Page - 7

NO PROJECT CAPACITY SCOPE REMARKS

1. TG. PRIOK STEAM POWER PLANT U-3 & 4 2 x 50 MW BOILER, TURBINE

GENERATOR & AUXILIARY AFTER MARKET SERVICE

2. PERAK STEAM POWER PLANT U-3 & 4 2 x 50 MW BOILER, TURBINE

GENERATOR & AUXILIARY

MARKETING, AFTER MARKET SERVICE

3. MUARA KARANG STEAM POWER PLANT U-1,2,3 3 x 100 MW TURBINE GENERATOR &

AUXILIARY

MARKETING, AFTER MARKET SERVICE

4. SEMARANG STEAM POWER PLANT U-3 1 x 200 MW TURBINE GENERATOR &

AUXILIARY MARKETING, AFTER MARKET SERVICE

5. MUARA KARANG STEAM POWER PLANT U-4, 5 2 x 200 MW BOILER, TURBINE

GENERATOR & AUXILIARY MARKETING, AFTER MARKET SERVICE

6. KAMOJANG

GEOTHERMAL POWER PLANT U-1

1 x 30 MW TURBINE GENERATOR & AUXILIARY

MARKETING, AFTER MARKET SERVICE

7. KAMOJANG

GEOTHERMAL POWER PLANT U-2 & 3

2 x 55 MW TURBINE GENERATOR & AUXILIARY

MARKETING, AFTER MARKET SERVICE

8. KAMOJANG

GEOTHERMAL POWER PLANT U-2 & 3

- COOLING TOWER

MARKETING, AFTER MARKET SERVICE

9. SAGULING

HYDRO POWER PLANT U-1, 2, 3 & 4

4 x 175 MW GENERATOR & 525 KV GIS MARKETING, AFTER MARKET SERVICE

10. TELLO UJUNG PANDANG DIESEL POWER PLANT

U-1 & 2 2 X 12.5 MW DIESEL GENERATOR &

AUXILIARY

MARKETING, AFTER MARKET SERVICE

11. SURALAYA

STEAM POWER PLANT U-1 & 2

2 x 400 MW TURBINE, GENERATOR & AUXILIARY

MARKETING, AFTER MARKET SERVICE

12. SURALAYA STEAM POWER PLANT U-3 & 4 2 x 400 MW TURBINE, GENERATOR &

AUXILIARY MARKETING, AFTER MARKET SERVICE

13.

JAWA TIMUR DISTRIBUTION PHASE I, II, III - CONVENTIONAL

SUBSTATION MARKETING, AFTER MARKET SERVICE

14. SURALAYA - STEAM POWER PLANT SIMULATOR

MARKETING, AFTER MARKET SERVICE

Page - 7

NO PROJECT CAPACITY SCOPE REMARKS

15. SEMARANG 150 KV CONVENTIONAL SUBSTATION

MARKETING, AFTER MARKET SERVICE

16. GRESIK COMBINED CYCLE POWER PLANT

1,500MW; 3 BLOCK

@ 500 MW TURN-KEY PROJECT MARKETING, AFTER MARKET SERVICE

17.

DARAJAT

GEOTHERMAL POWER PLANT

U-1

1 x 55 MW TURBINE, GENERATOR & AUXILIARY

MARKETING, AFTER MARKET SERVICE

18. SURALAYA STEAM POWER PLANT 3 x 600 MW TURBINE, GENERATOR &

AUXILIARY MARKETING, AFTER MARKET SERVICE

19. SAGULING 500 KV, BAY NO.4 - 500 KV GIS MARKETING, AFTER MARKET SERVICE

20. GRATI CCPP

1 BLOCK OF 500 MW

AND 3 x 100 MW G/T

TURN-KEY MARKETING, AFTER MARKET SERVICE

21. JAKARTA STOCK EXCHANGE

BUILDING DIESEL P/P

6 X 1500 KVA DIESEL

POWER PLANT

D/G SETS, CONTROL PANEL, AUXILIARY

ENGINEERING, PROCUREMENT, CONTRUCTION, AFTER MARKET SERVICE

22.

