initial environment examination - asian … environment examination this report has been submitted...
TRANSCRIPT
Initial Environment Examination
This report has been submitted to ADB by the Government of Uttarakhand, Dehradun and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB.
Project Number: 40648-033 May 2014
IND: Infrastructure Development Investment Program for Tourism – Tranche 2
Submitted by
Department of Tourism, Government of Uttarakhand
Environmental Assessment Document
Initial Environmental Examination (IEE) Loan Number: 2833 IND May 2014
Infrastructure Development Investment Program for Tourism, Uttarakhand
Subproject – Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
Prepared by the Government of Uttarakhand for the Asian Development Bank
This IEE is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
ABBREVIATIONS ADB - Asian Development Bank BOD - Biological Oxygen Demand BOQ - Bill of Quantities CO - Carbon monoxide CPCB - Central Pollution Control Board DSC - Design and Supervision Consultant EA - Executing Agency EAC - Expert Appraisal Committee EARF - Environment Assessment and Review Framework EIA - Environmental Impact Assessment EMP - Environment Management Plan ES - Environmental Specialist GC - General Conditions GoI - Government of India GoUK - Government of Uttarakhand IDIPT - Infrastructure Development Investment Program for Tourism IEE - Initial environmental examination INR - Indian Rupee IPIU - Investment Program Implementation Unit IPMU - Investment Program Management Unit KMVN Kumaon Mandal Vikas Nigam PUC - Pollution Under Control Certificate MLD - Million Liters per day MoEF - Ministry of Environment and Forests MFF - Multi- Trench Financing Facility NGO - Non-Governmental Organization NOx - Nitrogen oxide PD - Project Director PIU - Project Implementation Unit PM - Particulate Matter PMU - Project Management Unit RP - Resettlement Plan RPM - Respirable Particulate Matter SC - Scheduled Castes SEAC - State Expert Appraisal Committee SO2 - Sulphur dioxide SPM - Suspended Particulate Matter SPS - Safeguards Policy Statement ST - Scheduled Tribe
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
CONTENTS S.
No. Chapter Page No.
EXECUTIVE SUMMARY 5 I Introduction 9
A. Background 9 B. Purpose of the IEE 9 C. Environmental Regulatory Compliance 10 D. Report Structure 12
II Description of Project Components 13 A. Project Overview 13 B. Present Status 13 C. Project Components 14 D. Project Implementation Schedule 15
III Description of Existing Environment 15 A. Environmental Profile – Physical Resources 15 B. Ecological Resources and Biodiversity 17 C. Economic Resources 19 D. Social and Cultural Resources 20
IV Environmental Impacts and Mitigation Measures 22
A. Land Acquisition and Resettlement 22 B. Environmental Impacts 22
V Environmental Management Plan 35
A. Institutional Arrangements 35 B. Environment Management 36 C. Environmental Monitoring Plan 38 D. Capacity Building 39 E. Environmental Budget 42 F. Environmental Monitoring and Reporting 43
VI. Public Consultation and Information Disclosure 44 A. Consultation Process 44 B. Future Consultation and Information Disclosure 45 C. Grievance Redress Mechanism 45
VII Findings & Recommendations 48 VIII Conclusions 48
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
4
List of Tables
Table No.
Description Page No.
1. Environmental Regulatory Compliance 10
2. Ambient Air Quality (24 hours basis) 19 3. Ambient Noise Quality 19 4. Demographic profile of Project Area 20 5. Basic Amenities of Project Area 21 6. Summary of Environmental Impacts and Mitigation Measures 28 7. Environmental Monitoring Plan 38
8. Training Modules for Environmental Management 40 9. Environmental Budget 42 10. Consultations with Stakeholders 44
List of Annexures
Annexure No. Description Page no.
1. Rapid Environmental Assessment (REA) Checklist 49 2. Location Map 54 3. Photographs of Trekking Trail Project Area 55 4. NOC's from Stake Holders 56 5. Ambient Air Quality, Noise Level Monitoring Report 59 6. Public Consultation Photographs 62 7. Public Consultations on 26-30 December 2013 63 8. Public Consultations on 06-08 January 2014 72
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
5
EXECUTIVE SUMMARY
1. The Infrastructure Development Investment Program for Tourism (IDIPT) envisages an environmentally and culturally sustainable and socially inclusive tourism development, in the project states of Himachal Pradesh, Punjab, Tamil Nadu and Uttarakhand, delivered through a multi-tranche financing facility (MFF) modality. Project 2 includes the states of Uttarakhand and Tamil Nadu. 2. The project for the ‘Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak’ is located in Pithoragarh which is the district head quarters of the same name. The district forms the north-eastern part of the Kumaon Division and lies between Lat. 29º27´N. and 30º49´N. and Long. 79º50´E. and 81º3’E., the length from north to south, being about 151 Km. at its maximum, and the breadth from east to west, reaching its maximum at about 119 Km. It is bounded by Tibet on the north, Nepal on the east, district Almora on the south and the districts Almora and Chamoli on the west. 3. Pithoragarh is known as the gateway to the Himalayas from the north, as pilgrims trek through this town to the Kailash Lake Manasarovar, and Om Parvat. There are 12 temple sites in and around the town proper, located on hilltops or forested hillsides with attractive views over the valley. Most of the temples are only accessible by treks from the main roads and provide good opportunities for the establishment of trekking circuits between them.
4. The proposed trekking trail on Chandak hill is located to the north-west of Pithoragarh by road which is 150km north of Tanakpur and 210km from Kathgodam railway terminals. The airport at Pithoragarh (Naini Saini) is not operational. Chandak hill at an elevation of 6000 ft, on the northern frontier of the Soar Valley and offers a fascinating view of the Himalayan ranges and the sprawling meadows of Pithoragarh. Chandak hill has scenic and pilgrimage values and recognizing this potential it is being proposed to be developed as a tourism destination under the current Subproject.
5. This Initial Environmental Examination (IEE) has been prepared for "Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak" Uttarakhand under Tranche 2. The IEE has been prepared based on the primary, secondary data, field visits, reconnaissance survey and public and stake holder's consultations6. Under the scope of this sub-project the trekking route being proposed in two different sections include:
i. Nature and Culture based Eco-tourism Trail- (S4 to S6 -1.13 Km) connecting Forest Rest House entrance to connecting point of vehicular road (Bajethi road). It is at close proximity to Tourism Department’s Tourist Rest Rouse, Public Works Department and Forest Rest House. It is well frequented and heavily used by local people for walks and exercising in the midst of the natural environment. Nature lovers frequent this trek for features like vast natural expanses, jungle tracts, traditional village homes, streams, bio-diverse ecosystem, etc.
ii. Chandak Pilgrim Trail: From PT1- S5 (1.40 Km) connecting near from the meeting point of mid eco tourism trail (PT1) to Chandak Forest Check Post. Starts from midway of the eco-tourism trail and connects to the Chandak temple complex. This walk is just above the Bajethi road and the gradient is nominal. It is frequented by local people/villagers on foot and connects various natural features and provides good view of Pithoragarh town. The trail connects various natural and built features like streams, flora, small groves, redundant plant, ruins, etc. The trail has certain vantage points which can be developed further for various recreational purposes.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
6
6. The components proposed under the scope of this sub-project is meant to tap into recognized tourism potential of Chandak which presents to visitors panoramic views of Pithoragarh town and its beautiful mountain setting. The Nature trail is heavily used by the locals. The route of the proposed heritage and nature trail is also frequented by nature enthusiasts for birds and insects spotting. 7. The subproject is needed to strengthen the tourism potential of this area as this site is very popular among local visitors, nature lovers, bird watchers and other similar interest groups.
8. The proposed subproject mainly comprises of i. Redevelopment of Nature and Culture based Eco-tourism Trail (1.13 KM)
ii. Redevelopment of Chandak Pilgrim Trail (1.40 KM)
iii. Redevelopment of the existing Viewpoint as the start point for Nature and Culture
based Eco-tourism Trail. (below the PWD Guest House)
iv. Provision of Trail Markers, Directional and Facility Signage- Planning and design for
the trekking route
v. Provision of Street furniture, weather shelters, railing and fencing along the trekking
route.
vi. Landscaping and Horticulture development of trekking trail
9. Construction of all elements will begin in the Second quarter of the year 2014, and work will be completed in the third quarter of 2015. Total implementation period is 14 months. 10. Ownership of Land The trek starts from Pithoragarh town near PWD office and ends at Chandak covering the villages of Bajethi, Puneri and closed unit of Magnesite & Mineral Factory on the way.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
7
The trail is used by the students and other community of nearby 15 villages and Pithoragarh town. The proposed Trail alignment falls under the ownership of Nagar palika parishad, Pithoragarh except for a section of 300m which falls under the forest Department. One of the proposed view point falls under the ownership of Van panchayat. 11. There are 15 revenue villages situated in the surroundings of Chandak within a periphery of 8 kms. The population of these villages is about 3249 with 659 households, mainly Brahmins, Rajputs and scheduled castes. The people of these villages are dependent on religious tourism based activities for their livelihoods. There is potential of tourism development in the area which will provide more employment to the local youth and improve the livelihoods security of local community. Due to favorable climate, there is scope of floriculture, vegetable cultivation and dairy in the area. 12. The subproject has been categorized as B as per the ADB‘s Safeguard Policy Statement (2009). The subproject is not covered in the ambit of the EIA notification 2006 and EIA Act 2009. As a result, the categorization, and the subsequent environmental assessment and clearance either from the state or the central Government is not required. 13. As part of IEE, a detailed assessment of impacts due to location, design and pre-construction, construction, operation and maintenance have been made. The anticipated impacts are generic to the construction activities. But mitigation measures will be applied to minimize these impacts. 14. Sub project also entails separate plan for developing the proposed landscaping during the initial phase of trail design so that the existing landscape should be preserved and incorporated into the design. Incidental landscaping of appreciation foregrounds with minimal interventions to enhance strategic halts along the trail where trekkers can halt along the trail to appreciate the scenic beauty of the place has been proposed. Also, proposed is landscaping and place making of identified start and end points by highlighting the start and end point of the trekking trail through minimalistic landscaping to attract the visitors.
15. An Environmental Management plan (EMP) outlining the specific environmental measures to be adhered to during various phases of implementation of the subproject has been prepared. The subproject will conform to all Government regulations, policies, and standards, as well as Asian Development Bank‘s Safeguard Policy Statement (2009) 16. A number of stakeholder discussions have been conducted. The project design incorporates the views of primary and secondary stakeholders including local communities and local officials who were all meaningfully consulted during IEE and project preparation 17. The environmental impacts of the project are therefore not significant and at Category B level, as per ADB's Safeguards Policy Statement. The specific measures stated in the EMP will address all adverse environmental impacts due to the subproject. Impacts are readily mitigated through careful siting, specific selection criteria for procuring contractors with demonstrated experience; execution of proven mitigation measures during the design; and adoption of good engineering practices during construction and implementation. A detailed monitoring plan prepared as part of this IEE will further mitigate negative environmental impacts during implementation 18. A Project Management Unit (PMU) is established in Dehradun for the overall project management and Project Implementation Units (PIU) is also established at Bhimtal. A Safeguards Specialist within the PMU will be responsible for implementation of the resettlement and environmental safeguard provisions. Project Management Consultants (PMC) and Design and Supervision Consultants (DSC) provide assistance to the PMU/PIUs in project implementation. Within the PMC team a Safeguards Specialist will provide overall
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
8
management of environmental and social issues, and will provide technical support to the PMU including implementation of the environmental and resettlement issues according to ADB’s requirements, and assist in monitoring impacts and mitigation measures associated with sub- projects. The Safeguards Specialist of the DSC team will be responsible for preparation of the Environmental Assessment documents in line with the EARF and supervise the implementation of the EMP provisions in the various sub-projects. 19. The DSC Safeguards Specialist will support environmental management functions including updating sub-project IEEs in respect to environmental management plans, assisting in preparing IEEs, and assist in monitoring impacts and mitigation measures associated with sub- projects. He/she will be required to include mitigation measures in designs where appropriate, and to specify other measures in construction contracts. Contractors will be required by their contracts to implement all specified mitigation, monitoring, and reporting assigned to contractors as presented in sub-project IEE. 20. The subproject is unlikely to cause significant adverse impacts. The potential adverse impacts that are associated with design, construction, and operation can be mitigated to standard levels without difficulty through proper engineering design and the incorporation or application of recommended mitigation measures and procedures. Based on the findings of the IEE, the classification of the Project as Category “B” is confirmed, and no further special study or detailed EIA needs to be undertaken to comply with ADB SPS (2009) or GoI EIA Notification (2006).
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
9
I. INTRODUCTION
A. Background
1. The India Inclusive Tourism Infrastructure Development Project (IITIDP) envisages
an environmentally and culturally sustainable and socially inclusive tourism development, in
the project states of Himachal Pradesh, Punjab, Tamil Nadu and Uttarakhand. The expected
Impact of the Project in the four states is sustainable and inclusive tourism development in
priority State tourism sub circuits divided into marketable cluster destinations that exhibit
enhanced protection and management of key natural and cultural heritage tourism
sites, improved market connectivity, enhanced destination and site environment and tourist
support infrastructure, and enhanced capacities for sustainable destination and site
development with extensive participation by the private sector and local communities.
2. The proposed subproject mainly comprises of
i. Redevelopment of Nature and Culture based Eco-tourism Trail (1.13 KM)
ii. Redevelopment of Chandak Pilgrim Trail (1.40 KM)
iii. Redevelopment of the existing Viewpoint as the start point for Nature and Culture
based Eco-tourism Trail. (below the PWD Guest House)
iv. Provision of Trail Markers, Directional and Facility Signage- Planning and design for
the trekking route
v. Provision of Street furniture, weather shelters, railing and fencing along the trekking
route.
vi. Landscaping and Horticulture development of trekking trail
3. Construction of all elements will begin in the second quarter of the year 2014, and work
will be completed in the third quarter of 2015. Total implementation period is 14 months.
4. As per the Asian Development Bank’s (ADB) Environmental Assessment Guidelines, and in line with the Environment Assessment and Review Framework (EARF) for the project,
all the sub-project components for the proposed works are categorized as ‘B’ and an Initial Environmental Examination (IEE) prepared. This Initial Environmental Examination (IEE)
assesses the environmental impacts due to the proposed "Revival and Development of
Trekking Trail and Vantage Points at Pithoragarh to Chandak" and specifies measures
towards addressing the impacts. The IEE is based on a review of sub-project site plans and
reports; field visits, collection of primary and secondary data to characterize the environment
and identify potential impacts; and interviews and discussions with stakeholders.
5. Based on the findings of the IEE, an Environmental Management Plan (EMP) has
been prepared, outlining the specific environmental measures to be adhered to during
various phases implementation of the sub project. This EMP forms part of the contract
document, and shall enable integration of environmental provisions / management measures
in the Contract Document.
B. Purpose of IEE
6. The present proposal is aimed at "Revival and Development of Trekking Trail and
Vantage Points at Pithoragarh to Chandak". The environmental impacts due to this subproject
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
10
are mostly related to the location of the site and construction impacts. Therefore, as per the
Asian Development Bank’s (ADB) Environmental Assessment Guidelines, the sub-project
components are categorized as ‘B’ and this IEE has been carried out. This IEE provides
mitigation measures for impacts related to location and design, construction, operation, and
maintenance.
C. Environmental Regulatory Compliance
7. The realm of environmental regulations and mandatory requirements for the
proposed subproject is shown in Table 1. The Environmental Impact Assessment (EIA)
notification, 2006 by the Ministry of Environment and Forests (MoEF, GoI) specifies the
mandatory environmental clearance requirements. Accordingly, all projects and activities are
broadly categorized into two categories1 - Category A and Category B, based on the spatial
extent of potential impacts and potential impacts on human health and natural and man-
made resources. Given that the sub-project is not covered in the ambit of the EIA
notification, Environment clearance requirements from the GoI are not triggered.
Table 1: Environmental Regulatory Compliance for Revival and Development of
Trekking Trail and Vantage Points at Pithoragarh to Chandak
Applicability of Acts/Guidelines Compliance Criteria
The EIA notification, 2006 (and its
subsequent amendments in 2009)
provides for categorization of
projects into category A and B, based
on extent of impacts.
