information investment subcommittee meeting june 21, 2007 note: presentation contains pre-decisional...
TRANSCRIPT
Information Investment Subcommittee Meeting
June 21, 2007
Note: Presentation Contains Pre-decisional BY 2009 Dollars.Internal Use Only.
2
Agenda
• Current Events– Highlights of May IIS Meeting– BY 2009 CPIC Major Portfolio (see attachments 1 & 2)
Project Overviews – Quarterly Analyses– Earned Value Management (EVM) and Operational Analysis
(see attachment 3)– High-Risk (see attachment 4)
• Enterprise Architecture (see attachment 5)
• Timeline
Expected Outcomes: 1) Concurrence on updated BY 2009 Portfolio, 2) Concurrence on selecting Architecture segments, 3) Concurrence on corrective action plan for investments outside of acceptable variance, and 4) Concurrence on corrective action plan for high-risk investments, as needed
4
Potential New IIS Activities for FY 2008 Q1
• Organizational IT Profiles: How can READ be helpful to improve the IIS understanding of IT systems and potential cross-organizational data requirements?
• Enterprise Tools: What are the enterprise tools, what investments are using them, when will other investments use them, what is the governance structure for them?
• Case Study: At what stage does an IT system get identified for IIS oversight and what is the IIS role for interoperability, especially if it is a non-major investment?
6
OMB Exhibit 300 Changes Highlights
• Merged Performance Information Tables into a new Performance Information Table.
• Minor changes to the security and privacy status reporting tables.• Simplified Cost and Schedule Performance section.• Adds new questions about legacy system replacements.• Adds new questions about segment architectures.
– Is this investment identified in a completed (contains a target architecture) and approved segment architecture?
• If “yes,” provide the name of the segment architecture as provided in the agency’s most recent annual EA Assessment
• Adds new question about relation to the GAO High Risk Areas.– Does this investment directly support one of the GAO High Risk Areas?
• 25 high-risk areas to focus on the need for broad-based transformations to address major economy, efficiency, or effectiveness challenges.“ http://www.gao.gov/new.items/d07310.pdf
• Adds new requirement to identify certification levels via the Federal Acquisition Certification for Program and Project Managers (FAC-P/PM).
– What is the current FAC-P/PM certification level of the project/program manager? (Entry/Apprentice-level, Mid/Journeyman-level, Senior/Expert-level, DAWIA-Level-1, DAWIALevel-2, DAWIA-Level-3,TBD)
7
Status of EPA CPIC Major Process
3
BY 2009 Abstracts received and analyzedIIS selects initial CPIC portfolio of major IT investments for BY 2009
06/20
Bus. Case Due
Preliminary Activities
ALL
Bu
s. C
ase
s D
ue f
or
2n
d
Eva
luati
on
05/09
Training
Bus. Case Development
1st Evaluation
of Bus. Case
06/05
Bus. Case Due
1st Evaluation
of Bus. Case
06/17
Score Available
05/23
Training
Bus. Case Development
Bus. Case Development
for 2nd Evaluation
Bus. Case Development for 2nd Evaluation
07/06
Score Available
Training and 1st Evaluation 2nd Evaluation
Aug 2 – Scores from 2nd Evaluation AvailableAug 7 – Bus. Case Due for 3rd Evaluation, if neededAug 15 – Scores from 3rd Evaluation AvailableLate August - Additional evaluations if needed
3rd and Additional Evaluations to IIS
September 10, 2007Submission to OMB
Gro
up O
ne
Gro
up T
wo
07/18
Status as of 6/21/2007
Business Case Score Feedback:1st Round goes to OD, IMO and Bus. Case Preparer.2nd Round goes to IIS Member, plus those above.3nd Round goes to SIO, plus all those above.
9
EVM and Portfolio Variance FY 2007 Q2 - Cumulative
Cumulative Variance Report:
• 10 investments reporting Earned Value. 7 investments are within 10% cost and schedule variance
• eRulemaking: -16.0% schedule variance• FinRS: -14.7% schedule variance• PRISM: -36.5% schedule variance
• Portfolio performance within acceptable variance:
Cost Variance (CV) = -0.2%
Schedule Variance (SV) = -8.5%
10
EVM Metrics – Q2 FY 2007Cumulative
Notes: 1 – $ in Millions.2 – All data based on OMB approved baselines.
