information brochure | status 08/2014 ...€¦ · 3 dear readers! the joint-venture power...
TRANSCRIPT
2
table of contents
Gemeinschaftskraftwerk Inn .......................................................................4-8
Backwater Area and Weir System ..................................................................6
Mining Tunnels ................................................................................................7
Powerhouse .....................................................................................................8
Modern Construction-Site Management...................................................9-12
On-Site Production ..........................................................................................9
Quiet and Dust-Free Transport to the Storage Area .....................................10
Protecting People and the Environment .......................................................11
Improving the Ecological Condition of the Inn .............................................12
Operational Management and Safety .......................................................13
Timetable ..........................................................................................................14
Contact and Service Point .............................................................................15
LeGaL nOTICe
Publisher: Gemeinschaftskraftwerk Inn GmbH, Innstraße 52, 6500 Landeck, Tel.:+43 (0)50607-21744, www.gemeinschaftskraftwerk-inn.com,
Email: [email protected], Innsbruck District Court (FN 277806 p), VAT ID: ATU 62525529
Text & design: P8 GmbH, Sparkassenplatz 2, 6020 Innsbruck
Picture credits: GKI, Gappmaier, Pfennig, Shutterstock
3
Dear readers! The joint-venture power generating plant Gemeinschaftskraftwerk Inn (GKI) in the Upper Inn region at the Swiss-Austrian
border represents the largest new construction of a hydroelectric power plant in the Alpine region in this millennium. The
generating plant has undergone a comprehensive examination in both Austria and Switzerland. Following the completion
of its four-year construction phase (2014 – 2018), it will generate 400 gigawatt hours annually by using hydropower, a
renewable and domestic source of energy. This joint-venture power generating plant situated between the Swiss mu-
nicipality Valsot and the Austrian municipality Prutz, will be a milestone on the way to Tyrol‘s power autonomy, it will
significantly contribute towards achieving the goals of the European Energy Strategy and supports the conversion of the
energy industry to CO2 neutral and renewable energy generation.
The first plans for a power generating plant on the Upper Inn already existed in the 1920s. Since the project has been
taken up again by the shareholders of GKI – TIWAG, VERBUND and Engadiner Kraftwerke – a lot has happened. Our
idea has developed into a flagship project which has been further optimised several times and meets the highest environ-
mental standards and criteria. This development has been made possible by a comprehensive dialogue which took place
with the people of Oberes Gericht and Engadin and the many experts and planners involved. We would like to warmly
thank everyone involved and affirm a continued cooperation throughout the implementation.
The Gemeinschaftskraftwerk Inn is a project with many advantages. We will present these on the following pages. The
construction of GKI is going to make a significant contribution to the further use of the domestic renewable resource of
hydropower, and thus, to energy autonomy, which has been aspired to for such a long time, as well as to the reduction of
CO2 emissions. However, the GKI will not only provide significant advantages in terms of the environment and the energy
industry. It is the largest single investment made in the Oberland region of Tyrol in recent decades. Its construction and
operation means an important economic impulse for the region – in the form of employment, value added and industrial
development.
We are proud to be able to construct this milestone in environmentally-friendly power generation for Tyrol and the Engadin.
The GKI-Management
DI Johann Herdina, DI Peter Loidl, DI Michael Roth
4
Gemeinschaftskraftwerk inn:environmentally friendly, sustainable and cross-BorderHydropower has been used for pro-
ducing clean energy on the Upper Inn
since the 1950s. The Pradella-Martina
and Prutz-Imst Power Plants consti-
tute a “power plant chain” of which
the Gemeinschaftskraftwerk Inn will
become a link after its completion in
2018.
The joint-venture power genera-
ting plant Gemeinschaftskraftwerk
Inn (GKI) in the Upper Inn region at
the Swiss-Austrian border represents
a unique cross-border hydroelectric
power plant project. The largest part
of the power plant is built under-
ground and it will stretch from the
Martina district of the Swiss municip-
ality of Valsot across seven municipal-
ities in the Tyrolean region of Oberes
Gericht. The Gemeinschaftskraftwerk
Inn consists of three main elements:
a backwater area and weir system, a
pressure tunnel and a powerhouse.
