intern operations project
TRANSCRIPT
Intern Operations Project2012
Derek Waldron
Interiors/ Special ProjectsFoulger-Pratt Contracting, LLC.9600 Blackwell Road, Suite 200Rockville, MD 20850
Greystone Servicing Corp.
• Project Overview• Schedule Updates• Submittal Process• Request For Information• Cost Summary• Jobsite Reports
Greystone Servicing Corp.Project Overview
• Located at Rockville Metro Plaza I• 111 Rockville Pike, Suite 1150
Rockville, Maryland 20850
• Estimated SF 9345• Preconstruction estimated value of $328,400• Project Manager - Patrick Renzi• Superintendent – Gordon MacDonald• Building Engineer – Marty Patterson
Greystone Servicing Corp.
Project Overview
Greystone Servicing Corp.Project Overview- Subcontractors
• Cavalier Fire Protection, Inc. - $4,650• Control Tec - $54,000• Economy Glass of Calvert, Inc. - $28,000• Inspiration Plumbing Company - $9,800• McClary Tile, Inc. - $5,230• MDC Construction - $44,000• Precision Wall Tech, Inc. - $9,300• Specified Woodworking - $12,228• Tyson Floors - $33,699• W & W Electric Co., Inc. - $81,500• Cameron Concrete Scanning, LLC:
Greystone Servicing Corp.Submittals
Preferred Submittal Process
Subcontractors
F.P.C.
Architect
F.P.C.
Greystone Servicing Corp.Schedule
Greystone’s Submittal Process
Greytsone Servicing
Subcontractors
F.P.C.
Architect
F.P.C.
Greystone Servicing Corp.Schedule
Greystone Servicing Corp.Schedule
Greystone Servicing Corp.Schedule
Week 1-2 Week 3-4 Week 5-6 Week 7-8 Week 9-10
Mobilize Mechanical Hang Drywall Install Lighting Fixtures Drop Ceiling Tiles *
Site Make Safe Frame Partitions Install Doors & Frames Plumbing (Ceiling) Paint (2nd Coat)
Salvage & Demo Electrical/ Inspections Install Lighting Fixtures Prime & Paint (1st Coat) Install Glass Partitions
Layout Partitions Install Ceiling Grid * Plumbing (Ceiling) Install Millwork Install Carpet & Trim
Plumbing (Walls) Rework Sprinkler Heads
Hang Drywall
Greystone Servicing Corp.Schedule
Long lead items include:• Carpet• Glass• Light Fixtures
Greystone Servicing Corp.Progress Photos
Greystone Servicing Corp.Request for Information
• Done via email but using same process as submittals
• Problems faced:– Too many people involved– Client’s uncertainty held up some work from being
accomplished– Continuous change
Cost Summary
Cost Summary
Cost Summary
Cost Summary
Cost Summary
Greystone Servicing Corp.Daily Report
Intern Operations Project2012
Thank You!!