CAMDBS 3/31/2007 $15,093 $15,170 $14,834 -2.3% -1.7%
ICIS 3/31/2007 $25,558 $25,140 $25,538 1.6% -0.1%
eRulemaking 3/31/2007 $34,362 $28,648 $28,797 0.5% -16.2%
CDX 3/31/2007 $28,719 $27,553 $28,558 3.5% -0.6%
SDMS 3/31/2007 $43,947 $41,689 $41,729 0.1% -5.1%
FinRS 3/31/2007 $73,633 $65,117 $62,809 -3.7% -14.7%
ECMS 3/31/2007 $7,277 $7,618 $7,608 -0.1% 4.6%
EPASS 3/31/2007 $6,225 $6,094 $6,212 1.9% -0.2%
PRISM 3/31/2007 $9,334 $5,746 $5,924 3.0% -36.5%
STO RET 3/31/2007 $22,237 $21,501 $21,666 0.8% -2.6%
EPA PO RTFO LIO TO TALS $266,385 $244,276 $243,675 -0.24% -8.52%
Earned Value
(BCWP)
Cost Variance %
(CV)
Schedule Variance % (SV)
Investment Title
Values Through
Planned Cost
(BCWS)
Actual Cost
(ACWP)
12
EVM Cumulative Variance Trend Analysis – Previous Four Quarters
Comments
Cost Variance (CV) %
Schedule Variance (SV) %
Cost Variance (CV) %
Schedule Variance (SV) %
Cost Variance (CV) %
Schedule Variance (SV) %
Cost Variance (CV) %
Schedule Variance (SV) %
CAMDBS -4.1% -2.1% -3.9% -1.9% -2.4% -1.5% -2.3% -1.7%
Consistently within acceptable variance
ICIS 1.3% 0.0% 1.1% -0.1% 1.5% -0.1% 1.6% -0.1%
Consistently within acceptable variance
CDX 3.8% -5.2% 4.1% -0.7% 3.7% -0.6% 3.5% -0.6%
Consistently within acceptable variance
SDMS 4.3% -12.2% -4.9% -2.7% 0.4% -3.0% 0.1% -5.1%Within variance after re-baselining
ECMS 6.2% -46.2% 1.3% 1.4% 0.7% -1.7% -0.1% 4.6%Within variance after re-baselining
eRulemaking N/A N/A N/A N/A 1.2% -16.2% 0.5% -16.2% Schedule variance
STORET 0.5% -0.6% 0.2% -1.6% 1.4% -1.7% 0.8% -2.6%
Consistently within acceptable variance
EPASS N/A N/A N/A N/A 1.9% -0.4% 1.9% -0.2%Within acceptable variance
FinRS 4.8% -2.5% -0.07% -0.05% -3.7% -10.0% -3.7% -14.7% Schedule Variance
PRISM 2.1% -5.2% 5.5% -9.6% 6.3% -1.4% 3.0% -36.5%Schedule Variance
Q2 2007
Investment Title
Q3 2006 Q4 2006 Q1 2007
13
Investments Out of Variance
Contact person to provide justification on:
• eRulemaking: -16.2% schedule variance Funding deficit due to CR and multi-Agency funding
• FinRS: -14.7% schedule varianceSchedule change due to contract award delay and protest
• PRISM: -36.5% schedule varianceData provided initially was not in accordance with their projected planned cost
RECOMMENDATION: (1) Concurrence on proposed corrective actions (2) Concurrence to continue investments outside of acceptable level of variance
14
Rebaseline Status
• Status of Investments’ Rebaseline Requests: At OMB awaiting approval
FinRS – Modify schedule due to pending protest resolution CAMDBS - Combine milestones currently reported separately PRISM – Modify schedule due to significant budget cuts IGMS – Increase cost to support migration from IGMS to a Grants
Management Line of Business
Pending action to forward to OMB eRulemaking – Modify schedule and costs due to CR TIM – Modify milestones EPASS – Reduction of funding – Removal of Logical Security milestones (OEI) SDMS – Scope changes; adding ITCS
Pending receipt from Investment Managers ICIS – Due to OEI June 29, 2007
16
Operational Analysis Review
Investment Title Reported SV% Reported CV% Comments
SDWIS 5.00% 0%Within 10% of cost and schedule
PeoplePlus HR 0% 0%Within 10% of cost and schedule
LFS 0% -1.88%Within 10% of cost and schedule
IOME 0% 0%Within 10% of cost and schedule
ICMS 0% 0%Within 10% of cost and schedule
GEO 3.40% 3.40%Within 10% of cost and schedule
IGMS -2.10% -1.10%Within 10% of cost and schedule
CERCLIS 0% 2.00%Within 10% of cost and schedule
TIM 0% -19.50% Outside cost variance
17
Operational Analysis
Outside of Variance TIM -19.5% of Cost Variance (Cost Overrun)
RECOMMENDATIONS:
(1) Concurrence on proposed corrective action (2) Concurrence to continue investment outside of acceptable level of variance
(3) OEI and OCFO work together in the tracking of validated budget data
(4) SIO of each portion to receive quarterly reports for his/her office (HQ & Regions)
19
Summary
• OMB Definition: – OMB Circular A-11: investments requiring special attention from oversight
