integrating large quantities of wind in the electricity grid in portugal

26
Integrating large quantities of wind in the electricity grid in Portugal - A view of the Transmission System Operator - REN, SA EWEA Workshop Wind Energy and Facts - Integrating Wind Power in Romania Bucharest June 2nd 09 1/26 Integrating large quantities of wind in the electricity grid in Portugal A view of the Transmission System Operator REN – Rede Eléctrica Nacional, SA João da Silva Ricardo [email protected]

Upload: vuonghuong

Post on 03-Jan-2017

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   091/26

Integrating large quantities of wind inthe electricity grid in Portugal

A view of the Transmission System Operator

REN – Rede Eléctrica Nacional, SA

João da Silva Ricardo

[email protected]

Page 2: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   092/26

Summary

• The power sector organisation and electric system

• The Portuguese goals for renewables

• Key challenges for TSO and DSO

• Coordination TSO­DSO and with neighbouring TSO

• The generation access rules

• The need for transmission grid extension and CAPEX

• Wind power and hydro in service & in action

• Key innovations in 2006 call for wind proposals

• Conclusions

Page 3: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   093/26

The Power Sector organization (1/2)

PowerSector

Markets

Regulator for Electricityand Gas ­ ERSE

Producers

Special status(Wind + small RES)

Ordinary Status

Traders

Consumers

Distribution SystemOperator ­ EDPD

Transmission SystemOperator ­ REN

Ministry for Economy andInnovation ­ MEI

Direction for Energy andGeology ­ DGEG

20% of load on the market

Page 4: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   094/26

The Power Sector organization (2/2)

Key responsibilities for new generation

Ministry + Directorate forEnergy and Geology

ü Policy making, including definingfuture national wind objectivesü Decisions on access of new generationü Permits + licences (generation + grid)ü Value of feed­in tariffs for special

status generation

Transmission andDistribution Operators ü Adjust grid plans for objectives

ü Build and reinforce the gridsü Define capacities of grid (public)ü Give (or NOT) OK for connectionsü Define connection solutionsü Help wind producers in licensing +

constructionü Real time system balance (dispatch)

Page 5: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   095/26

The Portuguese electric system (1/2)

Key technical features: Grid (Dec 31st 2008)

§ Current peak demand: 9110 MW

§ Average load growth: 4,3 % (last 15 years)

§ Transmission grid – lines and substations

§ 400 kV: 1589 km Substations: 53

§ 220 kV: 3257 km

§ 150 kV: 2667 km

§ Transmission grid power transformers

§ Autotransformers: 9921 MVA

§ Transformers  to  60  kV  ­ distributionand renewable generation 16273 MVA

2*400 kV

400 kV

400 kV

3*220 kV

Interconnections

Page 6: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   096/26

The Portuguese electric system (2/2)

Key technical features (cont)

Portuguese Generation System (Dec 31st 2008)

§ Large Hydro 4578MW

§ 3598 MW from which§ 980 MW with pumping capacity

§ Other renewable (Special status): 4518 MW

§ Wind ­ 2624 MW§ Co­generation ­ 1463 MW§ Small hydro ­ 379 MW§ Photovoltaic ­ 50 MW§ Waves ­ 2 MW (experimental)

§ Natural Gas 2166 MW

§ Coal 1776 MW

§ Fuel Oil 1712 MW

§ Gas­Oil 165 MW (fast start turbines)

§ Total in service ­ 14916 MW (Dec 31st 2008)

990 MW 880 MW

1110 MW

760 MW

800 MW

240 MW1192 MW

946 MW

1886 MW

584 MW

Page 7: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   097/26

The Portuguese goals for renewables (1/2)

§ The  global  renewable  energy  (RE’s)  goals  setfor Portugal keep growing

Current 20­20­20 EU objectives for 2020 haveled to the new target around

8 GW of wind§ For  a  future 14  GW peak  load  system  this

means1  ­ Increasing  current  4,5  GW  of  large  hydrowith new capacity       with pumping capacity

SO  MUCH  WIND  NEEDS  MOREPUMPING HYDRO!2­ Securing  high  level  of  interconnectioncapacity (target: from current 1,3 to 3 GW)

540

90

4301190

160100

450

250

620

330

50 520

1290

360

950

430

1170

260

20

920

220

570

20

210

280

510

Target wind

New hydro

Page 8: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   098/26

More hydro complements more wind !

