ind: north eastern region capital cities development ... · pdf filesemi annual social...
TRANSCRIPT
Semi Annual Social Safeguard Monitoring Report Loan Number: 2528/2834 IND Reporting Period: (January – June 2013)
IND: North Eastern Region Capital Cities
Development Investment Program
Project City: Gangtok, Sikkim State
Implementing Agency: State Investment Program Management and Implementation Unit (SIPMIU)
NORTH EASTERN REGION CAPITAL CITY DEVELOPMENT PROGRAMME (NERCCDIP)
SEMI ANNUAL SOCIAL SAFEGUARD REPORT
January – June, 2013
Contributed by
State Investment Programme Management and Implementation Unit (SIPMIU)
(Gangtok)
Table of Contents 1. Introduction .................................................................................................................................... 4
2. institutional & Implementation Arrangements – an OVERVIEW ................................................ 5
3. Project information/ Sub Project Components in Gangtok Municipal Corporation................... 6
4. Social Safeguard Activities in Sub projects ................................................................................. 8
4.1 Implementation of Resettlement Activities in Tranche -2 sub projects .......................... 8
4.2 SCOPE AND STATUS OF IMPACT ............................................................................................... 8
4.3 SUMMARY OF RESETTLEMENT IMPACTS AND SOCIO-ECONOMIC DETAILS UNDER SUB-
PROJETS ........................................................................................................................................... 9
4.4 STATUS OF ATHE AFFECTED PEOPLE: LAND REQUIREMENT, COMPENSATION AND
REHABILITATION IN WATER SUPPLY AND SWM SUB PROJECTS ................................................... 11
4.5 LAND REQUIREMENT, COMPENSATION AND REHABILITATION IN SUB PROJECT .................. 11
4.6 PERMANENT LAND ACQUISITION AND OWNERSHIP DETAILS UNDER SUB-
PROJECT .................................................................................................................................... 16
Table 6: Land Parcel for Service Reservoirs and the Ownership Details ..................... 16
Table 7: Details of the land Owner .......................................................................................... 17
Table 8: Land Parcel for Landfill Site and the Ownership Details .................................. 17
4.7 COMPLIANCE STATUS WITH RESPECT TO LOAN COVENANT ............................ 18
5. Validation and Verifications of AP’s .......................................................................................... 19
5.1 Validation of APs ................................................................................................................. 19
6. Public Consultations and Disclosure ......................................................................................... 21
7. Compliance to national laws and Policy (policy and Legal Framework): .................................. 21
8. Grievance Redressal systems and mechanishms ...................................................................... 22
9. MONITORING AND REPORTING ................................................................................................ 23
10. Issues and Action Plan........................................................................................................... 23
11. Activities carried out with respect to Public participation and implementation of GAP. .... 23
12. ANNEXURES........................................................................................................................... 24
ANNEXURE 1: Details of Public Consultations, Disclosure, Awareness campaigns ...................... 25
Annexure 2: GENDER ACTION PLAN ............................................................................................. 26
Annexure 3: SOCIAL SAFEGUARD MONITORING CHECK LIST ....................................................... 30
Tranche-II: SOCIAL SAEGUARD MONITORING CHECKLIST ................................................................ 34
Annexure 4: Summary of IR and IP Check list ............................................................................... 39
Annexure 5: Summary of Policy and legal framework (Only relevant portions) .......................... 40
Annexure 6: LAND RECORD - TO BE ACQUIRED ............................................................................ 41
Annexure 7: LIST OF AFFECTED PERSONS ..................................................................................... 42
Annexure 8: RESETTLEMENT BUDGET AND FINANCIAL PLAN ...................................................... 48
ANNEXURE 9: DOCUMENTARY PROOFS ....................................................................................... 50
ANNEXURE 10: Land Acquried Document .................................................................................... 50
SEMI ANNUAL SOCIAL SAFEGUARD MONITORING REPORT
1. Introduction
North Eastern Region Capital Cities Development Investment Program (NERCCDIP) is
being undertaken for improvement of existing infrastructure, environmental quality and
access to basic urban services of Gangtok Municipal Corporation (GMC) area. The
NERCCDIP’s objective is to improve the urban environment and promote reforms for
sustainable, efficient, and responsive urban service delivery. The primary drivers for the
initiation of NERCCDIP have been bridging the gaps in urban infrastructure provision,
supplementing financial resources and technical capacity and meeting the unmet urban
public health and sanitation needs. The various Program components are Water supply,
Sewerage and Sanitation, Solid Waste Management infrastructure.
With an overall objective of sustainable urban development, the NERCCDIP is being
implemented in the five capital cities - Gangtok, Aizawl, Kohima, Gangtok and Shillong.
NERCCDIP implemented over a six year period beginning in 2010, and is funded by a loan
via the Multitranche Financing Facility (MFF) of the Asian Development Bank (ADB).
In Gangtok, capital city of Sikkim, the Executing Agency (EA) for the program is the Urban
Development Department (UDD) of the Government of Sikkim (GoS); and the Implementing
Agency (IA) is the State-level Investment Program Management and Implementation Unit
(SIPMIU), created within the UDD, specifically for the Investment Program implementation.
At central level Investment Program Coordination Cell (IPCC) is established in MOUD. IPCC
is responsible for overall management of the Investment Program and is support Program
Management & Monitoring Consultants (PMMC).
Under the program the physical investments include improvements to water supply,
sanitation and sewerage, and solid waste management infrastructure. The physical
improvements are being coupled with urban governance, finance, and service delivery
reforms and a capacity building program to support the implementation of the investment
program and the urban reform agenda. The Investment Program is being implemented in
three tranches of funding; began in 2009 the Program will be implemented through 2015.
At present, Project 1 (Tranche-1) is under implementation in Gangtok and focuses on
water supply improvements. This subproject covers
construction of Distribution Network for Burtuk Zone-1 of 17.75km, Burtuk Zone-2 of
10.57km &Chandmari Zone-3 of 15.87km length;
construction of Pump House and installation of pumps at Selep Water Treatment Plant of
capacity 1930 lpm at Head of 101m,
construction of New R.C.C Reservoir of 11.50 LL capacity near All India Radio (AIR) for
Burtuk Zone-1&Chandmari, and
supply& Installation of Electromagnetic Flow meters at outlet of Pump house at Selep, outlet
of storage reservoir for Burtuk Zone-1 and at outlet of storage reservoir for Chandmari Zone.
Works taken up under Tranche-2 are awarded in two lots and the construction work should
commence within a period of two weeks (probably by 3rd week of July’2013). Initially civil contractor has to carry out field survey and subsequently design construction and
construction activities will follow. Work as such should commence from September,
2013.
This is the consolidated report on implementation of Social Safeguard Activities between
January 2013 – June 2013, and is prepared in compliance with the ADB Policies.
2. INSTITUTIONAL &IMPLEMENTATION ARRANGEMENTS – AN OVERVIEW
The Ministry of Urban Development (MoUD) is the national-level executing agency (EA) of
the Program. An IPCC has been established in MOUD and will include a social officer. A
National Steering Committee (NSC) is monitoring fund use and overall implementation
performance of the Investment Program. A State-level Executing Agency (SEA) is executing
the part of the loan falling under respective State Governments. In each State there a State
Steering Committee (SSC) has been formed and an Investment Program Empowered
Committee (IPEC) is also operational. SIPMIU is responsible for overall program
implementation, monitoring, and supervision. The SIPMIU has a Safeguards and Social Unit
in operation at Gangtok since June third week, 2013. An Resettlement Officer (RO) is
supposed be part of the Unit. ROs and implementing NGOs will be responsible for RP
implementation. Roles and responsibilities are identified in Table 1. For taking up
implementation of RP, institutional arrangements including strengthening of existing
institutional systems are required. Towards this, it is proposed that the SIPMIU’s Social and Resettlement Unit will take care of redressing grievances and mitigating negative social
impacts caused due to the project especially on Affected people (APs). The Unit should have
staff fully aware of provisions of RP, adequate understanding on norms and customs of and
respect to the local people, especially the indigenous people (consistent with the IPDF).
Table 1: Institutional Roles and Responsibilities
Activities Agency Responsible
Sub-project Initiation Stage
Finalization of sites/alignments for sub-projects SIPMIU Disclosure of proposed land acquisition and sub-project details by issuing Public Notice Meetings at community/ household level with APs of land/property Formation of Valuation Committees
SIPMIU NGO* SIPMIU
RP Preparation Stage Conducting Census of all APs SIPMIU/NGO Conducting FGDs/ meetings / workshops during SIA surveys SIPMIU/NGO Computation of Replacement Values of land/properties proposed for acquisition and for associated assets
VC/SIPMIU
Categorization of APs for finalizing entitlements SIPMIU Formulating compensation and rehabilitation measures Conducting discussions/ meetings/ workshops with all APs and other stakeholders for this
SIPMIU SIPMIU/NGO
Fixing compensation for land/property with titleholders VC/SIPMIU Finalizing entitlements and rehabilitation packages SIPMIU Disclosure of final entitlements and rehabilitation packages SIPMIU/NGO
Activities Agency Responsible
Approval of RP IPCC/ADB Sale Deed Execution and Payment Taking possession of land
SIPMIU
RP Implementation Stage Implementation of proposed rehabilitation measures NGO/RO Consultations with APs during rehabilitation activities NGO/RO Grievances Redressal NGO/RO/GRC Internal Monitoring SIPMIU External Monitoring External
Agency
AP=affected person, VC=Valuation Committee, FGD=focus group discussions, GRC = Grievance Redressal Committee, NGO = nongovernment organization, SIPMIU = state-level investment program management and implementation unit, IPCC = investment program coordination cell, RO = resettlement officer, RP=resettlement plan, SIA=social impact assessment.
