intellipipe moving closer to commercial reality

1
Mike Reeves, GrantPrideco IT’S BEEN SEVERAL years since Grant Prideco, Novatek and the US Department of Energy first announced successful field trials of IntelliPipe ® , a high-speed drill pipe telemetry system. At the time many within the industry expressed doubts if such a system could make the leap from research project to commercial product. However, recent updates indicate this transition is already well underway. IntelliPipe is one of a suite of intelligent drill string components offered by Intel- liServ Inc., a company owned jointly by oilfield tubular manufacturer Grant- Prideco and Utah based Novatek. Using electrical cable, the IntelliPipe system transmits data from typical downhole sensors: MWD, LWD and rotary steer- able tools, with speeds on the order of 1 million bits per second. (In contrast to conventional mud-pulse MWD technolo- gy, which transmits data at rates up to 12 bits per second). The cable is attached to the inner pipe wall, and data is transmitted across tool joints via inductive couplers. These couplers are circular in design and require no special orientation of the tool joints. Essentially, the pipe is a modified version of conven- tional drill pipe, designed to look and behave just like standard tubulars with- out the need for special handling tools or processes. The system uses amplifi- cation joints or IntelliLinks ® at 1,000- foot intervals to boost the data signal. These amplification joints also have the ability to house measurement sensors, allowing data to be collected along the length of the drill string. Finally, a rotat- ing sub on the top drive delivers the data to surface workstations and servers. Since their initial industry launch, the IntelliServ team has been focused on the development and field-testing of a vari- ety of system components: In early 2003 IntelliServ conducted it’s first full drilling test of an IntelliPipe string at the Rocky Mountain Oilfield Test Center in Wyoming. Over 4,300 ft of 5 7 / 8-in. IntelliPipe and IntelliHWDP ® were utilized to side-track an existing well from a cement plug and then drill almost 400 ft and ream over 600 ft of hole. Throughout program, the IntelliS- erv team was able to establish and maintain two-way communication along the length of the string, transmitting basic temperature and shock data at speeds in excess of 1 million bps. Almost 4,000 ft of IntelliPipe has been in constant use at a private US test site since the summer of 2003. The string has been subjected to a full array of wellsite operations, including extensive drilling, reaming, tripping and cement- ing. IntelliServ has expressed satisfac- tion with the mechanical performance of the pipe during these tests and seem set to continue with ever more challenging operations in 2004. In addition, IntelliServ has worked closely with one of the industry’s largest drilling jar manufacturers and has suc- cessfully tested a first-generation Intel- liJar ® , a tool with all the mechanical properties of a standard drilling jar while supporting the transmission of IntelliServ data at high speeds even dur- ing jarring operations. The IntelliServ team is receiving posi- tive feedback from a number of US oper- ators and are confident the IntelliPipe system will be deployed to an active commercial well-site during the spring of 2004. Several major oilfield service companies have also expressed interest in the system and appear ready to com- plete the work necessary to link existing downhole tools to the network. The ultimate prize for IntelliServ, and the industry at large, is the opportunity to take advantage of high-speed, high- volume, bi-directional drilling data in real-time. Such a system offers a num- ber of advantages over current technol- ogy: Instantaneous data transmission will eliminate non-productive time asso- ciated with the low data rates offered by mud pulse telemetry; high-volume data transmission will allow real-time deliv- ery of logging information typically only available after drilling is finished (for example, fullbore images and seismic wave forms that have the potential to further improve wellbore placement); and bi-directional communication that could bring true closed-loop drilling sys- tems to fruition as well as allowing pre- cise control of mechanical tools like under-reamers and variable-gauge sta- bilizers. However, it’s the network’s ability to support distributed measurement points that may offer the biggest short- term prize. With measurement pack- ages placed at regular intervals along the string, drillers will have full visibili- ty of their wellbores at all times. Annu- lar pressure, vibration and temperature profiles from surface to TD should allow true pressure controlled drilling, improved drilling efficiency and, most importantly, enhanced well-control capabilities. A team of over 70 engineers work exclu- sively on IntelliPipe related projects and have so far completed over 11,000-feet of IntelliPipe for use in future field trials. IntelliPipe, IntelliLink, IntelliHWDP and IntelliJar are registered trademarks of IntelliServ Inc. March/April 2004 D R I L L I N G CONTRACTOR 43 Intellipipe moving closer to commercial reality The system uses amplification joints or IntelliLinks ® at 1,000-foot intervals to boost the data signal. These amplification joints also have the ability to house measurement sen- sors, allowing data to be collected along the length of the drill string.