§ More hydro creates more flexibility – Hydro is a valuableasset for high wind penetration

Night + weekendPUMPING

Also, some degree of more long term transfers arepossible (weekly, monthly) – in larger existing reservoirs

Peak hoursGENERATING

More capacity to follow shorter term wind variations(minutes, hours), easing stresses on thermal generation

to

Transferred

Possibility of fast launch to help after tripping of windor other generator types

Page 9: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   099/26

The Portuguese goals for renewables (2/2)

§ In  2007  the  Ministry  of  Environmentlaunched a National Plan for Hydro (NPH)

§ 8  new  hydro  power  stations        (PS)almost all of them reversible

§ New  1,1  GW  of  gen.  capacity  fromwhich 0,9 GW with pumping capacity

§ NPH 8 PS’s where divided into groups andcalls  for  proposals  to  build  +  own  +operate were submitted to the market

§ All  winning  proposals  multiplied  by  atleast 2 the foreseen installed power

The  NPH,  together  with  other  new  hydro

projects,  will  secure new  3,5  GWof hydro generating + pumping capacity

1160

350

260

220

320

4 PS

Page 10: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0910/26

1 Need of coordinated approaches of Ministry, TSO and DSO to

Review and update transmission grid planning decisions

Manage generation MW permit process – Max limits at each substationdefined and public

Key challenges for the TSO and DSO

2 Need to analyse and managethe future stability andsecurity of the system

Reactive control (inc post fault)

Fault ride through capability

Coping with gener. intermittence

3 Need for steep increase inconstruction and upgradingof lines and substations

Faster environmental and legalpermitting processes

Increase in project design +realisation outsourcing

From late 90’s REN has been creating a new paradigm to cope with growingtargets in renewable disperse generation, in close cooperation with theMinistry responsible for energy and the Distribution System Operator (DSO)

Page 11: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0911/26

§ Debate and agree on Distribution and Transmission grids developments

§ Debate on technical rules with influence on Transmission Grid

§ Review codes and standards on a coherent way

§ Dynamic specifications for frequency

§ Short circuit / Voltage dip generator adequacy – Fault ride through capability

It  is key to create conditions to avoid massive and uncoordinated outages of generation:

REMEMBER THE EUROPEAN INCIDENT ON NOV 4th 2006

§ Follow up on generation permit agreement decisions

§ Common dialogue with  investors, when necessary,  for access decisions

or investment realisation

Coordination with Distribution Operator (EDP, SA)

Page 12: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0912/26

Coordination with neighbour TSO (REE, Spain)

200 km

650 km

1,4 to 1,8 GWinterconncapacity

1000 km

900 km

Max Load9 GW

Max Load47 GW

43 M people

Spain

10 Mpeople

Portugal

France

17 GW wind *3 GW wind *

* December 2008values

Page 13: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0913/26

The generation access rules (1/2)

1. The TSO ­ REN takes into consideration the national goals for RE’s,the wind and hydro resource location and developer’s connectionapplications when making the ‘Grid Development Plan’

2. REN calculates grid generation reception capacities for allsubstations according to grid plan. These values are public

3. Investors present to the Ministry of Economy and Innovation (MEI)their applications for new generation projects, including location

4. For each substation, should there be excess capacity demand incomparison with grid capacity, a ‘prorata’ reduction criteria isapplied to define final MW which are attributed and reserved to eachdeveloper. TSO or DSO give MIE their OK (or opposition)

5. Also, in 2005 the Government launched a call for tenders for twoblocks of wind power (1000 MW and 500  MW)  all the different localcapacities respecting grid capacities

A new grid planning +coordinated RE’s MW permiting paradigm

Page 14: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0914/26

The generation access rules (2/2)

1 ­ Wind powerstation

2 – Connection line

3 ­Transmission orDistribution connection

point

4 – Transmission orDistribution grid

1. Wind generation power stationinner grid and main substation

Constructed, paid by and remainingproperty of the developer

2. Connection line

The same but once built, property willpass to TSO or DSO

3. Connection bay

Constructed by TSO or DSO and paidby developer

4. Transmission or Distribution internalreinforcementsIn charge of TSO or DSO costssocialized through tariffs

Who  builds/pays/operates what

Page 15: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0915/26

The need for TransmissionGrid extension (1/2)

§ The  Planning  decisions  for  RE’s includesome  new  lines  and  substations,  andanticipates  the  scheduling  of  otherspreviously planned

§ Reasons  to  reinforce  the  grid 1  ­ It  isnecessary  to  collect  wind  in  inner  areas2–More  transmission capacity  from  theseareas to  load areas  (litoral) and  to Spainis needed

