infrastructure australia project submission · infrastructure australia project submission august...
TRANSCRIPT
City to Gungahlin Transit Corridor
Infrastructure Australia Project Submission
AuGusT 2012
City to Gungahlin Transit Corridor Infrastructure Australia Project submission i
ContentsExecutive Summary ........................................................................................................ 1
1 Introduction ............................................................................................................ 51.1 Purpose ............................................................................................................................................ 5
1.2 Background ...................................................................................................................................... 5
1.3 A Package Approach ........................................................................................................................ 6
2 About the Project ................................................................................................... 82.1 ProjectObjectives ............................................................................................................................ 8
2.2 Proposed Works ............................................................................................................................... 9
2.3 Transport, Land Use and Pricing Scenarios ...................................................................................... 9
3 Alignment with Government Objectives ................................................................ 153.1 AlignmentbetweenACTandCommonwealthGovernmentObjectives ...................................... 15
3.2 AlignmentwithNationBuildingProgram2 ................................................................................... 17
3.3 NationalCapitalPlan ...................................................................................................................... 17
3.4 ACTGovernmentObjectives .......................................................................................................... 18
4 ProblemIdentification,AssessmentandAnalysis ................................................. 194.1 IdentificationandAssessment ....................................................................................................... 19
4.2 Analysis........................................................................................................................................... 23
5 Assessment of Options ........................................................................................ 255.1 SummaryofOptions ...................................................................................................................... 25
5.3 Demand Impacts ............................................................................................................................ 26
6 Next Steps ........................................................................................................... 306.1 EstablishmentoftheGungahlintoCityProjectOffice .................................................................. 30
6.2 Feasibility and Forward Design Works ........................................................................................... 30
6.3 Funding Requirements ................................................................................................................... 31
Appendix A: Stages 1 – 6 ............................................................................................ 33Stage1–GoalDefinition .......................................................................................................................... 36
Stage2–ProblemIdentification .............................................................................................................. 38
Stage 3 – Problem Assessment ................................................................................................................. 39
Stage5–OptionGeneration .................................................................................................................... 50
Stage6–OptionAssessment ................................................................................................................... 54
Appendix B: Stage 7 Template ...................................................................................... 62AppraisalSummaryTable1:DemandandEconomicModellingAssumptions ....................................... 62
AppraisalSummaryTable2:MonetisedCostBenefitAnalysisResults ................................................... 77
AppraisalSummaryTable3:Benefit-CostRatioSensitivityTesting ......................................................... 85
AppraisalSummaryTable4:Non-MonetisedBenefitsandCosts ............................................................ 86
AppraisalSummaryTable5:InformationSources ................................................................................... 88
ACT Government Environment and sustainable Development Directorate ii
Costs,RisksandFunding ............................................................................................. 89Staging ....................................................................................................................................................... 89
Risk Management ..................................................................................................................................... 89
EnvironmentalRisks .................................................................................................................................. 97
NeedforGovernmentFunding ................................................................................................................. 98
NeedforCommonwealthGovernmentFunding ..................................................................................... 99
DeliveryStrategy ..................................................................................................................................... 100
GovernanceStrategy .............................................................................................................................. 101
Economic Appraisal Table: BRT under a Business As Usual Land Use Scenario ..................................... 102
Economic Appraisal Table: LRT under a Business As Usual Land Use Scenario ..................................... 104
Economic Appraisal Table: LRT under a Higher Density Land Use Scenario .......................................... 108
Footnotes .................................................................................................................... 110
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 1
Executive Summary
Introduction
TheACTGovernmentisconstantlyworkingtowardssupportingamoresustainableCanberra,evidencedbyitscomplementaryACTPlanningStrategyandTransportforCanberrastrategythataresettingastrongframeworkfortheintegrationoftransportandlanduseplanningtodeliveramorecompactandsustainable city and Territory.
InitssubmissiontoInfrastructureAustraliain2011,theACTGovernmentoutlineditsintentionstoinvestigatethefeasibilityofdevelopingrapidtransitintheGungahlintoCitycorridor.TheGungahlintoCity Rapid Transit Corridor Project (the ‘Project’) was commissioned subsequently in late 2011 to assess the prospects of rapid transit.
AsadirectoutputoftheProject,anOutlineBusinessCasewaspreparedfortheACTGovernmentforitsconsiderationinApril2012.Subsequentupdatestothedesign,costsanddemandhavebeenmade,theresults of which are presented in this submission.
About the ProjectThissubmissionseeks$15millioninfundingfromtheNationBuildingProgram2fortheforwarddesign and planning of the City to Gungahlin Transit Corridor. Forward design and planning will include: furtherdemandmodellingandeconomicassessment(includingtriplebottomlineanalyses);feasibilityandpreliminarydesignofDicksonstation,GungahlinterminusandCityconnections;designoftransitorienteddevelopmentoptionsincludingapublictransportnetworkreview;avehicleoptionsfeasibilitystudy;andinfrastructurefeasibilityanddesignwork.
The City to Gungahlin Transit Corridor is a 12.5km rapid transit link between Gungahlin, Canberra’s fastestgrowingdistrict,andtheCity.ThecorridorcomprisesFlemingtonRoadandthenationallysignificantNorthbourneAvenue,andistheprimarytransportcorridorconnectingCanberra’sgrowingnorthern suburbs with the City and the South.
TheGovernmenthasconsideredtheeconomicoutcomesofinvestingineitherbusrapidtransit(BRT)orlightrailtransit(LRT)underabusinessasusuallandusesettingandagainsthigherpopulationandemploymentdensitiesintheProjectCorridor.
ThisProjectgoesbeyondsimplyprovidingatransportbasedsolutiontoatransportproblem.WhileaninvestmentinrapidtransitinfrastructureisacornerstoneofproposedinterventionswithintheProjectCorridor,theProjectfirmlyintegratestransportandlanduseasameanstodriveinvestmentinamorecompact, sustainable Canberra.
Key IssuesThelowresidentialdensitiesandthedispersednatureofactivitycentresandemploymentinCanberradolittletoimprovetheproductivityoftheCanberraeconomy,reducecardependency,sustainpublictransportoperationsorreducegreenhousegasemissions.TheseproblemswillbemagnifiedbyfuturepopulationgrowththatisanticipatedwithintheProjectCorridor.
Growingpopulation: The Gungahlin to City Corridor connects Canberra’s fastest growing district, GungahlinwiththeCityandtheParliamentaryTriangle,Canberra’sfocalpointsforcivicandemploymentactivities.Overthepastdecade,populationlevelswithintheGungahlindistrictgrewatanaveragerateof6.8%perannum.PopulationlevelsinGungahlinunderabusinessasusualcaseareprojectedtocomeclosetodoublingby2031,compoundingcurrentcongestion,socialexclusionandhousingaffordabilityconcernsunderabusinessasusualscenario.
ACT Government Environment and sustainable Development Directorate 2
Growingcongestion:ThekeyroadsformingtheProjectCorridor-FlemingtonRoadandNorthbourneAvenue-arefastapproachingcapacity.AlthoughcapacityonalternativeroutesincludingGungahlinDriveandMajuraParkwaycouldbeexpanded,theseroutesdonotdirectlyservetheCityandtherearefewoptionstoincreaseroadcapacityoutsideofcurrentroadcorridors.
Withoutintervention,futuregrowthwithintheProjectCorridorwillservetoleadtoafurtherdeclineinroadspeeds,increasingtraveltimeimpedingaccesstoemployment,communityfacilities,socialandrecreationalactivities.
Impacts on the broader bus network:Asakeybuscorridor,thedegradationoftravelspeedsalongtheProjectCorridoralsoimpactonthespeed,efficiencyandreliabilityofcross-regionalbusservicesoperatingbeyondtheProjectCorridor,impactingonpassengersacrosstheNorthaswellasthosetravellingtoandfromtheCentralNationalAreaandParliamentaryTriangle.
Unsustainabledevelopmentpatterns:Fromaninternationalstandpoint,Australiancitypopulationdensitiesarelowerthanthatoftheirglobalcounterparts–evenmoresoforCanberra.Lowdensitiesareincreasingcardependency,placingupwardpressureonpercapitacostsforprovidingpublictransportandcommunityservicesoverlargerareasandraisingsocialexclusionandserviceaccessissues.
The Project’s PotentialInvestmentinrapidtransitalongtheProjectCorridorhasthepotentialtounlockanumberofeconomicdevelopmentopportunities:
Increasingthetransportcapacityofexistingcorridors:Therearefewoptionstoincreasecapacityoutsideofexistingroadcorridors.Duringpeakperiods,existingbusservicesoperatingalongNorthbourneAvenuecarrymorepassengersthanallcarscombined.Aninvestmentinrapidtransitalongtheexistingcorridorwillsignificantlyincreaseitscarryingcapacity,providevitalcapacitytocaterforfuturegrowthandoptimisetheuseofexistingassets.
Promotingeconomicproductivity:AnumberofopportunitieshavealreadybeenidentifiedbytheACTGovernmenttoincreaseresidentialandcommercialdensitiesonsignificantlyunderdevelopedsitesalongtheProjectCorridor.Theseincludepublichousingredevelopments,aredevelopmentoftheDicksonGroupCentreandthepotentialredevelopmentoflandcurrentlyoccupiedbytheexhibitioncentreandCanberraRacecourse. As a key landowner and land manager under the Territory’s leasehold system, a unique opportunityexistsfortheACTGovernmenttoencourageurbanrenewalwithintheProjectCorridor,bothdirectlyandindirectly.Providingadditionaltransportcapacityisasignificantenableroffurtherdevelopmentof,andinvestmentin,thesesites,maximisingexistinglandcapacitywithintheProjectCorridor.
Promotinggreatersustainability:AspartoftheProject,theACTGovernmentwillactivelysupportincreasingdensityandastrongmixofactivitiesalongtheProjectCorridortoencouragelocalisedtravelandtrips,whichcouldbeservicedbytherapidtransportsystem.Whereinter-towntravelisrequiredtoconnectwithemploymenthubs,fasterandmorereliablepublictransportservices,facilitatedbyeitherBRT or LRT, will encourage a greater use of public transport.
Part of a broader network: TheProjectCorridoristhebackboneoftheGovernment’s2031StrategicPublic Transport Plan Network that establishes the future public transport network for Canberra. This networkwilldeployRapidandFrequentbusservicesthatwillsignificantlyenhanceservicefrequenciesandlegibilityofpublictransportservices.Thenetworkandcross-regionalservicesmeetingwiththeProject Corridor will originate as far out from Tuggeranong, Fyshwick, Queanbeyan and Molonglo Valley. Whenrealisedinfull,corridorsthatcombineurbanrenewal,redevelopmentsandtransportinvestmentwillbeextendedtoothercorridorssuchasConstitutionAvenueandCommonwealthAvenue.
Supportscross-governmentcity-buildinginitiatives: The Project will support other work being undertakenjointlywiththeCommonwealthGovernment,includinga$42mcommitmenttoredevelopingConstitutionAvenueand$500,000fortheRealisingtheCapitalinaCitymasterplanthatwillfocusonplanningalongCommonwealthAvenue.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 3
A2
Both projects propose new dedicated bus infrastructure, cycle paths and urban amenity treatments to facilitatefutureurbanredevelopment.SimilarmeasuresareproposedalongtheProjectCorridor.
Economicallyefficient:Preliminarycost-benefitanalysesundertakensuggestthat,despitethehighercostofdelivery,rapidtransithasthepotentialtobeeconomicallyviable.RapidtransitmaystillbeviableevenwithoutlanduseandpricingmeasuresbutthesecomplementarymeasuressignificantlyenhancetheprojectedlevelofeconomicreturnsandincreasethelikelihoodoftheProjectachievingitseconomic,socialandenvironmentalaims.
The ACT Government’s commitmentTheACTGovernmentiscommittedtothecontinueddevelopmentoftheProject.Aspartofthe2012–13ACTBudget,theACTGovernmentestablishedtheGungahlintoCityProjectOffice.TheProjectOfficewillensurethattransport,landuseandpublichousingplanninganddevelopmentsareconsideredandimplementedinanintegratedmannerandwillcontinuetomovetheProjecttowardsamoredetailedFeasibility and Forward Design stage.
TherearemanyissuesincludingcostandfinancingthatneedtobeconsideredbytheACTGovernmentand the community before determining which mode is preferred and what circumstances that an investmentmaybemade.Theplanningandfeasibilityworkthatwillbecarriedoutunderagreedfunding from Infrastructure Australia is required for, and will support, either mode.
CommunityconsultationundertakenaspartoftheProjectindicatedastrongcommunitypreferenceforlightrailgivenitsaestheticsaswellasitsgreaterpotentialtofacilitatesignificantmodeshift.TheProjectalsoconsideredbusrapidtransitasitmaydeliveramorecost-effectiveoutcome.Furtherfeasibilityworkhasbeenidentifiedtoinformthesedecisions.
Preliminaryeconomicassessmentsindicatethatundertherightcircumstances,investmentinrapidtransithasthepotentialtobeeconomicallybeneficial.Onthisbasis,thissubmissionproposesthattheCitytoGungahlinTransitCorridorProjectbeconsideredasaprojectwith‘RealPotential’byInfrastructureAustraliaandforfundingfromtheCommonwealthGovernmentona50:50basistoprogress the Project to the detailed Feasibility and Forward Design stage.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 5
1 Introduction
1.1 PurposeTheACTGovernmentisconstantlylookingforwaystoachieveTerritoryandnationalgoalswhich,amongst other things, include encouraging more people to use public transport. Greater public transportusagepotentiallyreducescongestiononroads.Inturn,lowerlevelsofcongestioncanhaveapositiveimpactonaneconomy’sproductivityandcapacity,promotecompetitionandleadtosustainableurbandevelopment.
TheGungahlintoCityCorridor(the‘ProjectCorridor’)hasbeenprioritisedbytheACTGovernmentforrapidtransitinvestment.TheProjectCorridoristheprimarytransportcorridorthatconnectsCanberra’snorthern suburbs with the City and the South, and accordingly is an integral part of the Transport for Canberra’s 2031 Frequent Network.
ServingasCanberra’sfastestgrowingcorridor,theProjectCorridoralreadyexperiencessignificantcongestionissuesduringpeakperiodswhichimpactsadverselyoncarandbustravel.Thissubmissionoutlinestheeconomicpotentialofapackageofmeasuresprimarilyfocusedoninvestmentinrapidtransit with complementary land use and pricing measures to remediate current transport issues that impedetheefficientoperationoftransportandimprovesustainabilityandexpandcapacitytocaterforfuture growth along the Corridor.
Based on the recent feasibility work, this submission proposes that the City to Gungahlin Transit Corridor Project be considered as a project with ‘Real Potential’ and for funding from the CommonwealthGovernmentona50:50basistoprogresstheProjecttoamoredetailedFeasibilityandForward Design stage.
1.2 BackgroundAtitsinception,CanberrawasplannedasapolycentriccitywiththeParliamentaryTriangleandtheCityservingasthecity’sciviccentrewithprovisionfortowncentresatBelconnen,TuggeranongandWoden,GungahlinandWestonCreekastimeprogressed.Parkwaysandrapidtransitlinkswereintendedtobebuilt between each town centre and the City.
WhilsttheparkwaysareingrainedintotheshapeofCanberra,theaspirationofdevelopingtheenvisagedrapidtransitlinkcontinuestothisday.Thissubmissionrepresentsacontemporaryviewoftheviabilityofrapidtransit,buildingonthefindingsofmanystudiesthathavebeenundertakentodateboth within the Corridor and across Canberra.
InitssubmissiontoInfrastructureAustraliain2011,theACTGovernmentoutlineditsintentionstoinvestigatethefeasibilityofdevelopingrapidtransitintheGungahlintoCitycorridor.TheGungahlintoCity Rapid Transit Corridor Project (the ‘Project’) was commissioned subsequently in late 2011 to assess the prospects of rapid transit. As a direct output of the Project, an Outline Business Case was presented totheACTGovernmentforitsconsiderationinApril2012.
UnderliningitscommitmenttodevelopingtheProjectCorridor,theACTGovernmentannouncedinits2012-13Budgettheestablishmentofadedicatedagency,theGungahlintoCityProjectOffice,tofocusonintegratingtheGovernment’spositionontransport,publichousingandlandusepoliciesanddevelopmentswithintheProjectCorridor.
Figure1outlinesthestepsundertakenbytheACTGovernmenttodevelopthematerialtoinformoursubmission to Infrastructure Australia.
ACT Government Environment and sustainable Development Directorate 6
Figure 1: Current Project Status
PreviousStudies
Gungahlin to City Rapid Transit Corridor Study
ACTGovernmentOutlineBusiness Case (April 2012)
Establishment of the Gungahlin toCityProjectOffice(June2012)
Submission to Infrastructure Australia (August 2012)
Thissubmissionrepresentsthenextstepinthedevelopmentoftherapidtransitconcept.ThissubmissionbroadlyreflectsthefindingsoftheOutlineBusinessCase,whichidentifiedtheneedforfurtherrefinementstobeundertakenonthedesignoftheschemeandassociatedcostingsandtoadvancethedemandmodelling.Theeconomicbenefitsandcostspresentedinthissubmissionreflectthoserefinements.
1.3 APackageApproachThissubmissiongoesbeyondsimplyprovidingatransportbasedsolutioninanattempttosolveatransport related problem. This submission presents an assessment of packages, whereby transport based measures are combined with complementary land use measures and parking pricing measures. Table 1 details the scope of each measure:
Table 1: Package Components by Measure
Transport Measures
Forthepurposesofthisstudy,transportmeasuresaredifferentiatedonlybytwoformsofrapidtransit – bus rapid transit (BRT) and light rail transit (LRT).
AsacomplementtoinvestmentsineitherBRTorLRT,designandcostingsalsoallowforimprovementsinpedestrianandcyclewaypathsthatwillenhancelocalaccessibilityandimprovepublic transport accessibility.
Land Use Measures
LandusemeasuresareprimarilyaimedatinvestigatinghowincreasesinresidentialandcommercialdensitieswithintheProjectCorridorwouldassistinnotonlyincreasingpublictransportpatronagebutalsoplacingdownwardpressureonprivatevehicletravel.Incombinationwithtransportmeasures,changesinlanduseprovideaperspectiveontheoftenneglectedlinkbetweenthetwomeasuresandhighlightingtheimportanceofpolicysettingsanditscontributiontoasustainablelong-termoutcome.
Parking Charge Measures
Parkingchargemeasuresrepresentathirdbutimportantprongtobettermanagedemandandensurethatallbeneficiaries,notjustpublictransportusers,contributetothedevelopmentofadditional(public)transportcapacityandtheimprovedoutcomessuchaninvestmentmaybringto both public transport and car users.
Byconsideringtransportinvestment,changesinlanduseandincreasedparkingcharges,therapidtransitoptionsconsideredinthissubmissionpotentiallyprovideanationalshowcasefortransitorientedlandusechanges,withstrongpotentialtofacilitateurbanrenewalintheresidentialandcommercialmarkets along the Corridor.
AlthoughitistypicalofproponentstopresentapreferredoptiontoInfrastructureAustralia,four‘do-something’optionsarepresentedtoInfrastructureAustralia.Thereexistscleartrade-offsbetweenthelevelofcapitalcost,levelofserviceandamenityandthewillingnessofCanberrans,whetherthroughtaxesorusercharges.Giventhesizeofthetrade-offs,furtherinvestigation,thepartialfundingofwhichisthesubjectofthissubmission,toinformthecommunityandstakeholdersofthistrade-off,isdeemedwarrantedbeforefurtherfilteringisundertaken.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 7
Itispertinenttonotethattheurbanrenewalandtransit-orientateddevelopmentparadigmsrunparalleltotheintentionsofthisProject.Authoritiesworldwideareseekingtodeliverimprovedcommunityoutcomesatalocallevelwhilstprovidingtransportconnectivitybyconsolidatingandco-locatingdifferentactivitiesindistinctlocationsandcorridors.Theactivationoftheseconceptsrequiresaproactiveandintegratedapproachbyauthoritiesthatappropriatelymixinvestmentwithpolicymeasurestoachievewelfareoutcomesbeyondthereturnsthatcanbeachievedthroughinvestmentalone.
Apackagedapproachcanmakemoreeffectiveuseofavailableland,supporteconomicdiversityanddevelopment,andimprovesocialequityandliveability,allofwhichresonatecloselywithInfrastructureAustralia’sstrategicgoalstopromotethesustainabledevelopmentofAustraliancitiesandregions.
However,thereexistsapragmaticrationale:theACTGovernmentrecognisesthatarapidtransitinvestmentanditsbenefitsinCanberrasimplycannotmaterialisewithoutarealisticconsiderationtohowitcouldbefundedandhowitmightcontributetothesustainabledevelopmentofthecity.
Acommonthreadthroughpreviousstudiessuggestsatransportonlyapproachresultsinaconundrum.Smallerscaleinterventionslikebuslanesarelikelytodeliverminimalchangesinsustainability.OntheotherhandrapidtransitmaybeeconomicallybeneficialbutgiventhecostandthesmallsizeoftheACTGovernment’sbudget,cannotbefundedjustbytaxpayers.Acohesive,packagedapproachwherebyhigherdensitiescontributetohigherpublictransportdemandandamajorityoffundingisdrawnfrombeneficiaries,istheonlyrealisticmeansbywhichlargescaletransportprojectshaveachanceofbeingdelivered.
ThisOverviewDocumentprovidesasummaryoftheInfrastructureAustraliasubmission.Thesubmissionoutlines,atapre-feasibilitylevel,thepotentialeconomicoutcomesthatmayarisefromanapproachtoinvestinrapidtransitwithcomplementarylanduseandpricinginterventions.
ACT Government Environment and sustainable Development Directorate 8
2 About the Project
2.1 Project ObjectivesThe Project seeks to assess the feasibility of a rapid transit corridor between Gungahlin and the City along FlemingtonRoadandNorthbourneAvenueusingeitherBRT or LRT technologies. It also assesses the impact ofhigherpopulationandemploymentdensities,andhigherparkingchargesontheviabilityofrapidtransitservicesoperatingalongtheProjectCorridor.
TheproposedworksaimtoachievetheProject’sgoals, which include:
• Providegreaterconnectivityandcapacitybetween future growth centres and the City
• Encourage greater use of more sustainable transport modes, such as public transport and activetransport.
• Encouragefurthereconomicdevelopmentwithinthe Gungahlin to CBD corridor.
ThesegoalsweresubsequentlyexpandedintosevenobjectivestoallowforcloseralignmenttoInfrastructureAustralia’s(IA)sevenstrategicgoals:
• Delivering transport capacity by increasing public transport capacity and speeds along theProjectCorridortoservicefastgrowingpopulationlevelsandeconomicactivity
• Supporting Canberra’s corebyimprovingaccessibilityandinturnsupportingCanberra’sroleasthenation’scapitalandpre-eminentfederalpoliticalandadministrativecentre
• Supporting economic diversity and development bypromotinganincreaseinthelevelanddiversityofeconomicactivitybyincreasingthemixandnumberofresidentsandemployment
• Improving equity and liveabilitybyenhancingaccesstokeycentresandcommunityfacilitiesandpromotingabroaderdiversityofhousingandimprovinghomeaffordability
• Maintaining and improving the amenitybyreinforcingthedesignofNorthbourneAvenueconsistentwithBurleyGriffin’soriginalintentionastheprimaryNationalGateway
• Managing road congestionbyincreasingtheattractivenessofnon-carmodestoreducelevelsofcardependencybyprovidinghighqualitypublicandactivetransportinfrastructure
• Creating an environmentally friendly transport systemaimedatreducinglevelsofgreenhousegasemissions,airandnoisepollutionbyreducinglevelsofcardependenceandincreasingthelevelofpublicandactivetransportusage.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 9
2.2 ProposedWorksTheProjectproposesthefollowingcapitalworkswithintheProjectCorridortoachievetheaforementionedobjectives:
• ThedevelopmentofasegregatedrapidtransitcorridorbetweenCityandGungahlinseparatedfromgeneraltraffic
• Supportingoff-roadinfrastructureintheformofbusstationsatCity,DicksonandGungahlintofacilitateinterchangingwiththeexistingACTIONbusnetwork
• WithLRT,LRTspecificinfrastructureincludingrollingstock,signalling,powersupply,substationsanddepots
• Aseparatedoff-roadcyclewayandfootpathsalongthelengthoftheProjectCorridortofacilitateaccessandegressfromthecorridorandtoencouragehigherlevelsofactivetransport.
TheProjectalsoconsiderstheeffectofhigherratesofpopulationandemploymentgrowth,andparkingchargesbasedonlandusepolicysettingswithintheProjectCorridoron:
• Numberofhighdensity,mixeduseresidentialandcommercialdevelopmentsalongNorthbourneAvenueandFlemingtonRoad
• Encouragegreaterretailandcommercialfrontagesadjacenttothekerbsideinappropriatelocations• Increasing parking charges to encourage public transport use and to ensure that the costs of the Project
aresharedbyallbeneficiaries.
2.3 Transport,LandUseandPricingScenariosTheProjectproposesmorethanjustaninvestmentinpublictransportinfrastructure.AspartoftheProject,arangeofcomplementarypolicymeasuresintheformofmaximisingcurrentlandusepoliciesandtakeupandhigherparkingpricinghavebeenconsideredtocomplementtheproposedtransportinvestmentwhichareaimedatmaximisingtheeconomicandfinancialreturnsoninvestment.
Acomprehensiveapproachthatintegratestransportinvestment,landusechangesandpricingisproposedasapragmaticapproachtoaddresstheACTGovernment’sobjectivestoimproveeconomic,financial,environmentalandsocialsustainability.
Accordingly,anumberoftransport,landuseandpricingscenariosweredevelopedandtestedwitheachother.ScenariosconsideredeitherBRTorLRTagainstabusinessasusualbusbasedsystem,maximisedtakeupofresidentialandcommerciallandwithintheProjectCorridor,andhigherparkingchargestoincentiviseashifttopublicandactivetransportandtoensurethatallbeneficiariescontributetothefunding of transport infrastructure.
Thefinaliterationofscenariodevelopmentprocessfilteredallbutthreetransportscenarios,twolandusescenariosandaparkingchargescenario,whichhavebeenassessedinmoredetailandformthebasis of the analysis for the current submission. These scenarios are summarised in Table 2.
Table 2: Shortlisted Scenarios
Transport Land Use Parking Charges
• Business as usual
• BRT
• LRT
• Business as usual
• Higher density
• Increased parking charges in the City as well as other designated Town Centres
ACT Government Environment and sustainable Development Directorate 10
Transport ScenariosBusiness as UsualThe‘businessasusual’transportscenarioassumesthat,apartfromcommittedroadandpublictransportinitiatives,includingthegradualimplementationofthe2031 Strategic Public Transport Plan, no further changes to the network are proposed.
ImprovementsinpublictransportwillstillbemadeacrossCanberraunderthebusinessasusualcasealthoughnosignificantchangesareproposedalongtheProjectCorridor.Thebusinessasusualscenarioisbasedonthe2031StrategicPublicTransportPlan,thecornerstoneofwhichwillbetheintroductionofhighfrequencyservicesprovidedalongtheidentifiedFrequentandRapidcorridors.Underthisscenario,thecurrentlimitedstopRedRapidservicethattravelsbetweenGungahlinandFyshwickviatheCitywillcontinuetobetheprimarypublictransportlinkbetweenGungahlinandtheCity.
WhiletheStrategicPublicTransportPlanwillbringaboutabetterleveloflegibilitytothepublictransportnetwork,itshouldbenotedthatbusserviceswouldcontinuetoshareroadspacewithgeneraltrafficalongtheProjectCorridor,whichisexpectedtobecomeincreasinglycongestedovertime.Figure2depictstheexistingalignmentsoftheProjectCorridorunderthebusinessasusualtransportscenario.
Figure 2: Business As Usual Northbourne Avenue
Flemington Road
Source: DCM & URS
Bus Rapid TransitUnlikeconventionalbusservices,BRTsystemstypicallyoperateondedicatedlanesandcorridors,separatedfromotherformsofroadtraffic.TheSouthEastBuswayinBrisbaneisanexampleofaBRTsystem (see Figure 3).
Figure 3: South East Busway in Brisbane
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 11
Theseparationofservicesfromgeneraltrafficallowsforhighertravelsspeeds,improvedservicereliabilityandincreasedfrequenciesrelativetoconventionalbusservices.BRTsystemsalsoallowoperationstobeintegratedwithabroaderbusnetworkbyconnectingBRTserviceswithfeederservicesorallowingconventionalbusroutesuseaportionoftheBRTcorridor.
UndertheBRTscenario,newbuslaneswouldbeconstructedinthemedianalongNorthbourneAvenueandFlemingtonRoad.Inaddition,busbayswouldbeconstructedalongtheCorridortoallowlimitedorexpressservicestobypassotherstoppingbusservices.Itisintendedthatconventionalbusserviceswould also be able to make use of these dedicated bus lanes. Figure 4 depicts the design and alignment ofNorthbourneAvenueandFlemingtonRoadunderthisscenario.
Figure 4: Project Corridor Cross Section under BRTNorthbourne Avenue
Flemington Road
Source: DCM & URS
NewstationswouldbeconstructedatGungahlin,DicksonandCivictofacilitateinterchangingwiththeexistingACTIONbusservices.Thecorridorwouldallowfor15stopsbetweenGungahlinandCivicandbeintegratedwiththeexistingNo.200route(knownasRedRapid)fromthereonwards.Itisexpectedthatthisservicewilloperateatfiveminuteintervalsduringpeakperiods.
Forplanningpurposes,constructionisassumedtotakethreeyearsafterthecompletionofforwarddesign and procurement.
Light Rail TransitLRTisanalternativeformofrapidtransit.Ittypicallyhasalowercapacityandspeedthanthatofconventionalheavyrailandmetrorailservicesbuthighercapacityandspeedoftraditionalstreet-runningtramservicesaswellasconventionalbusservices.ThemainbenefitofanLRTsystemisthatitprovideshigherlevelsofamenity,travelspeed,reliabilityandcapacitycomparedtoconventionalbusandtramserviceswithinanurbanenvironmentwithoutthehighcostsassociatedwithconventionalheavyrailsystems.
ACT Government Environment and sustainable Development Directorate 12
Thishigherlevelofserviceisachievedbythroughtheuseofdedicatedrailcorridorsseparatedfromothervehiclestraffic,whilestillbeingabletorunon-streettoprovideimprovedaccessibilitythroughmajoractivitycentres.AkeyfeatureofLRTsystemsistheabilitytointegrateLRTinfrastructureandoperationswithinanexistingurbanenvironment,allowingforthepossibilityofpromotingfurtherurbandevelopment.Figure5andFigure6illustrateLRTinAdelaiderunningonbothdedicatedtrackaswellason-street.
Figure 5: Adelaide Metro Light Rail Service Running on Dedicated Track
Figure 6: Adelaide Metro Light Rail Service Running On-Street in Glenelg
The LRT scenario would be based on a similar treatment used with BRT in that the light rail corridor wouldbebuiltinthemedianalongNorthbourneAvenueandFlemingtonRoad.LightrailtrackswouldbeembeddedintotheroadsurfacealongNorthbourneAvenuetoallowforthesharingbetweenlightrailandbuses.AlongFlemingtonRoad,onlylightrailserviceswouldoperateinthemediantomaximisetherunningspeedoflightrailservices.Figure7depictsthedesignandalignmentofNorthbourneAvenueandFlemingtonRoadunderthisscenario.
Figure 7: Project Corridor Cross Section under LRTNorthbourne Avenue
Flemington Road
Source: DCM & URS
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 13
NewstationsatGungahlin,DicksonandCivicwouldbedevelopedtosupportinterchangeswithconventionalbusservices.ThenewlightrailservicewouldreplacetheexistingRedRapidservicebetweenGungahlinandCivicandbeintegratedwiththeremainingRedRapidroutefromthereonwards.Itisexpectedtooperateatsevenandhalfminuteheadwaysduringpeakperiods.
Aspartofthisoption,supportingoperatinginfrastructurewouldbedevelopedincludingrollingstock,signalling,powersupply,substationsanddepots.Forplanningpurposes,constructionisassumedtotakethreeyearsafterthecompletionofforwarddesignandprocurement.
Land Use ScenariosShouldtheinvestmentsintransportinfrastructurebesufficientlyattractivetopotentialusers,theinvestmentsthemselvescouldgeneratechangesinlanduse.TheProjectislikelytoimproveaccessibilitythroughreducedtraveltimes,decongestionandimprovedtraveltimereliability.Inturn,improvementsinaccessibilitymaydrivelandusechanges.Peopleandindustriesmaychoosetomovethelocationoftheirresidence,employment,businesscentresandaltertheirlogisticschainstotakeadvantageoffastertraveltimesandimprovedaccessibility.Accordingly,transportinvestments,inparticularlightrailinvestments,mayresultinredevelopmentaroundstations.
Alternatively,evenwithoutsignificantchangestoexistingplanningcontrols,theProjectCorridorhasanumberofpropertiesthatcouldberedevelopedtosupporturbandensification.Forinstance,theACTGovernmentownsthemotorregistryandtouristinformationsiteatDicksonaswellaspublichousingcomplexesalongNorthbourneAvenue.TheeventualredevelopmentofwhichwouldfallwithintheremitofthenewlyestablishedGungahlintoCityProjectOffice.
TheintertwinednatureoftheissuesfacingtheProjectCorridormeanthatanintegratedtransport-landuseapproachislikelytooptimisetheeconomicoutcomesofinvestmentsintheProjectCorridor.Twolandusescenariosweredevelopedtoreflectpossibleurbanoutcomesfromgovernmentintervention,whetherthroughinvestmentintransportorthroughchangesinlandusescenarios–a‘businessasusual’ outcome or a higher density scenario.
Business as UsualThe‘businessasusual’landusescenarioisbasedoncurrentACTGovernmentpopulationandemploymentprojections,whichareusedforwholeofgovernmentdecisions.CurrentGovernmentprojectionsassumethatthecombinedACT–Queanbeyanpopulationwouldexceed500,000peopleby2031.QueanbeyanpopulationisincludedbecausethetransportnetworkmodelincludesQueanbeyan.
Tocaterforfuturepopulationgrowth,historicdevelopmentpatterns(mainly‘greenfield’developmentinthedistrictsofMolonglo,OuterGungahlinandQueanbeyan)wouldcontinueintothefuture.Underthisscenariothereisnosignificantchangetolandusepoliciesandplanningcontrolsinthestudyarea.
Higher DensityThehigherdensitylandusescenarioassumeshigherresidentialandcommercialdensitiesthroughafasterrealisationoftheProjectCorridor’sdevelopmentpotentialwithoutchangestoexistinglandusecontrols or policies in the Territory Plan. The urban outcomes implied by the scenario may arise through amarketresponsetotransportinvestment,aswellasthroughadjustmentsinlandusesettings,urbanrenewalprogramsorthroughacombinationofthesefactors.
The scenario allows for recent amendments in planning controls for: Dickson, Gungahlin Town Centre, InnerNorthurbanhousingandCityarea(ANUExchangeandGriffinLegacy).Underthehigherdensityscenario,populationandemploymentlevelswouldbe38%and21%higherthanunderthebusinessasusual land use scenario within the Project Corridor by 2031.
TheHigherDensitylandusescenarioassumesthattotalACT-Queanbeyanpopulationandemploymentlevelsremaininlinewiththatofthe‘businessasusual’landusescenarioforconsistency.Accordingly,higherdensitieswithintheProjectCorridorarebasedonaslowerreleaseofgreenfieldlanddevelopments.
ACT Government Environment and sustainable Development Directorate 14
Increased Parking ChargesTransportinfrastructuredevelopmentshouldnotonlybeconcernedwiththeprovisionofcapacitybutalsoeffectivemanagementoftransportdemand.
CanberrahasthelowestparkingratesamongstAustraliancapitalcities.ColliersInternationalestimatedthatdailyratesinCanberraat$10.Bycomparison,theaveragerateacrossAustraliancitieswas$39perdaywithSydneyandMelbournehavingthehighestratesat$64and$66respectively1. Low parking fees encouragesprivatevehicleuse,whichimposesarangeofcostsonsocietyandinfrastructure.
Theuseofparkingchargesisonerealisticleverthatwasconsideredtoincentiviseagreateruseofpublictransport.Arevisioninparkingratescouldprovidethefollowingoutcomes:
• EncourageagreateruseofpublicandactivetransportalongtheProjectCorridor
• EnsurethatallbeneficiariescontributetothecostoftheProject• SecureanadditionalfundingsourcefortheProject
ProvidinghigherparkingfeesarecapturedbytheACTGovernmentandhypothecatedtowardsimprovingtransport,thereexistsopportunitiesforpositivedialoguetodiscussthepotentialforabroaderbasedapproachtofundingrapidtransit.Forinstance,thecommunityconsultationprocessfortheACTGovernment’sTimetoTalkCanberra2030revealedthatCanberra’sresidentswerereasonablywellinformedwithrespecttotheneedforwiderpublictransportoptionsandthetrade-offsrequiredtodelivertheseoptions.Surveyparticipantsdiscussedtrade-offstheywouldbewillingtoacceptincludingtheincreaseofparkingchargestomoderateprivatevehicleuse2.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 15
3 Alignment with Government Objectives
3.1 Alignment between ACT and Commonwealth Government ObjectivesThedevelopmentoftheProjecthasgivendueconsiderationtohowtheProjectalignsnotonlywithACTGovernmentstrategicconcernsbutalsohowtheProjectalignswiththeobjectivesofthenation.TheACTGovernmentbelievesthatthereisastrongandsignificantalignmentbetweentheProjectandanumberofobjectives,principlesandstrategiesputforwardbythefollowingnationalandterritorypolicies:
Ofnote,theProjectalignswellwithanumberofInfrastructureAustralia’sStrategicPriorities.ThesesevenStrategicPrioritiesconcernthemselveswith:
• TheexpansionandincreaseofAustralia’sproductivity
• DiversificationofAustralia’seconomiccapabilitiesandthedevelopmentofcitiesandregionstobuildonthenation’sglobalcompetitiveadvantage
• Improvementofsocialequityandqualityofoutcomes,includingthereductionofgreenhouseemissions.