3. PROJECT INFORMATION/ SUB PROJECT COMPONENTS IN GANGTOK MUNICIPAL CORPORATION
The sub project components taken up under various tranches in Gangtok Municipal
Corporation is summarized in table.2
Table 2: Sub project components
Component Tranche Works Progress
Water Supply
1 It is proposed to provide water supply to 2 wards Burtuk and Chandmari New Pump House at Selep with 3 New Pump sets New 11.50 Lakh litters Reservoir alongside AIR station road Pumping main from Selep to Reservoir 40.28 Km of Distribution lines in Burtuk and Chandmari (32MM to 250 MM Dia Pipes of HDPE,PE and GI make) Installation of 4 Bulk flow meters to measure flows in pipe lines.
Civil work & tank completed. Retaining wall work near completion. Pump house completed, Pump sets ordered. Supply expected by 30-07-2013. DI pipe: 18.41 km
completed, Hydraulic
testing started. PE pipe:
2km laid
Component Tranche Works Progress
Water Supply
2 It is proposed to provide water supply to remaining 13 wards except Burtuk and Chandmari De-Bunching the secondary water distribution with equivalent distribution line for a length of 104 Km with proper zoning arrangements Providing Primary water distribution pipeline for a length of 3.9 Km to connect the proposed tanks to the nearest existing feeder for catering to hitherto uncovered peripheral areas. Contribution of additional 5 nos. of service reservoirs of total capacity of 33.95 lakh liters Providing 39 Bulk flow water meters Providing 12000 Household water meters and making reconnection to replace the existing bunched connections.
Approval received from MoUD and ADB for debunching of secondary water distribution network LoA and contract for contractor under preparation
Solid Waste Management
2 Door to door waste collection will be introduced and waste will be collected on a daily basis, every household will be provided with two bins for the storage of biodegradable and non-biodegradable waste. The primary waste collectors will be provided with small mechanical vehicles and further it will transferred to secondary vehicles and finally to Solid Waste Management Plant. Biodegradable waste will be converted to manure by composting at the plant and non- biodegradable will be segregated again to inert and scientifically disposed in sanitary land fill. Construction of sanitary landfill with leachate treatment plant.
No objection for contract award received from ADB. (Bid for negotiation with L1 for LOT 1 and for contract awarded to L1 for Lot 2
Bid for SLF under financial
evaluation and report sent to ADB
Water Supply Subproject
The existing primary distribution networks (feeder mains) presently conveying treated water
from Selep WTP to the existing service reservoirs was retained. The new feeder mains are
designed for ultimate demand exclusively for the proposed service reservoirs in peripheral
areas. The new feeder mains will either pass through the existing feeder main alignments or
will follow the existing RoW. The proposed secondary and tertiary distribution system will
also follow the existing RoW. It has been found on an inspection of the sites with water
supply design engineers that pipes can be laid along the 5 to 10 m wide roads of Gangtok
City without acquiring any further lands. The improvement work can be carried out within the
RoW in road shoulders without causing problems to the existing lines. The maximum
required trench width in busy commercial area will be only 30 cm and trenching can be done
without causing any temporary impact lasting more than a day. In order to estimate the
temporary impact resettlement expert of DSMC carried out a joint site visit along with design
engineers. A strip plan showing no IR impact (commercial area) is given as Annexure – 2 of
this report. However, corrective action plan shall be prepared to mitigate any unforeseen
temporary impacts during the time of project implementation.
Solid Waste Management Sub project
Livelihood of 38 rag pickers working in the landfill will be affected due to this project. A
census and socio-economic survey was undertaken in the proposed land fill site situated in
the Martham village. Based on the census conducted during the period of November, 2010,
it is estimated that 38 households will be affected by the subproject. Of the total 38 AHs, 12
are in the muster roll of UDHD working as trash sorter in Martham compost plant as daily
wage laborers. In addition, there are 26 APs who are also working as a trash sorters. These
26 rag pickers segregate the waste on site and sell the non-biodegradable waste like plastic
bottles, glass bottles and other solid waste etc to a middle man and in turn he sells the same
to the recyclers. The proposed project will therefore impact the temporary livelihood of all
these 38 APs. Other than the 38 APs no squatters or encroachers are found to be residing
or carrying out any productive occupation in the portion of the land proposed for land fill site.
4. SOCIAL SAFEGUARD ACTIVITIES IN SUB PROJECTS
4.1 Implementation of Resettlement Activities in Tranche -2 sub projects
This section deals with the implementation of social safeguard activities of Water Supply and Solid Waste Management sub projects taken up under tranche -2 in Gangtok Municipality under the programme of North Eastern Regional Capital Cities Development Investment Programme (NERCCDIP). Resettlement Plan (RPs) has been prepared for both the sub projects and both the RPs are approved and uploaded in the ADB web site (http://www.adb.org/projects/documents/nerccdip-gangtok-water-supply-subproject- rp).However, in case of any change in locations and scope of work, RPs shall be revised/corrective action plan shall be prepared and disclosed in ADB as well as respective EA web site (http://sikkimudhd.org/Gangtok_RP_WS__Revised_.pdf) At present, no physical activity has started. Application of Resettlement Plan will be started prior to commencement of work. A Proposal for appointing an NGO for implementation of Resettlement Plan, Gender Action plan including awareness & capacity building program is in process.
4.2 SCOPE AND STATUS OF IMPACT
The specific scope of activities related to these sub project component includes the following:
Conduct awareness, participatory, and sensitization activities to increase understanding of the project and its benefits amongst the local service area populations
Conduct participatory planning and implementation exercises to identify issues and develop community-driven social and environmental action plans.
Build capacities and help organize local women and community groups to take a leadership role in local social and environmental initiatives, particularly in the areas of hygiene and sanitation.
Conduct behavior change programs targeting women and poor households to engender positive behaviors in water conservation, sanitation and hygiene including segregation of waste at source.
Develop and disseminate Information Education Communication (IEC) and Behavior Change Communication (BCC) materialsat regular intervals using various media including electronic, print, audio-visual media.
Provide skill training in livelihood opportunities from available recyclable materials (Solid Waste Management) targeting female headed and other marginalized households.
Provide training to all PIU and contractor’s staff (including laborers) on gender and social issues including HIV and women and child trafficking issues;
Implement the Gender Action Plan.
The specific scope of activities for the NGO related to resettlement includes the following:
Carry out revalidation of census survey based on the RP; Prepare the list of the potential affected persons and issue identification cards; Facilitate the process of disbursement of compensation to the affected persons Assist SIPMIU to acquire land required for construction reservoir through negotiation. Assist affected persons in opening bank accounts explaining the implications, the rules
and the obligations of a joint account and how s/he can access the resources s/he is entitled to;
Prepare micro plan for rehabilitating the project affected persons integrating with various developmental schemes of LSGD, state government and central government.
Organize training programs for income restoration; Conduct meaningful, ongoing consultation and ensure disclosure of Resettlement Plans
in an accessible manner to the affected persons; Assist SIPMIU in establishing grievance redress mechanism; Assist SIPMIU in keeping detailed records of progress and establish monitoring and
reporting system of resettlement; Act as the information source center for community interaction with the project and
maintain liaison between community, civil contractors and SIPMIU during the execution of the works; and
Introduce construction facilitation services.
Once NGO will be appointed the agency will carry out the activities. Meanwhile the following activity is being implemented by the social safeguard specialists of SIPMIU and DSMC.
Project Baseline, Performance Monitoring, and Evaluation Community Awareness, Behaviour Change, and Livelihood Training Program Resettlement Plan Implementation
4.3 SUMMARY OF RESETTLEMENT IMPACTS AND SOCIO-ECONOMIC DETAILS UNDER SUB-
PROJETS
The Investment Program is intended to optimize the socio economic development in Gangtok Municipality area with an objective to improve the urban environment cum living conditions of citizens. The sub projects implementations will not create any major negative impact on community. The anticipated impact on rag pickers at existing waste disposing site and impact on one title holder has appropriately been taken care of in the respective RPs. Also the implementation of RPs integrating with various developmental schemes of governmental and non-governmental agencies will enhance the living standard of PAPs. Summary of negative social impacts in tranche -2 sub projects is summarised in below tables (table 3 and 4)
Table 3: Summary of Resettlement Impacts and Socio-Economic Details under Water Supply Subproject
Type of Impact Number of APs
1.Permanent Loss
Title Holder/Land Owner 1
Total Loss of land(sq.mts) 400
Loss of trees 8
Total land Holding in that Particular Plot (sq.mts) 1400
Occupation Teacher/Government employee
Vulnerability Non Vulnerable
Annual Income (INR) 2,42000/
2.Temporary Loss
A)Temporary Loss/ Disruption of Business(Nos) Nil B)Temporary Loss/ Disruption of BusinessEmployees of the business enterprises(Nos)
Nil
3. Encroacher in ROW
A) Encroacher in ROW(Nos) Nil Affected CPRs NIL
Source: census and Socio-Economic Survey, December 2010 and Joint site verification carried out by Resettlement Specialist on 20-06-2013
Solid Waste Management Sub project
Table 4: Summary of Resettlement Impacts and Socio-Economic Details of SWM
Particulars Quantity Permanent land aacquisition (private) Nil Temporary land aacquisition Nil Total Affected Households (Loss of Livelihood) 38 Total Affected Persons 198 Average Family Size of Affected Households 5.2 persons Total No. of Scheduled Caste HH 3 Total No. of Woman Headed Households 3 Total No. of Schedule Tribe Households 9 Total No. of Title Holders NIL Total Number of Non-Title holders 38 Total No. of Tenants NIL Main Occupation of the Affected Persons Casual labour (63.15% of total
worker) Average Annual Household Income Rs.72,982 (Rs.6098 per month)
Source: census and Socio-Economic Survey, November 2010
Details of “Affected Persons” for the sub projects including census data will be verified by concerned Govt. Dept. and Safeguard Specialist of SIPMIU before disbursement of
compensation to APs as per approved entitlement matrix. List of APs with photographs is
given in Annexure 3.