These sub-projects are not covered in the ambit of the EIA
notification as they are not covered either under Category A or
Category B of the notification. As a result, the categorization, and
the subsequent environmental assessment and clearance
requirements, either from the state or the GoI is not triggered. 1
The Water (Prevention and Control
of Pollution) Act 1974 and The
Water (Prevention and Control of
Pollution) Rules 1975
The Act and Rules outlines the activities which are prohibited
on account of their potential to cause water pollution. Pollution
from various sources in this Trekking Trail needs to be
controlled as per this Act and Rules
The Ancient Monuments and
Archaeological Sites and Remains
Act, 1958, and the rules, 1959
provide guidance for carrying out
activities, including conservation,
construction and reuse in and around
the protected monuments.
Project site is not an ASI protected monument and there are no any
monuments of this nature within the jurisdiction..
Therefore, the provisions of the act does not apply
1 Aノノ ヮヴラテWIデゲ ラヴ ;Iデキ┗キデキWゲ キミIノ┌SWS ;ゲ C;デWェラヴ┞ けAげ キミ デエW SIエWS┌ノWが キミIノ┌Sキミェ expansion and modernization of existing projects or activities
and change in product mix, will require prior environmental clearance from the Central Government in the Ministry of Environment and
Forests (MoEF) on the recommendations of an Expert Appraisal Committee (EAC) to be constituted by the Central Government for the
ヮ┌ヴヮラゲWゲ ラa デエキゲ ミラデキaキI;デキラミき Aノノ ヮヴラテWIデゲ ラヴ ;Iデキ┗キデキWゲ キミIノ┌SWS ;ゲ C;デWェラヴ┞ けBげ キミ デエW SIエWS┌ノWが キミIノ┌Sキミェ W┝ヮ;ミゲキラミ ;ミS マodernization of
existing projects or activities as specified in sub paragraph (ii) of paragraph 2, or change in product mix as specified in sub paragraph (iii) of
paragraph 2, but excluding those which fulfil the General Conditions (GC) stipulated in the Schedule, will require prior environmental
clearance from the State/Union territory Environment Impact Assessment Authority (SEIAA). The SEIAA shall base its decision on the
recommendations of a State or Union territory level Expert Appraisal Committee (SEAC) as to be constituted for in this notification. In
addition, GWミWヴ;ノ CラミSキデキラミ ふGCぶ ラa デエW ミラデキaキI;デキラミ ゲヮWIキaキWゲ デエ;デ ;ミ┞ ヮヴラテWIデ ラヴ ;Iデキ┗キデ┞ ゲヮWIキaキWS キミ C;デWェラヴ┞ けBげ ┘キノノ HW デヴW;デWS ;s
Category A, if located in whole or in part within 10 km from the boundary of: (i) Protected Areas notified under the Wild Life Protection)
Act, 1972, (ii) Critically Polluted areas as notified by the Central Pollution Control Board from time to time, (iii) Notified Eco-sensitive areas,
(iv) inter-State boundaries and international boundaries
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
11
Applicability of Acts/Guidelines Compliance Criteria
Forest (Conservation) Act, 1980
This act provides guidelines for conservation of forests and
diversion of forest land for non-forest use. The law also states
guidelines on de-reservation of various categories of forests for
diversion of forest land. This law describes the penalty for
contravention of the provisions of the Act. Restriction on the de-
reservation of forests or use of forest land for non-forest
purpose.
For felling of the tree if any permission will be required from local forest office. The Indian Wildlife (Protection) Act,
1972, amended 1993, The Wild Life
(Protection) Amendment Act, 2002
This Act provides guidelines for protection of [Wild animals,
birds and plants] and for matters connected therewith or
ancillary or incidental thereto. It also states the norms for
hunting of wild animals, prohibition of picking, uprooting, etc., of
specified plants. The Act deals with the declaration of area as
Sanctuary, National Park, and closed area and also states the
restriction of entries in the sanctuary. There is no protected
area in the vicinity.
Not Applicable for the subproject
Biodiversity Act 2002 and
Biodiversity Rules 2004
The Act essentially controls access to indigenous biodiversity
resources. No agency/person referred to in sub-section (2)
shall, without previous approval of the National Bio-diversity
Authority, obtain any biological resource occurring in India or
knowledge associated thereto for research or for commercial
utilization or for bio-survey and bio-utilization.
Not Applicable for the subproject ADB Safeguard Policy Statement,
(2009)
Categorization of subproject components into A, B or C and
developing required level of environmental assessment for each
component.
Sub-project is Category B as no significant impacts are
envisaged.
8. It can be observed from Table-1, that the proposed sub-project does not need to go
through a full-scale environmental assessment process; as the scale of impacts and
categorization of the sub-project components will not require clearances from Competent
Authorities. The environmental screening (REA Checklists annexed) reveals that the most
significant environmental impacts are anticipated during construction phase and are generic
to construction activities. However since it is an existing trail not much impacts are anticipated
even in the operation phase. Thus all impacts are site specific, reversible and can be readily
mitigated supporting a Category B classification.
9. The sub-project selection criteria specify that all project activities pertaining to "Revival and
Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak" are in
accordance with the provisions of the prevalent local norms and Forest guidelines.
10. The ADB guidelines, stipulate addressing environmental concerns, if any, of a
proposed activity in the initial stages of Project preparation. For this, the ADB Guidelines
categorizes the proposed components into categories (A, B or C) to determine the level of
environmental assessment required to address the potential impacts. The Rapid
Environmental Assessment (REA) checklist method was followed as per ADB requirement to
assess the potential impacts of the project in planning phase. The REA checklist is attached
as Annexure 1 with this report. The subproject has been categorized as B as per the ADB‘s
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
12
Safeguard Policy Statement (2009). Accordingly this IEE has been prepared to address the
potential impacts, in line with the recommended IEE content and structure for Category B
project. 2
The IEE has been conducted based on Primary and secondary sources of
information and field reconnaissance surveys and stakeholder consultations.
Evaluation has been conducted for impacts likely to accrue due to due to location, design
& pre-construction, construction, operation & maintenance. An EMP outlining the specific
environmental measures to be adhered to during implementation of the subproject has been
prepared.
D. Report Structure
11. This Report contains eight (8) sections including this introductory section: (i)
Introduction; (ii) Description of Project Components; (iii) Description of the Existing
Environment; (iv) Environmental Impacts and Mitigation Measures; (v) Environmental
Management Plan; (vi) Public consultation & Information Disclosure; (vii) Findings and
Recommendations; and (viii) Conclusions
2As per SPS 2009 projects are assigned to one of the following four categories: (i) Category A. A proposed
project is classified as category A if it is likely to have significant adverse environmental impacts that are irreversible, diverse, or unprecedented. These impacts may affect an area larger than the sites or facilities subject to physical works. An environmental impact assessment is required. (ii) Category B. A proposed project is classified as category B if its potential adverse environmental impacts are less adverse than those of category A projects. These impacts are site-specific, few if any of them are irreversible, and in most cases mitigation measures can be designed more readily than for category A projects. An initial environmental examination is required. (iii) Category C. A proposed project is classified as category C if it is likely to have minimal or no adverse environmental impacts. No environmental assessment is required although environmental implications need to be reviewed (iv) Category FI. A proposed project is classified as category FI if it involves investment of ADB funds to or through a FI (paras. 65-67).
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
13
II. DESCRIPTION OF PROJECT COMPONENTS
A. Project Overview
12. The project for the ‘Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak’ is located in Pithoragarh which is the district head quarters of the same name. The district forms the north-eastern part of the Kumaon Division and lies
between Lat. 29º27´N. and 30º49´N. and Long. 79º50´E. and 81º3’E., the length from north
to south, being about 151 Km. at its maximum, and the breadth from east to west, reaching
its maximum at about 119 Km. It is bounded by Tibet on the north, Nepal on the east, district
Almora on the south and the districts Almora and Chamoli on the west.
13. Pithoragarh is a small town that lies in the centre of the western half of the Soar
Valley surrounded by four distinct hills Chandak, Dhwaj, Kumdar and Thal Kedar, and
stretches in the southern flank to Jhulaghat demarcated by the Kali river adjoining the barren
peaks of Nepal Hills. It is snuggled in the folds of four kots Bhatkot, Dungerkot, Udaikot and
Unchakot. The view from some of the higher altitudes in Pithoragarh captures the snow-
capped peaks of Panch Chulhi, Nanda Devi and Nanda Kot.
14. Under the scope of this sub-project the trekking route being proposed in two different
section includes:
Nature and Culture based Eco-tourism Trail- (S4 to S6 -1.40 Km) connecting
Forest Rest House entrance to connecting point of vehicular road (Bajethi road).
This trail is off-shoots from Bajeti Road at the entrance of Forest Rest House which
passes through picturesque cultural, natural and man-made landscapes. Nature
lovers frequent this trek for features like vast natural expanses, jungle tracts,
traditional village homes, streams, bio-diverse ecosystem, etc.
Chandak Pilgrim Trail: From PT1- S5 (1.13 Km) connecting near from the meeting
point of mid eco tourism trail (PT1) to Chandak Forest Check Post.
Starts from midway of the eco-tourism trail and connects to the Chandak temple
complex. This walk is just above the Bajethi road and the gradient is nominal. The
trail connects various natural and built features like streams, flora, small groves,
redundant plant, ruins, etc. The trail has certain vantage points which can be
developed further for various recreational purposes.
15. Project location map is shown in Annexure 2. Photo illustration of project location is
depicted in Annexure 3
A. Present status
16. The trail route is proposed over an existing pedestrian trail route which is generally well
used by the local villagers. The trails have been identified on the basis of their accessibility
and the fact that they are linking routes for the temple and major roads. The overall condition
of the two identified sections of the trail namely the Nature and Culture based Eco-trail and
the Chandak Pilgrim Trail is as follows:
The trail alignment is there, but repair, enhancement required.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
14
Erosion and land slide was observed at many locations due to steep slopes and poor
drainage.
Trails are generally not well maintained and erosion poses problems on steep trails
or along trails that follow a contour line on a steep slope.
The evidence of historical remains along the trail not well preserved.
The trail is steep and narrow at a few places and there are loose rocks which poses a
challenge to the safety and ease of pedestrians using the trail.
Drainage across trail is an issue which is a major cause for degrading of slopes.
B. Project components
i. Redevelopment of Nature and Culture based Eco-tourism Trail (1.13 KM)
ii. Redevelopment of Chandak Pilgrim Trail (1.40 KM)
Sub Project Components:
(i) Redevelopment of the existing Viewpoint as the start point for Nature and Culture
based Eco-tourism Trail. (below the PWD Guest House)
(ii) Provision of Trail Markers, Directional and Facility Signage- Planning and design for
the trekking route
(iii) Provision of Street furniture- Design proposals for benches, weather shelters, railing
and fencing along the trekking route.
(iv) Landscaping and Horticulture development of trekking trail
Developing and Place making of identified entry and exit points
Provision of protection walls, natural retaining walls, etc.
Crossover bridge over the brook and Outlooks structures as view points
Widening of only select sections for safety reasons.
Provision of congruous drainage and stream crossovers.
Grade corrections at steep and unsafe places
Incidental landscaping of appreciation foregrounds
Environmental engineering- training, stream bank conservation, plantation, etc.
Slope protection; weather shelters; etc.
Pathways and rest points
(v) Development of pedestrian pathway along the main metalled Bajethi road from the end
point of heritage trail (Forest check post/ Dhabha) upto Meghna View point and
restaurant.
Design of Trail markers, directional and facility signage.
Design and Provision of street furniture at appropriate locations.
Design of segregated walkway for tourist/visitor/pilgrims along the Bajethi road.
The proposed Trail alignment falls under the ownership of Nagar palika parishad,
Pithoragarh except for a section of 300m which falls under the forest Department. One of the
proposed view point falls under the ownership of Van panchayat. No objection certificate
from all stakeholders Nagar Palika Parishad, Van Panchayat and Forest Department is
attached as Annexure 4.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
15
C. Project Implementation Schedule
17. The implementation period for the proposed subproject is 14 months. Concept Plan
preparation started in May 2013. Detailed design started in August 2013. Construction of all
elements will begin in the Second quarter of 2014, and work will be completed in the third
quarter of 2015.
III. DESCRIPTION OF EXISTING ENVIRONMENT
A. Environmental profile- Physical Resources
18. Uttarakhand became a separate state carved out of hill districts and sub Himalayan
regions of Uttar Pradesh in the year 2000 and is the newly formed hill state in the Indian
Himalayan Region. The geographical location (28°43' N to 31°27' N and 77°34' E to 81°02'
E) resource setting of Uttarakhand is unique and shares its borders with China and Nepal. It
borders the Tibet Autonomous Region on the north, Nepal on the east and the Indian states
of Uttar Pradesh to the South, Haryana to the West and Himachal Pradesh to the North
West. There are 13 districts in Uttarakhand which are grouped into two divisions: Kumaon
division and Garhwal division. The Kumaon division includes six districts: (i) Almora, (ii)
Bageshwar, (iii) Champawat, (iv) Nainital, (v) Pithoragarh, and (vi) Udham Singh Nagar. The
Garhwal division includes seven districts: (i) Dehradun; (ii) Haridwar; (iii) Tehri Garhwal; (iv)
Uttarkashi; (v) Chamoli; (vi) Pauri Garhwal (commonly known as Garhwal); and (vii)
Rudraprayag.
19. Uttarakhand has a total geographical area of 51,125 km², of which 64% is covered by
forest. A large part of the state is made mountainous. Most of the northern parts of the state
are part of Greater Himalaya ranges, covered by the high Himalayan peaks and glaciers,
while the lower foothills were densely forested. The difference in altitude between the lowest
parts and the highest part (snow peaks of Nandadevi) is almost 7,000 meters.
20. Topography Pithoragarh is located at 29.58°N 80.22°E. It has an average elevation of
1,514 metres (4,967 feet). Pithoragarh is a small town, which gives its name to the district. It
lies in the centre of the western half of the Soar Valley which resembles the Kashmir valley
on a miniature scale. It is prettily dotted with villages, generally placed on eminences. The
view from some of the higher altitudes in Pithoragarh captures the snow-capped peaks of
Panch Chulhi, Nanda Devi and Nanda Kot. The town is set in a valley popularly known as
"Soar" (root meaning is Cool) and lies in the centre of four hills Chandak, Dhwaj, Kumdar
and Thal Kedar, and stretches in the southern flank to Jhulaghat demarcated by the Kali
river adjoining the barren peaks of Nepal Hills. It is snuggled in the folds of four kots Bhatkot,
Dungerkot, Udaikot and Unchakot.
21. Pithoragarh, is known as the gateway to the Himalayas from the north, as pilgrims trek
through this town to the Kailash, Lake Manasarovar, and Om Parvat.The district is named
after its headquarters town, Pithoragarh. Tradition has it that during the reign of the Chand
rajas of Kumaon, one Piru, also called Prithvi Gosain, built a forthere and named it
Prithvigarh which in, in course of time, got changed into Pithoragarh. According to another
local legend, Pithora, a Gurkha raja, constructed a fort here and called theplace Pithoragarh.
According to the 2011 census Pithoragarh district has a population of 485,993, roughly equal to
the nation of Suriname.[1] This gives it a ranking of 546th among the 640 Districts of India. The
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
16
district has a population density of 69 inhabitants per square kilometre (180 /sq mi).
Its population growth rate over the decade 2001–2011 was 5.13%. Pithoragarh has a sex
ratio of 1021 females for every 1000 males, and a literacy rate of 82.93%. Native tribes in
the district include the Van Rawats and Bhotiya (an exonym). Van Rawats are hunter-
gatherers. Bhotiyas are traders. In Pithoragarh, the Bhotiya are divided into two main tribes – Johari Shauka and Rung. The Johari Shauka community inhabits the areas in Munsiyari
while Rung tribe are spread among the three valleys of Darma, Chaundas, and
Byans. Kandali Festival, celebrated once every 12 years by inhabitants of Chaundas Valley,
is one of the major festivals in this area.
