  • 7/30/2019 Installation Check List

    1/2

    Site : Location :

    Job No. : Voltage :

    Rating : Designation : Transformer

    Make : Sr. No.:

    No. CHECK REMARKS

    1.

    2.

    3.

    4.

    5.

    Foundation, Co-ordinates, Location, Level -ok?

    Installation as per equipment Tag no., Area of

    classification, layout drawing ok?

    Transformer centre line, level, roller stopper,

    ant-seismic mounting clamps etc ok?

    Assembly of all accessories and fittings

    completed?

    All cooling fans and fan control cubicle

    installed and connected?

    6.

    7.

    Oil cooling pump and piping connections

    completed?

    Oil / winding temperature gauges / relays

    installed?

    8. Buchholz relay

    a) Piping as per drawing

    b) Arrow towards conservator

    c) Float elements free

    d) Mercury Switches intact

    9. Breather

    a) Piping to conservator as per drawing

    b) Silica gel colour blue

    c) Air entry hole open

    d) Oil filled in bottom compartment10. Eplosion Vent

    Both and diaphragms intact

    11. Bushings

    a) No cracks observator

    b) Air Released

    c) Arcing horn gaps as per drawing

    12. All gaskets intact and new, drain valve closed?

    Dehydrated oil filled and topped up to level

    Oil level gauge in conservator ok & calibrated?

  • 7/30/2019 Installation Check List

    2/2

    12. All gaskets intact and new, drain valve closed?

    Dehydrated oil filled and topped up to level

    Oil level gauge in conservator ok & calibrated?

    13 Radiator

    a) Valves open

    b) No leakage at flanges & joints

    14 Air release from

    a) Radiators

    b) Bushings

    c) Buchholz relay

    d) Transformer tank

    e) OLTC Tank & Surge relay

    15 Instruments (OTI & WTI)

    a) Bulb inserted in pocket

    b) Pocket filled with oil

    c) Capacity checked and fixed properly

    16

    17

    18

    Marshalling box installed and connected?

    Tap Changer manual operation is free

    Bus duct installed and bus size and

    connections checked?

    19

    20

    O.H.HV jumpers, power and control cables

    terminated? size? connections?

    Earthing of neutral and body and Rail

    21

    22

    Danger Boards Installed?

    Fire extinguishers installed? Fire fightingsystem?

    23

    24

    Oil soak pit with gravel /collection pit?

    All unwanted materials cleared and

    Transformer kept clean?