● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Mar k A . Bouma , P.E . Te c h n i c a l O v e r s i g h t L e a d e r
N o r t h Te x a s To l l wa y A u t h o r i t y
O c t o b e r 1 7 , 2 0 1 2
Innovative But Familiar : Delivering
Chisholm Trail Parkway
![Page 2: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/2.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Who We Are – History
Origins with Texas
Turnpike Authority
Dallas North Tollway
opened in 1968
Created in 1997 as a
Texas political
subdivision
First TollTag issued in
1989
First option to build toll
roads
![Page 3: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/3.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Who We
Are Now
![Page 4: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/4.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
NTTA Growth
The f irst 15 years (1997-2012)
1997 2012*
Total Revenue $66.3 million $480.8 million
Toll Revenue $53.8 million $459.8 million
Operating Budget $11.5 million $117.4 million
Outstanding Debt $1.6 billion $9 billion
Center-line Miles 21 111
Lane Miles 124 824
Employees 228 733
Transactions 125 million 565 million
Toll Tags to Date 2,622,324
Counties with Toll Roads (Open / In Construction) 2 5
* Estimates for System and Special Projects System
![Page 5: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/5.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Creating Organiza tional Change
Traditional Engineering Department would not scale to
handle increased work load
Reviewed other major transportation organizations to
learn from their large project management systems
– DFW Airport ($2.1 billion, 5 years)
– Florida Turnpike Enterprise ($5 billion, 5 years)
– T Rex, Colorado ($1.7 billion, 5 years)
– I-15, Salt Lake City ($1.6 billion, open for 2002 Olympics)
– Illinois Tollway ($5 billion, 10 years)
![Page 6: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/6.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Lessons Learned From Other
Program Management Organiza tions
Clearly Defined Decision-Making Process
Manager Responsible to Deliver Programs/Corridors
Effective Communication and Coordination is Mandatory
Focused Schedule and Cost Control Approach
Flexible Resources Approach to Meet Program Demands
Co-Located/Integrated Agency and Consultant Team
Ability to Handle Projects in Various Stages in a
Consistent Manner
Delivery Methods Decisions Were Based on the
Agency’s Ability to Deliver
![Page 7: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/7.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
NTTA PMO Implementa tion
Created Project Delivery Department led by Assistant
Executive Director and Director of Project Delivery
Corridor Manager – concept to concrete
New tools to manage and deliver consistent results
– Quality Management System (QMS)
Document existing processes
New manuals (Design, Construction, ROW, etc.)
Project Estimating Templates
– Enterprise Project Delivery System (EPDS)
– Schedule & budget tracking with executive dash board
– ISO 9001 compliant – annual audits
![Page 8: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/8.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Project Delivery —
Organizational Char t
![Page 9: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/9.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Quali ty Management System
![Page 10: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/10.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Process Manuals
![Page 11: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/11.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Cost Control
Program Master Schedule
Design to Budget
Value Engineering
Forecasting
Change Order Process / Procedures
Risk Management
Project Delivery – Packaging / Methods
Bid Scheduling
![Page 12: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/12.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Estimating Templa tes
![Page 13: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/13.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Web-Based Management System
Access
Accountability
Audit Benefits
Cost and Schedule
– Reduces coordination errors
– Reduces travel & delivery costs
– Saves project management expense
– Eliminates lag time in moving information
– Encourages timely responses
Reporting
– Improves coordination & communication
– Enforces standards and procedures
– Establishes accountability - provides an audit trail
![Page 14: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/14.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Transparency in Financial Repor t ing
Monthly Project Delivery
Report
– Corridor progress reports
– Program status reports –
schedule and financial
– Major consultant expenditures
– Letting schedule
Bond documents
NTTA budgets & expenditures
![Page 15: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/15.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Project Delivery —
Organizational Char t
![Page 16: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/16.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
PMO – Lessons Learned
Rapidly mobilized new organization to respond to
change
Developed valuable procedures and standardization
Too many layers and levels
– Message diluted
– Delayed decision making
– Difficulties in resolving conflicts
Responsibility without authority
Contractors confused – who’s in charge?