Geology
22. The district lies in the Himalayas which are the youngest mountains in the world and the
land mass now covered by them was occupied by the great geosynclinal Tethys sea during
the Mesozoic period. The probable date of commencement of the elevation of the Himalayas
is about the close of the Mesozoic period. According to geological formations of the district, it
may be divided into four broad belts, viz., (1) the innermost Siwalik hill ranges, (2) the lesser
and middle Himalayas, (3) the inner Himalayas and (4) the thin belt bordering the Tibetan
Himalayas, roughly tending east-south-east.
23. The belt of the innermost hill ranges of the Siwalik group lies in the southern part of the
district. In the rock formations here sandstones alternate with clayey shales. The sandstones
are dirty, friable and micaceous and are, therefore, unsuitable for the building, ballast and
industry. The second belt, comprising the ranges of the lesser and middle Himalayas,
extend north of the Siwalik group to Dharchula. It contains sedimentary and low to medium
grade metamorphic rocks such as limestone, slate, quartzite, phyllite and mica-garnet schist.
Mineralization of copper, magnesite, soap-stone, etc., is known to occur in this belt. The
third belt, containing higher ranges of the inner Himalayas, is wholly composed of crystalline
metamorphic rocks such as mica and garnet schists, kyanite and sillimanite schists,
gneisses, granulites and quartzites. This belt is very little known geologically. The belt
extends from near Dharchula to Garbyang. The fourth belt, bordering the Tibetan Himalayas
has an average width of about 7 km. It contains marine sedimentary rocks such as
quartzites, fossiliferous limestones and shale. Minerals like copper, manganesite, soapstone,
arsenic, sulphur, kyanite, graphite, slate, limestone etc are found in various pockets in
Pithoragarh district.
Climate
24. The elevation of the district ranges from 500 m. above sea level in the valleys in the
south to over 7000 m. in the snow-bound Himalayas in the north and north-west. The
climate, therefore, largely depends on altitude and varies according to aspect and elevation.
Although tropical beat may be experienced in the southern valleys during the summer, the
winters are severe. As most of the district is situated on the southern slopes of the
Himalayas, monsoon currents penetrate through the deep valleys and rainfall is at the
maximum in the monsoon season (June to September), particularly in the southern half of
the district. The northern half of the district also gets considerable rain during the winter
season which lasts from mid-November to March.
25. Pithoragarh town, being in a valley, is relatively warm during summer and cool during
winter. During the coldest months of December and January, the tropical
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
17
and temperate mountain ridges and high locations receive snowfall and have an average
temperature of 5.5–8.0 °C (42–46 °F). Pithoragarh district has extreme variation in
temperature due to the large variations in altitude. The temperature rises from mid-March
through mid-June. The areas above 3,500 metres (11,500 ft) remain in a permanent snow
cover. Regions lying at 3,000–3,500 metres (9,800–11,500 ft) become snow bound for four
to six months. At places like the river gorges at Dharchula, Jhulaghat, Ghat and Sera,
temperatures reach 40 °C (104 °F). The annual average rainfall is 36.7 centimetres (14.4 in).
After June the district receives monsoon showers. Winter is a time for transhumance – the
seasonal migration of the Bhotiya tribe with their herds of livestock to lower, warmer areas.
Soils
26. The soil texture in the area varies from coarse loamy, to clayey loamy to silty clay
depending on location in the catchment. The majority of forest soil belongs to brown forest
soil category. Textural variation is high and within small area, sand content varies from 4.5 to
65%. Silt content ranged from 6.6 to 46.7% and clay content ranged from 3.1 to 56%.
Variations are explained by the change of parent material. Sand, stones and shales occur
side by side, where as limestone may be found erratically. Alluvium derives forms may vary
within short distances depending on the nature of streams.
Water Quality
27. There is no water body near the pithoragarh to chandak trekking trail.
B. Ecological Resources and Biodiversity
28. Part of the trail comes under forest department, Pithoragarh division, Van Panchayat
Forest. Mainly the trees are Pine, Acacia, Rhododendron.
Flora
29. The northern part of the district, comprising the larger portions of tahsils Munsyari and
Dharchula, where there are high mountains and ridges, is rocky, bland and covered with
perpetual snow. The forests are confined to the river valleys and the southern parts of the
district. Taking into consideration the differences in the altitudes and the climatic conditions
which obtain in the district, its flora may be divided into four main forest types i.e. the sal
forest, chir forests, oak forests and the coniferous forests. The willow and older trees are,
however, common everywhere in damp situations. The deodars are introduced plants in the
district but have become wild. They are found in the southern part of the district around the
temples where they had been planted for many generations, their magnificent groves being
seen around Gangolihat.
30. Sal Forests: These forests occur in the southern part of the district and the chief tree,
sal, is found up to a height of about 1,220 m. and as far as north as patti Malla Askot. On the
hills the sal does not attain the height to which it grows in the plains. Other associated trees
which also grow in these forests are the haldu, sain, kharik, and tun kharik, the last two
being comparatively less common. The sal logs are chiefly used for building purposes. The
bhyunl, an extremely useful tree, grows in the valleys and lower hilly slopes and is carefully
protected, for its leaves afford excellent fodder for cattle, and the fibres of its young shoots
are twisted into ropes. Up to heights of about 900 m., trees common in the plains, viz., the
mango, pipal, banyan and, sissoo are very frequently in evidence.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
18
31. Chir Forests: The chir is the principal component of forests up to altitudes of about
1,800 m., growing between 500m., when not unduly exposed to the sun, and 2,200 m. on a
south aspect. Chir trees are usually found alone, for they appear to have the power of driving
away all other vegetation from the tract where they are found Chir is the staple building
timber in the hills, while vast quantities of it are exported in the shape of sleepers. Torches
are cut out of the living wood. Resin is also extracted from the tree. Its seeds are eaten.
32. Oak Forests: The principal varieties of oak found in the district are the banj, tilonj and
the kharsu, each occupying a more or less distinct altitudinal zone. Banj begins to grow at
heights of 1,800 m. and 2,450 m. The tree usually attains no great height. Its wood, being
hard and gnarled, is used for agricultural implements and fuel. It has the capacity to
establish itself on the highly unfavorable south aspect. Banj forests are usually dense on the
north aspects but open on the south aspects. The other trees found in these forests are the
rhododendron and ringal which occurs in clumps rising to about 4 m. to 6 m. and containing
as many as one hundred shoots. Between the altitudes of 2,150m. and 2,450m. tilonj, is the
chief species of the oak forest and between the altitudes of 2,450 m. and 3,550 m. kharsu is
the dominant tree. The main associated trees of the tilonj and kharsu forests are the horse-
chestnut and the syeamore. The tilonj and kharsu, the hardier oaks, resemble the banj and
are used for the same purpose, but they are straighter and less knotted.
33. Coniferous Forests: Between the altitudes of 3,250 m. and 4,000 m. the dominant
species are the conifers. The chief species are the deodar and the ragha (Himalayan silver
fir) which mainly occurs between the heights of 3,250 m. above the sea-level. The blue pine
(chil), the yew (thaner) and the cypress (surain) are also found in this region. The cypress
sometimes attains an enormous size. The wood is hard, tough and durable and too heavy
for floatation by itself. With these forests is found the variegated bush rhododendron with
flowers of all colours, pink, purple, blue and pure white. The birch grows up to heights of
about 4,000m. and its stems give the famous bhurjapatra of Bhoj-patra which in earlier
times, was used as writing material before the invention of paper.
Fauna
34. Animal: The wild animals of the district have greatly declined in number and variety
during the past few decades. Of the animals in the district, the sambur which is the most
widely distributed of all the deer tribe is found up to an altitude of about 3,050 m. above sea-
level. The kakar or barking deer is also met with up to the same height. The musk-deer
(kastura) is found in the upper ranges above an altitude of 2,400 m. above sea level. The
tiger found here is different from that found in the plains, being stouter in build and with
longer and more furry hair and shorter and thicker tail. The bagh, baghera or panther is
common throughout the district. It lives upon cattle, goats and sheep and is bold and
bloodthirsty beast. The snow leopard is rare in the tract south of the snowy range. The
Himalayan black bear is common throughout the district and is generally seen during the
rains. The jackal is found up to a height of 2,150 m. and the wild pig up to that of 3,050 m.
Monkeys and langurs are found throughout the district.
35. Birds: The district is very rich in birds. Birds of prey like eagles hawks, falcons and
vultures, are very common. Among game-birds the lungi pheasant is found at an altitude of
about 3,700 m. and the monal pheasant at elevations between 2,400 m. and 3,700 m. The
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
19
kokla or pokra is seen between heights of 1,800 m. and 3,700 and the chir pheasant is found
between altitudes of 1,500 m. and 2,400 m. above sea-level. The kalij a common pheasant,
and black partridge frequent the thick forests up to a height of about 2,400 m. The chakor is
a very common bird among partridges. The snow partridges are rare. The Himalayan snow
cock is found on or near the snowline. Among pigeons, the wood-pigeons are also seen in
the higher ranges. Duck and teal occasionally rest on the rivers.
Ambient Air Quality
36. Ambient air quality measurements are shown in Table 2. (Details in Annexure 5) The
monitoring was done on 06/11/2013. The values of all parameters are well below the
permissible limits. This is expected in an area with no major sources of air pollution.
Table 4: Ambient Air Quality Parameters measured Unit At Trek Trail At Mostmanu
Temple Allowable Limit*
Respirable Particulate Matter (PM10)
µg/m3 64 56 100
Respirable Particulate Matter (PM2.5)
µg/m3 31 27 60
Sulphur Dioxide (SO2) µg/m3 10 08 80
Nitrogen Dioxide (NO2) µg/m3 14 18 80
Carbon Monoxide (CO) mg/m3 0.14 0.1 For 08 hrs is 02 and for 01 hrs is 04
*Allowable Limit = National Ambient Air Quality Standards as per CPCB Notification New Delhi, 18
Nov,2009, Date of sampling= 06.11.2013 Ambient Noise Levels
37. Ambient noise quality has been monitored during preparation of this report. The data of
noise monitoring are shown in Table 3 (Details in Annexure 5). The day time equivalent
noise levels are well below the permissible limit indicating no major source of noise pollution
in and around the site.
Table 3: Ambient Noise Quality S.No. Location Unit Measured values
(*Leq Values)
Allowable limits
/Specification (CPCB)/Leq
(dB (A)
1. At Trek Trail dB(A) 43.5 55 2. At Mostamannu Temple dB(A) 41.6
*Leq Values = Equivalent Continuous Sound Pressure Level Date of sampling= 06.11.2013
C. Economic Resources
Livestock
38. Livestock is mainly reared for milk production and compost agriculture is the project
area is closely integrated with forests and animal husbandry. The agriculture is
predominantly subsistence based and majority of population is dependent on market fall
grains, pulses, vegetables and milk. Tourism and allied activities are the main occupation
of local community. Due to closeness from the block and district head quarters and being a
tourist destination the project has almost all infrastructure facilities like road, electricity,
education, drinking water, health banks, post office, market, police station etc. within a
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
20
periphery of 5 kms.
Livelihood and Employment
39. The economy of the area is largely agriculture and tourism based with allied
activities like horticulture, and animal husbandry. Non-Agricultural economic activities
includes skilled and unskilled labour in construction works, Government service, private
jobs, shop-keeping, tailoring, transport service etc. and tourism related activities like selling
of wild edibles, fruits etc. The average monthly income of each household is INR 4,000 per
month. There is huge potential of tourism development in the area which will provide more
employment to the local youth and improve the livelihoods security of local community.
40. The number of females per thousand males is 888. The women face the challenge of
doing maximum households chores and most of the agricultural tasks. The time use
analysis shows that on average women spend 17, 15 and 14 hours per day in various
households and agricultural works during summers, winters and rainy season respectively.
D. Social and Cultural Resources
Demography
41. The subproject area lies in Bin block of Pithoragarh District. There are 15 revenue
villages situated in the surroundings of trek trail within a periphery of 8 kms. The
population of these villages is about 3249 with 659 households, mainly Brahmins, Rajputs
and scheduled castes. The people of these villages are dependent on religious tourism
based activities for their livelihoods. There is potential of tourism development in the area
which will provide more employment to the local youth and improve the livelihoods security
of local community. As per information received from the community, there is gender
disparity among boy and girl child. Also there is lack of entrepreneur skills among the
youths. Due to favourable climate, there is scope of floriculture, vegetable cultivation and
dairy in the area. Important baseline data related parameters are summarized in the
following table (as received from Himalayan Seva Samiti, a local NGO which conducted
this survey in 2012)
Table 4: Demographic profile of Project Area S.N. Name of
Village
Distance
from
Chandak
(Km)
Total
House-
holds
Total
Population
Total SC
Population
Tota BPL
Households
Total
literates
Total
Geographical
area (Ha)
1 Cheda 4 90 444 192 43 312 93.8
2 Dharigaon 5 33 172 26 9 119 14.9
3 Chanapandey 6 81 364 197 47 280 201.2
4 Guruda 7 29 130 7 13 91 31.9
5 Naikina 8 44 189 40 32 128 99.3
6 Bhurmuni 7 160 796 134 78 595 215.1
7 Nakot 5 37 179 68 23 119 27.0
8 Majhera 4 33 166 19 11 124 59.7
9 Kante 3 13 56 0 4 38 17.8
10 Ratwali 3 39 179 0 5 148 28.4
11 Dharapani 1 9 51 0 1 38 35.1
12 Halpati 2 14 71 0 3 51 99.9
13 Bakarkatia 2 18 105 0 4 80 106.5
14 Gauriagaon 2 13 72 0 3 54 24.5
15 Dhungabhool 3 46 275 125 21 193 13.4
Total 15 villages 659 3249 808 297 2370 1055.1
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
21
Basic Amenities and Infrastructure
42. Due to closeness from the block and district headquarters, the project has almost all
basic infrastructure facilities but their management is poor. All the villages are accessible
by motorable roads, electricity and telephone/mobile-phone. The primary and secondary
education facility are available in the project area, but the nearest primary health facilities
are available at Pithoragarh (8 kms). Bank and postal services are also available in the
project area. Pithoragarh is the main market of the project area. The details of basic
amenities and infrastructure available in the project area is given in the Table 5
Table 5: List of Basic Amenities in the project area S. No. Basic amenities and Infrastructure Location & Distance (km)
1 Primary Health Centre Pithoragarh (8 kms) 2 Intermediate School Pithoragarh (8 kms) 3 Post Graduate College Pithoragarh (8 kms) 4 Post Office Pithoragarh (8 kms) 5 Bank Chandak (1 kms), Pithoragarh (8 kms) 6 Veterinary Hospital Pithoragarh (8 kms) 7 Petrol Pump Pithoragarh (8 kms) 8 Main Market Pithoragarh (8 kms) 9 Mandi/market for selling of produce Pithoragarh (8 kms) 10 Police Station Pithoragarh (8 kms)
SWOT Analysis
43. The SWOT analysis of Pithoragarh region as a tourist destination was done with the
objective of assessing its tourism potential and possibilities for sustainable tourism
development in the next decade. The study of SWOT analysis shows that the important
and accepted livelihood option is tourism based. The strengths, weakness, opportunities
and threats of which are summarized below.
Strengths:
Availability of Pithoragarh and Munsiyari tourist
destination which attracts millions of tourists
every year
Climate and geographical conditions are
soothing and abundance of natural
endowments
Himalayan view, rich cultural heritage and bio
diversity of the region
Availability of KMVN as a government enterprise
to promote tourism in Kumaon region
Opportunities:
The Government of India has given special
attention to eastern Uttarakhand tourism circuit.
ADB has supported the state for tourism
development in this region of Uttarakhand.
There is potential for private sector investment in
tourism projects
Besides Intra regional tours there are
opportunities for promoting cross border towns
to neighboring countries like Nepal
Weaknesses:
Underutilized infrastructural facilities of the
government owned TRH's
Lack of effective marketing of tourism based
products
Poor industrial capacity and lack of proper
training.