4.4 STATUS OF ATHE AFFECTED PEOPLE: LAND REQUIREMENT, COMPENSATION AND
REHABILITATION IN WATER SUPPLY AND SWM SUB PROJECTS
4.5 LAND REQUIREMENT, COMPENSATION AND REHABILITATION IN SUB PROJECT
Out of two sub projects (Water supply and Solid Waste Management) taken up under
tranche -2, private land acquisition is envisaged only for construction of one service reservoir
at lower Sichey in water supply sub project. Details of additional land required for the sub
projects is given in table 5.
The land acquisition and resettlement impacts are minimal. Efforts have been made by the
engineering team to minimize the resettlement impact by careful design as most of the
implementation activities under the subproject will be confined to the available government
land and existing Right of Way. The subproject components and a summary impact on land
acquisition and resettlement is described in Table 5.
Table 5: Subproject Components and its Impact on Land Acquisition & Resettlement
Component Location Description Permanent Impact on LA and IR
Temporary Impact
Remarks
Providing new secondary water distribution network for a length of 104.10km with proper zoning arrangements to replace the present bunched distribution system and for uncovered peripheral area
De bunching will be done for existing secondary network system throughout Gangtok Municipal Area and extension of secondary distribution network to uncovered peripheral areas
PE/GI/DI pipes of diameter 32 to 350 mm to be laid in trenches along the right-of-way (RoW) of existing roads
Nil Nil Excavation will be carried out manually. The width of the trench will be within one feet and around one feet depth, hence this will not cause any loss of access to the commercial areas. Also appropriate design option would be explored to avoid trenching in busy commercial areas like MG Marg and Lal Bazaar.
Providing primary water distribution pipeline (feeder mains) of 150mm diameter DI to 100mm diameter for a length of
1. Tapping from nearest topographical feasible point of existing feeder main to the proposed Press Tank - Zone-3 2. Tapping
Nil Nil
Component Location Description Permanent Impact on LA and IR
Temporary Impact
Remarks
3.91km tapping from existing feeder mains to the newly proposed service reservoirs for catering to hitherto uncovered peripheral areas
from nearest topographical feasible point of existing feeder main to the proposed Bazar Tank – Zone-4 3. Tapping from nearest topographical feasible point of existing feeder main to the proposed lower Sichey Tank – Zone-5 4. Tapping from nearest topographical feasible point of existing feeder main to the proposed Enchey Tank – Zone-6 5. Tapping from nearest topographical feasible point of existing feeder main to the proposed Tank at TNSS area – Zone-7
Construction of additional 5 nos.. of service reservoirs of total capacity of 33.95 ML.
SR-1 at existing press tank area SR-2 at existing Bazar tank area SR-3 at lower
15.60 LL capacity rectangular reinforce concrete(RCC) tank of 5m depth 5.35 LL capacity rectangular
Yes Nil Out of the total 5 SRs 4 will be constructed on the existing government land. Only one SR (SR-3 (at lower Sichey) having 25m x 16m area will
Component Location Description Permanent Impact on LA and IR
Temporary Impact
Remarks
Sichey area SR-4 at existing Enchey tank area SR-5 at TNSS area
RCC tank of 4-m depth 4.40 LL capacity rectangular RCC tank of 4-m depth 5.30LL capacity rectangular RCC tank of 4-m depth 3.30 LL capacity rectangular RCC tank of 4-m depth
require acquisition of private land
Providing 39 nos. Bulk water meters.
Bulk meters will be fixed on pipeline at various locations in the Gangtok town
39 numbers to measure the quantity of water produced at WTP and supplied into the distribution network
Nil Nil Minor work with negligible physical construction.
Providing 12000 household water meters and making re-connections to replace the existing bunched connections.
Consumer meters will be fixed to each connection at the house
12000 numbers to to measure quantity of water supplied to consumer
Nil Nil Minor work with negligible physical construction.
Improvement of the waste collection and transportation system
All 15 Wards of Gangtok Municipal Corporation
introduction of door-to-door collection and segregation of waste 47,200 bins for segregation primary collection – mini tripper-11 nos (1.5 cum cap) & 3
Nil Nil
Component Location Description Permanent Impact on LA and IR
Temporary Impact
Remarks
tippers (4.5 cum cap) waste collection from street sweeping – pushcarts-100 nos. (100 ltrs cap) waste collection from street sweeping – litter bins-235 nos. secondary collection – metallic containers-8 nos. (1110 ltrs cap) Secondary collection – compactors- 5 nos.
Rehabilitation of existing compost plant
At Martham 20 Kms away from Gangtok
Replacement of broken shaft of second trammel and repair of other machineries.
Nil Nil
Construction of a new landfill and associated facilities
Martham adjacent to the land fill site
reengineering of the existing waste dump construction of new landfill construction of retaining wall construction of leachate collection and removal system construction of leachate treatment plant construction of entrance gate
Nil Yes Construction of new Landfill facility (4.2660 Heactre) with Leachate Treatment Plant (40 cum /day capacity). The land is already available with the UDHD,therefore, no private land acquisition is required. However, there will be impacts on 38 households on their livelihood.
Component Location Description Permanent Impact on LA and IR
Temporary Impact
Remarks
construction of chain link fencing construction of security cabin with room and toilet construction of office cum workers room construction of toilet block construction of access roads rehabilitation of existing road construction of storm water drainage network construction of water supply facilities provision of green belt (as buffer zone) construction of monitoring well earmarking of areas for waste segregation and recycling, top soil storage, vehicle washing area and vehicle parking area provision of electrical works for street lighting and internal lighting
All these 38 families are rag pickers
4.6 PERMANENT LAND ACQUISITION AND OWNERSHIP DETAILS UNDER SUB-
PROJECT
Permanent land acquisition will be there for the water supply sub project for the construction
of one service reservoirs amongst proposed five number of service reservoirs. All the
components of the water supply sub projects are located on vacant government land (except
one service reservoir) or along existing right-of-way (RoW) of city roads. The construction of
other 4 new service reservoirs is proposed within available public lands, identified in
consultations and as per the suggestions of Water Security and Public Health Engineering
Department (WSPHED), Government of Sikkim. One service reservoir which has been
proposed in the lower Sichey area will be located in private land. The total land requirement
for this service reservoir is 400 sq meters. The identified location of this proposed service
reservoir has also been done in-consultation with (WSPHED) as no Government land is
available in that area. Location and the required area for each service reservoir along with
the ownership are described in Table 6.
Table 6: Land Parcel for Service Reservoirs and the Ownership Details
Sl. No. Location of proposed SR Ward No. Required land Ownership of land
1 Proposed Reservoir-1 (at existing Press tank site )
7 25m x 16m Government Land
2 Proposed Reservoir-2 (adjacent to Existing Bazar Tank site )
7 20m x 13m Government Land
3 Proposed Reservoir-3 (at lower Sichey )
2 25m x 16m Private Land
4 Proposed Reservoir-4 (adjacent to existing Enchey Tank area )
4 26m x 16m Government Land
5 Proposed Reservoir-5 (at TNSS area )
3 24m x 12m Government Land
Source: census and Socio-economic Survey, November-2010
It can be seen from table 6 that the total required private land is 400 square meters. The
required land is under single ownership. The required land is nearly 1/4 of the total available
land in the same plot.
The total available land in that particular parcel of land is 1400 m2 as per land records. The
land owner is having total land including the parcel of land where tank has been proposed is
2723 m2. Only 28% of the particular plot and 14 % of the total Land holding is getting
affected due to the proposed sub project.
8 nos. of trees of non-timber value and non-fruit bearing will be affected due to tank
construction. The scanned copy of the certified land record (ParchaKhatian) of that particular
plot and the layout of the plot have been placed in Annexure-1.
Detailed consultations have been undertaken with the land owner. The land owner has
agreed to provide the land in the best interest of the project. A detailed site analysis has
been done jointly by the water supply and resettlement specialists and a tentative drawing
(not to scale) has been prepared for the positioning of the service reservoir. It can be seen
from the Annexure-1 , that the proposed location of the service reservoir will be in one corner
of the plot without alienating the total land enabling the owner to use rest of the land for his
own productive purpose.