![Page 17: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/17.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
PMO ver. 2
Size of the program shrinking
Reorganized the PMO structure
– PMO functional leads report to staff subject matter experts
– Eliminated senior PMO management layers
– Senior staff member involved in day-to-day activities
Decisions on budget, schedule, quality stay in-house
![Page 18: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/18.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Compressed Organiza tion
![Page 19: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/19.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Chisholm Trail
Parkway
Limits: I-30 to U.S. 67
Length: 27.6 miles
NTTA’s first project in
Tarrant and Johnson
counties
![Page 20: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/20.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
2008 2009 2010 2011 2012 2013 2014 Limits Section
FM 1187 to U.S. 67 6
S. of Altamesa to FM 1187 5
S. of Overton Ridge to S. of Altamesa 4
S. of Arborlawn to S. of Overton Ridge 3B
Arborlawn to Overton Ridge –
local access improvements 3A
Forest Park Blvd. to S. of Hulen St. 2C
At Hulen St. and UPRR Davidson Yard 2B
Rogers Rd. to S. of Arborlawn 2
I-30/Summit Ave. 1
Project Overview
![Page 21: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/21.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Chisholm Trail Parkway History
1960’s: First added to transportation plan
1997: Completed 1st traffic and revenue study
TxDOT led environmental clearance while NTTA led
development of schematics
2008: Southwest Parkway and Chisholm Trail
Parkway combined into one project
Total project cost estimated at $1.8 billion
![Page 22: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/22.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Project Parameters
• Corridor Design Aesthetics, per Corridor Master Plan
• Rails
• Lighting
• Bridge Design
• Landscape/trees
• Monuments
• “Parkway Feel”
• Reduced Speeds
• I-30 to north of SH 183 50 mph
• North of SH 183 to Altamesa 60 mph
• Altamesa to U.S. 67 70 mph
• Additional $0.04/mile for CMP
![Page 23: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/23.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
![Page 24: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/24.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Funding Gap
Chisholm Trail Parkway Construction
00/00/00
A lot of dollars
$$$$$$$
North Texas Tollway Authority
![Page 25: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/25.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Solving the Funding Gap
Considered value engineering and staging/ phasing
of construction:
Reduced pavement thickness
Use of RAP in HMA
Balanced the earthwork for the entire project,
not just within a section
Deferred construction of several direct
connectors
Deferred construction of ultimate roadway
section in allowable areas
![Page 26: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/26.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Financing the Project
Applied for federal assistance (TIGER and TIFIA)
Received $116 million TIGER grant
Did not receive TIFIA loan
Looked at innovative financing – entered into TELA
with TxDOT to reduce borrowing costs
Brought costs down to $1.4 billion
![Page 27: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/27.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Par tnership a t Work
NTTA
Tarrant County
Johnson County
City of Fort Worth
RTC
TxDOT
![Page 28: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/28.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Funding Contr ibutions
TxDOT: $154.3 million
RTC: $322.1 million
City of Forth Worth: $56.5 million
NTTA equity contribution: $328.4 million
Previous NTTA contribution: $68.3 million
Revenue bonds: $668.9 million
Revenue during construction: $2.5 million
![Page 29: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/29.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
CTP Project Management Plan
Goal – to deliver quality NTTA projects on time and
within budget
Expand opportunities for professional services firms
and contractors
Define daily management structure and reporting
Consultant and contractor training in NTTA tools
Keep the public involved and informed
![Page 30: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/30.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
CTP Project Organiza tion Char t
![Page 31: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/31.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Project Updates
31
www.ntta.org
General information: 817-916-5105
Lane closures: 817-207-0184
![Page 32: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/32.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Chisholm Trail Parkway Traf f ic Updates
• Updated daily
• NTTA website
• 817-207-0184
![Page 33: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/33.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
Chisholm Trail Update
Weekly e-Newsletter
• Emailed to you or available on the NTTA website
• Send an email to [email protected] to
subscribe
![Page 34: Innovative But Familiar: Delivering Chisholm Trail Parkway · 2017-01-04 · N o r t h Tex a s To l l way A u t h o r i t y Mark A. Bouma, P.E. Tec hnical Oversight Leader North Texas](https://reader035.vdocuments.us/reader035/viewer/2022080723/5f7c125664c914325f1eedfd/html5/thumbnails/34.jpg)
● N o r t h T e x a s To l l w a y A u t h o r i t y ●
MISSION ● provide a safe and reliable toll road system ● increase value
and mobility options for our customers ● operate the Authority
in a businesslike manner ● protect our bondholders ● partner to
meet our region's growing need for transportation