Environmental Monitoring Report This report has been submitted to ADB by Program Management Unit, Government of Uttarakhand, Dehradun and the Asian Development Bank and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Project Number: 40648-034 December 2017 Period: January 2017 – June 2017 IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Submitted by: Program Management Unit, Government of Uttarakhand, Dehradun

Upload: others

Post on 17-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

Environmental Monitoring Report

This report has been submitted to ADB by Program Management Unit, Government of Uttarakhand, Dehradun and the Asian Development Bank and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Number: 40648-034 December 2017 Period: January 2017 – June 2017

IND: Infrastructure Development Investment Program for Tourism - Tranche 3

Submitted by: Program Management Unit, Government of Uttarakhand, Dehradun

Page 2: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive
Page 3: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

1

Semi – Annual Environmental Monitoring Report

Loan No: 3223 IND Period: Jan to June 2017

IND: Infrastructure Development Investment Programme for Tourism, Uttarakhand (Tranche –III)

Prepared by Dept. of Tourism, Government of Uttarakhand for Asian Development Bank December, 2017

This Semi – Annual Environmental Monitoring Report is a document of the borrower. The views expressed

herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be

preliminary in nature.

Page 4: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

2

Table of Contents

1. INTRODUCTION ........................................................................................................................................................................................................................................................................................................................................................................................................................................................ 5555

2. COMPLIANCE STATUS ........................................................................................................................................................................................................................................................................................................................................................................................................ 33333333

3. COMPLIANCE STATUS WITH NATIONAL/ STATE/ LOCAL STATUTORY ENVIRONMENTAL

REQUIREMENTS ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 34343434

4. COMPLIANCE STATUS WITH THE ENVIRONMENTAL COVENANTS AS STIPULATED IN THE

LOAN AGREEMENT .................................................................................................................................................................................................................................................................................................................................................................................................................................................... 36363636

5. COMPLIANCE STATUS WITH ENVIRONMENT MANAGEMENT AND MONITORING PLANS AS

STIPULATED IN THE ENVIRONMENTAL DOCUMENTATION AS AGREED WITH ADB. ........................................................ 37373737

6. STATUS OF IMPLEMENTATION OF ENVIRONMENT MANAGEMENT PLAN ............................................................................................ 40404040

7. APPROACH & METHODOLOGY ENGAGED FOR ENVIRONMENTAL MONITORING OF THE

PROJECT .................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................... 83838383

8. MONITORING OF ENVIRONMENTAL RECEPTORS/ ATTRIBUTES ................................................................................................................................................ 83838383

9. IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN ................................................................................................................................................................ 85858585

10.1 INSTITUTIONAL ARRANGEMENTS FOR EMP IMPLEMENTATION ................................................................................................................................................ 97979797

10. PUBLIC CONSULTATION DETAILS .................................................................................................................................................................................................................................................................................................................... 99999999

11. IMPLEMENTATION OF GRIEVANCE REDRESS MECHANISM .................................................................................................................................................... 103103103103

12. ANY OTHER ENVIRONMENTAL ASPECTS, IMPACTS OBSERVED DURING

IMPLEMENTATION WHICH WERE NOT COVERED EARLIER ................................................................................................................................................................................................ 103103103103

13. DETAILS OF COMPLAINTS RECEIVED FROM PUBLIC AND ACTION TAKEN THEREOF TO

RESOLVE ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 104104104104

14. FOLLOW UP ACTIONS AND CONCLUSIONS .................................................................................................................................................................................................................................................... 104104104104

Page 5: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

3

List of Table

TABLE 1: PROJECT PROGRESS IN THE REPORTING PERIOD TILL JUNE, 2017 ............................................................................................ 7777

TABLE 2: WORK DETAILS AND RISKS FOR SUB PROJECTS ............................................................................................................................................................................................................ 8888

THE MAIN SUB-PROJECT COMPONENTS INCLUDE THE FOLLOWING: ........................................................................................................................................ 29292929

TABLE 3: STATUS OF COMPLIANCE WITH EARF/ADB PROCEDURES ............................................................................................................................................ 33333333

TABLE 4: STATUS OF ENVIRONMENT, FOREST AND OTHER CLEARANCE................................................................................................................ 34343434

TABLE 5: STATUS OF COMPLIANCE WITH ENVIRONMENTAL LOAN COVENANTS .................................................................... 36363636

