integrating prince2® and msp™ at the vietnam academy of social science arnaldo pelleni

20
1 Integrating PRINCE2® and MSP™ at the Vietnam Academy of Social Science Eddie Borup, ibp Solutions Arnaldo Pellini, Overseas Development Institute International Congress for Programme, Project and Risk Management London, 10 th -11th February 2009

Upload: bpug-congress

Post on 12-Apr-2017

855 views

Category:

Business


1 download

TRANSCRIPT

Page 1: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

1

Integrating PRINCE2® and MSP™ at the Vietnam Academy

of Social Science

Eddie Borup, ibp SolutionsArnaldo Pellini, Overseas Development Institute

International Congress for Programme, Project and Risk ManagementLondon, 10th-11th February 2009

Page 2: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

2

1) Some information on Vietnam and the Vietnam Academy of Social Sciences

2) A strategic approach to change management

3) Cultural challenges4) Conclusions

Content

Page 3: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

3

1)Vietnam and VASS

Vietnam and VASS

Strategic approach

Challenges Conclusion

Page 4: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

4

• 1000 staff/researchers

• 29 research institutes

• 4 departments

• Ca. 350 projects/year

• Involved in legislative process(Insert picture of VASS)

1)Vietnam and VASS

Vietnam and VASS

Strategic approach

Challenges Conclusion

Page 5: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

5

1)Vietnam and VASS

Vietnam and VASS

Strategic approach

Challenges Conclusion

Types of Projects

Page 6: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

6

1)Vietnam and VASS

Vietnam and VASS

Strategic approach

Challenges Conclusion

Types of Projects

• Institutional

• Ministerial

• State

• Private/external/foreign

Page 7: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

7

Our questions?

2) A strategic approach to change management

• Is VASS research having an influence on policy making in Vietnam?

• How can VASS know?

• How does VASS know they are conducting the right research, at the right time, and in the right sequence?

Vietnam and VASS

Strategic approach

Challenges Conclusion

Page 8: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

8

2) A strategic approach to change management

Vietnam and VASS

Strategic approach

Challenges Conclusion

Storytellers

Engineers

Networkers

Fixers

Page 9: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

9

2) A strategic approach to change management

Vietnam and VASS

Strategic approach

Challenges Conclusion

If we can accept that each Institute is running a multitude of projects/work packages and these should all be contributing towards the Goals of the Institute....

• Then VASS might be a portfolio of Programmes

• Each Institute/Centre a Programme

Could MSP™ be used to “run an Institute”?

Page 10: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

10

2) A strategic approach to change management

Vietnam and VASS

Strategic approach

Challenges Conclusion

Concept

ProjectManagement

VASS PortfolioManagement

Review

Concept

Review

Review

Identifying a Programme

Defining a Programme

Managing theTranches

Running a Programme (Managing the Delivering the Capability

and Realising the Benefit)

Closing a Programme

Identifying aProject

Defining aProject

Running a Project

Closing aProject

Stage

WorkPackage

Stage

Work Package

Stage

Work Package

Institute DecreeAnd stratgey

VASS Decree and strategy

ProgrammeManagement

External Programmes

External Projects

Page 11: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

11

2) A strategic approach to change management

Vietnam and VASS

Strategic approach

Challenges Conclusion

Use the method to implement the method...• Helps with adoption• Introduces common language• Early capacity building• “trial of the trial”

Page 12: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

12

2) Approach

Vietnam and VASS

Strategic approach

Challenges Conclusion

Assurance (on behalf of the board, ensuring that the project is viable, what VASS requires and will be fit for purpose)

All other Institute/Centre/Department DirectorsWhen appropriate various Ministries, Donors, UNDP etc

Sponsoring GroupChaired by Prof Nam

Depending on the benefits and outcomes (BCM’s)

Senior User(Appropriate BCM)

Senior Supplier(Resource Manager)

Executive(Programme Manager)

Project Team (Made up of Team Leaders and staff doing the work, including those required to review the quality of the outputs)

Sponsoring Group via the SRO

(SRO)

Prog Manager

Head of Support (PMO)

Not only Institute resource ie. Library, admin, Scientific Committee (Assurance) Finance, Personal

But also DepartmentsFinanceScientific ManagementAdminPersonal including when Assurance or reviews are completed

Project Support As well

Project Manager (focused on Delivering Outputs

Proj MgrTheme

Proj MgrMinisterial

Proj MgrMinisterial

Proj MgrTheme

Proj MgrInstitute

Proj MgrState

Proj MgrInstitute

Proj Mgr Internationa

Proj MgrTheme

Proj Mgr Institute

Project Organisation

Programme Organisation

*

*

Page 13: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

13

• Promotions are not based on skills• Seniority matters• Political and social hierarchy limits participation and debate

• Communist Party makes decisions

3) Challenges

‘In High Power distance societies, subordinates acknowledge the power of others simply based on where they are situated in certain formal, hierarchical positions.’ Geert Hofstede

Vietnam and VASS

Strategic approach

Challenges Conclusion

Cultural Challenges

Page 14: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

14

• Time for planning and re-planning• Time for procurement• Commitment of individuals• Recruitment and retention• Payment for results...

3) Challenges

‘Madness is an expectation that if you keep doing the same thingsin the same way, you can expect different results” Susan Bloch

Vietnam and VASS

Strategic approach

Challenges Conclusion

Impact on the programme

Page 15: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

15

Typical approachInvestigation > Training > Study tours > Planning for implementation > Hope that it works

4) Conclusion

But here we are in a different contextStart with the end in mind – results focused capacity building... transitioning to a known end state – but we might be facing the wrong way......

Vietnam and VASS

Strategic approach

Challenges Conclusion

Page 16: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

16

Planning and the sense of future

West

Asia

past present future

4) Conclusion

Vietnam and VASS

Strategic approach

Challenges Conclusion

Look at the future

Look at the past

past present future

Page 17: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

17

4) Conclusion

It takes time to make decisions, but when benefits are perceived and decisions are made => things move very quickly

January 2008

Vietnam and VASS

Strategic approach

Challenges Conclusion

Page 18: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

18

4) Conclusion

• We are testing a different way to manage projects in the Vietnamese culture and society

• We are testing flexibility of PRINCE2® and MSP™

• We are learning and so are VASS and our Donors...

Plan – Do - Review

Vietnam and VASS

Strategic approach

Challenges Conclusion

Page 19: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

19

Thank you for your attention

[email protected]@ibpsolutions.co.uk

Page 20: Integrating Prince2® And Msp™ At The Vietnam Academy Of Social Science Arnaldo Pelleni

20

1)Vietnam and VASS

Vietnam and VASS

Strategic approach

Challenges Conclusion

Bao Cap 1975 - 1986

Doi Moi 1986 – 2005

SEDP 2011 – 2020

•Rationing /coupon system for basic goods

•State at fixed price / Inefficient production

•Agrarian reform: market prices land ownership

•Private enterprises + state enterprises

•International integration

•Economic growth•Social policy•Role of civil society