industry updates and key performance indicators - q3 fy 2015-16 [company update]
TRANSCRIPT
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
1/56
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
2/56
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
3/56
DISCLAIMER
This presentation may contain certain forward looking statements concerning JSPL’s
future business prospects and business profitability, which are subject to a number of
risks and uncertainties and the actual results could materially differ from those in suchforward looking statements.
The risks and uncertainties relating to these statements include, but are not limited to,
risks and uncertainties regarding fluctuations in earnings, our ability to manage growth,
competition (both domestic and international), economic growth in India and the target
countries for exports, ability to attract and retain highly skilled professionals, time and
cost over runs on contracts, our ability to manage our international operations,government policies and actions with respect to investments, fiscal deficits, regulations,
etc., interest and other fiscal costs generally prevailing in the economy. Past performance
may not be indicative of future performance. We do not undertake to update our
forward-looking statements.
This presentation is not intended, and does not, constitute or form part of any offer,
invitation or the solicitation of an offer to purchase, otherwise acquire, subscribe for, sellor otherwise dispose of, any securities in JSPL or any of it’s subsidiary undertakings or
any other invitation or inducement to engage in investment activities, neither shall this
presentation nor the fact of it’s distribution form the basis of, or be relied on in
connection with, any contract or investment decision. The numbers in this presentation
are purely indicative and could change later.
2Analyst Presentation
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
4/56
STEEL OUTLOOK
Q3
FY’16
INDUSTRYDEVELOPMENTS
OUR
FACILITIES FINANCIALPERFORMANCE
OPERATIONAL
PERFORMANCE
3
PRESENTATION OUTLINE
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
5/56
1670
1140
169121 106
45 30 15
1623
1114
166111 102
44 30 15
World Asia EU (28) North America CIS South America Middle East Africa
CY 14 CY 152.8%
1.8 %
2.5 % 0.5 %
Global Steel performance during CY ‘15
413 February 2016
4.3 %
0.2%
Fig in (Mt)
2.3%
8.6 %
World Crude Steel Production down 3% Y-O-Y
All steel producing regions recorded decline in
crude production
Source: WSA
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
6/56
India became 3rd largest Steel producing country in the world
513 February 2016
CY 14
#1 China
#2 Japan
#3 India
#4 USA
CY 15
Global Crude
production Rank 823
804
111
105
87
90
88
79
2.3%
5%
2.6%
10.5%
Source: WSA
200
194
28
26
21.8
21.9
22
18
Q3 FY 15 Q3 FY 16
3.3%
4.3%
0.7 %
15.6%
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
7/56
Global Steel over capacity leads to continued lower utilization
613 February 2016
79.8%
76.9%
74.2%
69.5%
73.4%72.5%
72.2%
68.0%
69.3%
68.3%
66.9%
64.6%
2 0 1 1
2 0 1 2
2 0 1 3
2 0 1 4
J a n
F e b
M a r
A p r
M a y
J u n
J u l
A u g
S e p
O c t
N o v
D e c
2015
# More than 750 Mt of globalsteel capacity remains
unutilized
Source: WSA
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
8/56
Crude Production:o April – Dec ‘15: Crude steel production grow up by 1 % (y-o-y) only.
Real Consumption of Steel:
o April – Dec ‘15 : India’s Consumption of finished steel grow by 4 % (y-o-y)
Importso April – Dec ‘15: increased by 29 % (y-o-y)
Exportso April – Sept‘15: Exports down by 30 % (y-o-y)
How the Indian Steel Industry fared during April- Dec‘15 (source: JPC)
(Qty :million MT) FY ‘15 April – Dec ‘15
Qty
change
(y-o-y) Qty
change
(y-o-y)
Production: Crude Steel 88.3 8% 67.1 1%
Finished Steel (Non Alloy+Alloy)
Import 9.3 71% 8.4 29%
Export 5.5 (8)% 2.9 (30)%
Real Consumption 76.4 3% 58.9 4%
Source: JPC
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
9/56Source: *The Economist Intelligence Unit, Global Forecasting Service, dated June 17, 2015; # World Steel Association 3
India’s per capita steel consumption at 59.4 Kg below World average of 217 Kg(2014)*
Consumption of steel products is bound to increase with economic growth.
