inspection and maintenance of steel girders-2
TRANSCRIPT
-
8/12/2019 Inspection and Maintenance of Steel Girders-2
1/10
5.1.1 Foot OverBridges5.1.2 Road OverBridges
5.1.3 Track Bridges5.2 Inspection of steel girder
5.3 Cleaning and greasing of bearings
5.4 Protective painting of steel girder
5.4.1 Metallising5.4.2 Epoxy painting
5.4.2.1 Scheme of epoxy based paint5.4.3 Oil painting
5.5 Replacement of loose rivets
5.6 Repairs to welded joint
5.7 Strengthening of steel girder5.7.1 Common methods of strengthening
5.8 Replacement of corroded rivets
5.9 Conclusion
( i x )
-
8/12/2019 Inspection and Maintenance of Steel Girders-2
2/10
( x )
LIST OF ABREVIATIONS
BB&CI Rly Bombay Baroda and Central India Railway
BBJ & Co Braith Waite Burn and Jessop Company
BFR Bogie Flat type for Rails
BG Broad Gauge
BGBL Broad Gauge Branch Line
BGML Broad Gauge Main Line
BN Rly Bengal Nagpur RailwayCBE Chief Bridge Engineer
CDA Coefficient of Dynamic Augment
CECRI Central Electro Chemical Research Institute
DA Dynamic Augment
DFT Dry Film Thickness
DL Dead Load
DPT Dye Penetration Test
EI Rly East Indian Railway
EUDL Equivalent Uniformly Distributed Load
FOB Foot Over Bridge
GIP Rly Great Indian Peninsular Railway
HML Heavy Mineral Loading
HSFG High Strength Friction Grip
IRBM Indian Railway Bridge Manual
IRC Indian Road Congress
IRS Indian Railway Standard
IS Indian Standard
JE Junior Engineer
km KilometrekN Kilo Newton
kmph kilometer per hour
LG Light Gauge
-
8/12/2019 Inspection and Maintenance of Steel Girders-2
3/10
( x i )
LL Live Load
m Metre
MBG Modified Broad Gauge
MG Meter Gauge
MGML Metre Gauge Main Line
mm Millimetre
MMAW Manual Metal Arc Welding
MMG Modified Metre Gauge
MS Mild Steel
MSM Rly Madras Southern Maratha Railway
NDT Non Destructive Testing
NG Narrow Gauge
ODC Over Dimensional Consignment
PSC Pre-stressed Concrete
PTFE Poly Tetra Fluoro EthyleneRBG Revised Broad Gauge
RCC Reinforced Cement Concrete
RDSO Research Design & Standards Organisation
RH Girder Restricted Height Girder
RL Rail Level
Rly Railway
ROB Road Over Bridge
RSJ Rolled Steel Joint
RUB Road Under Bridge
SAW Submerged Arc Welding
SBC Substructure Bridge Code
SE Section Engineer
t tonnesUSFD Ultra Sonic Flaw Detection
WDM Water Bound Macadam
-
8/12/2019 Inspection and Maintenance of Steel Girders-2
4/10
1
CHAPTER - 1
INTRODUCTION
Ever since the 1st railway train was hauled in April 1853 by asteam engine over a stretch of 33 Km track between BombayVictoria Terminus to Thane, Railways in India have never lookedback and have continued with their achievements withaccelerated pace. As on date we have about 63,465 route km ofrailway track network throughout the length and breadth of thecountry.
Building of a railway track over various stretches of landcris-crossing different cities, districts and states all over,necessarily involves tremendous earthwork, rock cuttings,tunneling and bridging. Out of these vital prerequisites, bridging isthe most intricate and multifaceted constituent in the railwaytrack requiring a precise and exhaustive exercise in its planning
and execution, considering its probable repercussions on theentire railway system for long years.
Number of bridges on Indian Railways as on date are to the tuneof about 1.21 lakhs belonging to the various types and lengthsand in different categories.
With the inception of railway transport system in India the
railway traffic was handled by different companies such as GIPRly., BN Rly., El Rly., MSM Rly., BB & Cl Rly., etc. In addition,various princely states formed their own railway network with theavailable technical know-how and resources as obtained in thosedays. Hence each system followed its own gauge and standard.However, as far as the type of gauge is concerned we had onlyfour types of gauge namely, B.G., M.G., N.G. and L.G. But thecriteria for bridges adopted was different depending on the
technology and material as obtained in those days.
But all the same a sort of similarity appears to have beenmaintained in designing and construction of these bridges, maybe by interaction between various construction agencies at
-
8/12/2019 Inspection and Maintenance of Steel Girders-2
5/10
2
various places and locations throughout the country.
