india wtc 08

Upload: afzal-tai

Post on 01-Mar-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 India Wtc 08

    1/13

    PART II

    TUNNEL CONSTRUCTION IN INDIA CURRENT STATUS AND FUTURE TASK

  • 7/25/2019 India Wtc 08

    2/13

    Modern tunnel construction in India started in Nineteenthcentury for extension of rail network;

    First major tunnel for major Power Project MandiHydroelectric Project, Punjab early in the present century;

    Barring few tunnels in the soft rock formation of HimalayanFoothills, most of the tunnels in hard rock strata in PeninsularIndia;

    Dimensions of the tunnels limited to single broad gaugerailway track, in most of the cases;

    Construction of tunnels received a big boost after

    Independence when large programmes for exploitation ofwater resources were taken up.

  • 7/25/2019 India Wtc 08

    3/13

    Large number of tunnels constructed for following majormultipurpose and hydroelectric projects in the Himalayan region; Bhakra Beas Projects in Punjab; Beas Sutlej Link-Baira-Siul,Giri and Sanjay Projects in H.P. Lakhwar and Maneri Bhali Projects in UP

    Jaldhaka Project in West West Bengal Chukha Hydel Project in Bhutan Loktak and Umium Projects in North Eastern Region.

    Koyna, Nagarjunasagar, Sirisailam, Kalinadi, Malaprabha,Balimela, Sabirigiri, Idduki, Lower Periyar, PerambikulamAliyar and Kadamparai Projects in the Southern States ofPeninsular India

    Largest tunnels built Sizewise 14 m diameter Bhakra Dam Length wise about 27 Km - Nathpa Jhakri.

  • 7/25/2019 India Wtc 08

    4/13

    Besides tunnels for hydroelectric projects, a few

    tunnel projects were executed for: Roads;

    Banihal Tunnel(J&K) Water supply schemes;

    Bombay Water Supply;

    Urban tunnel Projects;

    Calcutta Metro Railway;

    Delhi Metro Railway (under construction).

  • 7/25/2019 India Wtc 08

    5/13

    Recent Tunneling Projects

    Head race Tunnel 6m dia, 31 KM LongParbati Stage II(*)

    Diversion & Head Race Tunnels - 11.0m/8.5m dia,

    - 8 nos. 10.7 km total Length

    - 2 Underground Power Houses

    Tehri Dam Project

    Uttar Pradesh

    Headrace Tunnel - 9.15 m dia, 27 km LongNaptha Jhakri Project(H.P.)

    Headrace Tunnel - 9.5m dia, 6.4 km long

    Tailrace Tunnel - 9.5 m dia, 2.4 km Long(Underground Power House )

    Chamera H.E. Project(*)

    Himachal Pradesh

    Headrace Tunnel - 8.0m dia, 10.4 km Long

    Tailrace Tunnel - 8.0m dia, 2.0 km Long

    Uri H.E. Project(*)

    Jammu & Kashmir

    Headrace Tunnel - 8.3m dia, 10.6 km Long

    (Underground Power House)

    Dul Hasti Project(*)Jammu & Kashmir

  • 7/25/2019 India Wtc 08

    6/13

    Current Status OfTunneling Technology In India

    Although tunnel construction in India has gained lot of

    momentum, our tunneling methods and techniques are

    rather outdated. Conventional drill and blast methods have been used for

    most of the tunnel jobs.

    The drilling equipment used for tunnel excavation has beeninvariably jack hammers and pusher legs except few caseswhere equipment like drifters with auto-feed and hydro-

    booms have been deployed. Conventional tip wagons/muck cars, overhead loaders androcker shovels are used as Mucking equipment.

    Progress rates generally achieved with above equipment is

    extremely low

  • 7/25/2019 India Wtc 08

    7/13

    Tunnel Excavation Rates Achieved onSome Indian Projects

    * Tunnel driven with use of Tunnel Boring Machine417 m/month*2.4 m/hourFull FaceMalabar Tunnel

    120 m/month104 m/month-Koyna Head Race Tunnel

    48 m/month30.0 m/month (Afterremoval of bottlenecks)

    HeadingTehri Tunnel

    23 m/month23 m/month(Supported Reach)

    45 m/month(Unsupported reach)

    Tunnel 1: 18.0 m/monthTunnel 2 : 21.0 m/month

    Full FaceLakhwar Diversion Tunnels(Yamuna)

    81 m/monthFull FaceUchari-Chibbro Tunnel(Yamuna)

    3.46 m/dayFull FaceBeas Tunnels

    120 m/monthFull FacePandoh Baggi Tunnel

    Max. Rate PerFace

    Average rate per faceMethod ofExcavation

    Project

  • 7/25/2019 India Wtc 08

    8/13

    Bottle Necks in Tunneling

    Construction Very little use of modern equipment in tunnel construction. Small

    capacity loaders, tip wagons/tippers for transport of excavated

    muck from tunnel are generally used. High prohibitive cost ofimported equipment is main reason for not using such equipment

    for tunnel jobs.