MUARA KARANG 4 & 5 GAS CONVERSION WORK 2 x 200 MW

PIPELINE, GAS TREATMENT

SYSTEM AND BOILER & CONTROL

MODIFICATION

ENGINEERING, PROCUREMENT,

CONSTRUCTION, AFTER MARKET SERVICE

23. EMPIRE TOWER DIESEL P/P

4x 1,275 KVA DIESEL

POWER PLANT

D/G SETS, CONTROL PANEL, AUXILIARY

ENGINEERING, PROCUREMENT, CONSTRUCTION, AFTER MARKET

SERVICE

24. PALACE VIEW APARTMENT DIESEL P/P

3 x 1,312 KVA DIESEL

POWER PLANT

D/G SETS, CONTROL PANEL, AUXILIARY

ENGINEERING, PROCUREMENT, CONSTRUCTION, AFTER MARKET

SERVICE

25. D/G FOR PLN WIL. III PADANG 6 x 600 KW D/G SETS,

CONTROL PANEL S/V, PROCUREMENT AND AFTER

MARKET SERVICE

26. PLUIT MEGA MALL DIESEL POWER PLANT

7 x 1,500 KVA DIESEL

POWER PLANT

D/G SETS, CONTROL PANEL, AUXILIARY

ENGINEERING, PROCUREMENT,

CONSTRUCTION, AFTER MARKET SERVICE

27. PLN AIR RAJA DIESEL POWER PLANT 2 x 5.65 MW TURN-KEY

ENGINEERING, PROCUREMENT, CONSTRUCTION, AFTER MARKET

SERVICE

Page - 7

NO PROJECT CAPACITY SCOPE REMARKS

28. PLUIT MEGA MALL

DIESEL POWER PLANT (ADDITIONAL)

