife (CPW) expressed concern about impacts in all
seasons to wildlife in the MBC corridor if alternative 2 was implemented. The CPW’s comments
on the DEIS, dated April 13, 2014, observes that:
It should be noted that if implemented impacts to this site will not be seasonal and limited
to winter, but will likely occur throughout the year. This is important in that, topography
at the location along MBC results in q natural corridor which funnels wildlife through the
[MBC] drainage. There is also a unique, well functioning riparian complex consisting of
beaver ponds, wetlands, and creek which has many benefits to wildlife resources and
hydrologic processes.
CPW letter at 2.
FEIS mitigation measures are so vague or imprecise that it is impossible to evaluate whether they
will be effective in preserving habitat. Moreover, the decision does not ensure that those
measures will be implemented to achieve the intended results. In National Audubon
Society v. Hoffman, 132 F.3d 7, 16-17 (2d Cir. 1997), the court overturned a Forest Service
logging project where the record lacked data showing that mitigation measures for migratory
bird habitat would be effective.
By statute and regulation, an EIS must include a discussion of possible mitigation measures to
avoid adverse environmental impacts. See 42 U.S.C. § 4332(C)(ii); 40 C.F.R. §§ 1502.14(f),
1502.16(h), 1508.14, 1508.25(b)(3); see also Methow Valley, 490 U.S. at 351-52. Such
discussion must be "reasonably complete" in order to "properly evaluate the severity of the
![Page 24: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/24.jpg)
24
adverse effects" of a proposed project prior to making a final decision. 490 U.S. at 352; see also
Holy Cross, 960 F.2d at 1523. It is not enough to merely list possible mitigation measures. See
Neighbors of Cuddy Mountain v. United States Forest Service, 137 F.3d 1372, 1380 (9th Cir.
1998).
Here, the project design criteria (PDC) designed “to maximize the vegetative buffer between the
collector ski trail and Middle Boulder Creek” (ibid.) reads as follows:
Along the Middle Boulder Creek corridor, maximize the vegetative buffer between
the proposed collector trail and Middle Boulder Creek. Minimize the collector trail
width while maintaining adequate width for ski trail effectiveness. Minimize tree
thinning in Placer Glades II near Middle Boulder Creek while achieving ski area
gladed skiing goals.
DROD at A-4; emphasis added. Clearly this PDC is designed to ensure that collector ski trail is
sufficiently wide. It would only “maximize” the vegetative buffer insofar as it would not
interfere with skiing. In other words, the needs of skiing will take precedence over the need to
retain ecological integrity of the riparian area. This is not mitigation for impacts to the riparian
area.
Similarly, other mitigation measures designed to reduce impacts to the riparian corridor are
conditional:
Where practicable, do not allow skiing within Middle Boulder Creek’s WIZ outside
of designated ski trails (i.e., skier’s left of traverse to Placer chairlift bottom
terminal). This measure would maximize vegetative growth in the riparian areas.
To the extent practicable, water bars must be designed and constructed to discharge
surface runoff originating within the proposed ski trails away from the WIZ and into
well vegetated areas, effectively disconnecting disturbed areas from the stream
network.
DROD at A-10, emphasis added. Implementation of these PDCs is too conditional to be
dependable, effective mitigation for impacts to the riparian corridor along MBC.
Amending away standard 99 for a portion of Eldora Ski Area expansion would set a dangerous
precedent: any time a Forest Plan provision designed to protect important resources stands in the
way of a project desired by a profit-making proponent, amend the plan rather than the project.
The purpose of a Forest Plan is to protect resources owned collectively by all American citizens.
It is not to protect the interests of a commercial proponent at the expense of those resources.
![Page 25: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/25.jpg)
25
But even with Standard 99 eliminated, the proposed project would still violate the Forest Plan
and the WCPH. Under the National Forest Management Act,
Resource plans and permits, contracts, and other instruments for use and occupancy
of National Forest System lands shall be consistent with the land management plans.
16 U. S. C. 1604(i).
The proposed expansion of EMR is illegal and cannot be approved.
IV. THE PROPOSED ACTION WOULD VIOLATE WILDLIFE, RIPARIAN,
WATERSHED, SOILS, WATER QUALITY, AND HABITAT PROVISIONS OF
THE FOREST PLAN.
A. THE PROJECT VIOLATES THE FOREST PLAN REQUIREMENTS FOR
LYNX.
Objectors raised concerns about possible effects to lynx on pp. 12-14 of our DEIS comments.
In 2008, the Regional Forester approved the Record of Decision for the Southern Rockies Lynx
Management Direction (better known as the Southern Rockies Lynx Amendment or SRLA).
This amended most of the forest plans in Region 2, including the one for the Arapaho-Roosevelt
National Forest, on which EMR lies. As shown below, the proposed expansion of EMR would
not comply with some provisions of SRLA, and thus would violate the forest plan.
1. Maintaining intertrail islands and hare habitat.
Human Use Guideline 1 from the SRLA reads as follows:
HU G1
When developing or expanding ski areas, provisions should be made for adequately
sized inter-trail islands that include coarse woody debris, so winter snowshoe hare
habitat is maintained.
SRLA ROD at Attachment 1-7.
Currently, sizable intertrail islands and areas outside of the developed portion of EMR (within
and just to the west of the special use permit boundary) provide lynx winter foraging and
denning habitat. See Biological Assessment (BA) Figure 6-4 at 92. Lynx winter foraging habitat
is, by definition, snowshoe hare habitat.
![Page 26: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/26.jpg)
26
The project would fragment this habitat, as the Biological Assessment (BA) describes:
Alternative 2 would further fragment some of the largest, highest quality, remaining
intertrail islands within the existing SUP boundary with conventional ski trails (C-1
to C-3), the proposed Placer Lift, and new glades (Placer Glades, Bryan Glades II,
and Salto Glades; Fig. 2-2). Alternative 2 would also fragment undeveloped and
unskied terrain outside of the existing development area boundary supporting
snowshoe hares with conventional ski trails (P-4 to P-6), a new glade (Placer Glades
II), the bottom of the proposed Placer Lift. Down CWD would no longer occur on
conventional trails and within the new lift corridors. … These permanent proposed
habitat modifications will degrade hare habitat values and skiing activity will
degrade hare habitat effectiveness, likely leading to the reduced abundance of hares
in the affected terrain.
Id. at 142.
Analysis of winter tracking found that
[H]ares were several times more common outside of developed and active terrain
than within developed and active terrain in all lynx habitat types and in winter
foraging and “other” lynx habitats.
Id. at 102; see Table 6-6, ibid. This result was consistent with similar surveys “at 20 other
existing and proposed Colorado ski areas”. Ibid.
Obviously, hare habitat would be degraded and not be maintained, and intertrail islands would
become much smaller. This violates the SRLA guideline and the forest plan.
2. Snow Compaction.
It is well known that lynx have an advantage over other predators in deep snow because they
have large feet, enabling them to travel efficiently where other animals would sink into the snow.
However, when snow is compacted from human use, such as skiing, lynx lose this advantage.
Thus the SRLA contains the following objective:
Objective HU O1
Maintain the lynx’s natural competitive advantage over other predators in deep
snow, by discouraging the expansion of snow-compacting activities in lynx habitat
![Page 27: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/27.jpg)
27
SRLA ROD at Attachment 1-6. The BA admits that alternative 2 would not be consistent with
HU O1. Id. at 141. Note that unlike HU G10, HU O1 does not have an exception for areas inside
permitted ski areas. We note that some of the new compaction would occur in areas outside the
current EMR SUP boundary. New ski runs and glades in expanded ski area boundaries cannot be
allowed in lynx habitat because doing so contradicts the intent of the SRLA to prevent any
increase in snow compaction in said habitat. If this were allowed, ski areas could be expanded
indefinitely and compact more snow, to the detriment of lynx.
The proposed EMR expansion obviously does nothing to discourage additional snow
compaction; rather it would cause additional compaction, especially in the Placer Pod and the
associated and adjacent glades on the north side of EMR. In addition, there would be new
compaction from the access road to the Placer Lift’s bottom terminal and the bridge over Middle
Boulder Creek. BA at 143.
With additional snow compaction, alternative 2 would not be consistent with HU O1 or with HU
G10. See BA, ibid.
B. THE ACTION ALTERNATIVES WOULD NOT PROTECT RIPARIAN
AND WATERSHED INTEGRITY, SOIL STABILITY, OR WATER
QUALITY, AND THE FEIS FAILS TO SUFFICIENTLY ANALYZE
WETLAND AVOIDANCE AND MITIGATION.
Objectors discussed this issue on pp. 6-8 of our DEIS comments.
Implementing alternative 2 would require soil disturbance on 156.6 acres, 25 of which would
involve grading. FEIS at 3-316. Within the water influence zone (WIZ), 12 acres would be
cleared and 1.3 acres would be graded. Id. at 3-309. Constructing the bottom terminal of the
Placer Lift would require 0.6 acres of grading within the Indian Peaks/Middle Boulder Creek
WIZ. Id. at 3-310.
This violates the Watershed Conservation Practices Handbook (WCPH) at section 12.1
(Management Measure 3):
In the water influence zone next to perennial and intermittent streams, lakes,
and wetlands, allow only those actions that maintain or improve long-term
stream health and riparian ecosystem condition. …
1. Design Criteria.
![Page 28: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/28.jpg)
28
e. Locate new concentrated-use sites outside the WIZ if practicable and outside
riparian areas and wetlands. Armor or reclaim existing sites in the WIZ to prevent
detrimental soil and bank erosion.
m. Do not excavate earth material from, or store excavated earth material in, any
stream, swale, lake, wetland, or WIZ.
Because these measures are incorporated into the Forest Plan (Plan at 13, fn 1), a violation of the
WCPH is also a violation of the Forest Plan.
The Placer Lift bottom terminal, and the area immediately adjacent to it where skiers would
congregate, is obviously an area of concentrated use and would be located within the WIZ.
Material would be excavated from this area within the WIZ to create the base for the bottom lift
terminal. Cutting trees is likely to be inconsistent with WCPH standards. Grading would be a
glaring violation of the requirement that actions “maintain or improve stream health or the
riparian ecosystem condition.”
Grading by use of heavy machinery would create severe and long-term impacts to
the soil by removing the protective vegetation cover, displacing the organic-rich
surface layer, degrading soil structure, altering the soil profile, and increasing soil
compaction resulting in reduced water infiltration and increase in runoff. All of these
impacts lead to an increase risk in erosion and sedimentation and reduction in soil
productivity. …
There would be severe and long-term impacts to the soil profile, soil structure, soil
hydrologic functions, and soil productivity in reclaimed areas following grading
activities. The extent of these areas is small compared to overall project disturbances.
The length of time to re-establish the soil profile and structure may take decades.
FEIS at 3-317.
The soils at the base of the proposed lift have severe limitations for revegetation following
disturbances. Geology and Soils Technical Report (GSTR) at 12. Revegetating these soils is not
easily accomplished, as “[t]ypically, revegetation establishment takes three to five years but
potentially can take up to ten years.” FEIS at 3-317. With snowmaking coverage on the new
runs, snow would be retained longer there. As a result, the growing season and soil temperature
would likely be reduced (see FEIS at 3-315), making vegetation re-establishment even more
difficult.
![Page 29: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/29.jpg)
29
The soils in the project area also have severe to very severe water erosion hazard. GSTR at 12. In
areas rated “very severe”, “significant erosion is expected, loss of soil productivity and off-site
damage are likely, and erosion-control measures are costly and generally impractical.” GSTR at
8.
The proposed decision would allow grading on 10.4 acres of soils with severe or very severe
water erosion hazard. FEIS at 3-319. 2.7 acres of soils with moderate landslide potential would
be graded. Id. This would occur on ski trails above Middle Boulder Creek, where some slopes
include areas that are saturated and have flowing water seasonally. Id. at 3-320. Some of these
slopes are up to 55 percent. Id. at 3-319.
