Sandia National Laboratories is a multi-program laboratory managed and operated by Sandia Corporation, a wholly owned subsidiary of Lockheed Martin Corporation, for the U.S. Department of Energy’s National Nuclear Security Administration under contract DE-AC04-94AL85000. SAND NO. 2011-XXXXP V&V and Scrum V&V has to be Agile too!

Upload: techwellpresentations

Post on 19-Aug-2015

19 views

Category:

Software


0 download

TRANSCRIPT

Page 1: Integrate V&V within Scrum: How Does That Work?

Sandia National Laboratories is a multi-program laboratory managed and operated by Sandia Corporation, a wholly owned subsidiary of Lockheed Martin

Corporation, for the U.S. Department of Energy’s National Nuclear Security Administration under contract DE-AC04-94AL85000. SAND NO. 2011-XXXXP

V&V and Scrum V&V has to be Agile too!

Page 2: Integrate V&V within Scrum: How Does That Work?

Agenda

Introduction

How to Fold V&V into Scrum

Demo of V&V Navigator

Currently Government Use tool

2

Page 3: Integrate V&V within Scrum: How Does That Work?

Introduction

Julie V&V (software and M&S)

Analyst, Model Developer

Kathy Certified PO, Certified SM, Scaled Agile Framework Agilist)

Software Development, V&V

Sandia National Laboratories Albuquerque, NM

3

Page 4: Integrate V&V within Scrum: How Does That Work?

Introduction

Why we are doing this?

We are passionate about Agile and Scrum.

We are passionate about V&V and especially M&S V&V.

It is a bad idea to develop using Scrum and then throw V&V in at the end.

We want the application of V&V, which is traditionally very “waterfall-ish” to be agile.

4

Page 5: Integrate V&V within Scrum: How Does That Work?

What V&V Is and Isn’t

IS Required for development of systems,

software, and models

Based on best engineering practices

Iterative – Plan, Act, Assess

ISN’T Prescriptive

One size fits all

Easy

5

Our definitions Verification – ensuring that the software is implemented correctly

Validation – ensuring that model assumptions, theory, algorithms and results are correct/reasonable

Note: This talk isn’t a forum for argument about the Vs.

Likewise, we won’t be explaining Scrum terms.

Page 6: Integrate V&V within Scrum: How Does That Work?

So… How do we make V&V Agile?

Plan Development Work

Plan V&V Work

Merge both plans Into Scrum Roadmap, Epics & Stories

Execute both incrementally Perform development activities

Create development artifacts, e.g. code, documentation

Perform V&V activities

Create V&V artifacts and evidence

6

Page 7: Integrate V&V within Scrum: How Does That Work?

So… How do we make V&V Agile?

Merge Scrum and V&V planning and execution

Use an approach to merge the two Approach 1 – Define V&V planning/execution as

stories in the product backlog

Approach 2 – Define V&V planning/execution as tasks in stories

Combine approaches 1 & 2

Other approaches

We will focus on approaches 1 & 2 in this presentation.

7

Page 8: Integrate V&V within Scrum: How Does That Work?

How do we merge Scrum and V&V?

Approach #1 Add V&V planning work as Epics & Stories

Add V&V activities as Epics & Stories

Backlog has embedded V&V plans and activities

8

Page 9: Integrate V&V within Scrum: How Does That Work?

Approach #1 Overview

Identify V&V Activities

Use a tool (V&V Navigator) or other analysis

“Front-plan” V&V Epics, as needed

Approach V&V planning incrementally

9

Example questions from

Navigator:

Activity: Review Design

• Is design consistent and

implementable?

• Are requirements

traceable to the design

and adequately

addressed by the

design?

Page 10: Integrate V&V within Scrum: How Does That Work?

Approach #1 Overview

Add V&V activities to the Roadmap as Epics

Will be Epics for “Do It” e.g., Data Planning

Will be Epics for “V&V” e.g., V&V Data Collection Plan

Add Stories for V&V work

Either in a separate V&V BL or merge with Product BL

Stories for “Do It” and “V&V”

10

Page 11: Integrate V&V within Scrum: How Does That Work?

Approach #1 - Example Select Stories for a Sprint

11

Story: Design Collection for

accumulation of Results.

Story: Develop potential new

Use Case.

Sprint Backlog

Story: Design V&V approach

for Input and Results Data

Epic Backlog

V&V of Data Analysis & Processing

Planning for Data

Use/Needs/Collection

Design Database

V&V of Data Collection Plan

Requirements and Use Cases

Other Epics

V&V of Data Verification Plan

User Interface Implementation

Story: Implement Error Path

for User Interface.

Legend

V&V stories

Other stories

Page 12: Integrate V&V within Scrum: How Does That Work?

