![Page 1: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/1.jpg)
1
Industry Day
![Page 2: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/2.jpg)
2
Airport Information
• Medium Hub Airport
• All domestic
• 14 gates
• Approaching 6 MAP
• Common Use Terminal
• Residual cost agreement
• Air Carriers• Alaska, American, Delta,
Jetblue, Southwest, Spirit, United
![Page 3: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/3.jpg)
3
Why replace the current terminal?
• Runway separation does not meet current standards
• Seismically deficient
• Inconsistent capability between gates
• Complicated maneuvers required on airfield
• Aging terminal building
• Limited concessions and amenities
• Underserves users with disabilities
![Page 4: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/4.jpg)
4
Opening Day, 1930
![Page 5: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/5.jpg)
5
Why replace the current terminal?
![Page 6: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/6.jpg)
6
![Page 7: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/7.jpg)
7
![Page 8: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/8.jpg)
8
![Page 9: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/9.jpg)
9
Passenger convenience and accessibility
![Page 10: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/10.jpg)
10
![Page 11: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/11.jpg)
11
![Page 12: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/12.jpg)
12
![Page 13: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/13.jpg)
13
![Page 14: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/14.jpg)
14
Concessions
![Page 15: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/15.jpg)
15
![Page 16: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/16.jpg)
16
![Page 17: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/17.jpg)
17
![Page 18: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/18.jpg)
18
![Page 19: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/19.jpg)
19
Benefits
• Safety • Proper runway separation
• Meets current seismic design standards
• Customer Convenience • ADA
• Amenities
• Maintain easy access and convenience
• Community • Resilience (Natural disasters)
• Sustainability/Energy efficiency
• Reduced emissions
![Page 20: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/20.jpg)
20
Benefits
• Operations• Reduction in taxi times and runway crossings
• Simplified aircraft maneuvers
• Consistency and capability at all gates
• Increased concessions revenue
• Expanded holdroom size
• Faster check-in
• Centralized TSA checkpoint
• Centralized bag check/screening
![Page 21: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/21.jpg)
21
Program Schedule
Development Agreement a
CEQA – FEIR a
Concept Validation Complete a
Program Manager Selected a
Design-Builder Selection
EIS ongoing Q4-2020 completion
Design Starts Q4-2020
Construction Starts Q3-2021
RPT Opens Q3-2024
Existing Terminal Demolished Q3-2025
![Page 22: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/22.jpg)
22
Development Agreement with City of Burbank
• 2016, 20 year duration
• 355,000 sq ft terminal (232,000 current)
• 14 gates (same as current)
• Public design charrettes workshop process
• 6,637 public parking spaces (same as current)
• Demolish existing terminal within 12 months of opening
![Page 23: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/23.jpg)
23
![Page 24: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/24.jpg)
24
![Page 25: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/25.jpg)
25
Preferred Location
NE Quadrant• Green field, no utilities, not
graded, narrow width• Elevation change 30+ ft
north to south• Greater distance from
Regional Intermodal Transportation Center
Alternative LocationSW Quadrant
![Page 26: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/26.jpg)
HOLLYWOOD BURBANK AIRPORT
REPLACEMENT PASSENGER TERMINAL CONCEPT VALIDATION
COPYRIGHT © BUROHAPPOLD ENGINEERING. ALL RIGHTS RESERVED
![Page 27: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/27.jpg)
The proposed Replacement Passenger Terminal
is feasible in the preferred location
HOLLYWOOD BURBANK AIRPORT
REPLACEMENT PASSENGER TERMINAL CONCEPT VALIDATION
![Page 28: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/28.jpg)
The proposed Replacement Passenger Terminal works in
the preferred location
✓ ADG III Aircraft Layout (Same capability at all gates)
✓ 14 Gates
✓ 355,000 SF Terminal
CO N C LU S I O N
![Page 29: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/29.jpg)
P E A K H O U R C A PAC I T Y
![Page 30: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/30.jpg)
M A S S I N G
Replacement Passenger Terminal
Parking
GSE &
Maint.