TheseStrategicPrioritiesultimatelyinformedtheneedforstrategiestoencouragebetterplanningandgovernance,andreducingthemultiplicityofrulesandregulationsfromadecisionandpolicymakingperspective.Italsoinformedtheneedtoenhanceinternationaltradethroughimprovingexportcapacityandreducingthelossofproductivityincapitalcitiesduetoageingtransportnetworks.
ACT Government Environment and sustainable Development Directorate 16
Table3demonstratesthelinkagesbetweentheobjectivesdefinedfortheProjectwithTerritoryandCommonwealthGovernmentobjectives.
Table 3: Alignment of Project, Territory and National Objectives
IA Objective Territory Objective Project Objective
Expand Australia’s productive capacity
Managing growth responsibly and sustainably by taking a regional approachtourbansettlementaspartofthe ACT Planning Strategy.
Delivering transport capacity TheProjectaimstoincreasestravelspeeds,reliabilityandfrequencyofpublictransportservicesalongtheProjectCorridor,ultimatelyaimedatprovidingcapacityforgrowingactivitycentresandcaterforpopulationgrowth.
Increase Australia’s productivity
ACT’s Planning Strategy aims to improvepeople’smobilityandcreatingmorechoicesintravelbyintegratinginvestmentinCanberra’stransportnetworkswiththelanduseitservicestoenhanceproductivityonexistingassets.
Managing road congestion TheProjectaimstoreducelevelsofcardependencyandincreasepublicandactivetransportmodeshares by increasing the frequency, reliability and speedofpublictransportservicesandthroughtheprovisionofhighqualitywalkingandcyclinginfrastructure.
Diversify Australia’s economic capabilities
The ACT Planning Strategy’sobjectiveonimprovingthemobilityofpeopleandincreasingtravelmodeoptionswillbesupportedthroughanintegrationofinvestmentinCanberra’stransportnetworks with the surrounding land use itservices.
Supporting economic diversity and development TheProjectaimstocontributetothediversificationanddevelopmentofeconomicactivitybyenhancingthe role of town and group centres located along the Project Corridor.
Build on Australia’s global competitive advantage
Creatingamoreprosperousregionbypromotingthestrengthsofaclean,knowledge based economy is part of the ACT Planning Strategy which is alignedwithAustralia’svisionforamoreefficientandsustainableeconomyin the future.
Supporting Canberra’s core TheProjectaimstoimproveaccessibilitytotheCityandtheParliamentaryTrianglebyprovidingfasterandmorefrequentservicestotheCityandimprovingconnectionstoongoingdestinations.
Develop our cities and/or regions
Theimplementationofthe2031 Strategic Public Transport Plan will facilitateincreasesindensitiesinestablished town centres and along key transport corridors. This will support the ACT Planning Strategy’s objectiveof taking a regional approach to urban settlementtopromoteresponsibleandsustainable planning.
Maintaining and improving the amenity of Northbourne Avenue The Project seeks to reinforce the linear alignment ofNorthbourneAvenuebymaintainingtheavenueof trees and adding the permanency of dedicated bus lanes or light rail tracks and retain Northbourne Avenue’sroleastheprimaryNationalGateway.
Reduce greenhouse emissions
Transport for Canberra’s Frequent Network includes a commitment for theintroductionofanenvironmentallyfriendlypublictransportfleettoreduce greenhouse gas emissions and particulates.
Creating an eco-friendly transport system Byreducinglevelsofcardependence,increasinglevelsofpublicandactivetransportusageandchanging the urban form, the Project aims to reduce levelsofgreenhousegasemissions,airandnoisepollution.
Improve social, equity and quality of life in our cities and regions
The ACT Planning Strategy calls for buildingthecapacitytoimprovingthequality of the public realm and access toservicesandinformation.Thiswillprovidemorelifestyleopportunitychoices as it aims to renew town centres as the hub for community life.
Improving equity and liveability The Project aims to enhance access to key centres andcommunityfacilitiesthroughimprovedpublicandactivetransport,relieduponbythelesswelloff,thedisadvantagedandtheelderly.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 17
3.2 Alignment with Nation Building Program 2NationBuildingIIistheCommonwealthGovernment’snextstepindevelopingthenation’sinfrastructurenetwork.NationBuilding2placesasignificantemphasisonimprovingAustralia’sproductivitywithanoverarchingobjectiveisto“liftAustralia’sproductivitythroughnationallysignificantlandtransportinfrastructure”.Beginningin2014–15,NationBuilding2willbuilduponthefirstphasebycontinuingtoprovideasolidfoundationforaddressingAustralia’stransportinfrastructureneedsgoingforward.
NationBuilding2identifiesfourkeyinvestmentthemes,allaimedatimprovingtheproductivityofAustralia’seconomythroughinvestmentininfrastructureandthroughusingassets,bothnewandexisting,better.Thesefourthemes,ofwhichthisProjectdirectlyaddressestwo,are:
1. Connecting peoplebyencouragingreliableandefficientlandtransportinfrastructuretoconnectpeopleacrossthenation
2. Innovationthroughenhancements,plansanddevelopmentstocurrentandfuturelandtransportnetworks
3. Moving freightbysupportingeconomicgrowththroughefficientandconnectionfreightnetworks
4. Safetybyimprovingthesafetyandsustainabilityofnationalrailandroadnetworks
Connecting PeopleTheAustralianGovernmentwantstoensurethatnational,urbanandregionalroadandraillinksaremaintainedinanefficient,productiveandsustainablemanner.The‘ConnectingPeople’themehasthefollowingobjectives:
• Connecting cities–toimprovetheconnectivitybetweencitiesandmajorpopulationcentres
• Urban living –toenhanceurbanliveabilityandaccesstoessentialservices• Pinch points–toincreasecapacityandefficiencyandreducecongestioninurbanareas
TheProjectisdirectlyaimedatimprovingconnectivitybetweenkeycentresandactivitygeneratorsin Canberra including Gungahlin, Mitchell, Dickson and the City by bypassing current and emerging pinchpointsalongtheProjectCorridor.Indirectly,theProjectwillimproveconnectionstoothercentresincludingBarton,Woden,TuggeranongandQueanbeyanbyfacilitatingandexpeditingthemovementofcross-regionalRapidservicesbetweenGungahlinandtheCity.
TheProjectaimstoenhanceurbanlivingbynotonlyimprovingaccessibilitytoemployment,educationcivicactivitiesandotheressentialservicesbutalsobyincreasingthedensityandmixofresidentialandcommercialactivitiesalongtheProjectCorridor.
InnovationAkeyelementoftheProjectistheintegratednatureinwhichlanduseandtransportsettingswillbedelivered.Foreconomicviability,theProjectislikelytorequirethedeliveryofhigherdensitieswithintheProjectCorridoroveralongperiodoftime.Governancestructurestoensureprogresstowardsthisobjectivearesomewhatunique.Asafirststep,therecentlyestablishedGungahlintoCityProjectOfficeiswellpositionednotonlyintegratetransportandlanduseplanningbutalsoensuretherealisationofthe requisite transport and land use outcomes.
3.3 National Capital PlanAlthoughplanningwiththenation’scapitallargelyresideswiththeACTGovernment,theCommonwealthGovernmentstillplaysaroletoensurethatCanberra’simageandpositionasthenation’scapitalisupheld.TheCommonwealthGovernment,throughtheNationalCapitalAuthority,outlinesitsplanningintentionsandcontrolsthroughtheNationalCapitalPlan.
ACT Government Environment and sustainable Development Directorate 18
TheNationalCapitalPlanaimstoensurethatCanberraisplannedanddevelopedinaccordancewithitsnationalsignificance.TheNationalCapitalPlanidentifiesNorthbourneAvenueasaMainAvenueandNationalApproachRoute.Assuch,theobjectiveforitsplanninganddevelopmentistoestablishandenhancetheidentityoftheapproachestotheCentralNationalAreaasroadsofnationalsignificanceand,whererelevant,asfrontageroadsforbuildingswhichenhancetheNationalCapitalfunctionandascorridorsforapossiblefutureinter-townpublictransportsystem,improvingpublictransportalongtheCorridor,promotingmorediverseurbandevelopmentandreducingpressureonyettobedevelopedgreenfieldresidentialsites.
3.4 ACT Government ObjectivesTheCitytoGungahlinProjectCorridorresonatesstronglywithcurrentACTGovernmentpolicyandobjectivesontransportandplanning.
Transport for Canberra TransportforCanberraistheACTGovernment’sstrategyforamoreeffectiveandefficienttransportsystemtomeettheneedsofthecommunitywhilereducingtheenvironmentalimpactsoftransport.Itsproposed policies for 2011 to 2031 build on the 2004 Sustainable Transport Plan and are aligned with thedraft2011ACTPlanningStrategy.
Theseincludefurtherreductionintrafficcongestionandgreenhousegasemissionswhilecontinuingtoincreasetheuseofactiveandpublictransportfrom20%in2011to23%in2016and30%in2026.Thestrategyaddressesfourbroadcategoriesofpublictransport,activetravel,managingroadsandvehicles,andmanagingtraveldemand.
The cornerstone of the Transport for Canberra Plan is the establishment a public rapid transit system capableofoperatingservicesat15minute(orbetter)intervalsalldaythroughmaincorridorsbasedonthe 2031 Strategic Public Transport Plan Network.TheProject,shoulditbedeveloped,wouldbepartofthefirststageofawiderrapidtransitsystemidentifiedbyTransportforCanberrathatwillconnectmajoractivitycentressuchas,Belconnen,Barton,andWodenwithCity.Theserapidtransitrouteswillbecriticalinachievingametropolitan-widepublictransportnetworkastheywilllinkwithFrequentLocallinesinmanyoftheseactivitycentrestoformtheplannedFrequentNetwork.
ACT Planning Strategy ThedraftACTPlanningStrategyproposesninestrategiestodeliverthecommunity’s‘desiredfuturescenariofor Canberra’ (through Time to Talk Canberra 2030),whiletakingintoaccountrecentdevelopmentsandevidencearisingfromresearchandimplicationsofchallengesahead,suchasclimatechange.
Thekeytargetofthestrategyistoachieve50%ofnewhousingtobeestablishedwithintheurbanareaofCanberrasoastosupportotherACTGovernmentpolicyoutcomes,includingthelegislatedgreenhouse gas emissions target for 2060.
TheProjectwouldsupportthecreationofopportunitiesforincreaseddensityanddispersedemploymentbyleveragingoffexistingstructuresofactivitycentresandinter-towntransportconnections.ItwouldalsoalleviatemobilityconcernsandcreatemorechoicesfortravelbyintegratinginvestmentinCanberra’stransportnetworkswiththelandusesitservices.
ACT Government Priorities 2011–122011–12governmentprioritiesforimprovingaccesstoanduseofpublictransportincludethedevelopmentofafeasibilityandproposalstudyforNorthbourneAvenuerapidpublictransportoptions,includinglightrail.Thesestudieswerecompletedin2011(NorthbourneAvenueBusPriority,CyclewayFacilityandDicksonBusStationFeasibilityStudyandNorthbourneAvenueTransportCorridorFinalProposalReport).
Thisbusinesscasebuildsonthesestudies,asthenextstepinimplementingthefirststageoftheRapidnetworkenvisagedintheStrategicPublicTransportNetworkPlan.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 19
4 ProblemIdentification,AssessmentandAnalysis
4.1 IdentificationandAssessmentAspartoftheProjectStudy,arangeofunderlyingtrendsandissueshavebeenidentifiedthatarecurrentlyorexpectedtoimpacttheProjectCorridorandthereforeaffecttheattainmentofGovernmentobjectives.ThefollowingsectionprovidesabriefoutlineoftheproblemswithintheProjectCorridor.
Rapid Population GrowthThe districts of Gungahlin and North Canberra, both of which surround the Project Corridor, are home tothefastestandhighestlevelsofpopulationgrowthwithaverageannualgrowthratesoutstrippingtheCityaverage(seeTable4).3
Table 4: Population Growth by District
District (SSD) 2001 2011Average Annual Change
Growth Growth Rate
North Canberra 38,585 49,674 1,109 2.6%
Belconnen 85,601 94,947 935 1.0%
Woden Valley 32,494 34,530 204 0.6%
WestonCreek-Stromlo 23,662 23,760 10 0.0%
Tuggeranong 90,875 88,382 (249) (0.3%)
South Canberra 23,324 26,880 356 1.4%
Gungahlin-Hall 24,398 47,067 2,267 6.8%
ACT 319,317 365,621 4,630 1.4%
Queanbeyan 41,598 52,620 1,102 2.4%Source: ABS Cat. No 3218.0.
ThesehighlevelsofgrowthareexpectedtocontinueandcurrentforecastssuggestthatthepopulationlevelintheGungahlindistrictcouldreach90,000by2031,or91%higherthanin2011.4
ItisnotunreasonabletoconcludethatNorthbourneAvenuewouldcaterforasignificantshareoftheprojectedgrowth.Givencurrentinfrastructure,thelikelyincreaseintrafficvolumesasaresultofthisgrowthwilllikelybelargelydrivenbyprivatevehicles.Apartfromtheresultantcongestion,thisoutcomewouldhaveanegativeimpactonthegovernmentpolicyofachievinghigherpublicandactivetransportmode shares along the Project Corridor.
TheProjectaimstoincreasepublictransportservicesandqualityalongtheCorridor.ThiswouldplayacriticalroleinensuringthattransportsupplyisabletocopewithfastgrowingpopulationlevelsandeconomicactivityinmajoractivitycentresalongtheCitytoGungahlinCorridor.
High Car Dependency and Poor Public Transport UsageJourney-to-Work(JTW)dataindicatesthatCanberrahasahighlevelofcardependency.Privatevehicleasthepreferredmodetoworkhasmaintainedamodesharegreaterthan80%between1976and2006(seeTable5).WhiletheProjectCorridorboaststhesecondhighestlevelofpublictransportinCanberra,onaverage,thisdecreasessignificantlyclosertoGungahlinwherenineoutofevery10tripsismadebycar.5
ACT Government Environment and sustainable Development Directorate 20
Table 5: Canberra Journey to Work Mode Share 1976 – 2006
Mode 1976 1981 1986 1991 1996 2001 2006
Cardriver 71.3% 70.9% 72.6% 70.7% 72.7% 73.9% 73.5%
Car passengers 13.8% 12.4% 11.4% 12.1% 10.2% 9.4% 8.7%
Sub-total: private transport 85.1% 83.3% 84.0% 82.8% 82.9% 83.3% 82.2%
Public transport 8.9% 9.9% 9.7% 9.9% 8.3% 6.7% 7.9%
Bicycle only 0.9% 2.1% 2.1% 2% 2.2% 2.3% 2.5%
Walk only 4.6% 4.0% 3.6% 4.0% 4.3% 4.2% 4.9%
Other modes 0.5% 0.6% 0.6% 1.4% 2.3% 3.5% 2.4%Source: ACTPLA (2009)
Byimprovingthequalityofpublictransportservicesandreducingoveralltraveldistancesandtimes,theprojectaimstoincreasetheattractivenessofpublictransport(andactivetransport).ThiswouldcontributetoareductioninthelevelofprivatevehiclerelianceinCanberra.ThroughmoreintensivedevelopmentoftheProjectCorridor,whichwillbeenabledthroughhighertransportcapacity,thereexistsanopportunitytoaccommodatefuturepopulationgrowthandeconomicdevelopmentinamoresustainablemannerandreducerelianceongreenfielddevelopment.
Growing Road CongestionHighpopulationgrowthinconjunctionwithhighlevelsofprivatevehicleswillresultinincreasedtrafficvolumes.Duringpeaktraveltimes,sectionsoftheProjectCorridorparticularlyNorthbourneAvenue,arealreadycongestedoperatingclosetocapacity.Basedoncurrenttrafficconditions,roadcongestionaddsapproximately15minutestoacartripduringpeakperiods.Thisconstraintisevidentbylongqueuesanddelaysthatcurrentlyexistalongthecorridorduringpeakperiods(seeFigure8).
Figure 8: Congestion on Northbourne Avenue during the Morning Peak
Source: ESDD
ESDDestimatewithinvestmentinBRTorLRT,currentdelayscouldbereducedbymorethanhalfasshowninFigure9,abenefitthatcouldbeexpectedtogrowovertimeshouldaninvestmentinrapidtransit be made.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 21
Figure 9: Estimated Peak Period Delays for a Trip between Gungahlin and the City for General Traffic
02468
1012141618
Current with BRT with LRT
Peak
Per
iod
Dela
y (m
in)
Source: ESDD
Trafficcongestionisnotonlyanirritantforresidentsbutitalsoimpactsnegativelyonthecostsofdoingbusinessthroughlongertraveltimesandunreliabilitywhichaffecteconomicactivityandproductivity.Roadcongestionalsoimpactsontheefficiencyandattractivenessofroad-basedpublictransportsystems, of which, Canberra is likely to rely on for the foreseeable future.
WithlimitedbusprioritycurrentlyprovidedwithintheProjectCorridor,roadcongestionimpactsadverselyontheefficiencyofbusoperations.Figure10belowillustratedincreasesinbustraveltimesalongtheProjectCorridorduringpeakperiods.Itshouldbenotedthattimetabledtimesdonotincludeunexpectedtraveltimewhichwouldlikelyincreaseaveragetraveltimesfurther,particularlyduringthepeak.
Figure 10: Red Rapid Route 200 Gungahlin to Civic: Current Timetabled Travel Times
0:00
Departure Time
0:05
0:10
0:20
0:15
0:25
0:30
0:35
0:40
7 AM
Trav
el T
ime
8 AM
9 AM
10 A
M
11 A
M
12 P
M
1 PM
2 PM
3 PM
4 PM
5 PM
6 PM
Source: ACTION Buses (2011)
TheimpactofcongestiononbusesisnotlimitedtoresidentslivingalongtheProjectCorridor.NorthbourneAvenueisakeybuscorridorandactsasatrunkformostbusservicesoriginatinginCanberra’snorthernsuburbsandsouthofLakeBurleyGriffinasfaroutasTuggeranongandFyshwick. As the Transport for Canberra 2031 Strategic Network Plan,whichenvisagedmorecross-regional(Rapid)busservicestooperatealongthecorridorfromdestinationsincludingQueanbeyanandMolongloValley,theimpactsofcongestionintheProjectCorridorwillbroadenovertime.Inshort,congestionintheProjectCorridorhasabroadimpactonmanyresidentsacrossCanberra.
Byincreasingtheattractivenessofnon-carmodesthoughincreasingthefrequency,capacity,reliabilityandspeedofpublictransportservicesandthroughtheprovisionofhighqualitywalkingandcyclinginfrastructure,theProjectcanbeaneffectivefacilitatortomanagingcongestion.
ACT Government Environment and sustainable Development Directorate 22
Low Land Productivity Fromaninternationalstandpoint,Australiancitypopulationdensitiesarelowerthanthatoftheirglobalcounterparts–theytendtobemorespreadoutintermsofurbansettlement.ThisisespeciallythecaseforCanberra.Alowerpopulationdensityhasseveraleconomicandsocialimplications.
Onaverage,itwouldtendtoresultinahigherpercapitacostforprovidingpublictransportandcommunityservicesLowerdensitiesincreasetheriskofsocialexclusionasappropriatepublicservicesmaybelessaccessibletoresidents.FortheACTGovernment,lowerdensitiesadverselyimpactthepotentialyieldonpropertybasedcharges,akeyconcernastheACTGovernmentreliesonpropertyrelatedchargesforhalfofitsannualrevenue.
TheProjectwillpromoteanincreaseinthelevelanddiversityofeconomicactivityalongtheProjectCorridorintheCity,alongNorthbourneAvenueandinkeytowncentresincludingDicksonandGungahlinbyincreasingthemixandnumberofresidentsandemploymentpositionsaswellasbyimprovingpublictransportaccessibilityalongtheProjectCorridor.
Employment and Population MismatchAlthoughplanningpoliciesinCanberrahavesoughttoincreaseself-containmenttoreducedemandforlongerdistancetravel,itisapparentthatthespatialdistributionofemploymentissuchthatinmostareasinCanberra,itisdifficulttoachievehighlevelsofself-containment.
MostdistrictsinCanberrahaveinsufficientemploymenttocaterforallworkingageresidentsandmoreover,manyofthesepositionsaretakenbyresidentslivinginotherdistricts.OnlyinNorthCanberra, South Canberra and Woden districts, the centre of Canberra, are there more employment positionsthanresidents.Table6outlinesthenumberofjobsperpersonineachdistrictandtheproportionofjobsprovidedwithineachdistricttakenbydistrictresidents.
Table 6: 2006 Employment Outcomes by District
District Number of Jobs per Person Proportion of District Jobs Taken by District Residents
North Canberra 2.55 23%
South Canberra 3.68 14%
Woden 1.30 23%
Weston 0.36 42%
Belconnen 0.55 61%
Tuggeranong 0.33 73%
Gungahlin 0.39 43%
Queanbeyan 0.56 58%Source: ACTPLA (2009)
Withoutsignificantchangesinhowemploymentisdistributedacrosstheterritory,norealisticlandusescenariocanbeexpectedtoprovidesignificantgrowthinemploymentattowncentres.
Hence,itislikelythatresidentslivingonthenorthernendoftheProjectCorridorwillgenerallyneedtotraveltowardstheCityinordertoseekemploymentfortheforeseeablefuture.Growingcongestiononkey transport links to employment in the City and the Parliamentary Triangle will increasingly inhibit the efficientmovementoflabourtotheseimportantemploymenthubs,decreasingtheproductivecapacityof the city.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 23
High Greenhouse Gas IntensityGreenhousegasemissionsintheACTarerelativelyhigherasaresultoflowresidentialdensitiesandtheassociatedprevalenceofdetacheddwellingsincreasingtheenergyintensityofhouseholds.Furthermore,theACT’shigherlevelofcaruseandresultantlowutilisationofpublicandactivetransportcombinetoincreasecarbonemissionsfromoverallvehicleuse.Withoutintervention,increasingtrafficvolumesandcongestion,arisingfromhighpopulationgrowth,willcombinetoincreasetransport-relatedemissionsevenfurther.
Byreducinglevelsofcardependence,increasinglevelsofalternativetransportusageandinterveningonCanberra’surbanform,theProjectaimstoreducelevelsofgreenhousegasemissions,airandnoisepollution.
Diminishing Corridor AmenityAsoneofthefirstimpressionsfornewvisitorsenteringCanberra,itsdesignandtreatmentsetsthetoneforthecity’scharacter.ItisalsoCanberra’skeycommercialaddressforapartmentsandbusinessesalike,servingavarietyoflanduses.Thereforethequalityofitsurbanenvironmentcanbeconsideredtobeimportant.
AlthoughNorthbourneAvenueprovidessomeformofcapacityforallmodesoftransport,theattractivenessofnon-carmodesissomewhatlimited.Combinedwithahighlevelofcarusageandcongestion,thewalking(andforpublictransportusers,thewaiting)environmentiscompromised,duetoexposuretohighlevelsoftrafficandassociatednoise,accidentsandpollutants.Insuchacardominatedspace,itcanalsobecomequitedifficulttodevelopurbanformsthatencouragethedesiredfuturecharacteroftheAvenueasaplaceofactivityandvibrancy.
TheProjectaimstoimproveaccessibilitytotheCityandtheParliamentaryTrianglebyprovidingfaster,morefrequentserviceswithhigherlevelsofcapacityandinturnsupportingCanberra’sroleasthenation’scapitalandpreeminentfederalpoliticalandadministrativecentreaswellastheCityCentre’srole as the preeminent municipal commercial centre.
4.2 AnalysisThereareamyriadofcurrentandfuturechallengesduetorapidpopulationgrowthanditsassociatedimpacts.Manyoftheissuesexploredinthissubmissioncanbetracedbacktotheplanninganddeliveryof both land releases and transport in Canberra.
Urban PlanningCanberrawasoriginallyplannedasapolycentriccitywhereplannersintendedforresidentstoworkandliveinthesametowncentre,reducingtheneedforlongerdistancetravel.PriortoWWII,muchofCanberra’sdevelopmentwasconfinedtothedistrictsofNorthandSouthCanberralocatedclosetothecity.
Overtime,largequantitiesofaffordablelandwerereleasedonthefringesofthecity.Althoughtheintentionwastolinkoutlyingsuburbstotowncentresthatwouldprovideemployment,shoppingandcommunityservices,employmentdidnotdecentraliseandlittleinvestmentwasmadeinhighcapacitypublictransportlinksthatwouldhaveotherwiseconnectedthesuburbstothetowncentresandtheCity.
Instead, employment agglomerated in the City and Parliamentary Triangle, requiring the workforce totravellongerdistanceseitherbycarorusingbusservices,whichoperatedatlowfrequenciesandstruggletomatchthefasterspeedsofcartravel.
ThisoutcomeisnotanunfamiliaroutcomeinanAustraliancontextalthoughevenbyAustralianstandards,densitiesinCanberraarelow.Lowdensitylivingtendstoleadtolongerjourneysthatarespreadoveragreaterarea.Thesetypesoftripsaremoredifficulttoservethroughpublictransport.
Whiledensityisnottheonlyfactortosupportpublictransport,mixedusedevelopmentsandhigherdensity housing along public transport corridor will mutually support each other.
ACT Government Environment and sustainable Development Directorate 24
Integratingthesetwoaspectswiththepublictransportcorridorimprovementwillsignificantlycontributetosustainability,productivityandsocialbenefits.
Road Focused InvestmentsTraditionally,governmentinvestmentintransporthasfavouredasupply-sideapproachforroadinfrastructure.Thisisduetothehighdemandforprivatemotorvehicles,itscost-effectivenessinconnectingnewresidentialestatesandtherelativelimitedrecurrentcostsofdevelopingroadinfrastructuredespitethecongestionandothercostsroadusebrings.
RoadinvestmentinCanberrahasactedasadeterrenttopublictransportuseduetothedevelopmentofhighqualityarterialsallowingforfastertravelspeedsandthereforeloweringtotaljourneytimes.Inparticular,overthepastfewdecades,anumberofinvestmentsweremadeinmotorwaygradeparkwaystojointhevarioustowncentresacrossCanberra.Althoughprovisionhadbeenmadeforrapidtransit,evidentintheprovisionofthewidemediansthatareprovidedalongmanykeyroadcorridorsinCanberra,investmentdidnotmaterialise.
Furthermore,aspublictransportsharestheroadsupplywithgeneraltraffic,anyresultingcongestionwouldalsoservetodeterioratetheperformanceofbusservices.
Current Bus Network DesignThecurrentdesignofthepublictransportnetworkinCanberrasignificantlyaffectsitsattractivenessasamodeoftransportofchoiceforpassengers.Withafocusonprovidingservicecoverage,busroutesarecircuitous,increasingtraveltimesandwaittimesforpassengers.ThefollowingattributesofthebusnetworkservetofurtherreducetheattractivenessofpublictransportinCanberra:
• Thebusnetworkiscurrentlydesignedtomaximiseservicecoverage,requiringmultipleroutesoperatingatlowfrequenciestoserviceaparticularareatoensurethat95%ofresidentsarenofurther than 500m from a route
• TerminationoflocalservicesatthelocaltowncentrewithtravellersrequiredtotransferforonwardtraveltotheCityandotherdestinations
• Significantdifferencesintheroutingandfrequencyofservicesbetweenweekdaypeakperiods,weekdayoff-peakperiodsandonweekends.
TheProject,byimprovingpublictransportservicesandbyencouragingachangeinlandusepatterns,aims to reduce car dependency and increase public transport usage. Changes in transport and land useproposedbytheProjectareoutlinedinthefollowingchapter.Theensuingoptions,basedoncombinationsofthescenarios,aimtoaddresstheidentifiedissuesby:
• Improvingthecompetitivenessofpublictransportservicesbyprovidingpriorityandseparatingsuchservicestoincreasetheirservicespeedsandreliability
• IncorporatinglandusechangesasadriverofincreasingsocialandenvironmentalsustainabilityofCanberrathroughhigherdensitiesandgreatermixedusesandsupporttheeconomicandfinancialsustainabilityofaninvestmentinpublictransport
• Increasetransportcapacitytoenablefurthereconomicdevelopmentwithinanestablishedcorridorinordertoreducerelianceongreenfielddevelopments
• Investigatethemeritsofadjustedparkingpricesasameansofbettermanaginglevelsofcaruseandprovideasecondarysourceoffundingforaninvestmentinrapidtransit
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 25
5 Assessment of Options
5.1 Summary of OptionsInordertoaddresstheproblemsidentifiedintheprevioussection,anumberofscenariosfortheProjectStudy,asoutlinedinSection2.2,havebeenidentifiedwhichincludetransport,landuseandparkingchargescenariosFiveoptionsweredeveloped,withfourdo-somethingoptionsoutlinedbelowagainst a base case:
• BRT with business as usual land use and higher parking charges
• LRT with business as usual land use and higher parking charges
• BRT with higher density land use and higher parking charges• LRT with higher density land use and higher parking charges
5.2 Capital Costs
TheoutturncapitalcostsoftheProjecthavebeenprovidedbytheProject’scostestimatorURS.Thefollowingcostdrivershavebeenincludedintheassessmentofthecapitalcosts:
• Directcosts:constructioncostsofworksspecificallycoveringthecostofplant,labour,materialsandspecialist contractors
• Indirectcosts:planning,design,mobilisationandgovernmentcosts.
The concept design used to inform this submission assumed that rapid transit infrastructure would be built inthemedianofNorthbourneAvenueandFlemingtonRoad.Thewidthofthemedianonbothroadsissufficientlywidetocaterforrapidtransitwithoutalteringthepositionofexistinggeneraltrafficlanes.
Thisconceptdesigninformedacostestimationbasedonunitrates,quantitiesandaveragelengths,allowingforthefollowingsignificantcostcomponents(whereapplicable):
• TheintroductionofsegregatedrapidtransitlanesinthemedianoftheProjectCorridor
• ModificationsandadditionstotwobridgesonFlemingtonRoad
• Belowrailinfrastructure(track,trackbedandcrossovers)
• Newstopsandstations
• Electrificationincludingsub-stations,overheadwiringandsupportsystems
• Signalling
• Rollingstock and depots• Ancillarymodificationsincludingtheintroductionofsegregatedcyclewaysandwideningoffootpaths
Onanundiscountedbasis,theupfrontcapitalcostsfortheBRTandLRTareestimatedtobe$276million,and$614millionrespectively.AdetailedbreakdownofcostsforBRTandLRTisprovidedinTable7:
ACT Government Environment and sustainable Development Directorate 26
Table 7: Breakdown of Undiscounted Upfront Capital Costs (2011 Prices in $ million)
Cost ComponentBRT LRT
Cost Prop. Cost Prop.
Preliminaries,designandgovernmentcosts $51 18% $113 18%
Enabling,generalconstructionplanningandmanagement $28 10% $28 5%
Below rail infrastructure - - $102 17%
Bridges $14 5% $14 2%
Separated rapid transit lanes $25 9% $25 4%
Road works and medians $10 4% $10 2%
Utilitiesanddrainage $33 12% $33 5%
Footpaths and cycle paths $4 1% $4 1%
Signalling $10 4% $10 2%
Electrical supply $13 5% $88 14%
Passengerinterfaceandcommunications $29 11% $42 7%
Depots $48 17% $91 15%
Fleet $11 4% $55 9%
Total $276 100% $614 100%Source: URS
5.3 Demand ImpactsThe Canberra Strategic Public Transport Model (CSTM) was used as the basis to assess the demand impactforeachoption,whichismaintainedbyESDD.CSTMisatypicalfour-stepStrategicPublicTransportdemandmodelcoveringtheACTandQueanbeyan.
Thedemandprojectionsforeachprojectscenarioweretestedundertwosetsoflanduse,populationandemploymentassumptions:a‘businessasusual’landusescenarioanda‘higherdensity’landusescenario.
The‘businessasusual’landuseprojectionsarebasedonACTGovernmentChiefMinisterandCabinetDirectoratelanduseprojections.The‘higherdensity’landuseprojectionswerepreparedbyESDDandURS,whichreflectsanassumptionofafasterrealisationoftheProjectCorridor’sdevelopmentpotentialwithoutrelyingonchangestoexistinglandusecontrolsorpoliciesintheTerritoryPlan.Table8outlinesthefirstandfinalmodelyearresultsfor2011and2031andprovideshighleveldemandmodelresultsfor the whole of the ACT transport system.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 27
Table 8: High Level Demand Model Results for whole of ACT transport system
Year 2011 2031
Land Use BAU BAU Higher Density
Mode BAU BAU BRT LRT BRT LRT
Passenger trips
Public transport 16,900 38,400 43,600 43,700 43,700 43,800
Car 239,300 291,300 286,500 286,300 285,600 285,400
Total passenger trips 256,200 329,700 330,100 330,000 329,300 329,200
Average journey time (mins)
Public transport 62.3 57.4 55.7 55.5 53.6 53.5
Car 12.4 12.8 12.5 12.5 11.4 11.4
PT Mode Share 6.6% 11.6% 13.2% 13.3% 13.3% 13.3%
PT Fare Revenue $ 20,100 $ 45,600 $ 51,800 $ 52,100 $ 52,000 $ 52,200
Passenger kilometres travelled
Public transport 210,100 506,100 591,700 596,500 574,400 579,300
Car(driveronly) 1,870,800 2,072,900 2,032,600 2,030,300 1,959,600 1,957,400
Passenger hours
Public transport 17,500 36,700 40,400 40,400 39,000 39,100
Car 49,400 62,300 59,500 59,400 54,300 54,200
Total passenger hours 66,900 99,000 99,900 99,800 93,300 93,300
Change in passenger hours
PTpassengerhours-contusers -1,100 -1,200 -800 -800
PTpassengerhours-newusers 6,400 6,600 16,500 16,600
PTpassengerhours-lostusers -1,600 -1,600 -13,400 -13,400
Carpassengerhours-contusers -1,500 -1,500 -3,000 -3,000
Carpassengerhours-newusers 1,700 1,800 18,400 18,300
Carpassengerhours-lostuser -3,000 -3,100 -23,400 -23,400
ACT Government Environment and sustainable Development Directorate 28
Table9:ChangeinDemandMetricsforthewholeoftheACTtransportsystem(2031versus2011)
Land Use BAU Higher Density
Mode BAU BRT LRT BRT LRT
Passenger trips
Public transport 127.0% 157.8% 158.9% 158.5% 159.5%
Car 21.7% 19.7% 19.6% 19.3% 19.2%
Total passenger trips 28.7% 28.8% 28.8% 28.5% 28.5%
Average journey time (mins)
Public transport -7.7% -10.6% -10.9% -13.9% -14.1%
Car 3.6% 0.7% 0.5% -7.9% -8.1%
PT Mode Share (percentage point change) 5.0% 6.6% 6.7% 6.7% 6.7%
PTFareRevenue 127.0% 157.8% 158.9% 158.5% 159.5%
Passenger kilometres travelled
Public transport 140.9% 181.6% 183.9% 173.4% 175.8%
Car(driveronly) 10.8% 8.6% 8.5% 4.7% 4.6%
Passenger hours
Public transport 109.5% 130.6% 130.7% 122.5% 123.0%
Car 26.1% 20.5% 20.3% 9.9% 9.6%
Total passenger hours 47.9% 49.3% 49.2% 39.4% 39.3%
Economic Appraisal TheeconomicevaluationwasundertakenonanincrementalbasiswhichcomparedtheProjectoptionsagainstawithoutprojectcaseusingadiscountedcashflowtechniqueonthebasisofarealdiscountrateof7%andundertakeninaccordancewithATCandInfrastructureAustraliainvestmentappraisalguidelines.
Allvaluesareexpressedin2011dollars.Thebenefitsoftheprojectwereassessedovera30yearevaluationperiodcommencingafterconstruction.
Thefollowingeconomicbenefitswereassessedaspartoftheeconomicappraisal:
• Changeingeneralisedjourneytimes
• Unperceivedvehicleoperatingcostsavings
• Avoidedenvironmentalexternality
• Avoidedaccidentcosts
• Avoidedroaddamage
• Incrementalfarerevenue• Incrementalparkingrevenue
The following economic costs were assessed as part of the economic appraisal:
• Constructioncosts
• Asset maintenance costs
• Incrementalpublictransportoperatingcosts
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 29
Table10outlinestheheadlineeconomicresultsfortheeconomicevaluation.
