interconnection costing model update study · costing methodologies - best practice the adoption a...
TRANSCRIPT
Interconnection costingmodel update study
November 2011
www.pwc.co.uk
Contents
Section Page
Interconnection pricing alternatives 6
Costing methodologies – alternatives 8
PwC
Costing methodologies – other issues 15
Costing methodologies – commonpractice
18
Costing methodology 20
Projected timeline 34
Issues raised at initial workshop 36
Introduction
PwC
Purpose of this document
The Uganda Communications Commission (UCC) has commissioned PwC to carry out anupdate/redevelopment of the interconnection costing model that was developed in 2009in order to take into account the changes that have taken place in the Ugandantelecommunications market including changes in technology, services and demandamong others.
As part of the process, the UCC has determined that operators should be allowed tocomment on the methodology to be used.
PwC
comment on the methodology to be used.
This document outlines the methodology that will be used, the proposed structure of themodel and services to be included among others.
Operators are therefore invited to comment on this document and the outlinedmethodology.
Comments on this document can be submitted to the UCC until the 15th ofDecember 2011.
Summary of the proposed approach
The proposed model approach will be:
• Single GSM network modelled
• LRIC
• Forward looking
• Hybrid
PwC
• Hybrid
• EPMU
• Average operator
• Scorched node
The description and discussion of the methodology is presented in the next sections ofthis document.
Interconnectionpricing alternatives
PwC
Interconnection pricing alternatives
Interconnection
Regulated Negotiated
Cost based
FAC
PwC
Price cap
Retail minus
Benchmark
LRIC
Historical/current cost
Mark-up type
Historical/current cost
Top down/bottom up
Costingmethodologies -alternatives
PwC
Costing methodologies - alternatives
Methodology Description Positives Negatives
Fully AllocatedCosts
A system of full cost absorptionwhere all costs are attributed toservices.
Transparent andreconcilable
Captures the real
Embeds economicallyinefficient allocation ofresources
A clear majority of regulators are using an incremental costing model or are progressingtowards it. This is typically lower than average costs in the presence of economies of scaleand scope.
PwC
services.
Takes as a starting point theaccounts of an operator and‘drills down’ into the accounts(FAR, cost centres)
Captures the real(actual) costs of doingbusiness
Allows full recovery ofcosts
resources
Incrementalcost
The additional cost of providingfor an additional increment ofoutput (or cost avoided if theproduct is removed).
CVRs are used to differentiatebetween common and jointcosts.
Efficient resourceallocation
Economic theorysuggest that marginalcost is the basis foroptimal prices
May create costrecovery issues, due tohigh fixed common andjoint cost in telecomindustry
Costing methodologies - alternatives
AccountingConvention Description Positives Negatives
Historical Cost recorded at the purchase orconstruction price
Transparent andreconcilable
Assesses the pastbehaviour, which may
The majority of regulators have forward-looking models, matching the period ofmodelling with the period of regulation, although including some uncertainty regardingfuture demand and new services
PwC
construction price reconcilable behaviour, which maynot relevant for futuredecisions
Forwardlooking(Long run)
Cost based on the current value ofthe assets
A forward looking long runapproach to costs assumes that allinputs are variable in the long run(number of employees, capitalcharges etc.) and thereforeinterconnect charges include areturn on capital.
Supports economicallyefficient decisions
Relevant costs for a newentrant
Establishes target costs
Complex modelling
Incorporatesassumptions
May give volatilemovements in profitover time
Costing methodologies - alternatives
Approach Description Positives Negatives
Top down Costs are taken from theaccounting record and areallocated to services based ondemand and allocation rules..
Transparent andreconcilable
Embeds economicallyinefficient allocation ofresources
A common type of model is a hybrid model, allowing for an efficient network construction andensuring in the same time reconcilability with the actual data. In other words, a bottom-up approach isused and accounting information is then used to cross check.
PwC
demand and allocation rules..
Bottom up Engineering model that estimatesthe cost of a theoretical networkon a green-filed site basis. Themodel will include networkdimensioning rules for differentsizes of demand.