Underutilized network and synergy among
public and private organization of the region
Threats:
Competition from other tourism destinations
like Kausani, Chaukori etc
Threats from uncontrolled urbanization and
tourism development
Environmental concerns like pollution,
overcrowding, landslides etc
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
22
IV. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
44. The assessment for environmental impacts due to the implementation of this project
has been carried out for potential impacts during the following stages of the project
planning and implementation:
Location impacts: Impacts associated with site selection, including
impacts on environment and resettlement or livelihood related impacts on
communities and wildlife
Design impacts: Impacts arising from project design, including the technology
used, scale of operations, discharge standards etc
Construction impacts: Impacts resulting from construction activities including
site clearance, earthworks, civil works, etc.
O&M impacts: Impacts associated with the operation and maintenance of the
infrastructure built in the project.
Location Impact:
A. Land Acquisition and Resettlement
45. The location considered for the subproject is within the area designated for eco- tourism
as part of developing Uttarakhand‘s conservation, heritage, natural and cultural attractions,
and are outside areas demarcated for habitat protection and conservation. The proposed
sub-project envisages "Revival and Development of Trekking Trail and Vantage Points at
Pithoragarh to Chandak". The subproject site is an existing trail widely used by the local
people, nature lovers, bird watchers, etc. No additional land is to be acquired. The
proposed Trail alignment falls under the ownership of Nagar palika parishad, Pithoragarh
except for a section of 300m which falls under the forest Department. One of the proposed
view point falls under the ownership of Van panchayat. NOCs of respective stakeholders
have been obtained. No private land is to be acquired for the subproject. Thus, resettlement
and rehabilitation is not required for the subproject.
B. Environmental Impacts
Design Impacts and Pre-Construction Impacts
46. Impacts arising from the inappropriate designs of proposed facilities would in general
include the contemporary designs for the traditional and cultural environment, etc.
Selection of materials, if not carefully chosen, will adversely impact the aesthetic appeal of
the surroundings. The results of interventions are unobtrusive and will be integral part of the
overall ambience so as to avoid impacts on the aesthetics of the site. Structural designs to
be worked out in such a manner that over ground structures do not affect the
aesthetics of the area. All component designs will be worked out to minimize any impacts
on the adjoining properties, and considering the drainage and sewerage conditions. Given
that the there is a need for disposal of construction wastes, the contractors will be
required to consult with the Project Implementation Unit (PIU) and Uttarakhand
Environment Protection and Pollution Board (UEPPB) for safe disposal sites.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
23
47. No additional land is required for the sub-project. The entire "Revival and Development
of Trekking Trail and Vantage Points at Pithoragarh to Chandak" will be carried out within
the available government land. Telephone lines, electric poles and wires, water and sewer
lines will not be affected. The storm water runoff from alterations of the site‘s natural
drainage patterns due to landscaping, excavation works in the chandak trail area and
landscaping near the surroundings will be taken care in the designs. Selection of materials
and construction technologies shall be carefully chosen, so that it does not adversely impact
the aesthetic appeal.
Construction Impacts
48. All construction activities to be undertaken at the site will be approved by PIU
and before start of any such activity in the vicinity of the site so that the history and sanctity
as well as the usability of the site by the projected number of tourists are not hampered.
The construction stage impacts due to the proposed project components are generic to the
construction activities. The EMP emphasizes on the construction impacts and necessary
mitigation measures to be strictly followed by the contractor and supervised by the DSC and
PIU. The key impacts are covered in the following paragraphs.
49. Majority of the significant impacts will occur during the construction phase and are
generic to the construction activities. Key impacts during construction phase are envisaged
on the following aspects: (i) drainage, (ii) quarry/borrow pit operations, (iii) dust generation, air
and noise pollution from construction activities, (iv) handling of construction materials at site,
(v) disposal of construction waste materials, and (vi) adoption of safety measures during
construction.
50. Impacts due to stock piles of waste and top soil: Improper stockpiling of construction materials and top soil can obstruct drainage, disturb local people, tourists, etc. Due consideration will be given for material storage and construction sites such that it doesn‘t cause any hindrance to public movement within the site. Stockpiles will be covered to protect from dust and erosion. 51. Disposal of construction waste: Safe disposal of the construction wastes, extraneous material will be ensured in the pre-identified disposal locations. In no case, any construction waste will be disposed around the project site indiscriminately. Maximum utilization will be done for construction of retaining walls, embankments and as filling material. Remaining material if any will be disposed off safely at the disposal sites approved by the DSC Engineer and PIU.
52. Debris/solid waste will be generated due to, excavated earth material and waste generated from construction camps if any. Debris/excavated earth material will be reused subject to the approval of the Engineer during the construction. Waste generated from the construction activities will be disposed off as per law to the satisfaction of the Engineer.
53. Quarry/Borrow pits operations: The construction material required shall be procured
for market areas. If some stone/rock material is required, then the same shall be taken from
existing quarries. No new quarry is proposed to be opened for the project, which will be
procured from market. No quarrying/borrow pit operation are required. Hence there are no
impacts in this subject.
54. Ground water will not be used for construction purposes and the problem of ground
water contamination is not anticipated during the construction phase as there will be proper
disposal of the sludge.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
24
55. Generation of dust is anticipated during transportation, excavation and construction
activities. Certain volumes of dust and gaseous emissions will also be generated during the
construction period from construction machineries like mixers, vehicles engaged in
transportation of construction materials. Pollutants of primary concern at this stage include
Respirable and Suspended Particulate Matter (SPM) and gaseous emissions (NOX, SO2,
CO, etc). However, transportation of construction materials will be confined to adequate trips
per day depending upon extent of construction activity. Therefore, impact at this stage will be
temporary and restricted to the close vicinity of the construction activities only.
56. All vehicles and construction equipment operating for the contractor and the
consultant will obtain and maintain “Pollution under Control” (PUC) Certificates. To control dust emissions, vehicles deployed for borrow material, sand and aggregate haulage, shall be
covered with tarpaulins to be spillage proof. Regular sprinkling of water during excavations,
loading, unloading, vehicular movement and raw material transport, provisions shall be made
during the construction period.
57. Periodic air quality monitoring to ensure emissions comply with standards will be
conducted. The Contractor will submit annual emission monitoring results required by the
SPCB as part of the annual consent to operate (CTO) renewal.
58. During construction phase, some noise will be generated from the various
construction activities like equipment and vehicles engaged in transportation of construction
materials. However, transportation of construction materials will be confined to the
requirement per day, depending upon extent of construction activity. Further the noise
associated with the equipments shall be reduced with the application of the lubricant. The
increase in noise levels is expected to be between 5 - 10 %. However, these noise levels will
be confined to the work sites only and will be temporary in nature and also short duration as
well.
59. The construction activity will be carried out away from environmentally sensitive area.
Therefore, no adverse impact on fauna and flora is anticipated due to the proposed activity.
60. The clean-up and restoration operations are to be implemented by the contractor prior
to demobilization. The contractor will clear all temporary structures and dispose of all
garbage. All construction zones used/affected by the sub-project will be left clean and tidy, at
the contractor’s expense as per the satisfaction the Engineer.
61. The Contractor is likely to engage local labour for various construction activities.
However, in case of engaging migratory labour for the purpose, the contractor has to
establish properly designed labour camp with all basic amenities such as potable drinking
water supply and sanitation facilities. EMP envisages mitigation measures for likely adverse
impacts associated with the labour camps.
62. The implementation of the sub project will not involve dislocation or involuntary
resettlement of people. Positive impact is anticipated in terms of employment opportunity as
many skilled, semi-skilled and un-skilled personnel will get direct and indirect employment
during construction phase.
63. Most of the predicted impacts are associated with the construction process, and are
produced because that process is invasive, involving ground disturbance. However the
routine nature of the impacts means that most can be easily mitigated. The project is
relatively small in scale and involves straightforward construction and low-maintenance
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
25
operation, so it is unlikely that there will be major impacts.
64. Impacts on drainage pattern: Proper care has been taken for location of construction
sites. Hence, no impact is expected on drainage pattern in the area.
65. Impacts due to sewage disposal: About 20-30 labor and technical staff are likely to be
involved in the project construction activities. The labor will be locally available. Hence no
labor colony will be established. Community toilets will be constructed near construction
sites. The sewage generated by labour population during their working hours at construction
site will be treated in a septic tank, prior to disposal.
66. Disturbance to traffic during construction phase: At the time of construction there will be
disturbance and inconvenience for the movement of the public and vehicles due to project
construction activities, particularly during transportation of construction materials. These
impacts will be temporary in nature and last for a very short period.
67. Impacts on cultural properties: The proposed project shall not affect any sites of
religious, historical and/or cultural significance.
68. Impacts on utilities: The entire construction work will be done within the existing trail
alignment. Hence no adverse impact is envisaged.
Operation and Maintenance Impacts
69. The most significant beneficial impact on the environment is through improvement of
infrastructure at Trekking Trail. The project initiatives will provide a pleasant experience to
the local community using the trek for walking (morning walks, commuting to school, picnics)
and encourage tourist populations to these destinations. Plantation plan will prevent soil
erosion together with enhancing the aesthetics. The project will also build the capacity of
primary and secondary stakeholders by training on environmental and livelihood aspect.
Environmental Mitigation Measures
70. The specific measures stated in the EMP will address all adverse environmental impacts
due to the subproject. A detailed monitoring plan prepared as part of this IEE will
ensure negative environmental impacts during implementation are mitigated. During the
detailed design stage, the IEE/EMP will be further updated and stand-alone EMPs for each
of the procurement packages will be prepared. These EMPs will be appended to the
respective contract documents to enable integration of environmental provisions in the
contract. Based on the environmental baseline conditions, planned project activities and
impacts assessed earlier, the set of measures to be adopted to ameliorate the adverse
impacts are listed in following paragraphs.
71. Measures to Mitigate Location Impacts
In accordance with the provisions in the subproject selection criteria, the subproject
design will include adequate provisions for ensuring effective maintenance and
protection of the assets created so as to ensure the long term sustainability of the
sites.
Designs will be worked out and implemented in accordance with the provisions.
Further, the design guidelines for the project components will strictly conform to
Uttarakhand architecture.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
26
72. Measures to Mitigate Design Impacts
Design of proposed components will enable efficient drainage at the project site and
maintain natural drainage patterns.
Designs will be worked out in such a manner that exposed steel and concrete
structures are avoided. The obsolete and inappropriate additions will be removed. The
design brief for all components proposed will strictly conform to the Uttarakhand
architecture. landscaping elements will only utilize native species to protect local
biodiversity
73. Measures to Mitigate Impacts due to Pre-construction Activities
Prior to commencement of site activities and mobilization on ground, the Contractor
will prepare and get approved by the PIU and DSC, circulation plan during
construction for safe passage of public, tourists during construction stage, including
development of alternative access routes, traffic regulations, signage, etc. during
construction.
The commencement of site clearance activities will be undertaken with due
permission from the Environment Specialist of the DSC consultant to minimize
environmental impacts.
All areas used for temporary construction operations will be subject to complete
restoration to their former condition with appropriate rehabilitation procedures.
Location of disposal sites will be finalized by the Environmental Specialist of the DSC
so that disposal of the material does not impact natural drainage courses or surface
water bodies or low lying areas and that no endangered / rare flora is impacted by
such materials
74. Measures to Mitigate Construction Impacts
Due consideration will be given for material storage and construction sites such that
it doesn‘t cause any hindrance to public, tourist movement within the site.
Stockpiles will be covered to protect from dust and erosion.
The topsoil from borrow areas, areas of cutting and areas will be stripped to a
specified depth of 150mm, translocated and stored in stockpiles.
The stockpile will be designed such that the slope does not exceed 1:2 (vertical to
horizontal).
Stockpiles will not be surcharged or otherwise loaded and multiple handling will be
kept to a minimum to ensure that no compaction will occur. The stockpiles will be
covered with gunny bags or tarpaulin.
Slope protection measures will be undertaken along slopes of the parking area. The
work will consist of measures as per design, or as directed by the Engineer to control
soil erosion, sedimentation and water pollution.
The contractor will take every precaution to reduce the levels of dust at construction
sites to the satisfaction of the Engineer. All earthworks to be protected/covered in a
manner acceptable to the satisfaction of the engineer to minimize dust generation.
Clearance will be affected immediately by manual sweeping and removal of debris,
or if so directed by the Engineer.
The discharge standards promulgated under the Environmental Protection Act, will
be strictly adhered to. All vehicles, equipment and machinery used for construction
will conform to the relevant Standard.
All vehicles, equipment and machinery used for construction will be regularly
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
27
maintained to ensure that pollution emission levels comply with the relevant
requirements.
Noise level for construction equipment used in this project (measured at one meter
from the edge of the equipment in free field) such as compactors, rollers, front
loaders, concrete mixers, cranes (moveable), vibrators and saws will not exceed 75
dB (A). Notwithstanding any other conditions of contract, noise level from any item
of plant(s) will comply with the relevant legislation for levels of noise emission.
All workers employed on cement, lime mortars, concrete etc., will be provided with
protective footwear and protective goggles.
Cut material generated because of cutting of hill slopes will be utilized for
construction of retaining walls, embankments and as filling material. Remaining
material if any will be disposed off safely at the disposal sites.
All reasonable precaution will be taken to prevent danger of the workers and the
public from fire etc.
All necessary steps will be taken for prompt first aid treatment of all injuries likely to
be sustained during the course of work.
Contractor to prepare site restoration plans for approval by the Engineer. The plan is
to be implemented by the contractor prior to demobilization.
On completion of the works, all temporary structures will be cleared away, all rubbish
burnt, excreta or other disposal pits or trenches filled in and effectively sealed off and
the site left clean and tidy, at the Contractor‘s expense, to the entire satisfaction of
the Engineer.
75. Measures to Mitigate O&M Impacts
In line with the Government targets of coverage of all urban and rural areas with
environmentally safe solid waste management systems, tourist destinations will be
covered with integrated waste management facilities, including treatment and
disposal, in line with the Solid Waste Handling Rules, 2000.
76. Responsibilities of Contractors
Abide by the environmental laws formulated by the community institution.
Regularly remove trash from the site on daily basis.
Cutting and collection of fuel wood by the construction workers from the nearby forest
should be strictly prohibited
It will be ensured by the contractor that the topsoil will not be unnecessarily trafficked
either before stripping or when in stockpiles. Such stockpiled topsoil will be returned
to cover the disturbed area and cut slopes.
Contractor with support of the PIU will carry out dissemination of these information and
circulation plan at key entry points to the respective destinations
Contractor will be responsible for arrangement of water in every workplace at
suitable and easily accessible place for the whole construction period.
Sufficient supply of potable water to be provided and maintained. If the drinking
water is obtained from an intermittent public water supply then, storage tanks will be
provided.
Contractor will ensure that construction activities do not result any contamination of
land, water or air by polluting substances
Contractor will ensure that no trees are felled or harmed except those required to be
cleared for execution of work. The Contractor will protect tree and vegetation from
damage to satisfaction of the engineer.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoagarh to Chandak
28
77. Responsibilities of PIU & DSC
Sponsor seminars and/or distribute educational materials to contractors and visitors
about environmentally beneficial conservation procedures
Organize workers’ training program for the contractors for environmental management
during construction works
Educate the contractors regarding the eco-sensitivity of the area and explain how to
protect bio-diversity during construction works
Regular site visit and reporting during construction works to check whether objectives of
EMP being followed.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
29
78. The summary of Environmental Impacts and Mitigation Measures to be followed in this project are given in Table 6.
Table-6: Summary of Environmental Impacts and Mitigation Measures
Field Duration/
Extent
Magnitude Mitigation Measures Responsibility
1. Location Impacts
1.1 Lack of sufficient planning to
assure long term sustainability of
the improvements and ensure
protection of the assets created
and the architectural character of
the surroundings.
Permanent Major In accordance with the provisions in the subproject selection
criteria, the subproject design will include adequate provisions for
ensuring effective maintenance and protection of the assets
created so as to ensure the long term sustainability of the sites.
The designs are be worked out and implemented in accordance
with the provisions. Further, the design guidelines for the project
components will strictly conform to Uttarakhand architecture.
PIU/DSC
2. Design Impacts
2.1 Increased storm water runoff from
alterations of the site‘s natural
drainage patterns due to
additional structures and
landscaping works in the area.
