institutional project experience...kramer marks architects 156 south bethlehem pike ambler, pa 19002...
TRANSCRIPT
INSTITUTIONAL PROJECT EXPERIENCE
TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L PAGE 2 OF 13
Project: Annenberg School for Communication Expansion
Use: Broadcast Production Studios
Location: Philadelphia, PA
Size: 4,600 SF
Description: Expanded broadcast production facilities on
second floor of Annenberg Center on accelerated 8-week
schedule to accommodate wishes of donor, Comcast.
Services Performed: 1 month of pre-construction services,
followed by 8 weeks of field supervision as construction
manager.
OWNERUniversity of Pennsylvania3101 Walnut St
Philadelphia, PA 19104
ARCHITECTLinn Architects1140 N. Providence Road
Media, PA 19063
A N N E N B E R G S C H O O L F O R C O M M U N I C AT I O N E X PA N S I O N
TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L PAGE 3 OF 13
Project: Cottage 6 Renovation
Use: Residence
Location: Elwyn, PA
Size: 7,500 SF
Description: Renovation of existing building including MEP
upgrades, new doors, windows, and roof. ADA compliance
with new sidewalks, stairs and railing.
Services Performed: 1 month of pre-construction services,
followed by 4 months of field supervision as construction
manager.
E LW Y N C O T TA G E 6 - E LW Y N , P A
ARCHITECT RHJ Associates, P.C.1000 W. Ninth Avenue
King of Prussia, PA 19406
OWNERElwyn, Inc.111 Elwyn Road
Elwyn, PA. 19063
TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L PAGE 4 OF 13
E LW Y N D AV I D S O N S C H O O L
Project: Elwyn Davidson School
Use: School, facilities and bus loop for special needs students
Location: Elwyn, PA
Size: 132,000 SF
Description: Project is separated into five separate phases.
Interior and exterior renovations with systems upgrades
throughout the Elwyn Campus encompassing eight buildings
and a bus loop. Bus loop is integral to student and faculty
safety concerns. Upgrades to accommodate employee
daycare, student and resident classrooms, recreation
areas, offices for administrative staff as well as healthcare
professionals and caregivers.
Services Performed: 6 months of pre-construction services
followed by 18 months of field supervision as construction
manager.
OWNERElwyn, Inc.111 Elwyn Road
Elwyn, PA 19063
ARCHITECTKramer Marks Architects156 South Bethlehem Pike
Ambler, PA 19002
PAGE 5 OF 13TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L
Project: Drexel University 34th Street Tennis Courts
Use: Recreation, streetscaping, lighting
Location: Philadelphia, PA
Size: 15,000 SF
Description: Sitework and preparation to accommodate two
new tennis courts. Seating, lighting and fencing.
Services Performed: 3 months of pre-construction services,
followed by 10 months of field supervision as construction
manager.
ARCHITECT/ENGINEER Stantec 1500 Spring Garden St.
Philadelphia, PA 19130
OWNERDrexel University3201 Arch Street
Philadelphia, PA 19104
D R E X E L U N I V E R S I T Y T E N N I S C O U R T S - P H I L A D E L P H I A , P A
TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L PAGE 6 OF 13
G R E E N T R E E S C H O O L
OWNERGreen Tree School1196 East Washington Lane
Philadelphia, PA 19138
Project: Green Tree School
Use: School for special needs students
Location: Philadelphia, PA
Size: 60,000 SF
Description: LEED Silver 2-story building with partial basement. Employee daycare, K-8 classrooms, multi-purpose gymnasium/auditorium, offices for administration, nurse and staff. Autism Spectrum Disorder {ASD} rooms designed for music therapy, speech therapy, movement therapy and life skills instruction.
Services Performed: 3 months of pre-construction services, followed by 10 months of field supervision as construction manager.
ARCHITECTKramer Marks Architects156 South Bethlehem Pike
Ambler, PA 19002
PAGE 7 OF 13TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L
ARCHITECT The Knabb Partnership901 Lancaster Ave.
Berwyn, PA 19312
OWNEROur Lady of Perpetual Help (OLPH)2130 Franklin Avenue
Morton, PA. 19070
Project: Our Lady of Perpetual Help (OLPH) - School
Use: Classroom expansion
Location: Morton, PA
Size: 9,000 SF
Description: New addition including ten new classrooms,
four new bathrooms, three administrative offices.
Services Performed: 2 months of pre-construction services,
followed by 8 months of field supervision as construction
manager.