Wetlands surround the bottom terminal of the Corona Lift. See FEIS Figure 12. Grading would
be done as part of reconstruction of this bottom terminal, as the terminal base would be raised six
feet, purportedly to “minimize the footprint necessary for this larger terminal structure”. Id. at 3-
315. Grading would presumably occur in the surrounding area, which could involve grading in
these wetlands, or adverse effects from concentrating runoff into the wetlands. This would
violate the WCPH: “Do not excavate earth material from, or store excavated earth material in,
any stream, swale, lake, wetland, or WIZ”. Id. at section 12.1 (Management Measure 3), design
criterion 1m.
Alternatively, if soil for the raised terminal base was hauled in from outside the immediate area,
additional truck trips would cause soil damage by damage or removal of vegetation and
compaction.
The project would affect 0.11 acres of the Corona fen via removal of forest overstory. FEIS at 3-
314. Presumably this is for a ski run or a lift. Both facilities are concentrated use areas. This
violates the WCPH section 12.1 (Management Measure 3), design criterion 1e. The loss of fen
wetland function would also violate section 12.4 (Management Measure 6), design criterion 1e :
“[a]void any loss of rare wetlands such as fens and springs”, as “[t]hese wetlands cannot be
replaced in kind” (ibid.).
According to EPA’s DEIS comment letter (at 5),
Additionally, due to the slow rate of accumulation of peat in fens, these ecosystems are
generally considered to be irreplaceable (Draft EIS, p. 3-295). Because of the irreplaceable
nature and rarity of montane fen wetland ecosystems, compensation for these wetland
impacts is extremely difficult. The EPA therefore strongly recommends avoidance of these
highly valued resources.
FEIS Appendices at 47.
![Page 30: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/30.jpg)
30
Given the ecological importance of rare fen wetlands, the Forest Service needs to heed EPA’s
avoidance recommendation. The Draft ROD fails to explain why Alternative 3 apparently avoids
the fen despite disturbing more acreage overall than Alternative 2. In any case, even if the initial
impacts are due to overstory trimming, it would seem that such trimming is proposed because
trails or infrastructure are located within or adjacent to the fen.
However, these impacts are avoidable. EPA wrote that “Alternative 3 by design largely avoids
and minimizes adverse impacts to special aquatic sites, including wetlands and fens.” Id.
Avoidance is warranted to the potential loss of irreplaceable fen wetlands. Under regulations
implementing section 404 of the Clean Water act:
Except as provided under section 404(b)(2), no discharge of dredged or fill material
shall be permitted if there is a practicable alternative to the proposed discharge which
would have less adverse impact on the aquatic ecosystem, so long as the alternative
does not have other significant adverse environmental consequences.
40 CFR 230.10(a).
Furthermore, for actions or projects affecting special aquatic sites that are not water dependent,
there is presumed to be a less damaging alternative outside of the special aquatic sites.
Where the activity associated with a discharge which is proposed for a special
aquatic site … does not require access or proximity to or siting within the special
aquatic site in question to fulfill its basic purpose (i.e., is not ‘‘water dependent’’),
practicable alternatives that do not involve special aquatic sites are presumed to be
available, unless clearly demonstrated otherwise. In addition, where a discharge is
proposed for a special aquatic site, all practicable alternatives to the proposed
discharge which do not involve a discharge into a special aquatic site are presumed
to have less adverse impact on the aquatic ecosystem, unless clearly demonstrated
otherwise.
40 CFR 230.10(a)(3).
Ski lifts, runs and other facilities are very clearly not “water dependent”, and thus cannot be sited
in a special aquatic site like a wetland or fen wetland, absent an analysis showing there is no
practicable alternative. No such analysis has been performed in the EIS.
Section 1502.2(d) of the CEQ regulations states that environmental impact statements shall state
how alternatives considered and decisions made will or will not achieve the requirements of
other environmental laws and policies. These other environmental laws and policies would, of
![Page 31: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/31.jpg)
31
course, include Section 404 of the Clean Water Act and the Guidelines for implementation of
Section 404 beginning at 40 CFR 230.1.
The CEQ regulations make it clear that the Forest Service cannot avoid these Guidelines and
their implications for the Forest Service’s decisions in this matter simply because Section 404
permits are outside the Forest Service’s jurisdiction. Compliance with these Guidelines may, in
fact, be the most important factor in the Forest Service’s ultimate decision on both the forest plan
amendments and the site-specific projects proposed by EMR.
Section 230.1(d) of these Guidelines provides that:
From a national perspective, the degradation or destruction of special aquatic sites,
such as filling operations in wetlands, is considered to be among the most severe
environmental impacts covered by these Guidelines. The guiding principle should
be that degradation or destruction of special sites may represent an irreversible loss
of valuable aquatic resources.
Ripple and pool complexes are also special aquatic sites. 40 CFR 230.45. These special aquatic
sites could also be impacted by additional water diversions from Jenny Creek at critical low-flow
periods in the winter for snow-making and the bridge across Middle Boulder Creek.
The Forest Service cannot brush these issues aside by simply stating that they can be resolved by
“mitigation.” The mitigation measures and their effectiveness should be discussed in the FEIS
and the DROD. The discussion should be consistent with the provisions in the Guidelines
Subpart J-Compensatory Mitigation (40 CFR 230.91 et seq.) for Losses of Aquatic Resources.
The Forest Service had in its possession, when preparing the DEIS, an Army Corps of Engineers
Preliminary Wetlands Delineation letter dated April 25, 2013 stating: “[r]egarding your request
for a Preliminary Jurisdictional Determination of the wetlands and other waters to include
Boulder Creek and Jenny Creek; these aquatic sites are preliminary considered to be waters of
the U.S .” See Exhibit 4. Section 1502.25(b) of the CEQ regulations requires that the draft
environmental impact statement list federal permits which must be obtained or indicate that there
is uncertainty as to whether a permit must be obtained.
The Forest Service has had plenty of time to determine whether a Clean Water Act Section 404
permit will be needed for the preferred alternative. Any doubt should be resolved by now.
Failure to resolve this issue by now simply indicates that the Forest Service would prefer to not
take a hard look at impacts to wetlands as they relate to Clean Water Act policies and
regulations, and avoid issues which might interfere with any decisions to allow EMR expansion.
![Page 32: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/32.jpg)
32
Section 1502.16(c) of the CEQ regulations states that the environmental consequences section or
chapter of the EIS shall include discussions of possible conflicts between the proposed action
and the objectives of federal policies and controls for the area concerned. The objectives of the
federal policies discussed above should have been discussed in both the FEIS and the DROD
even if had been determined that the wetlands and streams were not “jurisdictional.”
A categorical exclusion, or Army Corps of Engineers Nationwide Permit, is not available to
EMR. While the actual fill areas may be small, a categorical exclusion is a category of actions
which do not individually or cumulatively have a significant effect on the human environment.
40 CFR 1508.4. When taking into account past and reasonably foreseeable future wetlands fills
in the affected environment, it becomes immediately obvious that a Nationwide Permit is not
available. The Eldora Ski Area has filled a large area of wetlands, one of the largest in Boulder
County over time. See: Hallock, D., N. Lederer, and M. Figgs. 1986. Ecology, Status and
Avifauna of Willow Carrs in Boulder County. Boulder County Nature Association Publication
No. 4. 38 pp.
Finally, Executive Orders 11988 and 11990 direct federal agencies to evaluate the effects of
proposed actions on floodplains and wetlands, and to avoid taking action affecting such areas
unless there are no "practicable alternatives." They also require agencies to provide an
opportunity to the public and interested agencies to comment on proposed projects. Sierra Club
v. Hassell, 636 F.2d 1095, 1100 (5th Cir. 1981).
It is not acceptable under NEPA to defer these important considerations to decisions which will
be made in subsequent proceedings by the Army Corps of Engineers or other federal agencies.
Such a move can only be seen as an attempt to allow these decisions to be made outside the
public’s view and outside the NEPA process, or at least only after the decision to approve an
EMR expansion has been made. The fundamental purposes of NEPA include insuring public
involvement and scrutiny, and availability of information to the public. See CEQ regulations
Sections 1500.1(b) and 1500.2(d).
Section 1500.2(c) of the CEQ regulations states that federal agencies shall to the fullest extent
possible integrate the requirements of NEPA with other planning and environmental review
procedures required by law or agency practice, including the requirements of the Clean Water
Act. The purpose of this regulation is to insure that all these procedures run concurrently and
not consecutively so that federal agencies cannot avoid public disclosure of the basis for their
actions and decisions by deferring environmental reviews to a later time.
By definition, the Army Corps of Engineers was a cooperating agency in this NEPA process
because it had both expertise and probable jurisdiction under the Clean Water Act. 40 CFR
1508.5 Under Section 1501.6(a) and (b) of the CEQ regulations, the Army Corps was required
![Page 33: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/33.jpg)
33
to provide analysis on these important Clean Water Act Section 404 issues, and the Forest
Service was required to use this analysis “to the maximum extent possible.” The unexplained
absence of the Army Corps as a cooperating agency, and the absence of Army Corps analysis
relevant to the Section 404 Guidelines, leads one to think that both agencies prefer to deal with
these issues outside the NEPA process.
The Forest Service asserts that applying project design criteria to minimize impacts would make
the project consistent with the WCPH. DEIS at 3-320. However, even in a best-case scenario,
“frequent maintenance and costly erosion control measures would be required” to sufficiently
reduce impact. GSTR at 12. In addition, the expert report establishes that areas that have been
previously disturbed have not been fully rehabilitated, especially where grading occurred. Id. at
13. This refutes the reliance on design criteria to adequately mitigate impacts or achieve WCPH
compliance.
It has been almost 15 years since the last ski area expansion that could cause these significant
soil disturbances was implemented. See FEIS at 3-122. But frequent maintenance of erosion
control structures, needed to ensure their continued effectiveness, as well as the need for other
maintenance (see below), may themselves cause impacts to soils if heavy equipment is used.
Thus the soils may not have a chance to recover and revegetate.
Indeed, even without the proposed expansion of ski facilities at EMR, it appears that a
considerable amount of work is needed every year to maintain the existing infrastructure. See
DEIS at A-2 through A-5, which summarizes the work done under annual operating plans from
2000 through 2012. In the two most recent years “glade maintenance” and “road maintenance
with grading” were done. In most of the previous years, “[n]ormal snowmaking infrastructure
and trail maintenance” were performed. In at least four years “clean up [of] Corona Pod Glades”
was done. (See also FEIS at 3-123, 3-126.) It is likely that heavy equipment, which would
adversely affect soils and revegetation, was used for some of this work.2 It is thus reasonable to
expect that even more maintenance, some of it requiring the use of heavy equipment and
resulting in subsequent adverse impacts to soils, would be done if the proposed action is
implemented.
With less than full recovery from previous disturbances, it is questionable whether areas with
disturbances caused by the proposed project in areas of quite erodible and potentially unstable
soils would ever recover, especially given the need for frequent maintenance.
2 The FEIS states (p. 3-122):
Construction activities typically involve the use of heavy equipment such as backhoes, excavators and bulldozers;… Construction of new ski trails typically requires equipment such as chain saws, log skidders, wood chippers,
bulldozers, etc.
![Page 34: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/34.jpg)
34
In the Placer pod, “limited rock blasting through the use of dynamite” would occur. FEIS at 3-
128. This passage appears in the section on noise, but there is no analysis of what effects on soil
movement might occur from this activity.
The GSTR states that “Better application and maintenance of BMPs are needed to further reduce
existing erosion.” Id. at 13. But under a future “erosion-control monitoring and maintenance
plan”, EMR would do the inspections to see if erosion was being properly controlled. Id. at 3-
319. In other words, EMR would get to decide the effectiveness of mitigation measures it would
be required to implement. This is not acceptable.
Also, under this plan, only erosion control structures would be evaluated. That is important, but
under the WCPH the Forest Service is required to monitor the following:
Monitor integrity of organic ground cover and organic soil layers, plant community
composition and structure, soil structure, water levels, and drainage patterns.
Id. at section 12-4 (Management Measure 6), Monitoring.
Since design criteria and constant maintenance may not provide the required level of protection
to these sensitive soil resources, avoidance is the preferred mitigation measure. Proceeding with
the proposed action to construct the Placer Lift down to Middle Boulder Creek would
impermissibly violate the WCPH and Forest Plan.
C. THE PROPOSAL VIOLATES THE FOREST PLAN BY NOT
COMPLYING WITH HABITAT GUIDELINES.