Key initiatives being undertaken by Government would propel Steel demand:
•Housing for all by 2022
• “Make in India” lead to localization of manufacturing
• 24x7 Power for All initiative by 2019
• 100 Smart Cities by 2022
• AMRUT, Bullet Trains & Metro Rails, Railway Corridors, Dedicated Freight
Corridors
• 175,000 MW Clean-Energy initiative by 2022
India will continue to grow & Consume More Steel
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
10/56
STEEL OUTLOOK
Q3
FY’16
INDUSTRYDEVELOPMENTS
OURFACILITIES
FINANCIALPERFORMANCE
OPERATIONALPERFORMANCE
9
PRESENTATION OUTLINE
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
11/56
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
12/56
Domestic Iron Ore prices
1113 February 2016
Iron Ore Lump Prices Iron Ore Fines Prices
Odisha’s iron ore fines prices decreased by
- 11% since Apr’15
- 45% since Oct’15
Chhattisgarh’s iron ore fines prices decreased by
- 37% since Apr’15
- 49% since Oct’15
Odisha’s iron ore lumps prices decreased by
- 51% since Apr’15
- 26% since Oct’15
Chhattisgarh’s iron ore lumps prices decreased by
- 46% since Apr’15
- 28% since Oct’15
4400
4030
3820
35503325
30002900
2150
4040
38403840
3840
3840
2900
2215 2180
1600
2000
2400
2800
3200
3600
4000
4400
4800
5200
P r i c e i n R s / t ( e x - m i n e s )
Odisha DR Lumps (5-18mm, Fe 62-
63%)
Chhattisgarh DR Lumps (6-40mm,Fe 65.5%)
1800
1650
1600 15251430
1600
14501300
2546
2243
1960
1660 1660 16601560
1560
1560
900
1200
1500
1800
2100
2400
2700
3000
P r i c e i n R s / t ( e x - m i n e s )
Odisha Fines (0-10 mm, Fe 63%)
Chhattisgarh Fines (0-10 mm, Fe64%)
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
13/56
Declining Pellet Prices
1213 February 2016
Pellet Prices at Barbil-Keonjhar region witnessed a fall of 44% since Apr’15 & by around 16%
since Oct’15
5350
4775
4350
40754200
4400
3570
3200
2700 2900 3000
2000
2500
3000
3500
4000
4500
5000
5500
6000
Apr'15 May'15 Jun'15 July'15 Aug'15 Sep'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16
P e l l e t P r i c e s ( R s / M T )
Avg. Pellet Price Trend in Eastern India
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
14/56
Domestic Finished steel price trend (Oct’15-Feb’16)
1313 February 2016
30103
26896
25852
27124
23000
24000
25000
26000
27000
28000
29000
30000
31000 Domestic : Flat Steel Price Trend
HR Coil- Delhi HR Plate- Delhi
25600 25500
27400
23000
24600
26000
22000
23000
24000
25000
26000
27000
28000
Domestic : Long Steel Price Trend
Wire Rod-Raipur TMT Rebar- Raipur
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
15/56
Domestic Semis & intermediaries price trend (Oct’15-Feb’16)
1413 February 2016
24860
23590
22650
25700
19685
18440
17400
20000
14250
12450
12700
13900
11000
13000
15000
17000
19000
21000
23000
25000
27000
Domestic Semis & Intermediaries: Price Trend
Pencil Ingot- Mandi
Scrap (HMS 80:20)- Mandi
Sponge Iron- Raipur
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
16/56
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
17/56
Source: CEA
198.5
5.8
42.6 38.8
285.7
Thermal Nuclear Hydro Renewables Total
Installed Capacity (GW) in India
Thermal
69%
Nuclear2%
Hydro
15%
Renewables
14%
Wind 25.1
Solar 4.3Bio Mass
4.7
Small
Hydro 4.1
Renewables (GW) Portfolio
Installed Capacity
Portfolio
10610
11226
Apr'14 - Dec'14 Apr'15 - Dec'15
Generation Capacity Addition in MWs Y-o-Y
5.81% Increase
Installed Capacity in India (Dec 2015)
280 GW in
Q2FY16
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
18/56
794.7
829.8
H1+Q3 FY15 H1+Q3 FY16
Electricity Generation in BUs
4.4 % Increase Y-o-Y
-3.0%-3.6%
-1.6% -1.7%
-4.0%
-3.5%
-3.0%
-2.5%
-2.0%
-1.5%-1.0%
-0.5%
0.0%
Energy Deficit Peak Deficit
Dec-14 Dec-15
Major Highlights (Dec 2015)
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
19/56
15 18 20 2731 34 37 40
85 82 80 7369 66 63 60
2009 2010 2011 2012 2013 2014 2015 H1+Q3 FY16
Ever Increasing % Share by Private Sector Private Government
Increasing Private Share in Capacity and reducing % PLF
149 160 174 200 224 245 272 285
77% 78% 75% 73%70% 66% 66% 61%
0%
20%
40%
60%80%
100%
0
50
100
150
200
250
300
2009 2010 2011 2012 2013 2014 2015 H1+Q3 FY16
Total Capacity % PLFINSTALLED CAPACITY (GWs) vs PLF (%)
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
20/56
Coal Block
Auction
• In January, Govt annulled 4th round of 9 coal block auctions for non-regulated sector due to muted
response
Industry Update - Coal, Power and T&D
Long TermCoal Linkage
• Long term Fuel linkage will now be done only via auction for un-regulated sector by CIL & SECL,
24MT in the 1st year.