Permanent Minor Design of proposed components will enable efficient drainage of
the sites and maintain natural drainage patterns.
PIU/DSC
2.2 Selection of materials and
construction technologies, if not
carefully chosen, will adversely
impact the aesthetic appeal of the
destinations
Permanent Moderate The design brief for all components proposed will strictly conform
to the Uttarakhand architecture. Any new landscaping elements
will only utilize native species to protect local biodiversity
PIU/DSC
2.3 Integration of energy efficiency
and energy conservation
programs in design of subproject
components
Permanent Minor The detailed designs for the subproject components will ensure
energy efficiency
PIU/DSC
2.4 Slope stability related issues
Permanent
Major Along areas vulnerable to slope failures and along steep stretches, the designs of subproject components will include slope protection measures for uncovered slopes as pitching, vegetation, benching, paving etc.
PIU/DSC
2.5 In areas of shallow water table, Permanent Moderate At locations with shallow water table, the design of the septic tanks PIU/DSC
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
30
Field Duration/
Extent
Magnitude Mitigation Measures Responsibility
ensure that the septic tanks developed, do not impact the ground water quality
shall be done to ensure that there is a difference of at least 1.5m between the bottom bed of the septic tank and the maximum ground water level, to avoid any contamination of ground water
3. Pre-construction Activities
3.1 Circulation plan during
construction in the tourist
destinations
Temporary Moderate Prior to commencement of site activities and mobilization on
ground, the Contractor will prepare and get approved by the
Engineer, circulation plan during construction for safe passage of
public, tourists during construction stage, including development of
alternative access routes, traffic regulations, signages, etc., during
construction. The Contractor with support of the PIU will carry out
dissemination of these information and circulation plan at key entry
points to the respective destinations.
Contractor/
DSC/PIU
3.2 Site clearance activities, including
delineation of construction areas
Temporary Moderate The commencement of site clearance activities will be undertaken with due permission from the Environment Specialist of the DSC consultant to minimize environmental impacts. Vegetation (mainly shrub) shall be removed from construction site before commencement of construction. All works shall be carried out such that the damage or disruption of flora other than those identified for cutting is the minimum. Only ground cover/shrubs that impinge directly on the permanent works or necessary temporary works shall be removed with prior approval from the Environmental Expert of DSC
All areas used for temporary construction operations will be
subject to complete restoration to their former condition with
appropriate rehabilitation procedures like closure of camp,
removal of construction/ demolition waste, complete cleaning of
the area, re-plantation in case of tree felling etc.
Contractor/
DSC
3.3 Drinking water availability and
water arrangement
Temporary Major The contractor will be responsible for arrangement of water in
every workplace at suitable and easily accessible place for the
whole construction period. Sufficient supply of potable water to be
provided and maintained. If drinking water is obtained from an
intermittent public water supply then, storage tanks will be
provided.
Contractor/
DSC
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
31
Field Duration/
Extent
Magnitude Mitigation Measures Responsibility
3.4 Identification of sites for disposal
of construction and demolition
work
Permanent Major Location of disposal sites will be finalized by the Environmental
Specialist of the DSC so that disposal of the material does not
impact natural drainage courses or surface water bodies or low
lying areas and that no endangered / rare flora is affected by
disposal of construction and demolition waste
Contractor/
DSC
4. Construction Impacts
4.1 Improper stockpiling of
construction materials cause
impacts starting from obstruction
of drainage, disturbance/ safety
hazard to tourists, etc.
Temporary Minor Due consideration will be given for material storage and
construction sites such that it doesn‘t cause any hindrance to
movement within the site. Stockpiles will be covered to protect from
dust and erosion.
Contractor/
DSC
4.2 Stripping, stocking and
preservation of top soil
Permanent Minor The topsoil from borrow areas, areas of cutting and areas will be
stripped to a specified depth of 150mm, translocated and stored in
stockpiles. The stockpile will be designed such that the slope does
not exceed 1:2 (vertical to horizontal). Stockpiles will not be
surcharged or otherwise loaded and multiple handling will be kept
to a minimum to ensure that no compaction will occur. The
stockpiles will be covered with gunny bags or tarpaulin. It will be
ensured by the contractor that the topsoil will not be unnecessarily
trafficked either before stripping or when in stockpiles. Such
stockpiled topsoil will be returned to cover the disturbed area and
cut slopes.
Contractor/
DSC
4.3 Soil Erosion Temporary Moderate Slope protection measures will be undertaken along slopes of the
parking area and other sites vulnerable to soil erosion. The work
will consist of measures as per design, or as directed by the
Engineer to control soil erosion, sedimentation and water pollution.
Contractor/
DSC
4.4 Soil and Water Pollution due to
fuel and lubricants, construction
waste
Temporary Minor The fuel storage will be stationed such that fuel discharge does not
drain into the water body. Soil and water pollution parameters will
be monitored as per monitoring plan.
Contractor/
DSC
4.5 Siltation of water bodies due to
spillage of construction and
demolition wastes
Temporary Minor Haul roads on the site and approaches to the watercourse (or
drains leading to watercourses) will be regularly cleaned to prevent
the buildup of mud; areas of bare soil will be kept to a practical
Contractor/
DSC
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
32
Field Duration/
Extent
Magnitude Mitigation Measures Responsibility
minimum to reduce silt runoff. No disposal of construction wastes
will be carried out into any water body. Extraneous construction
wastes will be transported to the pre-identified disposal site for safe
disposal.
4.6 Generation of Dust Temporary Moderate The contractor will take every precaution to reduce the levels of
dust at construction sites to the satisfaction of the Engineer. All
earthworks to be protected/covered in a manner acceptable to the
satisfaction of the engineer to minimize dust generation. Clearance
will be affected immediately by manual sweeping and removal of
debris, or if so directed by the Engineer, the road surfaces will be
hosed or watered using necessary equipment.
Contractor/
DSC
4.7 Emission from construction
vehicles, equipment and
machinery
Temporary Minor The discharge standards promulgated under the Environmental
Protection Act will be strictly adhered to. All vehicles, equipment
and machinery used for construction will conform to the relevant
Standard.
All vehicles, equipments and machinery used for construction will
be regularly maintained to ensure that pollution emission levels
comply with the relevant requirements.
Contractor/
DSC
4.8 Noise from construction equipment Temporary Minor Maintenance of vehicles, equipment and machinery will be regular
and to the satisfaction of the Engineer, to keep noise from these at
a minimum.
All vehicles and equipment used for construction will be fitted with
exhaust silencers. During routine servicing operations, the
effectiveness of exhaust silencers will be checked and if found to
be defective will be replaced.
Noise limits for construction equipment used in this project
(measured at one meter from the edge of the equipment in free
field) such as compactors, rollers, front loaders, concrete mixers,
cranes (moveable), vibrators and saws will not exceed 75 dB (A).
Notwithstanding any other conditions of contract, noise level from
any item of plant(s) will comply with the relevant legislation for
levels of noise emission.
Contractor/
DSC
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
33
Field Duration/
Extent
Magnitude Mitigation Measures Responsibility
4.9 Material Handling at Site Temporary Minor All workers employed on mixing asphaltic material, cement, lime
mortars, concrete etc., will be provided with protective footwear
and protective goggles.
Workers, who are engaged in welding works, will be provided with
welder‘s protective eye-shields. Workers engaged in stone
breaking activities will be provided with protective goggles and
clothing
Contractor/
DSC
4.10 Disposal of Construction Waste/
Debris / Cut Material
Temporary Minor The Contractor shall confirm that safe disposal of the construction
wastes will be ensured in pre identified location. In no case, any
construction waste will be disposed around the project site
indiscriminately.
Cut material generated because of cutting of hill slopes will be
utilized for construction of retaining walls, embankments and as
filling material. Remaining material if any will be disposed off safely
at the disposal sites.
Contractor/
DSC
4.11 Safety Measures During
Construction
Temporary Moderate Personal Protective Equipment for workers on the project and
adequate safety measures for workers during handling of materials
at site will be taken up. The contractor has to comply with all
regulations regarding safe scaffolding, ladders, working platforms,
gangway, stairwells, excavations, trenches and safe means of
entry and egress.
Contractor/
DSC
4.12 Risk caused by Force Majeure Temporary Minor All reasonable precautions will be taken to prevent danger of the
workers and the public from fire etc. All necessary steps will be
taken for prompt first aid treatment of all injuries likely to be
sustained during the course of work.
Contractor/
DSC
4.13 Malaria Risk Temporary Minor The Contractor will, at his own expense, conform to all anti-malaria
instructions given to him by the Engineer.
Contractor/
DSC
5. O&M Impacts
5.1 Environmental Conditions Temporary Moderate The tourism department will undertake seasonal monitoring of air,
water, and noise and soil quality through an approved monitoring
agency. The parameters to be monitored, frequency and duration
of monitoring as well as the locations to be monitored will be as per
Tourism
department
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
34
Field Duration/
Extent
Magnitude Mitigation Measures Responsibility
the Monitoring Plan prepared.
5.2 Adequate drainage of site area Permanent Minor The tourism department to ensure efficient flow of surface water
and prevent water logging along the side of the roads and parking
lots.
Tourism
department
5.3 Increased waste loads onto the
existing waste disposal facilities
(that are non-conformant to the
Government requirements for
SWM)
Temporary Minor In line with the Government targets of coverage of all urban and
rural areas with environmentally safe solid waste management
systems, the tourist destinations will be covered with integrated
waste management facilities, including treatment and disposal, in
line with the Solid Waste Handling Rules, 2000.
Gram
Panchayats
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
35
V. ENVIRONMENTAL MANAGEMENT PLAN (EMP)
A. Institutional Arrangements
79. The institutional arrangements specify the arrangements for the implementation of
environmental provisions of the entire project, and include the proposed subproject also.
Project Management Unit (PMU) and Project Implementation Unit (PIU)
80. The Department of Tourism, Government of Uttarakhand is the Executing Agency (EA).
Project Management Unit (PMU) is established in Dehradun for the overall project management
and Project Implementation Units (PIU) are established for each of the three circuits. The
proposed sub-project will be implemented by the PIU, Bhimtal. A Safeguards Specialist in the
PMU is responsible for implementation of the resettlement and environmental safeguard
provisions. A Forest Conservation Specialist in PMU also takes care of matters related to forest
area in all the projects.
Project Management Consultant (PMC) and Design and Supervision Consultants
(DSC)
81. Project Management Consultants (PMC) and Design and Supervision Consultants
(DSC) are recruited to provide assistance to the PMU and PIUs respectively in project
implementation. Within the PMC team an Environment Safeguards Specialist will provide overall
direction for management of environmental issues, and will provide technical support to the
PMU including implementation of the environmental requirements according to ADB
requirements, and assist in monitoring impacts and mitigation measures associated with sub-
projects. The Safeguards Specialist of the DSC team will be responsible for preparation of the
Environmental Assessment documents in line with the EARF and supervise the implementation
of the EMP provisions in the various sub-projects. The PMU, will oversee the implementation of
the environmental provisions related to subproject implementation, its responsibilities include
preparation and updating of IEEs consistent with the ADBs Environmental Assessment
Guidelines and the environmental compliance requirements of the Government of Uttarakhand
and the Government of India.
82. The DSC Safeguards Specialist supports environmental management functions
including updating sub-project IEEs in respect to environmental management plans, assisting in
preparing IEEs, and assist in monitoring impacts and mitigation measures associated with sub-
projects. He/she is required to include mitigation measures in designs where appropriate, and to
specify other measures in construction contracts. Contractors will be required by their contracts
to implement all specified mitigation, monitoring, and reporting assigned to contractors as
presented in sub-project IEE. Environmental monitoring will be undertaken by the PMU
supported by the DSC- Safeguards Specialist.
83. Towards addressing the environmental issues in the project components during design
and implementation, the DSC will include provisions for inputs of an Environmental Specialist. In
addition to addressing the issues related to environmental management in the project, the
Environmental Specialist will play a central role in ensuring capability building on Environmental
Management of the PMU/PIU, Contractor and Line Departments.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
36
Committee
84. A sub project Monitoring Committee has been constituted to monitor, supervise and
facilitate the execution of works in the sub project under the Chairmanship of Distt. Magistrate,
& including the representatives of project stakeholders including Tourism department,
Mostamanu temple Committee, Nagar Palika Parishad, Pithoragarh etc. concerned villages to
ensure successful project implementation and sustainability of project pertaining to Mostamanu
site development and trek-trail development. PTC will comprise members from SHGs, NGOs,
public representatives from project area villages and representatives from
B. Environmental Management Plan 85. All works undertaken towards protection of environmental resources as part of the EMP
and as part of good engineering practices while adhering to relevant specifications will be
deemed to be incidental to works being carried out and no separate payment will be made
unless otherwise specified explicitly. The costs towards environmental management as per
EMP unless otherwise provided as a separate head, will be deemed to be part of the BoQ of the
project. The scope of works of the contractor towards the implementation of the environmental
provisions shall be as follows:
Abide by all existing Environmental regulations and requirements of the Government
of Uttarakhand and Government of India, during implementation,
Compliance with all mitigation measures and monitoring requirements set out in
the environmental Management Plan (EMP)
Submission of a method statement detailing how the subproject EMP will be
complied with as per the schedule of monitoring given in subsequent paragraphs.
Monitoring of project environmental performance and periodic submission of
monitoring reports.
Compliance with all measures required for construction activities in line with the
regulatory requirements and the guidelines set forth in the management plans for
these areas.
Compliance of all safety rules and regulations applicable at work, and provision
of adequate health and safety measures such as water, food, sanitation,
personal protective equipment, workers insurance, and medical facilities.
86. The detailed provisions for specific environmental issues shall be as outlined in the
Table 6. Key clauses are outlined in the following sections.
Debris Disposal
The contractor will, prior to start of construction operations, identify potential sites
for disposal of construction debris, sites for general construction wastes. The
contractor will obtain approval on identified sites from the Engineer of PIU and
Supervision Consultant and disposal will be only after consent letter from the
Engineer.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
37
Precautions for protection of Environmental Measures
The Contractor shall ensure that construction activities do not result in
any contamination of land or water by polluting substances.
Unless otherwise provided in the specifications, the Contractor shall ensure that no
trees or shrubs or other vegetation are felled or harmed except those required to be
cleared for execution of the works. The Contractor shall protect trees and
vegetation from damage to the satisfaction of the Engineer.
In the conduct of cleaning activities and operation of equipment, the
Contractor will utilize such practicable methods and devices as are reasonably
available to control, prevent and otherwise minimize air/noise pollution.
Noise and Air Pollution
All works will be carried out without unreasonable noise and air pollution. Subject and
without prejudice to any other provision of the Contract and the law of the land and its
obligation as applicable, the Contractor will take all precautions outlined in the EMP to
avoid the air and noise pollution.
The Contractor shall monitor the environmental parameters periodically as specified in
the monitoring plan and report to the Engineer. The Contractor shall reduce the dust
emission due to construction activities by regular water sprinkling in the affected areas.
All the construction equipments and vehicles shall have Pollution Under Control (PUC)
Certificate to ensure that no air pollution may be caused due to operation of their
equipments and vehicles. All the construction equipment and vehicles should remain all
time in good conditions up to satisfaction of site engineers.
The Contractor shall indemnify and keep indemnified the Employer from and against
any liability for damages on account of noise or other disturbance created while carrying
out the work, and from and against all claims, demands, proceedings, damages, costs,
charges, and expenses, whatsoever, in regard or in relation to such liability.
Occupational Health and Safety During Construction
The Contractor shall, in accordance with the safety and health provisions specified
in the EMP, provide workers with a safe and healthy working environment, in the
work areas, through application of preventive and protective measures consistent
with international good practice, as reflected in internationally recognized standards
such as the ADB’s Environment, Health and Safety Guidelines. The borrower/client
will take steps to prevent accidents, injury, and disease arising from, associated
with, or occurring during the course of work by-
Providing preventive and protective measures, including modification,
substitution, or elimination of hazardous conditions or substances;
Providing appropriate equipment to minimize risks and requiring and
enforcing its use;
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
38
Training workers and providing them with appropriate incentives to use and
comply with health and safety procedures and protective equipment;
Documenting and reporting occupational accidents, diseases, and incidents;
and
Having emergency prevention, preparedness, and response arrangements in
place.