Table 10: Economic Results for Project Options
Economic IndicatorBRT
with BAU Land Scenario
LRT
with BAU Land Scenario
BRT
with Higher Density Land Scenario
LRT
with Higher Density Land Scenario
Benefitcostratio 1.98 1.02 4.78 2.34
Netpresentvalue($m) $243.3 $10.8 $939.1 $701.1
NPVI $0.68 $0.01 $2.62 $0.87
Internal rate of return 14.6% 7.2% 26.7% 15.7%
Thepre-feasibilityeconomicevaluationresultsshowsthattheallcoreProjectoptionshavethepotentialtogeneratepositiveeconomicreturnsunderthebusinessasusualandhigherdensitylandusesettings.ThismedianoutcomesupportsthenotionthatrapidtransitinvestmentwithintheProjectCorridorhasrealpotentialtodeliverneteconomicbenefits.
Ofthetransportoptions,BRTisprojectedtodeliverhighereconomicreturns.
Ontheotherhand,theeconomicreturnsthatcanbedeliveredthroughLRTinvestmentalonearelikelytobeeconomicallymarginalandtheneteconomicoutcomeforLRTunderevenminoradversecircumstancesislikelytoresultinnegativeeconomicreturns.
Also,itshouldbenotedthatthereisahighunderlyinglevelofsensitivityassociatedtheevaluationoftheincrementalparkingrevenuestream.Shouldthisstreamonlymaterialiseinpart,economicoutcomesmaydifferfromthosepresentedabove.FurtherassessmentduringtheFeasibilityandForwardDesignstageisnecessarytoaffirmtheseestimates.
Theseobservationsunderlinetheneedtoconsidersupportinglandusesettingsincombinationwithtransportimprovements.Shouldtheseoccurcollectively,projectedeconomicoutcomesarelikelytobesignificantlyenhanced.
ACT Government Environment and sustainable Development Directorate 30
6 Next Steps
6.1 EstablishmentoftheGungahlintoCityProjectOfficeAsaclearindicationoftheACTGovernment’scommitmenttoprogressingtheProjecttotheFeasibilityandForwardDesignstage,theACTGovernmentestablishedtheGungahlintoCityProjectOfficeinits2012-13Budget.TheProjectOfficerecognisesthelinkbetweentransitandtheredevelopmentofthecorridor.TheProjectOfficewillcoordinatecurrentandfutureprojectsofvariousdirectorateswithinthecorridor,includingtransitcorridorfeasibilityanddesign,redevelopmentofpublichousingandcorridorplanningstudiestoexploredevelopmentscenariostosupporthigherdensitiesandthelike.
6.2 FeasibilityandForwardDesignWorksShould the Project proceed into the Feasibility and Forward Design Stage, further feasibility, design and planningworkwillneedtobecommissionedbytheACTGovernmenttoassesstheProject’sfeasibilityindetail.FullgovernmentfundingforthenextstageoftheProject’sdevelopmentisconsideredappropriate.
Table 11: Proposed Feasibility and Forward Design Works
Development Possible Investigations
Option development
Moredetailedprojectstaginganalysistoassesstheappropriatetimingoftheinvestmenttoensure that enhanced public transport capacity when it is warranted by the growth in demand
FurtherdefinitionofthetransportmodestobeusedFrequentNetworkisrequiredtoensurethatoptionsandtreatmentsappliedalongtheProjectCorridorwillalignwithtreatmentsandinvestmentsappliedacrosstheremainderoftheFrequentNetwork
Detailed design
ProductdefinitionincludingvehicleoptionsandLRT/BRTinfrastructureandoperationalspecifications
DetaileddesignoftheProjectCorridor,DicksonStationandtheGungahlinTerminus
Cost estimation
Refinementofthecapitalcostestimates,whichshouldbebasedonadetaileddesignandincludeanappropriateprojectcontingencyasaresultofaprobabilitybasedprojectriskassessment process
Public transport operations
Rationalisationoftheassumedbusnetworktoensuretheappropriatelevelofbusserviceisprovided,tomaximisethelevelofintegrationofrapidtransitwithinthecurrentnetworkandtoensurethatoperatingcostsandthelevelofoperatingsubsidyforpublictransportservicesareoptimised
Land use Refinedlanduseanalysistoensurethatthepopulationandemploymentdistributionalandgrowthimpactsareassessedindetail,reflectasustainablelevelofgrowthintermsofdemandandsupply,andarereflectedinthedemandassessmentandeconomicbenefitsquantification
Refinedlandvaluecaptureanalysistoensureallofthepotentialrevenuesourcesarecapturedto contribute to the funding of the project
Demand modelling
Detailedstrategicmodellingofthepreferredoptiontoensuretheservicecharacteristicsoftheproposedoptions(BRTorLRToracombinationofthetwo)areappropriatelyreflected.Thismayinvolvethecommissioningofstatedpreferencestudiestobetterassessthewillingnesstopayfor(oralternativelythewillingnesstouse)BRTandLRTservices
Modelvalidationandcalibrationusingupdateddemanddataincluding2011JourneytoWorkdata
Environmental Assessment
ConfirmwhetheranEnvironmentalImpactStatementwillneedtobepreparedfortheProject
Planning approvals
ConfirmwhatplanningapprovalswillberequiredtoprogresstheProject
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 31
Development Possible Investigations
Governance ConsiderwhatgovernancearrangementswillberequiredtofacilitatetheintegrateddevelopmentoftheProjectCorridor,withaspecificemphasisontheintegrationoflanduseand transport outcomes
Procurement Developmentofanappropriateprocurementstrategytofullyscopetheoptimumapproachtothefuturedevelopmentoftheproject
FurtherinvestigationisrequiredtoidentifycomponentsoftheProjectthataremostamenableforprivatesectorinvolvementandassessthefinancialattractivenessofprivatesectorinvolvementusingaPublicSectorComparatorapproachtoassessvalueformoney.
6.3 FundingRequirementsTheFeasibilityandForwardDesignStageisprojectedtocostanadditional$30millionover2013–14and2014/15.A50:50splitinfundingfortheFeasibilityandForwardDesignStageisproposedbetweentheACTandCommonwealthGovernment.A50:50splitinfundingfortheFeasibilityandForwardDesignStageissoughtfromtheCommonwealthGovernmentonthebasisthattheProjectis:
• Consistent with National Building 2 objectives:TheProjectdirectlyaddresses3ofNationBuildingIIobjectives:ConnectingPeople,SafetyandInnovation
• Consistent with the objectives of projects funded under the Commonwealth Government’s Liveable Cities Program:TheProjectaimsatexploringopportunitiesforcooperationbetweentheACTGovernmentandtheprivatesectortodirectlyaddressissuesincludingclimatechange,affordablehousing,trafficcongestionandagrowing,ageingpopulation
• Corridor of national significance:NorthbourneAvenue,whichformsalargepartoftheProjectCorridor,hasbeenidentifiedwithintheNationalCapitalPlanasacorridorofnationalsignificance.ProposedinvestmentsaspartoftheProjectareaimedatreinforcingthenationallysignificantceremonialroleoftheAvenue.AnumberofdesignelementsarelikelytoberequiredthatareoverandabovetherequirementsfortypicalrapidtransitprojectsinordertomeettherequirementsoftheNationalCapitalPlan.
• Opportunity to develop an integrated land use-transport governance structure:AnumberofpartiesincludingtheProductivityCommission,InfrastructureAustraliaandCOAGhaveoutlinedtheneedforimprovedgovernanceinrelationtothedevelopmentofAustralia’scities.TheACTGovernment’scommitmenttotheestablishmentoftheGungahlintoCityProjectOffice,aimedatcoordinatingtransport,redevelopmentofpublichousingandlanduseplanning,providesapotentialspecial-purposevehicletopromoteandrealisepotentialtransportandlanduseoutcomesoutlinedwithinthissubmission.
FundingarrangementsfortheProjectfor2012–13werefinalisedaspartofthe2012–13ACTBudget.Thisfundingwillbeallocatedtocommunityconsultationandfurtherfeasibilityanalysis.
ItisintendedthatmatchingACTGovernmentfundingwillbesoughtaspartofthenextBudgetcycle(2013–14).ShouldtheACTGovernmentreceiveaCommonwealthGovernmentcontribution,thesefundsare proposed to be used to accelerate the Feasibility and Forward Design Stage, with a focus on:
• Developinganintegratedlanduse-transportgovernanceframework
• Considerthedevelopmentofaspecial-purposevehicletoassistintherealisationoftheProject’sbenefitsincludingoverseeinggovernancearrangementsinrelationtodevelopmentswithintheCorridor
• Investigatingopportunitiesforprivatesectorfinancing
• Investigatingpricingmechanismstooptimisethelevelofupfrontandrecurrentgovernmentfundingincludinglandvaluecaptureopportunities
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 33
Appendix A: Stages 1 – 6 Proposal Summary
Initiative Name: City to Gungahlin Transit Corridor Study
Location (State/Region(or City)/ Locality): Australian Capital Territory
Name of Proponent Entity: ACTEnvironmentandSustainableDevelopmentDirectorate
Contact (Name, Position, phone/e-mail): MsKristinBlume–ProjectDirector,ESDD
Executive summary
About the ProjectTheProjectseekstoassessthefeasibilityofdevelopingarapidtransitcorridorbetweenGungahlinandtheCityalongFlemingtonRoadandNorthbourneAvenue(the‘ProjectCorridor’)usingeitherBRTorLRTtechnologies.Italsoassessestheimpactofhigherpopulationandemploymentdensities,andincreasedparkingchargesontheProject’sviability.
TheoptionsassessedweredevelopedfollowingthedefinitionofProjectgoals,thesegoalsare:
• ProvidegreaterconnectivityandcapacitybetweenfuturegrowthcentresandtheCity
• Encouragegreateruseofmoresustainabletransportmodes,suchaspublictransportandactivetransport.
• EncouragefurthereconomicdevelopmentwithintheGungahlintoCBDcorridor
TheProjectanditsgoalsareconsistentandalignedwithcurrentACTandCommonwealthGovernmentpolicy.Mostnotably,the2012TransportforCanberrapolicyhighlightstheneedforamoreeffectiveandefficienttransportsystem.ThePlanaimstoincreasetheactiveandpublictransportmodeshareto30%by2031from20%in2011.
Outsideoftransportpolicy,theProjectisalsoconsistentwithobjectivessetoutintheACTPlanningStrategy.Thekeytargetofthestrategyistoachieve50%ofnewhousingtobeestablishedwithintheurbanareaofCanberrasoastosupportotherACTGovernmentpolicyoutcomes.
TheProjectwouldsupportthecreationofopportunitiesforincreaseddensityanddispersedemploymentbyleveragingoffexistinglanduseofactivitycentresandinter-towntransportconnections.ItwouldalsoalleviatemobilityconcernsandcreatemorechoicesfortravelbyintegratinginvestmentinCanberra’stransportnetworkswiththelandusesitservices.
The proposed rapid transit system also addresses Infrastructure Australia’s strategic goals through publictransport,betterassetutilisationofexistingtransportinfrastructureandtransformingcitiesthroughintegratedlanduse-transportplanning.ItwillhavebothdirectandindirectbenefitsintermsofenhancingthenationalsignificanceofNorthbourneAvenuebyimprovingpublictransportalongthecorridorandpromotingmorediverseurbandevelopment.
IdentifiedProblemsThe City to Gungahlin Corridor has a range of current and emerging issues that are intertwined and potentiallyrequireinvestmenttoresolve.Theseissuesinclude:
1. Growingroadcongestion
2. Highlevelsofcardependency
3. Afastgrowingpopulation
4. A mismatch between jobs and employment
ACT Government Environment and sustainable Development Directorate 34
5. Lowlandproductivity
6. Diminishing corridor amenity
7. High greenhouse gas intensity
Alloftheproblemsoutlinedaboveimpedeonachievinggoalsandobjectivesasoutlinedbygovernment.Problems1to5presenthurdlestodeliveringpublictransportcapacity,managingroadcongestion,supportingCanberra’scoreadvantages,improvingequityandliveability.Problem6hindersonachievingthegoalofmaintainingandimprovingtheamenityoftheProjectCorridor,andProblem7isanimpedimenttowardscreatinganenvironmentallyfriendlytransportsystem.
Itcouldbeexpectedthatwithoutintervention,futuregrowthwithintheProjectCorridorwillservetoleadtoafurtherdeclineinroadspeeds,increasingtraveltimewhichimpedesaccesstoemployment,communityfacilities,socialandrecreationalactivities,hencefurtheraggravatingtheproblemsidentified
Preferred OptionsThesubmissionconsidersacombinationofthetransportandlandusescenarios.Fiveoptionsweredeveloped,withfourdo-somethingoptionsagainstabasecase.Thedosomethingoptionsare:
• BRT with business as usual land use and higher parking charges
• LRT with business as usual land use and higher parking charges
• BRT with higher density land use and higher parking charges• LRT with higher density land use and higher parking charges
Thebasecaseoptionassumesthatchangesinfuturetransportandlandusecontinueonabusinessasusualbasis,inlinewithcurrentGovernmenttransportcommitmentsandplanningstrategies
EvaluationResultsTheeconomicevaluationwasundertakenonanincrementalbasiswhichcomparedtheProjectoptionsagainstawithoutprojectcaseusingadiscountedcashflowtechniqueonthebasisofarealdiscountrateof7%inaccordancewithATCandInfrastructureAustraliainvestmentappraisalguidelines.Projectcapitalexpenditureisassumedtotakeeffectfrom2012andallvaluesareexpressedin2011dollars.Thebenefitsoftheprojectwereassessedovera30yearevaluationperiodcommencingafterconstruction.
The Canberra Strategic Public Transport Model (CSTM) was used as the basis to assess the demand impactforeachoption,andismaintainedbyESDD.TheCSTMisatypicalfour-stepStrategicPublicTransportdemandmodelcoveringtheACTandQueanbeyan.
TheeconomicevaluationresultsshowsthattheallcoreProjectoptionsareprojectedtogenerateapositiveeconomicreturnbasedonbusinessasusualandhigherdensitylanduseprojections.Table12outlinestheheadlineeconomicresultsfortheeconomicevaluation.
Table 12: Economic Results for Project Options
Economic IndicatorBRT
with BAU Land Scenario
LRT
with BAU Land Scenario
BRT
with Higher Density Land Scenario
LRT
with Higher Density Land Scenario
Benefitcostratio 1.98 1.02 4.78 2.34
Netpresentvalue($m) $243.3 $10.8 $939.1 $701.1
NPVI $0.68 $0.01 $2.62 $0.87
Internal rate of return 14.6% 7.2% 26.7% 15.7%
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 35
ItshouldbenotedthatbenefitsfortheLRTwitha‘businessasusual’landuseoption,aremarginal.IncrementalbenefitsforallProjectoptionsaredependentonparkingrevenuesandarethereforelikelytobesensitivetoparkingrates,demandandutilisation.Accordingly,furtherinvestigationwouldbeordertorefinetheoptionsshouldtheProjectproceedtothenextstage
Next stepsShould the Project proceed into the Feasibility and Forward Design Stage, further feasibility, design and planningworkwillneedtobecommissionedbytheACTGovernmenttoassesstheProject’sfeasibilityinmoredetail.FullgovernmentfundingforthenextstageisconsideredappropriateastheProjectisproposedtobecategorisedasa‘RealPotential’project.
TheFeasibilityandForwardDesignStageisprojectedtocost$30millionover2013/14and2014/15.A50:50splitfundingissoughtfromtheCommonwealthGovernmentonthebasisthattheProjectisconsistentwithobjectivesoutlinedin:
• TheNationBuilding2Program
• TheCommonwealthLiveableCitiesProgram• TheNationalCapitalPlanasacorridorofnationalsignificance
Itcanalsoberegardedasanopportunitytodevelopanintegratedlanduse-transportgovernancestructure. The scope for the proposed Feasibility and Forward Design Stage will include the following:
• Moredetailedoptiondevelopment
• Detailedproductdefinitionanddesign
• Refinedcostestimates
• RationalisationofcurrentbusnetworkwiththeProject
• Refinedlanduseanalysisandvaluecapture
• Further detailed strategic demand modelling
• ConfirmationontheneedforanEnvironmentalImpactStatementandrequiredplanningapprovalsfor the Project to proceed
• Furtherconsiderationwithrespecttoappropriategovernancearrangementsandaprocurementstrategy
ACT Government Environment and sustainable Development Directorate 36
Stage1–GoalDefinition
Initiative GoalsThedevelopmentoftheProjectaimsto:
• ProvidegreaterconnectivityandcapacitybetweenGungahlinandtheCity
• Encouragegreateruseofmoresustainabletransportmodes,suchaspublictransportandactivetransport
• EncouragefurthereconomicdevelopmentwithintheGungahlintoCitycorridor• ImprovetheefficiencyoftransportmovementswithintheGungahlintoCitycorridor.
Initiative ObjectivesUponimplementationoftheProject,thefollowingobjectivesareexpectedtoberealised:
• Delivering transport capacity by increasing public transport capacity and speeds along the Project CorridortoservicefastgrowingpopulationlevelsandeconomicactivityalongtheProjectCorridorandatkeyactivitycentres
• Managing road congestionbyincreasingtheattractivenessofnon-carmodesinorderintoreducelevelsofcardependencybyincreasingthefrequency,capacity,reliabilityandspeedofpublictransportservicesandthroughtheprovisionofhighqualitywalkingandcyclinginfrastructure
• Supporting Canberra’s core byimprovingaccessibilitytotheCityandtheParliamentaryTrianglebyprovidingfaster,morefrequentserviceswithhigherlevelsofcapacityandinturn supportingCanberra’sroleasthenation’scapitalandpreeminentfederalpoliticalandadministrativecentreaswell as the City Centre’s role as the preeminent municipal commercial centre
• Supporting economic diversity and development bypromotinganincreaseinthelevelanddiversityofeconomicactivityalongtheProjectCorridorintheCity,alongNorthbourneAvenueandinkeytowncentresincludingDicksonandGungahlinbyincreasingthemixandnumberofresidentsandemploymentpositionsaswellasbyimprovingpublictransportaccessibilityalongtheProjectCorridor
• Creating an environmentally friendly transport systemaimedatreducinglevelsofgreenhousegasemissions,airandnoisepollutionbyreducinglevelsofcardependenceandincreasingthelevelofpublicandactivetransportusageandreducingtraveldistances
• Improving equity and liveabilitybyenhancingaccesstokeycentresandcommunityfacilitiesthroughimprovedpublicandactivetransport,relieduponmorebythelesswelloff,thedisadvantagedandtheelderlyandpromotingabroaderdiversityofhousingandimprovinghomeaffordabilitybyincreasingtheprovisionofhigherdensitydwellings
• Maintaining and improving the amenity of the Project Corridor by reinforcing the linear alignment ofNorthbourneAvenue,maintainingtheavenueoftreesandaddingthepermanencyofdedicatedbuslanesorlightrailtracks,consistentwithBurleyGriffin’soriginalintentionfortheAvenueandNorthbourneAvenue’snationallysignificantroleastheprimaryNationalGateway
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 37
Initiative AlignmentTheProjectisconsistentwithpolicyobjectivessetoutbyrelevantCommonwealthGovernmentandACTGovernmentpoliciesandplanslistedinTable13.
Table 13: Relevant Government Policies
Jurisdiction Territory Policies
National Policies
NationalInfrastructurePriorities(IA,2009)
COAGReport:GettingthefundamentalsrightforAustralia’sinfrastructurepriorities(IA,2010)
NationBuildingIIProgram(CommonwealthGovernment,2012)
Inparticular,theProject’sgoalsareconsistentwithInfrastructureAustralia’sthemeof‘TransformingourCities’intermsofimprovingpublictransportnetworks,developmentofintegratedlanduseandinfrastructureplanningandcontributetosustainabilityimprovements.
Territory Policies
Strategic Public Transport Network Plan (MRC, 2009)
CanberraSpatialPlan(ACTPLA,2004)
Sustainable Transport Plan (ACTPLA, 2004)
ACTGovernmentInfrastructurePlan2011-21(ACTCM&CD,2011)
Transport for Canberra (ESDD, 2012)
TheProjectsupportsACTGovernment’sstrategicgoalsofprovidinganintegratedtransportsystem,sustainabletransportandencouragesactivetransport.
Policies in Development DraftACTPlanningStrategy(ESDD,2011)
ACT Government Environment and sustainable Development Directorate 38
Stage2–ProblemIdentification
City to Gungahlin CorridorTheProjectCorridorhasbeenidentifiedastheGovernment’sprioritycorridorfornewinfrastructureinvestmentintheshorttomediumterm,withtheviewofdevelopingrapidtransit,withintheGovernment’sTransportforCanberrapolicy.
TheProjectCorridorhasbeenidentifiedasakeycorridorinthe2031StrategicPublicTransportPlanNetwork,whichaimstodeliverpublictransportservicesatahighservicefrequencyacrossthedayontheNetwork.AlthoughtheNetworkhasbeendesignedfortheprovisionofabus-basedsolution,theNetworkhasbeendevelopedtobeadaptabletoandsupportiveofrapidtransitsolutionsaswellaspotentialcity-buildingactivities.
Also,planningworkandinvestmentshavebeenundertakenalongotherstrategiccorridorstoachieveawholeofnetworkimprovement.Forinstance,constructionisduetocommenceontheBelconnentoCity Transitway this year.
CurrentandFutureProblemsThe City to Gungahlin Corridor has a range of current and emerging issues that are intertwined and potentiallyrequireinvestmenttoresolve.Theseissuesinclude:
1. Growingroadcongestion
2. Highlevelsofcardependency
3. Afastgrowingpopulation
4. A mismatch between jobs and employment
5. Lowlandproductivity
6. Diminishing corridor amenity
7. High greenhouse gas intensity.
FurtherevidencetotheproblemsstatedaboveispresentedinStage3.AlloftheproblemsoutlinedaboveimpedeonachievinggoalsandobjectivesasoutlinedinStage1.Problems1to5presenthurdlestodeliveringpublictransportcapacity,managingroadcongestion,supportingCanberra’score,improvingequityandliveability.Problem6hindersachievingthegoalofmaintainingandimprovingtheamenityoftheProjectcorridor,andProblem7isanimpedimenttowardscreatinganenvironmentallyfriendly transport system.
Itcouldbeexpectedthatwithoutintervention,futuregrowthwithintheProjectCorridorwillleadtoafurtherdeclineinroadspeeds,increasingtraveltimewhichimpedesaccesstoemployment,communityfacilities,socialandrecreationalactivities,furtheraggravatingtheproblemsoutlinedabove.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 39
Stage 3 – Problem Assessment
IntroductionThissectionprovidesquantitativeandqualitativeassessmentsoftheproblemsoutlinedinStage2.
RoadCongestionEvenwithcurrentdemand,NorthbourneAvenuealreadyoperatesatorovercapacityduringpeakperiods.Basedoncurrenttrafficconditions,roadcongestionaddsapproximately15minutestoacartripduringpeakperiods.ESDDestimatewithinvestmentinBRTorLRT,currentdelayscouldbereducedbymorethanhalfasshowninFigure11,abenefitthatcouldbeexpectedtogrowovertimeshouldaninvestmentinrapidtransitbemade.
Figure 11: Estimated Peak Period Delays for a Trip between Gungahlin and the City for General Traffic
02468
1012141618
Current with BRT with LRT
Peak
Per
iod
Dela
y (m
in)
Source: ESDD
PrevailingroadcongestionalsoadverselyimpactsontheefficiencyofbusoperationsalongtheProjectCorridor.TimetablesforcurrentlimitedstopRedRapidservicesthattravelalongtheProjectCorridoralreadyadd12minutestoallmorningpeaktripstotheCity.Figure12illustratesthecurrenttimeofdayprofilefortheRedRapidwhichtravelsfromGungahlintoCivic,includingunexpectedtraveltimes.
Figure 12: Red Rapid Route 200 Gungahlin to Civic: Current Timetabled Travel Times
0:00
Departure Time
0:05
0:10
0:20
0:15
0:25
0:30
0:35
0:40
7 AM
Trav
el T
ime
8 AM
9 AM
10 A
M
11 A
M
12 P
M
1 PM
2 PM
3 PM
4 PM
5 PM
6 PM
Source: ACTION Buses (2011)
DuringtheAMandPMpeakhour,traveltimesincreasebyover50%andnearly30%respectively.Under
ACT Government Environment and sustainable Development Directorate 40
thecurrentarrangements,publictransportservicesontheProjectCorridorcompetewithgeneraltraffic.Thislimitsthespeedandreliabilityofservices,astheyhavenopriorityorabilitytobypasstrafficdelaysinthecorridororbypassotherbuses,whichcreatesbusbunchingandinturnreducestheefficacyofprovidingahighfrequencyservice.
TheimpactofcongestiononbusesisnotlimitedtoresidentslivingalongtheProjectCorridor.NorthbourneAvenueisakeybuscorridorandactsasatrunkformostbusservicesoriginatinginCanberra’snorthernsuburbsandsouthofLakeBurleyGriffinasfaroutasFyshwickandTuggeranong. As the Transport for Canberra envisagemorecross-regional(Rapid)busservicestooperatealongthecorridorfromdestinationsincludingQueanbeyanandMolonglo,theimpactsofcongestionintheProjectCorridorwillbroadenovertime.Inshort,congestionintheProjectCorridorhasabroadimpacton many residents across Canberra.
HighLevelsofCarDependencyInCanberra,theJourney-to-Work(JTW)datasetarguablyprovidesthemostreliablesnapshotofpublictransportusage.TheJTWdatasetsuggeststhatcarusagehasremainedpersistentlyhighwithmorethanfourofeveryfivecommutesmadeinaprivatemotorvehicle(asshowninTable14).
Table 14: Canberra Journey to Work Mode Share 1976 – 2006
Mode 1976 1981 1986 1991 1996 2001 2006
Cardriver 71.3% 70.9% 72.6% 70.7% 72.7% 73.9% 73.5%
Car passengers 13.8% 12.4% 11.4% 12.1% 10.2% 9.4% 8.7%
Sub-total: private transport 85.1% 83.3% 84.0% 82.8% 82.9% 83.3% 82.2%
Public transport 8.9% 9.9% 9.7% 9.9% 8.3% 6.7% 7.9%
Bicycle only 0.9% 2.1% 2.1% 2% 2.2% 2.3% 2.5%
Walk only 4.6% 4.0% 3.6% 4.0% 4.3% 4.2% 4.9%
Other modes 0.5% 0.6% 0.6% 1.4% 2.3% 3.5% 2.4%Source: ACTPLA (2009)
AlthoughtheProjectCorridorhasthesecondhighestlevelsofpublictransportpatronageinCanberra,reflectingahighlevelsofpublictransportuseinNorthCanberra,levelsofcardependencyintheGungahlinSSDarehigherwithclosetonineoutoftencommutesweremadeinaprivatevehicle(asshown in Table 15).
Table 15: 2006 Journey to Work Mode Share by District
Statistical subdivision Car driver
Car passenger
Sub-total: private
transport
Public transport
Bicycle Walk Other
Gungahlin – Hall SSD 79.2% 10.1% 89.3% 7.4% 1.1% 1.2% 1.0%
North Canberra SSD 55.0% 7.3% 62.3% 10.1% 8.0% 18.2% 1.5%
Belconnen SSD 76.0% 9.2% 85.2% 8.8% 2.1% 2.9% 1.1%
South Canberra SSD 71.1% 8.1% 79.2% 7.7% 3.3% 8.4% 1.4%
Woden Valley SSD 72.2% 7.8% 80.0% 10.0% 2.2% 6.7% 1.2%
Weston Creek – Stromlo SSD 78.7% 9.0% 87.7% 6.8% 2.3% 2.1% 1.1%
Tuggeranong SSD 81.0 8.9% 89.9% 6.8% 1.0% 1.4% 1.0%
Canberra 73.5 8.7% 82.2% 7.9% 2.5% 4.9% 2.4%
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 41
GrowingRoadCongestionIncreasingtrafficcongestionisnotonlyanirritantforresidents,butalsoaddstothecostsofdoingbusiness.Roadcongestionadverselyimpactsontraveloutcomesthroughlongerwaitingtimesandunreliabilityandimposessignificantdirectandindirectcostsoneconomicactivityandproductivity.
IncreasingroadcongestionhasimplicationsontheefficiencyonCanberra’spublictransportnetwork,whichislikelytorelyonabus-basedpublictransportsystemfortheforeseeablefuture.Intheabsenceofbusprioritymeasuresandsegregationofbusoperationsfromgeneraltraffic,roadcongestionwillimpactontheefficiencyandattractivenessofpublictransportoperationsinCanberra.
WhileCanberramaynothavethesamelevelsofcongestionasseeninSydneyandMelbourne,highlevelsofaccessibilityarehighlyvaluedbyCanberransandisviewedasakeypartofCanberra’scompetitiveadvantageintermsofattractingpeopletoliveandworkinACT.InthecontextoftheProject,highlevelsofcongestionalongtheprojectcorridormayservetocompromisetheattractivenessofGungahlinasaplacetolive,adverselyimpactingonthespeedofdevelopmentaroundGungahlin.
Asareflectionofhighlevelsofcardependency,particularlyinthenorthernendoftheProjectCorridor,duringpeaktraveltimes,NorthbourneAvenuealreadyoperatesatorovercapacity.Peakhourlyflowisaround3,000vehiclesperhouroverthethreetrafficlaneswithinterruptionsfromtrafficlights.ArterialroadssimilartoNorthbourneAvenuetypicallyhaveacapacityof1,000vehiclesperlaneperhour,althoughtrafficlightsandintersectionsalongNorthbourneAvenueadverselyimpactonthispotentialthroughput.Anecdotally,NorthbourneAvenue’scapacityconstraintisevidentbythelongqueuesanddelaysthatcurrentlyexistalongthecorridorduringthepeakperiodsasdemonstratedbyFigure13.
Figure 13: Congestion on Northbourne Avenue during the morning peak
Source: ESDD
CongestionandqueuingareexpectedtoworsenalongbothNorthbourneAvenueandFlemingtonRoadwithflowduetofuturepopulationgrowthinGungahlin,andinsurroundingareasofNSW.PopulationgrowthinthesurroundingareasofNSWwillseeadditionalcross-bordertrafficusingNorthbourneAvenue.TrafficflowfromNSWintotheACThasincreasedbymorethan15%inthelastfiveyears.
ACT Government Environment and sustainable Development Directorate 42
RapidPopulationGrowthOverthepastdecade,thedistrictsofGungahlinandNorthCanberra,whichencompasstheProjectCorridor,haveexperiencedthefastest(andlargest)levelsofpopulationgrowthintheACT.Forthetenyearsto2011,thepopulationsofthesetwodistrictshaveincreasedbyanaverageof6.8%and2.6%perannumrespectively.Bycomparison,theACTpopulationgrewatanaverageof1.4%perannumoverthesameperiod.Table16outlinesthechangesinpopulationbetween2001and2011bydistrict.
Table 16: Population Growth by District
District (SSD) 2001 2011Average Annual Change
Growth Growth Rate
North Canberra 38,585 49,674 1,109 2.6%
Belconnen 85,601 94,947 935 1.0%
Woden Valley 32,494 34,530 204 0.6%
WestonCreek-Stromlo 23,662 23,760 10 0.0%
Tuggeranong 90,875 88,382 (249) (0.3%)
South Canberra 23,324 26,880 356 1.4%
Gungahlin-Hall 24,398 47,067 2,267 6.8%
ACT 319,317 365,621 4,630 1.4%
Queanbeyan 41,598 52,620 1,102 2.4%Source: ABS Cat. No 3218.0. Population estimates for 2011 are provisional and may change with the release of 2011 Census data.
Thesehighlevelsofgrowthareexpectedtocontinue.Basedoncurrentbusinessasusualprojections,thepopulationlevelintheGungahlindistrictisexpectedtoreach73,000by2021,approximately70%higherthanin2011andequivalenttoanaveragegrowthrateof4.8%perannum.6 – When fully developed,Gungahlin’spopulationisexpectedtobe90,000,ordoublethecurrentlevel.
Thepaceandlocationofpopulationgrowthhaslong-termimplicationsforliveabilityandsustainability.Higherlevelsofpopulationgrowthincreasesdemandtoprovideadditionaltransportinfrastructureandservices.WithsignificantconstraintsontheabilitytoexpandroadcapacityinandaroundtheProjectCorridor,investmentintransportinfrastructurewouldberequiredtomitigatefuturecongestiononboththeroadandpublictransportnetworkandtomaintainandenhanceconnectivitybetweenGungahlinandtheCity.
Mismatch in Employment and PopulationAlthoughplanningpoliciesinCanberrahavesoughttoincreaseself-containmenttoreducedemandforlongerdistancetravel,itisapparentthatthespatialdistributionofemploymentpositionsissuchthatindoesnotachievehighlevelsofself-containment.
MostdistrictsinCanberrahaveinsufficientemploymenttocaterforallworkingageresidentsandmoreover,manyofthesepositionsaretakenbyresidentslivinginotherdistricts.OnlyinNorthCanberra, South Canberra and Woden districts, the centre of Canberra, are there more employment positionsthanresidents.Table17outlinesthenumberofjobsperpersonineachdistrictandtheproportionofjobsprovidedwithineachdistricttakenbydistrictresidents.
TheconcentrationofemploymentpositionsandthenatureoftheemploymentpositionsinthecentreofCanberraisintheprovisionofservicesparticularlywithinthepublicadministration,professional/scientific/technicalandeducation/trainingsectors.TheinstitutionsandorganisationsthatdeliverthesetypesofservicesaremostprevalentintheCityandtheParliamentaryTriangle
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 43
Table 17: 2006 Employment Outcomes by District
District Number of Jobs per Person Proportion of District Jobs Taken by District Residents
North Canberra 2.55 23%
South Canberra 3.68 14%
Woden 1.30 23%
Weston 0.36 42%
Belconnen 0.55 61%
Tuggeranong 0.33 73%
Gungahlin 0.39 43%
Queanbeyan 0.56 58%Source: ACTPLA (2009)
ItisdifficulttoforeseetheunwindingoftheconcentrationofthesetypesofactivitiesintheCityandParliamentaryTriangle.Totheextentthatplanningconstraintsallow,marketforceswilltendtoencourageeconomicactivitiesofacomplementarynaturetoconsolidatespatially.Furthermore,currentgovernmentlanduseprojectionsexpectemploymentandeconomicactivityinthecentreofCanberrawillcontinuetoincrease.
Hence,employmentintheCityandtheParliamentaryTrianglewillcontinuetobeakeyemploymentattractorfortheforeseeablefuture.Forthesetheseareastoaccessworkersandgoodsefficientlyandeffectively,theprovisionofatransportnetworktoconnectresidentialareasintoemploymenthubswithsufficientcapacity,speedandefficiencyisimperative.
Withoutsignificantchangesinhowemploymentisdistributedacrosstheterritory,norealisticlandusescenariocanbeexpectedtoprovidesignificantgrowthinemploymentattowncentres.Hence,itislikelythatresidentslivingonthenorthernendoftheProjectCorridorwillgenerallyneedtotraveltowardsthe City in order to seek employment for the foreseeable future.
LowLandProductivityByinternationalcomparison,thepopulationdensitiesofAustraliacitiesaremuchlowerthanthatoftheirinternationalcounterparts.AustraliancitiestendtobemorespreadoutintermsofurbansettlementbutevenbyAustralianstandards,Canberra’sdensityisquitelow.Figure14showsthesameblackboxthatcoversCanberra’spopulationofapproximately360,000peopleishometoapproximately1 million people in Sydney:
ACT Government Environment and sustainable Development Directorate 44
Figure 15: Spatial Comparison between Sydney and Canberra.
Source: Adapted from Google Maps
Alandusescenarioinfavouroflowdensitydevelopmenthasarangeofeconomicandsocialimplications:
• Higher per capita cost of providing public transport and community services: Lowdensitiesalsoimpactonthecostsofprovidingcommunityservicesonapercapitabasis.Tomaintainaconsistentlevelofservice,inlowdensitiesareasagenciesarecompelledtoputintoplacemoreinfrastructureandservicesinordertomaintaincoverage.Thisphenomenonisperhapsmostobservableintheprovisionofpublictransportservicesbutalsooccurswithprovisionofwater,sewerage,electricity,communications,schoolsandhospitals.
• Risk of social exclusion:Moreoftenthannot,thecostofprovidingcommunityfacilitiesandpublictransportthatishighlyaccessibleinlowdensityareaslimitstheprovisionofsuchsocialinfrastructureandservices.Withsuchinfrastructureandservicesbeinglessaccessible,thosethatdonothavereadyaccesstoacar,whichtendtobethemostvulnerableandinthemostneedforaccesstocommunityservices,canleadtoariskofsocialexclusion.