TABLE 6: EMP IMPLEMENTATION STATUS ............................................................................................................................................................................................................................................................................................................ 37373737

TABLE 7 (I): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM INFRASTRUCTURE IN KARTIKEYA SWAMI CIRCUIT (LOT-1) (TUNGESHWAR&DURGADHAR

TEMPLE) ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 41414141

TABLE 7 (II): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM

INFRASTRUCTURE IN KARTIKEYA SWAMI CIRCUIT (LOT-2) (KARTIEKEYA SWAMI TEMPLE) .... 44444444

TABLE 7 (III): EMP MONITORING STATUS CHART- RURAL TOURISM IN DISTRICT TEHRI AND

UTTARKASHI ............................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 46464646

TABLE 7 (IV): EMP MONITORING STATUS CHART- CONSERVATION OF CULTURAL HERITAGE

AND URBAN PLACE MAKING IN NAINITAL LOT-1........................................................................................................................................................................................................................................................................ 52525252

TABLE 7 (V): EMP MONITORING STATUS CHART- RESTORATION AND ADAPTIVE REUSE OF

ALMORA FORT (RANI MAHAL) .................................................................................................................................................................................................................................................................................................................................................................................... 56565656

TABLE 7 (VI): EMP MONITORING STATUS CHART- RESTORATION AND ADAPTIVE REUSE OF

CHAMPAWAT FORT (BANASUR) ........................................................................................................................................................................................................................................................................................................................................................................ 60606060

TABLE 7 (VIII) : EMP MONITORING STATUS CHART- CREATION OF PEDESTRIAN ROUTE FOR

PILGRIMS AND TOURISTS IN HARIDWAR .................................................................................................................................................................................................................................................................................................................... 65656565

TABLE 7(IX): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM

INFRASTRUCTURE IN SEM MUKHEM ................................................................................................................................................................................................................................................................................................................................................ 71717171

TABLE 7(X): EMP MONITORING STATUS CHART- DEVELOPMENT OF TRADITIONAL MEDICINE

AND YOGA TRAINING CENTRES ........................................................................................................................................................................................................................................................................................................................................................................ 79797979

Page 6: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

4

TABLE 8: PARAMETERS AND METHODOLOGY FOR ENVIRONMENTAL MONITORING ............................................ 84848484

TABLE 9 (I): IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN- FOR PROJECTS

UNDER DSC KOTDWARA .................................................................................................................................................................................................................................................................................................................................................................................................................... 85858585

TABLE 9 (II): IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN- FOR PROJECTS

UNDER DSC BHIMTAL ........................................................................................................................................................................................................................................................................................................................................................................................................................................ 90909090

TABLE 10(I): PUBLIC CONSULTATION MEETINGS FOR TRANCHE III SUB-PROJECTS UNDER

DSC DEHRADUN ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 99999999

TABLE 10(II): PUBLIC CONSULTATION MEETINGS FOR TRANCHE III SUB-PROJECTS UNDER DSC KOTDWAR .................................................................................................................................................................................................................................................................................................................................................................................................................................................................... 100100100100

TABLE 10(III): PUBLIC CONSULTATION MEETINGS FOR TRANCHE III SUB-PROJECTS UNDER

DSC BHIMTAL ................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 103103103103

ANNEXURE 1: PHOTO ILLUSTRATION ................................................................................................................................................................................................................................................................................................................................ 105105105105

ANNEXURE: 1(I): PHOTO ILLUSTRATION OF WORK PROGRESS- DSC DEHRADUN ........................................................ 105105105105

ANNEXURE: 1(II): PHOTO ILLUSTRATION OF WORK PROGRESS- DSC KOTDWAR ........................................................ 110110110110

ANNEXURE: 1(III): PHOTO ILLUSTRATION OF WORK PROGRESS- DSC BHIMTAL ................................................................ 112112112112

RESTORATION AND ADAPTIVE REUSE OF PITHORAGARH FORT PHASE II .................................................................................................... 115115115115

ANNEXURE 2: CONSULTATION RECORDS & PHOTOGRAPHS .................................................................................................................................................................................... 116116116116

ANNEXURE 3: NOCS AND RELATED CORRESPONDENCE ........................................................................................................................................................................................................ 127127127127

ANNEXURE 3(I): SITE VISIT NOTE OF TUNGNATH TEMPLE BY ASI ........................................................................................................................................................ 127127127127