There are no encroachers in the plot to be acquired either residing or carrying out productive
occupation. The summarized land details with name of the land owner are described is
provided in Table 7. Land acquisition process is in progress through negotiated purchase.
Table 7: Details of the land Owner
Name of the Owner
Parcha No.
Khatian No.
LA in (Sq.mts)
Total Area of the Plot (Sq.mts)
Total land holding of the owner (Sq.mts)
% of Loss compared to the total area of the affected plot
% of Loss compared to the total area of land holding
Number of Trees
Dhan Kumar Rai
139/354
287/1096
400 1400 2723 28% 14 % 8 trees –Non fruit bearing and non-timber value
Source: census and Socio-economic Survey, November-2010
The proposed subproject will require available government land for development of sanitary
land fill site and processing plant, access road to the processing plant and for developing a
green belt area all around the SWM site. The existing site of dump yard located at Martham
will be used to accommodate the entire proposal. Hence, no permanent land acquisition
from private sources is required for the sub project. The land belongs to the UDHD of
Government of Sikkim. It is evident from the table 4 that, 4.2660 hectare (ha) of land is
owned by UDHD department. The revenue department has already initiated the process for
mutation of the 4.2660 hectare of the land to be transferred to UDHD, Government of
Sikkim. The ownership status of the land is given in Table 8.
Table 8: Land Parcel for Landfill Site and the Ownership Details
Sl No Survey Number/Plot Number
Area in Hectare
Status of Ownership
1 1958 1.3720 Government/UDHD
2 1957 0.2240 Government/UDHD
3 1956 0.3060 Government/UDHD
4 1959 1.0280 Government/UDHD
5 1962 0.1140 Government/UDHD
6 1961 0.5580 Government/UDHD
7 1960 0.5060 Government/UDHD
8 1964 0.1580 Government/UDHD
Total Area 4.2660
4.7 COMPLIANCE STATUS WITH RESPECT TO LOAN COVENANT
The compliance status with respect to loan covenant is presented in below table.
Table 9: Compliance status
Sl
No
Loan Covenant Agency Status of
Compliance
1 GOI and the State will ensure that all land
and right of way required for investment
program are made available in timely
manner.
Government of
India and
Government of
Sikkim
No private land
acquisition and
resettlement issues
are involved under this
project. Hence RPs
has not been
prepared.
2 Adequate compensation are provided prior
to the signing of relevant civil works
contracts, and involuntary resettlement is
carried out in accordance with the
resettlement framework (RF) and
resettlement plans (RPs) agreed upon
between the Government and ADB. An RP
will be prepared for each sub project
involving land acquisition and resettlement
and shall be submitted to ADB for review
and approval prior to award of any related
civil works contracts.
Government of
India and
Government of
Sikkim
3 GOI and the State will ensure that sub
projects will not negatively impact on
vulnerable groups, such as indigenous
people. In the event of their involvement in
any of sub projects, the GOI and the states
will ensure the that the sub projects are
carried out in accordance with the
Indigenous People Development
frameworks (IPDF) agreed up on between
GOI and the states and the ADB and
comply with ADBs policy on Indigenous
People (1998)
Government of
India and
Government of
Sikkim
No negative Impact on
vulnerable groups
4 In the event any issues related to
indigenous people arise in course of project
implementation, the borrower and the state
shall ensure to address those issues in
accordance with the applicable laws and
policies of the borrower, ADB’s policy on indigenous Peoples (1998) and the
Indigenous Development Framework for
Government of
India and
Government of
Sikkim
Agreed. However, no
issues related to
indigenous people are
anticipated in course
of execution.
Sl
No
Loan Covenant Agency Status of
Compliance
the facility as agreed between the
borrower, the state and ADB. In the case of
any discrepancy between the borrower’s legislation and ADB’s policy, ADB’s policy shall prevail.
5 GOI and State will ensure that all civil
works contractors comply with all
applicable labour laws, including those on
occupational health and safety, and do not
employ child labour as defined in national
legislation for construction and
maintenance activities. Priority work will be
given to people from the area where the
works are implemented and men and
women will receive equal pay for work of
equal value.
Government of
India and
Government of
Sikkim
Adequate provision
has been made.
5 Within six months of the Effective Date, the
State shall have established a grievance
reporting and redressal mechanism
Government of
Sikkim
Soon to be
established.
4.8 STATUS OF CONTRACTOR SOCIAL SAFEGUARDS COMPLIANCE
Contractors are complying with all Social safeguard procedures advised by SIPMIU and
DSMC
5. VALIDATION AND VERIFICATIONS OF AP’S
5.1 Validation of APs
All the APs as per RPs will be validated and verified by the implementing NGO along with
SIPMIU’s Social safeguards Officer and DSMC’s Social Safeguard Specialist. This will be done with field verification (signature, photos & proof of identification like voter ID etc to be
taken) before Subproject ID Cards disbursement.
5.2 Compensation and Assistance
In accordance with the involuntary resettlement principles set forth above, the identified
affected persons will be entitled to a combination of compensation packages and
resettlement assistance depending on the nature of ownership rights on lost assets, and
scope of the impacts including socio-economic vulnerability of the affected persons and
measures to support livelihood restoration if livelihood impacts are envisaged.
Affected Persons, meeting the cut-off date requirements (for title holders, the date of Section
4.1 of the LAA will be treated as the cut-off date, and for non-titleholders the date of project
census survey will be considered as cut-off date), will be entitled to a combination of
compensation measures and resettlement assistance, depending on the nature of ownership
rights of lost assets and scope of the impact, including social and economic vulnerability of
the affected persons. Unforeseen impacts will also be compensated in accordance with the
principles of this Plan.
i. Compensation procedures. Paying compensation to the temporarily affected persons will take the following steps:
Step1. Conduct public awareness and information dissemination prior to construction works. This is to be done by the NGO and social safeguard experts of SIPMIU and DSMC.
Step2. The Design Supervision and Management Consultant (DSMC) to identify the roads in collaboration with contractor, which will experience full closure and estimated period of closure. Two types of disturbance anticipated from full closure of roads: (i) partial disturbance, where there is no vehicular access but pedestrian access is maintained, or (ii) full disturbance, where there is no vehicular and no pedestrian access.
Step 3: The DSMC’s social safeguard specialist (along with NGO/SE of SIPMIU) is to then (a) conduct an income survey of shops along sections of road closure identified for full closure, (b) update the Resettlement Plan (identifying income and potential loss based on actual income losses), and (c) send the updated Resettlement Plan to ADB for review and approval after detailed designs are complete.
Step 4: After ADB approval of the revised Resettlement Plan, the SIPMIU Social Safeguard Specialist with the help of NGO will distribute identity cards with compensation amount to the affected persons.
Step 5. Affected person can then collect payment at SIPMIU office or on site, based on SIPMIU’s discretion.
Step 6. SIPMIU to issue a cheque to affected persons based on survey record and identity card prior to construction works (if feasible). All payments to be recorded for accounting purposes with signature of affected person to verify payment made.
ii. Vendor Assistance: Vendors requiring temporary shifting during construction period will be notified in advance and allowed to salvage all materials for temporary shifting to alternative location. They will be allowed to return to the original location after construction is declared complete. Vendor assistance will take the following steps:
Step 1. Identification of impacted vendors based on detailed design by DSMC social specialist and Social Officer of SIPMIU in coordination with contractor.
Step 2. Notify vendors at least 2-3 weeks in advance. Consult with local Vendor Associations if exist.
Step 3. Identify alternative location nearby for affected vendors to continue their business.
Step 4. Assistance by contractor to shift to new location.
Step 5. Assistance by contractor to return to original location after construction works complete.
Cash compensation and other entitlements prescribed in the Entitlement Matrix will be provided to each AP before taking possession of the land/properties. APs will be provided with an advance notice of 60 days prior to possession being taken of the land/properties. After payment of compensation at replacement cost, APs would be allowed to take away the materials salvaged from their dismantled houses and shops and no charges will be levied upon them for the same. A notice to that effect will be issued clarifying that APs can salvage the materials. The SIPMIU will provide satisfactory evidences of payment of compensation
and assistances for each section prior to commencement of civil works in the respective sections of a subproject. All compensation and assistance will be paid to APs prior to commencement of construction activities. The budgetary provision for compensation and implementation of RP is shown in Annexure 4. Budget will be revised in case of change in number of affected persons after re-verification through NGO and social safeguard specialist of SIPMIU/DSMC.
6. PUBLIC CONSULTATIONS AND DISCLOSURE
The RP was prepared in consultation with stakeholders. Public consultations were
conducted to gather feedback from local people on the proposed development and
perceived socio-economic impacts. Meetings and consultations with relevant Government
Departments were carried out to assess the Project approach. Public consultations through
Focus Group Discussions (FGDs) with project beneficiaries and project-affected people have
been carried out. Consultations were also carried out during the course of environment
impact assessment.
Details of FGD conducted during verification of land ownership and for understanding the
views of the encroachers & squatters is given as Annexure -5. Annexure 5 shows the date,
location, participant list and summary of outcome of public consultation. All discussions and
recommendation were recorded for preparation of action plan and follow up in future.
