    INDUSTRIAL INTERNSHIP PROJECT REPORT

    OCTOBER 2012APRIL 2013

    AT

    I.Z.A CONSTRUCTION COMPANY SDN BHD

    ODU PAUL DUKU ERIKOLE

    14115

    DEPARTMENT OF CIVIL ENGINEERING

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    2/79

    i

    INDUSTRIAL INTERNSHIP PROJECT REPORT

    01ST OCTOBER 201212TH APRIL 2013

    SOIL CEMENT STABILIZATION OF PAVEMENT

    SUBGRADE FOR A NEW 2.5KM ROAD IN ANAK KURAU

    SUBMITTED TO

    CENTER FOR STUDENT INTERNSHIP, MOBILITY

    AND ADJUNCT LECTURESHIP (CSIMAL)

    UNIVERSITI TEKNOLOGI PETRONAS

    BY

    ODU PAUL DUKU ERIKOLE - 14115

    DEPARTMENT OF CIVIL ENGINEERING

    APRIL 2013

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    3/79

    ii

    HOST COMPANYS VERIFICATION STATEMENT

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    4/79

    iii

    EXECUTIVE SUMMARY

    The construction of new roads often results in the necessity to cope up with problematic

    subgrade materials such as expansive soils, collapsible soils, erodible soils, very soft

    soils and wet areas. These problems associated with subgrade materials are common in

    many parts of the world, although they tend to be localized in certain areas of which

    Kampung Anak Kurau is not an exception.

    Most of the soil at the project site is unsuitable (consists of mud/clay) which undergo a

    huge amount of volume change due to changes in temperature and moisture. This

    shrinking and swelling of the soil can lead to cracking of overlying pavement layers.

    According to (Karin, Sven-Erik & Ronny, 2002), a conventional solution in this

    situation is soil substitution, which involves excavating the loose soil layers and

    replacing them with frictional/granular material of higher bearing capacity. This layer is

    then followed by sub-base and base courses which are normally constructed of

    aggregates. But fill materials can deteriorate due to intrusion of stone base, pumping of

    subgrade soil and infiltration of water from subgrade, leading to a substantial damage of

    pavement[5].

    Soil substitution is also not cost effective (aggregates are costly) and frequently also

    problematic, as the replaced material must be disposed of and new filling material

    hauled to the site. Furthermore, soil substitution takes longer time (several layers to be

    constructed) and it is not environmentally friendly method due to the greenhouse

    emissions during raw material mining, processing, and transportation of raw materials to

    the construction site.

    This project entitled as Soil Cement Stabilization of Pavement Subgrade for a new

    2.5km road in Anak Kurau therefore, aims at improving the strength of subgrade

    materials and reducing road construction cost in terms of material, time and

    maintenance.

    The improvement of the strength of the subgrade materials is through the use of

    geotextile to separate the soft subgrade materials from the granular fill materials prevent

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    5/79

    iv

    migration and mingling of the soft subgrade soil and granular fill material under the

    action of the construction equipment or subsequent traffic but yet allow free movement

    of water. This unsuitable subgrade material replacement is then followed by stabilizing

    the fill materials with cement.

    During the unsuitable soil replacement by using geotextile separator, the unsuitable

    material was excavation to a sufficient depth, a type A non-woven geotextiles was

    then placed as a separator with a minimum overlap of about 500mm (figure 2.3.4-3),

    followed by river sand filling in layers and then compaction.

    The untreated fill material was then subjected to in-situ CBR test, Field Density Test,

    sieve analysis, Atterberg limits tests and compaction test to determine its properties.

    Samples of the granular fill materials were also dosed with different Portland cement

    content (2.5%, 3.5% and 5%) at the optimum moisture content and subjected to

    unconfined compressive strength (UCS) test so as to determine the optimum cement

    content to be used for the stabilization. The UCS test result shows that the strength of the

    subgrade material increases with an increase in the cement content and based on this

    result, a cement content of 4% was used in the Mix Design for the soil cement

    stabilization.

    The area to be stabilized is then demarcated and 4% of cement by proportion is added to

    the subgrade soil and mixed into it until a uniform color is obtained, and the mixture is

    then thoroughly compacted.

    Comparison of the CBR values before and after soil cement stabilization shows a

    significant increase in the value of CBR after soil cement stabilization. The CBR of the

    subgrade before stabilizing with cement is between 19% and 42% while the CBR value

    increases to between 78 and 82 at the age of three days and as high as 103% at the age of

    seven days after soil cement stabilization. This CBR value is higher than the

    recommended CBR value (80%) for road base constructed of crusher run or aggregate

    material. For this reason, it is not advisable to have sub-base and base courses, surface

    course can be constructed directly on the stabilized subgrade because it (the subgrade) is

    strong enough to withstand the subsequent traffic loading from the vehicle that will be

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    6/79

    v

    using the road. Soil cement stabilization of the subgrade therefore reduces the design

    and construction thickness of flexible pavement.

    Based on the cost analysis, it can be concluded that soil cement stabilization is more cost

    effective than conventional method of constructing flexible pavement becauseconstruction cost when using soil cement stabilization of the subgrade material is RM

    245,000.00 (table 2.4.2-1) but the cost would have been RM 516,390.26 (table 2.4.2-2)

    if conventional method were used.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    7/79

    vi

    ACKNOWLEDGEMENTS

    I would like to express my sincere gratitude to all those people whose immeasurable

    contributions made it possible for me to complete my industrial internship training. I

    would like to thank especially the Center for Student Internship, Mobility and Adjunct

    Lectureship (CSIMAL) and the Department of Civil Engineering of Universiti

    Teknologi PETRONAS (UTP) for giving the students such a golden opportunity to do

    industrial internship training and for their well-organized Internship Guidelines which

    made work easier for us during our training period. I would also like to thank my UTP

    supervisors Dr. Tee Hee Min of UTP for his encouragement and advice during the first

    visit and Dr. Mohd Faris Khamidi during the second visit for his support and guidance

    about what I need to add to the Internship Report.

    I am also thankful to the management of I.Z.A Construction Company for offering me

    the opportunity to do my industrial training with the company and for every assistance

    that they rendered to me from October 2012 up to date. Special thanks also go to my

    host company supervisor, Mr. Mior for assigning me several tasks and always being

    available to guide me in executing the tasks. I appreciate the project manager Mr.

    Firdaus, site manager Mr. Ravi and the project engineer Mr. Zulhelmy so much for

    helping me at site supervision work, in understanding construction drawings and taking

    off. I am thanking Mr. Rama of Jabatan Kerja Raya Malaysia (JKR) for his advance and

    for always asking me to join him for any laboratory tests and for providing an

    explanation for both laboratory and in-situ test results.

    Last but not least, I am thankful to all the staff of I.Z.A Construction Company and my

    fellow interns in the company for their support especially for providing me with relevant

    information that helped me during my training.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    8/79

    vii

    TABLE OF CONTENTS

    HOST COMPANYS VERIFICATION STATEMENT........................................................... ii

    EXECUTIVE SUMMARY .............................................................................................. iii

    ACKNOWLEDGEMENTS ............................................................................................. vi

    TABLE OF CONTENTS ................................................................................................ vii

    LIST OF FIGURES ....................................................................................................... ix

    LIST OF TABLES .......................................................................................................... x

    1.0. INTRODUCTION .............................................................................................. 1

    1.1. BRIEF DESCRIPTION OF THE HOST COMPANY ......................................................... 1

    1.2. OBJECTIVES OF THE INDUSTRIAL INTERNSHIP ......................................................... 1

    1.3. SCOPE OF WORK, TASKS OR PROJECTS UNDERTAKEN DURING INTERNSHIP ............ 2

    2.0. INTERNSHIP PROJECT REPORT ........................................................................ 6

    2.1.0. PROJECT BACKGROUND ..................................................................................... 6

    2.1.1. BACKGROUND ..................................................................................................................... 6

    2.1.2. PROBLEM STATEMENT ........................................................................................................ 7

    2.1.3. SIGNIFICANCE OF THE PROJECT .......................................................................................... 8

    2.1.4. PROJECT OBJECTIVE ............................................................................................................ 9

    2.1.5. SCOPE OF WORK FOR THE PROJECT ................................................................................... 9

    2.2.0. LITERATURE REVIEW ............................................................................................. 10

    2.2.1. BRIEF DESCRIPTION OF SOIL CEMENT STABILIZATION...................................................... 10

    2.2.2. TYPES OF CEMENT USED TO STABILIZE SOIL ..................................................................... 10

    2.2.3. SOILS SUITABLE FOR CEMENT STABILIZATION .................................................................. 11

    2.2.4. DESIGN CEMENT CONTENT FOR CEMENT-STABILIZED SOILS ........................................... 11

    2.2.5. SOIL CEMENT STABILIZATION PROCESS ............................................................................ 13

    2.2.6. OTHER STABILIZING AGENTS ............................................................................................. 13

    2.2.7. BENEFITS OF SOIL STABILIZATION (CATERPILLAR, 2006) .................................................. 14

    2.2.8. APPLICATION OF SOIL STABILIZATION .............................................................................. 15

    2.3.0. METHODOLOGY ............................................................................................... 16

    2.3.1. MOBILIZATION OF MACHINERY ........................................................................................ 16

    2.3.2. SITE CLEARANCE AND DEMOLITION WORKS .................................................................... 18

    2.3.3. EARTHWORKS ................................................................................................................... 18

    2.3.4. UNSUITABLE SOIL REPLACEMENT WITH GEOTEXTILE SEPARATOR................................... 19

    2.3.5. DRAINAGE WORK .............................................................................................................. 21

    2.3.6. MATERIAL SAMPLING, TESTING AND MIX DESIGN ........................................................... 24

    2.3.7. GRADING TO PROFILE ....................................................................................................... 25

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    9/79

    viii

    2.3.8. SPREADING THE STABILIZING AGENT ............................................................................... 25

    2.3.9. PULVERIZING AND MIXING ............................................................................................... 25

    2.3.10. PRELIMINARY COMPACTION ............................................................................................. 26

    2.3.11. GRADING TO CAMBER ...................................................................................................... 26

    2.3.12. FINAL ROLLING .................................................................................................................. 26

    2.3.13. CURING ............................................................................................................................. 26

    2.3.14. QUALITY CONTROL ............................................................................................................ 27

    2.3.15. RECOMMENDATION ......................................................................................................... 27

    2.3.16. SITE CLEANING AND DEMOBILIZATION ............................................................................ 27

    2.4.0. RESULTS AND DISCUSSION ............................................................................... 28

    2.4.1. RESULTS ............................................................................................................................ 28

    2.4.1.1. Sieve Analysis ................................................................................................................ 28

    2.4.1.2. Dry Density/Moisture Content Relationship for site soil .............................................. 29

    2.4.1.3. Atterberg Limits ............................................................................................................ 31

    2.4.1.4. Unconfined Compressive Strength (UCS) Test Result................................................... 33

    2.4.1.5. CBR Values before Soil Cement Stabilization ............................................................... 35

    2.4.1.6. CBR Values after Soil Cement Stabilization .................................................................. 38

    2.4.2. DISCUSSION ....................................................................................................................... 40

    Cost Benefit Analysis. ..................................................................................................................... 43

    2.5.0. CONCLUSION AND RECOMMENDATION ........................................................... 45

    2.5.1. CONCLUSION ..................................................................................................................... 45

    2.5.2. RECOMMENDATION ......................................................................................................... 46

    3.0. SAFETY TRAINING AND VALUE OF THE PRACTICAL EXPERIENCE ...................... 47

    3.1. LESSON LEARNED AND EXPERIENCE GAINED ........................................................ 47

    3.2. LEADERSHIP, TEAM WORK AND INDIVIDUAL ACTIVITIES ....................................... 49

    3.3. BUSINESS VALUES, ETHICS AND MANAGEMENT SKILLS ......................................... 50

    3.4. PROBLEMS OR CHALLENGES FACED AND SOLUTIONS TO OVERCOME THEM .......... 51

    4.0. CONCLUSION ................................................................................................. 52

    REFERENCES .............................................................................................................. I

    APPENDICES ............................................................................................................. II

    APPENDIX 1 TRAINING SCHEDULE .................................................................................. II

    APPENDIX 2

    PROJECT GANTT CHART ............................................................................. IIIAPPENDIX 2- LABORATORY REPORT ................................................................................. IV

    APPENDIX 3 UNSUITABLE SOIL REPLACEMENT WITH GEOTEXTILE SEPARATOR ............... XI

    APPENDIX 4 CULVERT INSTALLATION ........................................................................... XII

    APPENDIX 5 SOIL CEMENT STABILIZATION APPLICATION PROCESS ............................... XIV

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    10/79

    ix

    LIST OF FIGURES

    FIGURE 2.1-1 PROJECT LOCATION PLAN ............................................................................................................... 7

    FIGURE 2.3.1-1 SPECIALIZED MACHINE .............................................................................................................. 16

    FIGURE 2.3.1-2 SUPPORTING MACHINES............................................................................................................ 17FIGURE 2.3.3-1 ROAD CROSS SECTION IN CUT AND FILL AREAS .............................................................................. 19

    FIGURE 2.3.4-1 REASONS FOR DETERIORATION OF FILL MATERIALS .......................................................................... 20

    FIGURE 2.3.4-2 IMPORTANCE OF GEOTEXTILE SEPARATOR. ..................................................................................... 20

    FIGURE 2.3.4-3 JOINING OF GEOTEXTILE SEPARATOR BY OVERLAP......................................................................... 21

    FIGURE 2.3.4-4 TYPICAL DETAILS FOR STANDARD FILL SECTION TREATMENT TYPE 1(SAND REPLACEMENT WITH GEOTEXTILE

    SEPARATOR ............................................................................................................................................ 21

    FIGURE 2.3.5-1 SUB-SOIL DRAIN CROSS SECTION (CH900CH1150) ................................................................. 22

    FIGURE 2.3.5-2 BEDDING TYPE B1,SOFT FOUNDATION ........................................................................................ 23

    FIGURE 2.4.1-1 PARTICLE SIZE DISTRIBUTION CURVE ............................................................................................ 28

    FIGURE 2.4.1.2-1 DRY DENSITY /MOISTURE CONTENT RELATIONSHIP SITE SOIL ........................................................ 29

    FIGURE 2.4.1.2-2 DRY DENSITY /MOISTURE CONTENT RELATIONSHIP RIVER SAND FILL.............................................. 30FIGURE 2.4.1.2-3 DRY DENSITY /MOISTURE CONTENT RELATIONSHIP FOR IMPORTED EARTH FILL................................. 31

    FIGURE 2.4.1.3-1 LIQUID LIMIT GRAPH ............................................................................................................. 32

    FIGURE 2.4.1.4-1 ULTIMATE STRENGTH DESIGN MIX FOR SOIL AND SAND MIX......................................................... 33

    FIGURE 2.4.1.4-2 ULTIMATE STRENGTH DESIGN MIX FOR SOIL .............................................................................. 34

    FIGURE 2.4.1.4-3 ULTIMATE STRENGTH DESIGN MIX FOR SAND............................................................................. 35

    FIGURE 2.4.2-1 THICKNESS OF FLEXIBLE PAVEMENT BY USING SOIL CEMENT STABILIZATION........................................... 42

    FIGURE 4-1 PIE CHART OF BENEFITS OF INTERNSHIP TRAINING ................................................................................. 53

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    11/79

    x

    LIST OF TABLES

    TABLE 2.2.4-1 CEMENT REQUIREMENTS (QUANTITIES) FOR VARIOUS SOILS (HICKS,2002) ........................................... 12

    TABLE 2.2.4-2 MINIMUM UNCONFINED COMPRESSIVE STRENGTH AT 7 DAYS FOR CEMENT AND 28 DAYS FOR LIME, LIME-

    CEMENT, AND LIME-CEMENT-FLY ASH STABILIZED SOILS (GUYER,2011). ............................................................ 12TABLE 2.2.4-3 DURABILITY REQUIREMENTS FOR STABILIZED SOIL (GUYER,2011) ....................................................... 13

    TABLE 2.4.1-1 SIEVE ANALYSIS RESULTS............................................................................................................. 28

    TABLE 2.4.1.2-1 DRY DENSITY/MOISTURE CONTENT RELATIONSHIP FOR SITE SOIL ..................................................... 29

    TABLE 2.4.1.2-2 DRY DENSITY/MOISTURE CONTENT RELATIONSHIP FOR RIVER SAND FILL........................................... 30

    TABLE 2.4.1.2-3 DRY DENSITY/MOISTURE CONTENT RELATIONSHIP FOR IMPORTED EARTH FILL.................................... 31

    TABLE 2.4.1.3-1 PLASTIC LIMIT TEST RESULTS..................................................................................................... 32

    TABLE 2.4.1.3-2 LIQUID LIMIT TEST RESULTS...................................................................................................... 32

    TABLE 2.4.1.4-1 DESIGN MIX (TRIAL MIX) FOR SOIL-SAND MIXTURE...................................................................... 33

    TABLE 2.4.1.4-2 DESIGN MIX (TRIAL MIX) FOR SOIL ............................................................................................ 34

    TABLE 2.4.1.4-3 DESIGN MIX (TRIAL MIX) FOR SAND .......................................................................................... 35

    TABLE 2.4.1.5-1 CBRVALUES BEFORE SOIL CEMENT STABILIZATION....................................................................... 36TABLE 2.4.1.5-2 CBRVALUES AFTER SOIL CEMENT STABILIZATION......................................................................... 38

    TABLE 2.4.2-1 SOIL CEMENT STABILIZATION OF SUBGRADE MATERIALS ..................................................................... 43

    TABLE 2.4.2-2CRUSHER RUN ROAD BASE MATERIAL .............................................................................................. 44

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    12/79

    1

    1.0. INTRODUCTION1.1. BRIEF DESCRIPTION OF THE HOST COMPANY

    I.Z.A Construction Co. Sdn. Bhd was formed on 15th September 1982 and was

    incorporated under the Company Act 1965 on the 21st September 1991. The Board of

    Directors are Dato' Baharuddin Bin Hj. Mahyuddin, a Civil Engineer and Mr. Farouk

    Bin Anwar a Chemical Engineer. Since its formation in 1982, the company due to the

    expertise and technical experiences of the directors has secured and completed contracts

    well exceeding Ringgit Malaysia 560 million. The company has progressed

    tremendously from a small time Class 'D' contractor to a fully-fledged Class 'A'

    Bumiputera contractor registered with Contractor Service Centre since 1994. Since then

    it has well established itself and received high recognition by the Ministry of Finance

    and the Prime Minister's Department with the status COMPETENT CONTRACTOR.

    The award of MS ISO 9001:2000 certification by SIRIM QAS International Sdn. Bhd. is

    a proven testament of the company systematic management being recognized

    internationally.

    1.2. OBJECTIVES OF THE INDUSTRIAL INTERNSHIP

    To apply theoretical knowledge in industrial application and implement HealthSafety and Environment (HSE) practices at workplace.

    To expose the students to ethical and professional work culture, industrialpractices and potential employers

    To develop students skills in work ethics, communication, leadership andmanagement

    To engage students in real research-based assignments, research-based activitiesand team-work activities

    Hands-on training.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    13/79

    2

    1.3. SCOPE OF WORK, TASKS OR PROJECTS UNDERTAKENDURING INTERNSHIP

    During my training period, I was tasked with the following tasks which can be divided

    into project management, supervision, material testing, health safety and environment,

    and reporting.

    1. Project managementa. Help the QS in tendering work especially in taking off and in pricing the

    tender document.

    b. Attend a two days course about Microsoft Project 2010 and then come upwith work programs for assigned task and thereafter do weekly project

    tracking

    c. Report project progress based on project tracking to the supervisor.2. Supervision

    a. Inspect daily site activitiesb. Ensure effective flow of traffic flow is not interrupted by using adequate

    temporary traffic signs where necessary.

    c. Determine the area for closed turfing and ensure that closed turfing is donefor slope protection in both cut and fill slopes.

    4. Material testinga. Check the results for slump test before any concreting is doneb. Ensure that concrete cubes are cast during concreting and follow the JKR

    technician to the concrete suppliers laboratory for cube test on the seventh

    and 28th day after concreting

    c. Carry out speedy test for imported earth to ensure that the moisture content isnot less than 10% and does not exceed 27%

    e. Help the technician recommended by JKR during Field Density Test (FDT)f. Coordinate with JKR to inspect California Bearing Ration (CBR) test and

    ensure that the CBR value is 5% for soil, 30% for sand and 80% after soil

    cement stabilization

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    14/79

    3

    5. Health Safety and Environment (HSE)a. Involved in a BOMBA inspection to ensure the safety of occupants of

    completed building projects for a period of one week

    b. Always wear safety boots and ensure that all the general workers wear safetyboots when carrying out any site activity

    c. Ensure that each and every worker at the construction site wears face muskespecially during spreading of the stabilizing agent which can be airborne

    when it is windy.

    d. Ensure that traffic barriers are in place especially when working at roadintersection to prevent accidents.

    e. Ensure that water samples are collected every month for environmental waterquality monitoring.

    6. Reportinga. Prepare daily site diary including the daily site activities, workforce at site,

    machinery and equipment used, materials delivered to the site, visitors at the

    site, and daily weather conditions.

    b. Prepare weekly progress report consisting of the site activities for the weekand overall progress, workforce present and those on leave for the week,

    materials delivered to the site, machinery and equipment at the site, visitors

    at the site and weather conditions for the whole week

    c. Take site photos every Friday and make progress photo reportd. Do weekly project tracking and tracking on the 4th, 20th and 30th of every

    month

    e. Help the project manager in preparing monthly report

    The projects that I undertook during my training consists ofunsuitable soil replacementby using non-woven geotextile as a separator, drainage work and soil cement

    stabilization. My responsibilities as stated below are all under the direct supervision of

    the site manager Mr. Ravi. I performed most of the tasks in his presence and whether he

    is around or absent, he double check my work, make changes where necessary and then

    ask me to include those changes in my work.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    15/79

    4

    During unsuitable soil replacement by using non-woven geotextile as a separator,

    my responsibility is to:

    1. Determine the volume of cut materials and granular fill materials based on theexisting ground level and finished road level by using Microsoft office excel.

    2. Measure the volume of fill materials from each truck upon arrival at the site andthen compute the total daily volume hauled to the site and report it to the site

    manager Mr. Ravi

    3. Ensure that unsuitable materials such as roots of trees are removed from the fillmaterials during off hauling and leveling by motor grader.

    4. Ensure that, the overlap of geotextiles is as shown in the drawing (figure 3.6)before the geotextile is covered with fill materials.

    My responsibility during drainage work is to:

    1. Check with the project engineer and site manager the culverts upon arrival at thesite to ensure that the dimensions of each and the total quantities confirm to the

    one in the order sheet before unloading.

    2. Check the culverts to ensure that the culverts have not been damaged duringdelivery and set aside any damaged culvert during delivery and unloading.

    3. Ensure that the unloaded culverts are stockpiled near to where they will beinstalled so as to avoid re-handling and unnecessary equipment movement.

    4. Ensure that the culverts are installed in the right location and beddings wereproperly graded to avoid the culverts from settling after being installed

    5. Ensure proper alignment and jointing especially for box culverts in order toreduce the migration of soil fines and water between sections of the box culverts

    and their surroundings.

    6. Determine the volume of materials to be used for bedding preparation and forbackfill of culverts as shown in.

    7. Ensure that backfill materials are free from debris, organic matter, wood, frozenmaterial or large stones.

    8. Determine the quantity of reinforcement bars required for culvert wingwallsfrom construction drawings and the volume of concrete to be ordered after the

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    16/79

    5

    steelwork and formwork for the wingwalls as well as the quantities of bricks,

    cement and sand for sumps.

    9. Inspect the steelwork and formwork for culvert wingwalls to ensure that thespacing for the steel bars confirms to that in the drawing, the number of steel

    bars is as I determined and the formwork is strong enough to withstand the

    weight of the fresh concrete.

    10. Ensure the safety of the works during unloading and installation of culverts andduring the construction as well as concreting of culvert wingwalls.

    Last but not least, my scope of work during soil cement stabilization is to:

    1. Check and verify that the proportion of the stabilizing agent is as indicated in themix design

    2. Check and verify that mixing or depth of soil cement stabilization is as shown inthe construction drawing

    3. Ensure that all the workers wear face mask during spreading of stabilizing agent4. Ensure that soil cubes are cast and FDT conducted for use in the laboratory to

    determine the optimum moisture content and maximum dry density

    5. Ensure that CBR test is conducted at the age of three days and seven days todetermine the mechanical strength of the subgrade after stabilization with

    cement.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    17/79

    6

    2.0. INTERNSHIP PROJECT REPORT2.1.0. PROJECT BACKGROUND

    2.1.1. BACKGROUND

    This project involves the construction of a new road from Kamunting to Anak Kurau,

    Taiping-Perak Darul Ridzuan (figure 2.1-1) and it consists of two phases: - phase 1

    involves the construction of a 2.5 Km road starting at state route A137 at Kampung

    Anak Kurau while phase 2 involves the construction of an 11Km road connecting the 2.5

    Km road to state road A7 at Sungai Relong. Phase 1 uses soil cement stabilizationmethod for the road embankment construction while phase 2 uses the conventional

    method of road construction which composes of layers of crushed rock for the road sub-

    base and road base courses. This report is entirely about phase 1 of the construction in

    which unsuitable soil replacement with geotextile separator precedes the soil cement

    stabilization process.

    In this project, non-woven geotextiles type A are placed between the soft subgrade and

    the granular fill materials so as to filter and hence prevent migration and mingling of the

    soft subgrade soil and granular fill material under the action of the construction

    equipment or subsequent traffic but yet allow free movement of water. After the

    unsuitable soil replacement, a cement content of 4% is added to the soil and mixed into

    it until a uniform color is obtained, and the mixture is then thoroughly compacted. This

    process called soil cement stabilization is used to increase the strength of the subgrade

    materials, thereby elimination the need for sub-base and base courses which is normally

    constructed of crusher run, thus resulting into a great cost saving.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    18/79

    7

    Funding for the project is by Kementerian Kemajuan Luar Bandar & Wilayah (KKLW)

    and all the project work is done according to the JKR standards & specifications. The

    total value of the contract at award to I.Z.A Construction Sdn. Bhd was RM

    7,228,925.40. I.Z.A Construction Sdn. Bhd received the contract document on 27th

    December 2011 and it started the project work on 09th January 2012 with total project

    duration of 53 weeks. Contractually, the project is to be completed on 07th January

    2013.

    Figure 2.1-1 Project Location Plan

    2.1.2. PROBLEM STATEMENT

    An efficient road network is a key factor in the development of a region or an area

    because it helps in the mobility of people and goods from one place to another. The

    construction of this new road by the Malaysia Government will help connect the

    residents of Kampung Anak Kurau to Kamunting, Taiping and other parts of the

    country. Site condition however poses a serious challenge to the construction work.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    19/79

    8

    Most of the soil at the project site is unsuitable (consists of mud/clay) which undergo a

    huge amount of volume change due to temperature and moisture. This shrinking and

    swelling of the soil can lead to cracking of overlying pavement layers. According to

    (Karin, Sven-Erik & Ronny, 2002), a conventional solution in this situation is soil

    substitution, which involves excavating the loose soil layers and replacing them with

    frictional material of higher bearing capacity normally well-graded aggregates so as to

    obtain a stable sub-grade, sub-base or base layers. Soil substitution is however not cost

    effective and frequently also problematic, as the replaced material must be disposed of

    and new filling material hauled to the site. Soil substitution also takes longer time and it

    is not environmentally friendly method due to the greenhouse emissions during raw

    material mining, processing, and transportation of raw materials to the construction site.

    2.1.3. SIGNIFICANCE OF THE PROJECT

    A well-constructed road must be durable, cost effective, easy to maintain and most of all

    it must be able to serve its intended function. This can only be achieved if the road is

    constructed on a solid, stable foundation. Mixing cement and or lime into the soil will

    help stabilize the soil thus making it denser, waterproof and more stable. Soil

    stabilization improves the soil strength and it will be used as a substitute to well graded

    aggregates in this project because it takes shorter time to stabilize the soil than using

    layers of well-graded aggregates to obtain stable sub-grade, sub-base or base layers. For

    this 2.5km road, the soil stabilization process has taken only two weeks. Soil cement

    stabilization improves the engineering properties of soil thus making the stabilized base

    strong enough to withstand vehicle loading like crusher run base and it is cost effective,

    easy to maintain and more environmentally friendly than the conventional method of

    road construction. Cost effectiveness here is realized by the fact that soil cement

    stabilization eliminates the need to import large volume of aggregates and the associated

    production and hauling cost whereas it is more environmentally friendly because it

    reduces greenhouse emissions during raw material mining, processing, and

    transportation to the site in the conventional method.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    20/79

    9

    2.1.4. PROJECT OBJECTIVE

    The objective of this project is to improve the strength of subgrade materials and to

    reduce cost of road construction in terms of material, time and maintenance.

    2.1.5. SCOPE OF WORK FOR THE PROJECT

    The scope of work for this project can be divided into work prior to soil cement

    stabilization and soil cement stabilization work.

    The work to be done prior to soil cement stabilization include:1. Mobilization of machinery2. Site clearing and demolition of existing structures in the entire area of the

    road reserves

    3. Earthwork and unsuitable material replacement with geotextile separator4. Drainage work5. Sampling, testing and mix design

    Soil cement stabilization work on the other hand consists of:1. Spreading the stabilizing agent2. Weighing to verify proportion of stabilizing agent3. Pulverization and mixing4. Digging to verify the depth of mixing or depth of stabilization5. Preliminary compaction6.

    Grading to chamber

    7. Final rolling8. Curing9. Cube Casting and Testing, Field Density Test, CBR test

    10. Site cleaning and demobilization

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    21/79

    10

    2.2.0. LITERATURE REVIEW

    2.2.1. BRIEF DESCRIPTION OF SOIL CEMENT STABILIZATIONSoil stabilization and can be defined as the treatment of natural soil to improve its

    engineering properties (Garber & Hoel, 2002). Soil cement stabilization is a process to

    improve the strength and durability of soil by mixing an appropriate amount of cement

    with the soil. This can be achieved by pulverizing the natural soil or borrow material,

    adding the appropriate amount of cement to the pulverized soil and mixing it properly

    and then thoroughly compacting the mixture. When cement comes in contact with soil

    water, it forms calcium silicate hydrate and calcium hydroxide (Ca(OH)2). The calcium

    silicate hydrate formed has a strong cementing effect hence binding the soil together and

    increasing its strength. The Ca(OH)2 formed results in pozzolanic reactions which

    provides a further increment of strength in the longer term (Karin, Sven-Erik & Ronny,

    2002).

    Both subgrade and road base can be stabilized with cement. The thickness of a cement-

    stabilized road base depends upon the traffic loads, traffic volumes and the stability of

    the subgrade. The thickness of sub-base or subgrade cement stabilization on the other

    hand, depends up-on the nature of the soils and the conditions of the job. Theeffectiveness of soil cement stabilization depends on the type of soil being stabilized, the

    quantity of cement added, the degree of mixing, the time of curing, the dry density of the

    compacted mixture,

    2.2.2. TYPES OF CEMENT USED TO STABILIZE SOIL

    Normal (Type I) and Air Entraining (Type IA) Cements are most commonly used typesof cement for soil stabilization. Sulfate Resistant Cement (Type II) and High Early

    Strength Cement (Type III) have also been successfully used for cement stabilization of

    soils. Each type of cement used for soil stabilization depends on the type of soil and its

    contents (Guyer, 2011).

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    22/79

    11

    2.2.3. SOILS SUITABLE FOR CEMENT STABILIZATIONMost types of soil can be stabilized with cement ranging from gravelly and sandy soils

    to fine-grained silts and clays. It is generally more effective and economical to use it

    with granular soils due to the ease of pulverization and mixing and the smaller quantities

    of cement required (Hicks, 2002).

    Fine-grained soils of low to medium plasticity can also be stabilized, but not as

    effectively as coarse-grained soils. It is difficult to mix cement with the soil of PI more

    than 30 so in such cases, lime needs to be added first to reduce the PI and improve

    workability before adding the cement. For soils that contain sulfates, it is advisable to

    use sulfate resistant cement for stabilization of the soils. If the pH of the soil is lower

    than 12.1, it is not advisable to use cement to stabilize the soil (Hicks, 2002).

    2.2.4. DESIGN CEMENT CONTENT FOR CEMENT-STABILIZED SOILSDetermining the design cement content for cement-stabilized soils involves the

    classificationof the untreated soil (table 2.2.4-1) and the determination of the gradation

    of the soil to be stabilized and using it to select estimated cement content for moisture-

    density tests to determine the maximum dry density and optimum water content of the

    soil-cement mixture. Triplicate samples of the soil-cement mixture are then prepared for

    unconfined compression and durability tests at the cement content selected. The results

    of the unconfined compressive strength and durability tests are compared with the

    requirements shown in (table 2.2.4-2 and table 2.2.4-3).

    The lowest cement content which meets the required unconfined compressive strength

    requirement and demonstrates the required durability is the design cement content.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    23/79

    12

    Table 2.2.4-1 Cement requirements (quantities) for various soils (Hicks, 2002)

    Table 2.2.4-2 Minimum unconfined compressive strength at 7 days for cement and 28

    days for lime, lime-cement, and lime-cement-fly ash stabilized soils (Guyer, 2011).

    Usual Range in Estimated Cement Cement Contents

    AASHTO Cement Requirement Content and That for Wet-Dry and

    Soil Unified Soil

    Percent

    by

    Percent

    by

    Used in Moisture-

    Density Test Freeze-Thaw Tests

    Classification Classification* Volume Weight Percent by Weight Percent by Weight

    A-1-a GW, GP, GM, 57 35 5 357

    SW, SP, SM

    A-1-b

    GM, GP, SM,

    SP 79 58 6 468

    A-2GM, GC, SM,

    SC 710 59 7 579

    A-3 SP 812 711 9 7911

    A-4 CL, ML 812 712 10 81012

    A-5 ML, MH, CH 812 813 10 81012

    A-6 CL, CH 1014 915 12 101214

    A-7 OH, MH, CH 1014 1016 13 111315

    Stabilized soil layer Minimum Unconfined Compressive strength, MN/m

    Flexible Pavement Rigid Pavement

    Base course 5.171 3.447

    Sub-base course, select

    material or subgrade

    1.723 1.379

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    24/79

    13

    Table 2.2.4-3 Durability requirements for stabilized soil (Guyer, 2011)

    2.2.5. SOIL CEMENT STABILIZATION PROCESSThe basic soil cement stabilization processes include:

    Assessment and testing Site Preparation Introduction of cement Mixing Compaction and shaping or trimming Curing

    2.2.6. OTHER STABILIZING AGENTSOther soil stabilizing agents that have been used successfully include lime,

    bitumen/asphalt, fly ash, granulated blast furnace slag, filler materials.

    Lime is used to stabilize medium, moderately fine, and fine-grained clay soils. When

    mixed in soil, lime reduces the soil moisture content thus reducing the plasticity of the

    soil, making it more rigid. Lime also increases strength and workability of the soil and

    reduces the ability of the soil to swell (Caterpillar, 2006).

    Bitumen is used in soil stabilization because it makes the soil stronger and resistant to

    water and frost. Soil bitumen stabilization benefits from fewer-weather related delays

    Type of soil Stabilized Maximum Allowable Weight Loss After 12 Wet-Dry or

    Freeze-Thaw Cycles percent of Initial Specimen WeightGranular, PI < 10 11

    Granular, PI > 210 8

    Silt 8

    Clays 6

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    25/79

    14

    during construction and makes compaction easier and more consistent (Caterpillar,

    2006).

    Fly ash is normally mixed with lime and water to stabilize granular materials with few

    fines to produce a hard, cement-like mass. It acts as a pozzolan and as a filler to reduce

    air voids.

    Filler, such as fine sand is added in soil stabilization to increase the number of solid

    particles and to fill any voids formed during stabilization. The filler itself does not react

    but increases the strength of the soil by acting as a stiffener. Filler material is normally

    used in the stabilization of peat and mud, as these soils often require large quantities of

    stabilizers thus, replacing part of the stabilizer with inexpensive filler can save costs.

    Therefore, there are many stabilizers used in soil stabilization, the effectiveness of each

    stabilizer depends on the quantity of the stabilizer, the soil type, storage temperature,

    degree of compaction, weather condition and availability of the stabilizer.

    2.2.7. BENEFITS OF SOIL STABILIZATION (CATERPILLAR, 2006)

    There are several advantages of soil stabilization:

    Improved soil strength, improved soil workability and improved durability Cost reduction, dust reduction in work environment and reduction of soil volume

    change due to temperature and moisture

    Conservation of energy and aggregates materials Waterproofing the soil and improving runoff Functioning as a working platform for the project especially in wet weather Control shrinkage and swell Improve load carrying and stress distribution characteristics Improve substandard materials By-products from industry can be used as raw materials

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    26/79

    15

    2.2.8. APPLICATION OF SOIL STABILIZATION

    Soil stabilization is used in Yards, parking places, sports grounds, road, andstreet, railway, and cable/pipe channel and storage construction sites

    It is used as foundations for buildings pools, landfill areas and bridges It is also use in the protection of adjacent structures, slopes of the rivers, lakes,

    roads and earth pressure

    Noise embankments and Erosion control and for frost and ground waterprotection layers

    Stabilization of very soft soils for tunnel boring

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    27/79

    16

    2.3.0. METHODOLOGY

    2.3.1. MOBILIZATION OF MACHINERYTwo categories of machinery are used for the execution of the soil cement stabilization

    works, these include:

    a) Specialized Machine (figure 2.3.1-1)

    The specialized machines used in this project are the Stabilizer Spreader and Reclaimer

    or Mixer Machine. The reclaimer is a 4-wheel base CATERPILAR machine Model SS-

    250 which is equipped with a 300 horse power engine that has a self-propelled hydraulic

    rotor drum with mixing chamber that could mix and cut up to depth of 650mm. it is used

    for the mixing of soil stabilizer agent with the existing earth/material.

    Stabilizer Spreader Reclaimer

    Figure 2.3.1-1 Specialized Machine

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    28/79

    17

    b) Supporting Machines

    Supporting machines are provided by I.Z.A Construction Company Sdn Bhd except

    those supporting machines that I.Z.A Construction does not have, such machines are

    rented from local supplier when the soil cement stabilization work started. The

    supporting machinery used for this project includes: Motor Grader, Vibratory Rollers

    and Water Trucks as shown in (figure 2.3.1-2).

    Excavator

    Excavator has been used in this project to excavate unsuitable materials, excavate for

    culvert installation, excavate interceptor and toe drains, and to cut and trim slopes

    Motor Grader

    The Motor Grader is used for site preparation to remove unwanted vegetation and all the

    undergrowth during the site preparation. It is also used to trim and level area in the road

    reserve before the compaction of the stabilized materials.

    Vibratory Rollers

    Vibratory Rollers are used for the compaction of the mixed stabilized materials.

    Water Trucks

    The Water Trucks are used to supply water to the Reclaimer machine during the mixing

    process if the site condition requires and to supply water for curing.

    Excavator Motor Grader Vibratory Roller Water Truck

    Figure 2.3.1-2 Supporting Machines

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    29/79

    18

    2.3.2. SITE CLEARANCE AND DEMOLITION WORKSThe Right of Way (R.O.W) was surveyed and Right of Way Limits were indicated by

    wooden pegs. Photographs of structures, landscaping trees and shrubs, fences, telephone,

    electrical poles and anything that are payable were then taken before site clearing and

    demolition of existing structures commenced. Site clearing of trees, vegetation,

    undergrowth, bushes and demolition of existing structures in the entire area of the road

    reserve are then carried out by hydraulic excavators from CH O towards increasing

    Chainage. Demolished structures consists of two storey brickwork building, one storey

    masonry building, two storey masonry building, one storey timber building, two storey

    timber building, fences and gates, pipe culverts, box culverts, and inlet/outlet structures

    for culvert No.1 which is to be extended.

    2.3.3. EARTHWORKSBefore the earthwork commenced, surveying and setting out of center line was carried

    out using a theodolite and a tripod for Original Ground Level (OGL) and pegged at 10

    meters interval lengthwise. Survey pegs were also placed at the toe limits located at 5

    meter away from the center line.

    Where the OGL was higher than the finished road level, the road centerline and slope

    batters were set out and topsoil stripped, the area is then cut by hydraulic excavators.

    The cut materials were then hauled using Dump trucks to the filling area. Slopes

    trimming and slope or erosion protection (closed turf) was then immediately carried out

    for the slopes formed.

    Whereas in areas where the OGL was lower than the finished road level, topsoil was

    stripped off up to the filling limits and suitable cut materials hauled by Dump trucks

    from the cut area are placed and spread out using back pusher. The filling with suitable

    materials was carried out in layers and each layer compaction by vibratory roller until

    relative compaction of at least 90% of maximum dry density is obtained.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    30/79

    19

    Figure 2.3.3-1 Road Cross Section in Cut and Fill Areas

    2.3.4. UNSUITABLE SOIL REPLACEMENT WITH GEOTEXTILESEPARATOR

    Problem with soft subgrade

    The stability and the durability of any structure depend on how stable and durable its

    foundation is. For this Anak Kurau road project however, the subgrade material is very

    weak. It therefore needs to be replaced with granular fill materials which will then be

    compacted adequately to obtain a more stable subgrade. But fill materials can

    deteriorate, leading to a substantial damage of pavement. Such fill materials deteriorate

    due to intrusion of stone base, pumping of subgrade soil and infiltration of water from

    subgrade as illustrated (figure 2.3.4-1) [5].

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    31/79

    20

    Figure 2.3.4-1 Reasons for deterioration of fill materials

    Problem Solution

    This problem can be solved by using geotextiles. In road constructions, Geotextiles have

    been widely used for filtration and in order to prevent migration and mingling of

    materials, yet allowing free movement of water. In this project, a geotextile is used as a

    separator by placing it between the soft subgrade and the granular fill material. It acts as

    a filter to allow water but not fine material to pass through it, preventing any mixing of

    the soft subgrade soil and granular material under the action of the construction

    equipment or subsequent traffic [5].

    Figure 2.3.4-2 Importance of geotextile separator.

    Unsuitable soil replacement by using non-woven geotextile as a separator consists of

    excavation of unsuitable material to a sufficient depth, laying a type A non -woven

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    32/79

    21

    geotextiles as a separator with a minimum overlap of about 500mm (figure 2.3.4-3),

    followed by placement of river sand and then compaction. Filling with suitable fill

    materials continues to the specified embankment height as shown in (figure 2.3.4-4) and

    the unsuitable soil excavated is then leveled at the sides of roadway.

    Figure 2.3.4-3 Joining of Geotextile separator by Overlap

    Figure 2.3.4-4 Typical details for standard fill section treatment type 1 (sand

    replacement with geotextile separator

    2.3.5. DRAINAGE WORK

    It is important to ensure that there is an adequate drainage in any road construction in

    order to avoid road damage due to both surface water and underground water.

    Geotextiles

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    33/79

    22

    The drainage works for this project involved the construction of surface and subsoil

    drains, installation of new precast box and pipe culvert, extension of existing precast box

    culvert at CH 0, construction of sumps and wing walls both as inlet and outlet structures,

    not forgetting the excavation and backfilling for such works listed above.

    The surface drains for this project involved the excavation of interceptor drains and toe

    drains and the installation of precast concrete U-drains.

    Sub-Soil Drainage

    For sub-soil drains, concrete porous pipes were installed with the details as shown in

    (figure 2.3.5-1). The trench to receive the concrete porous pipe is first excavated

    followed by placing of geotextile with 300 mm overlap. The porous concrete pipe is

    then placed on a less thick aggregate layer and its sides and top also fill with aggregates.

    This aggregate layer is again covered with geotextile before filling granular materials

    until the finished road level is obtained.

    Figure 2.3.5-1 Sub-Soil Drain Cross Section (CH 900CH 1150)

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    34/79

    23

    Culvert works

    Trench Method is used to install both precast reinforced concrete pipe and box culverts

    based on the following procedures:

    After the Surveyor provides alignment of the Pipe Culvert, Invert Level, R.O.W.and all necessary point, Temporary diversion of water flow is constructed

    The trench to receive the culvert is then excavated, followed by Laying andcompaction of bedding materials.

    Pipe or box culvert is then laid and checked for alignment before insertingsubsequent pipe or box culverts. Both sides of culvert are temporary secured using

    timber wedges to prevent sideways movement.

    Upon completion of installation, both sides of the culvert are backfilledsimultaneously with suitable granular backfill in layer of 150mm thick and

    compact to 90% Maximum Dry Density.

    Wingwalls and headwalls are then constructed at upstream and downstream of theculvert with concrete G 20/20 and structural steel fabric B 705 placed as bedding

    The bedding type and installation locations for all the culvert except the giant culvert is

    as shown in (figure 2.3.5-2).

    Figure 2.3.5-2 Bedding Type B1, Soft Foundation

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    35/79

    24

    2.3.6. MATERIAL SAMPLING, TESTING AND MIX DESIGN

    Tests are conducted, both before and during the progress of soil cement stabilization to

    ensure compliance with the requirements of the Standard Specification for Road Works

    (JKR/SPJ/1988), Guidelines for inspection &Testing of Road Works. The tests are

    conducted by MMTS-IETS JOINT VENTURE Building & Construction Materials

    Testing Laboratory and by Tasek Soil & Materials Lab Sdn. Bhs (TSML) which is

    specialized in soil, concrete and asphaltic concrete testing.

    The Laboratory testing carried out on the Untreated Soil samples consisting of Imported

    soil fill, river sand fill, and imported soil-river sand mixture includes: Sieve Analysis

    (Gradation), Atterberg Limits, Soil Classification, Maximum Dry Density (MDD),Optimum Moisture Content (OMC), Unconfined Compressive Strength (UCS) and

    Californian Bearing Ration (CBR).

    It is important that those tests are carried out both before and during soil cement

    stabilization. Gradation or particle size distribution is particularly important in

    determining the stabilizer content; more fines require higher cement content or even

    addition of lime before adding the cement. Uniform gradation results in uniform mixing,

    uniform compaction and hence uniform strength development. The test method used insieve analysis is MS 30 Part 4: 1995. Atterberg Limits (Plastic Limit, PL and Liquid

    Limit, LL) are used to determine active clay content which helps in deciding if there is

    need to increase the cement content. The PL and LL test were conducted by following

    the test procedure of BS: 1377: Part 2: 1990, Clause 4.5. Moisture-density relationship

    is used to determine the degree of compaction of the material, high densities obtained is

    an indication that the shear strength and elastic modules improved and the ingress of

    water is reduced. Finally, CBR and UCS tests are used to determine the strength of the

    soil attained.

    Determination of the Mix Design is by trial and error. To determine the mix design

    (required cement content) for the soil cement stabilization, different dosage of cement

    (2.5%, 3.5% and 5% cement) is admixed with the untreated material thoroughly until a

    uniform color is obtained, the optimum moisture content is then added. Specimens were

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    36/79

    25

    then prepared for UCS test which was conducted at the age of 3 days and 7 days, the

    results obtained are shown in (table 2.4.1.4-1, table 2.4.1.4-2 & table 2.4.1-4) and for

    soil, sand and soil mixed with sand respectively.

    2.3.7. GRADING TO PROFILE

    Before the commencement of the soil cement stabilization work, the exposed platform is

    checked for reduced level to ensure that the reduced level of the working platform is

    within 12mm of the design level for the base of next layer. Where the reduced level of

    the working platform is not within 12mm, motor Grader was used to level and grade

    the existing material to the required new profile.

    2.3.8. SPREADING THE STABILIZING AGENT

    After the surface was leveled and graded with motor grader, the determined stabilization

    area was marked and the required quantity of cement was spread over the areas to be

    stabilized. Spreading of the stabilizing agent was done using a purpose built additive

    spreader to the design percentage at a spreading rate of +/-5 % absolute value.

    2.3.9. PULVERIZING AND MIXING

    Pulverizing and dry (primary) mixing by use of a purpose built Reclaimer- Stabilizer

    CMI RS500 to the design depth starts after spreading of the stabilizing agent on the

    prepared platform has reached a length of +/-60 meters and a minimum width of 3.0

    meters. Where necessary, water is added during mixing through the mixing chamber of

    the Reclaimer- Stabilizer CMI RS500 to ensure that the moisture content of the mix

    materials does not fall below 2% of Optimum Moisture Content (OMC). The secondary

    mixing (called wet run) is to ensure the chemical reaction between the stabilizing agent

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    37/79

    26

    and existing material and to ensure the highest density of the mixture after compaction

    since maximum Dry Density (MDD) is achieved at OMC.

    2.3.10.PRELIMINARY COMPACTIONA Vibratory Roller was used for preliminary compaction to enable the Motor Grader to

    work on the loose stabilize material. Vibratory roller with 10 metric tons static mass

    ideal was used with rolling pattern of two (2) static passes and six (6) vibration passes.

    The critical variable in achieving densification with minimum effort is moisture content

    of the material being compacted. Compaction by vibratory roller is continued until a

    maximum Dry Density (MDD) of 95% or more is achieved as confirmed by laboratorytest results. Final Rolling is then done using pneumatic tire roller after grading to

    chamber to ensure a better compaction and surface.

    2.3.11.GRADING TO CAMBER

    A Motor Grader was used to grade and form the desired camber; undulations were also

    eliminated by the motor grader. The grading and shaping of the stabilized treated layer is

    done to ensure that the finished levels are within +/- 6mm of the required reduced levels.

    During the process of grading and shaping, the vibratory roller is used for the

    compaction.

    2.3.12.FINAL ROLLINGFinal rolling is done after grading or trimming and shaping. Pneumatic tire roller is used

    for the final rolling so as to ensure a better compaction and surface.

    2.3.13.CURING

    Curing was done for seven days after soil cement stabilization. Curing is to increase the

    rate of hydration of the cement used as stabilizing agent and to prevent rapid setting. The

    main purpose of curing is so as to obtain the intended/required/design strength after

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    38/79

    27

    cement stabilization and to maintain a uniform temperature of the stabilized subgrade to

    prevent thermal shrinkage cracking.

    2.3.14.QUALITY CONTROL

    Testing was carried out accordingly during the soil cement stabilization work. The tests

    that have been carried out during the stabilization process include:

    Field Density Test to determine the degree of compaction of the stabilized layer, Moisture Content test is done both before and after mixing to ensure the

    relativity of moisture to the mix. This is because the best mixing when using

    cement is at the Optimum Moisture Content and so is the Maximum Dry

    Density,

    Cube test, UCS test to give an indication of the tensile strength of the materialafter stabilization and

    CBR test to evaluate the mechanical strength of the subgrade materials afterstabilization.

    2.3.15.RECOMMENDATION

    1. It is not advisable to proceed with the stabilization under the following climaticconditions:

    2. The ambient temperature is below 50C or above 380C3. It is raining or likely to rain4. The wind is sufficiently strong to cause the additive to become airborne5. During conditions that may cause danger to people, property or the environment

    2.3.16.SITE CLEANING AND DEMOBILIZATIONUpon completion of the soil cement stabilization work, all waste materials which

    resulted from the work is disposed to a dump site approved by JKR, construction

    machinery demobilized from the site before and the project handed over for the

    pavement works.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    39/79

    28

    0

    20

    40

    60

    80

    100

    120

    0 5 10

    % Passing

    Sieve Size

    Particle Size Distribution Curve

    2.4.0. RESULTS AND DISCUSSION

    2.4.1. RESULTS

    2.4.1.1. Sieve Analysis

    Test Conditions; Temperature: 28.60C Relative Humidity: 53%

    Table 2.4.1-1 Sieve Analysis Results

    Figure 2.4.1-1 Particle Size Distribution

    Curve

    Sieve Size Weight

    Retain

    ed

    %

    Retained

    %

    Passing

    50.0 mm

    37.5 mm

    28.0 mm

    25.0 mm

    20.0 mm

    14.0 mm

    12.5 mm 0.0 0.0 100

    10.0 mm 44.6 3.7 96.3

    6.30 mm 47.8 4.0 92.3

    5.00 mm 42.2 3.5 88.8

    3.35 mm 51.3 4.3 84.5

    2.36 mm 57.6 4.8 79.7

    1.18 mm 43.3 3.6 76.1

    0.600 10.1 0.8 75.3

    0.425 1.9 0.2 75.1

    0.300 3.3 0.3 74.8

    0.150 3.6 0.3 74.5

    0.075 4.0 0.3 74.2

    Pan 0.0Weight Before Wash: 1200.5 grams

    Weight After Wash: 309.7 grams

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    40/79

    29

    2.4.1.2. Dry Density/Moisture Content Relationship for site soil

    Test Condition: Temperature = 29.40C, Relative Humidity = 57% & Volume 998.4 cm

    3

    Table 2.4.1.2-1 Dry Density/Moisture Content Relationship for site soil

    Figure 2.4.1.2-1 Dry Density / Moisture Content Relationship site soil

    Test No. 1 2 3 4 5

    Mass of Soil + Mould (g) 7533 7632 7701 7745 7688

    Mass of Mould (g) 5395 5395 5395 5395 5395

    Mass of Compacted Soil (g) 2138 2237 2306 2350 2293

    Bulk Density of Soil (Mg/m3) 2.141 2.241 2.31 2.354 2.297

    Container No. B17 B5 B13 B3 B10

    Mass of Container + Wet Soil (g) 139.4 125.3 140.6 148.8 164.2

    Mass of Container + Dry Soil (g) 123.8 110.2 122.8 126.8 137.9

    Mass of Container (g) 36.3 35.5 38.3 38.1 37.6

    Mass of Dry Soil (g) 87.5 74.7 84.5 88.7 100.3

    Mass of Moisture (g) 15.6 15.1 17.8 22 26.3

    Moisture Content (%) 17.8 20.2 21.1 24.8 26.2

    Measurement uncertainty for Moisture content (%) 0.33 0.39 0.34 0.33 0.29

    Dry Density (Mg/m3) 1.817 1.864 1.908 1.886 1.82

    Measurement uncertainty for Dry Density (Mg/m3) 0.005 0.005 0.005 0.004 0.004

    1.8

    1.82

    1.84

    1.86

    1.88

    1.9

    1.92

    1.94

    0 5 10 15 20 25 30

    Dry Density

    (Mg/m3)

    Moisture Content (%)

    Dry Density/Moisture Content Relationship for Site Soil

    MDD = 1.839 Mg/m3

    s= 1.316 Mg/m3 OMC = 22.7 %

    OMC = Optimum

    Moisture Content

    MDD = Maximum

    Dry Density

    s = Bulk density

    of calibrating sand

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    41/79

    30

    Table 2.4.1.2-2 Dry Density/Moisture Content Relationship for River Sand fill

    Test Condition: Temperature = 29.90C, Relative Humidity = 62% and Volume 949 cm

    3

    Figure 2.4.1.2-2 Dry Density / Moisture Content Relationship River Sand fill

    Test No. 1 2 3 4 5

    Mass of Soil + Mould (g) 7245 7455 7698 7602 7450

    Mass of Mould (g) 5478 5478 5478 5478 5478

    Mass of Compacted Soil (g) 1767 1977 2220 2124 1972

    Bulk Density of Soil (Mg/m ) 1.862 2.083 2.339 2.238 2.078

    Container No. C2 C8 C13 C18 C19

    Mass of Container + Wet Soil (g) 209.0 223.0 198.0 221.0 205.0

    Mass of Container + Dry Soil (g) 204.0 215.9 190.4 210.0 193.6

    Mass of Container (g) 101.2 101.2 101.3 101.4 101.3

    Mass of Dry Soil (g) 102.8 114.7 89.1 108.6 92.3

    Mass of Moisture (g) 5.00 7.10 7.60 11.00 11.40

    Moisture Content (%) 4.9 6.2 8.5 10.1 12.4

    Measurement uncertainty for Moisture content (%) 0.28 0.25 0.32 0.26 0.31

    Dry Density (Mg/m3) 1.776 1.962 2.155 2.032 1.850

    Measurement uncertainty for Dry Density (Mg/m3) 0.005 0.005 0.006 0.005 0.005

    1.7

    1.8

    1.9

    2

    2.1

    2.2

    0 2 4 6 8 10 12 14

    Dry Density

    (Mg/m3)

    Moisture Content (%)

    Dry Density/Moisture Content Relationship for River Sand

    MDD = 2.156 Mg/m3

    s=1.186 Mg/m3

    OMC = 8.4 %

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    42/79

    31

    Table 2.4.1.2-3 Dry Density/Moisture Content Relationship for imported earth fill

    Test Condition: Temperature = 29.90C, Relative Humidity = 63% and Volume 949 cm

    3

    Figure 2.4.1.2-3 Dry Density / Moisture Content Relationship for imported earth fill

    2.4.1.3. Atterberg Limits

    Test No. 1 2 3 4 5

    Mass of Soil + Mould (g) 7188 7310 7468 7422 7314

    Mass of Mould (g) 5395 5395 5395 5395 5395

    Mass of Compacted Soil (g) 1793 1915 2073 2027 1919

    Bulk Density of Soil (Mg/m3) 1.889 2.018 2.184 2.136 2.022

    Container No. 17 24 28 32 34

    Mass of Container + Wet Soil (g) 85.2 76.3 92.4 78.1 79.4

    Mass of Container + Dry Soil (g) 80.0 71.5 84.2 71.4 71.8

    Mass of Container (g) 41.2 42.2 41.1 41.0 41.3

    Mass of Dry Soil (g) 38.8 29.3 43.1 30.4 30.5

    Mass of Moisture (g) 5.2 4.8 8.2 6.7 7.6

    Moisture Content (%) 13.4 16.4 19.0 22.0 24.9

    Measurement uncertainty for Moisture content (%) 0.74 0.98 0.67 0.95 0.96

    Dry Density (Mg/m3) 1.666 1.734 1.836 1.750 1.619

    Measurement uncertainty for Dry Density (Mg/m3) 0.010 0.013 0.009 0.011 0.010

    1.6

    1.65

    1.7

    1.75

    1.8

    1.85

    0 5 10 15 20 25 30

    Dry Density

    (Mg/m3)

    Moisture Content (%)

    Dry Density/Moisture Content Relationship for Dark Brown

    Sandy Clayed Silt

    MDD = 1.839 Mg/m3

    s=2.80 Mg/m3

    OMC = 19.5 %

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    43/79

    32

    0

    10

    20

    30

    40

    50

    60

    70

    0 10 20 30 40 50

    Moisture

    Content (%)

    Number of Blows

    Liquid Limit Graph

    Test Condition: Temperature = 29.40C, Relative Humidity = 57 & Test Date:16/10/2012

    Table 2.4.1.3-1 Plastic Limit Test Results

    Plastic Limit Test No. 1 2

    Container No. A2 A4

    Mass of Container + Wet Soil (g) 26.4 25.1Mass of Container + Dry Soil (g) 24.1 23.1

    Mass of Container (g) 15.0 15.4

    Mass of Moisture, M1 (g) 2.3 2.0

    Mass of Dry Soil, M2 (g) 9.1 7.7

    Moisture Content (M1 / M2) X 100 (%) 25.3 26.0

    Measurement uncertainty for Moisture content (%) 3.2 308.0

    Average Moisture Content (%) 25.6

    Table 2.4.1.3-2 Liquid Limit Test Results

    Liquid Limit Test No. 1 2 3 4 5Number of Blows 11.00 17.00 30.00 37.00 47.00

    Container No. A1 A3 A7 A5 A9

    Mass of Container + Wet Soil (g) 29.20 30.50 27.30 29.80 28.40

    Mass of Container + Dry Soil (g) 23.70 25.00 22.90 24.80 24.10

    Mass of Container (g) 14.60 15.50 14.60 14.90 14.70

    Mass of Moisture, M1 (g) 5.50 5.50 4.40 5.00 4.30

    Mass of Dry Soil, M2 (g) 9.10 9.50 8.30 9.90 9.40

    Moisture Content (M1 / M2) X 100 (%) 60.40 57.90 53.00 50.50 45.70

    Measurement uncertainty for Moisturecontent (%)

    3.63 3.44 3.86 3.20 3.31

    Figure 2.4.1.3-1 Liquid Limit Graph

    Proportion Retained on

    425 um Sieve:

    Liquid Limit (LL): 5

    Plastic Limit (PL): 26

    Plastic Index (PI): 29

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    44/79

    33

    2.4.1.4. Unconfined Compressive Strength (UCS) Test Result

    Table 2.4.1.4-1 Design Mix (Trial Mix) for Soil-Sand Mixture

    Water-

    Cement

    Ratio

    Weight

    (Kg)

    Nominal Size

    L x W x H

    (mm)

    Condition

    of

    Spacemen

    Max.

    Load

    (KN)

    Type of

    Failure

    Density

    (Kg/m3)

    Ultimate Strength

    (MN/m2) at

    3 days 7 days

    5%

    Cement

    6.910 150x150x150 Dry 128.6 Normal 2047 0.6 5.7

    3.5%

    Cement

    7.125 150x150x150 Dry 102.4 Normal 2111 0.8 4.6

    2.5%

    Cement

    7.140 150x150x150 Dry 62.3 Normal 2116 1.3 2.8

    Figure 2.4.1.4-1 Ultimate Strength Design Mix for Soil and Sand Mix

    0

    1

    2

    3

    4

    5

    6

    0 2 4 6 8

    Ultimate Strength

    (MN/m2)

    Age (days)

    2.5% Cement

    3.5% Cement

    5% Cement

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    45/79

    34

    Table 2.4.1.4-2 Design Mix (Trial Mix) for Soil

    Water-

    Cement

    Ratio

    Weight

    (Kg)

    Nominal Size

    L x W x H

    (mm)

    Condition

    of

    Spacemen

    Max.

    Load

    (KN)

    Type

    of

    Failure

    Density

    (Kg/m3)

    Ultimate Strength

    (MN/m2) at

    3 days 7 days

    5%

    Cement

    5.710 150x150x150 Dry 80.4 Normal 1692 0.3 3.6

    3.5%

    Cement

    5.705 150x150x150 Dry 48.6 Normal 1690 0.6 2.2

    2.5%

    Cement

    5.260 150x150x150 Dry 20.5 Normal 1559 1.2 0.9

    Figure 2.4.1.4-2 Ultimate Strength Design Mix for Soil

    0

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    0 2 4 6 8

    Ultimate Strength

    (MN/m2)

    Age (days)

    2.5% Cement

    3.5% Cement

    5% Cement

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    46/79

    35

    Table 2.4.1.4-3 Design Mix (Trial Mix) for Sand

    Water-

    Cement

    Ratio

    Weight

    (Kg)

    Nominal Size

    L x W x H

    (mm)

    Condition

    of

    Spacemen

    Max.

    Load

    (KN)

    Type

    of

    Failure

    Density

    (Kg/m3)

    Ultimate Strength

    (MN/m2) at

    3days 7days

    5%

    Cement

    6.610 150x150x150 Dry 75.2 Normal 1959 0.4 3.3

    3.5%

    Cement

    6.490 150x150x150 Dry 47.5 Normal 1923 0.8 2.1

    2.5%

    Cement

    6.310 150x150x150 Dry 40.2 Normal 1870 1.1 1.8

    Figure 2.4.1.4-3 Ultimate Strength Design Mix for Sand

    2.4.1.5. CBR Values before Soil Cement StabilizationJack/Load rig no. 0.0318 KN/div

    Mass of Surcharge: 4.5 kg Test date: 5/3/2013

    0

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    4

    0 2 4 6 8

    Ultimate Strength

    (MN/m2)

    Age (days)

    2.5% Cement

    3.5% Cement

    5% Cement

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    47/79

    36

    Table 2.4.1.5-1 CBR Values before Soil Cement Stabilization

    CH 10, Before Soil Cement Stabilization

    Jack/Load rig no. 0.0318 KN/div

    Mass of Surcharge: 4.5 kg Test date: 5/3/2013

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -

    0.5 35 1.11

    1 80 2.54

    1.5 120 3.82

    2 150 4.77

    2.5 175 5.57 13.24 42.03

    CH 260, Before Soil Cement Stabilization

    Jack/Load rig no. 0.0318 KN/div

    Mass of Surcharge: 4.5 kg Test date: 5/3/2013

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -

    0.5 30 0.95

    1 60 1.91

    1.5 100 3.18

    2 130 4.13

    2.5 160 5.09 13.24 38.43

    CH 510, Before Soil Cement Stabilization

    Jack/Load rig no. 0.0318 KN/div

    Mass of Surcharge: 4.5 kg Test date: 5/3/2013

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -

    0.5 40 1.27

    1 56 1.78

    1.5 70 2.23

    2 87 2.77

    2.5 100 3.18 13.24 24.02

    CH 760, Before Soil Cement Stabilization

    Jack/Load rig no. 0.0318 KN/div

    Mass of Surcharge: 4.5 kg Test date: 5/3/2013

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -

    0.5 30 0.95

    1 55 1.75

    1.5 80 2.54

    2 110 3.50

    2.5 130 4.13 13.24 31.22

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    48/79

    37

    CH 1010, Before Soil Cement Stabilization

    Jack/Load rig no. 0.0318 KN/div

    Mass of Surcharge: 4.5 kg Test date: 5/3/2013

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -0.5 10 0.32

    1 20 0.64

    1.5 31 0.99

    2 43 1.37

    2.5 52 1.65 13.24 12.49

    CH 1260, Before Soil Cement Stabilization (same for CH1510)

