inmr2015 - munich field experience and reliability tests ... · pdf filefield experience &...
TRANSCRIPT
Field Experience & Reliability Tests for the New EasyDry Condenser Bushing
LUKAS MUGGLI
© ABBSlide 1September 8, 2015
T. Schütte, ABB Schweiz Ltd, High Voltage Components, Bushings, 2015-10-19
INMR2015 - MunichField experience and reliability tests for the new EasyDry condenser bushing
© ABBSlide 2September 8, 2015
INMR2015 - Munich
Why do you care about bushings?
How does an EasyDry bushing look like?
Which ageing mechanisms do apply to EasyDry bushings?
How does an EasyDry bushing perform?
RIS Technology – applied to ABB EasyDry Bushings
© ABBSlide 3September 8, 2015
Bushings contribute for 3% of the total costs of a transformer, but…
… their failure is one of the three main causes for a transformer failure
… are responsible for up to 40% of transformer fires - in case of OIP bushings
Why do you care about bushings?
Source: S. Tenbohlen et al., «Transformer Reliability Survey: Interim Report», Electra No. 261, pp. 46-49, April 2012
© ABBSlide 4September 8, 2015
Why do you care about bushings?
1. Safety of people and equipment
2. Availability of equipment and assets:
Reliability
Long-life cycle
Safe to store
Customer needs
AGEING
© ABBSlide 5September 8, 2015
Ageing mechanisms in an EasyDry bushing
Ageing of a component depends heavily on the load and on the conditions on site
The three main contributors for ageing of a dry bushing:
Thermo oxidation is the main ageing mechanism for the insulation
Perform a ‘Thermal ageing test’
Multi cycle load due to mechanical impacts or temperature changes
Perform a ‘Multi bending test’
Humidity uptake of insulation material
Perform a ‘Boiling water test’
© ABBSlide 6September 8, 2015
How does an EasyDry bushing look like?EasyDry Cross-Section
Copper terminal (air side)
Silicone insulator
Condenser core
Mounting flangeMeasuring tap
Current transformer extension, if required
Clamp to fix terminal
Oil side shield
© ABBSlide 7September 8, 2015
Wind on air side connection leads to permanent mechanical forces on the bushing
Changes in current load of bushing and changes of outside temperature leads to thermal expansion and contraction of the bushing
Small, but steady mechanical impacts on the bushing over the entire lifetime
Reliability tests for EasyDry condenser bushingsMulti bending test – Why?
© ABBSlide 8September 8, 2015
Most severe test – in addition to standard requirements: This test was performed in collaboration with a utility (Westnetz, according to the RWE standard)
This test included 3 temperature cycles between -30°C and +40°C
The bushing was bent 25’000 times in x- and y-direction with 60% of the cantilever load according to IEC 60137 during the temperature cycles
Reliability tests for EasyDry condenser bushingsMulti bending test – Test procedure
© ABBSlide 9September 8, 2015
Following the thermo-mechanical pre-stress, a complete type test according IEC 60137 was performed and the bushing successfully passed it
An additional peeling test was performed by cutting into the insulation. The results showed no delamination between the silicone and the epoxy condenser core - even after these extreme tests
Reliability tests for EasyDry condenser bushingsMulti bending test – Results
© ABBSlide 10September 8, 2015
Humidity ingress of the condenser core during storage or installation leads to an increased power factor
Humidity on the interface between outdoor insulator and condenser core might lead to treeing and finally to flashover
Humidity inside of the bushing is dangerous and can cause fatal break downs
Reliability tests for EasyDry condenser bushingsBoiling water test – Why?
© ABBSlide 11September 8, 2015
Humidity ingress can be measured with tanδ measurements
So far, no type test is defined by IEC for direct molded bushings for testing the interface between silicone insulator and condenser core
Yet, IEC specifies a type test for surge arresters (IEC 60099)
The bushing was mechanically and thermally pre-stressed according toIEC 60099:
4 bending cycles per 90°(for 24h with 1400N)
Temperature cycles btw. -40°C and +60°C
Reliability tests for EasyDry condenser bushingsBoiling water test – Test procedure
© ABBSlide 12September 8, 2015
Most severe test No. 2 – in addition to standard requirements: The bushings were actually boiled for 42 hours in deionized water containing 1 kg/m3 NaCl (salt)
After this extreme boiling test, the bushings have (again) passed a complete type test acc. IEC 60137
After cutting the silicone and performing a peeling test for testing purposes we could not find any delamination between the silicone and the epoxy condenser core
Reliability tests for EasyDry condenser bushingsBoiling water test – Results
© ABBSlide 13September 8, 2015
Ageing of insulation material may limit the lifetime of a bushing due to occurrence of partial discharges or increased tanδ
Thermo-oxidation is the main ageing process of epoxy insulation within a dry-type condenser bushing
Reliability tests for EasyDry condenser bushingsThermal ageing tests – Why?