1 X 1,906 KVA DIESEL

POWER PLANT

D/G SETS, CONTROL PANEL, AUXILIARY

ENGINEERING, PROCUREMENT, CONSTRUCTION, AFTER MARKET

SERVICE

29. TAMAN RASUNA APARTMENT DIESEL POWER PLANT

1 x 288 KVA 1 x 500 KVA

D/G SETS, CONTROL PANEL, AUXILIARY

ENGINEERING, PROCUREMENT, CONSTRUCTION, AFTER SALES

SERVICE

30. ARCADIA OFFICE PARK DIESEL POWER PLANT

1 x 455 KVA 1 x 588 KVA

2 x 1,275 KVA 2 x 1,530 KVA

D/G SETS, CONTROL PANEL, AUXILIARY

ENGINEERING, PROCUREMENT, CONSTRUCTION, AFTER MARKET

SERVICE

31. PURI RATNA HOTEL DIESEL POWER PLANT 1 x 1,906 KVA D/G SETS,

CONTROL PANEL, AUXILIARY

ENGINEERING, PROCUREMENT,

CONSTRUCTION, AFTER MARKET SERVICE

32. PT. SOUTH PACIFIC VISCOSE, PURWAKARTA - BOILER NO.6 & 7 OVERHAUL AFTER MARKET SERVICE

33. PT TUGU KRESNA FOR PLN P3B (SAGULING)

FOR 500 KV (1 UNIT) SF6 GAS CIRCUIT BREAKER

ENGINEERING, PROCUREMENT,

ISTALLATION, TESTING, AFTER MARKET SERVICE

34. PT. KALIMANTAN ENERGI UTAMA

2 X 385KVA S6A3-PTA D/G SETS

ENGINEERING,PROCUREMENT,

TESTING COMMISIONING

35. PLN AIR RAJA DIESEL POWER PLANT

1 X 5.65 MW MITSUBISHI

S18KU

REWINDING & OVERHAUL GENERATOR UNIT I MAINTENANCE SERVICE

36. JAPANESE EMBASSY 2 X 750 KVA INSTALLATION WORKS

ENGINEERING,

PROCUREMENT & INSTALLATION

37. PT. SINAR GALAXY MALL

4 X 2,000 KVA MITSUBISHI S16R-PTA2

TOP OVERHAUL UNIT III & IV MAINTENANCE SERVICE

38. PT. NOVELL PHARMACEUTICAL FACTORY

1 X 1,000 KVA MITSUBISHI S1 2H-PTA

D/G SETS, CONTROL PANEL, AUXILIARY

ENGINEERING, PROCUREMENT & INSTALLATION

39. PLAZA INDONESIA ENTERTAINMENT CENTRE 2 X 1,385 KVA

D/G SETS,

CONTROL PANEL, AUXILIARY

ENGINEERING, PROCUREMENT & INSTALLATION

Page - 7

NO PROJECT CAPACITY SCOPE REMARKS

40. GADING MEDITERANIA RESIDENCES

2 X 2,000 KVA MITSUBISHI S16R-PTAA2

D/G SETS, CONTROL PANEL,

AUXILIARY

ENGINEERING, PROCUREMENT & INSTALLATION

41. PLAZA MEDAN FAIR

7 X 2,000 KVA MITSUBISHI S16R-PTAA2

D/G SETS ENGINEERING & INSTALLATION

42. PT. PJB SDPAP

GRESIK: 1,500 MW

GRATI: 800 MW PERAK: 100 MW

MITSUBISHI

TURBINE MARKETING, AFTER MARKET SERVICE

43. PT. INDONESIA POWER UBP, SURALAYA

unit 1-4 : 400 MW unit 5-7 : 600 MW total : 3,400 MW

MITSUBISHI TURBINE

TURBINE MARKETING, AFTER MARKET SERVICE

44. SURABAYA AIRPORT

PT.TOSHIBA PLAN SYSTEM & SERVICE CORPORATION

4 X 1,500 KVA MITSUBISHI

D/G SET PROCUREMENT

45. PT. BUMI LAKSAMANA JAYA 3 MW

MITSUBISHI S16U-PTK

D/G SETS MAINTENANCE (OVERHAUL), PROCUREMENT

46. PT. INDONESIA POWER UBP, KAMOJANG

145 MW

MITSUBISHI TURBINE

TURBINE MARKETING, AFTER MARKET SERVICE

47. PT. ANGELS PRODUCTS

3.5 MW STEAM TURBINE

TROUBLE-SHOOTING OF LOW CYCLE OPERATION

ENGINEERING PROCUREMENT & INSTALLATION

48. PT. PAKERIN 38.5 MW MHI STEAM TURBINE

THRUST BEARING INSPECTION,

RECOMMENDATION ENGINEERING SERVICE

49. PT. PJB UP. PAITON 1 X 200 MW STEAM TURBINE OIL CONTAMINATION ENGINEERING SERVICE/ INVESTIGATION

50. PT. BUMI LAKSAMANA JAYA

1.5 MW MITSUBISHI S8U-PTK

D/G SETS OVERHAUL, PROCUREMENT

51. UBP. SURALAYA, PJB 1 MW

MITSUBISHI S12N-PTA

PRIME MOVER, SEA WATER FIRE FIGHTER OVERHAUL, PROCUREMENT

52. UBP. SURALAYA, PJB 1 MW

MITSUBISHI S12A-PTA

PRIME MOVER, SEA WATER FIRE FIGHTER TOP OVERHAUL, PROCUREMENT

Page - 7

NO PROJECT CAPACITY SCOPE REMARKS

53. PT. UBP KAMOJANG

145 MW

Mitsubishi Turbine

TURBINE GENERATOR MARKETING, AFTER MARKET SERVICE

54. UBP. SAGULING 700 MW

Mitsubishi Generator

GENERATOR MARKETING, AFTER MARKET SERVICE

55.

PT. RIAU ANDALAN PULP & PAPER

28 MW MITSUBISHI

TURBINE

REPAIR SUPERVISION TURBINE

MAINTENANCE SERVICES

56. CHEVRON GEOTHERMAL INDONESIA Ltd

80MW MITSUBISHI TURBINE GEOTHERMAL TURBINE MARKETING AND AFTER MARKET

SERVICE