Objectors discussed additional areas where the proposed decision appears not to comply with
various Forest Plan measures in our DEIS comments at 12 and elsewhere.
The Forest Plan describes the role of guidelines:
Guidelines are defined as preferred or advisable courses of action or levels of
attainment designed to achieve the goals and objectives. When deviation from a
guideline is necessary, it will be documented during the project-level analysis. Under
those circumstances, the responsible official should recognize the purpose(s) for
which the guideline was developed and assure interested individuals that any
subsequently approved actions are not in conflict with the purposes for which the
guideline was developed. Guidelines are developed in the following circumstances:
(1) when they contribute to achievement of goals[.]
![Page 35: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/35.jpg)
35
Plan at 11.
Goal 94 in the Forest Plan is “[m]aintain or improve habitat capability for terrestrial wildlife”.
Forest Plan at 29. Goal 95 is “[r]etain the integrity of effective habitat areas.” Id. at 30. The
following guidelines contribute to meeting these goals:
107. … Avoid disconnecting or severing intact areas of effective habitat with new
open roads and trails. Favor seasonal use during noncritical times for wildlife when
this cannot be avoided.
108. … When developing new open roads and trails, do not reduce contiguous areas
of effective habitat to less than 250 acres or further reduce effective habitat of 20 to
250 acres in size, except where access is required by law. …
Plan at 31.
120. … Maintain or increase habitat effectiveness within identified old growth areas
and all old growth sites that are not planned for harvest.
Id. at 32.
The FEIS establishes that the proposed project would not comply with these guidelines. Habitat
effectiveness would decrease in an old growth development area, violating Guideline 120. The
reduction in areas of effective habitat would violate Guideline 108. New ski trails would
disconnect areas of effective habitat, contrary to Guideline 107. Forest Plan at 3-218 to 3-220.
Expert comments from CPW stated:
Old growth and late successional forest types provide habitat for a variety of species and
should be left intact to the extent that they can still provide the ecological services required
by wildlife that inhabit these areas. Such areas do not lend themselves to thinning or other
treatments that open the forest in a manner conducive to maintain or improve habitat quality.
Alternative 2 would not be consistent with guideline 120 because "new and conventional
trails would not maintain or increase habitat effectiveness within ARP-designated old growth
development area or ARP-designated old growth inventory." Specifically; alternative 2
would significantly impact high elevation old growth development habitat south of MBC,
which would adversely affect wildlife associated with these forest stands.
CPW DEIS Comments at 5.
CPW also stated that “Alternative 2 does not seem consistent with guidelines 107 and 108.” Id.
![Page 36: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/36.jpg)
36
Old growth designations should be observed, not waived. Boulder County and most public comments
agree that the lands south of Middle Boulder Creek are more valuable for habitat than ski runs and
lift corridors. The decision’s willingness to violate guidelines and standards are out of touch with
local and expert opinion respecting the importance of our remaining roadless forests. The Forest
Service needs to reconsider the Forest Plan Amendments to waive old growth and wildlife
protections.
These guidelines appear to have been placed in the Forest Plan to meet the goals quoted above.
The project would not comply, but would instead make it more difficult to meet the stated goals.
The Forest Service has failed to establish that the project would not conflict with the purposes
underlying these guidelines.
V. THE ANALYSIS DID NOT ATTEMPT TO DETERMINE IF THE PROPOSED
NEW LIFT LOCATIONS WOULD BE LESS SUSCEPTIBLE TO HIGH WINDS.
Objectors’ DEIS comments (at 2) questioned whether the proposed new lifts would be any less
susceptible to high winds that plague EMR, and in during extreme wind events, necessitate shut-
downs of some lifts. MBCC Scoping Comments addressed wind at page 4.
We do not find any data indicating the new lifts would experience less wind, and we noted that
some observations of wind speed from a nearby location could have been used to determine the
wind susceptibility of the proposed new lifts.
However, the Forest Service deliberately ignored this issue, as shown by its response to our
comment:
The Forest Service determined that there is not a need for wind data to validate the
Purpose and Need because EMR proposed the project locations based on an
operational understanding. EMR understands the prevailing wind direction and the
wind speeds in the area. EMR operates the ski area with these factors in mind and
used this knowledge to develop their proposed project locations.
FEIS at D-16, and see FEIS at 1-17.
This is another example of the Forest Service violating NEPA’s public participation mandate by
giving the ski area what it wants without gathering, analyzing, and considering relevant
information. The Forest Service may believe that the ski area knows where and how hard the
wind blows. But when the proposed project is inconsistent with the Forest Plan and would
impact sensitive environmental resources, it is incumbent on the agency to make a reasoned,
informed decision that considers public comments other than the proponents’ preference.
![Page 37: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/37.jpg)
37
The Council on Environmental Quality Regulations implementing the National Environmental
Policy Act state:
NEPA procedures must insure that environmental information is available to public
officials and citizens before decisions are made and before actions are taken. The
information must be of high quality. Accurate scientific analysis, expert agency
comments, and public scrutiny are essential to implementing NEPA.
40 CFR 1500.1(b).
The CEQ Regulations direct the agency to request needed information and verify its accuracy:
If an agency requires an applicant to submit environmental information for possible
use by the agency in preparing an environmental impact statement, then the agency
should assist the applicant by outlining the types of information required. The agency
shall independently evaluate the information submitted and shall be responsible for
its accuracy.
Id. at 1505.6(a); emphasis added.
Furthermore:
If the document is prepared by contract, the responsible Federal official shall furnish
guidance and participate in the preparation and shall independently evaluate the
statement prior to its approval and take responsibility for its scope and contents.
Id. at 1506.5(c).
And finally:
When an agency is evaluating reasonably foreseeable significant adverse effects on
the human environment in an environmental impact statement and there is
incomplete or unavailable information, the agency shall always make clear that such
information is lacking.
(a) If the incomplete information relevant to reasonably foreseeable significant
adverse impacts is essential to a reasoned choice among alternatives and the overall
costs of obtaining it are not exorbitant, the agency shall include the information in
the environmental impact statement.
![Page 38: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/38.jpg)
38
40 CFR 1502.22.
Here, the record fails to establish that the agency independently evaluated assertions by the
proponent and/or consultant that were relied on to support the proposed decision, or made a
reasonable effort to either obtain relevant data, or consider the relevance of information
submitted by knowledgeable commenters. Nearby residents and skiers have collected data on
wind conditions in and around the resort, and some of it was formally submitted to the agency.
The Forest Service has a duty to consider such local expertise and any other relevant
information, and make efforts to obtain additional data where it is lacking.
Wind data is important to making “a reasoned choice among alternatives” because skier safety in
times of high winds is a major part of the purpose and need for the project. See FEIS at 1-3, 1-4.
Currently, there is substantial uncertainty and attendant public controversy as to whether the
proposed new lifts would be significantly less susceptible to high winds, and/or if existing lifts
could be made more wind resistant. For instance, design, location, and other factors considered
when upgrading existing lifts could reasonably be expected to address wind concerns as
effectively as the proposed Placer Lift, while avoiding the most controversial impacts of the
expansion.
If true, this would undermine the justification building the Placer Lift. Then a less damaging
alternative that upgraded existing lifts and did not include the Placer Lift or the runs near Middle
Boulder Creek could be selected in fulfillment of the purpose and need. At a minimum, the
Forest Service needs to make an informed decision based on good science and after considering
all relevant information – even in submissions that did not come from the project proponent.
The intent of NEPA is to ensure that accurate information is available to the decision-maker and
for public comment before projects are approved. Meaningful public involvement is central to
the NEPA process. Here, the Forest Service lacked objective data on which to base its decision,
failed to obtain important information, and ignored information submitted by the public.
The agency cannot discount the possibility that EMR’s assertions regarding tricky and
challenging wind conditions in these mountain settings might not be entirely accurate, especially
given the lack of actual data or science. The agency can consider information from the project
proponent, but is required to verify the information presented and ascertain its accuracy before
relying on it to support a final decision. If wind conditions are used to justify the agency
decision, the underlying information and analysis must comply with NEPA. As it stands, the
agency’s dereliction of duty here violates NEPA.
![Page 39: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/39.jpg)
39
VI. THE EIS AND PROPOSED PROJECT DOES NOT COMPLY WITH THE NHPA
BECAUSE A PROPER SURVEY FOR HISTORIC AND ARCHAEOLOGICAL
RESOURCES HAS NOT BEEN CONDUCTED.
This section was prepared by Payson Sheets, PhD, Professor of Anthropology, specializing in
Archaeology, University of Colorado, Boulder. Dr. Sheets addressed the issue of archaeology in
his comment letter on the DEIS dated March 31, 2014. It was also addressed at page 23 of the
DEIS comment letter submitted by Rocky Smith and MBCC, et al dated April 10, 2014.
References cited in this section are listed in Exhibit 5.
The Legal Context and Archaeological Research Obligations. The National Historic Preservation
Act went into effect in 1966. That was followed by the Archaeological Resources Protection Act
(ARPA) in 1979, and subsequently amended four times. Under ARPA:
No person may excavate, remove, damage, or otherwise alter or deface or attempt to
excavate, remove, damage, or otherwise alter or deface any archaeological resource
located on public lands or Indian lands unless such activity is pursuant to a permit
issued under section 4 of this Act…
16 U. S. C. 470ee (a); see also 36 CFR 296.4.
To ensure compliance with the legal requirements, the first step is to conduct the research to
know the full range of cultural, historic, and prehistoric features within the area of potential
impact (Banning 2002; Sullivan et al. 2007). Knowledge of the time span of human occupation
of the area is essential, followed by knowledge of how people utilized their environment, and the
anticipated tangible material remains of those activities. The design of the historic-
archaeological survey of the area is based upon knowledge of the nature of human environmental
impacts in the past (Schiffer et al. 1978; Banning et al. 2006).
A crucial element in designing the survey is a knowledge of the scale (length, width, and depth)
of anticipated features, and the materials composing them, that could be discovered. That is
done by extrapolation from nearby areas where features are known. The design incorporates
pedestrian survey of the area with the researchers’ transects spaced no farther apart than the
physical scale of the anticipated features. If only large-scale features are anticipated, the people
surveying can be spread widely apart, for example 20 meters apart. If moderate-sized features
are anticipated, transects must be 5-10 meters apart, and if smaller features are anticipated, the
transects must be closer than that.
Where sediment or vegetative matter has accumulated after human utilization of the area,
subsurface testing is required. That is done routinely by many means, including augers, posthole
![Page 40: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/40.jpg)
40
diggers, shovel testing, and a wide range of geophysical instrumentation (resistivity,
electromagnetic induction, ground-penetrating radar, magnetometers, and seismometers).
A thorough professional survey results in the factual database, a complete inventory of features
of past human utilization of the environment over the full span of time that it occurred. Once the
database is complete, evaluation can commence. The most highly significant features can be
nominated for inclusion in the National Register of Historic Places. Less significant features can
be protected by relocating the planned activity, or by careful excavation and publication of the
features that must be destroyed by the planned activity.
The Archaeological Context. Human utilization of what is now Colorado began over 12,000
years ago (Noel et al. 1994), and most scholars now recognize the time span is about twice that
long (Cassells 1997). Hunting and gathering bands utilized the full range of habitats from the
plains to the high mountains at least to 11,000 feet (3353 meters) (Cassells 1997, Cassells 2000).
In the mountains the riparian habitats were particularly favored, as they provided rich floral and
faunal resources. Campsites were occupied for short or longer timespans, and small shelters
were constructed, firepits were built and used, foods were processed and consumed, animals
hunted and butchered and their hides utilized, and lithic artifacts were manufactured and
resharpened (Cassells 2000). The scale of the features remaining from archaeological (Ancient
Native American) land use is often sub-meter in diameter, and a few centimeters in depth.
The EIS Survey: Design, Discoveries, Results, and Inadequacies. The survey for past cultural
resources covered about 175 acres using pedestrian transects spaced 20 meters (over 65 feet)
apart (FEIS 3-92). Such spacing is appropriate for discovering large features such as the more
extensive or deep historic mining pits and their talus mounds. Most smaller historic features will
be overlooked and thus not be a part of the inventory. Only the smaller ones that happen to be
covered by a transect will be discovered, and Appendix D (p. 87) mentions such a discovery.