Provide first aid facilities in all the work sites and workers camp and having
qualified first aider to give first aid at the time of any accident.
Contractor shall provide safe drinking water, clean eating and resting.
Contractor shall have prepared emergency response plan with full details
and methods of emergency response during any accident and shall have
and display the emergency Contact numbers at site.
Contractor should follow all the applicable rules and regulations for workers
safety.
Post Construction Clearance
87. On completion of work, wherever applicable, the Contractor shall clear away and remove
from the sites all constructional plant, surplus materials, rubbish, scaffoldings, and temporary
works of every kind and leave the whole of the sites and works in a clean condition to the
satisfaction of the Engineer.
C. Environmental Monitoring Plan
88. Environmental monitoring will be done during construction in three levels; namely
monitoring development of project performance indicators done by the DSC Environmental
Specialist, monitoring implementation of mitigation measures done by the Contractor; and
overall regulatory monitoring of the environmental issues done by the PMU Environmental
Specialist. The Environmental Monitoring Plan for the project is presented in Table-7. The
proposed monitoring of all relevant environmental parameters, with a description of the
sampling stations, frequency of monitoring, applicable standards and responsible agencies are
presented.
Table7: Environmental Monitoring Plan
S.
No.
Attributes Stage Parameters
to be
Monitored
Location Frequency Responsibility
1 Debris
/Construction
materials
disposal
Construction
Stage
Safe disposal of construction wastes including bituminous wastes
Major construction sites
Random checks Contractor
2 Ambient Air
Quality
Construction
Stage
PM10, SO2, NO2,
CO
Major
construction
sites
Once in a season
(except
monsoons) for the
entire construction
period
Contractor, to be
monitor through
engagement of
agency approved
under NABL
Accreditation norm
3 Water quality Construction
stage
TDS, TSS, pH,
DO, BOD, COD,
Three
Locations
Twice a year (pre-
monsoon and
Contractor, to be
monitor through
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
39
S.
No.
Attributes Stage Parameters
to be
Monitored
Location Frequency Responsibility
Faecal Coliform,
Ammonia,
Nitrogen,
Organophosphat
es,
post- monsoon)
for the entire
period of
construction
engagement of
agency approved
under NABL
Accreditation norm
4 Noise Levels
Construction
and
Operation
Stage
Equivalent Day
& Night Time
Noise Levels
All
Construction
sites
Once in a season
during
construction and
operation stages
Contractor, to monitor
through on approved
Monitoring Agency
5 Supply of PPE
Construction
Stage
Provision of PPE on site, adequacy of equipment
All
Construction
sites
Continuous Contractor
D. Capacity Building
Institutional Strengthening
89. The Department of Tourism, Government of Uttarakhand is the Executing Agency (EA).
Project Management Unit (PMU) will be established in Dehradun for the overall project
management. This sub-project will be implemented by the PIU, Bhimtal. A Safeguards
Specialist within the PMU is responsible for implementation of the resettlement and
environmental safeguard provisions. Project Management Consultants (PMC) and Design and
Supervision Consultants (DSC) are recruited to provide assistance to the PMU/PIUs in project
implementation. Within the PMC team a Safeguards Specialist provides overall direction for
management of environmental and social issues, and will provide technical support to the PMU
including implementation of the environmental and resettlement requirements according to ADB
requirements, and assist in monitoring impacts and mitigation measures associated with sub-
projects. The Safeguards specialist of the DSC team is responsible to assist in preparation of
IEE and EMP report and supervise the implementation of the EMP provisions in the sub-
projects. The PMU will oversee the implementation of the environmental provisions related to
subproject implementation, consistent with the ADBs Environmental Assessment Guidelines
and the environmental compliance requirements of the Government of Uttarakhand and the
Government of India.
Training and Capacity Building
90. The Environmental Specialist of the PMC and DSC will provide the basic training
required for environmental awareness followed by specific aspects of infrastructure
improvement projects along with environmental implications for projects located within / in the
vicinity of natural and cultural heritage sites. Specific modules customized for the available skill
set will be devised after assessing the capabilities of the members of the Training Programme
and the requirements of the project. The entire training would cover basic principles of
environmental assessment and management; mitigation plans and programmes,
implementation techniques, monitoring methods and tools. The proposed training program
along with the frequency of sessions is presented in Table 8 below.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
40
Table 8: Training Modules for Environmental Management Program
Description
Participants
Form of
Training
Duration/
Location
Training Conducting
Agency
A. Pre-Construction Stage
Sensitization
Workshop
Introduction to Environment: Basic Concept of environment Environmental Regulations and Statutory requirements as per Government of India and ADB
Tourism / Forest / Roads / Culture Department Officials, Project Director (PD) and Environmental Specialist (ES) of the PMU/PIU
Workshop 1 Working Day
Environmental Specialist of the PMC
Session I
Module I Introduction to Environment: Basic Concept of environment Safeguards Regulations and Statutory requirements as per Govt. of India and ADB Guidelines on cultural resources, Environmental considerations in planning, design and implementing projects
PMU/PIU (including the ES) and Engineering staff of the implementing agencies
Lecture 1Working Day
Safeguards Specialist of the PMC
Module II Environmental components impacted in construction and operation stages Activities causing pollution during construction and operation stages Environmental Management Environmental Provisions Implementation Arrangements Methodology of Assessment Good engineering practices to be
integrated into contract
documents
PMU/ PIU (including the ES) and Engineering staff of Tourism dept
Workshop 1 Working Day
Safeguards Specialist of the PMC
Module III Improved Co-ordination with
Other Departments:
Statutory Permissions –
Procedural Requirements
Co-operation & Coordination
with other Departments.
PMU/PIU (including the ES) and Engineering staff of Tourism dept
Lecture / Interactive Sessions
1Working Day
Safeguards Specialist of the PMC
Module IV Environmental considerations
in planning, designing and
implementing heritage
buildings and conservation
projects
PMU/PIU (including the ES) and Engineering staff of Tourism dept
Lecture / Interactive
Sessions
and site
visits
2 Working
days
Safeguards specialist of the PMC with support from the Conservation specialist of the PMC
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
41
Program
Description
Participants
Form of
Training
Duration/
Location
Training Conducting
Agency
Module V Environmental principles of eco-tourism (as per Uttarakhand eco tourism policies) and training and awareness building on Conservation and management aspects of the area.
Local Community
Groups, NGOs
Lecture / Interactive Sessions
1 Working Day
Specialist from DSC and PIU
B. Construction Stage
Session II
Module VI Role during Construction- Roles and Responsibilities of officials / contractors / consultants towards protection of environment Implementation Arrangements Monitoring mechanisms
Engineers and
staff of line
departments of
the Government
of Uttarakhand,
and PMU/PIU
(including the ES)
Lecture / Interactive Sessions
1 Working Day
Safeguards Specialist of the DSC
Module VII Monitoring and Reporting
System
Engineers and
staff of
implementing
agencies and
PMU/PIU
(including the ES)
Lecture / Interactive Sessions
1 Working Day
Safeguards Specialist of the DSC
Session III
Module VIII Skill upgrade on ecotourism and nature guides Hospitality, Interpretational
skills, micro- planning,
Biodiversity etc
Youth in the villages in the periphery, and other NGOs in the district
Site visits,
interactive
sessions
2
working
days
Tourism department
Notes: PMU = Project Management Unit; PIU = Project Implementation Unit; PMC = Project Management
Consultant; DSC = Design and Supervision Consultant; ES = Environment Specialist; NGO= N on-
government organization
E. Environmental Budget
91. As part of good engineering practices in the project, there have been several measures
as erosion prevention, rehabilitation of borrow areas, safety, signage, provision of temporary
drains, plantation plan, etc., the costs for which will be included in the design costs of specific
subprojects. Therefore, these items of costs have not been included in the IEE budget. Only
those items not covered under budgets for construction are considered in the IEE budget.
92. This is a small construction project and there are no major structures to be constructed
therefore it is not expected to cause much significant air, water and noise pollution. The main
EMP cost will arise from monitoring of environmental parameters (air, water and noise).
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
42
93. The costs of personal protective equipments to construction workers shall be borne by
contractor as part of conditions of contract. In addition the sources of funds for Mitigation
measures during construction stage including monitoring during construction stage are also to
be borne by the contractor. These are deemed to be included as part of the contract price
amount quoted by the contractor for the works. The costs of components for monitoring in
operation stage and the capacity building costs are to be funded by the PMU. The EMP cost is
given in the Table 9.
Table 9: Environmental Budget S. No.
Particulars Stage Unit Total number
Rate (INR)
Cost (INR) Source of fund
A. Monitoring Measures During Construction Period 1 Water quality Construction Per
sample 12 samples {Twice a year (pre monsoon and Post Monsoon) at three locations (Surface and bottom)}
8,000 96,000 Contractor
2 Air quality monitoring
Construction Per sample
12 nos. {Once per season at three locations for pre-monsoon and post-monsoon season}
9,000
108,000 Contractor
3 Noise Levels – silence zones
Construction Per Sample
18 samples {Once in a season for 3 seasons at three locations}
2,000 36,000 Contractor
B. Monitoring Measures During Operation Phase
1 Noise Levels – silence zones
Operation Per Sample
6 samples {Once in a season for 3 seasons at three locations}
2,000 12,000 O & M contractor
2 Disposal of Sewage
Operation - 16 samples {Twice a year (pre monsoon and post monsoon) at four locations (Surface and bottom)}
8,000 128,000 O & M contractor
Sub -Total (A+B) 3,80,000 C. Capacity Building (All the workshops and trainings will be held in Pithoragarh)
1 Sensitization Workshop
Pre- Construction
L.S 1,00,000 PMU
2 Training Session I
Pre- Construction
L.S 4,00,000 PMU
3 Training Session II
Construction L.S 2,00,000 DSC
4 Training Session Construction L.S 5,00,000
Sub -Total (C) 12,00,000
Total Rupees Fifteen Lakhs and Eighteen Thousand only (A+B+C) 15,80,000
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
43
F. Environmental Monitoring and Reporting 94. The PMU will monitor and measure the progress of EMP implementation. The monitoring activities will be corresponding with the project’s risks and impacts and will be identified in the EIAs/IEEs for the subprojects. In addition to recording information of the work, deviation of work components from original scope, the PMU and PIU will undertake site inspections and document review to verify compliance with the EMP and progress toward the final outcome. 95. DSC will submit monthly monitoring and implementation reports to PIU, who will take follow-up actions, if necessary. PIU will submit the quarterly monitoring and implementation reports to PMU who will then submit to the PD. The PMU will submit semi-annual monitoring reports to ADB. Project budgets will reflect the costs of monitoring and reporting requirements. For subprojects likely to have significant adverse environmental impacts during operation, reporting will continue at the minimum on an annual basis. Monitoring reports will be posted in a location accessible to the public. 96. For projects likely to have significant adverse environmental impacts, the EA will retain qualified and experienced external experts to verify its monitoring information. The EA will document monitoring results, identify the necessary corrective actions, and reflect them in a corrective action plan. The EA, in each quarter, will study the compliance with the action plan developed in the previous quarter. Compliance with loan covenants will be screened by the EA. 97. ADB will review project performance against the EA’s commitments as agreed in the legal documents. The extent of ADB's monitoring and supervision activities will be commensurate with the Project’s risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system. ADB will monitor projects on an ongoing basis until a project completion report is issued. ADB will carry out the following monitoring actions to supervise project implementation:
o conduct periodic site visits for projects with adverse environmental or social impacts; o conduct supervision missions with detailed review by ADB’s safeguard specialists/
officers or consultants for projects with significant adverse social or environmental impacts;
o review the periodic monitoring reports submitted by EA to ensure that adverse impacts and risks are mitigated as planned and as agreed with ADB;
o work with EA to rectify to the extent possible any failures to comply with their safeguard commitments, as covenanted in the legal agreements, and exercise remedies to re-establish compliance as appropriate; and
o prepare a project completion report that assesses whether the objective and desired outcomes of the safeguard plans have been achieved, taking into account the baseline conditions and the results of monitoring.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
44
VI. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE
A. Process for Consultation followed
98. During Project preparation, consultations have been held with the District
Administration, Nagar Palika, Forest Department, Mostamanu Mandir Committee, public
representatives of project area villages, Hotel Owners, villagers of concerned various
villages in vicinity of sub-project site and tourists on project orientation, issues pertaining
to land acquisition problems and addressing the current gaps in provision of basic
services and improvement of tourist infrastructure. These consultations (Table-10)
provided inputs in identification of the felt needs of the communities, and the relevant
stakeholders. Photographs of consultations are attached as Annexure-6 with this report.
Table 10: Consultations with Stakeholders
S. No.
Place Date Consulted persons/ Community
Issues discussed / Output Received
1. Pithoragarh & Chandak
07-10 April 2013
Local Community
Nagar Palika
Preliminary Site visit for Preparation of Inception Report
Collection of Secondary Information
Introduction to Stakeholders
2. Pithoragarh &
Chandak
11-12 July 2013
Mostamannu Temple Committee
Meeting with Mostamannu Temple Committee Minutes to be provided
Project Orientation to Committee
Project Orientation and Need Assessment
Transect walk around chandak trekking trail
Baseline information collection
3. Pithoragarh &
Chandak
10-12 September 2013
Temple Committee Members
CDO
DM
Nagar Palika
Meeting with Temple Committee Members
NOC from Nagar Palika and Mandir committee received
Trek Trail and Mostamannu Temple Survey
4. Pithoragarh &
Chandak
21-22 September 2013
Temple Committee Members
CDO
DM
Nagar Palika
Sharing of plans and Survey findings
5. Pithoragarh &
Chandak
30-09-2013 & 01-10-2013
Temple Committee Members
CDO
DM
DTO
Subproject Monitoring Committee Meeting Annexure -7
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
45
S. No.
Place Date Consulted persons/ Community
Issues discussed / Output Received
6. Pithoragarh &
Chandak
26-29 October 2013
Temple Committee Members
Forest Department
Nagar Palika
Tehsildar
Collection of Revenue Records
7. Pithoragarh &
Chandak
26-30 December 2013
CDO
DM
Minutes of Meeting enclosed as Annexure - 8
8. Pithoragarh &
Chandak
06-09 January 2014
Temple Committee Members
CDO
DM
Minutes of Meeting enclosed as Annexure - 9
B. Future Consultation and Information Disclosure
99. To ensure continued public participation, provisions to ensure regular and continued
stakeholder participation, at all stages during the project design and implementation is
proposed. A grievance redress cell will be set up within the PIU and PMU to register grievances
of the people regarding technical, social and environmental aspects. This participatory process
will ensure that all views of the people are adequately reviewed and suitably incorporated in the
design and implementation process. Further, to ensure an effective disclosure of the project
proposals to the stakeholders, an extensive project awareness campaign will be carried out.
100. For the information and benefit of the community the summary of IEE will be translated in
the local language (Hindi) and made available at: (i) Office of the PIU/PMU; and, (ii) Office of the
District Magistrate, Pithoragarh and other relevant line departments in the District. These copies will
be made available free of cost to any person seeking information on the same. Hard copies of the
IEE will be available in the PMU/PIU as well as the district library at Pithoragarh, and accessible to
citizens as a means to disclose the document and at the same time creating wider public
awareness. On demand, the person seeking information can obtain a hard copy of the complete IEE
document at the cost of photocopy from the office of the PMU/PIU, on a written request and
payment for the same to the Project Director. Electronic version of the IEE will be placed in the
official website of the Tourism Department and the website of ADB after approval of the documents
by Government and ADB. This will create awareness of the project implementation among the
public.
C. Grievance Redress Mechanism
101. The affected person/aggrieved party can give their grievance verbally or in written to the
local grievances committee. Grievances of affected person will first be brought to the attention
of the implementing NGO who can resolve the issue at site level. If the matter is not solved
within 7 days period by the NGO or PIU, it will be brought to the Grievance Redress Committee
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
46
constituted for the purpose in PIU. This GRC shall discuss the issue in its monthly meeting and
resolve the issues within one month of time after receiving the grievance. If the matter is not
resolved by GRC at PIU level within stipulated time, it shall be referred to GRC at PMU level by
Executive Engineer of PIU.
