integrating risk
TRANSCRIPT
-
8/6/2019 Integrating Risk
1/38
Integrating Risk
Into Project Scheduling
Scott Brunton, PMP MASc MBA
Senior [email protected]
-
8/6/2019 Integrating Risk
2/38
Why Bother
Well Cross That Bridge When We Get There
That Will Never Happen On This Project Well Fix Them In The Next Version
Weve Always Done It This Way
Bearers of Bad News Get Punished
-
8/6/2019 Integrating Risk
3/38
PMI PMBOK
Project Risk Management
PMBOK Knowledge Area 11An uncertain event or condition
that, if it occurs, has a positive or
negative effect on a projectsobjective.
There Are No Facts About The Future
-
8/6/2019 Integrating Risk
4/38
Quality
Purpose of Project Risk Management
Identify Factors that are Likely to Impact
Project Objectives
Time (Schedule)
Scope Resources
-
8/6/2019 Integrating Risk
5/38
When Can Risk Occur
-
8/6/2019 Integrating Risk
6/38
Flavors of Risk
Spectrum of Risk
NoInformationPartialInformationFullInformation
Unknown
UnknownsKnown
UnknownsAbsoluteCertainty
-
8/6/2019 Integrating Risk
7/38
Risk According to Dilbert
Scott Adams 08 Nov 1997
United Feature Syndicates, Inc
-
8/6/2019 Integrating Risk
8/38
Risk Management Process
Systematic, Continuous Process
NASA Procedural RequirementsNPR 8000.4 Risk Management Procedural
Requirements
-
8/6/2019 Integrating Risk
9/38
Risk Management Process
Identify
Analyze
Plan
Track
Control
Clearly Articulate
Evaluate, Classify & Prioritize
Mitigation Opportunities
Monitor & Report
Act
-
8/6/2019 Integrating Risk
10/38
Risk Management Process
Risk Statement
Given the tile gap filler material is extended above the
tiles; there is a possibility that the protrusions mightproduce excessive heat during re-entry causingcatastrophic damage to the vehicle.
Identify
DiscoverySTS-114
-
8/6/2019 Integrating Risk
11/38
Risk Management Process
Risk Statement
Given the tile gap filler material is extended above
the tiles; there is a possibility that the protrusions mightproduce excessive heat during re-entry causingcatastrophic damage to the vehicle.
Identify
Risk
Condition
-
8/6/2019 Integrating Risk
12/38
Risk Management Process
Risk Statement
Given the tile gap filler material is extended above the
tiles; there is a possibility that the protrusions mightproduce excessive heat during re-entry causingcatastrophic damage to the vehicle.
Identify
Risk
Consequence
-
8/6/2019 Integrating Risk
13/38
Analyze
Likelihood of Occurrence
Consequences ofOccurrence
5x5 Impact Matrix
Risk Management Process
10 16 20 23 25
7 13 18 22 24
4 15 19 21
2 6 11 14 17
1 3 5 8
Consequence of Occurrence
Very High(5)
High(4)
Moderate(3)
Low(2)
Very Low(1)
Very High
(5)
High
(4)
Low
(2)
Very Low
(1)
LikelihoodofOccurrence
Moderate
(3) 9
12
Low
Moderate
High
I think there is a world market for five computers.- Thomas Watson, IBM President 1943
-
8/6/2019 Integrating Risk
14/38
Plan Risk Management Process
Do Nothing
Hope is not a Strategy Adjust Expectation
Develop Mitigation Activities
Assess Impact of Mitigation
Burn-Down Risk
-
8/6/2019 Integrating Risk
15/38
Track Risk Management Process
Integrate Risk into Project Schedule
-
8/6/2019 Integrating Risk
16/38
Control Risk Management Process
Obtain Approval from Risk Board
Update Risk Registry Request Support for Plan
Resources: To Support Mitigation
Schedule: To Align Delivery
Scope: To Communicate Expectations
Integrate into Cost & ScheduleFormal Implementation
-
8/6/2019 Integrating Risk
17/38
Obtaining Credible Estimates
Overcome Intrinsic Bias
MethodsExpert Judgment
Analogous Estimation
Parametric EstimationThree-Point Estimation
Reserve Analysis
-
8/6/2019 Integrating Risk
18/38
Critical Path Methodologies
Single-Pass
Multi-Pass
Discrete Continuous
Single-PointMulti-Point
Based UponProbability
Distributions
Simulation
-
8/6/2019 Integrating Risk
19/38
Single-Point Estimation
Critical Path Method (CPM)
Developed by DuPont in 1957 Novel, Yet Simplistic, Approach to Project
