integrating policy, planning, and electricity markets in ...raabassociates.org/articles/van welie...

16
Integrating Policy, Planning, and Electricity Markets In New England Gordon van Welie President & CEO, ISO New England June 10, 2011 Boston, Massachusetts

Upload: others

Post on 29-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Integrating Policy, Planning, and Electricity Markets In New England

Gordon van WeliePresident & CEO, ISO New England

June 10, 2011Boston, Massachusetts

Page 2: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Overview • Policy objectives (environmental requirements and the introduction

of competitive wholesale markets) started the transition of the New England resource base over a decade ago

• The transition has: – begun to accelerate because of prevailing economic conditions

and increasing environmental standards; – created operational challenges, which are becoming

exacerbated as the resource mix changes; and, – driven the need to make further improvements to the regional

wholesale market design, the transmission planning process and system operations

• The region has a successful and productive history of collaborating to solve complex problems – we will need to build on that success to address the upcoming challenges

June 10, 2011 – MA Restructuring Roundtable © 2011 ISO New England Inc. 2

Page 3: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Transition of the Capacity Base Historically Dominated by Oil and Nuclear, has Shifted to Natural Gas and Demand Resources, and may Trend towards Renewables

5%18%

38%41%34%

20%26% 18%**

13%10%

11%

8%

0.4%

7%

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

1990 2000 2010

Capacity (MW)*

Demand ResourcesHydro & other renewablesPumped storageCoalNuclearOilNatural gas

3

* Percentage values are based on a percent of total capacity, including generating resources and demand resources.** The reduction in capacity between 1990 and 2000 is largely due to the shutdown of more than 2,300 MW of nuclear capacity in the 1990s.

June 10, 2011 – MA Restructuring Roundtable © 2011 ISO New England Inc.

Page 4: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Dramatic Shift in Energy Production

4

Source: 2011 System Overview, Planning Advisory Committee, May 23, 2011.

June 10, 2011 – MA Restructuring Roundtable © 2011 ISO New England Inc.

Page 5: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Demand Resources Replace Generation as Capacity • 7% (2300 MW) of the region’s capacity comes from demand

resources today – growing to 10% (3200 MW) in 2013/14

5June 10, 2011 – MA Restructuring Roundtable

© 2011 ISO New England Inc.

Page 6: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Market And Regulatory Conditions Accelerate Transition

• 20% of the region’s capacity comprised of older oil-fired generation that produces only .5% of the region’s energy – Continued fuel/capacity market

pricing pressure– New EPA regulations– Salem station to retire in 2014

• The future of nuclear plants uncertain– Vermont Yankee

Total Oil Capacity6,868 MW

6June 10, 2011 – MA Restructuring Roundtable

© 2011 ISO New England Inc.

Page 7: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Hydro 1133 MW

14%

Landfill Gas34 MW

0%

Wind2836 MW

36%

Nuclear42 MW

1%

Natural Gas3357 MW

42%

Coal44 MW

1%

Biomass431 MW

5%Oil

42 MW1%

Approx. 7,000 MW

7

Looking Ahead, Continued Shift to Natural Gas, Integration of WindNearly 80% of New Generator Proposals are for Wind and Natural Gas

May 2011 Queue, by fuel type; values shown in MW and percent.

June 10, 2011 – MA Restructuring Roundtable © 2011 ISO New England Inc.

Page 8: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Transition Creates Operational Issues Today

• Several operational events in the last 12 months have revealed……. – Uncertain performance of aging supply resources and new

demand resources – Uncertain availability of natural gas generation during peak

winter demand conditions – Lack of system flexibility to recover from large source

contingency

• Reliable and efficient operations today – and successful transition to the future power system -- requires solutions

8June 10, 2011 – MA Restructuring Roundtable

© 2011 ISO New England Inc.

Page 9: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Strategic Planning Initiative LaunchedFive interrelated risks identified, near and long-term components

Resource Performance & Flexibility

Reliance on Natural Gas

RetirementsIntegrating Variable

Resources

Alignment of Planning and

Markets

9

Comprehensive review of markets, planning and operations necessary

June 10, 2011 – MA Restructuring Roundtable © 2011 ISO New England Inc.

Page 10: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Discussions With States and NEPOOL Sectors Refines Risks and Issues

10June 10, 2011 – MA Restructuring Roundtable

© 2011 ISO New England Inc.

Page 11: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Impact, Likelihood and Timing of Risks Identified

11

Resource Performance & Flexibility

Retirements

Alignment of Planning and Markets

Reliance on Natural Gas

Integration of Variable Resources

June 10, 2011 – MA Restructuring Roundtable © 2011 ISO New England Inc.

Page 12: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Significant Analysis in Support of Strategic Planning Effort

• Natural Gas Pipeline Capacity to Satisfy Short and Longer-Term Power Generation Needs

• Gas System Contingencies • Fleet performance and audit procedures• Operating reserve requirements• System impacts of units expected to need infrastructure

upgrades• Interconnection / economic studies of wind integration• Pilot Market Resource Analysis for VT/NH Needs

Assessment• Approaches for reflecting reliability needs in market design

12June 10, 2011 – MA Restructuring Roundtable

© 2011 ISO New England Inc.

Page 13: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Initial ISO Observations

• Solution design and implementation will need to be done in stages to address the most pressing issues first – and lay the groundwork for the longer-term, more complex market and planning issues

• Solutions range from minimal to significant market redesign and reorganization concepts

• In developing solutions, the region should utilize competitive markets and avoid the temptation of having ISO New England do integrated resource planning

13June 10, 2011 – MA Restructuring Roundtable

© 2011 ISO New England Inc.

Page 14: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Initial ISO Observations (cont)• Measures adopted in response to the 2004 Cold Snap

mitigated, but did not solve, the problem of gas availability during peak winter periods

• As gas-fired generation increases and the oil fleet retires, it’s clear that investment in dual-fuel capacity, duplicative resources, or firm access to gas will be required to ensure reliable operations during extreme winter periods -- and in the event of a gas system contingency

• Incorporating these types of long term reliability needs on a proactive basis into market design has not been addressed in any other wholesale electricity market -- and is likely to require several years of effort to achieve a fully integrated solution

14June 10, 2011 – MA Restructuring Roundtable

© 2011 ISO New England Inc.

Page 15: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Initial Solution Concepts • Near-term:

– Incentive/penalty structures for availability and performance– Elimination of barriers to economic repowering – Increase in non-spinning reserves and ramping capability

• Longer-term:– Consistent evaluation of transmission, generation and

demand solutions to meet reliability needs– Market design improvements to procure resources with

more geographic granularity and desired performance characteristics

– Evaluation of regional diversity and deliverability needs

15June 10, 2011 – MA Restructuring Roundtable

© 2011 ISO New England Inc.

Page 16: Integrating Policy, Planning, and Electricity Markets In ...raabassociates.org/Articles/van Welie Presentation_6.10.11.pdf · 6/10/2011  · Hydro 1133 MW 14% Landfill Gas 34 MW 0%

Next Steps• Draft documents refining the

problem statement -- and detailing the possible range and sequence of solutions to be posted next week

• Additional discussions – NECPUC Symposium – NEPOOL Summer Meeting

• Focused solution development phase this fall

• New and revised strategic planning documents on ISO New England’s website

16June 10, 2011 – MA Restructuring Roundtable

© 2011 ISO New England Inc.