installation instructions. delivery light fixtures, mounting structures and electrical components...

17
Installation Instructions

Upload: teagan-rone

Post on 16-Dec-2015

217 views

Category:

Documents


1 download

TRANSCRIPT

Installation Instructions

Delivery

Light fixtures, mounting structures and electrical components ship together

Poles ship on a separate truck

Field Installation

These Instructions are to be used as a

general guideline. It is up to the

contractor to determine their

own installation method

5 Step Process

Everything Supplied by USL

CE Fixture

Mounting Structure

Electrical Drop Cables

Electrical Enclosure

Pole Systems

CE Fixture Identification

Both Integral and Remote Ballast Systems Utilize the Same Optical Assembly and Share the Same Mounting ProcedureUp to 12 opticals ship in a large magna pack. Outside of magna pack is labeled fixture number and mounting structure.

Each optical assembly is labeled for specific location – pole designation and fixture number on mounting structure.

CE Fixture Optical Mounting

Optical has Plug Connection and Two Bolt Mounting

Mounting Structures / Factory Wired to Power Distribution Block in Junction Box

Service Basket Mounting

Crossarm Mounting

Electrical Drop Cable

Integral Ballast Drop Cable

Remote Ballast Drop Cable

Electrical Enclosures

Disconnect Enclosure

Remote Ballast / Disconnect Enclosure

Pole Installation Guidelines

The following pole installation steps cover direct embedded steel

and concrete poles, anchor bolt and flange base poles.

The information included in this document is to be used for

Guideline Purposes Only. It is up to the contractor to determine

their own installation method.

Before erecting poles it is recommended that the mounting

structure, fixtures and electrical be mounted to the poles while on

the ground.

Dig the Hole

The hole size and depth are determined by the size and type of

pole being installed, actual site soil conditions and wind.

It’s recommended that a geotechnical survey be conducted at

the pole locations and a certified

foundation design be provided and used

in determining base requirements.

Direct Burial Concrete and Steel

Setting Direct Burial Pole

Steel Pole

Direct Embedded Steel Poles can be a one, two or three section pole, depending on pole height. These poles can be set in two different ways. The pole sections can be put together while lying on the ground. The other option is to pick up and attach the base section of the pole then install the other sections over the already erected base section. Once pole is set and plumb back fill the hole with an aggregate material or concrete depending on soil conditions. Never back fill the hole with dirt.

Setting Direct Burial Pole

Concrete Pole

Direct Embedded Concrete Pole is a one section pole and can be picked up and set as a complete assembly. It is critical to use the pick points supplied by the pole manufacture when storing or lifting. Note: Be sure to check the pick point after reviewing weight of fixtures and mounting assembly. It is different than the pick points utilize to unload or move the pole alone. Once pole is set and plumb back fill the hole with an aggregate material or concrete depending on soil conditions. Never back fill the hole with dirt.

Anchor Bolt Steel

Setting An Anchor Bolt Pole

Construct the pole foundations as shown in picture. Due to site conditions, the foundation may extend above grade. The foundation design information is determined by a structural engineer and can be supplied by Universal Sports Lighting if included in the Bill of Material and a Geotechnical report is furnished. The foundation is determined by the size of pole, the soil conditions and wind.

The number of the anchor bolts is determined by the size of the pole and manufacturer of the pole. Universal Sports Lighting will supply the contractor with the information on how to orient the anchor bolts to the playing field. Care should be taken to provide the proper length of threaded anchor bolt projection.

Setting An Anchor Bolt Pole

Anchor bolt poles can be a one, two or three section pole, depending on pole height. These poles can be set in two different ways. The pole sections can be put together while lying on the ground and then picked up and attached to the anchor bolts. The other option is to pick up and attach the base section of the pole to the anchor bolts and then install the other sections over the already erected base section.

Pole Options

Tower Assemblies – Foundations Determined Site Specific