Diminishing Corridor AmenityAs the main approach route from Sydney or Melbourne and its link to the core of Canberra, the importanceofthequalityoftheurbanenvironmentalongNorthbourneAvenue,isformalisedwithintheNationalCapitalPlan.TheAvenueservesa:
• Nationally significant role: thepresentationoftheAvenueformsthevisitor’sfirstperceptionofthecity’scharacter.ItsroleastheprimaryNationalGatewayelevatesitsimportance,theimportanceofurbandesignandthedecision-makingfortreatmentswithinit
• Commercial role:theAvenueisCanberra’skeycommercialaddressforapartments,professionalandservicebusinesses.TheAvenuecatersforarangeoflandusesforresidential,commercial,recreationalandgovernmentpurposes
• Transport role:TheAvenueisthemajornorth-southroutenorthofLakeBurleyGriffin,providingconnectionsforcarsandpublictransportbetweenthenorthernsuburbsofCanberra,theCityandsouthern Canberra.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 45
However,theAvenue’scurrentdesignandfunctionality,inparticularitsroleasamajorarterialroad,diminishesthequalityoftheurbanenvironmentalongtheAvenue:
• Impact on natural amenity: Theincreaseinformalityisachievedbytheintroductionofalargecentralmedianwhichisfirstplantedwithsporadicclumpsoftreeswhichbecomescontinuoustreeplantingclosertothecitycentre.Thesetreesareplantedrandomlyratherthaninrowstoavoidamissingordyingtreebecomingobvious.Duetosoilandspeciesselectionissues,manyofthetreeshaveandwillcontinuetorequireremoval.TheProjectprovidesanopportunitytoremedythedeterioratinglandscapingandnaturalenvironmentalongtheAvenue
• Impact on urban amenity: AlthoughNorthbourneAvenueprovidessomeformofcapacityforallmodesoftransport,theattractivenessofnon-carmodesissomewhatlimited.Combinedwithahighlevelofcarusageandcongestion,thewalking(andforpublictransportusers,thewaiting)environmentiscompromised,withpedestriansandpassengersexposedtohighlevelsoftrafficandassociatednoise,accidentsandpollutants.Insuchacardominatedspace,itcanbecomequitedifficulttodevelopurbanformsthatencouragethedesiredfuturecharacteroftheAvenueasaplaceofactivityandvibrancy.
High Greenhouse Gas IntensityHighincomelevels,thelowdensitylevelsandlocationcombinetoresultinthelevelofgreenhousegasintensityintheACTtobeabovenationalaverages.GreenhousegasemissionsarerelativelyhighintheACT for the following reasons:
• Low densities:lowresidentialdensitiesandtheassociatedprevalenceofdetacheddwellingsincreasetheenergyintensityofdwellings.Canberra’scoldclimateservestoincreaseenergyconsumptionduringwinter.Lowdensitiesalsoareassociatedwithhighlevelsofcarownershipandusage
• High level of car dependency:highlevelsofcaruseandassociatedlowusageofpublictransportandactivetransportcombinetoincreaseemissionsfromtheburningoffossilfuels.Withoutintervention,increasingtrafficvolumesandcongestionwillcombinetoincreaseemissionsfromtransportfurther
• ThecontinuationofcurrentlandusescenariosarelikelytobeinconsistentwiththeACTClimateChangeStrategyastheywillcontinuetoencouragethedevelopmentofdetacheddwellingsandlimittheefficacyofpublicandactivetransportinvestments.
ThediscussionaboveisbasedonquantitativeanalysisofavailabledataregardingtheProjectCorridoraswellaspreviousworkdonebyprecedentstudies.Forthepurposeofthissection,aqualitativeassessmenthasbeenappliedinlieuofunavailabilityofproject-specificdata.
QualitativeProblemAssessmentFrameworkTheProblemAssessmentFrameworkusesa7-scaleratingtooutlinetheimpactofproblemsontheProjectoutcome.The7ratingsarethoserecommendedbyInfrastructureAustraliawhenundertakingaqualitativeassessment.ThesuggestedrankingsarelistedinTable18.
ACT Government Environment and sustainable Development Directorate 46
Table 18: Recommended Assessment Ratings
Rating Level Description Rating
Highly beneficial
Majorpositiveimpactsresultinginsubstantialandlong-termimprovementsorenhancementsoftheexistingenvironment.
Moderately beneficial
Moderatepositiveimpact,possiblyofshort,mediumorlonger-termduration.Positiveoutcomemaybeintermsofnewopportunitiesoroutcomeswhichenhanceorimproveoncurrentconditions.
Slightly beneficial
Minimalpositiveimpact,possiblyonlylastingovertheshort-term.Maybeconfinedto a limited area.
Neutral Neutral—nodiscernibleorpredictedpositiveornegativeimpact. –
Slightly detrimental
Minimalnegativeimpact,probablyshort-term,abletobemanagedormitigated,andwillnotcausesubstantialdetrimentaleffects.Maybeconfinedtoasmallarea.
Moderately detrimental
Moderatenegativeimpact.Impactsmaybeshort,mediumorlong-termandimpactswillmostlikelyrespondtomanagementactions.
Highly detrimental
Majornegativeimpactswithserious,long-termandpossiblyirreversibleeffectsleadingtoseriousdamage,degradationordeteriorationofthephysical,economicorsocialenvironment.Requiresamajorre-scopeofconcept,design,location,justification,orrequiresmajorcommitmenttoextensivemanagementstrategiestomitigatetheeffect.
AssessmentResultsTable19providesabriefoverviewoftheissues,theirimpactonCanberraandtheProject’sobjectives.Table20outlinesthescaleoftheimpactsofeachissueontheProjectobjectivesusingtheaforementioned7-scalerating.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 47
Table 19: Overview of Current Problems Impacting on Project Objectives
Problem Impact Impact on Project objectives
Growing Population
Impactsoncongestion(seeGrowingRoadCongestionbelow)
Increases demand for infrastructure
Increasesdemandforadditionalservices
ImpactsonrevenueraisedbyGovernment
NorthbourneAvenueisexpectedtocaterforasignificantshareoftheprojectedgrowth
ReducedmobilityimpactingonefficienttransportmovementalongtheProjectCorridor
Increasedprivatevehicletraveladverselyimpactsonachievinghigherpublicandactivetransportmode shares along Project Corridor
Low Land Productivity
Increasestraveldistancestoemployment,housing,servicesandleisureactivities
Inhibitsonbenefitsofeconomiesofscale
Opportunity cost of land use developmentforotherpurposes
Decreasedproductivityduetolongertraveltimesmovingin,outandthroughNorthbourneAvenue
Inhibitsonincreasingpublicandactivetransportmodesharesasprivatevehicletravelremainsmoreattractive
Lowdensitypropertydevelopmentimpactsonpropertyvalues–Governmentreliesonpropertyvaluestoraiserevenue
Diminishing Corridor Amenity
Decreasesperceivedcharacterandimageof Canberra
DecreasedperceivedcharacteralongProjectCorridorasanationalapproachroute
Growing Road Congestion
Increasesintraveltime
Increasesinvehicleoperationcosts
Reducedliveability
Poorer air quality
Decreasedproductivity
Decreased capacity
Decreasedregionalcompetitiveness
Increased greenhouse gasses
High Car Dependency and Poor Public Transport Usage
Increasesoperationalcosts/subsidy
Increasesprivatevehicletravel
Increases transport emissions
Decreased public transport mode share
Increasednoiseandairpollution
High Greenhouse Gas Intensity
Poorer air quality
Impactsonlocalenvironment
Increased greenhouse gases
Increasednoiseandairpollution
ACT Government Environment and sustainable Development Directorate 48
Table 20: Qualitative Assessment of Current problems and their Impact on Project Objectives
Problem Objective
Growing Population
Low Density
Development
Diminishing Corridor Amenity
Growing Road
Congestion
Poor Usage of Public Transport
High Greenhouse Gas Intensity
Delivering transport efficiently n/a
Managing congestion n/a
Developing a resilient system n/a -
Supporting economic prosperity/employment growth
n/a
Delivering safety and security n/a
Creating a low carbon and environmentally responsible transport system
Ensuring equity and accessibility, and protecting amenity and liveability
Stage 4 – Problem Analysis
Many of the issues presented earlier are the result of a range of underlying causes that can be traced backtothedevelopmentofCanberra,thehistoryofpublicinvestmentintransportalongwiththetravelbehaviourpatternsofthetravelpublicduetocar,fuelandparkingaffordability.Insummarythecausesoftheproblemscanbenarrowedtothefollowingsections.
UrbanPlanningHistoryAtitsinception,CanberrawasplannedasapolycentriccitywiththeParliamentaryTriangleandtheCityservingasthecity’sciviccentrewithtowncentresatBelconnen,TuggeranongandWoden,GungahlinandWestonCreekdevelopedastimeprogressed.Thecitywascarefullyplannedtobeaself-containedcommunitiessurroundedby‘greenbuffers’,containingproportionateareasofresidences,businessesandindustry.Aswithmanypolycentriccities,motorwaystyleparkwaysandrapidtransitlinkswereintended to be built between each town centre and the City.
Plannersintendedthatpeoplewouldliveandworkinthesametowncentre,reducingtheneedforlongerdistancetravel.Withlargequantitiesofavailableandaffordablelandthisresultedin,overtime,lowdensitysettlementpatterns(orurbansprawl)withdetachedhousingstyles.
Whilsttheparkwaylinkshavebeendeveloped,investmentintherapidtransitlinksdidnotmaterialise,withinvestmentflowingintotheexpansionofconventionalbusservicesinstead.
Also,thedecentralisationofemploymentdidnotmanifest;thebenefitsofagglomerationhaveseenemployment centralise in the City and the Parliamentary Triangle.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 49
TheproliferationofprivatevehicleuseinACThasledtotransportlargelyshapinglanduseratherthanthroughintegratedplanningstrategiesasaresultofaccesstolowcostprivatemotoring,highqualityparkwaysandanextensivesupplyoffreeparking.
Whiledensityisnottheonlyfactortosupportpublictransport,mixedusedevelopmentsandhigherdensity housing along public transport mutually support each other.
Thisinturnisimpactingtheregionaleconomicperformancethroughthelossofproductivityduetotimedelaysandincreasingjourneylengthstoplacesofworkandbusiness.Thiseffectisbeingrealisedby,notjustthemovementofpeoplebutthemovementofgoodsaswell–economiccostsassociatedwithgreenhousegasemissionsarealsoawell-knownconsequence.
RoadFocusedSupplySideMeasuresWhilethesuburbanisationhasbeenakeycauseofmanyoftoday’schallenges,governmentinvestmentintransporthasalwaysfavouredasupply-sideapproachthatfavouredroadsgiventhehighlevelofdemandforprivatemotorvehicleuse,thecost-effectivenessofconnectingnewresidentialestateswithroadsandthelimitedrecurrentfinancialimpactofdevelopingroadinfrastructuredespitethecongestionandothercoststhatroadusebrings.
InvestmentsinroadinfrastructureinCanberrahaveservedtoadverselyimpactontheattractivenessofpublictransportrelativetocarsinthefollowingways:
• Thedevelopmentofgrade-separatedparkwaysservedtoincreasetravelspeedsofcars,andloweringcartraveltimes
• Withlimitedseparationfromgeneraltraffic,roadcongestionwouldimpactonthespeedofbusservices,increasingbustraveltimes
• Developmentofloopandcul-de-sacroadnetworkstoreduceratrunningfurtherincreasedtraveltimesforbusesandpassengersaccessingandegressingfromtheseservicesbyforcingbusesandpedestrians to follow circuitous routes.
BusNetworkDesignandOperationsAlthough the Transport for Canberrapolicyenvisagessignificantchangestothecurrentbusnetwork,thefollowingattributesofthebusnetworkservetofurtherreducetheefficiencyofpublictransportin Canberra:
• Thebusnetworkiscurrentlydesignedtomaximiseservicecoverage,requiringmultipleroutesoperatingatlowfrequenciestoserviceaparticularareatoensurethat95%ofresidentsarenofurther than 500m from a route
• TerminationoflocalservicesatthelocaltowncentrewithtravellersrequiredtotransferforonwardtraveltotheCityandotherdestinations
• Significantdifferencesintheroutingandfrequencyofservicesbetweenweekdaypeakperiods,weekdayoff-peakperiodsandonweekends.
GovernanceSinceachievingself-governmentin1989,successiveACTGovernmentshavebeguntomanagetheissueofsustainabilityintheACT.Shiftingdemographics,predictedchangesinclimate,andcostpressureshaveraisedtheneedforthecitytoadaptitsshapeandform–anumberofstudiesandstrategieshaveacknowledgedthatCanberra,initscurrentstate,isnotefficient,sustainableorequitableenoughtocontinuetocaterforadispersedcity,reliantonprivatemotorvehiclesforalltravel.
Toovercomehistoricallegacies,theACTGovernmenthastakenanumberofstepstoimplementbest-practiceapproachestointegratedlanduseandtransportstrategiesbyadoptingsmartlandusegrowthpolicies,alongwithaprioritisedandmulti-modalapproachtotransportinvestment.
ACT Government Environment and sustainable Development Directorate 50
Stage 5 – Option GenerationAstrategicapproachwasadoptedbytheProjectSponsorindefiningandfilteringtherangeofoptionsconsideredforeconomicandfinancialassessment.
ThedevelopmentofoptionsfortheProjecthasbeeninformedbytheoutcomesofstudiesthathavebeenpreviouslyundertakenfortheProjectCorridor.
Theoptiondevelopmentandfilteringprocesswasnotdevelopedformallyperse.Feedbackduringstakeholderconsultationsuggeststhataformaloptiondevelopmentprocesstoexploreissuesincludingalternativecross-sectionaltreatments,spatialandtemporalstaging,complementarypolicymeasuresaswell as modal scenarios is warranted.
Thissaid,thestrategichigh-levelapproachtoidentifyandfilteroptionscouldbeconsideredappropriategiventhepre-feasibilitynatureoftheProjectandwouldprovideusefulinputintoaformaloptiondevelopmentprocess.ThefollowingsectionoutlinestheoptionevaluationframeworkusedbytheProjectteamtodeveloptheoptionsconsideredinthisSubmission.
OptionEvaluationFrameworkArangeofinvestmentandreformoptionscouldbeconsideredbytheACTGovernmenttoreducethedependenceonprivatevehicles,increasetheuseofpublicandactivetransportandbettermanageincreasingtraveldemand.Atahighlevel,thereexistfourbroadapproachesfromwhichoptionscouldbedeveloped:
Road focused approach: Theroadfocusedapproachwouldbebasedon“predictandprovide”styletransportplanningfocusedprimarilyonvehiculartraffic.Itentailsmaximuminvestmentinadditionalcapacityforgeneralpurposetrafficuseacrossthenetwork.Itcouldbedescribedasa“buildourwayoutoftrafficcongestion”strategy.Thisincludesnoemphasisonchargingforuseofroadspace.Investmentinpublictransportwouldbeassumedtobesetata‘dominimum’level.
Public transport approach: thepublictransportstrategyfocusentailsconcentrationofinvestmentonenhancedpublictransportinfrastructureandservices.Roadinvestmentbeyondcurrentlycommittedinvestmentswouldbeheavilyrestrictedinfavourofmajorinvestmentinbusandrail.Thiscouldbedescribedasa‘publictransportcansolveit’strategy.
Policy approach: The reform and policy approach uses a range of policy and demand management toolstobettermanagethelevelandtimingofpassengermovements.Suchtoolscanrangefromlandusestrategies,subsidisedfares,parkingchargesandroadpricingaswellassoftermeasureslikeindividualisedtransportmarketing(e.g.TravelSmart)andworkplacetravelplans.Suchpolicieshavenottraditionallybeenafocusgiventheeaseofimplementingsupply-sidesolutionshoweverhasbecomeattractivewiththehighcostsofprovidingadditionalroadandpublictransportsupplyandtomaximisetheuseofexistinginvestments.
Comprehensive approach: Thecomprehensiveapproachassumesthemaximumrangeofinvestmentandpolicyinitiativesareatworkinaddressingthetransportchallenges.Thisincludedaverystrongfocusonshiftingpeopletomoresustainablemodes(publictransportandactivetransport)commencingintheshorttomedium-termthroughacombinationofpolicytoolsandsmallscaleinvestments.Inthemediumterm,majorinvestmentsinthepublictransportnetworkaremadeinconjunctionwithstrongerpolicyinterventions.ThemeritsanddrawbacksofeachapproacharesummarisedinTable21.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 51
Table 21: Merits and Drawbacks of Each Approach
Approach Merits and Drawbacks
Additional road capacity
Whilstthereissomeabilitytoenhanceroadcapacityonexistingroutes,existingplanningandenvironmentalcontrolsplacesignificantrestrictionsindevelopingroadcapacityinnewcorridors.
EarlyplanningforGungahlinincludedprovisionforGungahlinDriveandMonashDrive.GungahlinDrivewascompletedin2008.TogetherwiththesoontobeconstructedexpandedMajuraParkway,thesetwocorridorsmayprovidesomerelief(althoughnotsignificantrelief)onNorthbourneAvenue.
Thesecondarterialroad,MonashDrive,isunlikelytobeconstructedasitsalignmentrunsthroughtheMountMajuraandMountAinslienaturereserveswhichhavewoodlandreservesthatareprotectedundertheFederalEnvironmentProtectionandBiodiversityConservationAct.TheACTGovernmenthasremovedthisalignmentfromtheTerritoryPlan.
Furthermore,theprovisionofadditionalroadcapacitywouldruncontrarytoarangeofProjectobjectivestoreducecardependencyandtheNationalCapitalPlanwhichaimstominimisethelevelofcongestioninthevicinityoftheCityandtheParliamentaryTriangle.
Additional public transport capacity
Withtheobjectivesofprovidingadditionalcapacityandtoencourageagreaterlevelofpublic transport usage, the Submission considers a range of possible public transport interventions,whicharediscussedfurtheronthefollowingpage.
However,thecurrentlowcostrecoveryofpublictransportservicessuggeststhatcomplementaryandsupportingpolicymeasuresandlandusescenariosmayberequiredtomaximisetheeconomicandfinancialsustainabilityofpublictransportoperations.
Policy approach Changestopolicyscenariosprovideopportunitiestobettermanagedemandandmakebetteruseofexistinginfrastructure.
AkeyelementofthisSubmissionistheexplorationoftheimpactofchangestocurrentlandusescenariosthatwillencourageahigherlevelofresidentialandcommercialdensitiesoverandabovethatprojectedfortheProjectCorridorinthefuture.
Thereareopportunitiestofurtherincreasetheviabilityoftherapidtransitoptionsconsidered as part of this Submission using policy measures. These measures may include higherparkingchargesandroadpricing.However,itisworthnoting:
• CSTM already makes an allowance for a general increase in parking and fuel costs. Other pricedbasedmeasureswillrequirefurthermodeldevelopmenttoexplore
• Thepoliticalandcommunityacceptabilityofcertainpolicymeasuresmaybeloworunknown
• Itisunlikelythatpolicymeasuresintheirownrightwillcreatesufficientcapacitytocaterfor future demand (although it may delay the need for such capacity)
• Policymeasuresaregenerallyprovidedinacomplementarymannerratherthanasanalternativetoinfrastructuresolutions.Forinstance,roadpricingschemesgenerallyareassociatedwiththeprovisionofmorepublictransportservices.
Policymeasurescouldbeconsideredfurtheraspartoftheoptiondevelopmentstageduringa more detailed feasibility analysis.
Comprehensive approach
Asmentionedpreviously,thisSubmissionconsiderspolicyinterventionsintheformofdifferentlandusescenarios.
Byconsideringthecombinedeffectsofpolicyandinvestments,thecomprehensiveapproachgenerallyleadstoanimprovementintheefficiencyofspendingbydeferringsomespendingand/orreducingtheamountofspendingrequired.
However,developingapackageofmeasurescanbecomplex.Suchanapproachwouldbewarrantedaspartoftheoptiondevelopmentstageduringamoredetailedfeasibilityanalysis.
ACT Government Environment and sustainable Development Directorate 52
Considered OptionsInconsideringthemeritsofthefourapproaches,theoptionsconsideredaspartoftheSubmissionareeitherpublictransportbasedoptionsorlanduseoptions(inconjunctionwithtransportinvestment).Noroadoptionswereconsidered.Furthermore,previousworkhasbeenundertakenfornewbusprioritylanes,BRTandLRT.WhilenewbuslanescouldbeconsideredasthemoreconservativeapproachtoaddressidentifiedProjectCorridorissues,previousstudieshaveshownthatnewbuslaneswouldhavelimitedimpactonsurroundingurbandevelopment,aswellastolikelynotprovideanetpositiveeconomic return.
Table22outlinestherangeofoptionsthatwereconsidered,whethertheywereshortlistedandtherationalefortheirinclusionorexclusion:
Table 22: Options Considered
Option Short listed?
Rationale
Conversion of existing lanes to transit lanes
No Theconversionofexistinggeneraltrafficlanestotransitlanesmayprovidesomeshortterm relief for buses.
However,thistreatmentmaycausecongestionassingle-occupantvehiclesareconstrained to fewer lanes.
ThiswillincreasethroughtrafficonnorthCanberrasuburbanroads,negativelyimpactingonresidentialamenityandliveability.
ThesetypesoflanestendtobeineffectiveinanAustraliancontextastheyrequiremanualenforcementandhencesufferfromhighviolationrates.
Furthermore,withsignificantincreasesinbusservicefrequenciesandbusbunchingissues,transitlanesareunlikelytoaddressinfullcurrentorfuturebusoperatingissues.
Conversion of existing lanes to bus lanes
No Theconversionofexistinglanestobuslanesmayprovidesomeshorttermreliefforbusesandmaypresentacost-effectivebusprioritymeasure.
However,previousstudieshavedemonstratedthatthistreatmentwillcausecongestionalongNorthbourneAvenueandresultinrat-runningoncurrentdaydemandlevels.
New bus lanes
No Whilepreviousstudiesagreeontheneedthatshouldbuslanesbedeveloped,thenumberofgeneraltrafficlanesshouldnotbereducedtoavoidcreatingroadcongestion.
Recentassessmentshaveshownthatnewconventionalbuslanesarenoteconomicallyandfinanciallyviable.
ThisSubmissiondoesnotconsidertheviabilityofdedicatedbuslaneswherethenumberofgenerallanesiskeptatcurrentlevels.
BRT Yes PreviousstudieshavenotexploredindetailtheviabilityofBRT.
ThisSubmissionconsiderstheviabilityofdedicatedBRTfacilitiesasacompromisebetween bus lanes and LRT.
LRT Yes PreviousstudieshavenotexploredindetailtheviabilityofLRTconfinedtotheProjectCorridor.
GiventhehighcommunitysupportforLRTandthatLRTisviewedasalongtermtransportsolutionwithintheProjectCorridor,thisSubmissionconsiderstheviabilityofLRT.
Other modes
No Othertransportmodessuchasmonorail,metrorailandheavyrailwerenotconsideredas part of this Submission.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 53
Option Short listed?
Rationale
Increased parking charges
Yes Higher parking charges are considered within the Submission as a mechanism toencouragealternativetransportuseandtosharetheProjectcostsacrossallbeneficiaries.
CSTMisalsounderpinnedwithanimplicitassumptionthatparkingchargesriseovertime.
Road pricing No RoadpricingisnotapartofACTGovernmentpolicy.Shouldroadpricingbeconsideredfurther,optionsfordifferenttypesofroadpricingandanassociatedassessmentofequity,communityandpoliticalacceptabilitywouldneedtobeundertakenbeforeitisconsideredaviableoption.
WhilstCSTMhassomecapacitytomodelroadpricing,furthermodeldevelopmentwould be required to accurately assess the impact of road pricing.
Land use scenarios
Yes LandusescenariosareseenasapivotalelementtoenhancingtheviabilityoftherapidtransitoptionsconsideredinthisSubmission.
ThisSubmissionconsiderstheimpactofhigherdensitiesinconjunctionwithtransportinvestment.
ACT Government Environment and sustainable Development Directorate 54
Stage 6 – Option AssessmentBasedontheshortlistingprocess,theProjectteamdevelopedthefollowingsetoftransportandlandusescenarios.Adescriptionofthesescenariosisprovidedasfollows.
Transport ScenariosThree transport scenarios were considered by the Project Team:
• Business as usual
• BRT• LRT
Thedetailofeachtransportscenariowasworkshoppedwithstakeholders.Stakeholderconsultationinformedthedesiredcrosssectionofthecorridorforeachofthescenarios.TheplacementoftheLRTor BRT corridor on the kerbside or within the median was assessed against factors including safety, amenity,landuseandlocationofutilities.Communityconsultationindicatedaclearpreferenceforamedianalignment.ThewidemedianofNorthbourneAvenueandFlemingtonRoadallowsfortheconstructionofatransitcorridorwithoutdisruptiontoexistingtrafficlanes.
Eachofthetransportscenariosdifferinthedegreeofpriorityandsegregationthatisaffordedtopublictransportservices.Keyfeaturesofeachtransportscenarioaredescribedasfollows:
BusinessasUsualUnderthebusinessasusualtransportoptionshowninFigure15,nochangestothetransportnetworkapartfromcommittedroadandpublictransportprojectsandinitiativesareproposed.BuseswillcontinuetosharecapacitywithgeneraltrafficalongbothNorthbourneAvenueandFlemingtonRoad(wherenobuspriorityiscurrentlyprovided).
Figure 15: Projects corridor cross section under business as usualNorthbourne Avenue
Flemington Road
Source: DCM & URS
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 55
ThehighfrequencyservicesprovidedalongidentifiedFrequentandRapidcorridorsisassumedtobeimplemented.ThecurrentlimitedstopRedRapidservicethattravelsbetweenGungahlinandFyshwickviatheCitywillcontinuetobetheprimarypublictransportlinkbetweenGungahlinandtheCity,augmentedwithlocalallstopbusservices.Figure16showskeybusroutesthatareproposedunderthePlan around the Project Corridor.
Figure 16: 2031 Strategic Public Transport Plan Network around the Project Corridor
Source: ESDD
ACT Government Environment and sustainable Development Directorate 56
BRTUnder the BRT scenario shown in Figure 17, a new median busway would be constructed on NorthbourneAvenuebetweenAlingaStreetandFlemingtonRoadandonFlemingtonRoadbetweenNorthbourneAvenueandGungahlinforusebyallbusservicestravellingonNorthbourneAvenueandFlemingtonRoad.Thecivilengineeringofthebuslaneswillbedesignedinmannertoreadilyallowforaconversiontolightrailshouldtheoptionbeexercised.
ThemediantreatmentwouldutiliseavailablespaceforadualdedicatedbuswayintheNorthbourneAvenuemedian.ThemedianofFlemingtonRoadwouldbedevelopedtoprovideadualdedicatedbuswayforbusoperations.TheBRTscenariomakesallowancefor15stopsbetweenGungahlinandCivicwithstopsclosertoGungahlinandCivicspacedclosertogetherwhilstintermediatestopsspacedfurtherapart.Busbayswouldbeconstructedtoallowlimitedstoporexpressbusestobypassdwellingbuses.
NewstationsatGungahlin,DicksonandCivicwouldbedevelopedtofacilitateinterchangingwithotherbusservices.
AnewBRTservicewouldoperatebetweenGungahlinandCivicandintegratewiththeremainingRedRapidroutebetweenCivicandFyshwickandinthefuturetoQueanbeyan.Thisservicewouldhaveaminimum headway of 5 minutes during peak periods.
The remainder of the public transport network is assumed to be based on the 2031 Strategic Public Transport Network Plan.
Figure17: Project corridor cross section under BRTNorthbourne Avenue
Flemington Road
Source: DCM & URS
Constructionisassumedtocommenceduring2013andconcludein2017.Fulloperationsareassumedto commence in 2018.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 57
LRTUndertheLRTscenarioshowninFigure18,betweenGungahlinandNorthbourneAvenue,adedicatedlightrailcorridorwouldbedevelopedinthemedianofFlemingtonRoadfortheuseoflightrailservices.OnNorthbourneAvenuebetweenFlemingtonRoadandCivic,adedicatedcorridorinthemedianwouldbeprovidedforlightrailbutwouldbedesignedtoallowthededicatedcorridortobesharedbybothbusandlightrailservices.Toachievethis,lightrailtrackswouldbeembeddedintoanasphaltroadsurfacealongNorthbourneAvenue.
NochangeinthenumberofgeneraltrafficlanesonNorthbourneAvenueorFlemingtonRoadisproposed.
Thededicatedlightrapidtransitcorridormakesallowancefor15stopsbetweenGungahlinandCivicwithstopsclosertoGungahlinandCivicspacedclosertogetherwhilstintermediatestopsspacedfurtherapart.
NewinterchangesatGungahlin,DicksonandCivicwouldbedevelopedtofacilitateinterchangeswithotherbusservices.
AnewlightrailservicewouldreplacetheexistingRedRapidservicebetweenGungahlinandCivicandintegratewiththeremainingRedRapidroutebetweenCivicandFyshwickandinthefuturetoQueanbeyan.Theminimumheadwayforthelightrailservicewouldbe7.5minutesduringpeakperiods.
OtherbusestravellingalongFlemingtonRoadorNorthbourneAvenuecouldalsousethededicatedcorridor. The remainder of the public transport network is assumed to be based on the 2031 Strategic Public Transport Network Plan.
Figure18: Project corridor cross section under LRTNorthbourne Avenue
Flemington Road
Source: DCM & URS
Aspartofthisoption,supportingoperatinginfrastructurewouldbedevelopedincludingrollingstock,signalling,powersupply,substationsanddepots.
Constructionisassumedtocommenceduring2013andconcludein2017.Fulloperationsareassumedto commence in 2018.
ACT Government Environment and sustainable Development Directorate 58
LandUseScenariosThesubmissionalsoseekstoexploretheeffectofchangesinlanduseontheviabilityofpublictransportservices.TheintertwinednatureoftheissuesfacingtheProjectCorridormeanthatanintegratedtransport-landuseapproachislikelytooptimisetheeconomicoutcomesofinvestmentsintheProjectCorridor.
Duringdevelopmentandconsultationwithstakeholders,thethreelandusescenarioswerecoined‘low’,‘medium’and‘high’scenarios,reflectingtherelativelevelofchangeinpopulationandemploymentintheProjectCorridorundereachscenario.AllscenariosassumedanincreaseindensitiesoverandabovethatalreadyprojectedbycurrentGovernmentlanduseforecastsbuttotalemploymentandpopulationacross the ACT and Queanbeyan was held constant.
Both‘medium’and‘high’scenariosweredeveloped,buthavebeenexcludedfromeconomicassessment.The‘medium’scenarioassumedasignificantlevelofredevelopmentwithintheProjectCorridorbuthasnotbeenpresentedinthissubmissionbecauseithadonlyamarginalimpactontheeconomicresultsabovethelowadditionaldevelopmentscenario.The‘high’scenarioprojectedgrowthintheProjectCorridorthatwouldrequireagrowthintotalACTpopulationoverandabovecurrentprojections,andthereforecouldnotbe compared to business as usual, low or medium scenarios, and was eliminated for this reason.
Hence,thissubmissiontestsonlythelowadditionaldensificationscenario,whichhasbeencoinedasthe ‘higher density’ scenario for the purposes of this submission.
Shouldtheinvestmentsintransportinfrastructurebesufficientlyattractivetopotentialusers,theinvestmentsthemselvescouldgeneratechangesinlanduse.TheProjectislikelytoimproveaccessibilitythroughreducedtraveltimes,decongestionandimprovedtraveltimereliability.Inturn,improvementsinaccessibilitymaydrivelandusechanges.Wheretransportinterventionsprovideasignificantenhancementinaccessibility,peopleandindustriesmaychoosetomovethelocationoftheirresidence,employment,businesscentresandaltertheirlogisticschainstotakeadvantageoffastertraveltimes.Transportinvestments,inparticularlightrailinvestments,mayalsoresultinredevelopmentaroundstations.
Landusesettingsareconsideredanimportantpolicytool.Evenwithoutsignificantchangestoexistingplanningcontrols,theProjectCorridorhasanumberofpropertiesthatcouldbereadilyredevelopedbyGovernmenttosupporturbandensification.Forinstance,theACTGovernmentownsthemotorregistrysiteandtouristinformationsiteaswellaspublichousingcomplexesalongNorthbourneAvenue.TherealsoexistsopportunitiestorezoneunderdevelopedsitesincludingpartsofEPICandCanberraRacecourse.TheGovernmentmayalsoseektomanagethespatialdistributionofdemandforhousingby constraining supply outside the Project Corridor. Finally, as land in the ACT is sold on a leasehold arrangement,theACTGovernmentistheultimateownerofalllandandcouldusethesearrangementstoeffectchangesinlandusepatterns.
However,modellingtherelationshipbetweenlanduseandtransportiscomplex.Althoughthenotioniswellespousedamongstplanners,fewstrategicdemandmodelsattempttomodeltheimpactoftransportinterventionsandaccessibilityonlanduseoutcomesasthereisadualendogeneitybetweenlanduseandtransporti.e.theybothinfluenceeachother,arelationshipwhichischallengingtocontrolinbothdirectionssimultaneously.Also,accessibilityisonlyoneofmanyfactorsthatwouldultimatelyimpact on land use outcomes.
Asanalternateapproach,theProjectteamdevelopedlandusescenariostoreflectpossibleurbanoutcomesfromgovernmentintervention,whetherthroughinvestmentintransportorthroughchangesin land use scenarios.
ThreelandusescenariosweredevelopedbytheProjectteamfortestinginadditiontothe‘businessasusual’landusescenario.ThelanduseprojectionsfocusedonalinearcorridoraroundtheProjectCorridor.Theareaofinvestigationforeachlandusescenario,showninFigure19isassumedtocoveraonekilometrebufferzonealongtheProjectCorridor,extendingfromLakeBurleyGriffininthesouthtotheGungahlinTownCentreinthenorthwithwideningatDicksontoreflectthestrategicimportanceofDicksonasatransporthubwithhigh-frequencytransportrouteconnections.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 59
Figure 19: Area of Investigation
Source: URS
Mostlandusechangeswereassumedtooccurwithinan800mcatchmentofeachstation.Thiscatchment is based on the commonly recognised walkability catchment for public transport.
Thehigherdensitylandusescenarioisnotnecessarilyapolicysetting.Theurbanoutcomesimpliedbythescenariomayarisethroughamarketresponsetotransportinvestment,aswellasthroughadjustmentsinlandusesettings,urbanrenewalprogramsorthroughacombinationofthesefactors.
Abriefdescriptionofthebusinessasusualand‘higherdensity’scenarioisprovidedbelow.
ACT Government Environment and sustainable Development Directorate 60
BusinessasUsualThe‘businessasusual’landusescenarioisbasedoncurrentACTGovernmentpopulationandemploymentprojections,whichareusedforwholeofgovernmentdecisions.
CurrentGovernmentprojectionsassumethatthecombinedACT–Queanbeyanpopulationwouldexceed500,000peopleby2031.Tocaterforfuturepopulationgrowth,historicdevelopmentpatterns(mainly‘greenfield’developmentinthedistrictsofMolonglo,GungahlinandQueanbeyan)wouldcontinueintothefuture.Underthisscenariothereisnosignificantchangetolandusepoliciesandplanning controls in the study area.
ThepopulationofQueanbeyanisincludedintheanalysisastheCSTMincludesitforthepurposeofmodelling the transport network.
Figure 20: Northbourne Avenue Cross Section under Existing Conditions
Source: DCM
HigherDensityScenario(LowAdditionalDensification)ThehigherdensitylandusescenarioassumesafasterrealisationoftheProjectCorridor’sdevelopmentpotentialwithoutchangestoexistinglandusecontrolsorpoliciesintheTerritoryPlan.Thescenarioallows for recent amendments in planning controls for:
• Dickson
• Gungahlin Town centre
• Inner North urban housing
• Cityarea(ANUExchangeandGriffinLegacy)
Underthehigherdensityscenario,populationandemploymentlevelswouldbe38%and21%higherthan under the business as usual land use scenario within the Project Corridor by 2031.
ParkingScenarioTransportdevelopmentshouldnotonlybeconcernedwiththeprovisionofsupplybutalsoeffectivemanagementoftransportdemand.Parkingchangescanbeusedasalevertofacilitateamodeshifttopublictransport.Furthermore,theincreaseofparkingratesalongtheProjectCorridorcouldprovideanarrayofbenefitstothecommunity,governmentandroadusers.
CanberrahasthelowestparkingratesamongstAustraliancapitalcities.ColliersInternationalestimatedthatdailyratesinCanberraat$10–theaveragerateacrossAustraliancitieswas$39perdaywithSydneyandMelbournehavingthehighestratesat$64and$66respectively.7
Whilethissuggestsaboontocurrentprivatevehicleroadusers,lowparkingfeesencourageprivatevehicleusewhichimposesarangeofcostsonsocietyandinfrastructure.Anincreaseinparkingratescouldprovidethefollowing:
• Encouragetheuseofpublictransportandotheralternativetransportmode,suchasactivetransport, along the Project Corridor
• EnsurethatthecostoftheProjectaresharedacrossallbeneficiariesalongtheProjectCorridor• PotentiallyprovideanadditionalfundingsourcefortheProject
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 61
Intermsofpossibleadversereactionbyasocietythatisheavilycarreliant,communityconsultation(viaTimetoTalkCanberra2030)revealedthatCanberra’sresidentswereinformedwithrespecttotheneedforwiderpublictransportoptions.Surveyparticipantsdiscussedtrade-offstheywouldbewillingtoacceptincludingtheincreaseofparkingchargestodiscourageprivatevehicleuse.8
Shortlisted Options
Asafinalstep,theProjectteamconsideredwhatcombinationofthethreetransportscenarios,twolandusescenariosandaparkingscenariothatwasmostlikelytooccur.Fromtheseconsiderations,theProjectteamdevelopedfiveoptions,withfourdo-somethingoptionsagainstabasecaseoption:
• BRT with business as usual land use and increasing parking charges
• LRT with business as usual land use and increasing parking charges
• BRT with higher density land use and increasing parking charges• LRT with higher density land use and increasing parking charges
Aconventionalbuslanescenariowithbusinessasusualorhigherdensitylandusewasnotconsideredasitwasconsideredunlikelythatlanduseswillchangesignificantlyfromaninvestmentinbuslanesonly.Increasedparkingchargeswereassumedforalloptionsasitwasconsideredakeymechanisminfacilitatingashifttoalternativetransportmodes,remediatecostsforremainingprivatevehicleusersandoptimisefundingfortheProject.