ARFF
ATCT
![Page 31: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/31.jpg)
P R O P O S E D L AYO U T : G R O U N D F LO O R
Total Floor Area = 247,601 SF
![Page 32: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/32.jpg)
P R O P O S E D L AYO U T : B A S E M E N T
Total Floor Area = 53,354 SF
Basement
![Page 33: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/33.jpg)
P R O P O S E D L AYO U T : S E CO N D F LO O R
Total Floor Area = 54,045 SF
Second Floor
![Page 34: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/34.jpg)
E L E VAT I O N LO O K I N G E A S T
![Page 35: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/35.jpg)
1. Terminal Depth
2. Site Grade
3. Airport Access
4. Employee Parking
5. Public Parking Structure
6. Air Traffic Control Tower
7. Aircraft Rescue and Fire Fighting Facility
O P P O RT U N I T I E S TO B E A D D R E S S E D I N D E S I G N P H A S E
![Page 36: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/36.jpg)
36
Public Design Charrettes Workshops
• Last workshop was held October 26, 2019
• Deliverable will be part of PDM and selection criteria for RFP
![Page 37: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/37.jpg)
37Design Charrette Workshop 1
![Page 38: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/38.jpg)
38Design Charrette Workshop 1
![Page 39: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/39.jpg)
39Design Charrette Workshop 1 - Vision Boards
![Page 40: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/40.jpg)
40Design Charrette Workshop 1 - Vision Boards
![Page 41: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/41.jpg)
41Design Charrette Workshop 1 - Sketches/Board Shots
![Page 42: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/42.jpg)
42Design Charrette Workshop 1 - Sketches/Board Shots
![Page 43: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/43.jpg)
43Design Charrette Workshop 2
![Page 44: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/44.jpg)
44Design Charrette Workshop 2
![Page 45: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/45.jpg)
45Design Charrette Workshop 2 - Posters
![Page 46: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/46.jpg)
46Design Charrette Workshop 2 - Posters
![Page 47: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/47.jpg)
47Design Charrette Workshop 3 & 4
![Page 48: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/48.jpg)
48Design Charrette Workshop 3 & 4 - Posters
![Page 49: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/49.jpg)
49
Financial Feasibility
The Authority is developing a Plan of Finance based on the availability of:• Airport Improvement Program funds
• PFC revenue backed bonds
• U.S. DOT Credit Programs
• Authority equity
• General Aviation Revenue Bonds
![Page 50: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/50.jpg)
50
Program components - not just a terminal
Design-Build Scope Elements• Replacement Passenger Terminal
• Roadways/utilities/parking structures
• Aircraft apron
• Air Cargo/GSE
Other Program Elements to be Delivered Under Separate Contracts• Demo Existing Terminal Building
• Aircraft Rescue Fire Fighting Facility/EOC
• Taxiways A & C extensions
![Page 51: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/51.jpg)
51
Delivery Method
Why Progressive Design Build• Facilitates coordination & cooperation between Airport, Airlines,
Designer and Builder
• Integration of Design and Build staff critical to accurate understanding of construction cost and schedule in real time as design progresses
• Single procurement / Single contract
• Establish Project Cost Expectations during D-B procurement and design to the defined target budget
• Allows Construction to start prior to finalizing design
![Page 52: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/52.jpg)
52
![Page 53: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/53.jpg)
53
Program Schedule
![Page 54: Industry Day - Elevate Bur · 10/26/2019 · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder](https://reader035.vdocuments.us/reader035/viewer/2022071215/60440c201bf2426aac10a32b/html5/thumbnails/54.jpg)
54
Today’s attendees list, project updates, and a portal to submit questions are available on
elevatebur.com
If you do not wish to be included in the attendees list, please alert the staff at the check-in desk