Network Modeling Requirements
Based on Fixed Estimates for TaskDurations
-
8/6/2019 Integrating Risk
20/38
Multi-Point Estimation
Program Evaluation & Review Technique
Developed by Booz-Allen Hamilton in 1958 Polaris Mobile Submarine-Launched Ballistic
Missile Program
Special Projects Office Contract with US Navy
Acknowledges Randomness SurroundingTask Duration Estimation
-
8/6/2019 Integrating Risk
21/38
PERT
Studied Bias and Reliability of Task DurationEstimates Collected by Variety of Methods
Correlated Estimates with Actual Durationsand Curve-fit Results to Beta Distribution
Closed-form First-Order Estimate
6
)*4( cPessimistiMostLikelyOptimistic
Expected
++
=
-
8/6/2019 Integrating Risk
22/38
Beta Distribution & PERT 3-Point Estimate
Shape Parameters: > 0 and > 0
Unimodal when > 1 and > 1 When = 3 Sqrt(2), = 3 + Sqrt(2)
-
8/6/2019 Integrating Risk
23/38
Limitations of PERT
Nave Task Durations Assumptions
Independent & Uniformly Biased
Does Not Account For Quality of Estimates
Expert, Analogous, Parametric
Assumes Underlying Probability DistributionOf Estimates Can Be Represented By Beta
Deterministic Single Pass Calculation
-
8/6/2019 Integrating Risk
24/38
Multi-Pass/Continuous Evaluation
Reveals Effects of Near-Critical Tasks
Probabilistic Estimation of Task Durations Monte Carlo Simulation
Randomly choose from probability distribution
Used during Manhattan Project in early 1940s
Appropriate When There Is SignificantUncertainty
-
8/6/2019 Integrating Risk
25/38
Defense Acquisition University
Monte Carlo simulation is a statisticaltechnique by which a quantity is calculatedrepeatedly, using randomly selected what-ifscenarios for each calculation
-
8/6/2019 Integrating Risk
26/38
Uniform Probability Distribution
All Choices are Equally Likely
May Lack Enough Information To Estimate
A B
-
8/6/2019 Integrating Risk
27/38
Normal Probability Distributions
Natural First Step
Estimates are Centered
-
8/6/2019 Integrating Risk
28/38
Triangular Probability Distributions
Baseline Distribution
Less Confident Than Normal
A B
-
8/6/2019 Integrating Risk
29/38
Triangular Probability Distributions
Can Be Skewed To Incorporate AsymmetricEstimates
Type 1 Estimator
A B
-
8/6/2019 Integrating Risk
30/38
Triangular Probability Distributions
Can Be Skewed To Incorporate AsymmetricEstimates
Type 2 Estimator
A B
-
8/6/2019 Integrating Risk
31/38
Beta Probability Distributions
Smaller Standard Deviation Than Normal
Implies Higher Confidence in Estimate
A B
-
8/6/2019 Integrating Risk
32/38
Native / Add-in Solutions
Native to MS Project
Single-Point Estimation
3-Point Estimation
Add-in Capability
@Risk by Palisade $795 Standard Version
Full Function 15-day Free Trial
Risk+ by Deltek $695
-
8/6/2019 Integrating Risk
33/38
Risky Business Demonstration
Well Formed Network
No Hard Constraints
Predecessors / Successors Defined80%+ Are Finish-to-Start
-
8/6/2019 Integrating Risk
34/38
Risk+ Analysis Process Steps
1. Develop Well Formed Project Plan
2. Enter Risk Parameters3. Identify Reporting Tasks
4. Run Simulation
5. Analyze Outputs
6. Repeat
Lets Demonstrate
-
8/6/2019 Integrating Risk
35/38
Key Takeaways
Existence of Risk is a Certainty
Risk Impacts Triple Constraint Objectives Continuous Risk Management
Work the Process & Report Results
Record Actions & Outcomes
Probabilistic Simulation of Project Network is
Meaningful and Do-able
-
8/6/2019 Integrating Risk
36/38
For More About Risk+
Deltek
http://www.deltek.com
Seamless Integration with MS Project
Cost & Schedule Risk Histograms
Add Custom Probability Distributions
Probability Branching
VBA Hooks
-
8/6/2019 Integrating Risk
37/38
Failure to Communicate
Modifications Made Without Documentation
-
8/6/2019 Integrating Risk
38/38
Questions
Thank you for attending
Presentation slides will be posted to theMember Area of the MPUG site archive
Phoenix