Thebasecaseoptionassumesthatchangesinfuturetransportandlandusecontinueonabusinessasusualbasis,inlinewithcurrentGovernmenttransportcommitmentsandplanningstrategies.
ACT Government Environment and sustainable Development Directorate 62
Appendix B: Stage 7 Template
Appraisal Summary Table 1: Demand and Economic Modelling Assumptions
1.DemandModelling,AssumptionsandResultsOutline the key drivers of demandTheCanberraStrategicPublicTransportModel(CSTM)wasusedtoestimatechangesintravelpatterns.CSTMisatypicalfour-stepStrategicPublicTransportdemandmodelcoveringtheACTandQueanbeyan.
Changesintraveldemandandtravelpatternsareprimarilyinfluencedbyeitherchangesinthelevelofpopulationandemployment,thelocationofpeopleandjobs,andgeneralisedtraveltimesbetweenindividualoriginsanddestinations.
Trip Generation
ThenumberoftripsgeneratedineachTrafficAnalysisZoneisestimatedonlanduseinputs.Theleveloftripgenerationisdependentonthetrippurposeaswellastheassumedsocio-economiccharacteristicsofagivenzone.Ratesandadjustmentfactorsareshowninthefollowingtables:
Table 23: Trip Generation Rates
Trip Purpose AM Peak Trip Rate
Home based Work 0.239
Education 0.104
Shopping 0.040
Other 0.085
Non-home based Business appointments etc. 0.107
Other 0.039Source: MRC, Transport Modelling and Analysis 2006/2011, Study Report
Table 24: Trip Rate and Public Transport Usage Adjustment Factors based on Income
Income Level 2006 Trip Rate Adjustment Factors 2006 PT Usage Adjustment Factors
Low (< $25,999 p.a.) 0.593 1.332
Medium ($26,000 to $51,999 p.a.) 1.142 0.959
High (> $52,000 p.a.) 1.327 0.649Source: MRC, Transport Modelling and Analysis 2006/2011, Study Report
Table 25: Trip Rate and Public Transport Usage Adjustment Factors based on Age
Age Level 2006 Trip Rate Adjustment Factors 2006 PT Usage Adjustment Factors
Under 15 years 0.756 0.781
15 to 24 years 0.704 1.537
25 to 44 years 1.316 1.091
45 to 64 years 1.198 0.795
65yearsandabove 0.336 0.705Source: MRC, Transport Modelling and Analysis 2006/2011, Study Report
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 63
Generalised Costs
Previoushouseholdtravelsurveysrevealedtrip-makerbehaviourandperceptions,whichservedasthebasisforestimatinggeneralisedcostfunctionparameters,asshowninbelow:
Table 26: Generalised Cost Components
Element Key Factors Base Year (2011) Value
Travel time
Distance,OperatingSpeeds,
Lane CapacityDefinedforeachlink
TrafficVolumes Identifiedthroughnetworkassignments
Operating Cost
FixedVehicleOperatingCost $0.13/km
FuelPrice($/L) $1.03/L
FuelCostperkm($/km) $0.09/km
Value of Time $10/hr
Road User ChargesParking Charges
Definedbyareaandfactored
with the Parking Charge Factor
Public Transport Fares Based on base year faresSource: MRC, Transport Modelling and Analysis 2006/2011, Study Report
Thefollowingequationsillustratethegeneralformofthegeneralisedcostfunctionanditscomponents:
Equation 1: Generalised Cost Equations
Car generalised cost =Travel Time ×Value of Time+ (Fixed VOC per km+Fuel Cost per km)×Distance+Parking Cost
PT generalised cost =(In-vehicle time+1.15 walk time+1.2 wait time+1.1 boarding time)×Value of Time+Fare Cost
Alloutofvehicletraveltimeelementsareweightedtoconverttheseelementsintoanin-vehicletraveltimeequivalent.
Changes in generalised costs, impact primarily upon mode choice within CSTM through the following equations:
Equation 2: Mode Choice Function
PT mode shareij,trip purpose = 1 1 + expλ (GC Car—GCPT )+α
Thefollowingparametersinformtheestimationoftheaboveequation:
Table 27: Mode Choice Parameters
Trip Purpose Spread Parameter (l) Constant (a)
Work -0.27 0.66
Education -0.2 0.2
Other -0.3 3Source: MRC, Transport Modelling and Analysis 2006/2011, Study Report
ACT Government Environment and sustainable Development Directorate 64
Describe the situation ‘without’ the initiative, i.e. the base case, including future works and associated capital, maintenance and operating costs
Thebasecaseoptionassumesthatchangesinfuturetransportandlandusecontinueonabusinessasusualbasis,inlinewithcurrentGovernmenttransportcommitmentsandplanningstrategies.
Underthebusinessasusualtransportoption,nochangestothetransportnetworkapartfromcommittedroadandpublictransportprojectsandinitiativesareproposed.BuseswillcontinuetosharecapacitywithgeneraltrafficalongbothNorthbourneAvenueandFlemingtonRoad(wherenobuspriorityiscurrentlyprovided).
The 2031 Strategic Public Transport Plan Network withhighfrequencyservicesprovidedalongidentifiedFrequent and Rapid corridors is assumed to be implemented. The current limited stop Red Rapid servicethattravelsbetweenGungahlinandFyshwickviatheCitywillcontinuetobetheprimarypublictransportlinkbetweenGungahlinandtheCity,augmentedwithlocalallstopbusservices. Figure 22 shows key bus routes that are proposed under the Plan around the Project Corridor.
Figure 22: 2031 Strategic Public Transport Plan Network around the Project Corridor
Source: ESDD
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 65
The‘businessasusual’landusescenarioisbasedoncurrentACTGovernmentpopulationandemploymentprojections,whichareusedforwholeofgovernmentdecisions.
CurrentGovernmentprojectionsassumethatthecombinedACT–Queanbeyanpopulationwouldexceed500,000peopleby2031.Tocaterforfuturepopulationgrowth,historicdevelopmentpatterns(mainly‘greenfield’developmentinthedistrictsofMolonglo,GungahlinandQueanbeyan)wouldcontinueintothefuture.Underthisscenariothereisnosignificantchangetolandusepoliciesandplanning controls in the study area.
2.LandUse,PopulationandEmploymentForecastsWhat land use, population and employment forecasts have been used and where have they been sourced from?
Twosetsoflanduseprojectionshavebeenusedfor2011,2021and2031:a‘businessasusual’landusescenarioanda‘higherdensity’landusescenario.ThefollowinglanduseinformationwasusedforestimatinggeneratedtripsataTrafficAnalysisZonelevel:
• Population
• Employment
• Retail space
• School enrolments
Tertiaryenrolments
The‘businessasusual’landuseprojectionsarebasedonACTGovernmentChiefMinisterandCabinetDirectoratepopulationprojections.The‘higherdensity’landuseprojectionswerepreparedbyESDDand URS.
What is the range of projections over the period forecast and used in the economic appraisal? What are the annual employment and residential growth rates implied by these land use forecasts? What are the factors that will affect the likely outcome given the demand drivers identified?
Twosetsoflanduseprojectionshavebeenusedfor2011,2021and2031:a‘businessasusual’landusescenario and a ‘higher density’ land use scenario.
TotalpopulationandemploymentprojectionsacrossthecombinedACT-Queanbeyanregionarecommontobothlandusescenarios.Table28showsprojectedtotalpopulationandemploymentlevelsacrosstheregion,whichshowsthatpopulationlevelsareanticipatedtoexceedhalfamillionpeopleby2031.
Table 28: Projected Total Population and Employment across ACT-Queanbeyan
Metric 2011 2021 2031
Total
Population 397,900 459,100 518,900
Employment 223,500 250,400 277,400
Change
Population 15.4% 13.0%
Employment 12.0% 10.8%
CAGRPopulation 1.4% 1.2%
Employment 1.1% 1.0%
ACT Government Environment and sustainable Development Directorate 66
If specific land use forecasts have been undertaken for the proposal what is the difference in terms of number of jobs and residents compared to the base case land use in the last year the forecasts are produced for?
TotalpopulationandemploymentprojectionsacrossthecombinedACT-Queanbeyanregionarecommon to the ‘business as usual’ and ‘higher density’ land use scenarios.
Has there been any redistribution of jobs and residents and if so, what are the assumptions underpinning this redistribution?
Althoughthepopulationandemploymenttotalsarecommontobothlandusescenarios,thedistributionofpopulationandemploymentwithintheregionhasbeenaltered.The‘higherdensity’landusescenarioreflectsanassumptionofafasterrealisationoftheProjectCorridor’sdevelopmentpotentialwithoutrelyingonchangestoexistinglandusecontrolsorpoliciesintheTerritoryPlan.TherealisationofhigherpopulationlevelswithintheProjectCorridorhasbeenassumedtobebasedonaslowerrealisationofproposedgreenfielddevelopmentsites,inparticularwithintheMolongloValleyandQueanbeyan.Underthehigherdensityscenario,populationandemploymentlevelswouldbe38%and21%higherthanunderthebusinessasusuallandusescenariowithintheProjectCorridorby2031.
Table29andTable30showlanduseprojectionsfortheProjectCorridorandotherdistrictsinCanberrafor 2011, 2021 and 2031 under the ‘business as usual’ and ‘higher density’ land use scenarios.
Table 29: Population Projections by District
District 2011 BAU
2021 BAU
2021 Higher Density
2031 BAU
2031 Higher Density
Project Corridor 50,400 62,500 71,900 74,100 102,600
North Canberra Outer 14,100 14,800 21,100 16,300 21,000
Gungahlin Outer 26,500 41,700 36,800 56,800 45,500
Belconnen 91,300 94,000 93,200 93,000 93,000
South Canberra 26,000 28,800 28,000 34,200 33,900
Tuggeranong 89,000 84,500 84,100 83,000 85,700
Woden 57,400 58,100 58,400 57,000 54,600
Molonglo 600 23,900 21,100 46,000 34,000
Majura 200 200 200 200 200
Queanbeyan 41,900 50,000 44,000 57,700 47,900
Jerrabomberra 700 700 700 700 700
Total 397,900 459,100 459,100 518,900 518,900Source: URS & ESDD. BAU estimates based on ACT Government Chief Minister and Cabinet Directorate projections
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 67
Table 30: Employment Projections by District
District 2011
BAU
2021
BAU
2021 Higher Density
2031
BAU
2031 Higher Density
Project Corridor 62,100 69,600 81,100 75,800 91,700
North Canberra Outer 14,000 15,900 13,200 17,800 16,400
Gungahlin Outer 2,000 3,700 6,000 4,700 3,600
Belconnen 27,500 29,500 28,100 30,400 29,400
South Canberra 48,400 51,700 48,500 56,200 55,900
Tuggeranong 18,000 20,200 18,000 20,900 18,700
Woden 27,900 29,200 25,300 30,000 30,100
Molonglo 100 2,300 3,500 6,300 5,100
Majura 7,900 10,300 8,700 14,200 10,000
Queanbeyan 10,700 12,500 12,100 13,800 9,500
Jerrabomberra 4,900 5,500 5,800 7,100 6,500
Total 223,500 250,400 250,400 277,400 277,400Source: URS & ESDD. BAU estimates based on ACT Government Chief Minister and Cabinet Directorate projections
3. Demand Modelling OutputsWhat demand model was used to generate the forecasts and who undertook the demand modelling?
The Canberra Strategic Public Transport Model (CSTM) was used as the basis to assess the demand impactforeachoption,whichismaintainedperiodicallybyESDD.CSTMisatypicalfour-stepStrategicPublicTransportdemandmodelcoveringtheACTandQueanbeyan.
SMECwascontractedbyESDDtopreparelanduseandnetworkassumptionsformodelling,runCSTMandprovidedemandoutputs.
What time period was modelled (for example a one hour AM peak on an average weekday, 24 hour period on an average weekday, etc.)
CSTM models a typical 2 hour weekday AM peak between 7am and 9am.
What expansion factor was used to translate the period of the day modelled into a daily observation? What expansion factor was used to translate the daily observation into an annual observation? What sources informed this expansion factor and / or what logic underpins it?
ArangeofexpansionandannualisationfactorsarerequiredtoconvertaverageweekdaypeakestimatesfromCSTMintoannualestimates.Thefollowingtableoutlinestherangeoffactorsused:
Table 31: Adopted Expansion Factors
Item AM Peak to Weekday Factor Weekday to Annual Factor
Public transport demand 4.74 280
Standardbusserviceprovision 5.43 286
Rapidtransitserviceprovision 5.00 336
Privatevehicledemand 4.74 300
ACT Government Environment and sustainable Development Directorate 68
What sources informed this expansion factor?
Thefollowingsourceswereusedtoinformtheestimationofexpansionandannualisationfactors.
Item Source
Public transport demand ATC Guidelines
Standardbusserviceprovision ACTIONBusesoperationaldata
Rapidtransitserviceprovision Basedonassumedoperatingpatterns
Privatevehicledemand ATC Guidelines
Servicepatternsforrapidtransit(BRTorLRT)serviceswereassumedtobedifferenttocurrentpublictransportservicepatterns.Bycomparisonwithcurrentservicepatterns,rapidtransitservicesareassumedtooperateathigherfrequencies,particularlyduringtheoff-peakandonweekends,andoperate for more hours of the day.
Does the model calculate new or “generated” trips (as opposed to using a fixed trip matrix)? How does the demand model deal with the issues of induced demand?
Theleveloftripgenerationisbasedonsocio-economicfactorsincludingage,incomeandstatus.TheleveloftripgenerationwithinagiventravelzoneinCSTMisonlydependentonthelevelofpopulationandemploymentaswellastheassumedsocio-economiccharacteristicsofpeopleresidingwithinthetravelzone.TheleveloftripgenerationwithinCSTMisnotdependentongeneralisedcosts,reductionsinwhichmaycreateadditionaltripsandincreasesinwhichmayleadtotripsbeingsuppressed.
4. Economic Model Parameters – Costs First year of construction / Last year of construction
Firstyearofconstruction:2014
Lastyearofconstruction:2017
State real discount rates used (if not 4, 7 and 10%), and the basis for any variation from these standard DRs
Arealdiscountrateof7%perannumwasadoptedwithsensitivityanalysisundertakenat4%and10%.
State appraisal period in years, and basis for its selection
Alleconomiccostsandbenefitswereevaluatedovera30yearoperatingperiod.
Remaining life of the initiative at the end of the appraisal period
BRTandLRToperationswithintheProjectCorridorhavebeenassumedtooperateasagoingconcernaftertheendoftheappraisalperiod.
Assetsofvaryingeconomiclifehavebeenaccountedforwithintheappraisal.Toreflectthelevelofeconomicliferemaininginassetsaftertheappraisalperiod,aresidualvaluehasbeenestimated.
Describe the basis for estimating all capital costs (for both base and project cases). Confidence level: are the construction costs P50, P90, P95?
CapitalcostshavebeendevelopedbytheProjectTeam’sengineeringadvisor,URS.Costestimatesreflectthatthelevelofdesignisatapre-conceptualorconceptscreeningstage.Inthesecircumstances,thetypicalrangeofaccuracyvariesbetweenalowrange(-30%to-15%)toahighrange(+20%to+50%).Basedonthepreliminarynatureoftheanalysisandthelackofadetailedengineeringdesignatthisstageoftheproject,theconfidencelevelassociatedwiththeconstructioncostsarelikelytobeconsistentwithaP50level.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 69
TheestimatesweregenerallyinaccordancewiththeCommonwealthDepartmentofInfrastructure,Transport,Regional,DevelopmentandLocalGovernment–BestPracticeCostEstimationforPubliclyFundedRoadandRailConstruction,19June2008,inparticularAppendix1&6.
The“EstimateClass”approachwasusedbasedonalevelofaccuracyofClass4(StudyorFeasibility).Itisimportanttonotethatthecostsarenotbasecosts,butshouldbeviewedasameancostwithanupper and lower probability, in our case Class 4.
Traditionally,benchmarkingisusedwhereappropriatetoestablisharangeofexpectedcostsandcostratiosforcomparisonpurposes.Inadditionitprovidesappropriatecostdatawherespecificdetailisnotreadilyavailablesuchashighlevelpre-conceptevaluation.ExamplesofbenchmarkingprojectsincludetheConstitutionAvenueUpgradeProject,GoldCoastRapidTransit,andtheMelbourneHoddleStreetPlanning Study.
Wherebenchmarkingrateswerenotused,RawlinsonsConstructionCostGuidewasused.Inestimatingthecoststhefollowingfactorshavebeenincluded:
• Direct Cost-Thedirectcostrepresentstheconstructioncostsoftheworksandspecificallycoversthe costs of plant, labour, materials and specialist subcontractors.
• Indirect Costs -Theindirectcostrepresentsthedesign,mobilisationandgovernmentcosts,whereapplicable.
EstimateshavebeentechnicallyreviewedinternallyatURSbutnotreviewedbyanindependentorganisation.Thisisconsistentwiththeconceptscreeningstageofaprojectandtheclientrequirements.AnindependentreviewofestimateswillberequiredduringtheFeasibilityandForwardDesign phase of the project.
The phase for this project is assumed to be between Project Identification & Project Scoping, with a contingency risk on Base Estimate of +40% to +60% & +25% to +40% respectively
ThiscorrelateswiththeEstimateClassapproachasstatedabove,butnegatesthepossibilitythatthecostsfortheprojectcouldbelessthantheBaseEstimate.Itisimportanttonotethatthecosts,asindicatedinourCostEstimate,areNOTbasecosts,butshouldbeviewedasameancostwithanupperand lower probability, in this case Class 4.
What rate of escalation has been assumed over the construction period?
Unitcostratesareassumedtoremainconstantacrosstheevaluationperiod.
What is the profile of the capital cost spending, for example: year 1 – 10%, year n – X%. Who were the capital cost estimates prepared by? Have they been independently verified?
Table32showsaprofileofcapitalspendingbytimeperiod.AproportionofcapitalspendingisincurredduringYear31–40toreflectthereplacementoflifeexpiredassets(e.g.track,signalling)justpriortothe end of the appraisal period.
Table 32: Breakdown of Capital Costs (Undiscounted)
Period throughout the appraisal period incurred with the replacement of life expired assets and staging costs BRT LRT
Year 1 – 10 77.2% 76.5%
Year 11 – 20 2.0% 1.4%
Year 21 – 30 12.5% 5.0%
Year 31 – 40 8.3% 17.2%
Total 100.0% 100.0%
ACT Government Environment and sustainable Development Directorate 70
CostestimateswerepreparedbyURS.Noindependentverificationofthecapitalcostshasbeenundertaken.
Describe the initiative’s out turned costs ($M, nominal, undiscounted)
Table33showsupfrontoutturncostsaswellastotaloutturncosts.Totaloutturncostsreflectcostsincurredwiththereplacementoflifeexpiredassetsduringtheappraisalperiod.
Table 33: Outturn Costs (Undiscounted)
Item BRT LRT
Upfrontoutturncosts $276m $615m
Totaloutturncosts $358m $804m
Economic costs:Describe and justify any adjustments made to the initiative’s out turned costs to generate an economic project cost
Noadjustmentshavebeenmadetotheinitiativesoutturnedcoststogenerateaneconomicprojectcosts.Unitcostratesusedwereexclusiveoftaxesandprofitmargin.
Economic cost - $M, real, undiscounted; and $M, real, discounted (using a real 7.0% discount rate)
Table 34 shows discounted and undiscounted capital costs for BRT and LRT.
Table 34: Undiscounted and Discounted Capital Costs
Item BRT LRT
Undiscounted capital costs $358m $804m
Discounted capital costs $215m $470m
Residual value - State the size of the residual value, economic lives of the assets included in the residual value and the methodology used to generate it (see note above for methodology).
Assumedassetlives,usedtoassessthetimingofrecurrentcapitalexpenditureandresidualvalues,areshown as follows:
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 71
Table 35: Assumed Effective Lives
Asset Assumed Asset Life
Planning
Enabling works Nil
Preliminaries and design Nil
Governmentcosts Nil
Other general planning and management Nil
Trafficmanagementandtemporaryworks Nil
Below rail infrastructure
Track work 30
Roadway
Busway 40
Road infrastructure 40
Bridges 100
Segregated Rapid Transport Lanes 40
Road works 40
Drainage 100
Cycle Lanes 60
Footpaths 60
Utilities 50
Electrical
Signalling 15
Powersupply,transformersandsub-stations 40
Other electrical and mechanical systems 15
Passenger interface and communications
Passengerticketing 15
Passengerinformationdisplaysandplatformcontrolsystems 10
Vehicle monitoring systems 10
Bus stops 20
Busandlightrailstations 50
Other buildings and structures 100
Fleet
Busfleet 20
Light rail rolling stock 35 Source: Deloitte assumptions based on ATC (2006d) and ATO (2011)
ACT Government Environment and sustainable Development Directorate 72
Forlonglastingcapitalassets,someeconomiclifewillremainfollowingtheevaluationperiod.Thevalueoftheremainingeconomiclifeisderivedona‘straightline’basisusingthefollowingformula:
Residual Value= (EconomicLife–EvaluationPeriod)×CapitalExpenditure (Economic Life)
Resultantdiscountedresidualvalueestimatesareshownasfollows:
Table 36: Residual Value by Option (Discounted)
Option Discounted ($m)
BRT $9
LRT $23
Maintenance costs - Describe the basis for estimating all maintenance costs, including growth rates over time (for both base and project cases). Are the maintenance costs P50, P90, P95? What is the basis for this estimate and who prepared the maintenance cost estimates?
Table37outlinestheassumedassetmaintenanceratesusedintheProjectBusinessCase,whichhavebeenkeptconstantinrealtermsovertheappraisalperiod.
Table 37: Asset Maintenance Cost Rates
Asset Maintenance Component Unit Rate Source
Annual BRT lane maintenance cost $450,000 URS
Annual LRT infrastructure maintenance cost $78,918 per track kilometre Australian Transport Council Guidelines
Light rail maintenance costs were indexed to June 2011 prices using the Road and Construction Cost Index
Replacement - Is there a need to replace or refurbish major components of the infrastructure / rolling stock during the appraisal period? If so, how are these replacement or refurbishment costs captured?
Anumberofassetswereassumedtohaveaneconomiclifeoflessthan30years.Accordingly,theseassets were assumed to be replaced at the end of their economic life at the cost incurred when they werefirstacquired.
Operating costs - Describe the basis for estimating all operating costs, including growth rates over time (for both base and project cases). Who were the operating cost estimates prepared by? Have they been independently verified?
Operatingcostswerebasedonaservicekilometrebasis.PublictransportservicekilometresandhoursestimatedbyCSTMweredisaggregatedbystandardbus,BRTandLRT.
Operatingcostswereinclusiveof:
• Directcosts:driverlabourcosts,fuel,electricityandotherconsumables• Overheads:costsassociatedwithoperationsoverheads(scheduling,rostering,driversupervisionand
depotrelatedcosts),vehiclemaintenanceoverheads(engineeringtechnologyservices),headofficecosts(highermanagementfunctions)andgenerallabourandnon-labouroverheads(informationtechnology, human resources, insurance).
EstimatesofservicekilometreoperatingcostswerebasedontheassumptionsshowninTable38andTable 39, which are broadly based on Australian Transport Council Guidelines.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 73
Table 38: Operating Cost Parameters
Variable Bus BRT LRT
On-vehiclecrewcosts($/hr) $30.00* $30.00* $76.40
Standardvehicleoperatingcosts($/km) $1.03 $1.03 $1.71
Articulatedvehicleoperatingcosts($/km) $1.29 $1.29
Proportionofarticulatedvehicles 5% 5%
Overheads(%onothercosts) 21% 21% 17.5%Vehicle operating costs, overheads and profit margins are based on ATC (2006c). Hourly bus wages are based on ACTION Buses. All values were indexed to June 2011 prices using changes in the Producer Price Index (vehicle operating costs) and Average Weekly Earnings (light rail crew costs). The proportion of articulated vehicles used reflects the current composition of the ACTION Bus fleet (ACTION Bus Wiki 2012).
Table 39: Dead Running and Layover Assumptions
Variable Bus BRT LRT
Peak dead running allowance 25% 25% 20%
Off-peakdeadrunningallowance 25% 5% 5%
Layoverallowance 5 min 5 min 5 minPeak dead-running statistics are based on current ACTION Buses levels of dead running whilst LRT levels of dead running are based on ATC (2006d). Off-peak dead-running is assumed to be equal to peak dead running for standard bus services whilst ATC (2006d) estimates have been used for BRT and LRT off-peak dead running. Layover allowances are based on ATC (2006d). Average service speeds are assumptions.
Table40showsthefinaloperatingcostratesusedbymode,whichwerekeptconstantinrealtermsforall years.
Table 40: Operating Cost Rate
Variable Bus BRT LRT
OperatingCostRate($/km) $3.98 $3.47 $6.06Operating cost rates were estimated by Deloitte based on ATC Guideline rates.
5.EconomicModelParameters–BenefitsBenefits ramp up - Describe how benefits ramp up over the construction period. What source and/or assumptions inform this ramp up?
Noramp-uphasbeenappliedtothebenefits.Itwouldbeanticipatedthatasanestablishedtransportcorridor(albeitwithsignificantanticipatedpopulationgrowthatthenorthernend),aramp-upperiodwouldlikelytobesmallineffect(>90%ofbenefits)andshortinduration(lessthan2years).
Cost and benefit time streams - Attach an appendix showing the time stream for each benefit and cost component ($M, real, undiscounted)
Costandbenefitstreamsovertheappraisalperiodareprovidedattheendofthistemplate.
Generalised trip cost - has generalised trip cost (GTC) been calculated on an origin – destination (OD) basis within the demand model, or using aggregate outputs from the demand model?
AlltraveltimebasedbenefitshavebeenbaseddirectlyoffdemandandtimeskimsprovidedbySMEC.Traveltimesweredisaggregatedbymodeandtypeofuserusingthesetofequationsshownbelowtofacilitatetheapplicationofthe‘ruleofhalf’.
ACT Government Environment and sustainable Development Directorate 74
Equation 3: Assessing Changes in Travel Time for a Given Mode k
Q: number of users C: generalised journey time (composite of IVT, wait, walk, boarding time and transfers) i: origin travel zone j: destination travel zone k: mode
AllotherbenefitsarebasedonaggregateoutputsfromCSTM,whichultimatelyarebasedonchangesindemandandtraveltimebyeachorigin-destinationpair.
Value of travel time: Commuter travel - What is the value of travel time used for this initiative? Does this value differ between modes? Is this value based on resource cost or willingness to pay? Business travel - Has a specific value been applied to business travel? If so, what was this value?
AcommonvalueoftimehasbeenadoptedforallmodelledtrippurposesusingthemethodologyoutlinedbyAustroads(2011).TheAustroadsapproachassumesthatvaluesoftimeareaproportionofaverageearnings,assumingthat:
• Forpersonaltravel,thevalueoftimeis40%oftheaveragehourlywage• Forbusinesstravel,thevalueoftimeforbusinesstravel(excludingcommercialvehicletravel)isvalued
at128%oftheaveragehourlywage.
• UsingtheAustroadsapproachandMay2011totalACTordinaryweeklyearningsforfulltimeadults(seasonallyadjusted)of$1306.90,thevalueoftimewascalculatedtobe$16.78perpassengerhour.
Growth - Has any rate of escalation been applied to these values?
Thevalueoftimehasbeenassumedtoremainconstantinrealtermsovertheappraisalperiod.
Source - What are the sources for the values used and any assumptions incorporated into the value of travel time?
Earnings data has been sourced from the ABS. The following table outlines the approach and assumptionsusedtocalculatetheaveragevalueoftime:
Table 41: Derivation of Value of Time
Variable Value
May2011totalordinaryweeklyearningsforfulltimeadults,seasonallyadjusted $1,306.90
Assumed working hours per week 38
Averagehourlywage $34.39 per hour
Personalvalueoftime(40%ofaveragehourlywage)perpassengerhour $13.76 per hour
Businessvalueoftime(128%ofaveragehourlywage)perpassengerhour $44.02 per hour
Assumedproportionofbusinesstravel 10.0%
Weightedvalueoftimeperpassengerhour $16.78 per hour
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 75
Weightings - Describe the weightings which have been used to calculate the generalised trip cost. Wait / Access / Egress - What weighting has been applied to egress time? What is the source for this? Transfer - What transfer penalty has been applied? What is the source of this? Boarding penalty - Has a boarding penalty been applied during the demand modelling and / or economic appraisal? If so, what is the magnitude of this boarding penalty (minutes) and how does it differ between modes?
GeneralisedjourneytimeskimsextractedfromCSTMweightanytransfersaswellasanywalk,waitorboardingtimeincurredwhilsttravellingonpublictransport.Thefollowingtableoutlinestheweightsused within CSTM:
Table 42: CSTM Out-of-Vehicle Time Weights
Time Component Weight relative to IVT
In-vehicletime 1.00
Walkaccesstime 1.15
Waittime 1.20
Boardingtime 1.20
Interchange penalty 7 minutesSource: MRC (2009) – ACT Strategic Public Transport Network Plan
Benefitparameters-Listthevalueandsourceofallbenefitparametersrelevanttotheappraisal.Forexampledecongestion;VehicleOperatingCosts(forallclassesofvehicles);Crashcostsetc.
Thefollowingparametersweresourcedtoassessthefollowingbenefitstreams:
• Traveltimesavings
• Incrementalfarerevenue
• Incremental parking costs
• Unperceivedvehicleoperatingcosts
• Road damage• Environmentalexternalities
Allvaluesarein2011prices.
Table 43: Key Benefit Parameters
Variable Value Source
Value of time $16.78 per passenger hour Austroads (2011)9
Unperceived vehicle operating costs 14.9centspervehiclekm RTA (2009)10
Incremental fare revenue
Incremental fare $1.19 per trip ACTION Buses MyWay data
Incremental parking revenue
2011 Parking Costs
City $0.750pervehicletripperhour MCR (2009)
Other town centres $0.375pervehicletripperhour MCR (2009)
2021 BAU Parking Costs
City $0.980pervehicletripperhour Projectassumption
ACT Government Environment and sustainable Development Directorate 76
Variable Value Source
Other town centres $0.490pervehicletripperhour Projectassumption
2021 Do-Something Parking Costs
City $1.880pervehicletripperhour Projectassumption
Other town centres $0.940pervehicletripperhour Projectassumption
2031 BAU Parking Costs
City $1.690pervehicletripperhour Projectassumption
Other town centres $0.840pervehicletripperhour Projectassumption
2031 Do-Something Parking Costs
City $2.850pervehicletripperhour Projectassumption
Other town centres $1.430pervehicletripperhour Projectassumption
Road damage
Car 0.241centspervehiclekm RailCorp (2010)11
Bus 2.830centspervehiclekm RailCorp (2010)
Air Pollution
Car 2.880centspervehiclekm ARRB (2011)12
Bus 32.386centspervehiclekm ARRB (2011)
Light rail 0.394centspervehiclekm ARRB (2011)
Greenhouse Gas Emissions
Car 2.269centspervehiclekm ARRB (2011)
Bus 13.344centspervehiclekm ARRB (2011)
Light rail 0.031centspervehiclekm ARRB (2011)
Noise Pollution
Car 0.943centspervehiclekm ARRB (2011)
Bus 2.269centspervehiclekm ARRB (2011)
Light rail 0.166centspervehiclekm ARRB (2011)
Accident Costs
Car $58,139permillionvehiclekm RTA (2009)
Bus $93,975permillionvehiclekm RTA (2009)
Light rail permillionvehiclekm RailCorp (2010)
Related initiatives - Are the benefits and costs closely related to, dependent upon or potentially influenced by another initiative(s)? If so, explain how that has been accounted for in the BCR.
As part of the Frequent Network, the Project Corridor may form part of a broader network of BRT or LRT servicesinthelongterm.
However,atthetimeoftheappraisaltheimpactofotherpotentialinitiatives(e.g.CitytoBelconnenTransitway)werenotassessedcollectivelywiththeProjectOptions.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 77
AppraisalSummaryTable2:MonetisedCostBenefitAnalysisResultsThefollowingdemandmetricsareprovidedinTable44forthefirstandfinalmodelyears,2011and2031:
• Number of trips by mode
• Averagejourneytimebymode
• PT mode share
• Publictransportfarerevenue
• Numberofkilometrestravelledbymode• Numberofhourstravelledbymode
Table 44: High Level Demand Model Results
Year 2011 2031
Land Use BAU BAU Higher Density
Mode BAU BAU BRT LRT BRT LRT
Passenger trips
Public transport 16,900 38,400 43,600 43,700 43,700 43,800
Car 239,300 291,300 286,500 286,300 285,600 285,400
Total passenger trips 256,200 329,700 330,100 330,000 329,300 329,200
Average journey time (mins)
Public transport 62.3 57.4 55.7 55.5 53.6 53.5
Car 12.4 12.8 12.5 12.5 11.4 11.4
PT Mode Share 6.6% 11.6% 13.2% 13.3% 13.3% 13.3%
PT Fare Revenue $20,100 $45,600 $51,800 $52,100 $52,000 $52,200
Passenger kilometres travelled
Public transport 210,100 506,100 591,700 596,500 574,400 579,300
Car(driveronly) 1,870,800 2,072,900 2,032,600 2,030,300 1,959,600 1,957,400
Passenger hours
Public transport 17,500 36,700 40,400 40,400 39,000 39,100
Car 49,400 62,300 59,500 59,400 54,300 54,200
Total passenger hours 66,900 99,000 99,900 99,800 93,300 93,300
Change in passenger hours
PTpassengerhours-contusers -1,100 -1,200 -800 -800
PTpassengerhours-newusers 6,400 6,600 16,500 16,600
PTpassengerhours-lostusers -1,600 -1,600 -13,400 -13,400
Carpassengerhours-contusers -1,500 -1,500 -3,000 -3,000
Carpassengerhours-newusers 1,700 1,800 18,400 18,300
Carpassengerhours-lostusers -3,000 -3,100 -23,400 -23,400Estimates rounded to nearest hundred
ACT Government Environment and sustainable Development Directorate 78
Total%agechangesbydemandmetricbetween2011and2031areshownbelow:
Table 45: Change in Demand Metrics (2031 versus 2011)
Land Use BAU Higher Density
Mode BAU BRT LRT BRT LRT
Passenger trips
Public transport 127.0% 157.8% 158.9% 158.5% 159.5%
Car 21.7% 19.7% 19.6% 19.3% 19.2%
Total passenger trips 28.7% 28.8% 28.8% 28.5% 28.5%
Average journey time (mins)
Public transport -7.7% -10.6% -10.9% -13.9% -14.1%
Car 3.6% 0.7% 0.5% -7.9% -8.1%
PT Mode Share (percentage point change) 5.0% 6.6% 6.7% 6.7% 6.7%
PT Fare Revenue 127.0% 157.8% 158.9% 158.5% 159.5%
Passenger kilometres travelled
Public transport 140.9% 181.6% 183.9% 173.4% 175.8%
Car(driveronly) 10.8% 8.6% 8.5% 4.7% 4.6%
Passenger hours
Public transport 109.5% 130.6% 130.7% 122.5% 123.0%
Car 26.1% 20.5% 20.3% 9.9% 9.6%
Total passenger hours 47.9% 49.3% 49.2% 39.4% 39.3%
Benefit Cost Analysis Results Table46toTable49provideheadlinebenefit-costanalysisresultsforthefollowingfouroptions:
• BRT under a business as usual land use scenario
• LRT under a business as usual land use scenario
• BRT under a higher density land use scenario• LRT under a higher density land use scenario
Allvaluesarebasedon2011prices.
Table 46: Benefit-Cost Analysis Results (BRT under a Business As Usual Land Use Scenario)
Metric Real Discount Rate
4% 7% 10%
BCR 2.71 1.98 1.48
NPV ($m) $536.2 $243.3 $98.7
NPVI $1.50 $0.68 $0.28
IRR 14.6% 14.6% 14.6%
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 79
Table 47: Benefit-Cost Analysis Results (LRT under a Business As Usual Land Use Scenario)
Metric Real Discount Rate
4% 7% 10%
BCR 1.43 1.02 0.75
NPV ($m) $283.2 $10.8 -$110.1
NPVI $0.35 $0.01 -$0.14
IRR 7.2% 7.2% 7.2%
Table 48: Benefit-Cost Analysis Results (BRT under a Higher Density Land Use Scenario)
Metric Real Discount Rate
4% 7% 10%
BCR 6.65 4.78 3.51
NPV ($m) $1,774.4 $939.1 $514.8
NPVI $4.95 $2.62 $1.44
IRR 26.7% 26.7% 26.7%
Table 49: Benefit-Cost Analysis Results (LRT under a Higher Density Land Use Scenario)
Metric Real Discount Rate
4% 7% 10%
BCR 3.31 2.34 1.69
NPV ($m) $1,512.7 $701.1 $302.5
NPVI $1.88 $0.87 $0.38
IRR 15.7% 15.7% 15.7%
Monetised Cost and Benefits
Table50toTable53provideabreakdownofbenefitsandcostsforthefollowingfouroptions:
• BRT under a business as usual land use scenario
• LRT under a business as usual land use scenario
• BRT under a higher density land use scenario• LRT under a higher density land use scenario
Allvaluesarebasedon2011prices.