7. COMPLIANCE TO NATIONAL LAWS AND POLICY (POLICY AND LEGAL FRAMEWORK):
The policy framework and entitlements for the program as well as for this subproject are based on following national laws: The Land Acquisition Act, 1894 (LAA, amended in 1984), and the National
Resettlement and Rehabilitation Policy, 2007 (NRRP); state laws and regulations: The Sikkim State Land Acquisition (LA) Act 1894, the Sikkim Urban and Regional Planning Development Act (1998) and the Sikkim Land (Requisition and Acquisition) Act of(1977), 1960; ADB’s Safeguard Policy Statement, 2009 (SPS); and the agreed Resettlement Framework (RF).
Based on these, the core involuntary resettlement principles applicable are:
i. land acquisition, and other involuntary resettlement impacts will be avoided or minimized exploring all viable alternative subproject designs
ii. where unavoidable, time-bound Resettlement Plans will be prepared and APs will be assisted in improving or at least regaining their pre-program standard of living
iii. consultation with APs on compensation, disclosure of resettlement information to APs, and participation of affected persons in planning and implementing subprojects will be ensured
iv. vulnerable groups will be provided special assistance v. payment of compensation to APs including non-titled persons (e.g., informal
dwellers/squatters, and encroachers) for acquired assets at replacement rates vi. payment of compensation and resettlement assistance prior to the contractor taking
physical acquisition of the land and prior to the commencement of any construction activities
vii. provision of income restoration and rehabilitation and viii. establishment of appropriate grievance redress mechanisms
The RP outlines the objectives, policy principles and procedures for land acquisition, compensation and other assistance measures for Affected Persons (APs). The Executing Agency (EA) and the Implementing Agency (IA) will have to endorse the Resettlement Plan prior to Project Appraisal. The RPs shall be disclosed to the affected persons (APs) and submitted to ADB for review and approval prior to commencement of any civil works. Compensation and other assistances will have to be paid to APs prior to any physical or economic displacement of affected households.
8. GRIEVANCE REDRESSAL SYSTEMS AND MECHANISHMS
Grievances of APs will first be brought to the attention of the implementing NGO or RO. Grievances not redressed within 30 days by the NGO or RO will be brought to the grievance redress committee (GRC), established in each State. GRCs will comprise the Investment Program Director, RO, LAO, implementing NGO representative, female and male AP representatives (including vulnerable households), and an eminent member of the community. The GRC will meet every month, determine the merit of each grievance, and resolve grievances within a month of receiving the complaint; failing which the grievance will be addressed by the IPEC. Further grievances will be referred by APs to appropriate courts of law. Records will be kept of all grievances received including: contact details of complainant, date that the complaint was received, nature of grievance, agreed corrective actions and the date these were affected, and final outcome. All costs involved in resolving grievances will be borne by the SIPMIU. The SIPMIU through the DSMC will keep records of all grievances received including: contact details of complainant, date that the complaint was received, nature of grievance, agreed corrective actions and the date these were effected, and final outcome. The grievance redress process is shown in Figure 1.The GRCs will continue to function throughout the project duration.
Figure 1: Grievance Redress Mechanism
NGO: Non- Government Organization, DSMC: Design Supervision Management Consultant,
SIPMIU: State Investment Program Management and Implementation Unit
Till date no GR committee is set up in Gangtok. As per project Executing Agency process has been initiated for setting up GR committee and which will be completed before commencement of physical activity.
9. MONITORING AND REPORTING
RP implementation will be closely monitored to provide the SIPMIU with an effective basis for assessing resettlement progress and identifying potential difficulties and problems Monitoring will be undertaken by the SIPMIU .The extent of monitoring activities, including their scope and periodicity, will be commensurate with the project’s risks and impacts. Monitoring will involve: (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; (ii) socio-economic monitoring during and after any resettlement impact utilizing baseline information established through the socio-economic survey of APs undertaken during project sub-preparation; and (iii) overall monitoring to assess AP’s status. The EA is required to implement safeguard measures and relevant safeguard plans, as provided in the legal agreements, and to submit periodic monitoring reports on their implementation performance. ADB will require the EA to:
establish and maintain procedures to monitor the progress of implementation of safeguard plans, verify the compliance with safeguard measures and their progress toward intended outcomes, document and disclose monitoring results and identify necessary corrective and preventive actions in the periodic monitoring reports, follow up on these actions to ensure progress toward the desired outcomes,(v) retain qualified and experienced external expert to verify monitoring information for projects with significant impacts and risks, Submit periodic monitoring reports on safeguard measures as agreed with ADB.
The SIPMIU monitoring will include daily planning, implementation, feedback and trouble
shooting, individual AP file maintenance, community relationships, dates for consultations,
number of appeals placed and progress reports. The SIPMIU will provide monthly monitoring
report to ADB on a quarterly basis. Monitoring reports documenting progress on resettlement
implementation and RP completion reports will be provided by the SIPMIU to ADB for
review. Additionally, ADB will monitor projects on an on-going basis until a project
completion report is issued.
10. ISSUES AND ACTION PLAN
Since RP has been prepared in the year of November 2010, it is anticipated that certain
changes can occur in the number and status of PAPs. This shall be confirmed only after
carrying out a revalidation of census survey. The revalidation of census survey and
preparation of micro plan for rehabilitating the project affected persons are in progress. As
implementation NGO has not yet mobilised at site the activities of RP implementations are
now attended by social experts of SIPMIU and DSMC. The resettlement activities shall be
completed before commencement of civil works at site.
11. ACTIVITIES CARRIED OUT WITH RESPECT TO PUBLIC PARTICIPATION AND IMPLEMENTATION OF GAP.
A Social Safeguard Officer has been appointed and is in SIPMIU since 3rd week of June,
2013. Formation of Grievance Redressal Committee and appointing an NGO for RP
implementation is in the process (as per approved RP).
A workshop on Community participation and gender sensitization for ULB councilors and
selected NGOs was conducted at GMC conference hall on 18th June, 2013. It was decided
to form ward wise women groups during the project consultative meetings which is part of
GAP and also to ensure community participation during the project implementation as well
as Operation and Maintenance (O&M). A report of the work shop is attached as annexure 9.
The action is operationally feasible. Accordingly, it has been planned to arrange 15
consultative meetings in 15 wards of Gangtok. Subsequently the women groups will be
formed in the 2nd half of 2013 (In the month of July, 2013).
Household survey to identify the women headed households and urban poor are in progress.
(IDC is conducting a 100% H/H survey for preparing an area profile. We have asked them to
incorporate some parameters to assess the no. of women headed household and urban
poor).
12. ANNEXURES
ANNEXURE 1: Details of Public Consultations, Disclosure, Awareness campaigns
Please attach list of meetings etc held only during the last 6 months (January to June,
2013 only) in the table provided below:
Sl. No.
Place & Date Participants Issues
discussed Opinion & consensus about
the Project
1 18
th June, 2013
at GMC Hall ULB councilors and
selected NGOs
Importance of Public
participation, Gender
Sensitization and IEC activities
It was decided to form ward wise women groups during the project
consultative meetings which is part of GAP and also to ensure
community participation during the project implementation as well as
Operation and Maintenance (O&M).
Annexure 2: GENDER ACTION PLAN
Activities as per
Approved GAP in
Gangtok
Activities conducted
in Gangtok Municipal
Corporation up to
January, 2013
Activities Conducted
During the period from
January, 2013 to June
2013
Issues and
Challenges
Conduct of 1 gender
sensitization
seminar for each
program city that
highlights gender
issues in water
supply, sanitation,
solid waste and
drainage, and the
need for women’s involvement in the
implementation,
O&M of these
services
1. City level gender
sensitization
seminar was held on
5th November, 2012.
Municipal council
officials,
Representatives of
women’s NGOs, community members,
SIPMIU staff &
contractors were
sensitized.
1. Sensitization
A work shop for Gender
Action Plan
implementation and
public participation
during the project
implementation a
workshop is conducted
on 18th June, 2013, 1.30
PM at GMC conference
hall
The primary objectives
of the workshop was to
sensitize the Councilors
and selected NGO
representatives about
the importance of public
participation, gender
sensitization and IEC
activities under this
project, Report is
attached as annexure 1
of this report.
2.Mobilization of Social
Development Officer in
SIPMIU: SDO is
mobilized at SIPMIU on
17.06.2013. The
candidate had also
undergone the ADB
training conducted
between 1st and 6th of
July 2013 at Hyderabad.
3. Appointment of
NGO: NGO for
Nil
Activities as per
Approved GAP in
Gangtok
Activities conducted
in Gangtok Municipal
Corporation up to
January, 2013
Activities Conducted
During the period from
January, 2013 to June
2013
Issues and
Challenges
assisting the GAP
implementation is in
progress by SIPMIU
Select an
appropriate NGO or
social workers for
implementation of
gender related
needs and actions
for water supply.
Divide the project
zone into three parts
viz. upper class
areas, middle class
areas and slum
areas since their
concerns and needs
may be different.
NGO engaging for RP
implementation will
assist SIPMIU to
implement the GAP, the
appointment of RP
implementation NGO is
in progress.
No Budget
available with
SIPMIU/DSMC
for the GAP
implementation.
Provision of
connections and
meters to poor
female-headed
households (FHHs)
in each program
city.
