integrated flood plain management strategy for the vaal

6
Integrated flood plain management strategy for the Vaal David Stephenson * Water Systems Research Group, Department of Civil Engineering, University of the Witwatersrand, P.O. Box 277, Johannesburg, Wits 2050, South Africa Received 26 June 2001; received in revised form 23 January 2002; accepted 10 July 2002 Abstract Owing to development pressure for land bordering the Vaal river, in South Africa. Rand Water are revising their development policy. Restrictions were in place to avoid flooding and obstructing the flood flow of the river. Relaxation of the regulations will permit controlled development along the river. A flood hazard-risk index was developed to indicate where development could be permitted. An economic comparison of costs and benefits supports the relaxation. Ó 2002 Elsevier Science Ltd. All rights reserved. Keywords: Development; Floods; Hazard; Risk; Rivers 1. Introduction The Vaal Barrage is the original water source for Johannesburg and surrounding areas. The banks of the Vaal river upstream of the Barrage are becoming sought after for urban development. The managers of the Barrage, Rand Water, have evolved a policy for con- trolling urban development along the banks. The prescriptive method of limiting development on the banks of the Vaal River Barrage has been applied for many years and has successfully protected the Vaal River against pollution and flooding. Rand Water ab- stracts potable water from the Barrage for supplying some 10 million consumers within its supply area. The importance of water quality and at the same time responsibility to the property owners along the banks of the Vaal River and Barrage with respect to flooding are paramount. The Vaal River and the Wilge River which flow into Vaal dam upstream of the Vaal River Barrage are the main contributors of water and the main sources of floods. There are however other tributaries downstream of the Vaal Dam, namely the Taaibosspruit, the Sui- kerbosrand, the Klip and the Riet rivers. Some of these rivers take return flow from Gauteng and the Vaal Triangle area so that the flow through the Barrage and downstream is considerably different to the flow entering the Vaal Dam. Rand Water owns the Vaal Barrage and is responsi- ble for its operation. The Barrage backs up water along the Vaal River past Vanderbijlpark, Vereeniging and Sasolburg (Fig. 1). Water levels along this reach of river are controlled by the Barrage gates as well as inflow from the tributaries and Vaal Dam. Flows, particularly in times of flood, are liable to spill onto the banks of the river and there is development along a considerable length of river which could be affected by floods. There have been occasions when property has been flooded owing to the high water level in the river. Buildings along the banks of the Vaal and trees tend to obstruct flow during floods and cause the water to back up behind those obstructions with consequent hazardous effects on other property upstream. A back- water is created, i.e. the blocking of the flow path in- creases water depth upstream and this effect can be felt for a few kilometres upstream. It is for this reason that Rand Water in 1982 prohibited development below the maximum recorded flood line which occurred in 1975. This policy had some advantages, inter alia that it pre- served vegetation along the banks in the form of a green strip. If further protected the river against pollution. However, pollution from stormwater reaches the river and on site treatment may become a necessity. * Tel.: +27-11-717-7154; fax: +27-11-403-2062. E-mail address: [email protected] (D. Stephenson). 1462-0758/02/$ - see front matter Ó 2002 Elsevier Science Ltd. All rights reserved. PII:S1462-0758(02)00032-8 Urban Water 4 (2002) 425–430 www.elsevier.com/locate/urbwat

Upload: david-stephenson

Post on 05-Jul-2016

252 views

Category:

Documents


9 download

TRANSCRIPT

Page 1: Integrated flood plain management strategy for the Vaal

Integrated flood plain management strategy for the Vaal

David Stephenson *

Water Systems Research Group, Department of Civil Engineering, University of the Witwatersrand, P.O. Box 277, Johannesburg,

Wits 2050, South Africa

Received 26 June 2001; received in revised form 23 January 2002; accepted 10 July 2002

Abstract

Owing to development pressure for land bordering the Vaal river, in South Africa. Rand Water are revising their development

policy. Restrictions were in place to avoid flooding and obstructing the flood flow of the river. Relaxation of the regulations will

permit controlled development along the river. A flood hazard-risk index was developed to indicate where development could be

permitted. An economic comparison of costs and benefits supports the relaxation.

� 2002 Elsevier Science Ltd. All rights reserved.

Keywords: Development; Floods; Hazard; Risk; Rivers

1. Introduction

The Vaal Barrage is the original water source for

Johannesburg and surrounding areas. The banks of the

Vaal river upstream of the Barrage are becoming sought

after for urban development. The managers of theBarrage, Rand Water, have evolved a policy for con-

trolling urban development along the banks.