Therefore the historic component is complete only for larger scale historic features, and is still
incomplete for smaller historic features.
The survey design is woefully inadequate to even begin to discover prehistoric features left
behind by the thousands of years of occupation by Native Americans prior to the historic period.
That is because the transect spacing is far too great, and no subsurface exploration of any sort
was conducted. Therefore, the legal obligation to conduct the research to create an inventory of
ancient land use has yet to be fulfilled.
A major failure of the survey design and accomplishment can be stated in terms of relative
timespans of human occupation. Native American occupation spanned well over 12,000 years,
while the mining activities spanned less than 50 years. The survey therefore provides data
covering less than ½ of one percent of the span of human activities in the area. Or if the more
![Page 41: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/41.jpg)
41
common 20,000-year Native American occupation time span, the survey has covered cultural
remains from an even more miniscule 0.25 % of one percent of the legally required time span.
To complete the archaeological research, surveys covering the remaining 99.75 % of the time
that people lived in and utilized the area must be accomplished. That must be done by close
spacing of transects, less than 2 meters apart, and include properly designed subsurface testing.
The February 8, 2013 Forest Service letter to the State Historic Preservation Office states that
pedestrian surveys will not be conducted for several project components. This decision is
unacceptable. Comprehensive, detailed Class III surveys cultural resources surveyed are needed
for all lands impacted by the proposed decision.
Conclusion. Clearly a decision was made prior to conducting the archaeological survey that only
large-scale features would be sought. Given knowledge of the history and prehistory of the
general area, that can mean a decision to search only for large features such as mining tests. And
the adage “you find what you look for” is appropriate, as that is what was encountered. Survey
transects separated by 20 meters cannot possibly discover smaller scale historic features from the
mining era, so one conclusion is that the historical portion of the survey is still incomplete.
Considerably more drastic is the fact that very wide transect spacing will miss small-scale
features, and those are what predominate in the at-least 12,000 years of Native Americans
utilizing the area. Such spacing will at best encounter a tiny proportion of them. And that
proportion is even farther reduced where visibility is obscured by pine duff, leaves, and some
alluvial sedimentation that characterizes the riparian habitat along Middle Boulder Creek. The
archaeological survey for ancient Native American features has yet to be properly designed,
carried out, and reported.
A list of references for this section is attached as Exhibit 11.
VII. PROPOSED PROJECT DESIGN CRITERIA ARE CONDITIONAL AND MAY
NOT MINIMIZE IMPACTS AS STATED.
Objectors discussed this issue in our DEIS Comments at 14.
CEQ regulations state the environmental impact statement “shall provide full and fair discussion
of significant environmental impacts and shall inform decisionmakers and the public of the
reasonable alternatives which would avoid or minimize adverse impacts or enhance the quality
of the human environment. 40 CFR 1502.1. Furthermore, Sec. 1508.20 defines mitigation to
include (a) [a]voiding the impact altogether by not taking a certain action or parts of an action;
and (b) [m]inimizing impacts by limiting the degree or magnitude of the action and its
implementation.
![Page 42: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/42.jpg)
42
In the 10th Circuit, the court has stated NEPA “places upon an agency the obligation to consider
every significant aspect of the environmental impact of a proposed action. Second, it ensures that
the agency will inform the public that it has indeed considered environmental concerns in its
decisionmaking process." Forest Guardians v. U.S. Fish and Wildlife, 611 F.3d 692, 711 (10th
Cir. 2010) (citing Balt. Gas Elec. Co. v. NRDC, 462 U.S. 87, 97 (1983). Thus, NEPA mandates a
process for federal agencies to make informed decisions by making both the agency and the
public aware of “the environmental effects of proposed actions.” New Mexico ex rel. Richardson
v. BLM, 565 F.3d 683, 703 (10th Cir. 2009) (ref. Marsh v. Or. Natural Res. Council, 490 U.S.
360, 371 (1989) and Balt. Gas Elec. Co. v. Natural Res. Defense Council, 462 U.S. 87, 97
(1983).
In discussing impacts to various species, the FEIS repeatedly states that project design criteria
(PDC) will “avoid or minimize” impacts to various wildlife species. Id. at 3-206 et seq.
However, a fair reading of the FEIS shows the implementation of several applicable project
design criteria are not required.
For example, with respect to several avian and mammalian species, tree removal would only be
conducted outside of the nesting or denning period “to the extent possible”. See DROD at A-3. It
would not be difficult to completely avoid cutting in the nesting or denning periods, as the
longest of them lasts only three and a half months. Id. Also, the nesting and denning periods are
in the spring and early summer when snow is melting and soils are usually wet, which limits
vegetation cutting and any use of heavy equipment to protect soils. Yet prohibiting activities
during these periods is not required.
As written, the PDCs do not require implementation. The Forest Service even acknowledged this
issue in FEIS (D-102, 103), but neither responded to the comment, nor changed the language to
provide additional certainty. Therefore, there is no assurance that the species or habitat will be
protected. If the agency relies on these PDCs to minimize impacts, they must be mandatory. But
because they are conditioned on language such as “to the extent possible,” there is no certainty
that impacts will be minimized. This plainly violates NEPA’s mandate that federal agencies
avoid and minimize adverse impacts to the environment.
The CEQ recently issued new guidance on Mitigation and Monitoring. This guidance
recommends that “[f]ederal agencies should take steps to ensure mitigation commitments are
actually implemented.” Memorandum for Heads of Federal Departments and Agencies,
Appropriate Use of Mitigation and Monitoring and Clarifying the Appropriate Use of Mitigated
Findings of No Significant Impact (hereafter Memorandum) at 8. “[T]he guidance affirms that
agencies should commit to mitigation in decision documents when they have based
environmental analysis upon such mitigation (by including appropriate conditions on grants,
![Page 43: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/43.jpg)
43
permits, or other agency approvals, and making funding or approvals for implementing the
proposed action contingent on implementation of the mitigation commitments).” White House
Council on Environmental Quality Issues Mitigation Monitoring Guidance under NEPA, Press
Release, January 14, 2011, at 2,
https://ceq.doe.gov/current_developments/docs/NEPA_Mitigation_Monitoring_Press_Release_1
4Jan2011.pdf.
Tenth Circuit case law applying NEPA and CEQ regulations requires that agencies provide a full
and fair discussion of the potential adverse impacts of this project. Here, the Forest Service failed
to meaningfully discuss the limitations of voluntary or conditional mitigation measures. This
frustrates informed public participation in decision-making, and falls short of fully disclosing the
impacts of the project.
VIII. THE SOCIO- PROPOSAL MAY VIOLATE THE FOREST PLAN AND AN
AGREEMENT WITH THE COUNTY BY INCREASING THE CAPACITY OF
THE SKI AREA.
Objectors addressed this issue on page 6 of our comments on the DEIS.
For the Boulder Creeks Geographic Area, the Forest Plan states the following under
“Management Area 8.22 (Eldora Ski Area))”:
It is anticipated that actual use levels will increase. There will, however, be no
increase, in the established maximum daily capacity.
Plan at 54.
The FEIS notes correctly that this prohibition on an increase in daily capacity is part of an
agreement with Boulder County that limits daily lift ticket sales to 5000. Id. at D-30.
The comfortable carrying capacity (CCC) under alternative 2 would increase to 5580 people per
day.3 FEIS at 3-15. It is currently 4250. Id. at 3-4.
The agency insists that the CCC “is a planning figure only and does not represent a regulatory
cap on visitation”. Id. at 3-3. However, the 5000 people per day limit in the agreement with the
County is a regulatory cap on daily use. Since the CCC is a use level “that facilitates a pleasant
recreational experience without overburdening the resort’s infrastructure” (ibid.), it will likely be
reached or exceeded on weekends and holidays during the peak ski season if EMR’s expansion is
3 In the alternative described in the DROD, the CCC might be higher, since it includes a larger Jolly Jug Pod than
was proposed for alternative 2.
![Page 44: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/44.jpg)
44
approved as proposed. Certainly, EMR will try to get at least that many people to visit the ski
area as often as possible.
Since the 5000 lift ticket sale limit does not include season passes (id. at D-30), it is possible
EMR could reach the new CCC and not violate the County agreement and the Forest Plan.
However, there is no information presented in the FEIS or other documents that we know of
indicating that the prescribed limit on the sale of lift tickets will not be exceeded. Notably, there
is no project design criterion limiting the sale of lift tickets. See DROD at A-1 through A-16.
IX. SUPPLEMENTAL NEPA IS REQUIRED BECAUSE THE FEIS FAILED
TO DISCLOSE THE COMBINED IMPACTS OF ALTERNATIVES 2 AND
3, AND NEWLY AVAILABLE INFORMATION INDICATES THE
RESPONSIBLE OFFICIAL PRE-DETERMINED THE OUTCOME OF
THE PUBLIC PROCESS .
Objectors did not specifically raise this issue in previous comments because there was no
indication that the two action alternatives analyzed in the DEIS would be combined into a final
proposed action. Therefore, we are entitled to raise this issue in the objection, per 36 CFR
218.8(c).
NEPA requires that alternatives, including the proposed action, should be presented in
“comparative form, thus sharply defining the issues and providing a clear basis for choice among
options by the decisionmaker and the public.” 40 CFR 1502.14. The regulations further state that
agencies shall “(b) [d]evote substantial treatment to each alternative considered in detail.” Id.
The regulations also govern preparation of supplements to EISs:
(c) Agencies: (1) Shall prepare supplements to either draft or final environmental impact
statements if: (i) The agency makes substantial changes in the proposed action that are
relevant to environmental concerns; or (ii) There are significant new circumstances or
information relevant to environmental concerns and bearing on the proposed action or its
impacts.
(2) May also prepare supplements when the agency determines that the purposes of the
Act will be furthered by doing so.
40 CFR 1502.9(c)
Here, 1) the proposed action includes substantial changes relevant to impacts; 2) new
information undermines the agency’s rationale for the proposed decision; and 3) the agency
![Page 45: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/45.jpg)
45
failed to analyze an action alternative that complied with the Forest Plan, although a viable
action alternative was proposed that would do just that while allowing the majority of the
proposed improvements to proceed.
In preparing the DEIS, the Forest Service developed two action alternatives. Alternative 2 would
add the Placer Lift and associated terrain, expanding the special use permit boundary down to
very near Middle Boulder Creek, and adding a lift and terrain in the Jolly Jug Area. Alternative 3
would not expand into the Placer area, but would provide a larger area in the Jolly Jug pod than
would Alternative 2. It would also create larger gladed/tree skiing areas in the Bryan II and Salto
areas compared to Alternative 2, and create the Moose Glades. Compare FEIS Figures 2 and 4.
Alternative 3:
includes several projects included in the Proposed Action; however, to respond to
identified issues raised during scoping, Alternative 3 does not include the Placer
Express chairlift and terrain and the associated SUP boundary adjustment to Middle
Boulder Creek at the north side of EMR
Draft EIS at 2-11, FEIS at 2-11.
The DROD at 2 and 3 describes the proposed approved alternative, combining some elements of
alternative 3 with alternative 2. There is no indication in either the DEIS or FEIS that the two
alternatives would be combined, especially since Alternative 3 was specifically formulated to
address some of the issues with the then-proposed action, alternative 2:
Alternative 3 includes several projects included in the Proposed Action; however, to
respond to identified issues raised during scoping, Alternative 3 does not include the
Placer Express chairlift and terrain and the associated SUP boundary adjustment to
Middle Boulder Creek at the north side of EMR. Alternative 3 includes additional
trails and tree and gladed skiing areas within the current SUP boundary.
FEIS at 2-11.
Since the alternative presented in the DROD is not one the public could have reasonably
expected based on the alternatives presented in the DEIS, it violates NEPA. See California v.
Block, 13 ELR 20099, 9th Cir, 1982.