Allows for constructionof an efficient network,supportingeconomically efficientdecisions
Economic measure ofdepreciation
Establishes target costs
May understate cost
Less good at modellingopex and indirectinvestments
May not capture ‘realworld’ issues
Complex
Hybrid An extension to the bottom-upmodel, where results arecompared to the actual data of theoperators.
Carries all benefits of abottom-up model, plusensures a coherencewith the actual data
Carries all issues of abottom-up model, butprovides for mitigationactions (adjustments)
Costing methodologies – alternatives
Mark up Description Positives Negatives
Zero mark-up No mark-up applied Stimulates marketentry
Threatens viability ofthe provider
Equi- Mark-up allowing recovery of Balances conflicting Inefficient to some
Regulators have nearly always adopted an EPMU mark-up for the recovery of fixed andcommon costs. Ramsey mark-up would be an appropriate alternative, but difficulties inestimating demand elasticity made implementation difficult.
PwC
Equi-proportionalmark-up(EPMU)
Mark-up allowing recovery offixed costs pro rata to incrementalcosts
Balances conflictingobjectives
Enable common andjoint costs recovery
Inefficient to somedegree, partly offsetsthe benefit derived frommoving away from FAC
Ramseymark-up
Mark-up inversely proportional todemand elasticity
Applied in non-competitivemarkets, with high fixed commoncosts
Promotes efficient finalservice prices
Depends on flexibilityof retail prices
Difficult to quantifyelasticity
Opportunitycost mark-up
Mark-up to incremental costrelated to the lost contribution oftraffic migrated to theinterconnecting operator
Promotes faircompetition
Ensures viability ofincumbent
Provides weakefficiency incentives
Does not addressmonopoly profits
Costing methodologies – alternatives
Operator Description Positives Negatives
Actualoperator
The model incorporates real dataabout an operator, such as marketshare, network traffic and
Captures differencesbetween operators
Calculates specific
Needs a separate modelfor each operator
Preserves inefficiencies
When choosing one of these approaches, the Regulator should analyse the costdifferences between operators and whether they can be quantified in a hypothetical model(of an efficient operator).
PwC
coverage.Calculates specifictermination costs
Preserves inefficiencies
Hypotheticaloperator
Parameters are not those of aparticular operator and it hasconsiderable flexibility
No confidentialityissues
One model onlyrequired
Irrelevant where thereare fundamental costdifferences in operators
Averageoperator
This is a mix of the hypotheticaloperator and actual operatormodels.
Enables the calculationof one IC rate
Addresses marketspecific issues
Needs a separate modelfor each operator
New entrant This is a form of hypotheticalmodel, looking at the parametersof a potential new entrant.
Incentivises newentrants
Disregards the specificcosts and limitations inthe market
Costing methodologies – alternatives
No of years Description Positives Negatives
Single year Uses a single year as an anchorpoint for multi-year regulatedprices
Simple
Does not requireforward-lookingassumptions
NRA cannot carry outcost modellingexercises each year
It may need a
The majority of the models available on the market are single year models, although it isunlikely a Regulator will carry a costing exercise every year.
PwC
assumptions It may need apercentage assumptionto update the chargeyearly
Multi-year Calculates differenttermination rates for severalyears
Allows multi-yeardepreciationmethodology (economicdepreciation)
Alternative networkdevelopments can bemodelled
More complex
Require forward-looking assumptions
Costingmethodologies –other issues
PwC
Symmetry
Issues with multiple rates:
• Confusing for customers from having different rates for calling subscribers of different operators,even if both were for example, mobile operators;
• Operators would have problems setting prices, billing and running settlement systems betweenthemselves with a multitude of rates;
There are demonstrable differences in cost for delivering traffic on the different types ofnetwork, which are unrelated to inefficiencies
PwC
Volume
• Operators can pass their inefficiencies to customers;
• Limited incentives for cost minimisation;
• New entrants are encouraged to set up cost efficient networks.
Setting single rates – alternatives:
• As the lowest rate of the group of operators;
• As the highest rate of the group of operators;
• As a simple average of the operators;
• As a weighted average of the operators.