§ The map shows the key items in orange,including mainly the following items:

§ Uprating or upgrading of existing lines§ Upgrading of a few existing substations§ Some new lines and substations§ Construction of new bays in substations§ Boost in reactive compensation capacity

Page 16: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0916/26

§ From 2000 on, for the transmission grid (TG)

§ New substations (SB’s)§ New lines and§ Uprating of existent lines and SB’s

§ 6 large wind projects     (900 MW) already inoperation in 220 or 150 kV

§ In  the  next  3­4  years,  other  1400  MW  willalso be connected to the grid

§ 70% of the current 3050 MW of wind areconnected to the distribution networks BUT

§ Most of the additional RE’s large generationwill  – mainly  almost  all  the  large  hydro  –will connect to the 400 kV level

114 MW80 MW

240 MW

106 MW

Substations with morethan 100MW of windpower in operation orreserved by TSO orDSO

The need for TransmissionGrid extension (2/2)

216 MW

144 MW

In service

Future substation

Page 17: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0917/26

Internal gridexpansion and

Others15%

Security of supply43%

Connection to newpower stations

7%

Reinforcement of theinterconnection

capacity9%

Connection to therenewable energy

s tations26%

§ In  the  overall  period  2009  –2014,  the  investment directlyattributable to wind and  largehydro, ie

(sum  of cost  % of  contributionfor  wind+hydro objectives ofeach investment item)

will amount to 400 M€ ( * seepie) for  new  4.5  GW  of  windand new 2 GW of large hydro

§ These numbers do not considerthe  investment  of  the  windpark  and  its  main  substationnor  the  direct  line  to  the  gridconnection point, which are allbuilt  and  paid  for  by  thedevelopers

Breakdown of 2009 – 2014

REN CAPEX ~1600 million €(6 years)

*

CAPEX and breakdown for wind and large hydro

Connection oflarge hydro andwind

26%

Connectionof thermalpower plants

7%

Increase in capacityto the distributiongrid and  TGV railways

43%

Reeinforcementof theinterconnectioncapacity

9%

Refurbishmentand other costs

15%

Page 18: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0918/26

§ In the past ­ Most of the line or substation projects made ‘in house’

§ Later:  Legal  increase  in  environmental  administrative  procedures –

outsourcing of studies – ‘in house’ formal procedures with Authorities

§ Early 2000’ – became clear  need  to  important increase  in  investments

due to RE’s national objectives

§ Need  to  adapt  further  in  recent  years – Total  investment  from 150  to

above 250 M€ per year – Further increase of outsourcing

§ Call for and help the creation of new construction service providers

§ Enlarge outsourcing – All projects and environmental studies outsourced

§ Even complete processes of environmental studies plus administrative plus procedures

plus construction are now organised and outsourced

REN construction management response

Page 19: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0919/26

0,0%

1,0%

2,0%

3,0%

4,0%

5,0%

6,0%

7,0%

8,0%

9,0%

10,0%

11,0%

12,0%

0

250

500

750

1000

1250

1500

1750

2000

2250

2500

2750

3000

1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

Capacity[MW]

Year

Total in service Entry in service In construction Penetration

Wind power in service and foreseen§ As of Dec. 31st 2008, 2760 MW of wind were in operation in Portugal andgeneration was 5 TWh, 11% of  total  injected  energy  into  the  grid during2008. Something as 13% is expected for 2009

§ The steep growth of wind will keep going for the next years

2760

680 740

Page 20: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0920/26

0

1000

2000

3000

4000

5000

6000

7000

8000

0 2 4 6 8 10 12 14 16 18 20 22 24

MW

hour

4 April 2009

Wind

Load

0

1000

2000

3000

4000

5000

6000

7000

8000

0 2 4 6 8 10 12 14 16 18 20 22 24

MW

hour

22 September 2008

Wind

Load

0

100

200

300

400

500

600700

800

900

1000

0 2 4 6 8 10 12 14 16 18 20 22 24

MW

hour

22 September 2008

0

500

1000

1500

2000

2500

0 2 4 6 8 10 12 14 16 18 20 22 24

MW

hour

4 April 2009

35%

With 3048 MW wind in servicePower: 73% averageEnergy: 35 % contribution forthe day

Power: 0.4% < < 3.3% of installedwind capacityEnergy: 0.7% contribution for theday