Starting even before scoping for the current EIS, the Forest Service appears to have committed to
the course of approving Forest Plan Amendments related to EMR expansions. In a favorable
light, the agency seems to have pre-determined the process. In a less favorable light, some
actions could be perceived as misleading the public by misrepresenting: 1) the extent to which
![Page 46: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/46.jpg)
46
the new master plan is inconsistent with the existing Forest Plan, and 2) how proposed
expansions would violate the existing Plan as well as local plans and policies including Boulder
County’s Comprehensive Plan.
The ARP Evaluation of the Eldora Master Plan and Proposed Projects (February 18, 2011) is
attached as Exhibit 6. This document discusses the suite of potential projects included in the
Draft 2010 Master Development Plan developed for EMR by the SE Group.
Initial Screening Criteria 2 asks whether "[u]se consistent or can be made consistent with
FLRMP’s.” Id. The response states “Yes, the existing use is a ski area within the Forest Plan
MA-8.22 (Ski Based resorts) and most of the proposed use is consistent with the Forest Plan, and
some of the potential projects (expansion of permit boundary area) can be made consistent with a
Forest Plan amendment via a NEPA assessment and affirmative decision.”
This appears to be the only acknowledgement that the expansions are inconsistent with the Forest
Plan. It supports consideration of the Infill Alternative by affirming what Objectors have long
argued: most of the proposed improvements can be approved and implemented within the
existing SUP without amending the Forest Plan.
Initial Screening Criteria 5 goes to “other scheduled or existing authorized uses, or adjacent non-
NFS lands.” Id. The response asserts: “There are adjacent Boulder County Open Space and
private lands. There is no foreseen conflict or interference with FS administrative use or other
scheduled or existing authorized uses, or adjacent non-NFS lands.” Id.
The response is incorrect. The proposed Placer pod expansion to Middle Boulder Creek, and
bridge across the creek, directly conflict with the Boulder County Comprehensive Plan, and the
County management goals stated in its DEIS comment letter. As to County Open Space, in 2006
the County accepted a conservation easement from a private landowner of a property described
as a “mix of forest, open meadows and rock outcroppings” that “offers pristine wildlife habitat
that connects nicely with the surrounding Forest Service land.” Exhibits 7 and 8, Boulder
County Board of Commissioners November 9, 2006 letter to Kathleen Lawler and Laurence
Tasaday, and map of easement, respectively.
The proposed ski area expansion in this area would adversely impact wildlife as established by
CPW, MBCC and other comments; contrary to the purpose of the easement intended “to
preserve natural lands and habitat and [] expand the currently protected area in the mountains
around Eldora.” Id.
Second Level Screening Criteria 1 at page 3 asserts that “the existing ski area and the MDP
proposed projects do not appear to be inconsistent or incompatible with purposes for which lands
are managed in the area or with other uses.” Id. This is false. Here, the Forest Service was
required to acknowledge that the new master plan was inconsistent with the Forest Plan. It
appears that the agency was either unaware of this key fact, or attempted to avoid stating that
expansions were inconsistent and incompatible with the Plan. It leaves the impression that the
responsible official was determined to deliver whatever Forest Plan Amendments might be
necessary to fully implement EMR’s desired expansions, notwithstanding the need for the future
NEPA process to be independent and objective.
![Page 47: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/47.jpg)
47
Second Level Screening Criteria 2 considers the public interest. The entire discussion addresses
the so-called public interest in expanding downhill resort skiing opportunities on public lands. It
lacks any mention of the public interest in following Forest Plan standards that protect wildlife,
habitat, soils, riparian areas, and other sensitive resources that are prized by all forest users,
skiers and non-skiers alike. Is it too much to ask that the Forest Service acknowledge the public
interest in respecting and implementing Plan standards that protect the environment? When the
agency decision maker only appeared to consider one side of the issue from the outset, how can
the EIS and Forest Amendment processes be considered independent and objective?
This Evaluation seems to expose an end-run around NEPA’s public involvement requirements
that permeated the NEPA process leading up to the DROD. The deciding officer might genuinely
believe that authorizing an expansion even more aggressive than those considered in the action
alternatives is in the public interest (Second Level Criteria 2 at 3, id.). However, this document
raises serious issues as to the objectivity and independence of the process.
The rationale for combining the most aggressive expansion aspects of the two action alternatives
was stated as follows in the DROD at 12:
Therefore while I acknowledge that the Alternative 3 version of Jolly Jug will have
greater impacts, I have included it in my decision because: 1) the benefits to the
recreation experience will be substantial, 2) the impacts on NFS lands are nearly the same
between the two configurations, and 3) the private lands that will be minimally impacted.
This rationale fails both logically and legally. First, it again shows that the decisionmaker
appears to be solely concerned with the “recreational experience” at the expense of other uses
and values, and only one aspect of recreation at that (downhill skiing at EMR). Second, absent
supplemental NEPA analysis on the alleged cumulative impacts being “nearly the same,” this
assertion is unsupported by the current record. If the Forest Service wants to choose and
implement a “Maximum Expansion Alternative,” it first needs to fully analyze it. Here, no effort
has been made to determine the full direct, indirect, and cumulative impacts of such a decision
(outside a few conclusory statements in the DROD), and the public has not been allowed to
comment or offer expertise on the new proposal. Because the new proposed action would have
greater environmental impacts than either action alternative considered in the DEIS, it cannot be
justified as coming within the range of impacts already analyzed.
Third, the existing decision fails to adequately weigh the environmental, socio-economic, and
other costs of the proposed expansion proposed for the first time in the DROD against the
purported benefits to the Resort and its customers.
The differences between Alternatives 2 and 3 in regard to the Jolly Jug pod are substantial. The
DROD acknowledges that “[t]he Alternative 3 Jolly Jug project adds approximately 62 acres of
![Page 48: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/48.jpg)
48
intermediate terrain, compared to approximately 35 acres in the Alternative 2 version.” The total
expansion proposed by the DROD would encompass “66 acres of ski trails, the creation of
approximately 77 acres of tree and gladed skiing areas and modifications to approximately 42
acres of existing tree and gladed skiing[.]” DROD at 3. The fact that the SUP adjustment for the
combined alternative proposed in the DROD is only 2 acres greater than under Alternative 2
does not nullify the fact that the 27 additional acres of additional terrain is more than a third of
the 85 total acres of intermediate terrain under consideration, and better than 40% of the 66 acres
of new trails.
The FEIS does not analyze cumulative impacts to elk, deer, and other wildlife from the
combined impacts of potentially losing the migration corridor and 64.8 acres of elk and deer
habitat under Alternative 2, and that “Alternative 3 would result in a loss of approximately 58.9
acres of potential elk and mule deer habitat.” DEIS at 2-64 and CPW DEIS comment.
In any case, the impacts of a proposed action that encompasses the combined action alternatives
have not been fully disclosed. For example, we do not see disclosure of use projections for the
combined action in FEIS section 3A. Usage affects the magnitude of the impacts, and it could
affect compliance with the limit on daily lift ticket sales, which is discussed in section VIII
above. It is also difficult to discern the effects on soils, vegetation, and wildlife because only
parts of alternative 3 are included in the alternative proposed for approval, and the disclosure of
effects for alternatives 2 and 3 does not accurately disclose the impacts for the proposed
approved alternative.
X. THE PUBLIC NEVER HAD A MEANINGFUL OPPORTUNITY TO COMMENT
ON THE PROPOSED PERMIT BOUNDARY ADJUSTMENT NEAR MIDDLE
BOULDER CREEK.
Objectors addressed this issue in their April 10, 2014 comments beginning at 5.
Under the current Forest Plan, expansion outside of the “boundaries currently specified in the
Master Development Plan” is prohibited. Plan at 54. It was the clear understanding of the Eldora
Civic Association at the time of Forest Plan development (1997) that there would be no
expansion of EMR outside the SUP. Just a few years before the revised Forest Plan was
finalized, EMR had expanded by constructing the Indian Peaks pod. The quoted Plan language
was thus clearly intended to limit the size of EMR on its north side.
The Forest Service believes such expansion is acceptable because the Master Plan was revised in
2011, and this newer version allows the proposed expansion. DEIS at 2-40, DROD at 13-14.
Specifically, “My decision is consistent with this statement because the projects contained in my
decision are included in the EMR’s 2011 Master Plan.” DROD at 14.
![Page 49: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/49.jpg)
49
The Forest Plan does not say “current master plan”, but rather “currently specified in the Master
Development Plan” (emphasis added). This clearly refers to the EMR master plan that existed
when the final revised Forest Plan was issued. That master plan did not include the expansion
now being proposed.
The current master plan also does not include part of the expansion now proposed. The 2011
Master Plan, Figure 5, shows the Jolly Jug Lift bottom terminal north of the Boulder/Gilpin
County Line. The proposed approved Jolly Jug Lift goes well south of the county line. See
Figure (D) ROD-1. Alternative 3, with the larger Jolly Jug pod, is now part of the proposed
action, as described at DROD-2. Thus the statement quoted above from the DROD is not true, as
the Forest Service admits:
Because Alternative 3 in this EIS includes a SUP boundary adjustment that differs
from the EMR 2011 Master Plan, should that alternative be approved through this
process, the 2011 Master Plan would need to be amended to reflect the correct SUP
boundary.
DEIS at 2-40.
The Forest Plan was not amended after completion of the 2011 Master Plan. In fact no public
input was sought or accepted when the ARP accepted the 2011 plan, as is clear from the
following correspondence:
…there is no provision in our MDP review process for public meetings or input….
It is during th[e] NEPA process that you will have an opportunity to submit your
comments/concerns for specific proposed project(s), potential forest plan
amendments and or any other actions requiring public involvement.
Exhibit 9, Letter from Forest Supervisor Glenn Casamassa to Dave Hallock of MBCC, October
6, 2010 at 1, 2.
Similar views were expressed in a letter from then-Boulder District Ranger Christine Walsh to
Payson Sheets, dated January 14, 2011:
Because all proposed projects and permit actions are conceptual at the MDP level,
acceptance of the MDP makes no commitments.
Id. at 1.
![Page 50: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/50.jpg)
50
Clearly, the Forest Service did not accept any public input on the proposed special use permit
boundary adjustments.
The latest chapter in this saga exacerbates this problem, as the DROD “amends the 2011 Master
Plan to include the Alternative 3 configuration of the Jolly Jug chairlift and terrain”. Alternative
2, the preferred alternative in the DEIS, did not include the expanded Jolly Jug configuration, nor
did it propose to amend the Master Plan.
Instead of attempting to amend the Forest Plan in an attempt to authorize a controversial
expansion that violated the existing Plan, the Forest Service should be implementing the Plan
and denying expansion beyond the existing SUP boundaries. Dave Hallock’s letter of March 7,
2010 to the Ski Area (attached as Exhibit *) clearly expresses concern with expansion down to
Middle Boulder Creek, as is now heading toward approval by way of the proposed Placer Lift
and associated runs and glades. Id. at 2-3.
Another letter from Mr. Hallock to Forest Supervisor Casamassa, dated September 12, 2010,
raises the question of the need for a public process at the time of the Master Plan revision:
Should the Forest Service consider having some type of public process at this time?
It may not be mandated by current policy, but should it be considered? One
downside of waiting until there is a specific proposal for improvements that trigger
NEPA, is that it may only cover a portion of all contemplated improvements and the
process only deals with a piece and not the whole. Context gets lost.
The 1997 Revision of the Land and Resource Management Plan for Arapaho and
Roosevelt National Forests and Pawnee National Grassland makes the following
statement relative to Management Area 8.22 (Eldora Ski Area): “There will be no
expansion of the area outside the boundaries currently specified in the Master
Development Plan” (Chapter 2, Page 54 in the Geographic Area Direction for
Boulder Creeks Geographic Area). Should the Forest Service be considering
accepting a MDP that indicates an expansion of the permit boundary that goes
against the current Forest Plan first without holding some public process at this time?
…
In closing, if a large-scale planning project for the Hessie area cannot be undertaken,
then at least there should be some public process to the Update of the Master
Development Plan.
Id. at 2.