Identification FHHs by
IDC is in progress
Employment of
women in the
construction of
pipelines, plants,
etc., with
implementation of
‘same pay forwork of equal value’
Contractors were
sensitized
Prioritize
connections to
sewerage system of
poor female-headed
households
No action has been
taken
Prioritize FHHs in
the provision of
household bins
(6,000 FHHs in
Identification FHHs by
IDC is in progress
Activities as per
Approved GAP in
Gangtok
Activities conducted
in Gangtok Municipal
Corporation up to
January, 2013
Activities Conducted
During the period from
January, 2013 to June
2013
Issues and
Challenges
Gangtok)
Conduct of 1
consultation per
program city, among
community
members (target:
50% women)
including SCs and
STs, and NGOs on
the manner and
schedule of trash
collection
1. City level gender
sensitization
seminar was held on
5th November, 2012.
Municipal council
officials,
Representatives of
women’s NGOs, community members,
SIPMIU staff &
contractors were
sensitized.
Conduct an
exploratory study on
possible livelihood
opportunities from
available recyclable
materials and the
market for possible
products from these
recycled materials
Nil Nil Scheduled
during the Month
of September-
October, 2013
Conduct of 2
trainings on
alternative
livelihoods for
women using
recyclable materials
(e.g., papiermache,
etc.) per program
city
Nil Nil Scheduled
during the Month
of September-
October, 2013
Conduct of
demographic survey
of program city,
showing gender
differential access to
urban services,
income / poverty
levels, among other
such indicators,
specifically, between
male-headed and
female-headed
households and
Study by IDC is in
progress
Activities as per
Approved GAP in
Gangtok
Activities conducted
in Gangtok Municipal
Corporation up to
January, 2013
Activities Conducted
During the period from
January, 2013 to June
2013
Issues and
Challenges
among SCs and STs
Instituting
geographic and sex-
disaggregated
project management
information system
Study by IDC is in
progress
Conduct of on-the-
job capacity-building
activities for SIPMIU
on gender-sensitive
recruitment,
management,
procurement and
contract
management,
project and
performance
monitoring,
safeguard
compliance, land
acquisition, and
preparation of
feasibilities studies
and detailed designs
Being complied
Annexure 3: SOCIAL SAFEGUARD MONITORING CHECK LIST
Project Data Name of Project & Subproject :
NERCCDIP Water Supply Taken up under Tranche -1
Project Disbursement Status (%) :
Type of contract :
Regular Design-Build Combined
Safeguards Categorization
A B C
IR Yes IP Yes
A. Design and Engineering Status
Item Status (Y/N)
Follow up required
(Y/N)
Type of Required Action
Final detailed engineering design of the sub project completed
Y N Updated draft IR/IP New RP/IPP preparation
Changes in project design/ scope (occurred or envisaged)
N N Project re-categorization (IR/IP) IR/IP Impact assessment New RP/IPP preparation
B. Institutional Status Readiness
No Item Status (Ready/Not ready/NA)
Follow up required
(Y/N)
Completion Deadline
1 Mobilization of civil works contractor
Ready N 19/03/2013
2 Mobilization of Project Supervision Consultant
Ready N 2015
3 EA’s Safeguards Unit with designated staff
Ready N
4 Recruitment of External Monitoring Agency
NA NA
C. Safeguards Requirements
No Item Status (Ready/Not ready/NA)
Follow up required
(Y/N)
Completion Deadline
1 Safeguards monitoring included in the project progress report
Ready No 01/07/2013
2 Final/ updated RP/IPP1 prepared and submitted
NA No 01/07/2013
3 Project’s Grievance Redress Mechanism established
Ready
4 Recruitment of third independent party for negotiated land acquisition
NA NA
5 Project’s ESMS (for FI) established
Ready
D. RP/ IPP Monitoring Checklist2 Item No.
Safeguards Related Requirements Status (Ready/Not ready/ NA)
Completion Deadline
Progress to Date/ Remarks
1.0 MANAGEMENT
Institutional and Financing Arrangements 1.1 Financing and budget : (i) safeguard office
and staff; (ii) RP/IPP cost
Ready
1.2 Establish Safeguard Unit: (i) resettlement offices (ii) resettlement staff as in RP (iii) safeguards’ database (iv) facilities (v) safeguards training
Ready
Updating of DD/RP/IPP based on Detailed 1.3 Update DD/RP/IPP: (i) revise based on DMS
(ii) revise implementation schedule (iii) revise budget
NA
1.4 Compensation rates: (i) approved by Government ; (ii) Adequate as per RP/RF; (iii) APs informed.
NA
Disclosure and Grievance Redress 1.5 Disclose final/updated RP/IPP: (i) to the APs
in local language; (ii) in ADB website; (iii) in EA’s website
Ready
1.6 Disclose project activities to affected communities: (i) put up a project sign boards; (ii) distribution of project leaflets and GRM to
NA
1.7 Grievance redress committees: (i) clear terms of reference; (ii) appointment decree;
NA
1.8 Grievance redress records: (i) list and numbers of grievances received; (ii) numbers of resolved issues; (iii) numbers of cases under GRC review; (iv) outstanding cases (filed to court)
NA
Monitoring and Reporting Arrangements 1.9 Set up internal monitoring system : (i)
assessment on capacity and staff requirements; (ii) criteria
Ready
1 Detail checklist for RP/IPP supervision provided in section D.
2 For project with multiple RPs/IPPs provide the status of each RP/IPP progress separately.
1.10 Appoint external monitoring agency (as relevant): (i) recruitment schedule; (ii) TOR; (iv) baseline survey (v) reporting mechanism (vi) Action taken by management on reports.
NA
1.11 Reporting: (i) frequency; (ii) timeliness; (iii) identified issues; (iv) action taken and/recommendation.
Ready
2.0 PR/IPP IMPLEMENTATION
Consultation 2.1 Consultation: (i) responsibility;
(ii)stakeholders NA
Mapping and Assets Inventory 2.2 AP Identity cards & affected assets records:
(i) issuance and distribution of AP ID cards, (ii) detail measurements survey of affected assets and documentation
NA
2.3 Land acquisition activities: (i) maps of affected and relocation sites; (ii) acquisition & relocation schedule; (iii) coordination with the asset’s acquiring, transfer and
NA
2.4 Common property/ public assets: (i) final inventory; (ii) restoration plan and schedule; (iii) funding sources
NA
Compensation, Relocation and Rehabilitation 2.5 Payment of compensation and entitlements
(as stated in the RP): (i) schedule of payment; (ii) records/ receipts of payment
NA
2.6 Relocation of process ( relocation site readiness): (i) housing & associated facilities established; (ii) transfer of new land/plot/ house ownerships
NA
2.7 Provision of (a) income restoration, (b) additional assistance for vulnerable APs, (c) training, etc. (as stated in the RP): (i) per type of activities; (ii) schedule of implementation
NA
Monitoring and Reporting 2.8 Submission of the reports: (i) semiannual
monitoring reports; (ii) external monitoring and evaluation reports (as required); (iii) completion report
NA
2.9 Transfer of acquired assets to the acquiring agency
NA
E. Safeguards Loan Covenants Item No.
Covenant Status of Compliance
1 GOI and the State will ensure that all land and right of way required for investment program are made available in timely manner. Adequate compensation are provided prior to the signing of
No private land acquisition and resettlement issues are involved under this project. Hence RPs has not been prepared.
relevant civil works contracts, and involuntary resettlement is carried out in accordance with the resettlement framework (RF) and resettlement plans (RPs) agreed upon between the Government and ADB. An RP will be prepared for each sub project involving land acquisition and resettlement and shall be submitted to ADB for review and approval prior to award of any related civil works contracts.
2 GOI and the State will ensure that sub projects will not negatively impact on vulnerable groups, such as indigenous people. In the event of their involvement in any of sub projects, the GOI and the states will ensure the that the sub projects are carried out in accordance with the Indigenous People Development frameworks (IPDF) agreed up on between GOI and the states and the ADB and comply with ADBs policy on Indigenous People (1998)
No negative Impact on vulnerable groups
3 In the event any issues related to indigenous people arise in course of project implementation, the borrower and the state shall ensure to address those issues in accordance with the applicable laws and policies of the borrower, ADB’s policy on indigenous Peoples (1998) and the Indigenous Development Framework for the facility as agreed between the borrower, the state and ADB. In the case of any discrepancy between the borrower’s legislation and ADB’s policy, ADB’s policy shall prevail.
Agreed. However, no issues related to indigenous people are anticipated in course of execution.
4 GOI and State will ensure that all civil works contractors comply with all applicable labour laws, including those on occupational health and safety, and do not employ child labour as defined in national legislation for construction and maintenance activities. Priority work will be given to people from the area where the works are implemented and men and women will receive equal pay for work of equal value.
Adequate provision has been made.