In the border region between Mar-
tina and Nauders, a weir system with
a 15 m high weir for water collection
will be constructed. From the dammed
water, up to 75 m3/s will be conveyed
along the 23.2 km long pressure tun-
nel. This tunnel ends in the pressure
shaft which leads to the turbines in
the powerhouse in Prutz/Ried. The two
machine units located there, each con-
sisting of a Francis turbine and a gener-
ator, produce environmentally friendly
electricity. The water that is used in the
process then flows through the under-
ground channel back into the Inn.
GEMEINSCHAFTSKRAFTWERK INN
environmental Information:
In comparison to a modern coal-fired
power plant, GKI annually saves
•322,000 tons of carbon dioxide (CO2)
•168 tons of sulphur dioxide (SO2)
•180 tons of nitrogen oxide (NOx)
•8 tons of dust
Fact box
GKI - generating jobs and investment
GKI GmbH is investing around €461
million in the construction of the
Gemeinschaftskraftwerk Inn. The result
of this significant investment is a total
value added for the wider economy
which is far in excess of the actual in-
vestment volume. The regions benefit
greatly during the construction phase.
Up to 400 professionals will be em-
ployed, they will live, shop as well as use
the local amenities and restaurants in the
region. The local municipalities will also
profit from the additional tax income.
Pradella-Martina Power PlantInstalled capacity: 72 MWAnnual generation: 276 GWhGross head: 114 m
”THE GKI MASSIVELY REDUCES THE CURRENT NECESSITY
FOR TYROL TO IMPORT ELECTRICITY FOR THE
DOMESTIC SUPPLY”
5
One Project – many advantagesClean energy from hydropower
The generation of electricity in GKI takes
place without the emission of pollu tants.
The GKI not only uses the available po-
tential of hydropower as a renew able
energy source in order to generate
CO2-free electricity, but at the same time
also reduces the dependence on im-
ports of electricity generated from fossil
and nuclear fuels.
Dynamic Residual Water Model
In the summer months the dynamic re-
sidual water model guarantees a natural
drainage behaviour of the Inn. This special
model that has been developed by experts
regulates the release of residual water at
the weir. The water-level of the Inn near
St. Moritz in Switzerland is not influenced
and is used as the reference for the release
volume. The more water flows past the
measurement point there, the more is re-
leased at the weir in Ovella. Even on dry
summer days, the GKI guarantees a min-
imum discharge volume of 10 m3/s.
Natural habitat thanks to
surge protection
The current surge situation in the Inn river
with discharge deviations of up to 1:30
between the minimum and maximum
flow-rate prevents the positive devel-
opment of the body of water between
Martina and Prutz. With the help of the
new backwater area and the weir struc-
ture, the GKI absorbs this surge almost
completely and ensures a steady water
release.
Minimum water discharge sup-
ports the development of aquatic
creatures living in the river
The construction of the GKI will signi-
ficantly improve the situation of the fish
and the microorganisms living in the
Inn. The GKI guarantees a minimum
discharge of at least 5.5 m3/s in the eco-
logically sensitive winter months. This
allows the fish and the microorganisms
to develop without being disturbed in
their winter dormancy phase.
GEMEINSCHAFTSKRAFTWERK INN
“THE REDUCTION OF THE SURGE MEANS A SIGNIFICANT
ECOLOGICAL IMPROVEMENT FOR THE INN.”