102. GRC at PMU shall discuss the issue and try to resolve it and inform the PIU accordingly.
If the matter is not resolved by the GRC at PMU level within one month of time, the aggrieved
person/party can bring the matter to The Court of Law. The PIU shall keep records of all
grievances received including contact details of complainant, date of receiving the complaint,
nature of grievance, agreed corrective actions and the date these were affected and final
outcome. The grievance redress process is shown below.
Composition and functions of GRC
103. Local Grievance Committee.(LGC) – In this LGC has worked with NGO, SHG, Line
Agency, representative of Gram Panchayat ,Special invitee.
104. Grievance Redress Committee (GRC) at PIU- In each PIU there shall be one GRC,
which will include Project Manager (PIU), District Tourist Officer of Department of Tourism of
Govt. Of Uttarakhand, Community Development Officer of PIU, nominated representative of
District Magistrate and nominated representative committee shall be headed by Project
Manager (PIU). The committee will meet at least once in every month. Agenda of meeting shall
be circulated to all the members and affected persons/aggrieved party along with venue, date
and time; informed in written at least 7 days in advance of meeting. The matters shall remain
with GRC at PIU level for one month and if grievance is not resolved within this time period, the
matter shall be referred to GRC at PMU.
105. GRC within Environmental and Social Management Cell (ESMC) at PMU- There
shall be one GRC in PMU. The matters not resolved by the GRC at PIU level within one month
shall come under GRC at PMU. GRC at PMU will include Community Development Expert of
PMU, Safeguard Specialist of PMU and Additional Project Director (APD) of PMU. The
Committee shall be headed by APD of PMU. This committee shall look the matters, which are
referred to and not resolved by GRC at PIU level. If the matter is not resolved by the GRC at
PMU level within one month of time, the aggrieved person/party can bring the matter to The
Executive Committee/State Level Empowered Committee (SLEC).
Approach to GRC
106. Affected person/aggrieved party can approach to GRC for redress of his/their grievances
through any of the following modes-
(a) Web based: A separate corner will be developed at the program website so that public /
community/ affected person can register their complaint in the online column.
(b) Telecom based: A toll free no. Will be issued by the PMU/ PIU so that general public
can register their complaint through telephone / mobile phone to the PIU/PMU office.
(c) Through implementing NGO: The local representative of the NGO appointed for the
purpose will collect the problems & issues of the community or affected person and pass
on the same to PIU / PMU.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
47
Figure 1: Grievance Redress Mechanism in IDIPT, Uttarakhand
Note: 1. LGC - NGO, SHG, Line Agency, Representative of Gram Panchayat, Special invitee 2. GRC – PM, CDO, Engineer, DFO, DTO, SDM 3. GRC in Environment and Social Management Cell (ESMC) – PMU (APD, SS, CDS, FS),
PMC (EE, CDE)
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
48
VII. FINDINGS & RECOMMENDATIONS
107. The proposed components of the project are in line with the sub-project selection criteria
for the IDIPT. The subproject conforms to all GoI, GoUK and ADB regulations, policies, and
standards including all necessary government permits and clearances.
108. The significance of the environmental impacts will be more due to the construction
related impacts. It is to be noted that the resultant potential impacts from these proposals can
be offset through provision of proven mitigation measures during the design and adoption of
good engineering practices during construction and implementation. Further, the provision of
environmental infrastructure will better the environmental conditions and minimize the pollution
related and aesthetic quality near the tourist areas and the other destinations.
109. The specific management measures laid down in the IEE will effectively address any
adverse environmental impacts due to the sub-project. The effective implementation of the
measures proposed will be ensured through the building up of capacity towards environmental
management within the PMU supplemented with the technical expertise of a Safeguards
Specialist as part of the DSC Consultants. Further, the environmental monitoring plans provide
adequate opportunities towards course correction to address any residual impacts during
construction or operation stages.
VIII. CONCLUSIONS 110. The project will deliver a unique and innovative tourist attraction to the city/region; incorporating the beauty of its natural environment, local indigenous culture and native plantings, wildlife corridor, recreational and landscaped areas including feature lookout over scenic point, landscaped rest stops and historic remains. The Pithoragh Chandak trail will develop new interpretive signage and create displays designed to enhance tourists' experience in trekking trails. In addition modifications to the existing trail will be undertaken in order to streamline, upgrade and enhance the existing trail route for the benefit of the local people and visitors without disturbing the natural setting. 111. The IEE carried out for the sub-project shows that the proposed sub-components
will result in net environmental benefits in terms of enhanced tourism facilities and revenue
generation, and that any adverse environmental impact can be addressed through proper
location, planning, and design of the proposed sub-project; control of construction activity and
mitigation measures. The EMP provided for mitigation of all identified short term impacts and
the contract clauses for the environmental provisions will be part of the civil works contracts.
Further, the proposed designs have been consulted with the stakeholders and no significant
issues requiring redress in terms of environmental safeguards exist.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
49
ANNEXURE- 1
RAPID ENVIRONMENTAL ASSESSMENT (REA) CHECKLIST
Instructions:
i. The project team completes this checklist to support the environmental classification of a project. It is to be attached to the environmental categorization form and submitted to the Environment and Safeguards Division (RSES) for endorsement by the Director, RSES and for approval by the Chief Compliance Officer.
ii. This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately considered, refer also to ADB's (a) checklists on involuntary resettlement and Indigenous Peoples; (b) poverty reduction handbook; (c) staff guide to consultation and participation; and (d) gender checklists.
iii. Answer the questions assuming the “without mitigation” case. The purpose is to identify
potential impacts. Use the “remarks” section to discuss any anticipated mitigation measures.
Country/Project Title: IDIPT: India/ Uttarakhand, Revival and development of Trekking Trail and Vantage points at Pithoragarh to Chandak, Uttarakhand
Sector Division: SAUW (South Asia Urban Development and Water Division)
SCREENING QUESTIONS Yes No REMARKS
A. Project Siting:
Is the project area adjacent to or
within any of the following areas?
Densely populated? Around 15 villages in the range of 1-8 km
Heavy with development
activities?
Adjacent to or within any
environmentally sensitive
areas?
Van Panchayat Forest
Cultural heritage site
Protected Area
Wetland
Mangrove
Estuarine
Buffer zone of protected
area
Special area for protecting
biodiversity
Bay
B. Potential Environmental
Impacts
Will the Project cause….
Impacts on the There will be no direct impacts on the
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
50
SCREENING QUESTIONS Yes No REMARKS
sustainability of associated
sanitation and solid waste
disposal systems and their
interactions with other
urban services.
sustainability of the systems due to the
proposed improvements.
Deterioration of
surrounding environmental
conditions due to rapid
urban population growth,
commercial and industrial
activity, and increased
waste generation to the
point that both manmade
and natural systems are
overloaded and the
capacities to manage
these systems are
overwhelmed?
This is a small project intending to
strengthen existing trek trail used by local
villagers and tourists. Hence no significant
interface with existing environmental
conditions of the area is expected.
Degradation of land and
ecosystems (e.g. loss of
wetlands and wild lands,
coastal zones, watersheds
and forests)?
Dislocation or involuntary
resettlement of people
Degradation of cultural
property, and loss of
cultural heritage and
tourism revenues?
Occupation of low-lying
lands, floodplains and
steep hillsides by squatters
and low- income groups,
and their exposure to
increased health hazards
and risks due to pollutive
industries?
Water resource
problems (e.g.
depletion/degradation
of available water
supply, deterioration
for surface and ground
water quality,
and pollution of receiving
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
51
SCREENING QUESTIONS Yes No REMARKS
waters?
Air pollution due to urban
emissions?
During construction phase only dust may
arise which should be mitigated through
sprinkling, no other significant emission is
expected. During operation phase no
emission expected as only pedestrian trek
trail
Risks and vulnerabilities
related to occupational
health and safety due to
physical, chemical and
biological
hazards during project
construction and
operation?
Only physical hazards to workers due to
accidents may come across during
construction for which safety of workers
should be taken in priority.
Social conflicts between
construction workers from
other areas and local
workers?
Road blocking and
temporary flooding due to
land excavation during
rainy season?
Noise and dust from
construction activities?
Minor impact envisaged during the
construction activity. Adoption of mitigation
measures shall effectively address such
impact during construction.
Traffic disturbances due to
construction material
transport and wastes?
Minor impact envisaged during construction.
Due care will be taken during construction to
avoid traffic disturbances
Temporary silt runoff due
to construction?
Temporary silt runoff is expected due to
construction activities, adoption of mitigation
measures shall effectively address such
impact during construction.
Hazards to public health
due to ambient, household
and occupational pollution,
thermal inversion, and
smog formation?
Water depletion and/or
degradation?
Overpaying of ground
water, leading to land
subsidence, lowered
ground water table, and
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
52
SCREENING QUESTIONS Yes No REMARKS
salinization?
Contamination of surface
and ground waters due to
improper waste disposal?
Waste disposal shall be done in legitimate
manner and will not cause pollution
Pollution of receiving
waters resulting in amenity
losses, fisheries and
marine resource depletion,
and health problems?
No water body nearby
Large population influx
during project
construction and
operation that causes
increased burden on
social infrastructure and
services (such as
water supply and
sanitation
systems)?
Social conflicts if
workers from other
regions or countries are
hired?
Workers from nearby areas shall be hired
Risks to community
health and safety due to
the transport, storage,
and use and/or disposal
of materials such as
explosives, fuel and other
chemicals during
operation and
construction?
Community safety risks
due to both accidental
and natural hazards,
especially where the
structural
elements or components
of the project are
accessible to members
of the affected
community or where
their failure could
result in injury to the
community throughout
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
53
SCREENING QUESTIONS Yes No REMARKS
project construction,
operation and
decommissioning?
Climate Change and Disaster Risk Questions
The following questions are not for environmental ca tegor i za t ion . They are
Included in this checklist to help identify potential climate and disaster risks.
Is the Project area subject
to hazards such as
earthquakes, floods,
landslides, tropical cyclone
winds, storm surges,
tsunami or volcanic
eruptions and climate
changes
The project area is located in an area prone
to landslides, cloud bursts, earthquakes etc
as it is located in the seismic Zone V as per
IS 1893:2002.
Could changes in
precipitation, temperature,
salinity, or extreme events
over the Project lifespan
affect its sustainability or
cost?
The project area lies in the hilly region
having landslides a major environmental
problem during monsoons. In case of such
events, the road blockage may hamper
project progress.
Are there any demographic
or socio- economic aspects
of the Project area that are
already vulnerable (e.g.
high incidence of
marginalized populations,
rural-urban migrants, illegal
settlements, ethnic
minorities, women or
children)?
Could the Project
potentially increase the
climate or disaster
vulnerability of the
surrounding area (e.g.,
increasing traffic or
housing in areas that will
be more prone to flooding,
by encouraging settlement
in earthquake zones)?
Due to development of tourism
infrastructure, it is envisaged that tourist
inflow in the area will increase resulting to
increase traffic and noise pollution in the
area. Also more enterprises like guest
houses, lodges, home-stays and shops are
likely to come. Proper systems need to be
developed to address such problems in
future.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
54
ANNEXURE- 2
PROJECT LOCATION MAP
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
55
ANNEXURE 3
PROJECT PHOTOGRAPHS
Start Point of Trekking Trail View from the proposed feature lookout
View of Existing Ruins Trekking Trail
View from the proposed View Point View of magnesium ore plant from the trail
Existing Road at the start of the trekking Trail Trail Condition
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
56
ANNEXURE 4
No objection certificate from Nagar Palika Parishad, Pithoragarh
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
57
No objection certificate from Sarpanch, Van panchayat
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
58
No objection certificate from Forest Department
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
59
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
60
ANNEXURE 5
AMBIENT AIR QUALITY REPORT
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
61
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
62
NOISE MONITORING REPORT
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
63
ANNEXURE 6
STAKEHOLDER CONSULTATION PHOTOGRAPHS
Public Consultation at Mostamannu Temple Public Consultation at Mostamannu Temple
Public Consultation at Mostamannu Temple Public Consultation at Mostamannu Temple
Public Consultation with local historian Public Consultation with local historian
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
64
ANNEXURE- 7
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
65
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
66
ANNEXURE- 8
Minutes of Meeting
Date 27 Dec 2013
Venue -Vikas Bhawan Pithoragarh
Chaired by- Dr Anand Srivastava, Chief Development Officer
CO-chaired by – S.D.M Pithoragarh
Attended By – Mr Tushar Chakravarty [Consultant DSC Bhimtal]
Ms Paromita De Sarkar [Consultant DSC Bhimtal
Mr Rajeeve Kulshrestra [ Team leader DSC Bhimtal]
Dr Jagat Sontiyal [C.D.O PIU Bhimtal]
Mr Raja Joshi [ S.E PIU Bhimtal]
1. The Meeting was held to discuss proposed concept plan of the Pithoragarh fort. The
consultant presented various aspects of the project including the overall vision, goals and
objectives, description of various interventions proposed in the fort enclosure complex and
the precinct, the re-use plan, and the road map for the proposed re-use of buildings.
2. The site issues pertaining to the projects was discussed and the consultants highlighted the
issue of unregulated high rise structures in the vicinity of the fort precinct and the need to
regulated high rise structure in the fort precinct. The CDO mentioned that development works
in Pithoragarh in currently regulated and asked the SDM to look into this matter.
3. The matter of Ram Leela ground came up for discussion in the context of the proposed
development works proposed by the consultants. The SDM mentioned that the land is
currently under the use of Ram Leela Committee for over a century.
4. Regarding the proposal to display artefacts in the local history museum, the CDO mentioned
the museum set by Mr Pangti on Bhutia culture located in Munsiari, and that exhibits from
such museums in the region can be put upat the Pithroagarh fort local museum as travelling
exhibition and therefore the consultants in their re-use plan for the tensil office can make
provisions for that.
5. Highlighting the danger of unsustainability of tourist destinations, the CDO highlighted the
case of Kasardevi in Almora district.
6. The CDO mentioned that necessary action has been taken for the rehabilitation of Tehsil
office.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
67
7. In the context of the proposed interventions highlighted in the Concept Plan, the SDM assure
the team of consultants that necessary help would be provided to resolve any land and other
related issues at administration level.
8. The consultants requested the CDO for another meeting to discuss project related issues
following the teams site work.
Meeting with Executive Officer, Nagar Palika Pithoragarh
1. Regarding land ownership of trek trail beyond 3 m belonging to the Van Panchayat, the EO
mentioned that the land of Van Panchayat belonged to the Van Panchayat of Shera village
and Bajeti village.
2. Regarding the ownership of Ram Leela grounds the JE mentioned that the land belonged to
Nagar Palika but it is occupied by Ram Leela committee and therefore it may be feasible to
take NOC from Nagar Palika, but consultation with the Ram Leela committee would be
necessary to implement any development activity proposed for the Ram Leela ground.
3. Regarding O& M cost of heritage trail, the EO stated the Nagar Palika lack of budget for the
O&M of the heritage trail. This matter would need to be discussed with the CDO/DM.
4. Regarding the proposal for the Nagar Palika Chowk and the proposed interventions the JE
mentioned that NOC would have to be taken from the PWD.
Meeting with Tehsildar
1. The rehabilitation of the Tehsil staff would need to be addressed for successful
implementation of the proposed Fort project. This issue has to be discussed further with the
DM/CDO.
2. The rehabilitation of the Tehsil office along with their proposal must be mentioned in the
Resettlement Plan.
3. The Tehsildar assured that the revenue records of trek trail and Mostmanu would be
provided to the team by the Revenue officer.