ACT Government Environment and sustainable Development Directorate 80
Table 50: Breakdown of Discounted Costs and Benefits (BRT under a Business As Usual Land Use Scenario)
Cost/Benefit Element Value in $m (Discounted at 7%)
Contribution
Capitalexpenditure 215.3 86.6%
Operatingandmaintenanceexpenditure 33.2 13.4%
Total Costs 248.5 100.0%
Changeingeneralisedjourneytime 133.9 27.2%
Incrementalfarerevenue 52.0 10.6%
Incrementalparkingrevenue 198.3 40.3%
Unperceivedvehicleoperatingcostsavings 57.1 11.6%
Avoidedaccidentcosts 21.7 4.4%
Avoidedairpollution 8.4 1.7%
Avoidedgreenhousegasemissions 7.6 1.5%
Avoidednoisepollution 3.4 0.7%
Avoidedroaddamage 0.7 0.1%
Residualvalue 8.7 1.8%
Total Benefits 491.8 100.0%
Table 51: Breakdown of Discounted Costs and Benefits (LRT under a Business As Usual Land Use Scenario)
Cost/Benefit Element Value in $m
(Discounted at 7%)
Contribution
Capitalexpenditure 469.8 89.6%
Operatingandmaintenanceexpenditure 54.3 10.4%
Total Costs 524.1 100.0%
Changeingeneralisedjourneytime 150.0 28.0%
Incrementalfarerevenue 53.8 10.1%
Incrementalparkingrevenue 198.2 37.1%
Unperceivedvehicleoperatingcostsavings 60.4 11.3%
Avoidedaccidentcosts 23.8 4.4%
Avoidedairpollution 11.7 2.2%
Avoidedgreenhousegasemissions 9.3 1.7%
Avoidednoisepollution 3.8 0.7%
Avoidedroaddamage 1.0 0.2%
Residualvalue 22.9 4.3%
Total Benefits 534.9 100.0%
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 81
Table 52: Breakdown of Discounted Costs and Benefits (BRT under a Higher Density Land Use Scenario)
Cost/Benefit Element Value in $m
(Discounted at 7%)
Contribution
Capitalexpenditure 215.3 86.6%
Operatingandmaintenanceexpenditure 33.2 13.4%
Total Costs 248.5 100.0%
Changeingeneralisedjourneytime 622.6 52.4%
Incrementalfarerevenue 51.7 4.3%
Incrementalparkingrevenue 192.7 16.2%
Unperceivedvehicleoperatingcostsavings 174.0 14.7%
Avoidedaccidentcosts 67.7 5.7%
Avoidedairpollution 31.1 2.6%
Avoidedgreenhousegasemissions 25.6 2.2%
Avoidednoisepollution 10.9 0.9%
Avoidedroaddamage 2.6 0.2%
Residualvalue 8.7 0.7%
Total Benefits 1,187.6 100.0%
Table 53: Breakdown of Discounted Costs and Benefits (LRT under a Higher Density Land Use Scenario)
Cost/Benefit ElementValue in $m
(Discounted at 7%)Contribution
Capitalexpenditure 469.8 89.6%
Operatingandmaintenanceexpenditure 54.3 10.4%
Total Costs 524.1 100.0%
Changeingeneralisedjourneytime 633.7 51.7%
Incrementalfarerevenue 53.3 4.4%
Incrementalparkingrevenue 192.5 15.7%
Unperceivedvehicleoperatingcostsavings 177.2 14.5%
Avoidedaccidentcosts 69.7 5.7%
Avoidedairpollution 34.5 2.8%
Avoidedgreenhousegasemissions 27.2 2.2%
Avoidednoisepollution 11.3 0.9%
Avoidedroaddamage 2.9 0.2%
Residualvalue 22.9 1.9%
Total Benefits 1,225.2 100.0%
ACT Government Environment and sustainable Development Directorate 82
Detailed Monetised BenefitsTable54detailsrealbutundiscountedbenefitsbyscenariobybenefitstreamfor2021and2031incrementaltothebasecase.Ayear-by-yearbreakdownofbenefitsaswellascostforeachoptionisprovidedattheendofthisdocument.
Table 54: Real Undiscounted Benefits by Scenario for Selected Years ($m)
Benefit StreamBRT (BAU) LRT (BAU) BRT (BAU) LRT (BAU)
2021 2031 2021 2031 2021 2031 2021 2031
Change in generalised time $10.9 $22.3 $12.6 $24.6 $12.6 $24.6 $40.2 $115.3
UnperceivedVOCsavings $5.8 $8.5 $6.1 $9.0 $6.1 $9.0 $20.2 $24.3
Road damage $0.1 $0.1 $0.1 $0.1 $0.1 $0.1 $0.3 $0.4
Incrementalfarerevenueresource cost adjustment $4.9 $8.0 $5.1 $8.3 $5.1 $8.3 $4.8 $8.4
Incremental parking revenueresourcecostadjustment
$26.6 $23.7 $26.6 $23.7 $26.6 $23.7 $25.0 $23.7
Avoidedaccidentcosts $2.2 $3.2 $2.4 $3.5 $2.4 $3.5 $8.0 $9.6
Avoidedairpollution $0.8 $1.3 $1.2 $1.7 $1.2 $1.7 $3.9 $4.7
Avoidedgreenhousegasemissions $0.7 $1.2 $0.9 $1.4 $0.9 $1.4 $3.1 $3.7
Avoidednoisepollution $0.3 $0.5 $0.4 $0.6 $0.4 $0.6 $1.3 $1.5
Residualvalue $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
Table 55: Derivation of Generalised Journey Time Benefits
ElementBRT under a
BAU Land Use Scenario
LRT under a BAU Land Use
Scenario
BRT under a Higher Density
Land Use Scenario
LRT under a Higher Density Land Use
Scenario
Demand model output Generalisedjourneytimeinin-vehicletraveltimeequivalentterms,disaggregatedbycontinuing,newandlostusersandbymode
Valuationparameterusedand source
Valueofpassengertimeof$16.78 (based on Austroads 2011 methodology and ABS AWE data)
Algorithm used
$M (undiscounted) in 2021 $10.9 $12.6 $12.6 $40.2
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 83
Table 56: Derivation of Unperceived Vehicle Operating Cost Benefits
ElementBRT under a
BAU Land Use Scenario
LRT under a BAU Land Use
Scenario
BRT under a Higher Density
Land Use Scenario
LRT under a Higher Density
Land Use Scenario
Demand model output Changesincarvehiclekilometres
Valuationparameterusedand source
$0.149pervehiclekilometre(basedonRTA2009)
Algorithm used ∆UnperceivedVOC=∆CarVKT×$0.149
$M (undiscounted) in 2021 $5.8 $6.1 $6.1 $20.2
Table 57: Derivation of Road Damage Benefits
ElementBRT under a
BAU Land Use Scenario
LRT under a BAU Land Use
Scenario
BRT under a Higher Density
Land Use Scenario
LRT under a Higher Density
Land Use Scenario
Demand model output Changesincarandbusvehiclekilometres
Valuationparameterusedand source
$0.00241 per kilometre for cars and $0.02830 per kilometre for buses (based on RTA 2009)
Algorithm used ∆RoadDamage=∆CarVKT×$0.00241+∆BusVKT×$0.02830
$M (undiscounted) in 2021 $0.1 $0.1 $0.1 $0.3
Table 58: Derivation of Incremental Fare Revenue Resource Correction
ElementBRT under a
BAU Land Use Scenario
LRT under a BAU Land Use
Scenario
BRT under a Higher Density
Land Use Scenario
LRT under a Higher Density
Land Use Scenario
Demand model output Change in public transport patronage
Valuationparameterusedand source
$1.19pertrip(basedonanalysisofMyWaybusfaredataprovidedbyACTIONBuses)
Algorithm used Incrementalfarerevenue=∆publictransporttrips×$1.19
$M (undiscounted) in 2021 $26.6 $26.6 $26.6 $25.0
ACT Government Environment and sustainable Development Directorate 84
Table 59: Derivation of Environmental Externality (Air Pollution, Greenhouse Gas and Noise Pollution) Benefits
ElementBRT under a
BAU Land Use Scenario
LRT under a BAU Land Use
Scenario
BRT under a Higher Density
Land Use Scenario
LRT under a Higher Density
Land Use Scenario
Demand model output Changeincar,busandlightrailvehiclekilometres
Valuationparameterusedand source
Valuationsareincentspervehiclekilometre(ARRB2011). Railexternalityrateshavebeenusedforlightrail.
Externalities Car Buses Light RailAirpollution 2.880 32.386 0.394Greenhouse 2.269 13.344 0.031Noise 0.943 2.269 0.166
Algorithm used Externalitybenefit(forcars)=∆VKT×(0.00288+0.00269+0.00943)
Externalitybenefit(forbuses)=∆VKT×(0.32386+0.13344+0.02269)
Externalitybenefit(forlightrail)=∆VKT×(0.00394+0.00031+0.00166)
$M (undiscounted) in 2021 $1.80 $2.50 $2.50 $8.30
Table 60: Derivation of Parking Revenue Resource Correction
Element BRT under a BAU Land Use Scenario
LRT under a BAU Land Use Scenario
BRT under a Higher Density Land Use
Scenario
LRT under a Higher Density Land Use
Scenario
Demand model output Changeincartripstoselectedtravelzones(City,BelconnenTownCentre, Woden Town Centre, Tuggeranong Town Centre and Queanbeyan Town Centre)
Valuationparameterused and source
Parking rates are an input into CSTM. The following rates (for a 2 hour period) were assumed for 2021 and 2031:
Town Centre2021 2031
BAU Do-Something Differential BAU Do-
Something Differential
Civic $1.97 $3.75 $1.78 $3.38 $5.70 $2.33Belconnen $0.98 $1.88 $0.89 $1.69 $2.85 $1.16Woden $0.98 $1.88 $0.89 $1.69 $2.85 $1.16Tuggeranong $0.98 $1.88 $0.89 $1.69 $2.85 $1.16Queanbeyan $0.98 $1.88 $0.89 $1.69 $2.85 $1.16
Algorithm used Incrementalparkingrevenue(bycentre)= continuingcartrips×∆price+∆cartrips×price
$M (undiscounted) in 2021 $26.6 $26.6 $26.6 $25.0
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 85
AppraisalSummaryTable3:Benefit-CostRatioSensitivityTesting
Thefollowingsensitivitytestswereundertaken:
• Lowerdiscountrate(4%)
• Higherdiscountrate(10%)
• Lowerconstructioncosts(30%)
• Higherconstructioncosts(+30%)
• Lowercardemandannualisationfactor(270)
• Highercardemandannualisationfactor(330)
• Longerevaluationperiod(50years)• Nodiscounting
TheresultsofthesensitivitytestsforalloptionsareshowninTable61:
Table 61: Sensitivity Test Results
Sensitivity Test Number
Variation BRT with BAU Land
Use
LRT with BAU Land
Use
BRT under Higher Density
Land Use
LRT under Higher Density
Land Use
Starting result 1.98 1.02 4.78 2.34
1 Lowdiscountrate(4%) 2.71 1.43 6.65 3.31
2 Highdiscountrate(10%) 1.48 0.75 3.51 1.69
3 Lowcapitalcosts(-30%) 2.66 1.38 6.44 3.18
4 Highercapitalcosts(+30%) 1.58 0.81 3.80 1.85
5 Lowcarannualisationfactor(270) 1.80 0.93 4.34 2.13
6 Highcarannualisationfactor(330) 2.16 1.11 5.22 2.55
7 50yearevaluationperiod 2.13 1.08 5.25 2.55
8 No discount rate 4.14 2.26 10.33 5.21
9 Noparkingrevenuebenefits 1.18 0.64 4.00 1.97
10 Lowcostandhighbenefits (Combinationof3&6) 2.90 1.50 7.04 3.47
11 Highcostandlowbenefits (Combinationof4&5) 1.44 0.75 3.45 1.69
ACT Government Environment and sustainable Development Directorate 86
AppraisalSummaryTable4:Non-MonetisedBenefitsandCosts
Cost/Benefit Description Rating
Improvedhighwaytraveltimereliability
TheProjectisexpectedtogeneratesomeimprovementinhighwaytraveltimereliabilitybenefitsastheProjectwillgeneratesomemodeshiftfromthehighwaynetworktothepublictransportnetwork.Inturn,theresultantreductioninroadcongestionshouldalsoservetoreducehighwaytraveltimevariability.
Moderately beneficial
Public transport traveltimereliability
Theprovisionofadedicatedrightofwayforpublictransportservicesislikelytoleadtoanimprovementintraveltimereliabilityofservices.Withservicesseparatedfromgeneraltraffic,servicesarelessexposedtoprevailingroadcongestionandincidents,leadingtomoreservicesrunningon-timeandwhereservicesdorunlate,averagedelaysarelikelytobelower.Withimprovedflow,busesarelesslikelytobunchup,improvingtheeffectivenessofprovidingahighservicefrequency.
Overtimeimprovementsintraveltimereliabilitycangeneratespilloverimpacts.Improvementsinreliabilitycanpotentiallyincreasepublictransportpatronageandbringaboutassociatedspilloverbenefitsincludingroaddecongestion,avoidedenvironmentalimpactsandavoidedaccidentcosts.
Overthemediumtolongterm,improvedreliabilitywouldallowACTIONBusestoreducetimetableslackandlayovertimethatwouldotherwisecompensateforunreliability.Inturn,improvedtimetableschedulingandresourcingcouldcontributetoimprovingtheoverallrobustnessandreliabilityofthenetwork,aswellasimprovingtheefficiencyofoperationsbymoreefficientplacementofassetsandmaximisingtheirutilisationthroughbetterallocationandacquisitionoffleet,labour,equipmentandotherresources.
Highly beneficial
Passenger amenity benefits
Relativetoconventionalbusservices,BRTandLRToperationsaregenerallyperceivedbyusersandnon-userstobemoredesirable.Theseamenitybenefitsarisefromimprovementsinserviceattributesoverandabovesavingsingeneralisedjourneytimeincluding:
• Greatervisibility
• Improvednetworklegibility
• Improvedridecomfort
• Widerrangeoffacilitiese.g.security,improvedlighting
Theseamenityimprovementsmaybesufficientlyhightogenerateadditionaldemandabovepredicteddemandlevels.
GiventhepreliminarynatureofthefeasibilityanalysiscommissionedbyESDD,noformalproductdefinitionwaspreparedfromwhichtoquantitativelyassessthelevelofpassengeramenitybenefits.ShouldtheProjectproceedtoamoredetailedfeasibilitystage,aformalproductdefinitionwouldprovideopportunitiestoassessthelevelofpassengeramenitybenefitsfromaninvestmentinBRTorLRT.
Moderately beneficial
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 87
Cost/Benefit Description Rating
Park and ride opportunities
TheProjectteamhasidentifiedaneedtomake,subjecttofurtherinvestigation,aprovisionforparkandridesites.Parkandridefacilitiesincreasethe catchment range of a rapid transit system by drawing demand from areas thatmayotherwisebepoorlyservicedbyfeederservices.Itmayalsogeneratedemandfrompassengerswhomaychoosenottousefeederservicestoaccessthe rapid transit network.
Throughimprovementsinaccessibilitytotherapidtransitsystem,parkandridefacilitiesmaygenerateadditionaldemand.Thissaid,furtherinvestigationisrequiredtoensurethattheeconomicbenefitsofprovidingparkandridefacilitiesdoesnotdivertsignificantdemandawayfromfeederservicesandthattheincrementalbenefitsexceedtothecostsofdeveloping,maintainingandoperatingtheparkandridesites.
Moderately beneficial
Improvedwalkand cycling access
TheProjectmakesaprovisionfootpathandcyclepathworkstoimproveactivetransportinfrastructureandimprovewalk/cycleaccessibilitytotherapidtransitcorridor.
Throughimprovementsinaccessibilitytotherapidtransitsystem,improvedwalkingandcyclingfacilitiesmayincreasethepotentiallevelofdemandforBRTandLRTservices.
Slightly beneficial
ACT Government Environment and sustainable Development Directorate 88
Appraisal Summary Table 5: Information SourcesACTChiefMinisterandCabinetDirectorate(undated),Planningdatastatistics,accessiblefromhttp://www.actpla.act.gov.au/tools_resources/research_based_planning_for_a_better_city/planning_data
ACTION Bus Wiki, ACTION Fleet Summary, http://www.actbus.net/fleetwiki/index.php?title=ACTION_Fleet_Summary
ARRB(2011),GuidetoProjectEvaluation–Part4:ProjectEvaluationData(UpdateRUEUnitValues),Austroads Project TP1672, August 2011
ATC (2006a), National Guidelines for Transport System Management in Australia – Volume 1
ATC (2006b), National Guidelines for Transport System Management in Australia – Volume 2
ATC (2006c), National Guidelines for Transport System Management in Australia – Volume 3
ATC (2006d), National Guidelines for Transport System Management in Australia – Volume 4
ATC (2006e), National Guidelines for Transport System Management in Australia – Volume 5
ATO (2011), Taxation Ruling RT 2011/2 Income tax: effective life of depreciating assets (applicable from 1 July 2011), accessible from http://law.ato.gov.au/atolaw/view.htm?rank=find&criteria=AND~Taxation~basic~exact:::AND~Ruling~basic~exact:::AND~TR~basic~exact:::AND~2011%2F2~basic~exact&target=EA&style=java&sdocid=TXR/TR20112/NAT/ATO/00001&recStart=1&PiT=99991231235958&Archived=false&recnum=2&tot=7&pn=ALL:::ALL
Austroads (2011), Updating Austroads RUE Unit Values and Related Methodologies, Austroads PublicationNumberAP–R373/11,February2011
MRC (2009), ACT Strategic Public Transport Network Plan Final Report
RailCorp (2010), A Compendium of CityRail Travel Statistics, SeventhEdition,June2010.
RTA (2009), Economic Analysis Manual: Appendix B – Economic Parameters for 2009.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 89
Costs,RisksandFunding
StagingCan the initiative be staged to reduce risks/improve manageability?
Duringtheoptiondevelopmentprocess,someconsiderationwasgiventostagingwiththeprimaryaimofoptimisingeconomicreturns.
Further work is proposed during the feasibility and forward design stage to consider further staging optionsandtheirimpactsonfeasibility,designandprocurement.
RiskManagementHave risks been formally identified, assessed and addressed through a management strategy? Overview
ApreliminaryRiskManagementStrategywaspreparedaspartofthepreparationofapre-feasibilitybusinesscasetotheACTGovernmentinApril2012.ThepreliminaryRiskManagementStrategyidentifiedpotentialrisksandmitigationstrategies.
AdetailedRiskManagementStrategywillbedevelopedoncetheProjectentersthefeasibilityandforwarddesignstage.ItisenvisagedthattheDetailedRiskManagementStrategywillconsidersrisksassociatedwithprocurementandtransactionalprocesses,withtheentirestrategypeerreviewedwhendeveloped.
Risk Management Governance
AhighlevelprovisionalriskmanagementgovernancestructureforfuturestagesoftheProjectareillustratedinFigure23.ThepreliminaryRiskManagementStrategyoutlinedaprovisionalgovernancearrangementinorderfortheProjectteamtoidentify,manageandmitigaterisksastheProjectprogressestoafeasibilityandforwarddesignstage.TheprovisionalRiskManagementGovernancearrangementscomprisesofthreekeyentitiesinorderofimportance:
• City to Gungahlin Project Office (Project Team):responsibleformanagingandimplementingtheRiskManagement Strategy
• Project Steering Committee:oversightandcertificationoftheRiskManagementStrategyandapotentialhighlevelconduitforkeystakeholderstoprovideinputintothedevelopmentoftheRiskManagement Strategy
• Project Risk Management Group: asecondconduitthroughwhichstakeholderscanprovideinputintothedevelopmentoftheRiskManagementStrategywithmembershipaimedatanofficerlevel
TheprovisionalriskmanagementgovernancestructuremakesprovisionfortheGungahlintoCityProjectOffice,establishedinthe2012-13BudgetbytheLandDevelopmentAgency.TheGungahlintoCityProjectOfficerecognisesthelinkbetweentransitandtheredevelopmentofthecorridor.TheProjectOfficewillcoordinatecurrentandfutureprojectsofvariousdirectorateswithinthecorridor,includingtransitcorridorfeasibilityanddesign,redevelopmentofpublichousingandcorridorplanningstudiestoexploredevelopmentscenariostosupporthigherdensitiesandthelike.
ACT Government Environment and sustainable Development Directorate 90
Figure 23: High Level Provisional Risk Management Governance Structure
Minister
Director General - ESDD
Project Steering CommitteeStakeholders
City to Gungahlin Project OfficeProject Risk Management Group
Risk Management Strategy Scope
The preliminary Risk Management Strategy considered:
• IdentificationoftherisksassociatedwitheachfuturestageoftheProject
• Assessment of the impact and likelihood of each of these risks on the Project
• Establishmentofanappropriatemitigationmechanismforeachriskmanagement
• MonitoringandreportingofeachoftheserisksoverthecourseoftheProject• DocumentationofeachriskwithintheassociatedProjectRiskRegister
ThepreliminaryRiskManagementStrategyandtheassociatedRiskRegisterhasbeendevelopedbytheProjectTeam.Itsdevelopmenthasconsidered:
• Typical risks associated with rapid transit projects similar to the Project
• Consultationundertakenwithstakeholders• ProjectspecificissuesknowntotheProjectteam
The Risk Register documents key risks and their consequence, assessed in terms of its impact and likelihood.Thelikelihoodandimpactassessmentprovidedaratingforeachidentifiedriskrangingfrom‘Lowto‘Severe’.Table62andTable63outlinerisksandpotentialmitigationstrategiesidentifiedduringthedevelopmentofthepreliminaryriskregister.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 91
Table 62: Risk Identification and Assessment Table
Risk Political Impact
Impact on Outputs and Service Delivery
Impact on Budget and Costs
Impact on Schedule
Community Acceptance
Risk Probability
Impact on Project
Limited technical expertisetodesign and construct BRT and LRT systems
Significantadversereactiontopoor design and customer experience
Deliveryofinfrastructure assets below expectations
Increased capital andoperatingcosts
Longer design time
Potentialadverseimpacts onservicedelivery,reducing customer experienceand acceptance
Possible Major
Limited operationalexpertisetooperate BRT and LRT
Potentialadversereactionto poor customer experience
Poorservicequality or unrealised improvementsinservicequality
Potentialimpactsonoperatingcosts associated withinefficientpracticesor remedial measures
Potentialadverseimpacts onservicedelivery,reducing customer experienceand acceptance
Possible Moderate
Non-compliant designs
Significantadversereactionfromspecificstakeholders
Higher costs associated with remedial design work to meet higher specification
Increased capital andpotentiallyhigheroperatingand maintenance costs
Longer design time Possible Moderate
Inability to deliveruponprojected growth assumptions
Higher densitieswithin the project corridor may encounter politicalresistance in response to community pressure
Lower than forecast public transport demandand/or higher car usage
Lowerfareboxrevenue,increasing the funding required tofinanceoperatingdeficits
Longer payback period
Higher densitieswithin the project corridor may encounter localised community opposition
Likely Major
Inability to secure upfront financing
Inability to secure financingmay force the abandonment of the Project due to cost
Inability to delivertheproject
Higher costs associated to restart Project should funding becomeavailablelater.
Postponement orindefinitedeferral of Project
Community oppositionassociated with deferral or dropping of Project
Possible Major
ACT Government Environment and sustainable Development Directorate 92
Risk Political Impact
Impact on Outputs and Service Delivery
Impact on Budget and Costs
Impact on Schedule
Community Acceptance
Risk Probability
Impact on Project
Poor informationdisseminationamongst stakeholder audiences
Significantadversereactionfromspecificstakeholders
Higher costs associated with remedial design work to meet higher specification
Increased capital andpotentiallyhigheroperatingand maintenance costs
Longer design time Unlikely Minor
Poor integrationof BRT and LRTserviceswithexistingservices
Adversereactioninresponse to poor design and customer experience
Higher operationalcosts associated with modifying operatingplan
Potentialadverseimpacts onservicedelivery,reducing customer experienceand acceptance
Possible Minor
Transport Product exceedsbudget
Significantadversereactiondue to cost overruns
Higher costs associated withoverspecification
Higher costs associated withoverspecification
Adversereactioninresponse to costoverruns
Likely Moderate
Changes to project scope orobjectives
Adversereactioninresponse to delays in program
Higher costs associated with resspecification
Longer design time
Adversereactioninresponse to delays in program
Likely Moderate
Project does notdelivercustomer requirements
Significantadversereactiontopoor design and customer experience
Lower than forecast public transport demandand/or higher car usage due to poorservicedeliveryandinfrastructure design
Potentialcostsassociated with remedialserviceor infrastructure treatments
Potentialadverseimpacts onservicedelivery,reducing customer experienceand acceptance
Possible Major
Patronage is substantiallydifferentfromforecast
Significantadversereactioninresponse to lower than expecteddemand forecasts
No impact on costs apart from costs associated with overservicingthecorridor
Adversereactioninresponse to overallocationof resources
Possible Moderate
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 93
Risk Political Impact
Impact on Outputs and Service Delivery
Impact on Budget and Costs
Impact on Schedule
Community Acceptance
Risk Probability
Impact on Project
ESDDstaffnotavailableasrequired or in required numbers to provideinputanddirectionto the project execution
Adversereactioninresponse topotentialdelays in program
Potentialcostsassociated with longer program and sourcing of alternativestaffor resources
Potentialdelays in program
Adversereactioninresponse topotentialdelays in program
Possible Major
Stakeholders haveunrealisticexpectationsof the Project and its specifications
Significantadversereactionfromspecificstakeholders
Higher costs associated with overspecification
Possible Moderate
Not all risks areidentified
Potentialsignificantadversereactionintheeventofasignificantriskmaterialising
Potentialadverseimpacts onservicedelivery
Potentialadverseimpactson costs
Potentialadverseimpacts on program
Potentialsignificantadversereactionintheeventofasignificantriskmaterialising
Possible Moderate
Table 63: Risk Management Strategy Table
RiskPotential Project
Risk
Risk Management
PriorityRisk Management Strategy
Limited technical expertisetodesign and construct BRT and LRT systems
Major High
• Developmentofarobustprocurementstrategytoidentifypreferred designers, contractors and constructors
• Developmentofapeerreviewprocesstocertifydesignandoperatingplans
• Considerationofashadowoperatormodeltoadviseonkeydesignandoperationalaspects
Limited operationalexpertisetooperate BRT and LRT
Moderate High
• ConsideranopenmarkettendertooperateBRTandLRTservices
• Developmentofarobustprocurementstrategytoidentifyexperiencedoperators
• UpskillingandtrainingofoperationallyfocusedTAMSstafftobenchmarkandmonitoroperationalperformance
• UpskillingandtrainingofACTIONBusesstaff
• Whereinternaltrainingandupskillingareinsufficient,considerexternalrecruitmentorengagementofconsultantstobenchmark performance
ACT Government Environment and sustainable Development Directorate 94
RiskPotential Project
Risk
Risk Management
PriorityRisk Management Strategy
Non-compliantdesign Moderate High
• InvolvekeystakeholdersaspartofthedraftanddetailedconceptdesignstagesthroughtheSteeringCommitteeandaProject Control Group
• DevelopmentofaproductdefinitionreporttospecificallyspecifyProjectattributesandagreeduponbystakeholderstoavoidoverscopingandtoobtainagreementbetweenstakeholdersonkey design parameters
Inability to deliveruponprojected growth assumptions
Major Severe
• Developmentofanintegratedlanduseandtransportstrategywithcommunitysignoff
• Undertakingofextensivecommunityconsultationwithintheproject corridor with respect to planned increases in density
• FormationofaSpecialPurposeAuthoritywithlegislatedpowerto implement land use strategies
• FormationofaSpecialPurposeAuthorityempoweredtoacquireanddeveloplandwithinthecorridor
• Engagecommercialpropertyexpertsearlytoappropriatelyinfluencedesign
• Implementationofplanningreformsandplanningcontrolstoencourageappropriateandtimelydevelopmentaroundstations
Inability to secure upfrontfinancing Major High
• Consideralternativemodesandstagingstrategiestospreadfunding requirements
• Diversifyfundingsourcestoincludefareboxstrategies,parkinglevies,redevelopment
Poorinformationdisseminationamongst stakeholder audiences
Minor Low• Communicationplantoensureinformationdissemination
• Regularmeetingswiththeprojectcontrolandreferencegroups
Poorintegrationof BRT and LRT serviceswithexistingservices
Minor Medium
• Developingandimplementingphysical(e.g.lifts/ramps/escalators)andnon-physicalmeasures(realtimeinfo)tofacilitatetravelandtransfers
• Communicationplantoinvolvethecommunityindesigningroutingandfrequency
• Undertakingon-boardsurveystobetterunderstanddemographicprofileofcurrentbususers
• UndertakinganalysisofMyWayfaredatatobetterunderstandtravelpatterns
Transport Productexceedsbudget
Moderate High
• Engagespecialistinfrastructureadvisorstoensurecapitalcostsareaccuratelypricedandsubjectedtoaprobabilisticriskassessment
• FurtherrefinementandexecutionoftheRiskManagementStrategytomanageidentifiedrisks
• Cost benchmarking referencing comparable projects
• Developmentofsub-optionstoallowforthescalingdownofnon-essentialelementsoftheProduct
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 95
RiskPotential Project
Risk
Risk Management
PriorityRisk Management Strategy
Changes to project scope or objectives
Moderate High
• EnsurealignmentofGovernmentintentionswithcurrentoremerginggovernmentstrategiesandpolicies
• ProductDefinitionincludesanalysisofalternativedesignsandoptionswithindesigns
• Undertakestakeholderandcommunityconsultationonareasonablybroadrangeofdesignsandoptionstomeetcommunity issues
Project does not delivercustomerrequirements
Major High
• Undertakefurthermarketanalysisonexistingdatasets(e.g.MyWay)touncovertravelpatternswithinstudycorridor
• Commissionfocusgroupsandsurveystoinvestigateandinterrogate community preferences and willingness to pay
• Consider engaging a shadow operator to report upon customer preferences
Patronage is substantiallydifferentfromforecast
Moderate High
• Undertakefurthermarketanalysisonexistingdatasets(e.g.MyWay)touncovertravelpatternswithinstudycorridor
• Commissionfocusgroupsandsurveystoinvestigateandinterrogate community preferences, willingness to pay and willingnesstotrade-offbetweencostsandservicequality
• Undertakeapeerreviewofthedemandmodellingprocess
• EnsureconceptdesignscancaterforoptimisticlevelsofdemandESDDstaffnotavailableasrequired or in required numbers to provideinputanddirectiontotheprojectexecution
Major High
• Developaresourcingstrategytoidentifyrequiredskills,thenumberofpersonnelrequiredandstaffthatcouldfillpositions
• Considerupskillingandtrainingforstaff
• Considercontractorsandconsultantstofillpositionsorprovidecontingentcover
Stakeholders haveunrealisticexpectationsofthe Project and itsspecifications
Moderate High
• InvolvekeystakeholdersaspartofthedraftanddetailedconceptdesignstagesthroughtheSteeringCommitteeandaProject Control Group
• DevelopmentofaproductdefinitionreporttospecificallyspecifyProjectattributesandagreeduponbystakeholderstoavoidoverscoping and to obtain agreement between stakeholders on key design parameters
• Undertakefrequentbriefings
Not all risks are identified Moderate High
• FurtherrefineRiskManagementStrategythatdevelopsasystematicapproachtoidentifyingrisks,managingrisks
• Undertakebothinternalandexternalpeerriskreviewsperiodically
ACT Government Environment and sustainable Development Directorate 96
Construction Risks
Does the initiative pose any significant construction risks due to its location, geology, design, etc.? Are those risks reflected in the construction cost estimate? Are those risks reflected in the initiative’s cost estimate and cost/benefit analysis?
TheProjectCorridorisanestablishedroadcorridorthroughanareathatisrelativelyflat.
Thekeyconstructionrisksidentifiedtodateincludeimpacttoutilities,thelocalenvironment,andtrafficdelays.Sitesurveys,desktopstudiesandstakeholderconsultationhasbeenundertakentounderstandtheseriskstothelevelofdetailsuitableforapre-feasibilitystudy,assuchsuitablecontingencyhasbeenallowedfortheserisksinthecapitalcostestimate.
Theseriskshavebeenquantifiedwithintheconstructioncostsestimatesthatformthebasisoftheeconomic appraisal.
Allconstructioncostestimateswillberevisedwithamoreaccurateaccountofprojectrisks,informedbymoredetaileddesignandspecificationsduringtheFeasibilityandForwardDesignstage.
Is there sufficient capacity (including relevant skills and expertise) to ensure the delivery of the initiative and realisation of benefits?
TheProjectteamthatwillresponsiblefordeliveringtheProjectwillbeformedinamannertoensuretheappropriateresourcesareselectedthatarecapableofdeliveringthescopeidentifiedtoprovidethebenefitspredictedinthetransportdemandmodellingandeconomicassessment.
FurtherconsiderationtotheresourcingneedsbothwithintheACTGovernmentanditsagenciesaswellastheneedforexternaladvisoryserviceswillbeconsideredduringtheinitialstagesoftheFeasibilityandForwardDesignStageoncetheTermsofReferenceandthescopeofthestagehavebeenformalised.
Will delivery require associated works to enable initiative to succeed in practical terms?
Nomajorassociatedworkshavebeenidentified.Allworkshavebeenidentifiedintheplanningworkundertakentodatefordevelopmentasanintegratedpackage.
How will interface risks with the initiative be managed?
TheACTGovernment,asproponent,isestablishingtheGungahlintoCityProjectOfficetomanagethedeliveryoftheproject.ThisdedicatedteamwillliaisewithallrelevantACTGovernmentagenciesaswellasCommonwealthGovernmentagenciesandotherstakeholdersandhaveprimaryresponsibilityforcoordination.
What requirements will need to be satisfied prior to construction of the initiative, including relevant planning and environmental approvals, land acquisition?
ApprovalwillberequiredfromNationalCapitalAuthority(NCA)foranychangestoroadsofnationalsignificance,whichincludesNorthbourneAvenue.
IfimpactavoidanceofCommonwealthlistedspeciesorThreatenedEcologicalCommunities(TEC)arefoundtooccurwithintheareaofproposedworksandimpactswereunavoidable,areferraltotheMinisterundertheEPBCActwouldberequiredtoensureadequateassessmentofimpactsonMattersofNationalEnvironmentalSignificance.
ApprovalwillalsoberequiredfromotherACTAgencies,includingTreasury,ACTPlanningandLandAuthority,RoadsACT,TerritoryandMunicipalServices,ParksandCityServices,andACTIONbuses.PartoftheroleoftheProjectOfficewillbetoensureallrelevantapprovalprocessesarefollowedattheappropriate stages of the project.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 97
EnvironmentalRisksAhighleveldesktopassessmentofpotentialenvironmentalrisksandlikelyfutureenvironmentalassessmentneedswasundertakenaspartofthepreparationofanACTGovernmentBusinessCasepreparedinApril2012.Thedesktopassessmentidentifiedthefollowingenvironmentalrisks:
Heritage
Non-indigenousheritageitemsarelocatedatthesouthernendofNorthbourneAvenueandincludetheSydneyandMelbournebuildingsandinHaigPark.TheProjectislikelytohaveaminimalimpactonthese items.
Land Use and Landscape Character
The character of much of the Project Corridor and its immediate surroundings will not be detrimentally affectedbytheProjectdueastheProject’simpactswillbeconfinedlargelytotheexistingandestablished road corridor.
NorthbourneAvenuebetweenAntillSttoAlingaStwillbeimpactedonbythelossofmedianandsignificanttrees.Thislosswillbeoffsetbyanincreaseinpedestrianvergeandhighqualitylandscapingandtreatments.InvestmentsalongtheAvenueareaimedatimprovingthecharacterofNorthbourneAvenueandwillbenotableandsignificant.
FurtherconsultationwiththeNationalCapitalAuthorityonthedesignofanytransportimprovementswithintheProjectCorridorwillberequiredtoensurethatthedesignisconsistentwiththeNationalCapitalPlan.Inparticular,treatmentsalongNorthbourneAvenuewillneedtobedesignandcompletedtoahighlevelofqualitytoreflecttheceremonialrolebestowedupontheAvenuewithintheNationalCapitalPlan.
Ecology
CommonwealthandACTlistedendangeredspeciesandthreatenedecologicalcommunitieshavebeenrecordedimmediatelyadjacenttotheexistingroadcorridor.