Approach #1 – Example Roadmap

12

Epic Sprint 1 Sprint 2 Sprint 3 Sprint 4 to 6 Quarter 2 Quarter 3 Quarter 4

V&V of Data Analysis & Processing

Design V&V Approach for Input and Results Data Story 6 Story 9

Adopt V&V Approach for Input Data Story3

Adopt V&V Approach for Results Data Story 7

Story 8

V&V of Data Characterization Plan

Story 1

Design Database

Story 1

User Interface Implementation

Story 1 Story 2 Story 3-5

V&V of Data Collection Plan

Story 1 Story 2

Requirements and Use Cases

Develop Potential New Use Case

Planning for Data Use/Needs/Collection

Story 1 Story 2-4

Legend

V&V stories

Other stories

Page 13: Integrate V&V within Scrum: How Does That Work?

Approach #1 – Another Example

Tie V&V activities to Development Activities all in one combined EPIC

Application: Develop Schedule Optimization Model

V&V approach: V&V Owner determines that V&V will include Expert Review of Optimization Algorithm

Integration testing

Epic: Develop Schedule Optimization Model Story – Select Optimization Algorithm (Dev)

Story – Prototype Optimization Algorithm - noncomputational model (Dev)

Story – Expert Review of Optimization Algorithm (V&V)

Story – Develop Code for Optimization Algorithm (Dev)

Story – Integration Test Optimization Algorithm Code (V&V)

13

Page 14: Integrate V&V within Scrum: How Does That Work?

How do we merge Scrum and V&V?

Approach #2 Embed V&V planning into Story Acceptance Criteria

Embed V&V activities into Story Tasks

Stories have embedded

V&V plans, activities, and Acceptance Criteria

14

Page 15: Integrate V&V within Scrum: How Does That Work?

Approach #2 Overview

As part of Planning, Identify the V&V Activities

Include each V&V Activity as a task in a Story e.g., Peer Review of Design (task) would be included in Design (story)

Drive V&V activities via Story Acceptance Criteria

15

Page 16: Integrate V&V within Scrum: How Does That Work?

Approach #2 - Example Acceptance Criteria In Stories

16

Story #: Design Collection for accumulation of Results Acceptance Criteria: Design Checked-in V&V Criteria: Peer Review of Design Complete V&V Owner Review

Story #: Meeting to discuss potential new Use Case Acceptance Criteria: Meeting held, notes distributed and in repository. V&V Criteria: none

Epic Backlog

Planning for Data

Use/Needs/Collection

Design Database

Requirements and Use Cases

Other Epics

User Interface Implementation

Story #: Implement Error Path for User Interface Acceptance Criteria: Implementation Checked-in; User Guide Updated V&V Criteria: Unit Test Pass, Regression Tests Pass, Test Plan Updated

Page 17: Integrate V&V within Scrum: How Does That Work?

Approach #2 - Acceptance

• Product Owner

Accepts completion of story according to the Acceptance Criteria when V&V tasks are included

Accepts completion of story including V&V Criteria met when V&V Criteria is included as part of the Acceptance Criteria

17

Page 18: Integrate V&V within Scrum: How Does That Work?

Considerations For Each Approach

Approach #1 – V&V embedded in the BL as stories V&V stories are visible

PO is responsible for V&V stories

Story Acceptance Criteria is explicit for V&V activities

V&V activities could be overlooked due to there not being an enforced 1:1 relationship between development and V&V

Approach #2 – V&V embedded in story tasks Team is responsible for tasking V&V activities

V&V is directly related to development activities

Coordination/effort required to embed the right activities as tasks in a story

V&V tasks could become box-checking-exercise instead of a useful task.

18

Page 19: Integrate V&V within Scrum: How Does That Work?

Consider a V&V Champion

Identify a person responsible for Ensuring V&V is addressed throughout development

Understanding how to merge Scrum and V&V

Assisting with selection of V&V methods (V&V Navigator lives here)

The V&V Champion can be the Product Owner The roles require different skill sets

V&V could be driven by the organization, not the customer

A designated V&V Champion is especially important with Approach 2 to ensure that V&V isn’t overlooked

19

Page 20: Integrate V&V within Scrum: How Does That Work?

V&V Navigator

Assists planning for V&V of Modeling and Simulation (M&S)

Any portion of the model includes theory or unknown science

Some output results are intentionally variable (e.g., optimization, prediction of future)

Where all answers/outputs are not known or agreed upon

The Process Step flow identifies what to plan for and what to do

Page 21: Integrate V&V within Scrum: How Does That Work?

21

Demonstration

V&V Navigator v. 2.0 can be distributed for Government Use.

Navigator

Page 22: Integrate V&V within Scrum: How Does That Work?

Final Thoughts

Plan Development Work

Plan V&V

Combine both plans Into Scrum Roadmap, Epics & Stories

Execute plans as per Roadmap Perform development activities

Perform V&V activities

Assess

Consider involving a V&V Champion!

22

Page 23: Integrate V&V within Scrum: How Does That Work?

QUESTIONS?

23

Page 24: Integrate V&V within Scrum: How Does That Work?

Contact Information

Julie Bouchard, [email protected]

Kathy Aragon, [email protected]