Meeting with Chief Development Officer, Pithoragarh
Venue: Vikas Bhawan, Pithoragarh
DAY 1: Friday 27th December 2013
Chaired by- Dr Anand Srivastava, Chief Development Officer
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
68
CO-chaired by – S.D.M Pithoragarh
Attended By :
Mr Rajeeve Kulshrestra [ Team leader DSc Bhimtal]
Dr Jagat Sontiyal [Community Development Officer, PIU Bhimtal]
Mr Raja Joshi [ Support Engineer PIU Bhimtal]
Mr Tushar Chakravarty [Cultural Heritage Management Expert DSC Bhimtal]
Ms Paromita De Sarkar [Cultural Heritage Conservation Specialist DSC Bhimtal]
The Meeting was held to discuss proposed concept plan of the Pithoragarh fort. The
consultant presented various aspects of the project including the overall vision, goals and objectives,
description of various interventions proposed in the fort enclosure complex and the precinct, the re-
use plan, and the road map for the proposed re-use of buildings.
1. The site issues pertaining to the projects was discussed and the consultants highlighted the
issue of unregulated high rise structures in the vicinity of the fort precinct and the need to
regulated high rise structure in the fort precinct. The CDO mentioned that development works
in Pithoragarh in currently regulated and asked the SDM to look into this matter.
2. The matter of Ram Leela ground came up for discussion in the context of the proposed
development works proposed by the consultants. The SDM mentioned that the land is
currently under the Ram Leela Committee.
3. Regarding the proposal to display artefacts in the local history museum, the CDO mentioned
the museum set by Mr Pangti on Bhutia culture located in Munsiari, and that exhibits from
such museums in the region can be put up at the Pithroagarh fort local museum as travelling
exhibition and therefore the consultants in their re-use plan for the Tehsil office can make
provisions for that.
4. Highlighting the danger of unsustainability of tourist destinations, the CDO highlighted the
case of Kasardevi in Almora district.
5. The CDO mentioned that necessary action has been taken for the rehabilitation of Tehsil
office.
6. In the context of the proposed interventions highlighted in the Concept Plan, the SDM assure
the Dsc and PIU team that necessary help would be provided to resolve any land and other
related issues at administration level.
7. The consultants requested the CDO for another meeting to discuss project related issues
following the team’s site work.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
69
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
70
DAY 2: Saturday 28th December 2013
Chaired by- Dr Anand Srivastava, Chief Development Officer
Attended By
Mr Rajeeve Kulshrestra [ Team leader DSc Bhimtal]
Dr Jagat Sontiyal [Community Development Officer, PIU Bhimtal]
Mr Raja Joshi [ Support Engineer PIU Bhimtal]
Mr Tushar Chakravarty [Cultural Heritage Management Expert DSC Bhimtal]
Ms Paromita De Sarkar [Cultural Heritage Conservation Specialist DSC Bhimtal]
1. The DSc and PIU informed the CDO about the discussions held with various stakeholders
and issues identified for the consideration of the District Administration for their perusal.
2. The issue pertaining to the ownership of Ram Leela ground was discussed. It was informed
that the land ownership of the historic Ram leela ground in the Fort precinct was with the
Nagar Palika Pithoragarh however the ground is currently occupied by the Ram Leela
Committee and therefore it would be necessary to initiate a dialogue with the Ram Leela
Committee to take their consonance for the proposed interventions in the Ram Leela ground.
3. The CDO informed the team that the SDM would help in coordinating between the Nagar
Palika and the Ram Leela Committee to resolve all matters in hand pertaining to the
proposed interventions in the Ram Leela ground.
4. The visiting team recommended that it would be appropriate to notify the Pithoragarh fort
enclosure after the evacuation of the Tehsil office and its ancillary buildings to minimize the
risk of appropriation.
5. The PIU and DSc team informed the CDO about their meeting with the Tehsildar Pithoragarh
on 28th December 2013 and need to address the issue of rehabilitation of Tehsil staff
residences at present located in the Fort enclosure and precinct area. The DSc team
informed the CDO that nearly 22 staff members together with their family would need to be
relocated. The CDO informed that following the shifting of the Tehsil Office the shifting of the
staff members would also be considered after discussion as a proposal would have to be
forwarded to the Revenue board and this would take some time.
6. In view of the proposed resettlement of the Tehsil staff, the chair was of the opinion that the
project should be phased in such a manner that the proposal for the fort enclosure should be
executed in the first phase and subsequently the proposals outside the fort in the precinct
area could be implemented. During this period an alternate residential arrangement can be
worked out for the Tehsil staff.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
71
7. For the Resettlement Plan of the Pithoragarh Fort enclosure the DSc requested for a letter
confirming the shifting of the Tehsil Office to the new site, the CDO informed that the SDM
can be requested for the same.
8. The DSc informed the CDO about the need to look into the issue of O& M of the Chandak
Heritage trail project. The CDO informed the team that the matter would be taken up with the
Nagar Palika and the District administration would advice them with options for revenue
generation that can be ring-fenced to operate and maintain the trail including PPP options.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
72
ANNEXURE- 9
Report on Trip to Pithoragarh, 6-8 January 2014
Day 1, 6 January 2014: Travel to Pithoragarh
Meeting 1: Shri Manoj Matwal, Harela Society, Pithoragarh
Points of discussion:
1. There are many other significant sites around Pithoragarh, that could be taken up for appropriate tourism development. For instance, the Devdar forest behind the abandoned factory site could be taken up for trail development.
2. There are many mineral deposits in the area, and Harela had organised geological walks for students to experience them.
3. Udaipur hill fort is a historic structure which ought to be showcased and protected.
4. There are sites where fossil remains are found between Chandak and Udaipur Fort. The two resources can be combined for a comprehensive trail experience.
5. Chandika Devi temple is another important shrine, as significant as Mostamanu temple.
6. The forest near Mostamanu temple is a sacred grove, with dense Oak forests that are a catchment area for Rai Gaard (stream). In order to ensure the protection of the water catchment area, the local villagers have taken wood from the sacred grove and offered it at the Kot Gaadi (Goddess) temple, thereby symbolically ensuring its protection. This affirmative action on the part of the village community demonstrates their awareness of the environmental significance of the forest, as also their desire to protect it. This should be respected.
7. It was suggested that website and social media should be used to showcase the cultural and environmental heritage of Pithoragarh to visitors. Events like Sharadotsav festivals should be vehicles to promote Kumaoni performing arts like Chhalia dance etc.
8. It was decided that a Cultural Walk be undertaken by the project team on Day 3 to experience a traditional settlement (Kot) of Pithoragarh.
Day 2, 7 January 2014
Meeting with Chief Development Officer, Shri Anand Srivastava (09412151050; [email protected])
Project team: Dr. Yaaminey Mubayi, PRIMA-ACS, Dr K.K. Gaur, WAPCOS, Mr Tyagi, WAPCOS, Dr Suresh Mathpal, Shri Arun Dev, DSC Bhimtal, Representative of PIU
Points of Discussion:
1. Pithoragarh Fort:
- Regarding the issue of full evacuation of the Fort for restoration work, CDO agreed that rehabilitation of residents and staff will be carried out via alternate accommodation. He said the matter had been discussed with DM who was fully apprised of the situation.
- Regarding the situation vis-a-vis the Ramlila Committee, CDO agreed that a detailed Public Consultation should be carried out involving multiple stakeholders, including Nagar
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
73
Palika, Ramlila Committee, Market Associations, residents and local institutions. It may be chaired by SDM, who was the appropriate officer in charge of the Tehsil and other land related matters. It was recommended that stages of public consultations could be carried out to resolve any issues in the area. It was also agreed that draft plans for the project should be placed in the public domain, so that feedback from various stakeholders could be elicited.
- The Reuse Plan for the Fort, including the involvement of DRDA and SHGs in running the Craft Centre and Cafeteria, had already been communicated to the CDO, who approved of them in principle.
- Regarding notification of the Fort by State Department of Culture following its restoration, it was agreed that it was a favourable option for future maintenance and sustainability. CDO was apprised of the possibility of Buffer Zone Regulations coming into play, and recommended that the matter be further discussed at various levels.
2. Mostamanu Temple:
- CDO was informed that there appeared to be conflicting claims (Mandir Committee, Mostamanu Vikas Samiti) for the position responsible for the temple affairs. It was stated that the Mandir Committee was an unregistered body. He recommended that registration of the Committee under the Societies Act of 1860 was not a problem, and could be immediately done in Pithoragarh itself by the Chief Treasury Officer (Shri Hemendra Gangwar). He said that the District Administration would help to facilitate the registration process.
- The issue of ownership of land relating to the temple was discussed in detail and it was stated that the two nalis (approximately) of land on which the temple was located, was registered at “Mandir Prangan” (temple courtyard) in the land records, thereby indicating its position following the settlement (bandobast) of the area carried out in 1960. The surrounding land on which the proposed project interventions were to be located, according to CDO, may not be Nazul land as initially assumed, but registered under two Gram Panchayats of villages Dhunga and Bakarkatiya respectively.
- CDO stated that all NOCs had to be on a valid letterhead with stamp of Tehsildar or other signing authority, in order to be valid. NOCs on plain paper without stamp were not valid.
- CDO directed that the project team meet with the Patwari and clarify all land ownership by checking the records.
3. Chandak Trails:
- CDO was asked whether ownership of the land on which the trails were located rested with the Nagar Palika. He clarified that there was a difference between “ownership” of the land and “management authority” over the area, and it was to be ascertained whether Nagar Palika was actually the owner or simply the manager. Even if they were the managers responsible for maintenance of the trails, NOCs would be required from other stakeholders like Van Panchayats and any others to mitigate the risk of any dispute arising in the future.
4. In summation:
- Regarding overall strategy for tourism development in the region, CDO stated that it was dependent on the “convergence” of different factors, i.e. the opening of the Naini Saini airport proposed for October 2014, the parallel development of better hotels and tourist accommodation and facilities in Pithoragarh. Only then would the proposed project activities find a viable market for successful operations and sustainability.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
74
Visit to Nagar Palika and meeting with Shri Madan Singh Bora, PWC (09760299236). List of contacts given:
- Shri Jagat Singh Khati, Chairman, Nagar Palika (07599093844/09690234555)
- Shri Khemanand Joshi, Executive Officer, Nagar Palika (09410113386)
- Shri N.C Pandey, Patwari
Meeting with Shri Pandey, Patwari, and verification of land records by some members of project team.
Visit to Trail site along with Patwari to verify some details.
Meeting with Shri Jagat Singh Khati, Chairman, Nagar Palika, Pithoragarh
1. Fort: The Chairman stated that he was reluctant to engage in conflict with any citizens group, particularly the Ramlila Committee, and was willing to find mutually acceptable solutions to any issues that may arise. The Nagar Palika would participate in any public consultation that may be held regarding the Fort project.
2. Trails project: The trails are located within the territorial jurisdiction of the Nagar Palika. The Palika would also take up any responsibility for maintenance that is entrusted to it. Regarding any cess or other funding source, the idea is not viable at this point.
3. Chairman suggested lighting be installed along the trail to facilitate people’s movement.
4. Regarding NOCs for the trail, the Nagar Palika is willing to give a blanket NOC for the entire trail.
Day 3, 8 January 2014
Cultural Geography Walk at Kumaur, a village adjoining Pithoragarh town.
Participants: Entire project team, guided by Shri Manoj Matwal of Harela Society
Observations:
- The “village” is heavily urbanised in an unplanned and agglomerated manner. There is heavy traffic and the approach is dangerous in terms of fast vehicles and no traffic controls. There is s sense of dilapidation and lack of care about the space and its people, which is subordinated to the interest of the town of Pithoragarh.
- While some aspects of the traditional morphology and layout of streets still exist, the buildings are completely transformed, with vernacular structures replaced by brick and cement buildings.
- As one goes deeper into the village settlement, there are some remaining vernacular houses, possible inhabited by rural households that have not yet managed to urbanise their homes, livelihoods and lifestyles. Thus one finds a few domestic animals, well-drawn water usage etc. not visible in the urbanised fringes that are closer to Pithoragarh.
- The Kot was traditionally the citadel or centre of the settlement, home to 40-50 families of the land-owning aristocracy of the village. It consists of a central double storeyed building constructed with mud mortar with wooden beams and roof. Two wings abut the central building, all opening onto a central courtyard. Carved wooden balconies face the courtyard from the upper stories. Water was supplied from the Naulas (springs) from the lower slopes.
- The building was the focus of several community based practices and festivals, such as the Yatras in the month of Chaitra (April) and Bhitoli (festive gifts to the sister’s village). Such Yatras were a symbolic means of interaction and links of reciprocity between the village communities in the region.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
75
- The building is possibly about 300 years old. Ownership is possibly with the Gram Panchayat. It is abandoned and in an advanced stage of dilapidation. It requires urgent conservation.
Meeting with Shri Bahadur Singh Mahar, Elderly resident of Kumaur
- Origin myth of the settlement: Four brothers of the Mahar family based in Chittor (Rajasthan), owing to a quarrel with a rival clan, came away to Pithoragarh about 400 years ago. They took shelter in the hut of an old woman who stayed in the village of Pandeygaon (Brahmin village in the vicinity). She warned them about a man-eating tiger that had terrorised the settlement. At night, the tiger came to the hut and tried to tear off the roof. The brothers fought with it and killed it, cutting off its paw as proof. The next morning, the dead tiger was found by a local resident, who reported it to the king as his kill. The king had declared a reward for whoever killed the man-eater, and accordingly was about to give it to the finder. However, the queen asked him to produce the missing paw as proof of his having killed it. When the false claimant failed to do so, the four brothers came forward and produced the paw. The king offered them as much land as they could see with the naked eye, and this became the settlement of Kumaur. The word “Kumaur” is derived from “Kuru Mahar”, the name of the eldest brother.
-
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
76
Meeting with District Magistrate, Dr. Neeraj Khairwal (08193396001)
Participants: Full Project Team, Shri Anand Srivastava, CDO
Points of Discussion:
1. The DM requested to view the project presentation, which he had not yet seen. The presentation was made by Shri Arun Dev and Dr. Yaaminey Mubayi.
2. The DM was briefed on the previous day’s discussion by CDO.
3. The Fort:
- DM assured the team that the fort would be evacuated before the project began. However, he emphasised that he should be informed about the date of commencement of the project work, and accordingly he would have the fort evacuated. He did not want to clear the fort and have it lying empty for long, in case the project was delayed.
- The residential areas of the Tehsil would also be cleared, it was assured.
- He wished to have the details of the interventions at the Fort explained to him on a room-to-room basis, and recommended an on-site meeting for the purpose.
- He had some comments regarding the proposals for interventions, for example, he recommended that the walking pathway be paved in heavy stone for longer lasting and durable usage.
4. Mostamanu Temple:
- Having been briefed by the CDO regarding the issues at the temple, DM called for the SDM and directed him to hold a Mediation Meeting with all concerned parties related to the temple. He said the threat of takeover of temple management by District Administration could be used as a last resort to decide which agency would manage the temple.
5. NOCs pertaining to Mostamanu Temple and Trails:
- DM stated that regardless of whether the areas lay in the Nagar Palika’s jurisdiction, it was imperative to get NOCs from all owners registered in the land records, including Van Panchayats, Gram Panchayats etc. This is to mitigate the risk of any dispute regarding ownership in the future.
Meeting at Mostamanu Temple, Chandak
Two attempts were made to have a discussion with the temple committee, however, on both occasions, only the Temple Pujari and the MLA’s representative, Shri Mahendar Singh Bisht, were present.
Points of discussion:
1. The matter was discussed and the stipulations of ADB regarding the existence of a formal registered body with transparent functioning, auditing systems etc. to hand over the assets created as part of the project, were explained.
2. Shri Bisht informed us that there was another committee, Mostamanu Vikas Samiti, of which the Mandir Committee was a part, which was registered and appropriate for the job.
3. The Secretary of the Mandir Committee in a separate interview, declared that the Mandir Committee had nothing to do with the registered entity, and would not allow them to enter the temple premises.
Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak
77
4. The team intimated the Pujari that it was imperative that a resolution to the issue must be found soon. We urged the Mandir Committee to complete the registration process, asking them the reason for their delay in registering. We emphasised that the District Administration had offered to facilitate the process of registration.
5. The team was informed that the Mandir Committee would have a meeting in the next two days to decide the issue. However, subsequently it was learned that the meeting did not take place as the President had hurt his leg and was hospitalised.
6. It is hoped that the matter would be decided via mediation by SDM, as indicated by DM.