Common practice:
• The use of a weighted average, with the weights based on traffic volumes, on the basis that thisshould result in the overall profitability of the industry being close to the reasonable rate of return.
Symmetry
Benchmark – ERG study
• An ERG study on asymmetry (European Regulators Group) concluded that termination rates shouldnormally be symmetric and asymmetry, acceptable in some cases, requires an adequate justification.
• Potential reasons for asymmetry include exogenous factors, e.g. 900Mhz has lower cost than1800Mh and less are needed for the same coverage.
PwC
Volume
• However this should be mitigated by Regulators, by eliminating cost differences due to frequenciesallocation, either by aligning spectrum endowment of operators or by ensuring that licenses areacquired at market price, so that the asymmetry can be removed.
– 8 operators chose the cost reference of an efficient operator
– 1 uses the lowest cost of all the MNOs
– 3 use an average or a weighted average of costs of all the MNOs
– 2 use the highest costs of operators
– 2 use the actual costs of each operator
– 4 use a benchmark
– 5 did not decide yet
Costingmethodologies –common practice
PwC
Costing methodologies - best practice
The adoption a forward looking, hybrid, symmetrical, long run incremental cost approachrepresents best practice among a variety of competing methods
• In order to achieve efficient resourceallocations, interconnection chargesshould be cost based
• FAC is sometimes used in the interim
With LRIC based prices, competitors areable to decide whether to use anincumbent network or build their own
LRIC calculates the costs at which areasonably efficient operator wouldproduce a required service
PwC
Cost
Incremental cost of A
Standalonecost of B
Volume
mc1 unit
Long-run Incremental CostFully Allocated Costsproduce a required service
Cost
Volume
Averagecost of B
AB
Averagecost of A
AB
Costingmethodology
PwC
Bottom-up LRIC Model
Key characteristics
• Builds a hypothetical network
• Engineering model designed to meet a given level of demand at a prescribed grade ofservice
• Allows for construction of an efficient network
• All inputs are variable in the long run (number of employees, capital charges etc.)
PwC
• All inputs are variable in the long run (number of employees, capital charges etc.)
• CVRs are typically specified through network engineering rules, rather than explicitlycaptured as percentage relationships between costs and volumes.
• Includes a mark-up to cover fixed common and joint costs
• Retail costs are not to be recovered through interconnect rates since interconnectservices are wholesale services which do not require retail activities
Key modelling concepts
• Basis for valuing asset prices is the replacement cost of an asset as derived from theapplication of current cost accounting (CCA)
• Apply the Financial Capital Maintenance concept
• An annuity approach is used in the model to estimate the annualised capital costs,including the cost of capital
Bottom-up LRIC Model
PwC
including the cost of capital
• Use Efficient component Pricing Mark-Up (EPMU) approach
• Scorched node – current location and number of network nodes are the basis for themodelled network topology
Example: Mobile Operator: Main network elements modelled
• Switching and Access
- Base Transceiver Stations
- Base Station Controller
- Mobile Switching Centre
- Home Location Register
• Platforms
INHLR PSTN
MSC MSC
INSMSC ININ
Bottom-up LRIC Model
HLR INSMSC
PwC
- Intelligent Network
- SMS Platform
- Voicemail Platform
• Transmission
- Microwave
- Cable (copper/fibre)
- Satellite
• Technologies modelled:
- Options: 2G only / 3G only / 2G-3G;
- NRAs many times chose to ignore 3G on thebasis that operators would invest in 3G if it isa cheaper technology, therefore there no risk of under-recovered cost by including 2G only;
- 3G modelling ultimately depends on the extent and type of services delivered
B ayN etwo rks
BSC
BTSBTS
MSMSMSMS
Bay N etwor ks
BSC
BTSBTS
MSMSMSMS
The following table lists the proposed services to be modelled. The final list will depend on theinformation that is actually provided during the data request and the consultation regarding theservices that are actually provided.