Upload: others

Post on 04-Dec-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Mike Reeves, GrantPrideco

IT’S BEEN SEVERAL years sinceGrant Prideco, Novatek and the USDepartment of Energy first announcedsuccessful field trials of IntelliPipe®, ahigh-speed drill pipe telemetry system.At the time many within the industryexpressed doubts if such a system couldmake the leap from research project tocommercial product. However, recentupdates indicate this transition isalready well underway.

IntelliPipe is one of a suite of intelligentdrill string components offered by Intel-liServ Inc., a company owned jointly by

oilfield tubular manufacturer Grant-Prideco and Utah based Novatek. Usingelectrical cable, the IntelliPipe systemtransmits data from typical downholesensors: MWD, LWD and rotary steer-able tools, with speeds on the order of 1

million bits per second. (In contrast toconventional mud-pulse MWD technolo-gy, which transmits data at rates up to12 bits per second). The cable isattached to the inner pipe wall, and datais transmitted across tool joints viainductive couplers. These couplers arecircular in design and require no specialorientation of the tool joints. Essentially,the pipe is a modified version of conven-tional drill pipe, designed to look andbehave just like standard tubulars with-out the need for special handling toolsor processes. The system uses amplifi-cation joints or IntelliLinks® at 1,000-foot intervals to boost the data signal.These amplification joints also have theability to house measurement sensors,allowing data to be collected along thelength of the drill string. Finally, a rotat-ing sub on the top drive delivers the datato surface workstations and servers.

Since their initial industry launch, theIntelliServ team has been focused on thedevelopment and field-testing of a vari-ety of system components:

In early 2003 IntelliServ conducted it’sfirst full drilling test of an IntelliPipestring at the Rocky Mountain OilfieldTest Center in Wyoming. Over 4,300 ft of5 7/8-in. IntelliPipe and IntelliHWDP®

were utilized to side-track an existingwell from a cement plug and then drillalmost 400 ft and ream over 600 ft ofhole. Throughout program, the IntelliS-erv team was able to establish andmaintain two-way communication alongthe length of the string, transmittingbasic temperature and shock data atspeeds in excess of 1 million bps.

Almost 4,000 ft of IntelliPipe has been inconstant use at a private US test sitesince the summer of 2003. The stringhas been subjected to a full array ofwellsite operations, including extensivedrilling, reaming, tripping and cement-ing. IntelliServ has expressed satisfac-tion with the mechanical performance ofthe pipe during these tests and seem setto continue with ever more challengingoperations in 2004.

In addition, IntelliServ has workedclosely with one of the industry’s largestdrilling jar manufacturers and has suc-cessfully tested a first-generation Intel-liJar®, a tool with all the mechanical

properties of a standard drilling jarwhile supporting the transmission ofIntelliServ data at high speeds even dur-ing jarring operations.

The IntelliServ team is receiving posi-tive feedback from a number of US oper-ators and are confident the IntelliPipesystem will be deployed to an activecommercial well-site during the springof 2004. Several major oilfield servicecompanies have also expressed interestin the system and appear ready to com-plete the work necessary to link existingdownhole tools to the network.

The ultimate prize for IntelliServ, andthe industry at large, is the opportunityto take advantage of high-speed, high-volume, bi-directional drilling data inreal-time. Such a system offers a num-ber of advantages over current technol-ogy: Instantaneous data transmissionwill eliminate non-productive time asso-ciated with the low data rates offered bymud pulse telemetry; high-volume datatransmission will allow real-time deliv-ery of logging information typically onlyavailable after drilling is finished (forexample, fullbore images and seismicwave forms that have the potential tofurther improve wellbore placement);and bi-directional communication thatcould bring true closed-loop drilling sys-tems to fruition as well as allowing pre-cise control of mechanical tools likeunder-reamers and variable-gauge sta-bilizers.

However, it’s the network’s ability tosupport distributed measurementpoints that may offer the biggest short-term prize. With measurement pack-ages placed at regular intervals alongthe string, drillers will have full visibili-ty of their wellbores at all times. Annu-lar pressure, vibration and temperatureprofiles from surface to TD should allowtrue pressure controlled drilling,improved drilling efficiency and, mostimportantly, enhanced well-controlcapabilities.

A team of over 70 engineers work exclu-sively on IntelliPipe related projects andhave so far completed over 11,000-feet ofIntelliPipe for use in future field trials.

IntelliPipe, IntelliLink, IntelliHWDP andIntelliJar are registered trademarks ofIntelliServ Inc. n

March/April 2004 D R I L L I N G C O N T R A C T O R 43

Intellipipe moving closer to commercial reality

The system uses amplification joints orIntelliLinks® at 1,000-foot intervals to boostthe data signal. These amplification joints alsohave the ability to house measurement sen-sors, allowing data to be collected along thelength of the drill string.