integrating lng infrastructure for power generation utilizationlng-world.com/lng_bali2014/slides/lng...
TRANSCRIPT
1
INTEGRATING LNG INFRASTRUCTURE FOR POWER GENERATION UTILIZATION
4th LNG SUPPLY, TRANSPORT & STORAGE INDONESIA
Bali, 19th – 21st May 2014
Main Conference Day 2
Chairani Rachmatullah Senior Manager Primary Energy Planning and Evaluation
PT PLN (Persero)
E L E C T R I C I T Y F O R A B E T T E R L I F E
2
Installed Capacity
48 GW installed capacity to serve 53 million customers with 75% electrification
ratio.
All GFPPs installed and can be operated in 2014 require supply of around 660
TBTU Natural Gas, however only 463 TBTU can be secured.
COAL GAS OIL HYDRO GEOTHERMAL OTHERS TOTAL
IPP 5.02 1.22 0.07 1.20 0.06 0.01 7.59
RENTAL 0.16 0.79 2.71 0.00 - - 3.66
PLN 17.54 12.06 3.00 3.51 0.57 0.00 36.67
TOTAL 22.72 14.07 5.78 4.72 0.63 0.02 47.93
-
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
GW
INSTALLED CAPACITY PER DECEMBER 2013
E L E C T R I C I T Y F O R A B E T T E R L I F E
Electricity Demand Projection 2013-2022
Sumatera: 10,6%
26
TWh
66
TWh
TWh
IT : 10,8%
18 44
TWh
JB : 7,6%
144
TWh
275
TWh
2013 2022
TWh
TWh 188
385
Kalimantan: 10,7% Sulawesi: 10,8%
Indonesia: 8,4%
Papua: 10%
Maluku: 10,9%
Nusa Tenggara: 11,1%
Year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Demand (TWh) 189 208 227 246 266 286 308 332 358 387
ER ( % ) 79.6 82.6 85.9 88.9 91.9 93.7 95.3 96.8 97.4 97.8
E L E C T R I C I T Y F O R A B E T T E R L I F E
4
New Additional 60 GW Power Plants (2013-2022)
Additional Plants to 2022: •CFPP : 38 GW •Hydro : 6.5 GW •GeoPP : 6 GW •CCPP : 5 GW •GTPP : 3.7 GW •Others : 0.3 GW
Additional HV Transmission line : 58.000 kmc Additional S/S Transformer : 134.000 MVA Additional Coal demand: 125 million ton/year Additional Gas demand: 500 TBTU/year
7,878
4,598
3,622 3,637
7,465 6,946
5,204
3,366 3,433
5,332
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
CFPP HEPP GeoPP CCPP GTPP Other Total
E L E C T R I C I T Y F O R A B E T T E R L I F E
Production cost vs Revenue (2004 – 2013)
58
63 71
76
84
90 103
113
127
153
25
37
63 66
108
85 94
131 137
148
621
751
1,007 1,002
1,360
1,051 1,087
1,301 1,356 1,331
-
200
400
600
800
1,000
1,200
1,400
-
20
40
60
80
100
120
140
160
180
200
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Rp
/KW
h
Tri
llio
n R
p
Sales (T Rp)
Fuel Cost (T Rp)
Production Cost(Rp/kWh)
1. 60% of Production cost is for Fuel cost influenced by primary
energy price volatility
2. Revenue increase due to sales growth and tariff increase
3. Loss is covered by subsidy from Government.
E L E C T R I C I T Y F O R A B E T T E R L I F E
6
PT PLN
(Persero)
INPUT:
Coal, Fuel
Oil, Gas
Electricity
from IPP
Market
Price
OUTPUT:
Electrical
Energy to
support
economic
growth
Regulated
Price
Government of Indonesia to provide
Subsidy + Margin = Market Price – Regulated Price
Public Service Obligation
E L E C T R I C I T Y F O R A B E T T E R L I F E
Fuelmix optimisation
1. ROR type Hydro and Geothermal as Baseloader
2. SCPP as base loader
3. GTPP as intermediate peaker and peaking unit
4. Oil fueled PP only for :
- peaking unit
- must run unit
- remote area
E L E C T R I C I T Y F O R A B E T T E R L I F E
2008 – 2014 Fuelmix
43.1% 40.9% 44.1%
50.6% 51.4% 55.5%
22.0% 22.4%
20.8%
23.3% 24.1%
22.4% 4.9% 5.6%
5.1%
4.7% 4.4%
4.5%
7.3% 10.5% 6.8%
6.5% 7.7%
6.1%
22.7% 20.6% 23.1%
14.9% 12.4% 9.2%
2.3%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2009 2010 2011 2012 2013 2014
Biofuel FUEL OIL HYDRO GEOTHERMAL GAS COAL
E L E C T R I C I T Y F O R A B E T T E R L I F E
Role of primary energy for National Electricity
9
Hydro
Geothermal
Coal
Gas
LNG
Oil
Fuel oil demand may increased when Gas/LNG is not available
E L E C T R I C I T Y F O R A B E T T E R L I F E
0
20
40
60
80
100
120
140
160
180
200
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Baseloader Load Follower Peaker
mm
scfd
Role of a gas power in Indonesia electricity supply system
Pipelined Gas Baseloader, Load follower
LNG Load follower, Peaker
CNG Peaker
E L E C T R I C I T Y F O R A B E T T E R L I F E
PLN Gas Balance
11
-
200
400
600
800
1,000
1,200
1,400
1,600
1,800
2,000
2013 2014 2015 2016 2017 2018 2019 2020 2021
BB
TU
D
Batam Aceh Sumatera Utara
Riau Sumatera Selatan Jambi
Bangka Lampung Kalimantan Barat
Kalimantan Sulawesi Selatan Sulut-Gorontalo dan Sulteng
Papua Indonesia Timur Tersebar Jawa Bagian Barat
Jawa Bagian Tengah Jawa Bagian Timur Bali
TOTAL SUPPLY