UMPPRevised
Documents
• Power Ministry will seek Cabinet approval for revised bidding documents for Ultra Mega Power
Projects (UMPPs)
• Bid documents have been finalised and 3 plants in Bihar, Odisha & Tamil Nadu will be auctioned by
March-end entailing an investment of over Rs 80,000 crore.
New TariffPolicy
• The Cabinet has approved amendments to the power tariff policy . Some highlights of the Policy
Amendments are :
Microgrids for remote unconnected villages and small power plants near coal washeries
Allows sale of un-requisitioned power in the spot market
Mandatory minimum purchase for clean energy
No inter-State transmission charges and losses to be levied for solar and wind power.
Allows cost pass-through for use of imported and e-auctioned coal
All new inter-state transmission projects through competitive bidding
Smart meters compulsory for consumption over 200 units
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
21/56
‘ UDAY-Ujjwal Discoms Assurance Yojana ’Scheme for DISCOMS
• The Cabinet has cleared the debt-recast and reform package to revive loss-making DISCOMs. As of March 2015,
the DISCOMs accumulated losses of INR 3.8 trillion (2.8% of GDP) with their outstanding debt nearly doubling
over the last three years to INR 4.3 trillion. The Plans includes following initiatives :
Improving Operational Efficiency : Reduce AT&C Losses to 15% in 2018-19 / Smart Grids & Smart Metering
/ Reduce gap between cost and revenue from Power / Up gradation of Network / GIS Mapping of losses
Reduction in Power Costs : Coal Swapping, Better Linkages, cheap domestic coal, Increased supplyPrice
Rationalization, Correct Tariff Fixation
Reduction in interest costs : States shall take over 75% of DISCOM debt as of Sep15 – 50% in FY16 and 25%in FY17. States will issue Non-SLR bonds in lieu of the debt and the remaining 25% will be converted by
Banks/FIs into loans/Bonds.
Enforcing financial discipline : Future losses of DISCOMs will have to be taken up by states in a phased
manner, starting from FY18. Working capital allowed will be only 25% of DISCOM’s last year’s revenue.
Additional Benefits for states accepting schemes on achievement of operational milestone : priority
funding through DDUGJY, IPDS / additional coal at notified prices / low cost power from NTPC
Policy Interventions : Segregation of carriage from content / Rationalize tariff determination process /
recovery of revenue by Licensees without any revenue gap / Renewable Energy Generation Obligation
(RGO) on all future coal and lignite based power plants
• 15 States have agreed to join UDAY Scheme as on date
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
22/56
STEEL OUTLOOK
Q3
’FY16
INDUSTRYDEVELOPMENTS
OURFACILITIES
FINANCIALPERFORMANCE
21
PRESENTATION OUTLINE
OPERATIONALPERFORMANCE
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
23/56
Steel PowerMines &Minerals
GlobalVentures
Current Capacities – Domestic & Global
Business Segments
• Domestic
**Includes 600 MW - synchronized & will be commissioned in FY16
ConstructionMaterial &
Solution
22
4.75 MTPA Steel* 3.11 MTPA*
IPP – 3400** MW
CPP – 1649 MW
Renewable – 24 MW
2 MTPA Steel
6.25 MTPA Mines
Cement
Road solutions
LGS
Copyright @ 2015 Jindal Steel & Power Limited
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
24/56
Capacity in
deail
Hot Metal
(6.75 MTPA)
BF 2.13 MTPA
DRI 3.12 MTPA
HBI 1.50 MTPA
Liquid Steel
(6.75 MTPA)
SMS 6.75 MTPA
Finished Steel
(5.25 MTPA)
WRM 0.60 MTPA
RUBM 0.75 MTPA
MLSM 0.70 MTPA
Plate Mill 2.20 MTPA
BRM 1.0 MTPA
Steel Capacities across Life Cycle
** To be commissioned 23Copyright @ 2015 Jindal Steel & Power Limited
BRM 2.8* - Will be commissioned by 1QFY17 Effective Finished Steel 8.05 MTPA
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
25/56
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
26/56
JSPL diversifies into Value added products – will boost EBITDA margins