Services modelled - Voice
Voice services
Voice services Outgoing On-net
Voice services Outgoing Off-net to mobile
Voice services Outgoing Off-net to fixed
Voice services Outgoing Off-net to international
PwC
Voice services Outgoing Inbound roaming
Voice services Outgoing Calls to Voicemail
Voice services Outgoing Outgoing on-net IP voice traffic
Voice services Outgoing Outgoing off-net IP voice traffic
Voice services Outgoing Outgoing other calls not included above
Voice services Incoming Calls from other Mobile operators
Voice services Incoming Calls from Fixed operators
Voice services Incoming Calls from international
Voice services Incoming Inbound roaming
Voice services Incoming Incoming off-net IP voice traffic
Voice services Incoming Incoming calls not included above
Services modelled – Other services
SMS messages
SMS Messages Outgoing On-net
SMS Messages Outgoing Off-net to mobile
SMS Messages Outgoing Off-net to international
SMS Messages Incoming From other mobile
PwC
SMS Messages Incoming From international
MMS messages
MMS Messages Incoming On-net
MMS Messages Incoming Off-net
MMS Messages Outgoing On-net
MMS Messages Outgoing Off-net
Data traffic
Data traffic - Traffic in Mb
Model structure
Key8. Core
2. Demand
7a. Radio
4. Networkdesignparameters
5. UnitInvestment &opex
6. NE Demand
3. Routeingfactors
1. Masterfiles
7b. Radio
PwC
Key
Input sheet
Calculationsheet
Control
8. CoreEquipmentdimensioning
11. ServiceCosting
7a. RadioNetworkDimensioning(2G)
A. Results10. AnnualizedNetwork cost
6. NE Demand
9. Transmissiondimensioning
NetworkDimensioning(3G)
Estimation of network elementdemand
Usage(calls, SMS
etc)
PwC
Unsuccessful%, Holding
times
RouteFactors
Busy Hour &SMS Factors
NetworkElementDemand
Radio dimensioning
Average cellradius
Area of eachregion
No of requiredcells forcoverage
GSM 900Spectrum
PwC
Additionalcapacityrequired
CapacityPlanningFactor
Grade ofService
ErlangTable
coverage
Capacityprovided bycoverage cells
Traffic No of TRX for900 and 1800
TrafficDistribution(by area)
Trafficdemand byarea type
Trafficdemand(radio BHE)
TRX/Sector/Cabinetcapacity
GSM 1.800Spectrum
Additionalcapacity tobuild
Total number ofsites (900 onlyand shared)
Number ofcabinets
Number ofBSC
TRX per BSCcapacity
Core equipment dimensioning
Capacityplanningfactor
Traffic percore platform
PwC
No. of MGW,MSS, HLR,SMSC, etc.
No ofsubscribers
Minimumnumber ofcore platforms
Capacity percore platform
Transmission dimensioning
Trafficbetweenelements
Number ofsites/nodes
# of radio andfibre links
Distribution oflinks by type
Av no ofmicrowavehops
PwC
elements
Regionaltrafficdistribution
Number oflinks by typeand capacity
Standard linkcapacity
No of Radioequipmentelements
Averagedistancebetween links
Km of fibreand # ADMsneeded
Number ofcore nodes
Traffic mappingbetween corenodes
Routercapacity
Number ofrouters
Estimation of total cost by NE and unit cost
• Having dimensioned the equipment, total investment costs are calculated based oncurrent equipment prices and related costs.
• Total investment costs are then annualized based on asset lives and price trends.
• The mark-ups and license costs are computed into the NE annualized cost.
• Finally, unit cost of service are calculated based on demand by each service, therouting factors and annual NE costs.
PwC
WACC
Dimensionedswitchingequipment
License cost
AnnualisedEqpt costs
Transmissioncosts
Network costsby NE
Total costsby NE
Opex andCapexmark-ups
Dimensionedaccessequipment
Dimensionedtransmissionequipment
Demand byservice
Routingfactors
Unit cost byservice
Equipmentcost
Annualization procedure – tilted annuity
The value of an asset may be influenced bya number of factors including:
• Its running costs and changes in runningcosts over its lifetime;
• The value of its outputs and changes invalue of outputs over its lifetime;
ntt
r
i
irIC
1
11
.01
PwC
• Its productivity (in terms of the volumeof outputs it can generate) and changesin productivity over its lifetime; and
• The existence or expectation of achallenger asset (i.e. an alternativetechnology), which threatens to redefinethe modern equivalent asset.