Intermsofecologicalconstraints,onlinedatacovering2kmeithersideoftheexistingProjectCorridorwerereviewedresultingintheidentificationofarangeofrecordedTerritoryandCommonwealthprotectedandthreatenedspeciesandcommunities.Recordsincluded:
• ThreatenedFlora—1threatenedfloraspecies.ThereisthepotentialforsuitablehabitatfornineadditionalthreatenedACT/CommonwealthprotectedfloraspeciestooccurinproximityoftheProject Corridor
• ThreatenedFauna—13threatenedfaunaspecieshavebeenrecordedwithinproximityoftheProjectCorridor.Thereisthepotentialforsuitablehabitatfortwenty-threeadditionalthreatenedACT/CommonwealthprotectedfaunaspeciestooccurinproximityoftheProjectCorridor
• ThreatenedEcologicalCommunities—2ThreatenedEcologicalCommunities(TECs)havebeenrecordedinproximityoftheProjectCorridor.TheseTECsareprotectedunderACTandCommonwealthlegislation
Targetedsitesurveyswillberequiredtoreconfirmtheserecordsandestablishtheenvironmentalimpacts of the project.
Soils, Geology and Groundwater
Theprojectisnotlikelytohaveanysignificantimpactsonsoils,geologyandgroundwater.
Noise, Vibration and Air Quality
TheProjectwillreducethenumberofcarmovementsalongthecorridorbuttheresultingincreaseinbusorlightrailmovementshasthepotentialtogenerateincreasedpeakintermittentnoiseandvibration(inthecaseoflightrail).ThisislikelytonegativelyimpactonpropertiesfrontingNorthbourneAvenue.
ACT Government Environment and sustainable Development Directorate 98
ThereductionofvehiclesmovementsalongthecorridorasaresultoftheProjectislikelytoresultinimprovementstolocalisedairquality.
Should the Project proceed to the Feasibility and Forward Design stage, the following assessments will be undertaken:
• Detailedassessmentofenvironmentalrisks
• Landuseandplanningapprovalsrequired,includingtheneedforaformalEnvironmentalImpactStatement
• Associatedcommunityengagementandconsultation
NeedforGovernmentFundingShould the Project proceed into the Feasibility and Forward Design Stage, further feasibility, design and planningworkwillneedtobecommissionedbytheACTGovernmenttoassesstheProject’sfeasibilityindetail.FullgovernmentfundingforthenextstageoftheProject’sdevelopmentisconsideredappropriate. The Feasibility and Forward Design Stage will be aimed at:
Table 64: Proposed Feasibility and Forward Design Works
Development Area
Possible Investigations
Option development
Moredetailedprojectstaginganalysistoassesstheappropriatetimingoftheinvestmenttoensure that enhanced public transport capacity when it is warranted by the growth in demand
FurtherdefinitionofthetransportmodestobeusedFrequentNetworkisrequiredtoensurethatoptionsandtreatmentsappliedalongtheProjectCorridorwillalignwithtreatmentsandinvestmentsappliedacrosstheremainderoftheFrequentNetwork
Detailed design
ProductdefinitionincludingvehicleoptionsandLRT/BRTinfrastructureandoperationalspecifications
DetaileddesignoftheProjectCorridor,DicksonStationandtheGungahlinTerminus
Cost estimation
Refinementofthecapitalcostestimates,whichshouldbebasedonadetaileddesignandincludeanappropriateprojectcontingencyasaresultofaprobabilitybasedprojectriskassessment process
Public transport operations
Rationalisationoftheassumedbusnetworktoensuretheappropriatelevelofbusserviceisprovided,tomaximisethelevelofintegrationofrapidtransitwithinthecurrentnetworkandtoensurethatoperatingcostsandthelevelofoperatingsubsidyforpublictransportservicesareoptimised
Land use Refinedlanduseanalysistoensurethatthepopulationandemploymentdistributionalandgrowthimpactsareassessedindetail,reflectasustainablelevelofgrowthintermsofdemandandsupply,andarereflectedinthedemandassessmentandeconomicbenefitsquantification
Refinedlandvaluecaptureanalysistoensureallofthepotentialrevenuesourcesarecapturedto contribute to the funding of the project
Demand modelling
Detailedstrategicmodellingofthepreferredoptiontoensuretheservicecharacteristicsoftheproposedoptions(BRTorLRToracombinationofthetwo)areappropriatelyreflected.Thismayinvolvethecommissioningofstatedpreferencestudiestobetterassessthewillingnesstopayfor(oralternativelythewillingnesstouse)BRTandLRTservices
Modelvalidationandcalibrationusingupdateddemanddataincluding2011JourneytoWorkdata
Environmental Assessment
ConfirmwhetheranEnvironmentalImpactStatementwillneedtobepreparedfortheProject
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 99
Development Area
Possible Investigations
Planning approvals
ConfirmwhatplanningapprovalswillberequiredtoprogresstheProject
Governance ConsiderwhatgovernancearrangementswillberequiredtofacilitatetheintegrateddevelopmentoftheProjectCorridor,withaspecificemphasisontheintegrationoflanduseand transport outcomes
Procurement Developmentofanappropriateprocurementstrategytofullyscopetheoptimumapproachtothefuturedevelopmentoftheproject
FurtherinvestigationisrequiredtoidentifycomponentsoftheProjectthataremostamenableforprivatesectorinvolvementandassessthefinancialattractivenessofprivatesectorinvolvementusingaPublicSectorComparatorapproachtoassessvalueformoney.
TheFeasibilityandForwardDesignStageisprojectedtocost$30millionover2013–14and2014–15.
FundingfromtheCommonwealthGovernmentwillenhancetheACTGovernment’sabilitytoacceleratetheFeasibilityandForwardDesignStageandinvestigatepotentialmeasuresregardinganintegratedlanduse-transportgovernanceframeworkfortheProject.
NeedforCommonwealthGovernmentFundingPartialfundingfortheFeasibilityandForwardDesignStageissoughtfromtheCommonwealthGovernmentonthebasisthat:
• Consistent with National Building II objectives:TheProjectdirectlyaddressesthreeNationBuildingIIobjectives:ConnectingPeople,SafetyandInnovation
• Consistent with the objectives of projects funded under the Commonwealth Government’s Liveable Cities Program:TheProjectaimsatexploringopportunitiesforcooperationbetweentheACTGovernmentandtheprivatesectortodirectlyaddressissuesincludingclimatechange,affordablehousing,trafficcongestionandagrowing,ageingpopulation
• Corridor of national significance:NorthbourneAvenue,whichformsalargepartoftheProjectCorridor,hasbeenidentifiedwithintheNationalCapitalPlanasacorridorofnationalsignificance.ProposedinvestmentsaspartoftheProjectareaimedatreinforcingthenationallysignificantceremonialroleoftheAvenue.AnumberofdesignelementsarelikelytoberequiredthatareoverandabovetherequirementsfortypicalrapidtransitprojectsinordertomeettherequirementsoftheNationalCapitalPlan.
• Opportunity to develop an integrated land use-transport governance structure: A number of partiesincludingtheProductivityCommission,InfrastructureAustraliaandCOAGhaveoutlinedtheneedforimprovedgovernanceinrelationtothedevelopmentofAustralia’scities.TheACTGovernment’scommitmenttotheestablishmentoftheGungahlintoCityProjectOffice,aimedatcoordinatingtransport,redevelopmentofpublichousingandlanduseplanning,providesapotentialspecial-purposevehicletopromoteandrealisepotentialtransportandlanduseoutcomesoutlinedwithin this submission.
ACT Government Environment and sustainable Development Directorate 100
Delivery StrategyThe process currently underway establishes the concept design for the project and its feasibility. The nextstageoftheprojectcycleforwhichfundingisrequiredisFeasibilityandForwardDesign.Furtherdetailed feasibility analysis and detailed design work will be required prior to procurement. Table 65 outlinesaprovisionaltimelinebetweenthedetailedfeasibilityprocessandthecommencementofconstruction.ThetimelinewillberefinedduringtheFeasibilityandForwardDesignStage.
Table 65: Provisional Delivery Program
Key Milestones Potential Timing
FunctionalBriefLodged 1st month
SelectDesign/FeasibilityConsultants 4th month
DesignOptionStudies 7th month
Preliminary Sketch Plan 15th month
ConsultationCompletion 12-15thmonth
Final Sketch Plan 21st month
DA Lodged 21th month
DAApproved 22th month
EIS Required Tobeconfirmed
EIS Complete Tobeconfirmed
Document ready 27th month
TenderingandEvaluation 28-30thmonth
ConstructionContractsSigned 31st month
ConstructionBegins 32nd month
AnumberofassetsandrelatedserviceswillneedtobeprocuredundertheProjecttofirstlydevelopthedesign,constructtheworksandthentooperatethetransportservices.InkeepingwithACTGovernmentprocurementprocesses,thefundamentalprinciplesofthefutureprocurementwillbetoensure that the items procured are:
• Fit for purpose
• RepresentvalueformoneyfortheACTGovernment
• In accordance with ACT procurement guidelines.
TheFeasibilityandForwardDesignStagewillconsiderthenatureandlevelofinvolvementoftheprivatesectortodevelopandfinancetheProject.
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 101
Governance StrategyProposedgovernancearrangementstodiscusskeyissuesandProjectdirectionarealreadyinplace.Theprovisionalgovernancearrangementsbroadlyreflectgovernancearrangementtodate,withtheexceptionthattheGungahlintoCityProjectOfficenowtakestheplaceastheleadprojectteam,inlieuofESDD.TheProjectSteeringCommitteewillensureseniorexecutivecommitmenttotheProjectwithdirect input from the Minister for ESDD as well as from key stakeholders. A Project Reference Group willdealwithday-to-dayissuesandtohighlightkeyissuesfortheSteeringCommittee’sconsideration.Figure24outlinesatahighleveltheprovisionalgovernancestructurefortheFeasibilityandForwardDesign stage.
Figure 24: High Level Provisional Governance Structure
Minister
Director General - ESDD
City to Gungahlin Project Office
Project Reference Group
Stakeholders Project Steering Committee
AstheProjectmovestotheFeasibilityandForwardDesignstage,adetailedgovernanceplanwillbedevelopedthatsetsoutindetailthegovernancearrangementsfortheplanningandprocurementoftheprojectandincludestherolesandresponsibilitiesassociatedwithspecificgovernancebodiesinordertoassistintheproject’sdeliveryandachievementofoutcomes.
Specificdetailsonmembershipwillbedependentonthepotentiallevelofprivatesectorinvolvement.Potentialstakeholdersmayinclude:
• EnvironmentandSustainableDevelopmentDirectorate
• TerritoryandMunicipalServicesDirectorate
• Treasury Directorate
• Chief Minister and Cabinet Directorate
• EconomicDevelopmentDirectorate
• CommunityServicesDirectorate• NationalCapitalAuthority
Dependingonthelevelofprivatesectorfunding,alternativegovernancearrangementsmaybeexplored.Forinstance,theGoldCoastLightRailprojectestablishedanauthorityofmultipleagenciesandconsortiumpartners.AssociatedGatewayprocedureswillalsoberevisitedbyTreasuryshouldthisoccur.
ShouldCommonwealthGovernmentfundingbesecured,currentgovernancearrangementswillalsobereviewedtoallowforgreaterinvolvementfromtheCommonwealthGovernment.
ACT Government Environment and sustainable Development Directorate 102
EconomicAppraisalTable:BRTunderaBusinessAsUsualLandUseScenarioAllvaluesinJune2011prices.Allvaluationswithrespecttobasecase.Allfiguresinmillions
COSTS BENEFITS UNDISCOUNTED
Disc
ount
fact
or
DISCOUNTED
Capi
tal e
xpen
ditu
re
(Cha
nges
in) b
us
oper
ating
cost
s
Rapi
d tr
ansit
(BRT
or
LRT)
ope
ratin
g co
sts
Asse
t mai
nten
ance
High
way
trav
el ti
me
savi
ngs
Publ
ic tr
ansp
ort
trav
el ti
me
savi
ngs
Savi
ngs i
n ge
nera
lised
tim
e
Unp
erce
ived
VO
C sa
ving
s
Road
dam
age
Incr
emen
tal f
are
reve
nue
reso
urce
co
st a
djus
tmen
t
Incr
emen
tal p
arki
ng
reve
nue
reso
urce
co
st a
djus
tmen
t
Avoi
ded
acci
dent
co
sts
Avoi
ded
air
pollu
tion
Avoi
ded
gree
nhou
se
gas e
miss
ions
Avoi
ded
noise
po
llutio
n
Resid
ual v
alue
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce C
osts
All b
enefi
ts
Net
ben
efit
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce C
osts
All b
enefi
ts
Net
ben
efit
2011 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 1.000 $0.0 $0.0 $0.0 $0.02012 $5.1 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $5.1 $0.0 $0.0 -$5.1 0.935 $4.7 $0.0 $0.0 -$4.72013 $7.6 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $7.6 $0.0 $0.0 -$7.6 0.873 $6.6 $0.0 $0.0 -$6.62014 $19.9 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $19.9 $0.0 $0.0 -$19.9 0.816 $16.2 $0.0 $0.0 -$16.22015 $58.9 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $58.9 $0.0 $0.0 -$58.9 0.763 $45.0 $0.0 $0.0 -$45.02016 $110.1 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $110.1 $0.0 $0.0 -$110.1 0.713 $78.5 $0.0 $0.0 -$78.52017 $74.8 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $74.8 $0.0 $0.0 -$74.8 0.666 $49.8 $0.0 $0.0 -$49.82018 $0.0 $0.0 $2.6 $0.5 $23.0 -$15.4 $7.6 $4.0 $0.0 $3.4 $18.6 $1.5 $0.5 $0.5 $0.2 $0.0 $0.0 $3.1 $36.6 $33.5 0.623 $0.0 $1.9 $22.8 $20.92019 $0.0 $0.0 $3.0 $0.5 $26.3 -$17.6 $8.7 $4.6 $0.1 $3.9 $21.3 $1.7 $0.6 $0.6 $0.3 $0.0 $0.0 $3.4 $41.8 $38.4 0.582 $0.0 $2.0 $24.3 $22.32020 $0.0 $0.0 $3.4 $0.5 $29.6 -$19.8 $9.8 $5.2 $0.1 $4.4 $23.9 $2.0 $0.7 $0.7 $0.3 $0.0 $0.0 $3.8 $47.0 $43.2 0.544 $0.0 $2.1 $25.6 $23.52021 $0.0 $0.0 $3.7 $0.5 $32.8 -$22.0 $10.9 $5.8 $0.1 $4.9 $26.6 $2.2 $0.8 $0.7 $0.3 $0.0 $0.0 $4.2 $52.3 $48.1 0.508 $0.0 $2.1 $26.6 $24.42022 $0.0 $0.0 $3.7 $0.5 $34.7 -$22.6 $12.0 $6.0 $0.1 $5.2 $26.3 $2.3 $0.8 $0.8 $0.4 $0.0 $0.0 $4.2 $53.9 $49.7 0.475 $0.0 $2.0 $25.6 $23.62023 $0.0 $0.0 $3.7 $0.5 $36.5 -$23.3 $13.1 $6.3 $0.1 $5.5 $26.0 $2.4 $0.9 $0.8 $0.4 $0.0 $0.0 $4.2 $55.6 $51.4 0.444 $0.0 $1.9 $24.7 $22.82024 $0.0 $0.0 $3.7 $0.5 $38.3 -$24.0 $14.3 $6.6 $0.1 $5.8 $25.7 $2.5 $0.9 $0.9 $0.4 $0.0 $0.0 $4.2 $57.2 $53.1 0.415 $0.0 $1.7 $23.7 $22.02025 $0.0 $0.0 $3.7 $0.5 $40.1 -$24.7 $15.4 $6.9 $0.1 $6.2 $25.5 $2.6 $1.0 $0.9 $0.4 $0.0 $0.0 $4.2 $58.9 $54.7 0.388 $0.0 $1.6 $22.8 $21.22026 $0.0 $0.0 $3.7 $0.5 $41.9 -$25.3 $16.6 $7.1 $0.1 $6.5 $25.2 $2.7 $1.0 $1.0 $0.4 $0.0 $0.0 $4.2 $60.5 $56.4 0.362 $0.0 $1.5 $21.9 $20.42027 $7.3 $0.0 $3.7 $0.5 $43.7 -$26.0 $17.7 $7.4 $0.1 $6.8 $24.9 $2.8 $1.1 $1.0 $0.4 $0.0 $7.3 $4.2 $62.2 $50.7 0.339 $2.5 $1.4 $21.1 $17.22028 $0.0 $0.0 $3.7 $0.5 $45.5 -$26.7 $18.8 $7.7 $0.1 $7.1 $24.6 $2.9 $1.1 $1.0 $0.5 $0.0 $0.0 $4.2 $63.8 $59.7 0.317 $0.0 $1.3 $20.2 $18.92029 $0.0 $0.0 $3.7 $0.5 $47.4 -$27.4 $20.0 $7.9 $0.1 $7.4 $24.3 $3.0 $1.2 $1.1 $0.5 $0.0 $0.0 $4.2 $65.5 $61.3 0.296 $0.0 $1.2 $19.4 $18.12030 $0.0 $0.0 $3.7 $0.5 $49.2 -$28.1 $21.1 $8.2 $0.1 $7.7 $24.0 $3.1 $1.3 $1.1 $0.5 $0.0 $0.0 $4.2 $67.2 $63.0 0.277 $0.0 $1.2 $18.6 $17.42031 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.258 $0.0 $1.1 $17.8 $16.72032 $22.5 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $22.5 $4.2 $68.8 $42.1 0.242 $5.4 $1.0 $16.6 $10.22033 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.226 $0.0 $0.9 $15.5 $14.62034 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.211 $0.0 $0.9 $14.5 $13.62035 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.197 $0.0 $0.8 $13.6 $12.72036 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.184 $0.0 $0.8 $12.7 $11.92037 $22.2 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $22.2 $4.2 $68.8 $42.5 0.172 $3.8 $0.7 $11.8 $7.32038 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.161 $0.0 $0.7 $11.1 $10.42039 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.150 $0.0 $0.6 $10.3 $9.72040 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.141 $0.0 $0.6 $9.7 $9.12041 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.131 $0.0 $0.5 $9.0 $8.52042 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.123 $0.0 $0.5 $8.4 $7.92043 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.115 $0.0 $0.5 $7.9 $7.42044 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.107 $0.0 $0.4 $7.4 $6.92045 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.100 $0.0 $0.4 $6.9 $6.52046 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.094 $0.0 $0.4 $6.4 $6.12047 $29.8 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $99.8 $29.8 $4.2 $168.6 $134.6 0.088 $2.6 $0.4 $14.8 $11.8Total $358.2 $0.0 $109.5 $13.5 $1,355.8 -$791.3 $564.5 $227.9 $2.8 $211.3 $720.2 $86.7 $34.2 $30.8 $13.8 $99.8 $358.2 $123.0 $1,992.0 $1,510.8 14.035 $215.3 $33.2 $491.8 $243.3
NPV = $243.3 BCR = 1.98
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 103
EconomicAppraisalTable:BRTunderaBusinessAsUsualLandUseScenarioAllvaluesinJune2011prices.Allvaluationswithrespecttobasecase.Allfiguresinmillions
COSTS BENEFITS UNDISCOUNTED
Disc
ount
fact
or
DISCOUNTED
Capi
tal e
xpen
ditu
re
(Cha
nges
in) b
us
oper
ating
cost
s
Rapi
d tr
ansit
(BRT
or
LRT)
ope
ratin
g co
sts
Asse
t mai
nten
ance
High
way
trav
el ti
me
savi
ngs
Publ
ic tr
ansp
ort
trav
el ti
me
savi
ngs
Savi
ngs i
n ge
nera
lised
tim
e
Unp
erce
ived
VO
C sa
ving
s
Road
dam
age
Incr
emen
tal f
are
reve
nue
reso
urce
co
st a
djus
tmen
t
Incr
emen
tal p
arki
ng
reve
nue
reso
urce
co
st a
djus
tmen
t
Avoi
ded
acci
dent
co
sts
Avoi
ded
air
pollu
tion
Avoi
ded
gree
nhou
se
gas e
miss
ions
Avoi
ded
noise
po
llutio
n
Resid
ual v
alue
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce C
osts
All b
enefi
ts
Net
ben
efit
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce C
osts
All b
enefi
ts
Net
ben
efit
2011 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 1.000 $0.0 $0.0 $0.0 $0.02012 $5.1 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $5.1 $0.0 $0.0 -$5.1 0.935 $4.7 $0.0 $0.0 -$4.72013 $7.6 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $7.6 $0.0 $0.0 -$7.6 0.873 $6.6 $0.0 $0.0 -$6.62014 $19.9 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $19.9 $0.0 $0.0 -$19.9 0.816 $16.2 $0.0 $0.0 -$16.22015 $58.9 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $58.9 $0.0 $0.0 -$58.9 0.763 $45.0 $0.0 $0.0 -$45.02016 $110.1 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $110.1 $0.0 $0.0 -$110.1 0.713 $78.5 $0.0 $0.0 -$78.52017 $74.8 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $74.8 $0.0 $0.0 -$74.8 0.666 $49.8 $0.0 $0.0 -$49.82018 $0.0 $0.0 $2.6 $0.5 $23.0 -$15.4 $7.6 $4.0 $0.0 $3.4 $18.6 $1.5 $0.5 $0.5 $0.2 $0.0 $0.0 $3.1 $36.6 $33.5 0.623 $0.0 $1.9 $22.8 $20.92019 $0.0 $0.0 $3.0 $0.5 $26.3 -$17.6 $8.7 $4.6 $0.1 $3.9 $21.3 $1.7 $0.6 $0.6 $0.3 $0.0 $0.0 $3.4 $41.8 $38.4 0.582 $0.0 $2.0 $24.3 $22.32020 $0.0 $0.0 $3.4 $0.5 $29.6 -$19.8 $9.8 $5.2 $0.1 $4.4 $23.9 $2.0 $0.7 $0.7 $0.3 $0.0 $0.0 $3.8 $47.0 $43.2 0.544 $0.0 $2.1 $25.6 $23.52021 $0.0 $0.0 $3.7 $0.5 $32.8 -$22.0 $10.9 $5.8 $0.1 $4.9 $26.6 $2.2 $0.8 $0.7 $0.3 $0.0 $0.0 $4.2 $52.3 $48.1 0.508 $0.0 $2.1 $26.6 $24.42022 $0.0 $0.0 $3.7 $0.5 $34.7 -$22.6 $12.0 $6.0 $0.1 $5.2 $26.3 $2.3 $0.8 $0.8 $0.4 $0.0 $0.0 $4.2 $53.9 $49.7 0.475 $0.0 $2.0 $25.6 $23.62023 $0.0 $0.0 $3.7 $0.5 $36.5 -$23.3 $13.1 $6.3 $0.1 $5.5 $26.0 $2.4 $0.9 $0.8 $0.4 $0.0 $0.0 $4.2 $55.6 $51.4 0.444 $0.0 $1.9 $24.7 $22.82024 $0.0 $0.0 $3.7 $0.5 $38.3 -$24.0 $14.3 $6.6 $0.1 $5.8 $25.7 $2.5 $0.9 $0.9 $0.4 $0.0 $0.0 $4.2 $57.2 $53.1 0.415 $0.0 $1.7 $23.7 $22.02025 $0.0 $0.0 $3.7 $0.5 $40.1 -$24.7 $15.4 $6.9 $0.1 $6.2 $25.5 $2.6 $1.0 $0.9 $0.4 $0.0 $0.0 $4.2 $58.9 $54.7 0.388 $0.0 $1.6 $22.8 $21.22026 $0.0 $0.0 $3.7 $0.5 $41.9 -$25.3 $16.6 $7.1 $0.1 $6.5 $25.2 $2.7 $1.0 $1.0 $0.4 $0.0 $0.0 $4.2 $60.5 $56.4 0.362 $0.0 $1.5 $21.9 $20.42027 $7.3 $0.0 $3.7 $0.5 $43.7 -$26.0 $17.7 $7.4 $0.1 $6.8 $24.9 $2.8 $1.1 $1.0 $0.4 $0.0 $7.3 $4.2 $62.2 $50.7 0.339 $2.5 $1.4 $21.1 $17.22028 $0.0 $0.0 $3.7 $0.5 $45.5 -$26.7 $18.8 $7.7 $0.1 $7.1 $24.6 $2.9 $1.1 $1.0 $0.5 $0.0 $0.0 $4.2 $63.8 $59.7 0.317 $0.0 $1.3 $20.2 $18.92029 $0.0 $0.0 $3.7 $0.5 $47.4 -$27.4 $20.0 $7.9 $0.1 $7.4 $24.3 $3.0 $1.2 $1.1 $0.5 $0.0 $0.0 $4.2 $65.5 $61.3 0.296 $0.0 $1.2 $19.4 $18.12030 $0.0 $0.0 $3.7 $0.5 $49.2 -$28.1 $21.1 $8.2 $0.1 $7.7 $24.0 $3.1 $1.3 $1.1 $0.5 $0.0 $0.0 $4.2 $67.2 $63.0 0.277 $0.0 $1.2 $18.6 $17.42031 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.258 $0.0 $1.1 $17.8 $16.72032 $22.5 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $22.5 $4.2 $68.8 $42.1 0.242 $5.4 $1.0 $16.6 $10.22033 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.226 $0.0 $0.9 $15.5 $14.62034 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.211 $0.0 $0.9 $14.5 $13.62035 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.197 $0.0 $0.8 $13.6 $12.72036 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.184 $0.0 $0.8 $12.7 $11.92037 $22.2 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $22.2 $4.2 $68.8 $42.5 0.172 $3.8 $0.7 $11.8 $7.32038 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.161 $0.0 $0.7 $11.1 $10.42039 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.150 $0.0 $0.6 $10.3 $9.72040 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.141 $0.0 $0.6 $9.7 $9.12041 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.131 $0.0 $0.5 $9.0 $8.52042 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.123 $0.0 $0.5 $8.4 $7.92043 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.115 $0.0 $0.5 $7.9 $7.42044 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.107 $0.0 $0.4 $7.4 $6.92045 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.100 $0.0 $0.4 $6.9 $6.52046 $0.0 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $0.0 $0.0 $4.2 $68.8 $64.6 0.094 $0.0 $0.4 $6.4 $6.12047 $29.8 $0.0 $3.7 $0.5 $51.0 -$28.7 $22.3 $8.5 $0.1 $8.0 $23.7 $3.2 $1.3 $1.2 $0.5 $99.8 $29.8 $4.2 $168.6 $134.6 0.088 $2.6 $0.4 $14.8 $11.8Total $358.2 $0.0 $109.5 $13.5 $1,355.8 -$791.3 $564.5 $227.9 $2.8 $211.3 $720.2 $86.7 $34.2 $30.8 $13.8 $99.8 $358.2 $123.0 $1,992.0 $1,510.8 14.035 $215.3 $33.2 $491.8 $243.3
NPV = $243.3 BCR = 1.98
ACT Government Environment and sustainable Development Directorate 104
EconomicAppraisalTable:LRTunderaBusinessAsUsualLandUseScenarioAllvaluesinJune2011prices.Allvaluationswithrespecttobasecase.Allfiguresinmillions.
COSTS BENEFITS UNDISCOUNTED
Disc
ount
fact
or
DISCOUNTED
Capi
tal
expe
nditu
re
(Cha
nges
in) b
us
oper
ating
cost
s
Rapi
d tr
ansit
(BRT
or
LRT)
ope
ratin
g co
sts
Asse
t m
aint
enan
ce
High
way
trav
el
time
savi
ngs
Publ
ic tr
ansp
ort
trav
el ti
me
savi
ngs
Savi
ngs i
n ge
nera
lised
tim
e
Unp
erce
ived
VO
C sa
ving
s
Road
dam
age
Incr
emen
tal f
are
reve
nue
reso
urce
co
st a
djus
tmen
t
Incr
emen
tal
park
ing
reve
nue
reso
urce
cost
ad
just
men
t
Avoi
ded
acci
dent
co
sts
Avoi
ded
air
pollu
tion
Avoi
ded
gree
nhou
se g
as
emiss
ions
Avoi
ded
noise
po
llutio
n
Resid
ual v
alue
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
2011 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 1.000 $0.0 $0.0 $0.0 $0.02012 $5.1 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $5.1 $0.0 $0.0 -$5.1 0.935 $4.7 $0.0 $0.0 -$4.72013 $7.6 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $7.6 $0.0 $0.0 -$7.6 0.873 $6.6 $0.0 $0.0 -$6.62014 $19.9 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $19.9 $0.0 $0.0 -$19.9 0.816 $16.2 $0.0 $0.0 -$16.22015 $58.9 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $58.9 $0.0 $0.0 -$58.9 0.763 $45.0 $0.0 $0.0 -$45.02016 $110.1 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $110.1 $0.0 $0.0 -$110.1 0.713 $78.5 $0.0 $0.0 -$78.52017 $74.8 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $74.8 $0.0 $0.0 -$74.8 0.666 $49.8 $0.0 $0.0 -$49.82018 $0.0 $0.0 $2.6 $0.5 $42.2 -$14.7 $27.5 $13.9 $0.2 $3.3 $17.5 $5.4 $2.5 $2.0 $0.9 $0.0 $0.0 $3.1 $73.2 $70.1 0.623 $0.0 $1.9 $45.6 $43.72019 $0.0 $0.0 $3.0 $0.5 $48.2 -$16.8 $31.4 $15.9 $0.2 $3.7 $20.0 $6.2 $2.8 $2.3 $1.0 $0.0 $0.0 $3.4 $83.7 $80.2 0.582 $0.0 $2.0 $48.7 $46.72020 $0.0 $0.0 $3.4 $0.5 $54.2 -$18.9 $35.3 $17.9 $0.3 $4.2 $22.5 $7.0 $3.2 $2.6 $1.1 $0.0 $0.0 $3.8 $94.1 $90.3 0.544 $0.0 $2.1 $51.2 $49.12021 $0.0 $0.0 $3.7 $0.5 $60.2 -$21.0 $39.2 $19.9 $0.3 $4.7 $25.0 $7.7 $3.5 $2.9 $1.2 $0.0 $0.0 $4.2 $104.6 $100.4 0.508 $0.0 $2.1 $53.2 $51.02022 $0.0 $0.0 $3.7 $0.5 $67.2 -$20.6 $46.7 $20.3 $0.3 $5.0 $24.9 $7.9 $3.6 $3.0 $1.3 $0.0 $0.0 $4.2 $112.9 $108.8 0.475 $0.0 $2.0 $53.7 $51.72023 $0.0 $0.0 $3.7 $0.5 $74.2 -$20.2 $54.1 $20.7 $0.3 $5.4 $24.8 $8.0 $3.7 $3.0 $1.3 $0.0 $0.0 $4.2 $121.3 $117.1 0.444 $0.0 $1.9 $53.9 $52.02024 $0.0 $0.0 $3.7 $0.5 $81.3 -$19.8 $61.5 $21.1 $0.3 $5.7 $24.7 $8.2 $3.8 $3.1 $1.3 $0.0 $0.0 $4.2 $129.6 $125.5 0.415 $0.0 $1.7 $53.8 $52.12025 $0.0 $0.0 $3.7 $0.5 $88.3 -$19.4 $68.9 $21.5 $0.3 $6.1 $24.5 $8.4 $3.8 $3.2 $1.3 $0.0 $0.0 $4.2 $138.0 $133.8 0.388 $0.0 $1.6 $53.5 $51.92026 $0.0 $0.0 $3.7 $0.5 $95.3 -$18.9 $76.3 $21.9 $0.3 $6.4 $24.4 $8.5 $3.9 $3.2 $1.4 $0.0 $0.0 $4.2 $146.4 $142.2 0.362 $0.0 $1.5 $53.0 $51.52027 $7.3 $0.0 $3.7 $0.5 $102.3 -$18.5 $83.8 $22.3 $0.3 $6.8 $24.3 $8.7 $4.0 $3.3 $1.4 $0.0 $7.3 $4.2 $154.7 $143.3 0.339 $2.5 $1.4 $52.4 $48.52028 $0.0 $0.0 $3.7 $0.5 $109.3 -$18.1 $91.2 $22.7 $0.3 $7.1 $24.1 $8.8 $4.1 $3.3 $1.4 $0.0 $0.0 $4.2 $163.1 $158.9 0.317 $0.0 $1.3 $51.6 $50.32029 $0.0 $0.0 $3.7 $0.5 $116.3 -$17.7 $98.6 $23.0 $0.3 $7.5 $24.0 $9.0 $4.1 $3.4 $1.4 $0.0 $0.0 $4.2 $171.4 $167.2 0.296 $0.0 $1.2 $50.7 $49.52030 $0.0 $0.0 $3.7 $0.5 $123.3 -$17.3 $106.0 $23.4 $0.4 $7.8 $23.9 $9.1 $4.2 $3.5 $1.5 $0.0 $0.0 $4.2 $179.8 $175.6 0.277 $0.0 $1.2 $49.7 $48.62031 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.258 $0.0 $1.1 $48.6 $47.52032 $22.5 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $22.5 $4.2 $188.1 $161.4 0.242 $5.4 $1.0 $45.4 $39.02033 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.226 $0.0 $0.9 $42.5 $41.52034 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.211 $0.0 $0.9 $39.7 $38.82035 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.197 $0.0 $0.8 $37.1 $36.32036 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.184 $0.0 $0.8 $34.7 $33.92037 $22.2 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $22.2 $4.2 $188.1 $161.8 0.172 $3.8 $0.7 $32.4 $27.92038 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.161 $0.0 $0.7 $30.3 $29.62039 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.150 $0.0 $0.6 $28.3 $27.72040 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.141 $0.0 $0.6 $26.4 $25.92041 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.131 $0.0 $0.5 $24.7 $24.22042 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.123 $0.0 $0.5 $23.1 $22.62043 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.115 $0.0 $0.5 $21.6 $21.12044 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.107 $0.0 $0.4 $20.2 $19.72045 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.100 $0.0 $0.4 $18.9 $18.42046 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.094 $0.0 $0.4 $17.6 $17.22047 $29.8 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $99.8 $29.8 $4.2 $287.9 $253.9 0.088 $2.6 $0.4 $25.2 $22.2Total $358.2 $0.0 $109.5 $13.5 $3,278.5 -$529.6 $2,748.9 $669.7 $10.0 $212.7 $708.5 $260.5 $120.2 $98.5 $42.0 $99.8 $358.2 $123.0 $4,970.8 $4,489.6 14.035 $215.3 $33.2 $1,187.6 $939.1
NPV = $939.1 BCR = 4.78
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 105
EconomicAppraisalTable:LRTunderaBusinessAsUsualLandUseScenarioAllvaluesinJune2011prices.Allvaluationswithrespecttobasecase.Allfiguresinmillions.