![Page 51: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/51.jpg)
51
EMR did conduct some voluntary public involvement, as noted at FEIS D-24, but EMR’s
process was never intended to satisfy NEPA obligations in any way. Rather, EMR’s process was
geared toward improving the recreational experience for guests, not in addressing environmental
concerns, as was stated by a Jan. 5, 2011 letter from MBCC to Glenn Casamassa and Christine
Walsh, discussing the problems with the November, 2010 “Analysis Of The Purpose, Process,
And Content Of Eldora Mountain Resort’s 2010 Master Plan And Related Public Comments”
distributed by EMR:
The public process and the three open houses that were run by the ski area were
focused on gathering “comments from the general public on how to improve the
guest experience” (Section II of the Report). We ask that in any consideration of the
Report in the Forest Service review process of the Master Development Plan it be
recognized that the public process was run by the proponents (Eldora Mountain
Resort) and was geared toward users of the ski area. The Report also states that
“particular effort was made by Eldora not to show support or opposition to any
particular suggestion or comment” (Section II of the Report). But, based on
comments made by ski area representatives at the meetings, there is evidence of bias.
For example, at the open house in Boulder the ski area manager stated in his
introductory remarks “in any development we will not affect natural habitats." When
creating a ski run and converting a closed canopy forest ecosystem to a grassland, it
is rather difficult to have no impact on the natural habitat, but we will hold the ski
area to that comment and level of impact. Also at the open house in Boulder the ski
area manager was asked about the effects on wildlife habitat, but the question was
cut short: the ski area manager indicated that the meeting was for improving the area
for users. At the open house at the ski area the ski area manager was asked about
impacts to moose, to which he replied “None, the moose will stay.” This is not a
neutral position during an open house. The ski area’s wildlife consultant corrected
the ski area manager and said there would be displacement.
The list of the “Breakdown of Comments by Topic” (Section III of the Report)
provides only limited mention to environmental concerns, and they are listed
exclusively under “Concerns about the Hessie area (Water Quality, Wildlife, General
Recreational Use, and Traffic). We know that there were other environmental
concerns raised by participants in the public process and a number of the concerns
were regarding the existing operation and not just expansion into Hessie, including
impacts to wetlands and aquatic ecosystems, noise from snowmaking and grooming,
noxious weeds, erosion, and the use of carbaryl. We wonder why there is no mention
of these concerns. The exclusion of known comments from this list brings into
question the validity of the evaluation process.
![Page 52: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/52.jpg)
52
Id. at 1, 2.
The public “outreach” done by EMR cannot substitute for legal requirements applying to the
Forest Service. EMR’s representative that the Resort’s plans “will not affect natural habitats” is
demonstrably false, as just one example of the bias associated with EMR’s process and proposal.
Even with all the emphasis on the proposed action being consistent with the current (2011)
master plan, it isn’t, as is discussed above.
Clearly, there was an issue of major public concern involved in the Master Plan update --
expansion outside existing SUP boundaries including the intensely controversial expansion
toward Middle Boulder Creek. –Instead of “accepting” the new Master Plan, the Forest Service
should have noted that certain elements were inconsistent with the Forest Plan and thus could not
be endorsed or approved unless the Plan were amended. Instead, the Forest Service has played a
shell game, changing the rules at it goes: changing the Master Plan to allow expansions outside
the SUP without changing the Forest Plan or involving the public, then proposing to approve
even more development beyond that contained in new master plan, and seeking to change the
master plan to allow that expansion as part of the proposed decision.
The Forest Service has failed to take account of broad public and stakeholder support for 1)
adhering to the existing Forest Plan, and 2) denying proposed amendments that seek to allow
highly controversial expansions to the detriment of competing values and uses. The unlawfulness
of the agency’s procedures is especially glaring in light of its decision to eliminate from analysis
the only action alternative that would have complied with the Forest Plan: directing
improvements and upgrades to the existing SUP under an infill alternative.
The solution is simple. The Forest Service needs to analyze an alternative that would allow the
Resort to proceed with the great majority of proposed actions: those inside the existing permit
boundary. It is patently unreasonable and unlawful not to analyze even one action alternative that
1) complies with the Forest Plan, and 2) complies with the Boulder County Comprehensive Plan,
and would allow local governments and residents to implement their policies and achieve their
objections while still authorizing the lion’s share of improvements sought be EMR. Failing to
analyze such an alternative violates NEPA by depriving the public of a meaningful opportunity
to comment on a viable action alternative that is consistent with the existing Forest Plan, and
local plans and policies.
If the Forest Service would continue to follow its Plan for the ARP, it would allow the County to
continue to implement the county’s plan. But the EIS failed to analyze an action alternative that
complies with either plan, despite deep public support for both plans, and the fact that the
![Page 53: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/53.jpg)
53
existing plans are environmentally preferable to the expansions considered in Alternatives 2 and
3.
XI. THE FOREST VIOLATED NEPA’S HARD LOOK REQUIREMENT FOR KEY
ISSUES INCLUDING SOCIO-ECONOMICS, AND WILDLIFE AND HABITAT
IMPACTS
The EIS violated NEPA by failing to taking the requisite hard look at the impacts the proposed
expansion will have on issues including terrestrial and aquatic wildlife, special status fish and
wildlife, socioeconomics; recreation; and wilderness values.
A. The EIS violated NEPA by failing to take a hard look at the socioeconomic
impacts of the project and the lack of consistency with local government plans
and policies.
MBCC challenged the economic assumptions that the expansion will be a financial success in the
context of the fundamentally different perspective on the EMR’s proper niche in the community
in its scoping comments. These comments (at 18) stated:
The ski area has been touting the number of jobs being created by the proposed
expansion. There needs to be a complete breakdown of these jobs, including construction
vs. ongoing ski operations; jobs related to each portion of the expansion (Placer, Jolly
Jug, guest service facilities); and further broken down by kinds of jobs, their pay, and
their benefits.
We also argued that the Draft ROD allows development that is inconsistent with both the Eldora
Environmental Preservation Plan (EEPP) and the Boulder County Comprehensive Plan (BCCP).
As the agency acknowledged, the Eldora Environmental Preservation Plan was created in 1992
by the Eldora Civic Association to “address growth and development issues, and concerns with
recreational growth” in the Eldora area.”
Objectors commented that the DEIS was inconsistent with the EEPP on ten specific topics
ranging from habitat protection to the 5,000 skier per day capacity limit. The EEPP is included
in the BCCP, which states: “Eldora Civic Association would work towards limiting the eventual
size and operations of the ski area. There should be no expansion of the ski area outside their
current permit boundary and no expansion below the existing Corona and Indian Peaks pods.”
This directly conflicts with the draft decision.
Nederland PROSAB opposed Alternative 2 because it conflicts with the Town’s vision and
would have unacceptable impacts.
![Page 54: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/54.jpg)
54
It is important that the critical balance between active recreation areas and wilderness,
referenced in the first Nederland Vision 2020 vision statement, be maintained, as well as
the water quality in Middle Boulder Creek, which provides drinking water for the Town
of Nederland and the City of Boulder. With this in mind, PROSAB urges the Responsible
Official to reject the proposed EMR expansion north to Middle Boulder Creek, as
presented in Alternative 2 of the DEIS.
Nederland PROSAB Comment Letter at 2.
These comments also stated that the agency failed to take a hard look at traffic impacts: The
impact of EMR traffic within the Town of Nederland is inadequately treated. Reliance upon
CDOT criteria for highway carrying capacity ignores the very real gridlock created during
afternoon peak hour EMR traffic within the town.” Id.
In stating that ARP standards, guidelines and conditions will be applied by the Forest Service,
the agency fails to mention that the pre-Amendment standards, guidelines, and conditions were
consistent with the local vision and zoning.
The agency would suggest that it is enough that these plans were considered “throughout the
Preparation of the DEIS,” (FEIS at D-27) where they were ultimately rejected without any
serious effort to integrate their goals and objections into the ROD, or even fully analyze an
alternative that would do so.
Federal law requires that the Forest Service take account of local zoning and land use plans, and
encourages consistency between federal, state and local plans. See Granite Rock, 480 U.S. 572,
585 (1987) (citing 16 U.S.C. § 1604(a) and 43 U.S.C. § 1712(c)(9). Although federal agencies
are not obligated to defer to local plans, local jurisdictions are injured when federal action
preempts their enactments and plans. City of Sausalito v. O’Neill, 386 F.3d 1186, 1197-98 (9th
Cir. 2004).
CEQ’s Forty Most Asked Questions Concerning CEQ's National Environmental Policy Act
Regulations addresses conflicts with local land use plans or policies:
23a. Q. Conflicts of Federal Proposal With Land Use Plans, Policies or Controls. How
should an agency handle potential conflicts between a proposal and the objectives of
Federal, state or local land use plans, policies and controls for the area concerned? See
Sec. 1502.16(c).
A. The agency should first inquire of other agencies whether there are any potential
conflicts. If there would be immediate conflicts, or if conflicts could arise in the future
when the plans are finished…, the EIS must acknowledge and describe the extent of
those conflicts. If there are any possibilities of resolving the conflicts, these should be
explained as well. The EIS should also evaluate the seriousness of the impact of the
proposal on the land use plans and policies, and whether, or how much, the proposal will
![Page 55: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/55.jpg)
55
impair the effectiveness of land use control mechanisms for the area. Comments from
officials of the affected area should be solicited early and should be carefully
acknowledged and answered in the EIS.
Here, it is incumbent on the FS to better describe the conflict and endeavor to resolve it. Boulder
County has not indicated it is prepared to waive the protective designations in the controlling
land use plans for one of the most sensitive and highly valued recreational and environmentally
important landscapes in the County. Analyzing the Infill Alternative would fulfill the obligation
that the FS explore resolving the conflicts between the proposed MBC Placer Lift expansion, the
Forest Plan Amendment that would make it possible, on the one hand, and local land use
policies, on the other.
Such analysis would also address the local concerns submitted by Boulder County, the Town of
Nederland, Nederland PROSAB and Eldora townsite residents. To date, the agency appears to
have not even acknowledged the extent to which its draft decision conflicts with important local
planning documents and land-use objectives on a wide range of important resource issues.
The FEIS relies on the Economic Impacts Assessment prepared for SE Group by Doug Kennedy
Advisers for its apparent assumption that the expansion will be a guaranteed financial success.
However, the Economic Assessment offers little or no confidence that its projections are accurate
or reliable. Stated otherwise, if the report isn’t taken at face value, it could easily be perceived as
a case of “garbage in, garbage out”. In this case, the garbage was generated to support expansion
plans rather than an independent, objective evaluation that takes a hard look at ski industry
economics or the unique challenges facing EMR based on a host of factors that went unanalyzed
by the consultant.
The agency needs to explore a joint Forest Service/Boulder County review process for the
proposed ski area improvements, as well as a comprehensive planning process for Middle
Boulder Creek. Nederland, Eldora townsite representatives, and other stakeholder could also
participate.
Much of the controversy involves the extent to which upgraded facilities and opportunities
within EMR’s existing footprint might better serve skiers and contribute to financial viability
than the proposed expansions. Upgrading existing lifts is an obvious component of an infill
alternative from any reasonable perspective.
But the FEIS declined to meaningfully analyze replacing the existing Indian Peaks lift, simply
because EMR apparently isn’t interested, and seems to prefer to build entirely new infrastructure
to serve new terrain outside the Resort’s existing footprint. To justify its deference to EMR’s
preference, the agency Response to Comments opines that upgrading both Indian Peaks and
![Page 56: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/56.jpg)
56
Corona lifts “would not make common sense from a technical and economic standpoint.” FEIS
at D-20.
The appeal to logic here is mystifying. Regular EMR skiers use both lifts to access the mountain.
Although Corona is sometimes more exposed to wind than Indian Peaks, Indian Peaks can see
more use when the Corona trails are closed or unattractive to some skiers on high wind days. The
question is not whether an upgraded lift is needed to serve the Indian Peaks part of the mountain;
it is whether the upgraded lift should extend outside the current boundaries to MBC instead of
being configured to best serve terrain as proposed by the Infill Alternative.
Contrary to the agency assertion to defend its decision, it would appear to “not make common
sense” to not consider infill upgrades that would: 1) significantly improve the user experience on
existing terrain, and 2) avoid the significant impacts and controversy associated with the lower
portion of the proposed Placer lift. If we assume that either a new lift, or an upgraded
replacement lift will be built – the Forest Service needs to take a hard look at addressing all
relevant concerns, not just the Resort’s preference for the full Placer pod expansion. As
numerous stakeholders including Boulder County continue to note, this has not happened.
