initial plan of boiler light up feb 13
DESCRIPTION
Initial Plan of Boiler Light Up Feb 13TRANSCRIPT
Sheet1
Boiler Light Up Start Up Power planStatus as onInstallation, testing and commissioning of station batteries along with associated battery chargersThe temporary 400 Volt supply for battery charger may be arranged from construction power available at site, which will ultimately be fed from regular 400 Volt switchboards.Installation, testing and commissioning of 4 nos. 11 KV switchboards in 33 / 11 KV sub-station for extending startup power at 11 KV to main 11 KV switchboards OCA, OCB, 1CA and 1CB through 11 KV 3 core 300 mm2 cableTo install 16 MVA, 11 / 6.6 KV station service transformer just outside A-row near column no 10 11 and commissioningCharging 6.6 KV station service switchboards Installation of 2.5 MVA station and unit PCC transformersCharging of station and unit PMCCs at 415 Volt so that 415 V supplies will be extended to boiler MCCInstallation of DCS panels in main control room and cabling for essential services required for boiler light up.Identification of essential services for Boiler Light UpCommissioning of DCS batteries including DCS battery chargers.
Power Supply to ID & FD Fan Power Supply to APHPower Supply to Fuel Oil System
Arrangement of DM and ACW System
Raw water supply to clarifloculator by operating intake pumping station pumpsCommissioning of clarifloculators (HRSSC)for making available clarified water which shall be fed to ACW system through service water piping and for making available DM water required for boiler and DMCCW system for steam generatorReadiness of Condensate Storage Tanks (at least 1 no.) with completion of piping from CST to boiler fill pump for boiler fillingA return piping of size 300 NB is required to be laid down by DBPL from ACW Hot water header up to clarified water storage tanks
Fuel Oil System:The piping from fuel oil tanks up to the fuel oil pressurizing and forwarding pumps (supplied by BHEL) is required to be completed by L&T.The fuel oil pressurizing pumps are required to be installed and are to be commissioned by BHEL for which 400 V supply shall be arranged by L&T from 400 V switchboards being installed in the fuel oil pump houseThe fuel oil piping from fuel oil pump house up to the boiler is required to be got completed through BHEL for which the readiness of the pipe rack PR-4 is required
Availability of ID and FD Fan:Mechanical readiness is required to be ensured for 1 ID and 1 FD fan including oil system and oil flushing etc.The DMCCW system for cooling of ID fan and FD fan 11 KV cabling including protection cabling is required to be completed for 1 ID and 1 FD fan for their operation from local / DCS including commissioning of VFD system for ID fan
Bottom Ash Hopper:Readiness of bottom ash hoper with refractory lining with seal truf arrangement is required to be ensured
Compressed Air System: At least one compressor is required to be made ready and commissioned for supply of instrument / service air required for various systems. Idenntification of various system requiring instrument and service Air for Boiler Light Up
Fire System for Boiler Operating FloorThe fire hydrant system is required to be made available with commissioning of booster pumps for feeding fire hydrant at boiler platform. Since the fire hydrants pumps are yet to be installed by L&T as such this system may have to be charged by using another available pump which can develop pressure around 6 Kg/cm2