The prescriptive method of limiting development on

the banks of the Vaal River Barrage has been applied for

many years and has successfully protected the Vaal

River against pollution and flooding. Rand Water ab-

stracts potable water from the Barrage for supplying

some 10 million consumers within its supply area.The importance of water quality and at the same time

responsibility to the property owners along the banks of

the Vaal River and Barrage with respect to flooding are

paramount.

The Vaal River and the Wilge River which flow into

Vaal dam upstream of the Vaal River Barrage are the

main contributors of water and the main sources of

floods. There are however other tributaries downstreamof the Vaal Dam, namely the Taaibosspruit, the Sui-

kerbosrand, the Klip and the Riet rivers. Some of these

rivers take return flow from Gauteng and the Vaal

Triangle area so that the flow through the Barrage and

downstream is considerably different to the flow entering

the Vaal Dam.

Rand Water owns the Vaal Barrage and is responsi-

ble for its operation. The Barrage backs up water alongthe Vaal River past Vanderbijlpark, Vereeniging and

Sasolburg (Fig. 1). Water levels along this reach of river

are controlled by the Barrage gates as well as inflow

from the tributaries and Vaal Dam. Flows, particularly

in times of flood, are liable to spill onto the banks of the

river and there is development along a considerable

length of river which could be affected by floods. There

have been occasions when property has been floodedowing to the high water level in the river.

Buildings along the banks of the Vaal and trees tend

to obstruct flow during floods and cause the water to

back up behind those obstructions with consequent

hazardous effects on other property upstream. A back-

water is created, i.e. the blocking of the flow path in-

creases water depth upstream and this effect can be felt

for a few kilometres upstream. It is for this reason thatRand Water in 1982 prohibited development below the

maximum recorded flood line which occurred in 1975.

This policy had some advantages, inter alia that it pre-

served vegetation along the banks in the form of a green

strip. If further protected the river against pollution.

However, pollution from stormwater reaches the river

and on site treatment may become a necessity.

* Tel.: +27-11-717-7154; fax: +27-11-403-2062.

E-mail address: [email protected] (D. Stephenson).

1462-0758/02/$ - see front matter � 2002 Elsevier Science Ltd. All rights reserved.

PII: S1462-0758 (02 )00032-8

Urban Water 4 (2002) 425–430

www.elsevier.com/locate/urbwat

Page 2: Integrated flood plain management strategy for the Vaal

2. Flood frequencies and magnitudes

The flood which occurred in 1975 was the highest

recorded and was originally estimated to have a recur-

rence interval of 34 years. That is, from a statistical

analysis of flood flows in the Vaal River, it was found

that there was approximately a 3% chance that that flowcould be exceeded in any one year. The statistical

analysis used historical flows (Chang, 1989).

As the Vaal catchment becomes developed with

towns and industries, flood flows will tend to increase.

This is because the construction of impermeable roads,

roofs and reduction of natural ground cover, act to re-

duce infiltration and increase the proportion of rainfall

which runs off to the rivers. In addition, the smoother

roads and storm water conduits concentrate the water

faster and therefore a higher flood peak can be expected.

A study of the floods of the Vaal river was undertaken

by Stephenson, Van Zantwijk, and Hoge (1997) using

the RAFLER model (Stephenson & Paling, 1992).

The estimation of extreme floods is generally made byassessing the amount of rainfall which runs off the

catchment and down the river. The recurrence interval is

obtained from statistical analysis of the rainfall data,

since rainfall data is generally more readily available

over a longer period. The area which is flooded on the

banks of the river is therefore a function of the flood

magnitude represented by recurrence interval as well as

Fig. 1. Map illustrating chainages from Vaal Barrage.

Fig. 2. Flood plain zones proposed by Rand Water.

426 D. Stephenson / Urban Water 4 (2002) 425–430

Page 3: Integrated flood plain management strategy for the Vaal

the physical factors, such as bank development and landuse.

The channel which is generally occupied by flow

during low flows is referred to as the river channel. The

water line is seldom below this level. In the case of the

Vaal Barrage area, this channel is of considerable width

as the water is backed up by the Barrage.

There could however be regular flooding at succes-

sively higher water levels. There is an area which will beinundated regularly, i.e. every few years, and this is re-

ferred to as the waterway. No development should be

permitted in the waterway as there is a real and frequent

danger to life and property.