The Economic Impacts Assessment purports to be able to predict increases in skier-days with
precision of 1/100 of 1% up to five years into the future following project implementation. It
seemingly lacks any disclaimers as to how other variables, such as snow conditions, resort skiing
trends in Colorado, fuel prices, lift ticket prices, or the health of the economy – might affect
skier-days and revenue as much or more than the expansion. The “Assessment” does not seem to
inquire into how lift tickets, or the total cost of downhill skiing (including equipment rentals,
food, etc.) could contribute to skier-days, revenues, or financial success.
The sentiment of Eldora users was aptly captured in a March 27, 2015 article in the Mountain
Ear newspaper regarding the FEIS and ROD:
Last Sunday, a group of three families from Denver enjoyed a barbecue tailgate party at
the end of the day. “We are taking lessons in this kind of awesomeness,” said Byron
Hittle. When asked how he felt about the expansion, he said, “I am excited about having
more terrain, but I hope the expansion doesn’t make Eldora too crowded. Right now, it
has a welcoming, family area-feel and I wouldn’t like to bring in too much traffic.
Exhibit 17.
Eldora’s future success depends on being in tune with the land ethic of Boulder County and the
hardy skiers who relish the unique skiing experience provided by the resort. A significant
proportion of customers are looking to avoid not just the traffic, but many of the other trappings
![Page 57: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/57.jpg)
57
of the I-70 resorts as well. Maintaining a “welcoming, family-area feel” will continue to be a key
contributor to a thriving resort. Crowds and “too much traffic” will compromise the experience,
the feel and the “vibe.” An over-aggressive expansion plan that is out of touch with users’ values
risks killing the goose that lays the golden eggs at EMR.
Unfortunately, the Economics Impacts Assessment lacks any discussion of this aspect of the
issue. Perhaps that is unsurprising that a Vermont-based consultant would be less likely to have
knowledge of local culture and custom or analyze these factors as part of quantifying the
projected costs and benefits of various expansion alternatives. That does not make the omission
any less glaring or justify the NEPA violation. Simply put, the Forest Service decision entirely
failed to analyze a key aspect of the issue – let alone take the required hard look.
Objectors’ claim is supported by the expert conclusions of one of the leading resource
economists in the Rocky Mountain region, Pete Morton, PhD, Senior Economist
Conservation Economics Institute. According to Dr. Morton:
There is little discussion on how other variables influence future skier-days. Some
variables that are reasonable to consider when predicting future skier visitation and
revenue at a ski area include snow conditions, competition from destination results,
current economic conditions, the cost of gasoline, and lift ticket prices. For example, will
the cost of the aggressive expansion included in Alternative 2 and 3 be paid for by higher
lift ticket prices? If so, how will higher priced lift tickets affect future visitation rates?
In a similar vein, future visitation rates should consider local skiers like myself who will
choose not to ski, or to ski less at Eldora Mountain as a result of unnecessary expansion
outside the current ski area boundary. As an avid backcountry and area skier, and a long
time Colorado and Boulder County resident I have never understood Eldora Mountain’s
over-aggressive expansions plans which run counter to the land ethic of Boulder County
and of nearly all of the skiers I talked to this year while riding the lifts at Eldora.
Exhibit 12 at 1.
This expert review casts doubt on the methodology and conclusions of the Economic Impacts
Analysis. Unlike the consultant who purported to project the differences in skier-visits with an
accuracy of hundredths of percentage points five years into the future, Dr. Morton is a Colorado
resident and regular user of EMR. Dr. Morton reached a very different conclusion about the
likely viability of some improvements than the Economics consultant retained for the EIS, and
casts enough doubt on the underlying methodology that the existing Economic Impacts
Assessment cannot be relied on to support the Forest Service decision. Quite simply, pie-in-the-
sky projections of increased visitation directly correlated to the level of expansion do not hold
water as currently presented. According to Dr. Morton:
![Page 58: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/58.jpg)
58
Another very reasonable improvement I agree with is to simply replace/upgrade the
existing lifts in order to address performance issues, stalling, length of time enduring
wind gusts, and people getting stuck. This improvement would certainly improve the
overall quality of every skier's experience.
There is also room for improvement in terms of the service amenities currently offered.
Updating and improving existing eating and drinking facilities at the base lodge and on
the mountain make great sense to me. To be honest, I am more likely to stop in
Nederland on my way home for food and drink because the eating-drinking facilities at
Eldora Mountain are pretty lame. Simply upgrading the existing food and beverage
services would be a huge leap forward in capturing more revenue from existing skiers
like me.
Another concern I have with the EIS is the increasing visitation rates assumed for each
plan alternative. The assumed rate of skier visits for each alternative is a key input into
the economic analysis completed. If a higher rate is assumed the economic impacts (i.e.
jobs, revenue) increase. Alternatively, if a low rate is assumed for an alternative the
economic impacts decrease. Unfortunately there is little documentation or discussion on
the justifications used for the high rates assumed for Alternatives 2 and 3, or importantly
the large discrepancy between those high rates and the much lower rate for Alternative 1.
Why did the author assume such a low rate for the do nothing alternative and much
higher rates for the other alternatives?
There is little discussion on how other variables influence future skier-days. Some
variables that are reasonable to consider when predicting future skier visitation and
revenue at a ski area include snow conditions, competition from destination results,
current economic conditions, the cost of gasoline, and lift ticket prices. For example, will
the cost of the aggressive expansion included in Alternative 2 and 3 be paid for by higher
lift ticket prices? If so, how will higher priced lift tickets affect future visitation rates?
In a similar vein, future visitation rates should consider local skiers like myself who will
choose not to ski, or to ski less at Eldora Mountain as a result of unnecessary expansion
outside the current ski area boundary. As an avid backcountry and area skier, and a long
time Colorado and Boulder County resident I have never understood Eldora Mountain’s
over-aggressive expansions plans which run counter to the land ethic of Boulder County
and of nearly all of the skiers I talked to this year while riding the lifts at Eldora.
Since the visitation rates assumed in each alternative are one of the key assumptions used
in the economic analysis, much more documentation and discussion is needed on the
![Page 59: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/59.jpg)
59
reasonableness of the assumed rates of future visitation. Obviously, some sensitivity
analysis of this key variable is in order.
Exhibit 12 at 2-3.
In sum, the Economics Assessment does not withstand expert scrutiny. Dr. Morton’s analysis
raises questions that undermine the document prepared to justify the proposed expansions, and
establishes scientific controversy on at least two of the central social science questions facing the
project: 1) whether the proposed expansions are likely to result in the level of increases visitation
predicted by the EIS (or could even decrease skier-days and revenue due to controversy), and 2)
whether an infill alternative might capture most of the economic benefits sought by the Resort, at
substantially lower cost, avoiding most of the controversy, while avoiding significant
environmental impacts and allowing Forest Plan protections to remain in place?
The level of controversy surrounding what some local Forest Service officials seem to consider a
relatively modest expansion of the Resort is understandable only if one is aware of the context
for the decision. The framework and local public opinion need to be taken into account, as well
as expert reviews of the complicated socioeconomics of EMR, both in developing alternatives
and reaching the final agency decision.
B. The EIS violates NEPA by failing to take a hard look at wildlife and habitat
impacts of the project.
Objectors raised wildlife issues in their comments at 4-9, and Dave Hallock’s comments (at 1-6).
Wildlife concerns and potentially significant impacts from expansion were also addressed by
CPW’s comment letter, addressed above, and Boulder County DEIS comments.
ARP users, including Boulder County residents, put great value on wildlife viewing and habitat
stewardship. Most visitors to Indian Peaks and adjacent lands report that elk and other
“charismatic megafauna” are viewed infrequently in the backcountry, making sightings all the
more precious to hikers. But the Forest Service does not appear to have attempted to balance the
relative benefits of protecting the existing elk herd against a controversial and incremental
expansion of EMR down to MBC. The Economics Impact Assessment was notably silent on any
and all potential adverse environmental impacts of the expansion, neither qualitatively
acknowledging nor attempting to quantify any negative impacts to wildlife, riparian, water
quality, or other threatened values – despite the fact that the project includes Forest Plan
amendments intended to authorize actions that would violate the existing Forest Plan.
CEQ regulations implementing NEPA require agencies “to prepare supplements to either draft or
final EIS's if there ‘are significant new circumstances or information relevant to environmental
concerns and bearing on the proposed action or its impacts.’” Id. (citing 40 CFR § 1502.9(c)).
Supplemental review is triggered by new and significant information not previously
![Page 60: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/60.jpg)
60
analyzed under NEPA. The CEQ regulations list several factors that indicate significance,
including the following:
(3) Unique characteristics of the geographic area such as proximity to . . .
ecologically critical areas.
(4) The degree to which the effects on the quality of the human environment are
likely to be highly controversial.
(5) The degree to which the possible effects on the human environment are highly
uncertain or involve unique or unknown risks.
(6) The degree to which the action may establish a precedent for future actions with
significant effects or represents a decision in principle about a future consideration.
40 CFR 1508.27.
These four factors apply here. First, the northern expansion will impact unique and ecologically
critical resources in the area of Middle Boulder Creek. According to CPW:
Our primary concern regarding the expansion of EMR is the extension of the special use
permit (SUP) boundary to and along the south side of MBC and associated riparian
habitat and CO Highway 130 (Hessie Road). This expansion of the SUP boundary and
associated ski area projects are all summarized and contained in the DEIS proposed
alternative 2. It should be noted that if implemented impacts to this site will not be
seasonal and limited to winter, but will likely occur throughout the year. This is
important in that, topography at the location along MBC results in a natural corridor
which funnels wildlife through the drainage. There is also a unique, well functioning
riparian complex consisting of beaver ponds, wetlands, and creek which has many
benefits to wildlife resources and hydrologic processes. Throughout the year Hessie
Road is a primary access point to the Indian Peaks Wilderness. Currently, due to MBC
and marshy conditions along the creek human activities are restricted to Hessie Road
until recreationists (by foot or vehicle) reach access points farther west into the Indian
Peaks Wilderness via established trails. It would be fair to say that this is the most
congested roadway for recreationists accessing the Indian Peaks Wilderness. Because of
the high volume of recreational use along the road and the natural barrier afforded by the
creek, riparian corridor and mature forest stand to the south, wildlife use tends to
concentrate to the south side of the creek. The development of several projects outlined in
alternate 2 . . . adjacent to and south of MBC could directly and indirectly adversely
impact wildlife resources using the area south of the creek negatively impacting this
wildlife movement corridor.
CPW Comment Letter at 3.
Second, the highly controversial nature of the project is undisputed by the Forest Service. Public
controversy and intensive disagreement over the environmental impacts and socio-economic
components of the project are snowballing, the more the public learns about the draft decision
![Page 61: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/61.jpg)
61
and actual impacts. A sampling of recent media coverage is indicative of the controversy, which
is also manifest in the number and quality of objections to the DROD.
An article in 5280 Magazine by a local skier who sees both sides of the issues spoke for many
locals and much of the public. First, he recognizes what is obvious to most Eldora users, that
better lifts and facilities will go a long way to improving the experience and luring more skiers.
Second, he expressed his preference for mostly leaving well enough alone. The article is
significant because5280 Magazine generally leans more pro-business establishment than
environmentally minded.
It sounds great—in theory. Better technology, more terrain, faster equipment. But to get
those things, we’ll have to give up the Brian’s Glades’ powder stash—and potentially
create other issues for the environment and area residents. Faster lifts and more runs
mean easier skiing for everyone, but those few solitary turns in the trees and the soft,
static whoosh of my edges in fresh-fallen powder are the things great skiing is made of.
Yes, Eldora must grow and change to survive—any business does—but I have to say, I’m
kind of fond of the old girl just the way she is.
Exhibit 14 at 4.
A February 21, 2015 Boulder Daily Camera article summarized the perspective of two local
residents, establishing deep opposition from the Eldora Civic Association to the northern
expansion, and serious concerns about the both the northern and southern expansion from a
former EMR Ski Instructor who has skied Eldora all his life:
Diane Brown was a year-round resident of Eldora for 18 years. She still lives there May
through October each year and is former president of the Eldora Civic Association Board.