Imst Power Plant
Installed capacity: 89.5 MW
Annual generation: 550 GWh
Gross head: 143.5 m
Gemeinschaftskraftwerk Inn• Installed capacity: 89 MW
• Annual generation: around 414 GWh (subject to optimisation)
• Flow-rate of the generating plant: maximum 75 m3/s
• Surface of the water catchment area: 1,960 km2
• Investment volume: around €461 million
• Gross head: 160.7 m
6 GEMEINSCHAFTSKRAFTWERK INN
Backwater area and weir systemA core part of the Gemeinschaftskraft-
werk Inn is the weir system. It dams the
Inn along a length of roughly 2.6 km in
the Austrian-Swiss border region. The
entrance to the pressure tunnel is loc-
ated at the orographic right side of the
weir system. A maximum of 75 m3/s of
water for electricity production is con-
veyed from the backwater area along
the headrace channel and the inclined
shaft to the powerhouse. During the
winter and in the weeks before and after
winter, a constant, ecologically adapted
minimum acceptable flow is released.
In the summer season, the dynamic
residual water model requires the ad-
aptation of the residual flow to the nat-
ural tributaries of the Inn. This water is
also used in an economically sensible
manner: an additional separate turbine
at the weir generates 7.84 GWh of
electricity.
Backwater area Data:
• Length: around 2.6 km
•Water depth: maximum 15 m
• Effective usable volumes: 500,000 m3
• Flow-rate: maximum 75 m3/s
Fact box
This is how we build the weir system
From 2018, the Inn will be dammed at Ovella and up to 75 m3 of water per second will be direc-ted into the tunnels. A fish pass allows fish to cross the weir system.
Even before construction begins, the entire
area of the weir system is secured with seven
rock fall protection nets, some of which have
a length of up to a few hundred metres. The
subsequent construction of the weir system
is then carried out in the wet-construction
method. In concrete terms, this entails the Inn
being diverted for limited sections depending
on the construction phase in order to create
“dry areas” for the construction work. The
weir is the first structure created. The Inn is
then directed through the completed weir in
order to drain the orographic right side. The
headrace entrance, the fish pass and the op-
eration building are constructed there and,
thus, the weir system complex is completed.
7
through the Undergroundtunnel to the turbineThe water flows from the weir sys-
tem in Ovella to the powerhouse in
Prutz/Ried through a 23.2 km long
pressure tunnel. This tunnel goes
through the mountain on the oro-
graphic right side of the valley at a
depth of approx. 130 m to 1.200 m,
depending on the topography. There
is only limited pressure in the pressure
tunnel, comparable to the pressure
in a normal household water-supply
pipe. This pressure increases to about
16 bar in the steeply falling and rein-
forced inclined shaft. The water then
hits the turbines in the powerhouse
and drives them.
GEMEINSCHAFTSKRAFTWERK INN
The view into the tunnel: The water flows through the mountain to the powerhouse along a distance of 23.2 km. Concrete segments produced on-site from reinforced concrete secure the head-race waterway.
Maria Stein: Starting point of tunnelling operations
Key Data on the Tunnel:
•Headrace channel length: 23.2 km
•Diameter of the the tunnel:
approx. 5.8 m
• Number of segments incorporated:
approx. 50,000
•Gross head: 160.7 m
• Diameter of the inclined shaft: 3.8 m
Fact box
The starting point of the tunnel is the
access tunnel in Maria Stein. The actual
12.7 km head-race tunnel is then milled
in the direction of the weir system
and around 8.9 km in the direction of
the powerhouse by tunnel boring ma-
chines. At the weir system in Ovella and
the powerhouse in Prutz/Ried, drilling
is also carried out from the other side.
The inside of the tunnels are lined and
secured with reinforced-concrete seg-
ments. In total, approximately 1 mil-
lion m3 of rock are excavated from the
mountain.
8
Powerhouse:the energetic core
GEMEINSCHAFTSKRAFTWERK INN
The Prutz/Ried powerhouse is the core
part of the Gemeinschaftskraftwerk
Inn. With two Francis turbines it gen-
erates electricity from hydropower. This
electricity is then conveyed via an un-
derground cable to the neighbouring
transformer station of the Kaunertal
power plant and from there it is fed
into the public grid. The water flows
along an underground channel back
into the Inn.
888.37
m.a.s.l.