5 Within six months of the Effective Date, the State shall have
Established
established a grievance reporting and redressal mechanism
Overall Status of Compliance
Not complied – Redressed
action & monitoring required
Complied with further
monitoring
Fully complied – no further
action
TRANCHE-II: SOCIAL SAEGUARD MONITORING CHECKLIST
Project Data
Name of Project & Subproject :
NERCCDIP WS- Tranche -2
Project Disbursement Status (%) :
Type of contract : Regular Design-Build
Combined
Safeguards Categorization
A B C
IR Yes IP No
F. Design and Engineering Status
Item Status (Y/N)
Follow up required
(Y/N)
Type of Required Action
Final detailed engineering design of the sub project completed
Y N Updated draft IR/IP New RP/IPP preparation
Changes in project design/ scope (occurred or envisaged)
N N Project re-categorization (IR/IP) IR/IP Impact assessment New RP/IPP preparation
G. Institutional Status Readiness
No Item Status (Ready/Not ready/NA)
Follow up required
(Y/N)
Completion Deadline
1 Mobilization of civil works contractor
Not ready Y September 2013
2 Mobilization of Project Supervision Consultant
Ready N 2015
3 EA’s Safeguards Unit with designated staff
Ready N
4 Recruitment of External Monitoring Agency
Ready (PMMC)
H. Safeguards Requirements
No Item Status (Ready/Not ready/NA)
Follow up required
(Y/N)
Completion Deadline
1 Safeguards monitoring included in the project progress report
Ready N
2 Final/ updated RP/IPP3 prepared and submitted
Ready N
3 Project’s Grievance Redress Mechanism established
Ready
4 Recruitment of third independent party for negotiated land acquisition
NA NA
5 Project’s ESMS (for FI) established
Ready
I. RP/ IPP Monitoring Checklist4
Item No.
Safeguards Related Requirements Status (Ready/Not ready/ NA)
Completion Deadline
Progress to Date/ Remarks
1.0 MANAGEMENT
Institutional and Financing Arrangements 1.1 Financing and budget : (i) safeguard office
and staff; (ii) RP/IPP cost Ready
1.2 Establish Safeguard Unit: (i) resettlement offices (ii) resettlement staff as in RP (iii) safeguards’ database (iv) facilities (v) safeguards training
Ready
Updating of DD/RP/IPP based on Detailed 1.3 Update DD/RP/IPP: (i) revise based on
DMS (ii) revise implementation schedule (iii) revise budget
Ready
1.4 Compensation rates: (i) approved by Government ; (ii) Adequate as per RP/RF; (iii) APs informed.
Ready
Disclosure and Grievance Redress 1.5 Disclose final/updated RP/IPP: (i) to the
APs in local language; (ii) in ADB website; (iii) in EA’s website
Ready
1.6 Disclose project activities to affected communities: (i) put up a project sign boards; (ii) distribution of project leaflets and
Ready
1.7 Grievance redress committees: (i) clear terms of reference; (ii) appointment decree; (iii) publicly disclosed among APs.
Ready.
3 Detail checklist for RP/IPP supervision provided in section D.
4 For project with multiple RPs/IPPs provide the status of each RP/IPP progress separately.
1.8 Grievance redress records: (i) list and numbers of grievances received; (ii) numbers of resolved issues; (iii) numbers of cases under GRC review; (iv) outstanding cases (filed to court)
Ready
Monitoring and Reporting Arrangements 1.9 Set up internal monitoring system : (i)
assessment oncapacity and staff requirements; (ii) criteria of safeguards assessment ; (iii) reporting mechanism
Ready
1.10 Appoint external monitoring agency (as relevant): (i) recruitment schedule; (ii) TOR; (iv) baseline survey (v) reporting mechanism (vi) action taken by management on reports.
NA
1.11 Reporting: (i) frequency; (ii) timeliness; (iii) identified issues; (iv) action taken and/recommendation.
Ready
2.0 RP/IPP IMPLEMENTATION
Consultation 2.1 Consultation: (i) responsibility;
(ii)stakeholders Identified; (iii) consultation and process; (iv) documentation
Ready 30-09-13
Mapping and Assets Inventory 2.2 AP Identity cards & affected assets
records: (i) issuance and distribution of AP ID cards, (ii) detail measurements survey of affected assets and documentation
Ready 30-09-2013
2.3 Land acquisition activities: (i) maps of affected and relocation sites; (ii) acquisition & relocation schedule; (iii) coordination with the asset’s acquiring, transfer and registration bodies
Ready 30th September 13
2.4 Common property/ public assets: (i) final inventory; (ii) restoration plan and schedule; (iii) funding sources
NA
Compensation, Relocation and Rehabilitation 2.5 Payment of compensation and entitlements
(as stated in the RP): (i) schedule of payment; (ii) records/ receipts of payment
Not Ready 15-10-13
2.6 Relocation of process ( relocation site readiness): (i) housing & associated facilities established; (ii) transfer of new land/plot/ house ownerships completed
NA
2.7 Provision of (a) income restoration, (b) additional assistance for vulnerable APs, (c) training, etc. (as stated in the RP): (i) per type of activities; (ii) schedule of implementation
NA
Monitoring and Reporting 2.8 Submission of the reports: (i) semiannual
monitoring reports; (ii) external monitoring and evaluation reports (as required); (iii) completion report
Ready
2.9 Transfer of acquired assets to the acquiring agency
Not Ready
J. Safeguards Loan Covenants Item No.
Covenant Status of Compliance
1 GOI and the State will ensure that all land and right of way required for investment program are made available in timely manner. Adequate compensation are provided prior to the signing of relevant civil works contracts, and involuntary resettlement is carried out in accordance with the resettlement framework (RF) and resettlement plans (RPs) agreed upon between the Government and ADB. An RP will be prepared for each sub project involving land acquisition and resettlement and shall be submitted to ADB for review and approval prior to award of any related civil works contracts.
RP has been prepared and uploaded in the ADB’s as well as EA’s web site. RP implementation is in progress, Compensation for loss of land and assets shall be paid before commencement of civil construction work at site.
2 GOI and the State will ensure that sub projects will not negatively impact on vulnerable groups, such as indigenous people. In the event of their involvement in any of sub projects, the GOI and the states will ensure the that the sub projects are carried out in accordance with the Indigenous People Development frameworks (IPDF) agreed up on between GOI and the states and the ADB and comply with ADBs policy on Indigenous People (1998)
No negative Impact on vulnerable groups
3 In the event any issues related to indigenous people arise in course of project implementation, the borrower and the state shall ensure to address those issues in
Agreed. However, no issues related to indigenous people are anticipated in course of execution.
accordance with the applicable laws and policies of the borrower, ADB’s policy on indigenous Peoples (1998) and the Indigenous Development Framework for the facility as agreed between the borrower, the state and ADB. In the case of any discrepancy between the borrower’s legislation and ADB’s policy, ADB’s policy shall prevail.
4 GOI and State will ensure that all civil works contractors comply with all applicable labour laws, including those on occupational health and safety, and do not employ child labour as defined in national legislation for construction and maintenance activities. Priority work will be given to people from the area where the works are implemented and men and women will receive equal pay for work of equal value.
Adequate provision has been made.
5 Within six months of the Effective Date, the State shall have established a grievance reporting and redressal mechanism
Established.
Overall Status of Compliance
Not complied – Redressed action & monitoring required
Complied with further
monitoring
Fully complied – no further
action
Annexure 4: Summary of IR and IP Check list
Name of the Work
Has involuntary
resettlement (IR) impact, a resettlement
plan (or corrective
action plan) is required
Has No IR impact, no
resettlement plan is
required
issues if any
Has Indigenous People (IP) impact, an indigenous people plan
(IPP) (or specific IP
action plan) is required
Has No IP impact, no
IPP/specific action plan is required.
issues if any
Construction
of Solid
Waste Land
fill, Leachate
Treatment
Plant and
Associated
Infrastructure
Works.
Yes NA Nil No NA Nil
Construction
of Service
Reservoirs for
Water supply
sub project at
lower Sichey
Yes NA Nil No NA Nil
Annexure 5: Summary of Policy and legal framework (Only relevant portions)
The policy framework and entitlements for the program as well as for this subproject are based on following national laws: The Land Acquisition Act, 1894 (LAA, amended in 1984), and the National
Resettlement and Rehabilitation Policy, 2007 (NRRP); state laws and regulations: The Sikkim State Land Acquisition (LA) Act 1894, the Sikkim Urban and Regional Planning Development Act (1998) and the Sikkim Land (Requisition and Acquisition) Act of(1977), 1960; ADB’s Safeguard Policy Statement, 2009 (SPS); and the agreed Resettlement Framework (RF).
Based on these, the core involuntary resettlement principles applicable are:
ix. land acquisition, and other involuntary resettlement impacts will be avoided or minimized exploring all viable alternative subproject designs
x. where unavoidable, time-bound Resettlement Plans will be prepared and APs will be assisted in improving or at least regaining their pre-program standard of living
xi. consultation with APs on compensation, disclosure of resettlement information to APs, and participation of affected persons in planning and implementing subprojects will be ensured
xii. vulnerable groups will be provided special assistance xiii. payment of compensation to APs including non-titled persons (e.g., informal
dwellers/squatters, and encroachers) for acquired assets at replacement rates xiv. payment of compensation and resettlement assistance prior to the contractor taking
physical acquisition of the land and prior to the commencement of any construction activities
xv. provision of income restoration and rehabilitation and xvi. establishment of appropriate grievance redress mechanisms The RP outlines the objectives, policy principles and procedures for land acquisition, compensation and other assistance measures for Affected Persons (APs). The Executing Agency (EA) and the Implementing Agency (IA) will have to endorse the Resettlement Plan prior to Project Appraisal. The RPs shall be disclosed to the affected persons (APs) and submitted to ADB for review and approval prior to commencement of any civil works. Compensation and other assistances will have to be paid to APs prior to any physical or economic displacement of affected households.
