industry day - elevate bur · 10/26/2019  · 51 delivery method why progressive design build...

54
1 Industry Day

Upload: others

Post on 11-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

1

Industry Day

Page 2: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

2

Airport Information

• Medium Hub Airport

• All domestic

• 14 gates

• Approaching 6 MAP

• Common Use Terminal

• Residual cost agreement

• Air Carriers• Alaska, American, Delta,

Jetblue, Southwest, Spirit, United

Page 3: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

3

Why replace the current terminal?

• Runway separation does not meet current standards

• Seismically deficient

• Inconsistent capability between gates

• Complicated maneuvers required on airfield

• Aging terminal building

• Limited concessions and amenities

• Underserves users with disabilities

Page 4: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

4

Opening Day, 1930

Page 5: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

5

Why replace the current terminal?

Page 6: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

6

Page 7: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

7

Page 8: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

8

Page 9: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

9

Passenger convenience and accessibility

Page 10: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

10

Page 11: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

11

Page 12: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

12

Page 13: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

13

Page 14: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

14

Concessions

Page 15: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

15

Page 16: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

16

Page 17: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

17

Page 18: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

18

Page 19: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

19

Benefits

• Safety • Proper runway separation

• Meets current seismic design standards

• Customer Convenience • ADA

• Amenities

• Maintain easy access and convenience

• Community • Resilience (Natural disasters)

• Sustainability/Energy efficiency

• Reduced emissions

Page 20: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

20

Benefits

• Operations• Reduction in taxi times and runway crossings

• Simplified aircraft maneuvers

• Consistency and capability at all gates

• Increased concessions revenue

• Expanded holdroom size

• Faster check-in

• Centralized TSA checkpoint

• Centralized bag check/screening

Page 21: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

21

Program Schedule

Development Agreement a

CEQA – FEIR a

Concept Validation Complete a

Program Manager Selected a

Design-Builder Selection

EIS ongoing Q4-2020 completion

Design Starts Q4-2020

Construction Starts Q3-2021

RPT Opens Q3-2024

Existing Terminal Demolished Q3-2025

Page 22: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

22

Development Agreement with City of Burbank

• 2016, 20 year duration

• 355,000 sq ft terminal (232,000 current)

• 14 gates (same as current)

• Public design charrettes workshop process

• 6,637 public parking spaces (same as current)

• Demolish existing terminal within 12 months of opening

Page 23: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

23

Page 24: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

24

Page 25: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

25

Preferred Location

NE Quadrant• Green field, no utilities, not

graded, narrow width• Elevation change 30+ ft

north to south• Greater distance from

Regional Intermodal Transportation Center

Alternative LocationSW Quadrant

Page 26: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

HOLLYWOOD BURBANK AIRPORT

REPLACEMENT PASSENGER TERMINAL CONCEPT VALIDATION

COPYRIGHT © BUROHAPPOLD ENGINEERING. ALL RIGHTS RESERVED

Page 27: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

The proposed Replacement Passenger Terminal

is feasible in the preferred location

HOLLYWOOD BURBANK AIRPORT

REPLACEMENT PASSENGER TERMINAL CONCEPT VALIDATION

Page 28: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

The proposed Replacement Passenger Terminal works in

the preferred location

✓ ADG III Aircraft Layout (Same capability at all gates)

✓ 14 Gates

✓ 355,000 SF Terminal

CO N C LU S I O N

Page 29: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

P E A K H O U R C A PAC I T Y

Page 30: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

M A S S I N G

Replacement Passenger Terminal

Parking

GSE &

Maint.

ARFF

ATCT

Page 31: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

P R O P O S E D L AYO U T : G R O U N D F LO O R

Total Floor Area = 247,601 SF

Page 32: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

P R O P O S E D L AYO U T : B A S E M E N T

Total Floor Area = 53,354 SF

Basement

Page 33: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

P R O P O S E D L AYO U T : S E CO N D F LO O R

Total Floor Area = 54,045 SF

Second Floor

Page 34: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

E L E VAT I O N LO O K I N G E A S T

Page 35: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

1. Terminal Depth

2. Site Grade

3. Airport Access

4. Employee Parking

5. Public Parking Structure

6. Air Traffic Control Tower

7. Aircraft Rescue and Fire Fighting Facility

O P P O RT U N I T I E S TO B E A D D R E S S E D I N D E S I G N P H A S E

Page 36: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

36

Public Design Charrettes Workshops

• Last workshop was held October 26, 2019

• Deliverable will be part of PDM and selection criteria for RFP

Page 37: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

37Design Charrette Workshop 1

Page 38: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

38Design Charrette Workshop 1

Page 39: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

39Design Charrette Workshop 1 - Vision Boards

Page 40: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

40Design Charrette Workshop 1 - Vision Boards

Page 41: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

41Design Charrette Workshop 1 - Sketches/Board Shots

Page 42: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

42Design Charrette Workshop 1 - Sketches/Board Shots

Page 43: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

43Design Charrette Workshop 2

Page 44: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

44Design Charrette Workshop 2

Page 45: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

45Design Charrette Workshop 2 - Posters

Page 46: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

46Design Charrette Workshop 2 - Posters

Page 47: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

47Design Charrette Workshop 3 & 4

Page 48: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

48Design Charrette Workshop 3 & 4 - Posters

Page 49: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

49

Financial Feasibility

The Authority is developing a Plan of Finance based on the availability of:• Airport Improvement Program funds

• PFC revenue backed bonds

• U.S. DOT Credit Programs

• Authority equity

• General Aviation Revenue Bonds

Page 50: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

50

Program components - not just a terminal

Design-Build Scope Elements• Replacement Passenger Terminal

• Roadways/utilities/parking structures

• Aircraft apron

• Air Cargo/GSE

Other Program Elements to be Delivered Under Separate Contracts• Demo Existing Terminal Building

• Aircraft Rescue Fire Fighting Facility/EOC

• Taxiways A & C extensions

Page 51: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

51

Delivery Method

Why Progressive Design Build• Facilitates coordination & cooperation between Airport, Airlines,

Designer and Builder

• Integration of Design and Build staff critical to accurate understanding of construction cost and schedule in real time as design progresses

• Single procurement / Single contract

• Establish Project Cost Expectations during D-B procurement and design to the defined target budget

• Allows Construction to start prior to finalizing design

Page 52: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

52

Page 53: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

53

Program Schedule

Page 54: Industry Day - Elevate Bur · 10/26/2019  · 51 Delivery Method Why Progressive Design Build •Facilitates coordination & cooperation between Airport, Airlines, Designer and Builder

54

Today’s attendees list, project updates, and a portal to submit questions are available on

elevatebur.com

If you do not wish to be included in the attendees list, please alert the staff at the check-in desk