867.00
869.07
846.08
873.85874.70
863.80865.50
883.87883.87
856.90
0 1 2 3 4 5 10m
High-Pressure Grout Curtain
Indoor Crane
Turbine Axis
High-Pressure Grout Curtain
Tailrace Channel
Anchor
Concrete Slab
2 Turbines
Generator
Current Terrain
State Road
Distribution Pipe
Horizontal Section
Prutz/Ried Powerhouse
Transformer
Underground electricity generation
The powerhouse is barely visible from the
outside. A mere 4.5 m of the buil ding is
above the level of the surrounding ter-
rain. The vast majority of the technical
equipment – such as, for example, the
turbines and generators – are installed
underground at a depth of around 26 m.
This type of construction offers the
advantage that it only has a minimum
impact on landscape and also operates
very quietly.
An interesting detail of the powerhouse
is the integrated crane with a span width
of 21 m in the machine hall. With the
help of the crane, the turbines and gen-
erators are lifted into their anchorings
and taken out for servicing work.
9MODERN CONSTRUCTION-SITE MANAGEMENT
On-site ProductionAt the construction site in Maria Stein,
the concrete segments are produced
in a production facility set-up for this
purpose. The facility will be located dir-
ectly next to the entrance of the access
tunnel. This makes the transport of these
reinforced concrete segments on public
roads redundant. The reinforced con-
crete segments produced on-site will be
used to line the pressure tunnel.
“THE PRODUCTION OF THE REINFORCED CONCRETE
SEGMENTS WILL TAKE PLACE DIRECTLY ON-SITE AND WILL NOT
CAUSE NOISE POLLUTION BE-CAUSE A HALL TO HOUSE
THE FACILITY WILL BE CONSTRUCTED.”
The area around the powerhouse is designed to merge with the sur-rounding nature. Little hills and hollows and a pond with a surface area of 240 m2 will be created.
Reusing excavated material
During the excavation work for the weir
system and the powerhouse, but in par-
ticular when digging the tunnel, a total
of roughly 1 million m3 of material will be
excavated from the mountain. To avoid
transporting this material with lorries,
a sophisticated recycling and storage
concept will be applied. All excavated
material which is suitable for the manu-
facture of concrete will be used directly
on-site in the production facility in Maria
Stein for the production of the concrete
segments. Material that is not suitable will
be transported on conveyor belts to the
near-by storage area.
10 MODERN CONSTRUCTION-SITE MANAGEMENT
Before and after: After the construction has been completed, the storage area will be integrated into the surrounding landscape and used for agriculture.
Quiet and Dust-free transportto the storage areaThe vast majority of the material ex-
cavated from the tunnels will be stored
near Maria Stein and Schönegg. This
material will be predominantly trans-
ported on conveyor belts from the
access tunnel to the near-by storage
area in order to minimise transport
with heavy machinery. The modern
conveyor-belt system is constructed
in such a way that it runs as quietly
as possible during construction op-
erations. A further advantage is the
efficient dust reduction resulting from
the fact that the excavated material
will be transported directly from the
tunnels to the storage area.
Renaturation of the storage area
An important aspect when storing
the excavated material is the natural
integration of the storage area into the
surrounding landscape and the possibil-
ity to return the area to agricultural use
after the completion of the construction
work. For this reason,the fertile top soil
is removed and stored so it can be put
back in place following completion of
the construction work. Subsequently,
the area that had been covered by the
storage area will be replanted in order to
be integrated as well as possible into the
landscape. Afterwards, the agricultural
use of the area will be possible to the
same extent as before.
11
Protecting People and the environmentRight from the planning phase, we have
attached great importance to being as
considerate as possible with respect to all
areas and aspects of the construction. In
the area of the powerhouse construction
site – the only area where work is carried
out in a densely populated area – the
vegetation around the school complex
will remain untouched and, in addition
to this natural barrier, a noise protection
wall between the construction site and
the school will be built. At the exit of the
construction site, a tyre-washing sys-
tem will also be put in place in order to
wash the tyres of the construction ma-
chinery and vehicles as they leave. Thanks
to these and further measures the strict
requirements stipulated by the environ-
mental impact assessment are fulfilled.