Speed Floor LGSCement
Road Stabilizer Bricks & PaversEPS Panels LWA
Welded MeshCut & Bend
25
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
27/56
Angul
Satara
Tamnar
RaigarhCaptive power projects (within JSPL)
ProjectCapacity
(MW)Fuel Configuration Status
DCPP, Raigarh 540 Coal 4x135 MW Operational
JSPL, Raigarh 299
Coal &
waste
heat
2x25 MW & 40 MW
(Waste heat)
2x55 MW
3x25 MW
24 MW
Operational
Angul, Odisha 810 Coal 6 x135 MW Operational
Independent Power Projects (IPP)
Project
Capacity
(MW) Fuel
Configurati
on Status
Tamnar 1(a) 1,000 Coal 4x250 MW Operational
Tamnar 2(a) 2,400 Coal 4x600 MW
1,800 MW
operational,
balance 600 MW
synchronized
Satara (b) 24 Wind 18x1.5 MW Operational
(a) Within JPL; (b) Within JSPL
IPP CPP
One of the largest thermal portfolios in India
JSPL - Power Capacities
26Copyright @ 2015 Jindal Steel & Power Limited
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
28/56
96.43% subsidiary of JSPL
JINDAL POWER LIMITED
27
EUP -I1000MW (4 X 250)
EUP -II1200MW (2 X 600)
EUP -III1200MW (2 X 600*)
*600 MW Synchronized, Await Commissioning
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
29/56
Tamnar-I, 1,000 MW (EUP I)
Awaiting clarity on Tara
Coal Block
In the interim, coal
sourced through – market
purchase and e-auction
Bilateral/short term/
merchant
258km transmission line
from plant to national grid
Tamnar-II - 1,200 MW (EUP II)
Long term linkage from
Mahanadi Coal Limited
(MCL) and South Eastern
Coalfields Limited (SECL)
TNEB – 400MW
CSEB – 60MW
KSEB – 200MW
KSEB – 150MW
Full Open access for 400MW
TNEB PPA commenced from
Oct 2015
Tamnar-II - 1,200 MW (EUP III)
Awaiting clarity on Gare
Palma IV/2 & 3 Coal mine
Market purchase and e-
auction
CSEB – 60MW
Open access to be finalised
against PPAs
FSA
PPA
Evacuation
Raw materials, transmission & PPAs in place for achieving higher PLF
(a) E xc ludi ng auxi li ary consumpti on
Key Contractual Arrangements for JPL
28Copyright @ 2015 Jindal Steel & Power Limited
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
30/56
Project Buyer Type
Period Quantum
(MW)From To
Tamnar II
(Phase 1)Tamil Nadu Long Term Feb-14 Sep-28 400
Tamnar II
(Phase 1)
KSEB
Long Term Jun-16 May-41 200
Tamnar II
(Phase 1)Long Term Oct-17 Sep-42 150
Tamnar II
(Phase 1)
Chhattisgarh
Long Term
After commercial
operation of Unit and for
complete life of plant
60
Tamnar II
(Phase 2)Long Term
After commercialoperation of Unit and for
complete life of plant
60
PPA Arrangements
Over 30% of total capacity tied up *
* Out of 3400 MW (IPP) 29Copyright @ 2015 Jindal Steel & Power Limited
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
31/56
Upcoming PPAs
Procurer Type Quantum (MW) Schedule delivery Tenure (years)
Uttar Pradesh Long Term 2,800 Oct-16 15
Bihar Long Term 5003 year after
submission of RFPNA
Uttar Pradesh Long Term 1,000 Oct-16 15
JPL - Well placed on account of low capital cost base
30Copyright @ 2015 Jindal Steel & Power Limited
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
32/56
• Tamnar II (Phase 1):
350 MW KSEB PPA, transmission corridor
is expected from Jun-16
• Long term access from WR to NR granted
for 557 MW is expected to be available by
Jun-16 upon commissioning of Champa –
Kurukshetra HVDC link (3,000 MW). This
will be useful for power sale to UP
• No constraint in power evacuation to
Western and Eastern Region entities
including Bangladesh, where we have
participated for 250 MW power supply
Kolhapur
Narendra
Wardha
Warangal
Warora
Nizamabad
Raigarh P.S
Pugalur
Jaipur
Kurukshetra
ChampaJabalpur
Orai
Gwalior
Banaskantha
Chittorgarh
Gorakhpur
Barh
Gaya
Vanarasi
3000 MW+ 3000
MW
6000MW
S
R
WR
NR
ER
NE R
Oct’1
5
Shujalpu
r`Angul
Srikakulam
DharamjaigarhRanc
hiJharsugu
da
Rapp
C&D
Bishwanath Charali
Agra
Legends:
400 kV D/C Line
765 kV D/C Line
765 kV S/C Line
800 kV HVDC Line
Rihand
Vidhyanchal