COSTS BENEFITS UNDISCOUNTED
Disc
ount
fact
or
DISCOUNTED
Capi
tal
expe
nditu
re
(Cha
nges
in) b
us
oper
ating
cost
s
Rapi
d tr
ansit
(BRT
or
LRT)
ope
ratin
g co
sts
Asse
t m
aint
enan
ce
High
way
trav
el
time
savi
ngs
Publ
ic tr
ansp
ort
trav
el ti
me
savi
ngs
Savi
ngs i
n ge
nera
lised
tim
e
Unp
erce
ived
VO
C sa
ving
s
Road
dam
age
Incr
emen
tal f
are
reve
nue
reso
urce
co
st a
djus
tmen
t
Incr
emen
tal
park
ing
reve
nue
reso
urce
cost
ad
just
men
t
Avoi
ded
acci
dent
co
sts
Avoi
ded
air
pollu
tion
Avoi
ded
gree
nhou
se g
as
emiss
ions
Avoi
ded
noise
po
llutio
n
Resid
ual v
alue
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
2011 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 1.000 $0.0 $0.0 $0.0 $0.02012 $5.1 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $5.1 $0.0 $0.0 -$5.1 0.935 $4.7 $0.0 $0.0 -$4.72013 $7.6 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $7.6 $0.0 $0.0 -$7.6 0.873 $6.6 $0.0 $0.0 -$6.62014 $19.9 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $19.9 $0.0 $0.0 -$19.9 0.816 $16.2 $0.0 $0.0 -$16.22015 $58.9 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $58.9 $0.0 $0.0 -$58.9 0.763 $45.0 $0.0 $0.0 -$45.02016 $110.1 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $110.1 $0.0 $0.0 -$110.1 0.713 $78.5 $0.0 $0.0 -$78.52017 $74.8 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $74.8 $0.0 $0.0 -$74.8 0.666 $49.8 $0.0 $0.0 -$49.82018 $0.0 $0.0 $2.6 $0.5 $42.2 -$14.7 $27.5 $13.9 $0.2 $3.3 $17.5 $5.4 $2.5 $2.0 $0.9 $0.0 $0.0 $3.1 $73.2 $70.1 0.623 $0.0 $1.9 $45.6 $43.72019 $0.0 $0.0 $3.0 $0.5 $48.2 -$16.8 $31.4 $15.9 $0.2 $3.7 $20.0 $6.2 $2.8 $2.3 $1.0 $0.0 $0.0 $3.4 $83.7 $80.2 0.582 $0.0 $2.0 $48.7 $46.72020 $0.0 $0.0 $3.4 $0.5 $54.2 -$18.9 $35.3 $17.9 $0.3 $4.2 $22.5 $7.0 $3.2 $2.6 $1.1 $0.0 $0.0 $3.8 $94.1 $90.3 0.544 $0.0 $2.1 $51.2 $49.12021 $0.0 $0.0 $3.7 $0.5 $60.2 -$21.0 $39.2 $19.9 $0.3 $4.7 $25.0 $7.7 $3.5 $2.9 $1.2 $0.0 $0.0 $4.2 $104.6 $100.4 0.508 $0.0 $2.1 $53.2 $51.02022 $0.0 $0.0 $3.7 $0.5 $67.2 -$20.6 $46.7 $20.3 $0.3 $5.0 $24.9 $7.9 $3.6 $3.0 $1.3 $0.0 $0.0 $4.2 $112.9 $108.8 0.475 $0.0 $2.0 $53.7 $51.72023 $0.0 $0.0 $3.7 $0.5 $74.2 -$20.2 $54.1 $20.7 $0.3 $5.4 $24.8 $8.0 $3.7 $3.0 $1.3 $0.0 $0.0 $4.2 $121.3 $117.1 0.444 $0.0 $1.9 $53.9 $52.02024 $0.0 $0.0 $3.7 $0.5 $81.3 -$19.8 $61.5 $21.1 $0.3 $5.7 $24.7 $8.2 $3.8 $3.1 $1.3 $0.0 $0.0 $4.2 $129.6 $125.5 0.415 $0.0 $1.7 $53.8 $52.12025 $0.0 $0.0 $3.7 $0.5 $88.3 -$19.4 $68.9 $21.5 $0.3 $6.1 $24.5 $8.4 $3.8 $3.2 $1.3 $0.0 $0.0 $4.2 $138.0 $133.8 0.388 $0.0 $1.6 $53.5 $51.92026 $0.0 $0.0 $3.7 $0.5 $95.3 -$18.9 $76.3 $21.9 $0.3 $6.4 $24.4 $8.5 $3.9 $3.2 $1.4 $0.0 $0.0 $4.2 $146.4 $142.2 0.362 $0.0 $1.5 $53.0 $51.52027 $7.3 $0.0 $3.7 $0.5 $102.3 -$18.5 $83.8 $22.3 $0.3 $6.8 $24.3 $8.7 $4.0 $3.3 $1.4 $0.0 $7.3 $4.2 $154.7 $143.3 0.339 $2.5 $1.4 $52.4 $48.52028 $0.0 $0.0 $3.7 $0.5 $109.3 -$18.1 $91.2 $22.7 $0.3 $7.1 $24.1 $8.8 $4.1 $3.3 $1.4 $0.0 $0.0 $4.2 $163.1 $158.9 0.317 $0.0 $1.3 $51.6 $50.32029 $0.0 $0.0 $3.7 $0.5 $116.3 -$17.7 $98.6 $23.0 $0.3 $7.5 $24.0 $9.0 $4.1 $3.4 $1.4 $0.0 $0.0 $4.2 $171.4 $167.2 0.296 $0.0 $1.2 $50.7 $49.52030 $0.0 $0.0 $3.7 $0.5 $123.3 -$17.3 $106.0 $23.4 $0.4 $7.8 $23.9 $9.1 $4.2 $3.5 $1.5 $0.0 $0.0 $4.2 $179.8 $175.6 0.277 $0.0 $1.2 $49.7 $48.62031 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.258 $0.0 $1.1 $48.6 $47.52032 $22.5 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $22.5 $4.2 $188.1 $161.4 0.242 $5.4 $1.0 $45.4 $39.02033 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.226 $0.0 $0.9 $42.5 $41.52034 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.211 $0.0 $0.9 $39.7 $38.82035 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.197 $0.0 $0.8 $37.1 $36.32036 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.184 $0.0 $0.8 $34.7 $33.92037 $22.2 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $22.2 $4.2 $188.1 $161.8 0.172 $3.8 $0.7 $32.4 $27.92038 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.161 $0.0 $0.7 $30.3 $29.62039 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.150 $0.0 $0.6 $28.3 $27.72040 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.141 $0.0 $0.6 $26.4 $25.92041 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.131 $0.0 $0.5 $24.7 $24.22042 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.123 $0.0 $0.5 $23.1 $22.62043 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.115 $0.0 $0.5 $21.6 $21.12044 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.107 $0.0 $0.4 $20.2 $19.72045 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.100 $0.0 $0.4 $18.9 $18.42046 $0.0 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $0.0 $0.0 $4.2 $188.1 $184.0 0.094 $0.0 $0.4 $17.6 $17.22047 $29.8 $0.0 $3.7 $0.5 $130.4 -$16.9 $113.4 $23.8 $0.4 $8.2 $23.8 $9.3 $4.3 $3.5 $1.5 $99.8 $29.8 $4.2 $287.9 $253.9 0.088 $2.6 $0.4 $25.2 $22.2Total $358.2 $0.0 $109.5 $13.5 $3,278.5 -$529.6 $2,748.9 $669.7 $10.0 $212.7 $708.5 $260.5 $120.2 $98.5 $42.0 $99.8 $358.2 $123.0 $4,970.8 $4,489.6 14.035 $215.3 $33.2 $1,187.6 $939.1
NPV = $939.1 BCR = 4.78
ACT Government Environment and sustainable Development Directorate 106
EconomicAppraisalTable:BRTunderaHigherDensityLandUseScenarioAllvaluesinJune2011prices.Allvaluationswithrespecttobasecase.Allfiguresinmillions.
COSTS BENEFITS UNDISCOUNTED
Disc
ount
fact
or
DISCOUNTED
Capi
tal
expe
nditu
re
(Cha
nges
in) b
us
oper
ating
cost
s
Rapi
d tr
ansit
(B
RT o
r LRT
) op
erati
ng co
sts
Asse
t m
aint
enan
ce
High
way
trav
el
time
savi
ngs
Publ
ic tr
ansp
ort
trav
el ti
me
savi
ngs
Savi
ngs i
n ge
nera
lised
tim
e
Unp
erce
ived
VO
C sa
ving
s
Road
dam
age
Incr
emen
tal f
are
reve
nue
reso
urce
co
st a
djus
tmen
t
Incr
emen
tal
park
ing
reve
nue
reso
urce
cost
ad
just
men
t
Avoi
ded
acci
dent
co
sts
Avoi
ded
air
pollu
tion
Avoi
ded
gree
nhou
se g
as
emiss
ions
Avoi
ded
noise
po
llutio
n
Resid
ual v
alue
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
2011 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 1.000 $0.0 $0.0 $0.0 $0.02012 $11.3 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $11.3 $0.0 $0.0 -$11.3 0.935 $10.5 $0.0 $0.0 -$10.52013 $16.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $16.0 $0.0 $0.0 -$16.0 0.873 $13.9 $0.0 $0.0 -$13.92014 $36.6 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $36.6 $0.0 $0.0 -$36.6 0.816 $29.9 $0.0 $0.0 -$29.92015 $129.3 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $129.3 $0.0 $0.0 -$129.3 0.763 $98.6 $0.0 $0.0 -$98.62016 $248.5 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $248.5 $0.0 $0.0 -$248.5 0.713 $177.2 $0.0 $0.0 -$177.22017 $172.8 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $172.8 $0.0 $0.0 -$172.8 0.666 $115.1 $0.0 $0.0 -$115.12018 $0.0 $0.0 $3.0 $2.4 $24.3 -$15.5 $8.8 $4.3 $0.1 $3.6 $18.6 $1.7 $0.8 $0.7 $0.3 $0.0 $0.0 $5.5 $38.8 $33.4 0.623 $0.0 $3.4 $24.2 $20.82019 $0.0 $0.0 $3.5 $2.4 $27.8 -$17.7 $10.1 $4.9 $0.1 $4.1 $21.3 $1.9 $1.0 $0.8 $0.3 $0.0 $0.0 $5.9 $44.4 $38.5 0.582 $0.0 $3.4 $25.8 $22.42020 $0.0 $0.0 $3.9 $2.4 $31.2 -$19.9 $11.3 $5.5 $0.1 $4.6 $23.9 $2.2 $1.1 $0.8 $0.4 $0.0 $0.0 $6.3 $49.9 $43.6 0.544 $0.0 $3.4 $27.1 $23.72021 $0.0 $0.0 $4.3 $2.4 $34.7 -$22.1 $12.6 $6.1 $0.1 $5.1 $26.6 $2.4 $1.2 $0.9 $0.4 $0.0 $0.0 $6.8 $55.5 $48.7 0.508 $0.0 $3.4 $28.2 $24.82022 $0.0 $0.0 $4.3 $2.4 $36.5 -$22.7 $13.8 $6.4 $0.1 $5.4 $26.3 $2.5 $1.2 $1.0 $0.4 $0.0 $0.0 $6.8 $57.2 $50.4 0.475 $0.0 $3.2 $27.2 $24.02023 $0.0 $0.0 $4.3 $2.4 $38.2 -$23.2 $15.0 $6.7 $0.1 $5.8 $26.0 $2.6 $1.3 $1.0 $0.4 $0.0 $0.0 $6.8 $58.9 $52.2 0.444 $0.0 $3.0 $26.2 $23.22024 $0.0 $0.0 $4.3 $2.4 $40.0 -$23.8 $16.2 $7.0 $0.1 $6.1 $25.7 $2.7 $1.4 $1.1 $0.4 $0.0 $0.0 $6.8 $60.7 $53.9 0.415 $0.0 $2.8 $25.2 $22.42025 $0.0 $0.0 $4.3 $2.4 $41.8 -$24.4 $17.4 $7.3 $0.1 $6.4 $25.4 $2.9 $1.4 $1.1 $0.5 $0.0 $0.0 $6.8 $62.4 $55.7 0.388 $0.0 $2.6 $24.2 $21.62026 $0.0 $0.0 $4.3 $2.4 $43.5 -$24.9 $18.6 $7.5 $0.1 $6.7 $25.1 $3.0 $1.5 $1.2 $0.5 $0.0 $0.0 $6.8 $64.2 $57.4 0.362 $0.0 $2.4 $23.3 $20.82027 $10.9 $0.0 $4.3 $2.4 $45.3 -$25.5 $19.8 $7.8 $0.1 $7.0 $24.9 $3.1 $1.5 $1.2 $0.5 $0.0 $10.9 $6.8 $65.9 $48.2 0.339 $3.7 $2.3 $22.3 $16.32028 $0.0 $0.0 $4.3 $2.4 $47.1 -$26.1 $21.0 $8.1 $0.1 $7.3 $24.6 $3.2 $1.6 $1.2 $0.5 $0.0 $0.0 $6.8 $67.6 $60.9 0.317 $0.0 $2.1 $21.4 $19.32029 $0.0 $0.0 $4.3 $2.4 $48.8 -$26.7 $22.2 $8.4 $0.1 $7.7 $24.3 $3.3 $1.6 $1.3 $0.5 $0.0 $0.0 $6.8 $69.4 $62.6 0.296 $0.0 $2.0 $20.5 $18.52030 $0.0 $0.0 $4.3 $2.4 $50.6 -$27.2 $23.4 $8.7 $0.1 $8.0 $24.0 $3.4 $1.7 $1.3 $0.6 $0.0 $0.0 $6.8 $71.1 $64.4 0.277 $0.0 $1.9 $19.7 $17.82031 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.258 $0.0 $1.7 $18.8 $17.12032 $25.3 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $25.3 $6.8 $72.9 $40.8 0.242 $6.1 $1.6 $17.6 $9.92033 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.226 $0.0 $1.5 $16.4 $14.92034 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.211 $0.0 $1.4 $15.4 $13.92035 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.197 $0.0 $1.3 $14.4 $13.02036 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.184 $0.0 $1.2 $13.4 $12.22037 $14.6 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $14.6 $6.8 $72.9 $51.5 0.172 $2.5 $1.2 $12.5 $8.92038 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.161 $0.0 $1.1 $11.7 $10.62039 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.150 $0.0 $1.0 $11.0 $9.92040 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.141 $0.0 $0.9 $10.2 $9.32041 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.131 $0.0 $0.9 $9.6 $8.72042 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.123 $0.0 $0.8 $8.9 $8.12043 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.115 $0.0 $0.8 $8.4 $7.62044 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.107 $0.0 $0.7 $7.8 $7.12045 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.100 $0.0 $0.7 $7.3 $6.62046 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.094 $0.0 $0.6 $6.8 $6.22047 $138.2 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $262.1 $138.2 $6.8 $335.0 $190.0 0.088 $12.1 $0.6 $29.3 $16.6Total $803.5 $0.0 $127.4 $72.7 $1,399.5 -$772.1 $627.5 $241.0 $3.9 $218.6 $719.6 $94.8 $46.8 $37.0 $15.3 $262.1 $803.5 $200.1 $2,266.6 $1,263.1 14.035 $469.8 $54.3 $534.9 $10.8
NPV = $10.8 BCR = 1.02
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 107
EconomicAppraisalTable:BRTunderaHigherDensityLandUseScenarioAllvaluesinJune2011prices.Allvaluationswithrespecttobasecase.Allfiguresinmillions.
COSTS BENEFITS UNDISCOUNTED
Disc
ount
fact
or
DISCOUNTED
Capi
tal
expe
nditu
re
(Cha
nges
in) b
us
oper
ating
cost
s
Rapi
d tr
ansit
(B
RT o
r LRT
) op
erati
ng co
sts
Asse
t m
aint
enan
ce
High
way
trav
el
time
savi
ngs
Publ
ic tr
ansp
ort
trav
el ti
me
savi
ngs
Savi
ngs i
n ge
nera
lised
tim
e
Unp
erce
ived
VO
C sa
ving
s
Road
dam
age
Incr
emen
tal f
are
reve
nue
reso
urce
co
st a
djus
tmen
t
Incr
emen
tal
park
ing
reve
nue
reso
urce
cost
ad
just
men
t
Avoi
ded
acci
dent
co
sts
Avoi
ded
air
pollu
tion
Avoi
ded
gree
nhou
se g
as
emiss
ions
Avoi
ded
noise
po
llutio
n
Resid
ual v
alue
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
2011 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 1.000 $0.0 $0.0 $0.0 $0.02012 $11.3 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $11.3 $0.0 $0.0 -$11.3 0.935 $10.5 $0.0 $0.0 -$10.52013 $16.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $16.0 $0.0 $0.0 -$16.0 0.873 $13.9 $0.0 $0.0 -$13.92014 $36.6 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $36.6 $0.0 $0.0 -$36.6 0.816 $29.9 $0.0 $0.0 -$29.92015 $129.3 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $129.3 $0.0 $0.0 -$129.3 0.763 $98.6 $0.0 $0.0 -$98.62016 $248.5 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $248.5 $0.0 $0.0 -$248.5 0.713 $177.2 $0.0 $0.0 -$177.22017 $172.8 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $172.8 $0.0 $0.0 -$172.8 0.666 $115.1 $0.0 $0.0 -$115.12018 $0.0 $0.0 $3.0 $2.4 $24.3 -$15.5 $8.8 $4.3 $0.1 $3.6 $18.6 $1.7 $0.8 $0.7 $0.3 $0.0 $0.0 $5.5 $38.8 $33.4 0.623 $0.0 $3.4 $24.2 $20.82019 $0.0 $0.0 $3.5 $2.4 $27.8 -$17.7 $10.1 $4.9 $0.1 $4.1 $21.3 $1.9 $1.0 $0.8 $0.3 $0.0 $0.0 $5.9 $44.4 $38.5 0.582 $0.0 $3.4 $25.8 $22.42020 $0.0 $0.0 $3.9 $2.4 $31.2 -$19.9 $11.3 $5.5 $0.1 $4.6 $23.9 $2.2 $1.1 $0.8 $0.4 $0.0 $0.0 $6.3 $49.9 $43.6 0.544 $0.0 $3.4 $27.1 $23.72021 $0.0 $0.0 $4.3 $2.4 $34.7 -$22.1 $12.6 $6.1 $0.1 $5.1 $26.6 $2.4 $1.2 $0.9 $0.4 $0.0 $0.0 $6.8 $55.5 $48.7 0.508 $0.0 $3.4 $28.2 $24.82022 $0.0 $0.0 $4.3 $2.4 $36.5 -$22.7 $13.8 $6.4 $0.1 $5.4 $26.3 $2.5 $1.2 $1.0 $0.4 $0.0 $0.0 $6.8 $57.2 $50.4 0.475 $0.0 $3.2 $27.2 $24.02023 $0.0 $0.0 $4.3 $2.4 $38.2 -$23.2 $15.0 $6.7 $0.1 $5.8 $26.0 $2.6 $1.3 $1.0 $0.4 $0.0 $0.0 $6.8 $58.9 $52.2 0.444 $0.0 $3.0 $26.2 $23.22024 $0.0 $0.0 $4.3 $2.4 $40.0 -$23.8 $16.2 $7.0 $0.1 $6.1 $25.7 $2.7 $1.4 $1.1 $0.4 $0.0 $0.0 $6.8 $60.7 $53.9 0.415 $0.0 $2.8 $25.2 $22.42025 $0.0 $0.0 $4.3 $2.4 $41.8 -$24.4 $17.4 $7.3 $0.1 $6.4 $25.4 $2.9 $1.4 $1.1 $0.5 $0.0 $0.0 $6.8 $62.4 $55.7 0.388 $0.0 $2.6 $24.2 $21.62026 $0.0 $0.0 $4.3 $2.4 $43.5 -$24.9 $18.6 $7.5 $0.1 $6.7 $25.1 $3.0 $1.5 $1.2 $0.5 $0.0 $0.0 $6.8 $64.2 $57.4 0.362 $0.0 $2.4 $23.3 $20.82027 $10.9 $0.0 $4.3 $2.4 $45.3 -$25.5 $19.8 $7.8 $0.1 $7.0 $24.9 $3.1 $1.5 $1.2 $0.5 $0.0 $10.9 $6.8 $65.9 $48.2 0.339 $3.7 $2.3 $22.3 $16.32028 $0.0 $0.0 $4.3 $2.4 $47.1 -$26.1 $21.0 $8.1 $0.1 $7.3 $24.6 $3.2 $1.6 $1.2 $0.5 $0.0 $0.0 $6.8 $67.6 $60.9 0.317 $0.0 $2.1 $21.4 $19.32029 $0.0 $0.0 $4.3 $2.4 $48.8 -$26.7 $22.2 $8.4 $0.1 $7.7 $24.3 $3.3 $1.6 $1.3 $0.5 $0.0 $0.0 $6.8 $69.4 $62.6 0.296 $0.0 $2.0 $20.5 $18.52030 $0.0 $0.0 $4.3 $2.4 $50.6 -$27.2 $23.4 $8.7 $0.1 $8.0 $24.0 $3.4 $1.7 $1.3 $0.6 $0.0 $0.0 $6.8 $71.1 $64.4 0.277 $0.0 $1.9 $19.7 $17.82031 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.258 $0.0 $1.7 $18.8 $17.12032 $25.3 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $25.3 $6.8 $72.9 $40.8 0.242 $6.1 $1.6 $17.6 $9.92033 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.226 $0.0 $1.5 $16.4 $14.92034 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.211 $0.0 $1.4 $15.4 $13.92035 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.197 $0.0 $1.3 $14.4 $13.02036 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.184 $0.0 $1.2 $13.4 $12.22037 $14.6 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $14.6 $6.8 $72.9 $51.5 0.172 $2.5 $1.2 $12.5 $8.92038 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.161 $0.0 $1.1 $11.7 $10.62039 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.150 $0.0 $1.0 $11.0 $9.92040 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.141 $0.0 $0.9 $10.2 $9.32041 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.131 $0.0 $0.9 $9.6 $8.72042 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.123 $0.0 $0.8 $8.9 $8.12043 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.115 $0.0 $0.8 $8.4 $7.62044 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.107 $0.0 $0.7 $7.8 $7.12045 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.100 $0.0 $0.7 $7.3 $6.62046 $0.0 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $0.0 $0.0 $6.8 $72.9 $66.1 0.094 $0.0 $0.6 $6.8 $6.22047 $138.2 $0.0 $4.3 $2.4 $52.3 -$27.8 $24.6 $9.0 $0.1 $8.3 $23.7 $3.5 $1.7 $1.4 $0.6 $262.1 $138.2 $6.8 $335.0 $190.0 0.088 $12.1 $0.6 $29.3 $16.6Total $803.5 $0.0 $127.4 $72.7 $1,399.5 -$772.1 $627.5 $241.0 $3.9 $218.6 $719.6 $94.8 $46.8 $37.0 $15.3 $262.1 $803.5 $200.1 $2,266.6 $1,263.1 14.035 $469.8 $54.3 $534.9 $10.8
NPV = $10.8 BCR = 1.02
ACT Government Environment and sustainable Development Directorate 108
EconomicAppraisalTable:LRTunderaHigherDensityLandUseScenarioAllvaluesinJune2011prices.Allvaluationswithrespecttobasecase.Allfiguresinmillions.
COSTS BENEFITS UNDISCOUNTED
Disc
ount
fact
or
DISCOUNTED
Capi
tal
expe
nditu
re
(Cha
nges
in) b
us
oper
ating
cost
s
Rapi
d tr
ansit
(B
RT o
r LRT
) op
erati
ng co
sts
Asse
t m
aint
enan
ce
High
way
trav
el
time
savi
ngs
Publ
ic tr
ansp
ort
trav
el ti
me
savi
ngs
Savi
ngs i
n ge
nera
lised
tim
e
Unp
erce
ived
VO
C sa
ving
s
Road
dam
age
Incr
emen
tal f
are
reve
nue
reso
urce
co
st a
djus
tmen
tIn
crem
enta
l pa
rkin
g re
venu
e re
sour
ce co
st
adju
stm
ent
Avoi
ded
acci
dent
co
sts
Avoi
ded
air
pollu
tion
Avoi
ded
gree
nhou
se g
as
emiss
ions
Avoi
ded
noise
po
llutio
n
Resid
ual v
alue
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
2011 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 1.000 $0.0 $0.0 $0.0 $0.02012 $11.3 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $11.3 $0.0 $0.0 -$11.3 0.935 $10.5 $0.0 $0.0 -$10.52013 $16.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $16.0 $0.0 $0.0 -$16.0 0.873 $13.9 $0.0 $0.0 -$13.92014 $36.6 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $36.6 $0.0 $0.0 -$36.6 0.816 $29.9 $0.0 $0.0 -$29.92015 $129.3 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $129.3 $0.0 $0.0 -$129.3 0.763 $98.6 $0.0 $0.0 -$98.62016 $248.5 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $248.5 $0.0 $0.0 -$248.5 0.713 $177.2 $0.0 $0.0 -$177.22017 $172.8 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $172.8 $0.0 $0.0 -$172.8 0.666 $115.1 $0.0 $0.0 -$115.12018 $0.0 $0.0 $3.0 $2.4 $42.7 -$14.6 $28.1 $14.2 $0.2 $3.4 $17.5 $5.6 $2.8 $2.2 $0.9 $0.0 $0.0 $5.5 $74.8 $69.3 0.623 $0.0 $3.4 $46.6 $43.22019 $0.0 $0.0 $3.5 $2.4 $48.8 -$16.6 $32.1 $16.2 $0.3 $3.8 $20.0 $6.4 $3.2 $2.5 $1.0 $0.0 $0.0 $5.9 $85.5 $79.6 0.582 $0.0 $3.4 $49.8 $46.32020 $0.0 $0.0 $3.9 $2.4 $54.9 -$18.7 $36.1 $18.2 $0.3 $4.3 $22.5 $7.2 $3.5 $2.8 $1.2 $0.0 $0.0 $6.3 $96.2 $89.8 0.544 $0.0 $3.4 $52.3 $48.92021 $0.0 $0.0 $4.3 $2.4 $61.0 -$20.8 $40.2 $20.2 $0.3 $4.8 $25.0 $8.0 $3.9 $3.1 $1.3 $0.0 $0.0 $6.8 $106.9 $100.1 0.508 $0.0 $3.4 $54.3 $50.92022 $0.0 $0.0 $4.3 $2.4 $68.1 -$20.5 $47.7 $20.7 $0.3 $5.2 $24.9 $8.1 $4.0 $3.2 $1.3 $0.0 $0.0 $6.8 $115.3 $108.6 0.475 $0.0 $3.2 $54.8 $51.62023 $0.0 $0.0 $4.3 $2.4 $75.3 -$20.1 $55.2 $21.1 $0.3 $5.5 $24.8 $8.3 $4.1 $3.2 $1.3 $0.0 $0.0 $6.8 $123.8 $117.1 0.444 $0.0 $3.0 $55.0 $52.02024 $0.0 $0.0 $4.3 $2.4 $82.5 -$19.8 $62.7 $21.5 $0.3 $5.9 $24.6 $8.4 $4.2 $3.3 $1.4 $0.0 $0.0 $6.8 $132.3 $125.6 0.415 $0.0 $2.8 $54.9 $52.12025 $0.0 $0.0 $4.3 $2.4 $89.7 -$19.5 $70.2 $21.9 $0.4 $6.3 $24.5 $8.6 $4.3 $3.4 $1.4 $0.0 $0.0 $6.8 $140.8 $134.0 0.388 $0.0 $2.6 $54.6 $52.02026 $0.0 $0.0 $4.3 $2.4 $96.9 -$19.1 $77.7 $22.3 $0.4 $6.6 $24.4 $8.8 $4.3 $3.4 $1.4 $0.0 $0.0 $6.8 $149.3 $142.5 0.362 $0.0 $2.4 $54.1 $51.72027 $10.9 $0.0 $4.3 $2.4 $104.0 -$18.8 $85.2 $22.7 $0.4 $7.0 $24.2 $8.9 $4.4 $3.5 $1.4 $0.0 $10.9 $6.8 $157.8 $140.1 0.339 $3.7 $2.3 $53.4 $47.42028 $0.0 $0.0 $4.3 $2.4 $111.2 -$18.5 $92.7 $23.1 $0.4 $7.4 $24.1 $9.1 $4.5 $3.5 $1.5 $0.0 $0.0 $6.8 $166.2 $159.5 0.317 $0.0 $2.1 $52.6 $50.52029 $0.0 $0.0 $4.3 $2.4 $118.4 -$18.1 $100.2 $23.5 $0.4 $7.7 $24.0 $9.2 $4.6 $3.6 $1.5 $0.0 $0.0 $6.8 $174.7 $168.0 0.296 $0.0 $2.0 $51.7 $49.72030 $0.0 $0.0 $4.3 $2.4 $125.6 -$17.8 $107.7 $23.9 $0.4 $8.1 $23.9 $9.4 $4.6 $3.7 $1.5 $0.0 $0.0 $6.8 $183.2 $176.4 0.277 $0.0 $1.9 $50.7 $48.82031 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.258 $0.0 $1.7 $49.5 $47.82032 $25.3 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $25.3 $6.8 $191.7 $159.6 0.242 $6.1 $1.6 $46.3 $38.62033 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.226 $0.0 $1.5 $43.3 $41.72034 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.211 $0.0 $1.4 $40.4 $39.02035 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.197 $0.0 $1.3 $37.8 $36.52036 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.184 $0.0 $1.2 $35.3 $34.12037 $14.6 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $14.6 $6.8 $191.7 $170.4 0.172 $2.5 $1.2 $33.0 $29.32038 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.161 $0.0 $1.1 $30.8 $29.82039 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.150 $0.0 $1.0 $28.8 $27.82040 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.141 $0.0 $0.9 $26.9 $26.02041 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.131 $0.0 $0.9 $25.2 $24.32042 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.123 $0.0 $0.8 $23.5 $22.72043 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.115 $0.0 $0.8 $22.0 $21.22044 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.107 $0.0 $0.7 $20.6 $19.82045 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.100 $0.0 $0.7 $19.2 $18.52046 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.094 $0.0 $0.6 $18.0 $17.32047 $138.2 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $262.1 $138.2 $6.8 $453.8 $308.9 0.088 $12.1 $0.6 $39.7 $27.0Total $803.5 $0.0 $127.4 $72.7 $3,335.4 -$540.1 $2,795.3 $682.3 $11.1 $219.5 $707.8 $268.5 $132.8 $104.7 $43.5 $262.1 $803.5 $200.1 $5,227.5 $4,224.0 14.035 $469.8 $54.3 $1,225.2 $701.1
NPV = $701.1 BCR = 2.34
City to Gungahlin Transit Corridor Infrastructure Australia Project submission 109
EconomicAppraisalTable:LRTunderaHigherDensityLandUseScenarioAllvaluesinJune2011prices.Allvaluationswithrespecttobasecase.Allfiguresinmillions.
COSTS BENEFITS UNDISCOUNTED
Disc
ount
fact
or
DISCOUNTED
Capi
tal
expe
nditu
re
(Cha
nges
in) b
us
oper
ating
cost
s
Rapi
d tr
ansit
(B
RT o
r LRT
) op
erati
ng co
sts
Asse
t m
aint
enan
ce
High
way
trav
el
time
savi
ngs
Publ
ic tr
ansp
ort
trav
el ti
me
savi
ngs
Savi
ngs i
n ge
nera
lised
tim
e
Unp
erce
ived
VO
C sa
ving
s
Road
dam
age
Incr
emen
tal f
are
reve
nue
reso
urce
co
st a
djus
tmen
tIn
crem
enta
l pa
rkin
g re
venu
e re
sour
ce co
st
adju
stm
ent
Avoi
ded
acci
dent
co
sts
Avoi
ded
air
pollu
tion
Avoi
ded
gree
nhou
se g
as
emiss
ions
Avoi
ded
noise
po
llutio
n
Resid
ual v
alue
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
Capi
tal c
osts
Ope
ratin
g an
d M
aint
enan
ce
Cost
s
All b
enefi
ts
Net
ben
efit
2011 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 1.000 $0.0 $0.0 $0.0 $0.02012 $11.3 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $11.3 $0.0 $0.0 -$11.3 0.935 $10.5 $0.0 $0.0 -$10.52013 $16.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $16.0 $0.0 $0.0 -$16.0 0.873 $13.9 $0.0 $0.0 -$13.92014 $36.6 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $36.6 $0.0 $0.0 -$36.6 0.816 $29.9 $0.0 $0.0 -$29.92015 $129.3 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $129.3 $0.0 $0.0 -$129.3 0.763 $98.6 $0.0 $0.0 -$98.62016 $248.5 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $248.5 $0.0 $0.0 -$248.5 0.713 $177.2 $0.0 $0.0 -$177.22017 $172.8 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $172.8 $0.0 $0.0 -$172.8 0.666 $115.1 $0.0 $0.0 -$115.12018 $0.0 $0.0 $3.0 $2.4 $42.7 -$14.6 $28.1 $14.2 $0.2 $3.4 $17.5 $5.6 $2.8 $2.2 $0.9 $0.0 $0.0 $5.5 $74.8 $69.3 0.623 $0.0 $3.4 $46.6 $43.22019 $0.0 $0.0 $3.5 $2.4 $48.8 -$16.6 $32.1 $16.2 $0.3 $3.8 $20.0 $6.4 $3.2 $2.5 $1.0 $0.0 $0.0 $5.9 $85.5 $79.6 0.582 $0.0 $3.4 $49.8 $46.32020 $0.0 $0.0 $3.9 $2.4 $54.9 -$18.7 $36.1 $18.2 $0.3 $4.3 $22.5 $7.2 $3.5 $2.8 $1.2 $0.0 $0.0 $6.3 $96.2 $89.8 0.544 $0.0 $3.4 $52.3 $48.92021 $0.0 $0.0 $4.3 $2.4 $61.0 -$20.8 $40.2 $20.2 $0.3 $4.8 $25.0 $8.0 $3.9 $3.1 $1.3 $0.0 $0.0 $6.8 $106.9 $100.1 0.508 $0.0 $3.4 $54.3 $50.92022 $0.0 $0.0 $4.3 $2.4 $68.1 -$20.5 $47.7 $20.7 $0.3 $5.2 $24.9 $8.1 $4.0 $3.2 $1.3 $0.0 $0.0 $6.8 $115.3 $108.6 0.475 $0.0 $3.2 $54.8 $51.62023 $0.0 $0.0 $4.3 $2.4 $75.3 -$20.1 $55.2 $21.1 $0.3 $5.5 $24.8 $8.3 $4.1 $3.2 $1.3 $0.0 $0.0 $6.8 $123.8 $117.1 0.444 $0.0 $3.0 $55.0 $52.02024 $0.0 $0.0 $4.3 $2.4 $82.5 -$19.8 $62.7 $21.5 $0.3 $5.9 $24.6 $8.4 $4.2 $3.3 $1.4 $0.0 $0.0 $6.8 $132.3 $125.6 0.415 $0.0 $2.8 $54.9 $52.12025 $0.0 $0.0 $4.3 $2.4 $89.7 -$19.5 $70.2 $21.9 $0.4 $6.3 $24.5 $8.6 $4.3 $3.4 $1.4 $0.0 $0.0 $6.8 $140.8 $134.0 0.388 $0.0 $2.6 $54.6 $52.02026 $0.0 $0.0 $4.3 $2.4 $96.9 -$19.1 $77.7 $22.3 $0.4 $6.6 $24.4 $8.8 $4.3 $3.4 $1.4 $0.0 $0.0 $6.8 $149.3 $142.5 0.362 $0.0 $2.4 $54.1 $51.72027 $10.9 $0.0 $4.3 $2.4 $104.0 -$18.8 $85.2 $22.7 $0.4 $7.0 $24.2 $8.9 $4.4 $3.5 $1.4 $0.0 $10.9 $6.8 $157.8 $140.1 0.339 $3.7 $2.3 $53.4 $47.42028 $0.0 $0.0 $4.3 $2.4 $111.2 -$18.5 $92.7 $23.1 $0.4 $7.4 $24.1 $9.1 $4.5 $3.5 $1.5 $0.0 $0.0 $6.8 $166.2 $159.5 0.317 $0.0 $2.1 $52.6 $50.52029 $0.0 $0.0 $4.3 $2.4 $118.4 -$18.1 $100.2 $23.5 $0.4 $7.7 $24.0 $9.2 $4.6 $3.6 $1.5 $0.0 $0.0 $6.8 $174.7 $168.0 0.296 $0.0 $2.0 $51.7 $49.72030 $0.0 $0.0 $4.3 $2.4 $125.6 -$17.8 $107.7 $23.9 $0.4 $8.1 $23.9 $9.4 $4.6 $3.7 $1.5 $0.0 $0.0 $6.8 $183.2 $176.4 0.277 $0.0 $1.9 $50.7 $48.82031 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.258 $0.0 $1.7 $49.5 $47.82032 $25.3 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $25.3 $6.8 $191.7 $159.6 0.242 $6.1 $1.6 $46.3 $38.62033 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.226 $0.0 $1.5 $43.3 $41.72034 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.211 $0.0 $1.4 $40.4 $39.02035 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.197 $0.0 $1.3 $37.8 $36.52036 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.184 $0.0 $1.2 $35.3 $34.12037 $14.6 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $14.6 $6.8 $191.7 $170.4 0.172 $2.5 $1.2 $33.0 $29.32038 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.161 $0.0 $1.1 $30.8 $29.82039 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.150 $0.0 $1.0 $28.8 $27.82040 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.141 $0.0 $0.9 $26.9 $26.02041 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.131 $0.0 $0.9 $25.2 $24.32042 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.123 $0.0 $0.8 $23.5 $22.72043 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.115 $0.0 $0.8 $22.0 $21.22044 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.107 $0.0 $0.7 $20.6 $19.82045 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.100 $0.0 $0.7 $19.2 $18.52046 $0.0 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $0.0 $0.0 $6.8 $191.7 $184.9 0.094 $0.0 $0.6 $18.0 $17.32047 $138.2 $0.0 $4.3 $2.4 $132.7 -$17.5 $115.3 $24.3 $0.4 $8.4 $23.7 $9.6 $4.7 $3.7 $1.5 $262.1 $138.2 $6.8 $453.8 $308.9 0.088 $12.1 $0.6 $39.7 $27.0Total $803.5 $0.0 $127.4 $72.7 $3,335.4 -$540.1 $2,795.3 $682.3 $11.1 $219.5 $707.8 $268.5 $132.8 $104.7 $43.5 $262.1 $803.5 $200.1 $5,227.5 $4,224.0 14.035 $469.8 $54.3 $1,225.2 $701.1
NPV = $701.1 BCR = 2.34
ACT Government Environment and sustainable Development Directorate 110
Footnotes
1 ColliersInternational(2011)GlobalCBDParkingRateSurvey
2 ACTGovernment(2010)TimetoTalkCanberra2030
3 ABS(2011)Populationestimatesbasedon2006Census
4 CMCD (undated)
5 ACTPLA (2009)
6 CMD (undated)
7 ColliersInternational(2011)GlobalCBDParkingRateSurvey
8 ACTGovernment(2010)TimetoTalkCanberra2030
9 Austroads(2011),UpdatingAustroadsRUEUnitValuesandRelatedMethodologies,AustroadsPublicationNumberAP–R373/11,February2011
10RTA(2009),EconomicAnalysisManual:AppendixB–EconomicParametersfor2009.
11RailCorp(2010),ACompendiumofCityRailTravelStatistics,SeventhEdition,June2010.
12ARRB(2011),GuidetoProjectEvaluation–Part4:ProjectEvaluationData(UpdateRUEUnitValues),Austroads Project TP1672, August 2011