ANNEXURE 3(II): FOREST LAND CLEARANCE FOR DEVELOPMENT OF FACILITIES AT TANKI CHEENA TREK (.075 HEC) UNDER NAINITAL SUB PROJECT ............................................................................................................................................................................................ 132132132132

ANNEXURE 5: OFFICE ORDER OF GRIEVANCE REDRESS COMMITTEE AT PIU AND PMU

LEVEL ............................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 134134134134

ANNEXURE 4: OFFICE ORDER OF GRIEVANCE REDRESS COMMITTEE AT PIU AND PMU

LEVEL ............................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 135135135135

ANNEXURE 5: SUMMARY OF WORKSHOP ORGANIZED BY PMU .................................................................................................................................................................... 137137137137

Page 7: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

5

1. Introduction

Overall Project Description

1. The Infrastructure Development Investment Program for Tourism Financing Facility (the Facility) will

develop and improve basic urban infrastructure and services in the four participating states of Himachal

Pradesh, Punjab, Uttarakhand and Tamil Nadu—to support the tourism sector as a key driver for

economic growth. It will focus on: (i) strengthening connectivity to and among key tourist destinations;

(ii) improving basic urban infrastructure and services, such as water supply, road and public transport,

solid waste management and environmental improvement, at existing and emerging tourist destinations

to ensure urban amenities and safety for the visitors, and protect nature and culture-based attractions.

Physical infrastructure investments will be accompanied by: (iii) capacity building programs for

concerned sector agencies and local communities for better management of the tourist destinations and

for more active participation in the tourism-related economic activities, respectively.

2. The proposed Project targets enhanced economic growth and provision of livelihood opportunities for

local communities through tourism infrastructure development with a focus on preservation and

development of natural and cultural heritage and incidental services. The Project supports the state of

Uttarakhand to develop the tourism sector as a key driver for economic growth.

3. The Executing Agency (EA) for the Investment Program is Dept. of Tourism, Govt of Uttarakhand. The

Loan Agreement and Project Agreement for the IDIPT, Uttarakhand is 3223-IND. Project

Implementation Unit have been established in three towns respectively (Dehradun, Bhimtal and

Kotdwar) for implementation of sub-projects. Design and Supervision Consultants (DSCs), has already

been established in three towns for designing the Infrastructure, managing the tendering of Contractors

and supervising construction, and providing support to the PIUs.

Outputs of the Project

4. The outputs of the Project are as follows:

Component 1: Urban Infrastructure and Service Improvement

Component 2: Improved connectivity

Component 3: Quality Enhancement of Natural and Cultural Attractions

Component 4: Greater participation by local communities

Component 5: Capacity Development, Community Participation and Project Management

Page 8: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

6

Environment Category:

5. The project under IDIPT was categorized as Environment Category “B”, according to ADB’s Safeguard

Policy Statement (2009). All the subprojects under execution have been categorized as category 'B'.

Environment Performance Indicators, if any:

6. For effective monitoring, selected environmental parameters have been identified as indicators which

may be qualitatively and quantitatively measured and compared over a period of time in order to

assess/ ensure the compliance to environmental management plans (EMPs). The environmental

performance indicators selected are physical, biological and social characteristics identified as most

important in affecting the environment at critical locations at all the sub projects. The parameters

identified as performance indicators are:

1. Compliance with environmental management and monitoring plan

2. Compliance to State/ National environmental regulations.

3. Monitoring of ambient air quality, water quality and noise levels and comparison with baseline

environmental quality and State/ National Standards.

Overall project progress, agreed milestones and Implementation schedule

7. Construction works for the following sub projects are in progress and shown in Table 1.

Page 9: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

7

Table 1: Project Progress in the Reporting Period till June, 2017

SI. No.

Package Ref No.

General Description Goods or Works

Contract Signing Date and Start

date Name of the Contractor Contract Value

Contract period

1 UK/IDIPT-III/ DDN/01 Lot1

Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-1) (Tungeshwar & Durgadhar Temple)

LOA 22.01.16 Work started 26.02.2016

M/s Aaradhya Engineers & construction pvt Ltd.,2nd Tulsi Vihar, Hardiwar road ,Post –Virbhadra ,Rishikesh (UA)

INR 7.59 Cr.