Transmission constraints expected to be resolved in the near term
Upcoming Transmission Infrastructure
31Copyright @ 2015 Jindal Steel & Power Limited
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
33/56
Developing a coal mine
(3 MTPA) in
Mozambique’s coal-rich
Moatize region
Coal resources
estimated at 1.2 bn
tonnes including coking
coal
Mozambique,
Africa
JSPL’s Kiepersol Colliery produces Anthracite
coal, sold domestically and internationally Plans
to ramp up capacity
South Africa, Africa
Botswana, Africa
Acquired CIC Energy in 2012 for 120 mn USD
Coal Mine with Resource of over 3 bn MT (high
grade thermal coal)
Acquired 82.04% controlling
stake in Wollongong Coal
(Erstwhile Gujarat NRE coking
coal Limited)
Australia
1.5 MT HBI & 2 MT SMS Plant – plans to make it an Integrated
Steel Plant
Shadeed, Oman
Medium to large sizedeposits of prime hard
coking and low ash – low
sulphur thermal coal for
open-cast operation
Indonesia, Asia
Summary of International Operations
Copyright @ 2015 Jindal Steel & Power Limited 32
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
34/56
Oman
Holding structure for global operations
Jindal Steel & Power Ltd
Listed Operating Entity in India
Australia
Coking Coal
South Africa
Anthracite Coal
Mozambique
Thermal/ Coking Coal
Jindal Steel & Power (Mauritius) Ltd
Holding company for overseas business
2 MTPA Steel plant
Copyright @ 2015 Jindal Steel & Power Limited 33
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
35/56
Jindal Shadeed Iron & Steel, Oman
Marching towards becoming a Fully Integrated Steel Plant
1.5 HBI 2 MTPA SMS 1.4 MTPA Rolling Mill(By 4QFY16)
34Copyright @ 2015 Jindal Steel & Power Limited
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
36/56
35
First & Largest Integrated steel plant of Oman
Third largest in Arabian Peninsula
Port based steel plant
Largest Arc furnace in Arabian Peninsula, with contracted natural gas
Worlds Best Performing Midrex plant (category 1.5MTPA)
Products : HBI, Blooms & Billets
Salient Features
Copyright @ 2015 Jindal Steel & Power Limited
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
37/56
In July 2010, JSPL acquired Shadeed Iron & Steel Co. LLC
• Gas-based 1.5 MTPA HBI plant
commenced production in
January 2011
• Commissioned SMS of 2 MTPA
in April 2014
• 1.4 MTPA Rebar to be
commissioned in 4QFY16
36Copyright @ 2015 Jindal Steel & Power Limited
Rolling Mill
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
38/56
37
• Total Project Cost: USD 190 million
• Expected to be commissioned in 4Q FY 2016
g
1.4 MTPA Rebar Mill
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
39/56
38
• Iron Ore Pellets from Vale (Next door neighbour)
• Natural Gas from Oman Government through long term contract (at concessional prices)
• Scrap from External Purchase
Sourcing of Raw Materials - Oman Plant
Sales break up by customer (FY-15) Sales break up by geography (FY-15)
US
Others
Conares
Sohar SteelEmirates
JSW
Al- Wataniyah
Arcellor
Vilmeks
Fecat
UAE
Kuwait
Others
Oman
India
China
Ethiopia
South Africa
South Korea
ItalySaudi Arabia
Key Markets
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
40/56
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
41/56
A) STEEL BUSINESS
• 19% growth in Steel Production in Q3 y-o-y (1.07 million MT in Q3 FY 16 vs 0.89 million MT in
Q3 FY15)
• Two fold growth in TMT Retail sales in Q3 y-o-y
• Secured order of Prime rails for DFCC
Ever highest Monthly Rail despatch in Jan – 16
Launch of E- Commerce portal for TMT
Performance highlights
4013 February 2016
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
42/56
• JSPL-Barbil Pellet Plant awarded with most prestigious JIPM award for TPM –Excellence
• First pellet plant in the world to be conferred with this JIPM award
• Jindal Shadeed won following laurels
• Prestigious “Sultan Qaboos Award” for Industrial Excellence by the Ministry of