At a higher level, such as the 1 in 25 year flood, there

is still a risk of flooding which could endanger property

and life but it does not occur frequently enough to be

a nuisance. The area within the boundaries of this floodwould be called the flood zone, which comprises the

waterway and the flood plains.

There is an area outside this flood zone at a higher

level which could be flooded even less frequently and

this area is referred to as the flood fringe. This extends to

the limits of the 50 year flood, although the Water Act

(1998) now requires the 100 year flood to be indicated

on plans. Fig. 2 illustrates the various zones.Above the 100 year flood line, the possibility of

flooding is so remote, it is seldom accounted for in

planning, but it should be borne in mind in important

developments, e.g. dangerous depositories.

3. The hazards associated with flooding

The reason that development of private and public

buildings is undesirable within flood areas is not only

due to the fact that it endangers lives and property butalso because the buildings obstruct the flow and cause

backing up of the river. The concern regarding this

damage is due to a number of reasons:

If the river is very deep and flows fast, it could wash

away buildings and property and also drown people. At

successively lower flows corresponding to lower water

velocities and shallower depths, the water becomes safer

and at a low depth it may not be life endangering, butit could still result in damage to property. However,

shallow depths can be countered by protective measures

which could be instituted if there was a warning of an

impending flood. In other less dangerous situations, very

shallow flooding on roads could be minimized by vehi-

cles avoiding those roads or travelling very slowly. The

danger or hazard associated with flow is generally ex-

pressed in terms of a diagram such as Fig. 3. This type ofdiagram has been adopted by various flood management

organisations such as Minnesota in the United States of

America (1969) and New South Wales in Australia

(1986). The ranking of the hazard was simplified by

Stephenson and Furumele (2001) in studies for Eastern

Gauteng and a hazard index was proposed. Similar

studies were done on rural rivers (Du Plessis, 2000;

Adriaans, 2001).Another point to consider is the risk, or probabil-

ity, of the hazard occurring. Thus, if the hazard is

only likely to occur with a probability of 1% in any

one year, it may be tolerable, but if it occurs fre-

quently. E.g. at least once every year it may be intoler-

able. This is the risk factor and it can be evaluated

in terms of the recurrence interval of the flood. Thus a

high risk index could be associated with floods occur-ring more often than once in 20 years and an interme-

diate risk index for floods occurring with a recurrence

Fig. 3. Flood hazard diagram.

D. Stephenson / Urban Water 4 (2002) 425–430 427

Page 4: Integrated flood plain management strategy for the Vaal

interval between 20 and 100 years, and low risk index for

events which occurred less frequently than once in 100

years.

The hazard index and the risk index could be com-

bined by multiplying them to give a hazard risk indexwhich is an indicator of desirability of development

within the floodway or flood fringe. Fig. 4 shows the

results. A hazard risk index of 2 or less is considered

acceptable.

What HRI to accept may vary with the authority. They

must decide based on human values, legal and economic

consequences. Some may rate remote probabilities low

and some may have different values. Similarly, the cost ofland may influence the hazard acceptable. Developing

and dense areas may initially accept higher HRIs, e.g.

more frequent or more severe flooding, but as they de-

velop, reduce the acceptable HRI.

4. Integrated floodplain management

It is thus apparent that a more flexible approach than

previously adopted is possible for planning development

along the Vaal River. In fact, an integrated management

approach is considered at this stage. This implies that

a trade off could be made between the implications of

flooding and the implications of prohibiting develop-

ment within the flood zone. The cost of not permitting

development in the flood zone will increase over theyears as attractive riverbank land becomes scarcer. An

economic balance between the average hazard cost and

the availability of land is needed.

This will require a proactive approach. That is, a

flexible approach within guidelines whereby developers

may negotiate to develop within the flood fringe or even

the flood zone. The developer may be able to physically

design his development such that it results in negligibleadverse effects but on the other hand has high social

benefits. Alternatively, he may be able to contribute

economically to the enhancement of the Vaal Barrage in

return for being permitted to develop within an ap-

proved area. The principles of integrated management

can be applied at this stage, and a detailed plan will

emerge as more data is gathered.

It would also be desirable to benchmark the proposedintegrated flood plain management approach with other

practices. International attention paid to integrated

flood plain management is now producing useful guide-

lines and an international comparison would be of use.

The methodology for plotting HRIs is well devel-

oped. The steps could be:

1. Determine flood flow for various recurrence intervals,e.g. from records or rainfall runoff modelling. Con-

sider future catchment use.