A large number of experts and the au-
thority constantly check the compliance
with all regulations and limit values and,
thus, ensure that the project is imple-
mented as considerately as possible.
MODERN CONSTRUCTION-SITE MANAGEMENT
Undisturbed learning: Before the construction of the GKI began, a modern ventilation system was installed in the Prutz-Ried New Secondary School. This allows fresh air supply and optimal air-conditioning of the classrooms without the windows needing to be opened.
ensuring free fish migration
In order to ensure that fish can pass the
weir system when swimming up and
down the river, a fish pass has been
integrated on the orographic right-hand
side of the weir system in cooperation with
experts. The fish can pass the weir system
upstream by means of 81 pools that are
arranged as steps. Downstream, the fish
can pass the weir system by means of
a downstream migration facility.
12
improving the ecological condition of the innWith the implementation of the GKI
and the resulting reduction of the
surge, the ecological condition of the
Inn and its banks will be improved.
Further ecological optimisations of
the Inn are achieved thanks to the ad-
ditional compensation measures and
the ecological restorations.
All areas used during the construction
will generally be greened with plants,
grass and woodland after the project
has been completed. Beyond that,
we will also implement various
measures which will improve the Inn
as a natural habitat. Example of this
are the creation of natural habitats
in Maria Stein or the widening of the
Inn‘s river bed at various points, where
gravel banks and islands will be set up
that will act as stream breakers and
riverside woodland will be planted. The
implementation of the compensation
measures as well as the ecological
restoration will be monitored by the
independent ecological construction
supervisory authority.
MODERN CONSTRUCTION-SITE MANAGEMENT
“WITH THE CONSTRUCTION OF THE GEMEINSCHAFTSKRAFT-
WERK INN, THE ECOLOGY OF THE INN RIVER APPROACHES
AN ALMOST COMPLETELY NATURAL CONDITION.”
a biotope for Maria Stein
Overview
Compensation Measures:
• Backwater area design in Martina
• Biotope in Maria Stein
• Planting of plants and grass
near the powerhouse
• Reforesting the Inn canyon
•Widening of the river banks and
construction of gravel banks along
the Inn
• Ensuring that fish can pass the
tributary inlets into the Inn
Fact box
In Maria Stein, a large natural habitat will
be created once the construction work
has been completed. The open gravel
areas, reeded zones and marsh areas
will provide a variety of different types
of natural habitats with permanent and
temporary bodies of water. Fish and small
animals will find a suitable habitat there.
The area surrounding the natural habitat
will be completely reforested and diverse
riverside floodplains created as a result.
13
24-hour monitoring
The operation of the GKI is fully auto-
mated and monitored and controlled
remotely around the clock from the
constantly manned control centre. All
measured values and operating messa-
ges are transmitted to the technicians
manning the control centres and are at
the same time recorded by the central
computer. In addition to that, all the
relevant areas of the power plant can
be monitored in real-time thanks to the
most modern monitoring systems.
The GKI is equipped with the most
high-tech security systems which corre-
spond to state-of-the-art standards. In
the project planning phase, all possible
events which could occur were ana-
lysed and simulated. The GKI structure
was then designed to be capable of
withstanding all potential events and
dealing sufficiently with their conse-
quences. Seals and the safety equip-
ment in particular – such as a pipe-burst
hatch – have been installed in order to
prevent water flowing out.
OPERATIONAL MANAGEMENT AND SAFETY
Complete 24-hour monitoring: Highly-qualified technicians monitor and control the fully-automated GKI.
“ALL THE IMPORTANT AREAS OF THE GEMEINSCHAFTS- KRAFTWERK INN CAN BE
MONITORED IN REAL-TIME THANKS TO EXTENSIVE
MONITORING SYSTEMS.”