O U R L A D Y O F P E R P E T U A L H E L P ( O L P H ) S C H O O L - M O R T O N , P A
PAGE 8 OF 13TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L
ARCHITECT 3GHC Architects, LLC100 Park Ave
Swarthmore, PA 19081
OWNERSwarthmore College500 College Avenue
Swarthmore, PA 19081
Project: Swarthmore College - Papazian Hall Expansion
Use: Expanded psychology department
Location: Swarthmore, PA
Size: 3,000 SF
Description: New addition was constructed on the roof of
landmark Papazian Hall. Existing psychology department
facilities were renovated including new HVAC, electrical,
plumbing and fire protection systems.
Services Performed: 3 months of pre-construction services,
followed by 9 months of field supervision as construction
manager.
S WA R T H M O R E C O L L E G E - PA PA Z I A N H A L L E X PA N S I O N - S WA R T H M O R E , P A
PAGE 9 OF 13TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L
U N I V E R S I T Y O F P E N N S Y LVA N I A - E VA N ’ S S C H O O L O F D E N TA L M E D I C I N E
OWNERUniversity of Penn Design & ConstructionLeft Bank,
3401 Walnut Street
Philadelphia, PA 19104
Project: University of Pennsylvania - Evan’s School of Dental Medicine
Use: Dental School
Location: Philadelphia, PA
Size: 21,000 SF
Original Project Duration: 18 months
Actual Project Duration: 18 months
Description: The first major component in the renovation of
the Evans Building Main Clinic. The second main component
is to add a two-story addition to the west end of the
Schattner Building. This extension will connect to the main
floor and second floor of the Schattner Building, with the
intention to provide additional gathering space.
ARCHITECTEwingCole, RDLA100 N. 6th Street
Philadelphia, PA 19106
PAGE 10 OF 13TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L
ARCHITECT Lenhardt Rodgers Architects438 S. Bethlehem Pike
Fort Washington, PA 19034
OWNERValley Forge Military Academy1001 Eagle Road
Wayne, PA 19087
Project: Valley Forge Military Academy - Hart Hall
Use: Science Classrooms
Location: Wayne, PA
Size: 16,000 SF
Description: Interior upgrades to laboratory space. Work
included mechanical, electrical and plumbing. Extensive
installation of laboratory casework and surfaces.
Services Performed: 1 month of pre-construction services,
followed by 4 months of field supervision as construction
manager.
VA L L E Y F O R G E M I L I TA R Y A C A D E M Y - H A R T H A L L - WAY N E , P A
PAGE 11 OF 13TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L
ARCHITECT Lenhardt Rodgers Architects438 S. Bethlehem Pike
Fort Washington, PA 19034
OWNERValley Forge Military Academy1001 Eagle Road
Wayne, PA 19087
Project: Valley Forge Military Academy - Von Steuben Hall
Use: Cadet residence
Location: Wayne, PA
Size: 3,000 SF
Description: Renovation to accommodate female cadets in
new dormitory.
Services Performed: 1 Month of pre-construction services,
followed by 4 months of field supervision as construction
manager.
VA L L E Y F O R G E M I L I TA R Y A C A D E M Y - V O N S T E U B E N H A L L - WAY N E , P A
TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L PAGE 12 OF 13
ARCHITECT/ENGINEER Associated Engineering Consultants, Inc 485 Devon Park Drive
Wayne, PA 19087
OWNERWidener UniversityOne University Place
Chester, PA 19013
Project: Widener University - Howell Hall
Use: Interior fit-out, LEED consulting
Location: Chester, PA
Size: 17,000 SF
Description: 2-story building renovation including upgrades
to MEP systems. Carpentry package included millwork,
flooring, and installation of new doors and windows
throughout.
Services Performed: 1 month of pre-construction services,
followed by 4 months of field supervision as construction
manager.
W I D E N E R U N I V E R S I T Y - H O W E L L H A L L - C H E S T E R , P A
TARGETBUILDING.COM 610.521.3300 I N ST I T U T I O N A L PAGE 13 OF 13
Project: Wilmington Friends School - Private School Interior
and Exterior Renovation
Use: Meeting and Study Facilities
Size: 25,000 SF
Location: Wilmington, DE
Description: Historic renovation of interior and exterior of
Quaker school founded in 1748. Demolition and structural
reinforcement and shoring. Foundation underpinning.
Rough and finish carpentry. Gypsum wallboard, suspended
acoustical ceilings, flooring and architectural millwork
installation. New mechanical, electrical, plumbing and fire
protection systems.
OWNERWilmington Friends School 1001 School Road
Wilmington, DE 19803
ARCHITECTFrens & Frens435 West Miner St.
West Chester, PA 19382
W I L M I N G T O N F R I E N D S S C H O O L