2. Calculate corresponding water levels and flood lines

using a water surface profile program and topogra-

phy.

3. Decide the hazard level associated with different

water depths and assign HIs.

4. Allocate RIs to flood recurrence intervals and calcu-late HRIs.

5. Decide the acceptable HRI and demarcate it on the

flood plain map.

Fig. 4. Hazard risk indices.

428 D. Stephenson / Urban Water 4 (2002) 425–430

Page 5: Integrated flood plain management strategy for the Vaal

The latter can be done by the flood model and plottedon a GIS map by computer (see e.g. Stephenson &

Furumele, 2001).

5. Flood plain development policy

The decision as to level of development on the banks

of a river and how to close the river depends on what the

effect of the development will be on the flood as well as

what the effect of the flood is on development. That is,

will construction obstruct the flow of water, thereby

affecting water levels upstream of the development? Thiswas in the past largely a responsibility of the Depart-

ment of Water Affairs and Forestry, but Rand Water is

adopting a holistic attitude in addressing the problem.

The following factors will affect the decisions:

(a) What the effect of development will be on flood levels?

(b) What a flood will do to the development?

(c) How the value of the new and existing developmentis affected?

(d) What the damage cost would be?

(e) What pollution threat there is to the water?

(f) The risk of adverse effects?

5.1. Alternative planning zones

American practice in Minnesota is to plot the 100-year flood line and divide the waterway into floodway

(main channel and edges) and flood fringe (largely dead

water). Only pastoral and recreational/sporting activities

are permitted in the floodway, and development in the

flood fringe is subject to negotiation.

Australian policy is more flexible, the objective being

to minimize impact and liabilities of flooding. Social,

economic, ecological and hydrological factors are con-sidered. New South Wales derived a valuable criterion in

terms of water depth and velocity for deciding whether

to permit development.

It therefore appears from experience that the method

to adopt is to define different zones, for example as fol-

lows:

(a) Waterway: No development permitted, except possi-ble channel improvements.

(b) Flood plain: Development only if it is advantageous

and proved not adverse.

(c) Flood fringe: Development at developer�s risk.

Delimitations of the different zones could be based on

the following:

(a) Waterway: either

(i) covered by a common flow, for example 10 years

or less, or

(ii) 90% of the 50-year flood, or(iii) velocity greater than 1 m/s, or

(iv) depth greater than 1 m, or

(v) a combination of (i), (iii) and (iv) which gives a

flood hazard risk index of 2 or less.

(b) Flood plain: outside of (a) but bounded by either

(i) 1975 flood line (which is estimated to be the 25-

year frequency flood), or

(ii) 95% of the 50-year flood, or(iii) velocity greater than 0.5 m/s, or

(iv) depth greater than 0.5 m, or

(v) a combination of (i), (ii) and (iv), e.g. a flood

hazard index of 1 or less.

(c) Flood fringe: outside of flood plain but bounded by

either

(i) 50-year or 100-year flood line, or

(ii) no pollution source.

The designated waterway should be the zone within

which obstructive or dangerous development should be

prohibited.

The suggested prohibition line below which devel-

opment should be prohibited could be based on a haz-

ard-risk index of above 2. The boundary corresponds to

the 10-year flood line (the 10-year line nearer the Bar-rage but nearer the 5-year line further upstream). To use

a more frequent (e.g. 1-year) flood line would expose

developers and Rand Water to a greater risk. The value

of the additional land thus available is evaluated below.

It is demonstrated that the value of the additional land

thus made available is greater than the cost of additional

flooding if building is on stilts. The policy suggested is to

restrict development for a hazard-risk index of 2 or less,and use economic principles in allowing development

above that zone.

Developers may propose altering the flood lines on

the flood plain, for example by replacing exotic gum

trees by indigenous shrubs or reshaping the ground, but

the onus should be on them to prove this is beneficial

from an economic, social, environmental, water quality

and hydrological point of view and it is sustainable. Thismay enable them to make even more area available for

development.

For the upper limit of the flood plain, the 25 year

flood line or 1975 year flood line is suggested. The 25-

year flood line corresponds with the 1975 flood, mea-

sured and marked along the riverbanks. This is based on

the 1997 revised flood estimates. Hence it is a practical

line to apply.It would not be wise for floor levels of buildings to be

below the 25 year flood line as the cost of flooding could

be excessive and the backup effect would be greater.