authorities and the highest levels of agency management– All E-Gov and Line of Business (LoB) initiatives managed by EPA and
investments associated with migrating to an E-Gov or LoB initiative– OMB has reduced the High Risk list from 18 to a total of 14 investments
• High Risk Projects: – FM LoB Legacy System (part of the LFS investment)– FM LoB Migration (part of the FinRS investment) – E-Travel Migration (part of the FinRS investment) – People Plus HR (major, alignment with EHRI and the HR LoB)– HR LoB Migration (part of the People Plus HR investment) – EHRI-eOPF (non-major, Enterprise Human Resources Integration-electronic
Official Personnel Folder)– EZ Hire (non-major, vacancy announcement and application system)– E-Training (non-major)– eRulemaking (major)– ICMS (major, Integrated Contracts Management System, alignment with IAE)– IGMS (major, Integrated Grants Management System, alignment with
Grants.GOV and the GM LoB)– E-Authentication (non-major) – E-Authentication Shared Service Provider (non-major)– E-Clearance Migration (non-major)
20
FY 2007 Q3 Status
• Four projects have been removed from the High Risk List– E-Payroll Legacy System (non-major): investment is complete,
EPA has migrated to DFAS.– FAS-Legacy System (non-major): system does not exist,
incorrectly added to the High Risk list.– FAS-Migration (non-major): system does not exist, incorrectly
added to the High Risk list.– FinRS (major): separated into component investments FM LoB,
E-Payroll and E-Travel
• Of the current fourteen projects, three do not meet a high risk principal criteria (cost and schedule are not within 10% variance)– FM LoB Migration (component of the FinRS investment)– E-Travel Migration (component of the FinRS investment)– eRulemaking
See Attachment 4
21
FY 2007 Q3 Status (cont.)
• Cause and Corrective Action:– FM LoB Migration: Exceeds 10% of Schedule Variance. A
component of the FinRS investment. EPA submitted an interim rebaselining request to OMB and is awaiting approval.
– E-Travel Migration: Exceeds 10% of Schedule Variance. A component of the FinRS investment. EPA is working with GSA and the contractor to resolve the implementation issues and to adjust the rollout schedule.
– eRulemaking: Exceeds 10% of Schedule Variance. The FY2007 Continuing Resolution delayed the receipt of funding from contributing partner agencies. Re-structure of the FY2006 budget and lower monthly expenditures to cover FY2007 costs until sufficient funding is received. The eRulemaking PMO will be submitting a rebaseline request in June 2007.
• Reporting:– Sent to OMB June 15, 2007– Report to be sent to GAO and EPA IG
See Attachment 4
Enterprise Architecture:Advancing Segment Prioritization
June 21, 2007
Kevin J. KirbyEPA Data ArchitectOEI/OTOP/MISD
25
Agenda
(1) Setting the Stage: OMB Requirements and EPA’s EA
(2) Aligning FY09 CPIC Investments to EA Segment Plans
(3) Segment Architecture Development Prioritization, Selection, and Sequencing
Expected Outcomes:
Concurrence and Executive sponsorship of selected EPA EA priority segment architectures for FY 07 and FY 08
26
Setting the EA Stage
Agencies must:• Architect Invest Implement IT Solutions (in that order)
• Mature Enterprise Architecture Programs by closely aligning the IT Investment Portfolio with the Enterprise Architecture
• Demonstrate architecture: a) Completion, b) Use, and c) Results in “Segments” of the Agency’s business
Agencies should use Enterprise Architecture Planning to ensure IT portfolios support Agency strategic missions
(President’s Management Agenda, e-Government goals)
27
Segment Architecture Focus in New CPIC Guidance
2006 OMB requirement: demonstrate at least one business area (Segment) with complete architecture, and use of it, leading to demonstrable programmatic performance improvement
Changes for 2007:
• New guidance further ties FY09 investments to segment architectures
Exhibit 300:Q F3. Is this investment identified in a completed (contains a target architecture) and approved segment architecture? Yes /No a. If “yes,” provide the name of the segment architecture.