"We've done numerous surveys regarding ski area expansion, and the town is
overwhelmingly opposed to any expansion that would come in our direction, and
particularly Hessie," Brown said. "This is a real sore point." [. . . ]
Morgan Ruskay, a 1995 graduate of Nederland High School and former ski instructor at
both Eldora and Aspen, lives just outside Nederland and fears the effects of expansion.
And, as an avid alpine and nordic skier, she is convinced expansion isn't even needed.
"My concern with the expansion is that it's going to go into an absolutely beautiful area,
the Fourth of July and Hessie area, and the (ski) terrain isn't going to improve that much.
And then, there's all the stuff into Jenny Creek, the south terrain, which is a pristine area,
and isn't going to hold the snow," Ruskay said.
![Page 62: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/62.jpg)
62
"It's not going to be that great, and is really going to take away from the beauty of
Nederland, Colorado, and Eldora."
Exhibit 15 at 4-5.
Although EMR claims that the southern expansion will hold snow and make sense, local experts
are skeptical. Contrary to Forest Service assertions in the DROD, significant controversy
surrounds the proposed southern expansion regarding whether it makes sense, and whether the
impacts on a currently pristine area are justified.
A March 17, 2015 Daily Camera article examines at length the concerns of environmental
stakeholders representing Middle Boulder Creek Coalition and the Sierra Club, in addition to
establishing that failing to reconsider the proposed expansion will only extend the controversy;
ensure that objections and possible litigation are paralleled by charged county review processes.
Because of the resort's split between Forest Service land and privately held land that is
subject to county jurisdiction, [Boulder County Land Use Director Dale] Case said
numerous aspects of the expansion may still likely need to undergo special use review by
county commissioners.
Exhibit 17 at 5.
A March 18, 2015 Denver Post story quoted the Middle Boulder Creek Coalition’s coordinator
on the prevailing view of many local residents who commented constructively and participated
in the public process in good faith -- but found the Forest Service seemed to be deaf to public
concerns.
"This is even worse than Eldora's proposal," coalition coordinator Dave Hallock said of
the blended alternative. "The Forest Service even expanded this thing for them. The
relationship between the ski area and the Forest Service and the consultants — they are
all in bed together. The Forest Service didn't listen to anyone, only the ski area."
Exhibit 18 at 2.
As the FEIS and DROD objection deadline approached, media coverage continues to document
growing and ongoing controversy regarding the agency’s draft decision. According to a recent
Daily Camera story, Boulder County sees little to like in the expansion plans and is asking why
EMR can’t limit improvements to the existing footprint.
And, reiterating an earlier position on Eldora's plans that the county has taken in previous
letters to the Forest Service, the letter says, "Based on the Forest Service's analysis in the
![Page 63: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/63.jpg)
63
final EIS, we are not convinced that the ski area cannot accomplish its goal within its
existing footprint."
Exhibit 20 at 2.
The County’s position 1) disposes of the Forest Service’s unsupported assertion that only the
northern expansion is controversial; and 2) removes any doubt as to the reasonable-ness of fully
analyzing and infill alternative.
Third, impacts to wildlife, habitat, riparian areas, and the neighboring Indian Peaks Wilderness
are uncertain and risky. CPW and others are concerned that wildlife impacts could be year-
round, not just during the Resort’s winter operation as asserted by the EIS. The potential for
backcountry or wilderness users to cross the bridge and use informal access to the Indian Peaks
wilderness is a point of disagreement. CPW stressed that “The potential recreational access
issues on the south side of MBC outside the ski season have not been addressed in the DEIS.” Id.
at 5. This deficiency was not rectified in the FEIS. CPW (at 5-6) concluded by emphasizing that:
The potential recreational access issues on the south side of MBC outside the ski season
have not been addressed in the DEIS. Again, there is a likelihood that recreationists will
use the bridge crossing over MBC to access the forest and Indian Peaks Wilderness
further to the west, potentially increasing use and social trails thereby impacting wildlife
in areas where human activity is supposed to be absent.
Fourth, approval of the two expansions currently on the table could be precedent for future
expansions of EMR. Objectors, Eldora residents, and local government have repeatedly stated
concerns about future expansion plans to Moose Glades or elsewhere.
In its Response to Comments 8.3.19, the agency appears to assume that elk will be “largely
unaffected” by the proposed expansion, contrary to the opinion of CPW: “if moose respond in
the same way as mule deer and elk, seasonal movement patterns should be largely unaffected.”
FEIS at D-47.
Legally, the FS is required to analyze these impacts even if the agency considers them justified
when weighed against the financial interest of EMR. From a policy perspective, the agency has
an obligation to avoid and minimize impacts to highly valued wildlife populations and habitat,
and local residents and forest users who place great importance on wildlife protection.
The ROD attempts to downplay the potential for unauthorized use of the bridge to access the
south side of Middle Boulder Creek and Indian Peaks. “Human presence on the south side of
Middle Boulder Creek is not anticipated to increase because the gate on the bridge across Middle
Boulder Creek can be designed to effectively block unauthorized access.” D-48. This assertion is
inconsistent with the CPW comment letter. It doesn’t take account of local conditions including
the shortage of parking for the nearby Hessie trailhead, and the fact that this part of Indian Peaks
is one of the most heavily visited wilderness areas in Colorado. The acknowledgement that
“people currently cross the creek in localized areas after peak flow periods (typically beginning
in August)” highlights the likelihood of the bridge being used as a bridge, notwithstanding
![Page 64: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/64.jpg)
64
signage. Ibid. The agency finally falls back on unspecified “adaptive management,” a speculative
reference that provides no assurances to residents, wilderness users, or wildlife life, and falls
short of satisfying the law. Ibid.
Supplemental analysis needs to take a hard look at these impacts, including concerns raised in
DEIS comments that constitute new information.
SUGGESTED REMEDIES
The proposed expansion of EMR does not comply with NEPA, ARPA, various regulations, and
the Forest Plan. Objectors suggest the following remedies to achieve compliance with applicable
law and craft a better-reasoned decision that incorporates the well-founded objections of the
objectors as well as other commenters, including Boulder County, Nederland, PROSAB,
Colorado Parks and Wildlife, the EPA, and hundreds of concerned local residents:
Withdraw the draft record of decision.
Issue a Supplemental EIS that fully analyzes the Infill Alternative, including an updated
economic impacts assessment that credibly compares the predicted economic impacts and
user-day estimates to existing alternatives.
If any expansion of EMR outside current permit boundaries is still pursued, issue a
supplement EIS for public comment that fully analyzes an Infill Alternative and compares
the impacts to existing alternatives.
Reconsider and reject the proposal to expand to the north impacting Middle Boulder Creek,
including construction of the Placer Lift and new trails near MBC and a new bridge across
the creek.
Withdraw the Forest Plan Amendment that would remove protection of riparian
vegetation along Middle Boulder Creek.
If any facilities (lifts, runs, roads, buildings, etc.) would be constructed in this
corridor, analyze how composition, structure, function, and ecological integrity of
the riparian area would be maintained.
In a draft supplemental EIS, analyze alternatives for maximum avoidance of
damage to and destruction of wetlands in full compliance with 40 CFR 230.
![Page 65: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/65.jpg)
65
Reconsider and reject the proposal to expand to the South impacting Jenny Creek backcountry
access, Nordic use, and implicating serious user safety concerns.
If the newly formulated alternative in the DROD is carried forward, fully analyze it as a new
stand-alone Alternative combining Alternative 2 with parts of Alternative 3 to allow
informed public comment and a full disclosure of the impacts of such a proposal. A draft EIS
supplement analyzing the impacts of this new alternative must be issued because the
combined impacts were not analyzed in the DEIS or subject to public comment under NEPA.
If any version of the Jolly Jug pod will be considered, relocate the Jenny Creek backcountry
trail or provide another solution to the problem of alpine skiers intersecting backcountry
travelers in the Jolly Jug Pod.
Before approval of any action alternative:
Heed Boulder County’s request to ensure the project is consistent with County zoning
and land-use designations by avoiding construction of a new bridge across MBC and
impacts to the sensitive environmental resources and habitat on adjacent lands
including Chittenden Mountain.
Heed the Town of Nederland Parks, Recreation & Open Space Advisory Board
request to reject the Middle Boulder Creek expansion proposal
Heed Colorado Parks and Wildlife’s comment that the proposed northern expansion
could significantly impact or eliminate use of the land above MBC as an elk
migration corridor
Heed EPA comments regarding fen wetlands by avoiding direct and indirect impacts
to such wetlands in reconfiguring the Corona lift
Ensure full compliance with the Watershed Conservation Practices Handbook by
locating all facilities outside the Water Influence Zone. At a minimum, do not allow
any grading in the WIZ.
Conduct a detailed, comprehensive Class III survey of archaeological resources using
professionally approved methods, including the proper spacing of transects. Report
the results to the public and interested professional archaeologists, and invite
comments prior to finalization.
![Page 66: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/66.jpg)
66
Gather sufficient wind data to demonstrate that the proposed new Placer Lift would
indeed be less susceptible to wind compared to other lifts at EMR.
Reduce cutting of new runs and creation of new glades/tree skiing areas so that: fen
wetlands are entirely avoided, large intertrail islands are not fragmented, snow
compaction in lynx habitat is not increased, and the project complies will all measures
in the SRLA.
Demonstrate that EMR will comply with the limit of 5000 lift tickets sold daily.
![Page 67: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/67.jpg)
67
List of Exhibits to Conservation Groups Objection
Exhibit 1 Letter from GMUG National Forest Supervisor Charles S. Richmond to owners of
Crested Butte Mountain Resort, November 5, 2009.
Exhibit 2 May 6, 2010 decision on CBMR’s appeal of December 18, 2009.
Exhibit 3 BLM Press Release on Roan settlement.
Exhibit 4 Army Corps of Engineers Wetland Determination letter, April 25, 2013, to
Western Ecological Resource, Inc.
Exhibit 5 Links to references for Archaeological Resources.
Exhibit 6 Evaluation Process for Eldora Mountain Resort MDP and Potential Projects,
signed by Arapaho-Roosevelt National Forest Supervisor Glenn Casamassa on
February 18, 2011.
Exhibit 7 Letter from Boulder County concerning the Lawler-Tasaday Easement,
November 9, 2006
Exhibit 8 Map of Lawler-Tasaday Easement
Exhibit 9 Letter from Dave Hallock to EMR, March 7, 2010
Exhibit 10 MBCC Infill Alternative from website, summary and map
Exhibit 11 List of References Cited in Archeological Resources Section VI of Objection
Exhibit 12 Letter by Pete Morton, PhD, Senior Economist, Conservation Economics
Institute, May 3, 2014
Exhibit 13 USFS Approves EMR Expansion, Nederland Mountain-Ear newspaper, March
27, 2015
Exhibit 14 Expanding Interests, 5280 Magazine, November 2014
![Page 68: INTRODUCTION - a123.g.akamai.neta123.g.akamai.net/7/123/11558/abc123/forestservic... · resorts in North America, and far and away the biggest employer and economic engine in all](https://reader033.vdocuments.us/reader033/viewer/2022060207/5f03ed0e7e708231d40b73a5/html5/thumbnails/68.jpg)
68
Exhibit 15 Resort's neighbors see bumps ahead with possible Eldora expansion - Eldora and
Nederland residents voice concerns about ski area's growth, Boulder Daily
Camera, February 21, 2015
Exhibit 16 Eldora Mountain Ski Resort gets preliminary go-ahead for expansion, Fox 31
Denver, March 17, 2015,
Exhibit 17 Eldora Mountain Resort's expansion plans get green light from feds U.S. Forest
Service process allows 45 days for objections to be filed, Boulder Daily Camera,
Marc 17, 2015
Exhibit 18 Feds bless Eldora ski area expansion; environmental groups cry foul, Denver Post
March 18, 2015
Exhibit 19 Bill Thibedeau: Eldora expansion decision flawed, Boulder Daily Camera, April
29, 2015
Exhibit 20 Boulder County renews opposition to Eldora's expansion plans Monday ends 45-
day window for objecting to expansion details, Boulder Daily Camera, April 30,
2015