Hence, apart from surface development, e.g. roads,

recreation areas on the ground, buildings will have ele-

vated floors, by up to 3 m, or more if the consequences

of flooding are great.

D. Stephenson / Urban Water 4 (2002) 425–430 429

Page 6: Integrated flood plain management strategy for the Vaal

The flood fringe (between the 25-year and 50-yearor 100-year now flood lines) may also be developed to

an even greater density and development need not be

banned in the flood fringe as long as the developers and

owners are aware of and responsible for the risk of

flooding and indicate this in writing. The flood lines

should be indicated on all development plans, as well as

floor levels. The hazard risk index is low and backup

effect also negligible due to development on this fringe.In all cases, the responsibility needs legal opinion, and

insurance against hazards should be considered.

6. Conclusions

The RI is adequate for indicating risk of flooding and

the HI for degree of hazard. The combined HRI is ofmost use in demarcating zones adjacent to waterways.

Development in the waterway along the Vaal river

barrage should be prohibited as it is dangerous to de-

velopers and will obstruct floods, causing backup of

water upstream. The waterway corresponds to the 10-

year frequency flood lines and a HRI of 2.

Restricted development may be permitted on the flood

plains, i.e. between the waterway and the 25 year floodlines. Restricted development includes construction on

stilts to raise the floor level above the 50-year flood level.

The support structure should not occupy more than 1%

of the land (erf) area. Structures and associated devel-

opment, earthworks and planting of trees should only be

commenced if the approval is obtained.

At-risk development may be permitted on the flood

fringes, i.e. beyond the 25 year flood line and the de-veloper shall indicate on all relevant plans the position

of the flood lines and indemnify the authorities from any

responsibility. Drainage and waste disposal should

comply as in paragraph 2 above.

Appendix A. Calculation of hydraulic effect and cost atstructures in flood plain

Based upon turbulent loss behind obstructions:

Backup ¼ dy ¼ KDv2

2g

� �¼ K

2v2g

dv ¼ 2Kv2

2g

� �dvv:

Now dv=v ¼ db=b and K ¼ 1. So for v ¼ 1:4, dy ¼ 2�1 � ð2=20Þð1=200Þ ¼ 0:001 m per building, where y is

the water depth, v is the water velocity, g is the gravi-

tational acceleration, K is the loss coefficient and b is the

width of flood plain.

It is assumed stilts have a blockage of 1 m wide in

a 200 m wide flood zone width. If bank slope ¼ 1=30

and backwater effect is over 5000 m, and there is one

building per 200 m, then additional area inundatedover 20 km, on one bank is 0:001� 30� 5000� ð20000=200Þ ¼ 15000 m2. The effective increase in water depth is

0:001� 5000=200 ¼ 0:025 m.

If building overlay is 10% of the newly flooded area

and floor area costs R2000 m�2, extra cost of flooding

is R2000 � 0:1 � 15000 ¼ R3 million. However, if the

buildings were not on stilts, the blockage would in-

crease by a factor of 100, so the cost would be R300million.

On the other hand, the value of the land released on

the flood plain is estimated to be 3 m depth � 30 slope

width � 20000 m river reach � R10 m�2 ¼ R18 million

(based on 3 m depth difference between the 1/10 and 1/

25 year flood lines). So it is economically sensible to

release the land for development on stilts but not for

denser floor areas below the 25 year flood line.

References

Adriaans, R. (2001). Development control in the floodplain, a key

feature of river management. IMIESA, 26(1), 22–23.

Chang, T. J. (1989). Characteristics of extreme precipitation. Water

Resources Bulletin, 25(5), 1037–1040.

Du Plessis, L. A. (2000). A new and unique approach of flood disaster

management. SA Water Bulletin, 26(5), 16–19.

Minnesota (1969). Floodplain Management Act, Minneapolis.

New South Wales (1986). Flood Development Manual, Sydney.

Stephenson, D., & Furumele, M. (2001). A hazard-risk index for urban

flooding. IAHR Congress, Beijing.

Stephenson, D., & Paling, W. A. J. (1992). An hydraulic based

model for simulating monthly runoff and erosion.Water SA, 18(1),

43–52.

Stephenson, D., Van Zantwijk, A., & Hoge, P. (1997). A flood plain

development policy for the Vaal Barrage. Proceedings of the

Institution of Civil Engineers––Municipal Engineer, London 121,

199–205.

Water Act (1998). Pretoria.

430 D. Stephenson / Urban Water 4 (2002) 425–430