Exhibit 53:Segment Architecture represents the status of the investment's alignment to the agencies segmentarchitecture process. The following options are available:(1) - This investment is identified as supporting an approved, complete segment architecture(2) - This investment is part of an incomplete or in-process segment architecture(3) - This investment is part of a planned, but yet to be initiated, segment architecture
28
Current “Segment” Architecture Development at EPA
Core Mission Area Segment
Business Service Segment
Enterprise Service Segment
Partner Views
• 17 – initial EPA Segments identified based on mission business lines, functions, and support services
• 13 – Segments formalized in architecture activities to date
• 11 – Segments with some baseline architecture information collected
• 9 – Segments that have demonstrated progress towards Target Architecture
• 1 – Records Management identified as EPA’s Priority “Segment” for the Feb 07 EA Maturity Assessment (needs completion)
• 1 – Land Quality Management Segment architecture completed and approved by Program Official (shared with OMB)
31
Advancing EA Segments
All Segments – Re-define Baseline Information - Validate Inventory of existing Tools and Services
Use Architectural Planning to: - Support Programmatic Business Planning - Complete Segment Architecture- Define core services/tools- Underpin Strategic Planning- Align IT Resources & Investment Planning- Track Strategic Performance Improvement
Role of IIS:- Advance EA Segment Development - Develop Queuing Strategy for Segments- Identify which Segment to Advance –Next to go Public
32
Proposed Segment Priorities• Tier 1: Priority Selected Segments
- Land Quality Management (submitted)- Records Management (in process)
• Tier 2: Advanced Segments in process - Water Quality Management - Substances Management - Air Quality Management
• Tier 3: Well defined Segments in process- Geospatial Services - Financial Services (component of Admin. Services) - Emergency Management - IT/IM Management
ACTION RECOMMENDATIONS: • Identify internally which segment(s) are most important and/or ready to become Priority Segments• Schedule completion of these segments: identify and schedule the remaining segments
34
BY 2009 CPIC Milestones
ACCOMPLISHMENTS
May 2 OMB Draft E-300 Guidance Available May 3 CPIC Kick-Off Meeting with SMEs May 9 E-300 Training for Project Managers (Group One) May 20 OMB Releases Draft A-11 (Sections 53 and 300) May 23 EPA’s E-300 Draft Guidance Available to CPIC Community May 23 E-300 Training for Project Managers (Group Two) June 5 E-300 Business Cases for Group One Due to OEI’s CPIC Team June 15 High Risk Report to OMB June 15 E-Gov Non-Duplication Report to OMB June 17 Scores and Feedback Available to Investments in Group One June 20 E-300 Business Cases for Group Two Due to OEI’s CPIC Team
COMING SOON
Early July OMB Releases Final A-11, Sections 53 and 300 July 6 OMB Final E-300 Format and Guidance to Program Offices July 6 Scores and Feedback Available to Investments in Group Two July 9 FY2009 Draft E-53 to OMB (Agency IT Budget) July 18 All E-300 Business Cases due to OEI for Second Evaluation August 2 Scores and Feedback Available for All Investments August 7 E-300 Business Cases due to OEI for Third Evaluation August 15 Scores and feedback on all Investments provided to SIOs, IIS Members, PMs, IMOs, and ODs August 22 SIOs Sign Cover Sheets for their E-300s Late August IIS Meeting to Review Final BY2009 Portfolio for OMB Submission August 31 E-300 Final Submissions due in eCPIC Sept 10 OMB Submissions: 53, 300, CPIC Documents, and applicable PIAs
35
ITIM Schedule
Q1 Q2 Q3 Q4
CPIC Major / CPIC Lite
BY08 Major IT Inv. Bus. Case – Updates to OMB Dec 20
BY08 Major IT inv. Bus. Case – Redacted Posted on Web Feb 20
EVMS Data Analysis Nov Feb May Aug
Operational Analysis Nov Feb May Aug
High Risk Report Nov Feb May Aug
BY09 Major IT Investment Abstracts Feb 24
BY09 Major IT Investment Business Cases 6/5, 6/20 7/18, 8/7
BY09 Major IT Investment Bus. Case Feedback 6/17 7/6, 8/2
BY09 Major IT Investment Business Cases to OMB Sept 10
CPIC Lite Annual Certifications Aug 1
CPIC Lite Proposal Forms Nov
Agency IT Budget – Exhibit 53
BY09 Draft Exhibit 53 to OMB July 9
BY09 Exhibit 53 to OMB Sept 10
Note: Red text indicates SIO Approval/Submission
36
ITIM Schedule
Q1 Q2 Q3 Q4
E-Government
E-Gov Non-Duplication Certification Nov Feb May Aug
E-Gov Scorecard Updates Nov Feb May Aug
Enterprise Architecture
OMB Submission Feb
EA Compliance Review Aug
EA Quarterly Milestone Report Dec Mar June Sept
Solution Architecture READ Record June 20
NDU Training June 25 - 29
Full Solution Architecture DME 300 (plus CPIC Lites) July 31
Chief Architect Certification of Portfolio Aug 15
Note: Red text indicates SIO Approval/Submission