    The practice of continuous ribbing, as tunnel support system inweaker rocks is adopted at very heavy costs. Methods like NATM

    are used on few projects only in our country;

    Tunneling by drill and blast methods, particularly in soft rocks

    results in over-breaks of the order of 10 - 15 % leading to time &cost overruns;

    Above Bottle Necks in Tunnel Construction Technology, need to

    be addressed by use of latest state-of-art technology such as

    TBM to accelerate development since tunneling work is generally

    on critical path for completion of project.

  • 7/25/2019 India Wtc 08

    9/13

    USE OF NEW TUNNELING

    TECHNIQUES Induction of modern tunneling technology avoids time and

    cost overruns by minimizing construction problems;

    Tunnel Boring Machine (TBM) used by French Contractorin Dul - Hasti Project in Himalayan Strata.

    TBM used for Bombay Water Supply tunnel of 3.5 mdiameter earlier in 1984;

    Modern tunneling equipments were deployed by Konkan

    Railway Corporation for the construction of 760 kms longKonkan railway which has about 78 kms tunnels, mostly inhard rock.

  • 7/25/2019 India Wtc 08

    10/13

    -29 KM (3.5 7.5 m dia)3Manipur

    8 KM (3 4.75 m dia)43 KM (2.8 4.5 m dia)11Meghalaya

    -72 KM (3.5 9.5 m dia)3Mizoram

    -18 KM (3 3.5 m dia)2Kerela

    11 KM (5 9 m dia)31 KM (6.5 8.3 m dia)5Karnataka

    1.5 KM (10 14 m dia)81 KM (3 12 m dia)6J & K

    3.7 KM (2.6 9.45 m dia138 KM (2.6 9.45 m dia)15HimachalPradesh

    16 KM (3.7 10.5 m dia185 KM (2.4 10.5m dia)40ArunachalPradesh

    TRTHRTNo. OfSchemes

    State

    Future Scenario for Tunneling

  • 7/25/2019 India Wtc 08

    11/13

    10 KM (2.5 12 m dia.)174 KM (2.5 8.35 mdia.)

    33Uttaranchal

    4 KM (3.3 6 m dia)63 KM (3.3 6 m dia)10Sikkim

    -17 KM (6.7 8.5 m dia)2Orissa

    -4 KM (5 m dia.)1Nagaland

    TRTHRTNo. ofSchemes

    State

    Total HRT Length 855 KM; 2.4 12 m diaTotal TRT Length 54 KM; 2.5 12 m dia

    Future Scenario for Tunneling

    Road tunnel of 9.0 KM across Rohtang Pass in H.P. is underconstruction for completion by 2012 at an estimated cost of 1710

    Crores

  • 7/25/2019 India Wtc 08

    12/13

    DPR Completed6.7Bangalore Metro

    DPR Completed Planned in 3 phases:Phase-1 include 12 Km tunnelling

    32Mumbai Metro

    DPR Completed9.3Kolkatta Metro E/W Line

    Completed (TBM + Cut & Cover)

    Planned by 2009

    Subsequent Phase

    12.5

    10.0

    6.0

    Delhi Metro

    Phase-I

    Phase-II

    Phase-III

    RemarksLength ofUndergroundPortion (Km)

    Project

    Adoption of faster & cost-effective latest techniques for tunnel driving undercomplex geological environment and development of appropriate methodologyfor tunnel construction below heavily inhabited urban areas would be requiredin the coming years.

    Future Scenario for

    Tunneling Metro Railway

  • 7/25/2019 India Wtc 08

    13/13

    Conclusion Latest State-of-art Tunneling Technology is to be

    adopted on priority to expedite development of :-

    Power Sector involving about 900 KM of tunnelsvarying from 2.4 12 m dia.

    Construction of Metro Railways to avoid traffic

    congestion. Railway Tunnels

    Highway Tunnels

    In the deliberations in the congress, we areparticularly looking forward to presentations fromtunnel engineers, who are working on these recenttunnel projects about their experience about the use

    of high technology, the resulting problems and thesolutions adopted for their mitigation and about theactual performance on ground.