E L E C T R I C I T Y F O R A B E T T E R L I F E
PLN LNG Balance
12
2014 2015 2016 2017 2018 2019 2020
1 Sumatera - 12 14 15 13 13 13
2 East Indonesia - - 4 5 6 6 6
3 Bali - 2 4 4 3 3 3
4 Muara Karang and Priok 26 27 27 28 32 36 35
5 Muara Tawar 2 9 11 11 11 13 21
Total Demand 28 51 61 63 65 70 78
Total Supply 26 34 33 34 35 47 47
LNG Balance (2) (17) (28) (29) (30) (23) (31)
E L E C T R I C I T Y F O R A B E T T E R L I F E
Optimizing existing gas supply using CNG Storage
Sungai Gelam 5 MMSCFD CNG storage system
In operation since December 2013, for 80 MW peaking unit
Jakabaring 3 MMSCFD CNG storage system
In operation since February 2013, for 60 MW peaking unit
Other CNG Storage Project in progress:
PROJECT INSTALLED CAPACITY PLANNED COD STORAGE CAPACITY
PLTG Peaker Lampung 100 2014 10
PLTG Jambi Peaker 100 2014 5
PLTG Bawean 8 2014 2
PLTGU Gresik 1500 2014 20
PLTMG Tanjung Selor 8 2014 1,5
PLTG Bangkanai 300 2014 20
Grati 15 MMSCFD CNG storage system
In operation since July 2013, for full operation of Garti
CCPP (660 MW) during peaking time
Muara Tawar 25 MMSCFD CNG storage system
In operation since January 2014, for full operation of Muara
Tawar CCPP (2000 MW) during peaking time
Duri 5 MMSCFD CNG storage system
In operation since February 2014, for 100 MW peaking unit
Tambak Lorok 20 MMSCFD CNG storage system
Ready for operation since April 2014
1
2
3
4
5
6
E L E C T R I C I T Y F O R A B E T T E R L I F E
CNG Marine with Containerized CNG Tube and LCT Barge
Small amount of
existing gas supply in
Batam (4 BBTUD) is
compressed and
transported to nearby
island using truck and
Landing Craft Tank
Barge to suppy 6 MW
Gas engine.
E L E C T R I C I T Y F O R A B E T T E R L I F E
CNG Marine with Vessel
Gresik
Lombok
28 mmscf existing gas
supply in Gresik is
compressed and
transported to Lombok
using Vessel installed with
CNG tubes, to supply a 90
MW Peaking Unit.
E L E C T R I C I T Y F O R A B E T T E R L I F E
LNG FSRU
FSRU West Java operated by PT
Nusantara Regas. Deliver gas supply
to Muara Karang and Priok CCPPs
(4000 MW) around 26 cargo per year.
FSRU Lampung operated by PT
PGN, Tbk. Potential as gas supplier
for Muara Tawar CCPP (2000 MW)
during peak time (14 hours) up to 12
cargo per year.
Arun Regas Facility operated by PT
Pertamina. Will deliver gas supply to
Arun Peaker GTPP and Belawan
CCPP (total 1500 MW), up to 12
cargo per year.
16
E L E C T R I C I T Y F O R A B E T T E R L I F E
17
Integrating LNG Infrastructures
Issues at MIDSTREAM side :
Vessel ownership and operation
Regasification facility
Jetty
Pipeline
Permits
Issues at UPSTREAM side :
Gas well head
LNG Plant
Permits
Issues at DOWNSTREAM side :
Land acquisition
Construction schedule
Transmission lines
E L E C T R I C I T Y F O R A B E T T E R L I F E
18
PLN’s Mini LNG Projects – Business Schemes
PLN buy gas at Plant Gate :
Gas Developer (and its
consortium) develop / provide:
- LNG Plant
- LNG Transportation
- LNG Regasification Facility
- LNG Terminal
- Necessary infrastuctures :
pipelines, ORF, meters
PLN buy gas at well head:
PLN or its contractors develop /
provide:
- LNG Plant
- LNG Transportation
- LNG Regasification Facility
- LNG Terminal
- Necessary infrasturctures :
pipelines, ORF, meters
Gas
Source
LNG
Plant Transportation
LNG
Storage Regas
Facility
Power
Plant
E L E C T R I C I T Y F O R A B E T T E R L I F E
Airport D/GEPP Pesanggaran (250 MW)
GTPP Gilimanuk (130 MW)
SCPP Celukan Bawang (380 MW)
GTPP Pemaron (90 MW)
New 150 kV
Existing 150 kV
Gas supply to Bali
Supply from
Jawa :
1. Submarine
Cable
(4x100 MW)
2. Overhead TL
500 kV
(400 MW)
E L E C T R I C I T Y F O R A B E T T E R L I F E
Very Small LNG vs Olein
1. Distributed small volume gas demand in Eastern
Indonesia
2. Savings compare to fuel oil : HSD, MFO, Biodiesel, Olein
3. Benefit of consuming Olein
Reduce import dependency
Cheaper price compare to HSD
Opportunity for local farmers
E L E C T R I C I T Y F O R A B E T T E R L I F E
Closing Remarks
1. Implementation of CNG/LNG technology is SIGNIFICANT as solution
to replace current Power Plant’s fuel oil consumption.
2. In short term, LNG still be used as base loader, to replace fuel oil for
all dual fired units. For long term, LNG will be assigned as
peaking/medium units with supply swing rate (peak/off peak) vary
from 40% - 100%.
3. Using MERIT ORDER analysis with least cost approach for electricity
generation planning : “The more of LNG price the less volume it is
required”.