Broadly speaking, the bridges in the early days of the railwaysystem were mostly based on steel structures shipped fromBritish Railways to India and after cannibalising in railwayworkshops and placing them in the track as super-structures forwhich suitable substructures out of stone or brick masonry piersand abutments or steel piles for piers and abutments wereconstructed. As the loads to be hauled initially were quite low,the sizes of substructures and girders were also less massive.
The bridge superstructures in the form of steel girders are either(1) beam type -(plate girders) or (2) truss type (open web). Themetal used in the fabrication of these girders was mostly wroughtiron based on the technology as obtained in those days. Thisperiod is roundabout earlier to 1885. These girders were eitherfabricated in England or released from British Railways andtransported to India by ship and after due modifications in railway
workshops in India were placed in track. Since these wereshipped from England to India, the despatch list accompanyingthe material was named as Shipping list. This nomenclatureholds good even today for despatch list of materialaccompanying the girders from railway workshops to varioussites.
Some of the early workshops known as Girder FabricationWorkshops were established at Manmad and Mugalsarai. Thetranshipped girders and structures were strengthened/modified inthese workshops to suit the extant loading standard anddimensions and put in the road wherever needed.
As the steel technology developed over the years and as therailways began expanding in a big way especially afterindependence in 1947, a dire need was felt to undertakefabrication of these girders on a huge scale during the
successive five year plans for various new construction lines aswell as for regirdering programmes. With this in view thefabrication of these steel girders was undertaken in railwayworkshops at Manmad, Mugalsarai and other railway workshops.
-
8/12/2019 Inspection and Maintenance of Steel Girders-2
6/10
3
After 1960 these workshops started fabricating open web girdersalso. As on date railway workshops fabricate girders of spans
ranging from 9.15m length to 76.2m length, (9.15, 12.2, 18.3,24.4m spans being plate girders and 30.5m, 45.7m, 61.0m and76.2m spans being open web through girders and also 30.5munderslung deck girders).
In addition a few spans of 91.4m and 122.2m have beenfabricated and erected by M/s. BBJ & Co. of Calcutta. CivilEngineering Workshop Manmad had also fabricated 3 nos.122.2m welded open web through spans, for Konkan RailwayCorporation in the year 1995.
After 1980 welded construction is being adopted for fabrication ofplate girders (open deck), open web girders and compositegirders (ballasted deck) of track bridge. Steel being an idealmetal for fabrication of railway bridge girders due to its tensileand compressive strengths being more or less equal, it isextensively used for railway bridge girders. Moreover before final
failure, it generally gives sufficient warning to the maintenanceengineer in the form of loss of camber, thus avoiding suddenfailure.
1.1 TYPES OF STEEL GIRDERS
In the early days, the railway track bridge- steel girders were ofthe following types :
1) Duplicated channels with longitudinal sleepers to carry
the track.2) Duplicated beams with cross sleepers to carry thetrack.3) Wide flange beam girders.4) Fish belly type girders, single or duplicated, called
beams of uniform strength.5) Pin connected triangulated type--Single or duplicated.6) N type open web deck girders7) Whipple through girders
8) Howe type through truss9) Pratt type through truss10) Camel back truss11) Baltimore through truss
-
8/12/2019 Inspection and Maintenance of Steel Girders-2
7/10
4
1676
250
1676
300
1676
1200
Fig. 1.1 DUPLICATE CHANNEL GIRDER(FOR SPAN UPTO 2.4 m)
Fig. 1.3 WIDE FLANGE BEAM GIRDER
Fig. 1.2 DUPLICATE BEAM WITH CROSS SLEEPERS(FOR SPAN UPTO 3.6 m)
-
8/12/2019 Inspection and Maintenance of Steel Girders-2
8/10
5
ELEVATIO
N
FIG.1.4FISH
BELLY
GIRDERS
(SINGLE
OR
DUPLIC
ATE)
SECTIO
N
X-X
(SINGLE)
SECTION
X-X
(DUP
LICATE)
X X
-
8/12/2019 Inspection and Maintenance of Steel Girders-2
9/10
6
Fig. 1.5 PIN CONNECTED TRIANGULATED TRUSS
Fig. 1.6 N TYPE TRUSS
Fig. 1.7 WHIPPLE TRUSS
Fig. 1.8 HOWE TRUSS
Fig. 1.9 PRATT TRUSS
-
8/12/2019 Inspection and Maintenance of Steel Girders-2
10/10
7
Fig. 1.10 CAMEL BACK TRUSS
Fig. 1.11 BALTIMORE TRUSS
Fig. 1.12 WARREN TRUSS
THROUGH TRUSS PONY TRUSS
Fig. 1.14
DECK TRUSS
Fig. 1.13 K TRUSS