© ABBSlide 14September 8, 2015
Material samples aged at different temperatures (btw. 160 = T1 and 240°C = T5)
After defined periods, samples were tested (diagnostic property)
Time till diagnostic property drops to 50% of initial value is determined using linear regression
Determined lifetimes τ50% are plotted against temperature T
Temperature resulting in defined lifetime (typically 20’000h) is determined
Reliability tests for EasyDry condenser bushingsThermal ageing tests – Test procedure
© ABBSlide 15September 8, 2015
The comparison between RIP and RIS revealed that RIS material showed a slower ageing process than RIP material. Yet, this is just a comparison between the two materials. A final answer about lifetime cannot be given at this time.
Although the tests are of comparative nature, they show that the expected life time should exceed that of RIP material 30 years lifetime in service expected
Reliability tests for EasyDry condenser bushingsThermal ageing tests – Results
Time [h]
Time [h]
© ABBSlide 16September 8, 2015
- International transmission
- 132kV, 230kV, 300kV DC
- National transmission
- 132kV, 275kV, 500kV DC
- Local Distribution
-11, 22, 33kV
RIS Bushing Field Performance – Malaysian ExperienceAbout TNB Malaysia
Owner of Malaysian grid network from 500kV to 11kV
© ABBSlide 17September 8, 2015
RIS Bushing Field Performance – Malaysian Experience
The assessment of risks and gathering knowledge on new technologyperformance and reliability in a tropical climatic environment
Shorter lead time, faster manufacturing duration
Ease of storage, no special requirement i,e protective cover etc
What interest TNB to embark on this project….
© ABBSlide 18September 8, 2015
RIS Bushing Field Performance – Malaysian Experience
Project Commencement Date : April 2013
Pilot Installation Date : Apr 2014
Pilot Completion Date : Dec 2014
Summary of Project
8 months duration
© ABBSlide 19September 8, 2015
RIS Bushing Field Performance – Malaysian Experience
Max Ambient 24-40 deg C
Average Humidity 70-90%
Rainfall 4000mm per year
High Average isokeraunic level 300 light.days/year
Why Malaysia ? - Geographical Information
© ABBSlide 20September 8, 2015
• Manufactured in 1999
• Manufacturer Wilson, Australia
• 60/90MVA full transformer
• 132/33kV Load Transformer
• ONAN/ONAF (Cooling)
• Fitted with 145kV GOB ABB Sweden OIP Bushings
Easy Dry RIS Bushing
Um=145kV, 650kVp BIL, 1250A
RIS Bushing Field Performance – Malaysian ExperiencePilot Transformer
© ABBSlide 21September 8, 2015
RIS Bushing Field Performance – Malaysian ExperienceFactory Routine Test
Partial Discharge Test
Dielectric Dissipation & Capacitance
@167kV (2Uo) < 2.0 pC
Parameter Before Dielectric After Dielectric
DielectricDissipation
Factor
0.243% 0.241%
Capacitance 220pF 220pF
© ABBSlide 22September 8, 2015
Service Performance ResultsCapacitance and Voltage Monitoring
No permanent change or capacitance more than allowable +-3%
12 3
1 2 3UL +3%
LL -3%
© ABBSlide 23September 8, 2015
Service Performance ResultsInfrared Scanning
47.6C
19.6K
46.7C
18.7K
46.9C
18.9K
The max difference between phases approx 0.7K@38MW
85.9K84.9K89.0K
The limits between adjacent bushing werebelow of max limit < 20K
38MW
Full Load 81MW
© ABBSlide 24September 8, 2015
Service Performance ResultsCapacitance & Dissipation Factor Measurement
Offline Dissipation Factor & Capacitance did noexceed the agreed tolerances, indicating that therewas no significant change in insulation structure orpresence of contaminants that can influence theresults.
© ABBSlide 25September 8, 2015
RIS Bushing Field Performance – Malaysian Experience
Based on findings and conclusion based on trial project evaluation, the project team concluded that the RIS bushing technology was proven reliable and showed excellent performance in the field
Conclusion
© ABBSlide 26September 8, 2015
Summary
Main ageing mechanisms for EasyDry bushings are:
Mechanical bending
Humidity ingress
Thermo oxidation of insulation material
All performed tests have shown equal or better results when compared with the existing RIP technology
RIS used for EasyDry bushings is a maturing technology for dry-type bushings