Commerce and Industry on February 9, 2016
• 2016 Steel Manufacturing Product Line Strategy Leadership Award, GCC'', at GIL
2016: Middle East, Dammam, Saudi Arabia on February 10, 2016• Jindal Shadeed have received 2 Awards from Midrex
For the achievement of 5 Million tons of production within 4 years of Operation [2011 –
2014]
For the achievement of Exceptional annual operational availability for the year 2014 -
98.51%. (Total 3 plants have received the awards out of 72 Midrex DR Plants in the world,
and Jindal Shadeed stands number 2.) • JSPL Raigarh got placed in Limca book of world records’ for manufacturing longest 121
meter long single piece track rail
• JPL received “Par Excellence Award for 5’S implementation” by QCFI on 7th Nov’ 15
Awards & Recognitions
4113 February 2016
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
43/56
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
44/56
Consolidated Steel Sales Volumes
Total Steel Sales volumes up 23%*
Copyright @ 2015 Jindal Steel & Power Limited 43*Year on Year
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
45/56
THE PANTHER ADVANTAGE
Construction TMT Rebars
44Copyright @ 2015 Jindal Steel & Power Limited
Compelling Brand Recall
Customer centric B2C Model
Panther epitomizes strength & agility – the brand promise
Jindal Panther – USP
Excellent bonding with cement
Uniform Parallel Rib Pattern
Earthquake Resistant
Corrosion Resistant
Greater Resistance to Fire
Key Customers
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
46/56
Key Customers
45Analyst Presentation
PRESENTATION OUTLINE
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
47/56
STEEL OUTLOOK
Q3
FY’16
INDUSTRY
DEVELOPMENTS
OUR
FACILITIES
FINANCIAL
PERFORMANCE
46
PRESENTATION OUTLINE
OPERATIONAL
PERFORMANCE
Analyst Presentation
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
48/56
47- -
Standalone Q3 FY 16 –Snapshot of Key Financials
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
49/56
48- -
Consolidated Q3 FY 16 –Snapshot of Key Financials
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
50/56
49- -
JPL–Snapshot of Key Financials
2014-15Q3 Q2 Q3
Turnover 815 889 825
EBITDA 186 168 414
EBITDA% 23% 19% 50%
PBT 51 61 (798)
PAT 38 45 (758)
Depreciation + Amortization 130 130 131
Cash Profit 171 178 -532
Generation (million units) 2,580 2,728 2699
PLF (%) - 4X250 MW 70% 60% 96%
PLF (%) - 3X600 MW 26% 35% 20%
Particulars 2015-16
i i i f
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
51/56
Key Initiatives for FY16
Copyright @ 2015 Jindal Steel & Power Limited 50
Capacity Utilization Operational Efficiency
Financial Prudence
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
52/56
• Reduce Working capital – Receivables & Inventories
• Skill Enhancement to enable multitasking & productivity improvements
(PBO)
• Go for volume to ensure full capacity utilization
• Focus on “Value Added Products”
• Thrust on Heavy Fabrication business
• Commission Rebar mill in Angul
• Operationalize mines in Australia
• Diversify into High Rise building segment and Low cost housing segment &
offer complete package of Steel and Construction material
Key Priorities & Focus Areas
5113 February 2016
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
53/56
- - 52
Centrade Business Park, KRasa, Noida (Structure,Speedfloor)
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
54/56
- -
Dharamsala Cricket Stadium Extension
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
55/56
For any information please contact: -
Mr. D.Balasubramanyam – Head of Investor Relations
Tel: +91 11-26739166
Mobile: +91 8130755166
Email: - [email protected]
Mr. Nishant Baranwal – Investor Relations
Tel : +91 11-26739178
Mobile:+91 8800690255
Email: - [email protected]
54Analyst Presentation
-
8/20/2019 Industry Updates and Key Performance Indicators - Q3 FY 2015-16 [Company Update]
56/56