Wind power in action – extreme days 2008/09

Sept. 22nd 2008

April 4th 2009

0,7%

Page 21: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0921/26

§ Dec 2008 – average power factor above 35%

§ Active power factor varies along the months of the year

§ Wind generation is somewhat lower during the day

§ Total year variability of wind energy much lower than the one of hydro

0%

5%

10%

15%

20%

25%

30%

35%

40%

Jan Fev Mar Abr Mai Jun Jul Ago Set Out Nov Dez

Average active power factor

Average 2001­2007

Average 2008

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

0 2 4 6 8 10 12 14 16 18 20 22

Power(pu)

Hourly average generation 2008

Dez

Set

Wind power in action – monthly variability

Page 22: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0922/26

Hydro power in service

§ Existing large hydro

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

0 2 4 6 8 10 12 14 16 18 20 22 24

MW

hour

5 February 2009ReseroirRun of riverSmal hydroLoad

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

0 2 4 6 8 10 12 14 16 18 20 22 24

MW

hour

6 February 2009ReseroirRun of riverSmal hydroWindLoad

§ Plus existing 537MW of small hydro

4.4 GW1580 MW reservoir1860 MW run of river

980 MW pumping

§ Average year productivity ~11 TWh

§ Important year variability ratiodry/wet year ~ 1 to 3

§ The largest production in one day2008­09 ­ Feb 6th 2009

Hydro ­> 49% of loadHydro + wind ­> 62% of load

~21% of total current consumption

Feb. 5th 2007

Feb. 6th 2009

5 February 2007

Page 23: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0923/26

Key innovations in 2006 call for proposals (1/2)

Innovative characteristics of the new wind power stations

1. Management of wind power stations by clusters (“local wind

power dispatch centers”)

2. Steady state reactive power control: tg fi within [­0.2, +0.2]

3. Wind curtailment (no­load periods; 50h/year, max)

4. Solutions for “wind/RE’s energy storage”; specially withhydro power stations

5. Participation in the primary frequency controlwind turbine operation at 95% of Popt in previously requested periods (by TSO)

6. RTFC ­ Ride Through Fault Capability as a “minimumrequirement” for system security

7. Installation of Wind Generation Dispatch Centres with windforecast (also in REN’s national control dispatch centre)

Page 24: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0924/26

§ The  need  for  TSO’s and  DSO’s  (60%  of  wind!) to safeguard  systemsecurity following post­fault or voltage dips lead  to  the  specificationof FRTC for wind generators in any high wind penetration scenario

§ Joint Iberian dynamic studies of REN and REE justified this need

§ Wind  generator  manufacturers had  already  understood  that  lack  ofresistance was becoming  a barrier  to high wind penetration and havebeen developing excellent FRTCperformance of new generators

0 ; 0,2 0,5 ; 0,2

0 ; 1

10 ; 0,9

1,5 ; 0,8

0

0,2

0,4

0,6

0,8

1

1,2

­2 0 2 4 6 8 10 12tempo [s]

U / 

Uno

min

al [p

u]U

 / U

nom

inal

[pu]

Time [s]

§ Post  fault  reactive  behaviour  isalso key for grid security

0.9 ; 0

0.5 ; 0.90 ; 0.9

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

U / Unominal [pu]

Ireac

tiva 

/ Ipr

é­de

feito

 [%]

Ireactive /

Ipre­

fault

[%]

U / Unominal [pu]

Key innovations in 2006 call for proposals (2/2)

Page 25: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0925/26

Conclusions§ High penetration of wind and hydro generation – IT  IS POSSIBLE  ­

Main challenge for TSO and DSO

§ New approaches needed and implemented: results OK so far

§ A wise level of central management is important

§ Cooperation  and  coordination between  TSO  and  DSO’s and  alsowith neighbour TSO’s and RE’s associations are also necessary

§ Specification  of new  technical  requirements for secure andflexible future system operation is key

§ Revision of codes and rules must be done at an early stage of theprocess

§ Internal changes inside TSO and DSO at planning,  construction andsystem operation

Page 26: Integrating large quantities of wind in the electricity grid in Portugal

Integrating large quantities of wind in the electricity grid in Portugal ­ A view of the TransmissionSystem Operator ­ REN, SA

EWEA Workshop Wind Energy and Facts ­ Integrating Wind Power in Romania    Bucharest  June 2nd   0926/26

MUL UMESC

Thank you

for your attention

João Ricardo

REN, Rede Eléctrica Nacional, SAPortuguese TSO

[email protected]