14
2014 2015 2016 2017 2018
TIMETABLE
timetable
Maria Stein
Excavation of the access tunnel at the surge tank
Construction of the upper chamber
Excavation of the inclined shaft
Construction of the powerhouse
Excavation of the underwater channel
Technology and installations
Reinforcement of the inclined shaft
Prutz
Ovella
With the building decision made by
the shareholders of the Gemeinsch-
aftskraftwerk Inn GmbH, full con-
struction began on the three con-
struction sites in Ovella, Maria Stein
and Prutz in the summer of 2014.
A few months before, preparatory
work measures had already started:
rocks were secured, vegetation cleared
and building site facilities for the
Gemeinschaftskraftwerk Inn prepared.
In accordance with the timetable, all
elements of the power plant should
be completed by the middle of 2018
and ready for test operation. Follow-
ing the test operation, which will
take a number of months, the regu-
lar operation will commence once the
correct functioning and operation of
all machines and mechanical elements
of the power plant have been checked
and confirmed. From this point-in-
time, the Gemeinschaftskraftwerk Inn
will feed-in clean electricity produced
from domestic hydropower via the
Kaunertal power plant‘s transformer
station into the public grid.
Construction of the weir
Technology and installations
Construction of the reserved flow power plant and the pressure tunnel entrance
Construction of the access tunnel
Sealing and finishing of the tunnel
Excavation of the tunnel towards Ovella
Excavation of the tunnel towards Prutz
15
iCONTACT AND SERVICE POINT
The direct connection to GKI: Questions, requests and complaints, if these should arise, can be directed to the contact and service point of GKI.
Questions? requests?complaints?Providing local residents as well as
the interested people with constant
and transparent information is of
importance to us. The possibility to
communicate directly with those
responsible for the power plant is
ensured by the contact and service
point set up for this very purpose.
You can direct your questions, re-
quests or even complaints to the
contact point during its normal
office hours on weekdays from
9:00 am to 5:00 pm. Following an
immediate reply, improvement mea-
sures will be instigated if necessary.
The contact point can be contacted
via its own information line or under
the following e-mail address.
+43 664 8264770
+41 81 851 4313
[aUt]
[ch]
www.gemeinschaftskraftwerk-inn.com
CH
B180
Schmalzkopf2,724 m
Piz Mundin3,146 m
NaudererHennesiglspitze
3,042 m
Pfroslkopf3,148 m
Piz Lat2,808 m
Zirmesspitze2,944 m
Ovella Weir and BackwaterMax. Operating Level 1,029.50 mMin. Operating Level 1,025.50 m
Surge Tank
Apparatus Chamber
Pressure TunnelInner ∅ = ca. 5.8 m
Turbine Axis 863.80 m.a.s.l.
Tailrace ChannelLength = 300 m
Maria Stein Access Tunnel Pfunds
Prutz/Ried PowerhouseInclined Shaft,ArmouredInner ∅ = 3.8 mLength = 415.7 m
Access Tunnel
Ob
er
in
n
t
al
Inn
Horizontal SectionInner ∅ = 3.8 mLength = 40.3 m
Distribution PipeReturn Building
Ried
Tösens
Fiss1,483 m
Serfaus1,429 m
876 m
930 m
970 m
Maria Stein
Schuls, Davos
Landeck, Innsbruck
Nauders, Reschenpass
1,059.80 m
967.00 m
Prutz
Fendels1,352 m
Gfrans
Gschwendtbach
Gstals
Leiten
Frauns
Fisser Höfe
Ladis
St. Christina940 m
Steinbrücken
Breithaslach
Tösener Bach
Freitsberg
Boden
Schönegg
Badeteich
Prutz-Ried Secondary School
Urgenebner Bach
Resc
he
n Main
Road
Christiner Bach
Radurschlbach
Breithaslachbach
Beutelbach
Argebach
Kaunertal Power Plant
Substation
A u s t r i a S w i t z e r l a n d
a project of: