india wtc 08
TRANSCRIPT
-
7/25/2019 India Wtc 08
1/13
PART II
TUNNEL CONSTRUCTION IN INDIA CURRENT STATUS AND FUTURE TASK
-
7/25/2019 India Wtc 08
2/13
Modern tunnel construction in India started in Nineteenthcentury for extension of rail network;
First major tunnel for major Power Project MandiHydroelectric Project, Punjab early in the present century;
Barring few tunnels in the soft rock formation of HimalayanFoothills, most of the tunnels in hard rock strata in PeninsularIndia;
Dimensions of the tunnels limited to single broad gaugerailway track, in most of the cases;
Construction of tunnels received a big boost after
Independence when large programmes for exploitation ofwater resources were taken up.
-
7/25/2019 India Wtc 08
3/13
Large number of tunnels constructed for following majormultipurpose and hydroelectric projects in the Himalayan region; Bhakra Beas Projects in Punjab; Beas Sutlej Link-Baira-Siul,Giri and Sanjay Projects in H.P. Lakhwar and Maneri Bhali Projects in UP
Jaldhaka Project in West West Bengal Chukha Hydel Project in Bhutan Loktak and Umium Projects in North Eastern Region.
Koyna, Nagarjunasagar, Sirisailam, Kalinadi, Malaprabha,Balimela, Sabirigiri, Idduki, Lower Periyar, PerambikulamAliyar and Kadamparai Projects in the Southern States ofPeninsular India
Largest tunnels built Sizewise 14 m diameter Bhakra Dam Length wise about 27 Km - Nathpa Jhakri.
-
7/25/2019 India Wtc 08
4/13
Besides tunnels for hydroelectric projects, a few
tunnel projects were executed for: Roads;
Banihal Tunnel(J&K) Water supply schemes;
Bombay Water Supply;
Urban tunnel Projects;
Calcutta Metro Railway;
Delhi Metro Railway (under construction).
-
7/25/2019 India Wtc 08
5/13
Recent Tunneling Projects
Head race Tunnel 6m dia, 31 KM LongParbati Stage II(*)
Diversion & Head Race Tunnels - 11.0m/8.5m dia,
- 8 nos. 10.7 km total Length
- 2 Underground Power Houses
Tehri Dam Project
Uttar Pradesh
Headrace Tunnel - 9.15 m dia, 27 km LongNaptha Jhakri Project(H.P.)
Headrace Tunnel - 9.5m dia, 6.4 km long
Tailrace Tunnel - 9.5 m dia, 2.4 km Long(Underground Power House )
Chamera H.E. Project(*)
Himachal Pradesh
Headrace Tunnel - 8.0m dia, 10.4 km Long
Tailrace Tunnel - 8.0m dia, 2.0 km Long
Uri H.E. Project(*)
Jammu & Kashmir
Headrace Tunnel - 8.3m dia, 10.6 km Long
(Underground Power House)
Dul Hasti Project(*)Jammu & Kashmir
-
7/25/2019 India Wtc 08
6/13
Current Status OfTunneling Technology In India
Although tunnel construction in India has gained lot of
momentum, our tunneling methods and techniques are
rather outdated. Conventional drill and blast methods have been used for
most of the tunnel jobs.
The drilling equipment used for tunnel excavation has beeninvariably jack hammers and pusher legs except few caseswhere equipment like drifters with auto-feed and hydro-
booms have been deployed. Conventional tip wagons/muck cars, overhead loaders androcker shovels are used as Mucking equipment.
Progress rates generally achieved with above equipment is
extremely low
-
7/25/2019 India Wtc 08
7/13
Tunnel Excavation Rates Achieved onSome Indian Projects
* Tunnel driven with use of Tunnel Boring Machine417 m/month*2.4 m/hourFull FaceMalabar Tunnel
120 m/month104 m/month-Koyna Head Race Tunnel
48 m/month30.0 m/month (Afterremoval of bottlenecks)
HeadingTehri Tunnel
23 m/month23 m/month(Supported Reach)
45 m/month(Unsupported reach)
Tunnel 1: 18.0 m/monthTunnel 2 : 21.0 m/month
Full FaceLakhwar Diversion Tunnels(Yamuna)
81 m/monthFull FaceUchari-Chibbro Tunnel(Yamuna)
3.46 m/dayFull FaceBeas Tunnels
120 m/monthFull FacePandoh Baggi Tunnel
Max. Rate PerFace
Average rate per faceMethod ofExcavation
Project
-
7/25/2019 India Wtc 08
8/13
Bottle Necks in Tunneling
Construction Very little use of modern equipment in tunnel construction. Small
capacity loaders, tip wagons/tippers for transport of excavated
muck from tunnel are generally used. High prohibitive cost ofimported equipment is main reason for not using such equipment
for tunnel jobs.
The practice of continuous ribbing, as tunnel support system inweaker rocks is adopted at very heavy costs. Methods like NATM
are used on few projects only in our country;
Tunneling by drill and blast methods, particularly in soft rocks
results in over-breaks of the order of 10 - 15 % leading to time &cost overruns;
Above Bottle Necks in Tunnel Construction Technology, need to
be addressed by use of latest state-of-art technology such as
TBM to accelerate development since tunneling work is generally
on critical path for completion of project.
-
7/25/2019 India Wtc 08
9/13
USE OF NEW TUNNELING
TECHNIQUES Induction of modern tunneling technology avoids time and
cost overruns by minimizing construction problems;
Tunnel Boring Machine (TBM) used by French Contractorin Dul - Hasti Project in Himalayan Strata.
TBM used for Bombay Water Supply tunnel of 3.5 mdiameter earlier in 1984;
Modern tunneling equipments were deployed by Konkan
Railway Corporation for the construction of 760 kms longKonkan railway which has about 78 kms tunnels, mostly inhard rock.
-
7/25/2019 India Wtc 08
10/13
-29 KM (3.5 7.5 m dia)3Manipur
8 KM (3 4.75 m dia)43 KM (2.8 4.5 m dia)11Meghalaya
-72 KM (3.5 9.5 m dia)3Mizoram
-18 KM (3 3.5 m dia)2Kerela
11 KM (5 9 m dia)31 KM (6.5 8.3 m dia)5Karnataka
1.5 KM (10 14 m dia)81 KM (3 12 m dia)6J & K
3.7 KM (2.6 9.45 m dia138 KM (2.6 9.45 m dia)15HimachalPradesh
16 KM (3.7 10.5 m dia185 KM (2.4 10.5m dia)40ArunachalPradesh
TRTHRTNo. OfSchemes
State
Future Scenario for Tunneling
-
7/25/2019 India Wtc 08
11/13
10 KM (2.5 12 m dia.)174 KM (2.5 8.35 mdia.)
33Uttaranchal
4 KM (3.3 6 m dia)63 KM (3.3 6 m dia)10Sikkim
-17 KM (6.7 8.5 m dia)2Orissa
-4 KM (5 m dia.)1Nagaland
TRTHRTNo. ofSchemes
State
Total HRT Length 855 KM; 2.4 12 m diaTotal TRT Length 54 KM; 2.5 12 m dia
Future Scenario for Tunneling
Road tunnel of 9.0 KM across Rohtang Pass in H.P. is underconstruction for completion by 2012 at an estimated cost of 1710
Crores
-
7/25/2019 India Wtc 08
12/13
DPR Completed6.7Bangalore Metro
DPR Completed Planned in 3 phases:Phase-1 include 12 Km tunnelling
32Mumbai Metro
DPR Completed9.3Kolkatta Metro E/W Line
Completed (TBM + Cut & Cover)
Planned by 2009
Subsequent Phase
12.5
10.0
6.0
Delhi Metro
Phase-I
Phase-II
Phase-III
RemarksLength ofUndergroundPortion (Km)
Project
Adoption of faster & cost-effective latest techniques for tunnel driving undercomplex geological environment and development of appropriate methodologyfor tunnel construction below heavily inhabited urban areas would be requiredin the coming years.
Future Scenario for
Tunneling Metro Railway
-
7/25/2019 India Wtc 08
13/13
Conclusion Latest State-of-art Tunneling Technology is to be
adopted on priority to expedite development of :-
Power Sector involving about 900 KM of tunnelsvarying from 2.4 12 m dia.
Construction of Metro Railways to avoid traffic
congestion. Railway Tunnels
Highway Tunnels
In the deliberations in the congress, we areparticularly looking forward to presentations fromtunnel engineers, who are working on these recenttunnel projects about their experience about the use
of high technology, the resulting problems and thesolutions adopted for their mitigation and about theactual performance on ground.