integration of the piping into the casing of the hamitabat...

19
| Integration of the piping into the casing of the Hamitabat boiler HRS 19.12.17 1

Upload: others

Post on 17-Jan-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

Integration of the piping into

the casing of the Hamitabat

boilerHRS

19.12.17 1

Page 2: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

Project summary

In the context of a PRP on optimisation of the design of

horizontal HRSGs, an idea for reducing costs was to

reconsider the standard elevations of the boilers. The

implementation of this solution required the development of

equipment in partnership with a supplier.

19.12.17 2

Page 3: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

The project managers

Sponsor: Pierre Blaise: HRS President

PRP 5.2: Re-design of horizontal boilers

Jean-Marie Firquet: HRS Draughtsman

Jean-François Galopin: CTO Energy Sector

Régis Frankard: President of the Storage Department

Mesut Saylamis: HRS Construction Vice-President

Thomas Streel: HRS Project Engineering Vice-President

Participation of Energy LLC in the PRP

Technical development with a supplier

19.12.17 3

Page 4: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

What has been achieved/implemented

“Mechanical” optimisation of the horizontal boilers

Reconsideration of the established standards: height of the lower headers (+4700mm) related to the level of the lowest drain

Reduction in the boiler height: reduction of costs by reduction of BOQs

Specification of a new standard height of the lower headers (+3700mm) by integration of steam piping manifolds into the casing of the boiler, with lateral pipe penetrations through the casing allowed by development of a new expansion joint technology in partnership with a supplier

Innovative aspect in the technical development of high-temperature piping expansion joints with a high degree of shear, a technology necessary for achieving the optimisation

Reduction in BOQs (main steel structure, piping, expansion joints, etc.) and thus of costs of a 3P+R horizontal boiler on the order of €75,000 per boiler

19.12.17 4

Page 5: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

Objective(s) of the project

Objective: increase in competitiveness by reduction of costs

New expansion joint technology

Decrease in the boiler height by 1m

Reduction by 1m of all the main columns of the boiler

Reduction of all the lengths of vertical pipes by 1m (reduction of pressure drops for better performances)

Reduction in the need for insulation on steam pipes (integrated manifolds)

Decrease in the number of pipe penetrations through the casing (decreased heat and energy losses through the casing)

Reduction in the boiler depth by better layout of the steam manifolds

Response to strategic focus 5 by implementation of a creative idea for better competitiveness

19.12.17 5

Page 6: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

Parties affected/concerned

Beneficiaries:

CMI HRS: competitiveness

Final operator: maintenance facilitated (less expansion joints)

CMI client: cost reduction

Partner of CMI for implementation of the development

Assemblers: reduction in the insulation work onsite

People involved (title at the time of involvement):

Jean-Marie Firquet: PRP Draughtsman

Jean-François Galopin: PRP Leader

Régis Frankard: HRS Proposal Vice-President for estimation of savings

Mesut Saylamis: Site Technical Advisor on Hamitabat site

Thomas Streel: HRS Technical Project Manager for Hamitabat Project

19.12.17 6

Page 7: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

Date and scope of

achievement/implementation

Launch of the PRP on 03/12/2010

Finalisation of the PRP on 24/05/2012

Development of the expansion joint technology in 2013

Solution with integration of the manifolds offered as of 2014

Signature of the Hamitabat contract on 19/12/2014

1st placement of an order for high-shear expansion joints on 29/10/2015

1st installation on the Hamitabat site in 2016 in the presence of the partner

1st commissioning in April 2017

In operation since

19.12.17 7

Page 8: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

Method of promotion/media coverage of the

project

PRP followed by sector management

Presentations in the quarterly meeting of the sector

Solution used by LLC for the Woodbridge project

19.12.17 8

Page 9: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

Budget allocated

Idea brought forward in a PRP

Development of the technology by the members of the

PRP in partnership with a supplier

Implementation on project

19.12.17 9

Page 10: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

Sustainable/reproducible nature of the

project

The solution installed has become standard in the design

of HRS.

The solution is always offered when integration of the

manifolds is allowed by the contract.

It involves improvement in an existing product in order to

reassess standards and optimise design to improve the

competitiveness of HRS.

19.12.17 10

Page 11: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

Measured impact

Reduction by 1 metre of the metallic structure: €20,000/HRSG

Decrease in the length of all the vertical piping: €20,000/HRSG

Reduction in the number of expansion joints: €5000/HRSG

Decrease in the boiler depth: €15,000/HRSG

Reduction of the BOQ for external insulation: €15,000/HRSG

19.12.17 11

Page 12: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

The project in pictures

(idea of PRP)

19.12.17 12

BEFORE

AFTER

Page 13: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

The project in pictures

(development)

19.12.17 13

Page 14: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

The project in pictures

(mock-up test)

19.12.17 14

Page 15: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

The project in pictures

(engineering supplier)

19.12.17 15

Page 16: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

The project in pictures

(implementation - installation)

19.12.17 16

BEFORE AFTER

Page 17: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

The project in pictures

(start-up)

19.12.17 17

Page 18: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

The project in

pictures

(standardisation)

19.12.17 18

Page 19: Integration of the piping into the casing of the Hamitabat boilerawards.cmigroupe.com/upload/awards/presentations/30-CMI... · 2017-12-19 · Objective(s) of the project Objective:

|

www.cmigroupe.com

19.12.17 19