24 months

2 UK/IDIPT-III/ DDN/02

Development of Tourism Infrastructure in Kartikeya Swami Circuit (Kartikeya Swami Temple)

LOA issued 23.05.16 Work started 07.07.2016

M/S APS Structures Private Ltd,Fort Sports complex ,Tara Hall,Mussorie

INR 3.97 Cr.

24 months

3 UK/IDIPT-III/DDN/03

“Conservation & Development of Rural Tourism Sites of Rudraprayag, Chamoli and Uttarkashi Districts of Uttarakhand”

LOA issued 23.05.16 Work started 02.08.2016

M/S Navya Associates in JV with Agrawal Brothers INR 15.26 Cr. 24 months

4 UK/IDIPT/III/BHT/01

Conservation of Cultural Heritage and urban place making in Nainital Lot-1

19-10-2015

M/s Simplex Project Limited 407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India

INR 38.52Crore 24 months

5 UK/IDIPT/III/BHT/03

Restoration and adaptive reuse of Almora Fort (Rani Mahal)

19-10-2015

M/s Simplex Project Limited 407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India

INR 29.90 Crore 24 months

6 UK/IDIPT/III/BHT/05

Restoration and adaptive reuse of Champawat Fort (Banasur)

19-10-2015

M/s Simplex Project Limited 407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India

INR 15.53Crore 24 months

7 UK/IDIPT-III/ KOT/01

Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

22/07/2015 M/s SS InfratechJv, Tikola Nagar, Roorkee, Haridwar 247670

INR 22.38 Cr.

24 months

8 UK/IDIPT-III/KOT/02

Development of Tourism Infrastructure in Sem Mukhem

22/08/2015 M/s Mangalam and Construction Company in JV with Sunil Garg and Company, Kesarganj, Meerut.

INR 10.18 Cr.

24 months

Page 10: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

8

8. Work Details In the reporting period has been shown in Table 2.

Work progress of 10 packages is reported in the given table. Photographs showing work progress are provided in Annexure 1.

Table 2: Work Details and Risks For sub projects

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

UK/IDIPT-III/

DDN/01 Lot1

Development of

Tourism

Infrastructure In

Kartikeya Swami

Circuit (Lot-1)

(Tungeshwar,

Durgadhar

Temple)

Aradhya

Engineers

Durgadhar Temple precinct

Upgradation of infrastructure around the approach area of the temple, including drinking water facilities and sanitation

Parking facility and vehicular approach along with adjoining retaining walls

Solid waste management

Pathway development with railings & protection wall wherever necessary and signage and seating and lighting

Temple entrance arch

Improvement of the temple complex in terms of restructuring of the newly added temporary structures and overall landscaping to facilitate better movement and space for gathering of pilgrims and

22.01.2016 21.01.2018 DURGADHAR:-

Main Temple: -

Temple dome

work in progress

after completion

of temple frame.

Dharamshala: -

Color washing,

electrical works &

final touch work

is in progress.

Toilet: - Truss

work completed

roofing to be

started

CC Road,

43.00% Not

visualized till

now

Nil Frequent Weather

disturbances

during monsoon

season may delay

the work progress

9 UK/IDIPT/III/BHT/07

Restoration and Adaptive Reuse of Pithoragarh Fort Phase II

05/07/2016 M/S COX Infratech Private Limited in JV with Conaech Associates

INR 27.11 Cr.

24 months

10 UKIDIPT/III/GEN/03

Development of Traditional Medicine and Yoga Training Centers

08/03/17 M/s Bansal Construction INR 3.76 Cr. 24 months

Page 11: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

9

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

tourists

Lodging facilities with rooms and dormitories and toilet block at the rear side of the temple complex and a langar hall

Area confinement with edge wall , viewing decks etc

Restoration of Temple premises Construction of C.C road(main road to Temple,400 mtr length with drain

Development of Solar lighting and Fire Fighting work.

Capacity building for temple committee members for O&M activities.

Tungeshwar Temple precinct

Entrance area development with appropriate signage

Development of the 1.5km long pathway with railing to the main temple, increase in width and edge protection wherever required.

Seating arrangements , viewing decks and toilet facilities

Signage along the pathway and Temple premises.

Improvement in the temple precinct

Parking & Railing

work:- Work

Completed .

TUNGESHWAR:

Dharamshala:-

1st floor roof slab

completed &

brick work to be

started.