    Jack/Load rig no. 0.0318 KN/div

    Mass of Surcharge: 4.5 kg Test date: 5/3/2013

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -0.5 20 0.64

    1 30 0.95

    1.5 40 1.27

    2 50 1.59

    2.5 55 1.75 13.24 13.21

    CH 1760, Before Soil Cement Stabilization

    Jack/Load rig no. 0.0318 KN/div

    Mass of Surcharge: 4.5 kg Test date: 5/3/2013

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -0.5 30 0.95

    1 60 1.91

    1.5 75 2.39

    2 85 2.70

    2.5 95 3.02 13.24 22.82

    CH 2010, Before Soil Cement Stabilization

    Jack/Load rig no. 0.0318 KN/div

    Mass of Surcharge: 4.5 kg Test date: 5/3/2013

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -0.5 30 0.95

    1 52 1.65

    1.5 65 2.07

    2 83 2.64

    2.5 90 2.86 13.24 21.62

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    49/79

    38

    2.4.1.6. CBR Values after Soil Cement Stabilization

    Jack/Load rig no. 0.02577 KN/div

    Mass of Surcharge: 4.5 kg Test date: 21/3/2013

    Table 2.4.1.5-2 CBR Values after Soil Cement Stabilization

    CBR at CH 115, three days after soil cement stabilization

    Jack/Load rig no. 0.02577 KN/div

    Mass of Surcharge: 4.5 kg

    Penetration of Force on Plunger Standard

    Plunger (mm) Load Guage KN Force (KN) CBR Value

    0 0 -

    0.5 165 4.25

    1 274 7.06

    1.5 340 8.76

    2 420 10.82

    2.5 430 11.08 13.2 83.95

    3 475 12.24

    3.5 490 12.63

    4 501 12.91

    4.5 510 13.14

    5 515 13.27 20 66.36Ave. 75.15

    CBR at CH 125 three days after soil stabilization

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -

    0.5 81 2.09

    1 160 4.12

    1.5 250 6.44

    2 330 8.502.5 410 10.57 13.20 80.04

    3 460 11.85

    3.5 495 12.76

    4 520 13.40

    4.5 530 13.66

    5 555 14.30 20.00 71.51

    Average 75.78

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    50/79

    39

    CH 150, Age: 3days after Soil Cement Stabilization

    Jack/Load rig no. 0.02577 KN/div

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -

    0.5 139 3.581 220 5.67

    1.5 290 7.47

    2 361 9.30

    2.5 429 11.06 13.2 83.75

    3 475 12.24

    3.5 520 13.40

    4 594 15.31

    4.5 615 15.85

    5 625 16.11 20 80.53

    Average 82.14

    CH 110, Age: 7days after Soil Cement Stabilization

    Jack/Load rig no. 0.02577 KN/div

    Penetration of Force on Plunger Standard CBR Value

    Plunger (mm) Load Guage KN Force (KN) (%)

    0 0 -

    0.5 185 4.77

    1 283 7.29

    1.5 420 10.82

    2 517 13.32

    2.5 580 14.95 13.2 113.23

    3 623 16.05

    3.5 654 16.85

    4 680 17.52

    4.5 710 18.30

    5 725 18.68 20 93.42

    Average 103.32

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    51/79

    40

    2.4.2. DISCUSSION

    Sieve analysis is used to determine the gradation of the soil which is a very important

    element used in the determination of the proportion of the stabilizing agent. A well

    graded soil makes an excellent soil cement and requires the least amount of cement forits stabilization as compared to a poorly graded soil. The sieve analysis result shows that

    the soil at the site is well graded as indicated by the particle distribution curve (figure

    2.4.1-1).

    As shown in (figures 2.4.1.2-1, 2.4.1.2-2 and 2.4.1.2-3), the optimum moisture content is

    22.7%, 8.4% and 19.5% for site soil, river sand and imported earth respectively.

    Maximum dry density for each soil type is obtained at the respective optimum moisture

    content. For this reason, mixing of the stabilizing agent into the soil at the time of

    stabilization will be done at those moisture contents. Water will be added during mixing

    if the moisture content is found to be lower that the optimum moisture content and thesoil will be dried by application of pressurized air if it is too wet. During the process of

    soil cement stabilization, traces of water in the hand are indications that the optimum

    moisture content is exceeded.

    Since the PI obtained is 29% which is greater than 10% and less than 30%, cement can

    be used to stabilize the soil at this project site. If PI is found to be more than 30%, it is

    not advisable to used cement alone to stabilize the soil because it is difficult to mix

    cement with the soil of PI more than 30% except when lime is first added to reduce the

    PI and improve workability before adding the cement (Hicks, 2002).

    As shown in (table 2.2.4-2), the minimum Unconfined Compressive Strength (UCS) for

    cement stabilized soil at the age of 7 days is 5.171 MN/m2 and 1.723 MN/m2 for base

    course and sub-base course or subgrade respectively. Table 2.2.4-2 therefore serves as a

    reference for the Mix Design of cement content to be used for the subgrade stabilization.

    To determine the Mix Design, Samples of soil, sand and soil-sand mixture were

    thoroughly mixed with 2.5%, 3.5% and 5% cement content until a uniform mixture of

    soil-cement, sand-cement and soil-sand plus cement at Optimum Moisture Content

    (OMC) is obtained. The OMC for site soil, river sand fill material and imported earth fill

    material are 22.7%, 8.4% and 19.5% respectively.

    Cubes were then cast and Cube and UCS Tests were conducted at the age of 3 days and

    7 days to determine the density and the UCS and the results obtained for UCS test are

    shown in (table 2.4.1.4-1, table 2.4.1.4-2 & table 2.4.1-4) for soil, sand and soil mixed

    with sans respectively.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    52/79

    41

    Table 2.4.1.4-1, table 2.4.1.4-2 and table 2.4.1-4 show that the UCS for 3.5% cement

    content at the age of 7 days are 2.1 MN/m2 for soil, 2.2 MN/m2 for sand and 4.6

    MN/m2 for soil-sand mix. All these values of UCS are higher than the minimum UCS

    (1.723 MN/m2) for cement stabilized subgrade at the age of 7 days shown in (table

    2.2.4-2). This proves that a cement content of 3.5% is sufficient enough to stabilize the

    subgrade for this project but a cement content of 4% has been used to ensure very stable

    subgrade is obtained.

    The result of CBR test shows a significant increase in the CBR values of the subgrade

    after soil cement stabilization. The CBR value obtained before cement stabilization is

    between 12.49% and 42% (table 2.4.1.5-1). The different CBR values obtained before

    stabilization is due to the different types of subgrade materials and different degree of

    compaction. For the different soil types, JKR specification recommend a CBR value of

    5%, 30% and 80% for soil, sand and aggregates respectively. The effect of the

    degree of compaction is indicated by the fact that the CBR value obtained is highest at

    CH10 which is just at the beginning of the new road and the lowest CBR is attained at

    CH2260 which is close to the end of the road. The highest CBR value obtained at CH10

    is due to adequate compaction by the construction trucks used to transport construction

    materials to increasing chainage along the road.

    Just three days after soil cement stabilization, the average CBR value increased to

    between 78% and 82% and at the age of seven days, the average CBR of the cement

    stabilized subgrade is 103% as shown in (table 2.4.1.5-2). This CBR value is higher the

    80% CBR recommended for aggregate road base course and since CBR value measures

    the mechanical strength of the subgrade, this high CBR obtained shows how strong the

    subgrade is after been stabilized with cement. It is this improved strength of the

    subgrade that results in the reduction of the total thickness of the pavement. The

    reduction in thickness is as shown in (figure 2.4.2-1) which compares the cross sections

    of flexible pavement constructed by conventional method to the one constructed with

    cement stabilization of the subgrade materials

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    53/79

    42

    Figure 2.4.2-1 Thickness of flexible pavement by using soil cement stabilization

    Since the subgrade is strong enough to withstand vehicle loading, sub-base and base

    courses will be eliminated and the binder course is going to be spread directly on the

    subgrade after an application of prime coat to facilitate its bonding to the subgrade. The

    surface course will then be overlaid on the binder course after application of tact coat

    also to facilitate bonding of the two layers. This pavement work is scheduled to start on

    the 20th

    April 2013.

    Eliminating the base and sub-base courses conserves aggregate material and the

    environment by eliminating the greenhouse gas emission associated with aggregatemining, procession and transportation to the site. This also eliminates traffic congestion

    and noise pollution which would have resulted from construction trucks used to haul the

    crushed stones to the site.

  • 8/22/2019 Industrial Internship Project Report-Odu Paul-14115

    54/79

    43

    Cost Benefit Analysis.

    Table 2.4.2-1 Soil Cement Stabilization of subgrade materials

    Task Description Length

    (m)

    Width

    (m)

    Area

    (m2)

    Rate

    (RM/m2)

    Amount

    (RM)

    Spread stabilizing agent,

    pulverize and mix with

    subgrade material, compact

    and grade to chamber

    2500.00 7.00 17,500 14.00 245,000.00

    The sub-contractor, Specialized Pavement Malaysia (SPM) Sdn. Bhd. has accepted to do

    the soil cement stabilization work with rate and amount shown in table 2.4.2-1 which is

    the same as that provided in the Bill of Quantity. SPM has its own manpower and all the

    necessary machineries and equipment to carry out the cement stabilization of the

    subgrade materials. The cement stabilization of the subgrade materials will be followed

    by an application of the prime coat and then construction of binder and surface courses.

    If conventional method of constructing flexible pavement is used, the subgrade

    materials will be compacted to 95% or more of the maximum dry density (MDD)

    without any additive based on JKR specification. As shown in (figure 2.4.2-1a), this

    compacted subgrade material is normally followed by sub-base, base, binder and surface

    courses. The sub-base and base courses are constructed of crusher run while the binder

    and surface courses used the same materials and machineries whether for conventional

    method or for soil cement stabilization method. The sub-base course c