Annexure 6: LAND RECORD - TO BE ACQUIRED
Scope of Work Proposed in Tranche-II and Resettlement Impacts
SNo Location WS SWM Involuntary Resettlement Impact
1 Proposed Reservoir-1 (at existing Press tank site )
Yes NA No
2 Proposed Reservoir-2 (adjacent to Existing Bazar Tank site )
Yes NA No
3 Proposed Reservoir-3 (at lower Sichey )
Yes NA Yes
4 Proposed Reservoir-4 (adjacent to existing Enchey Tank area )
Yes NA No
5 Proposed Reservoir-5 (at TNSS area )
Yes NA No
6 providing water supply to 13 wards of GMC (out of 15 wards except Burtuk and Chandmari)
Yes NA No
7 Sanitary land fill site and SW processing plant at Martham
NA Yes Yes
Annexure 7: LIST OF AFFECTED PERSONS
LIST OF AFFECTED PERSONS
Sl No Name of the APs APs with Photo Identity
1 PemalamuTamang
2 Bhagi Sherpa
3 PavitraChettri
4 AjitTamang
5 Suk BahadurRai
6 Ashok Tamang
7 NandlalPradhan
Sl No Name of the APs APs with Photo Identity
8 Mani Kumar Rai
9 Kumar Rappal
10 Sanjay Rai
11 Md.ZakirHussain
12 BiplobHalder
13 SushmaChettri
14 LalBahadurDorji
Sl No Name of the APs APs with Photo Identity
15 Uttar Kumar Dorji
16. Guman Singh Subba
17. Kumar Chettri
18. BhimBahadurSubba
19. Laden Lepcha
20. ParimalGhosh
Sl No Name of the APs APs with Photo Identity
21. Dil Kumar Subba
22. NagendraRai
23 Tilak Raj Subba
24 ShivalallSubba
25. Karma BahadurSubba
26. SitaChettri
27. SukhbirLimboo
Sl No Name of the APs APs with Photo Identity
28 Thakur Kumar bassnet
29 Raj Kumar pradhan
30 LallbahadurLimbu
31 Pempa Sherpa
32 Adhirpaul
33 ShavitraLepcha
34 NirBahadurChettri
Sl No Name of the APs APs with Photo Identity
35 Khetteynabihbi
36 ShyamSundarPanwa
37. JitanThalabda
38. Md. Bagamia
Annexure 8: RESETTLEMENT BUDGET AND FINANCIAL PLAN
(Solid Waste Management sub project)
The resettlement cost estimate for the Gangtok SWM subproject includes resettlement
assistance, as outlined in the entitlement matrix, support cost for RP implementation and
contingency provision amounting to be 5% of the total cost. The state government will be
responsible for releasing the funds for resettlement in a timely manner. The total
resettlement cost for the subproject is INR 2.34 million. The resettlement cost items and
estimates are outlined in Table
Resettlement Costs
Srl. No Item Unit Quantity
Unit Cost
Amount
1 Assistance for Relocation & Transfer
Loss of Income Livelihood5 @ Rs.170 per day for 3 months
38 15300 5,81, 400
Additional Assistance for Vulnerable HH
Lump Sum 15 30,000 4,50,000
Sub Total Item 1 10,31,400 2 Administrative &
Implementation costs
Implementing NGO Lump Sum 500,000 SIPMIU Social team Lump sum 500,000 Monitoring Lump Sum 200,000 Sub Total Item 2 12,00,000
3 Total 22,31,400 4 Contingency 5% 1,11,570 5 Grand Total 23,42,970
Million Rupees 2.34
RESETTLEMENT BUDGET AND FINANCIAL PLAN (WATER SUPPLY)
The resettlement cost estimate for the Gangtok water supply subproject includes
compensation for land, stair case, resettlement assistance, and RP implementation support
cost as outlined in the entitlement matrix, support cost for RP implementation and
contingency provision amounting to be 10% of the total cost. The state government will be
responsible for releasing the funds for resettlement in a timely manner. The total
5 The amount is based on the average per day income as derived from the census and socio economic survey
resettlement cost for the subproject is INR 6.98 million. The resettlement cost items and
estimates are outlined in Table.
Resettlement Costs
Sl. No.
Item Unit Qty Unit Cost Total Cost
A. Compensation 1 Private Land Value Sqmts 400 11,900 47,60,000 2 Stamp Duty
&Registration cost 5% of Basic land cost
238,000
3 Tree Numbers 8 2,000 16,000 4 Solatium 30% of
Basic land cost
14,28,000
5 Interest 12% of Basic land cost
1 year 5,71,200
6 Compensation for structure/Stair case
Numbers 2 1,00,000 2,00,000
Sub-Total of A 72,13,200
B. R&R Assistance – Additional Assistance to Vulnerable Group
1 Loss of livelihood Allowance Allowances for temporary disruption of livelihood for 15 households and 10 workers temporary disruption for 30 working days a month
Days 15+10*30=750 Rs.170/perday 1,27,500
2 Vulnerable Allowance
Nil Nil
Sub-Total of B 1,27,500-
C. Support for RP Implementation
1 Engaging NGO for RP Updating & Implementation
L/s 1,50,000
2 Social and Resettlement Team of SIPMIU including Logistics
L/s 1,00,000
3 Training L/s 50,000 4 Monitoring L/s 1,50,000
Sub-Total of C 4,50,000 Total 77,90,700
Contingencies @ 10%
7,790,70
TOTAL 85,69,770 Say Rs 8.56 million
ANNEXURE 9: DOCUMENTARY PROOFS
Provide proof of any training, Workshop, public consultations, land acquired documents etc
conducted during the period January to June, 2013 only
North East Region Capital Cities
Development Investment
Program (NERCCDIP)
REPORT OF
WORKSHOP ON
PUBLIC PARTICIPATION,
COMMUNITY AWARENESS AND
GENDER SENSITIZATION FOR
COUNCILLORS AND SELECTED
STAKEHOLDERS
IN GANGTOK MUNICIPAL CORPORATION
18th June, 2013 - Gangtok Municipal
Corporation Conference Hall
1. Project Introduction
The Govt. of India is pursuing the implementation of the Infrastructures development for the
city capitals of North Eastern States under NERCCDIP with the financial assistance from the
ADB since 2009. The Gangtok Municipal Corporation (CMG) is one among the cities taken up
for the program implementation in terms of improving the water supply, sewerage and solid
waste management.
A sum of Rs. 220 Crores is earmarked for the implementation of the project within a period of
three years. The tranche 1 works includes, providing water supply distribution to Chandmari
and Burtuk wards. Under this, construction of water tank for a capacity of 11.55Lakh litter
near AIR road, pump room near Selep, nine numbers BP (Break Pressure) tanks and laying of
distribution pipes lines for a length of 41 KM. The implementation of the tranche -1 started in
the month September, 2011 and would be completed by September, 2013.
The works programmed under tranche -2 is Solid Waste Management System which includes
door to door collection, segregation; composting of bio degradable wastes, sanitary land
filling of inert materials, and recycling of recyclable wastes for which a compost plant,
sanitary landfill and leachate treatment plant are required. This work includes the
construction of all the required components and it is programmed to be completed within a
period of 24 months.
Providing underground sewerage system for Chandmari and Thathenchen area is envisaged
under tranche -3 works. Preparation of DPR is under progress for this work.
As part of information dissemination of project activities and ensuring public involvement a
sensitisation programme for GMC councillors and selected NGO representatives are
conducted on 18th June, 2013, 1.30 PM at GMC conference hall.
Out of 15 councillors 13 have attended the workshop. Apart from this 5 participants
represented various NGOs and 3, the related department. Attendance sheet is attached as
annexure -1.
2. Objectives of the Workshop
The primary objectives of the workshop was to sensitize the Councillors and selected NGO
representatives about the project, Importance of public participation, gender sensitisation
and IEC activities under this project
3. Proceedings of the Workshop
This workshop was inaugurated by the Hon’ble Mayor. At the outset of the workshop the Project Director, SIPMIU and the Additional Secretary to Govt, UD & HD, Sikkim welcomed the
gatherings. In his welcome address he explained the project objectives and importance of
the workshop. Further he requested the Hon’ble mayor to inaugurate the workshop and give his inaugural address.
While inaugurating the workshop, Hon’ble Mayor extended his whole hearted support to the project implementation. He also suggested involving the respective councilors in every stage
of the project implementation.
The Specialists from the Design Supervision and Management Consultant (DSMC) and
Institutional Development Consultant (IDC) have explained the project activities taken up
under NERCCDIP in Gangtok through Power Point presentations and interactive discussions
with the participants. Copy of power point presentation on various activities is attached as
annexure -3 of this report. Participants were clarified of their doubts during the interactive
session. Snap shots of the workshop are attached as annexure -2 of this report.
As part of involving public at large in the implementation of the project activities, it was decided to
convene ward level meetings, mainly focusing on solid waste management system. Workshop was
concluded with a vote of thanks by
Contents
Title No Title Page
1 Project Introduction 1
2 Objective of the Workshop 1
3 Proceeding of the workshop 1
Annexures
Annexure
No. Annexure Name
1 Attendance
2 Snap shots of workshop.
3 Copy of power point presentation.
\
Annexure 10: land Acquired Document for Proposed Reservoir -3 at Lower Sichey