The best approach for annualization istherefore using a tilted annuity approach.
Where:
C is the constant annual capital changein period t
It=0 is the replacement value of the assetat the start of the period
r is the cost of capital
n is the useful life of the asset
i is the annual change in the price of theasset.
32
WACC methodology
• The cost of capital is calculated using relevant benchmarks and publically availabledata.
• The result is the pre-tax WACC which will be used for the annualization
Post -Tax WACC =
Ke(E/V) + Kd(1-Tx)(D/V)
Target Gearing
Pre - Tax WACC =
After-Tax WACC/(1 -Tx)
PwC 33
Cost of Equity
Ke = Rf + ße(Rm-Rf)
Cost of Debt
Kd = Rf + Pd
Equity Beta
ßeRisk Free Rate
Rf
Debt Premium, PdMarket Risk Premium
Rm-Rf
Corporate Tax Rate Tx
Target Gearing
D/V
E/V
Country risk
CR
Projected timeline
PwC
Key activities and deliverables
Below is the proposed timeline of this project.
Please note that in order to achieve this timeline it will be crucial that operators submitthe complete data request on time.
• 12th December 2011: PwC to receive complete data request by all operators.
PwC
• 12th December 2011: PwC to receive complete data request by all operators.
• 12th – 16th December 2011: PwC to have meetings with operators in Kampala todiscuss received data.
• December 15 2011: UCC to receive responses on proposed model methodology
• Week of 30th January: Presentation of final results to operators
Issues raised atinitial workshop
PwC
Key activities and deliverables
Some of the issues that were raised during the workshop carried out on November 1st.2011 include:
• Enforcement of compliance with Regulations
• Timeline for implementation after issuance of final report by PwC
• Possibility of leaving interconnection rates to bilateral negotiations
PwC
• Possibility of leaving interconnection rates to bilateral negotiations
• Possibility of incorporating network externality
• Effects of current economic turmoil and high inflation on the model / sources are to beused for inflation projections
• Effect of operators having and operating old assets
• Possibility of using international benchmarks, including benchmarks of neighbouringand other Sub-Saharan countries
• Operator to be modelled (e.g. Average, existing, most efficient, etc.)
• Cost of SMS messages
Key activities and deliverables (cont)
• Scope of interconnection study (does not include the financial regulation aspects ofMobile Money)
• Possibility of using asymmetric tariffs (pros and cons)
• Desirability of national roaming
• How to take into account infrastructure sharing
PwC
• How to take into account infrastructure sharing
• Effect of transit traffic
• Benefits of a decentralised point of interconnection
Contact us
This publication has been prepared for generalguidance on matters of interest only, and does notconstitute professional advice. You should not actupon the information contained in this publicationwithout obtaining specific professional advice. Norepresentation or warranty (express or implied) isgiven as to the accuracy or completeness of theinformation contained in this publication, and, to theextent permitted by law, PricewaterhouseCoopersLLP, its members, employees and agents do notaccept or assume any liability, responsibility or dutyof care for any consequences of you or anyone elseacting, or refraining to act, in reliance on the
Telecoms and Technology, UK
+44 20 7804 3112
+44 7808 904 351
Michael Hardt
acting, or refraining to act, in reliance on theinformation contained in this publication or for anydecision based on it.
© 2011 PricewaterhouseCoopers LLP. All rightsreserved. In this document, “PwC” refers toPricewaterhouseCoopers LLP (a limited liabilitypartnership in the United Kingdom) which is amember firm of PricewaterhouseCoopersInternational Limited, each member firm of which is aseparate legal entity.
Telecoms and Technology, UK
+44 20 7212 6626
+44 7740 241 166
Tom Mowat
Telecoms and Technology, UK
+44 207 213 8119
+44 7715 486839
Carlos Soto