Institute Of Hospital Engineering, Australia
Infrastructure Business Continuity Planning
Practical Problems Encountered
Neil Whittington (Arnold Risk Consulting)
![Page 2: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/2.jpg)
Crisis Management
Business Continuity
PlansIncident
Response
(Findings)
Advanced Incident
Investigation
IT Disaster Recovery
Strategic, Operational and
Project Risk
ARC Enterprise Risk Management
Range of Analytical Techniques,
Applicable to All Business Risks
Controls:
•Robustness
•Criticality
•Performance measurement
Prevention RecoveryResponse
Inci
dent!Hazard 1
Hazard 2 Control 3
Control 2Control 1
Insurance
![Page 3: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/3.jpg)
BCP POLICY
• Driver: Good governance• Purpose: Focus on external customers• Problem: Internal staff needs
![Page 4: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/4.jpg)
FINANCIAL RESOURCES
• Shortage in many industry sectors• Constrains BCP development• Seen as low priority (“couldn't happen”)• Solution: share costs with similar
organisations
![Page 5: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/5.jpg)
HUMAN RESOURCES
•Shortage: to develop and maintain•Solution: shared effort with others; external maintainer•Issue: can limit staff buy-in
![Page 6: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/6.jpg)
IDENTIFICATION OF POTENTIAL EVENTS
• Deficiency: available staff time• Prompts: insufficient for wide-ranging
thinking• Commonality: similar events in same
industry sector
![Page 7: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/7.jpg)
BCP PROCEDURES FOR RECOVERY
• Weakness: Long winded script • Result: Procedures ignored and hard to
find key actions• Solution: Quick reference cards
![Page 8: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/8.jpg)
CONFUSION WITH EMERGENCY RESPONSE
• Emergency: short phase, objectives mostly “make safe”
• Recovery: Restore critical business processes
• Teams involved: different skills
![Page 9: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/9.jpg)
NO LINK WITH CRISIS MANAGEMENT (CMT)
•Senior management role (CMT): stakeholders, authorizations
•BCP: recovery actions w/o stakeholder distractions
![Page 10: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/10.jpg)
TRAINING & TESTING
•Skills: inadequate, decline with organization changes•Solution: low cost, table-top format•Learnings: not included in BCP updates•Solution: easier with quick reference cards
![Page 11: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/11.jpg)
GAPS & OVERLAPS
• Result: key actions missed (or duplicated)• Solutions:
• team priorities vs individual action • tabletop tests• adhere to listed actions
![Page 12: Institute Of Hospital Engineering, Australia Infrastructure Business Continuity Planning Practical Problems Encountered Neil Whittington (Arnold Risk Consulting)](https://reader036.vdocuments.us/reader036/viewer/2022082821/5697c0141a28abf838ccd613/html5/thumbnails/12.jpg)
OVERVIEW
• Achievable with reduced resources• Share: development, testing, maintenance