Page 12: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

10

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Construction of entrance gate

Lodging facilities and langar hall

Development of Solar lighting and Fire Fighting work

Improvement in the drinking water facility for the approach areas

Capacity building for temple committee members for O&M activities.

UK/IDIPT/III/DD

N/02

Kartikeya Swami

Temple

M/s APS

Structure

Pvt.

Ltd ,Fort

Sports

Complex,

Tara Hall,

Mussorie

Civil Work Pedestrian Pathway Sitting Arrangement Railing at Temple Premises Pathway Renovation Existing Dharamshala Rest Shelter Retaining & Breast Walls View Point Pre-fabricated Small Size Toilet Entrance Gate Renovation of Lodging Facility Furniture for Lodging Facility Camping Site development Renovation of Main Temple Solar Lighting Fire Fighting works Additional items Renovation of Existing Toilet Toilet Block Provision of Pathway Covering Shelter

07.07.16 06.07.18 Retaining wall and protection wall completed

Entrance Gate Structure completed and final finishing work is in progress.

Pathway and Drain: - Pathway from Dharamshala to Bhaira Nath Temple completed & near entrance gate work is in

35.00% Appropriate

measures

has been

taken for

fulfillment of

the

objectives

Page 13: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

11

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Directional Signage Informative Signage Solar Power Plant (2KW) Hill View location pointer model Electrical Work (Internal/External) From Provisional Sums Water Supply Connection Electricity Connection Rain Water Harvesting Capacity building for Temple Committee members for O&M activities

progress.

Staircase to Temple:- Widening and new alignment for straightening for staircase & steps work in progress.

Due to Mela festival & continues rain work slowed & procurement of material for renovation of temple and staircase work in progress.

Page 14: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

12

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

UK/IDIPT/III/DD

N/03

Rural Tourism

M/s Navya

Associates

JV with M/s

Agarwal

Brothers

Name of Village

Proposed Hardware Components

Tungnath Restoration of Temple through removal of incongruent additions and preservative coating and foundation retrofitting of main temple

Removal and reconstruction of bulged retaining walls

Shivalinga water/Rain water disposal system of the temple/premises

Up gradation of main entrance gateway

Improvement of pathway upto new gateway structure

Kaviltha Upgradation of Pathway

Construction of Guest House

Renovation of KalidasSmarak& Community centre

Repair of existing Parking facility

Repairing of Existing Water source

Renovation of PanchayatBhawan

02.08.16 01.08.18 1. Tungnath:-

Reconstruction of

retaining walls in

progress. Joint

site visit of DSC

Conservation

expert with Joint

Director, ASI,

New Delhi on 4th

June-17 including

CBRI Roorkee

for soil

investigation &

proper drainage.

Soil test and

structure stability

to be carried out

by CBRI

,Roorkee)

(Annexure 3( i)

2.Kaviltha:

Guest house

foundation work

include grade

beam completed

12.00%

Page 15: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

13

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Landscaping

Informative Signage

Directional Signage

Renovation of Existing gate and Railing

Furniture For Kaviltha Guest House and Kaviltha Library

Solar light and Water Heater System

Phalasi Up gradation of Pedestrian Pathway and providing retaining &breast Wall

Construction of Toilet Block

Directional and Informative Signage

Solar Lighting

Railing

Sitting Benches

Durgadhar (Bora)

Up gradation of Pedestrian Pathway and covering shelter

Construction of Toilet Block

Directional and Informative Signage

Solar Lighting

Railing and Sitting

and column in

super structure

work in progress.

Pathway and

other finishing

work is in

progress.

Kalidas

Smarak:- Work

not started due to

rain & to be

started by

contractor in

August-17

3.Phalasi:-

Plastering work,

plastering of toilet

block and

electrical fitting

work is in

progress.

4.Bora:-

Retaining wall

and pathway

work started by

contractor but

villagers stopped

Page 16: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

14

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Benches

Renovation of Existing Panchayatbhawan

Harshil

Up gradation of Pedestrian Pathway and Pathway Covering Shelter and Construction of Retaining Walls

Upgradation of existing Sitting Arrangement

New Railing

Renovation of Existing Entrance Gate

Renovation of Existing Rain Shelter, Temple Premises, Parking Area and Water Tank

Informative and Directional Signage

Beautification of Existing Helipad

Protection wall for Camping Site

Solar Lighting

Mukhwa Upgradation of existing Pedestrian Pathway and Construction of Pathway Covering Shelter, retaining and breast wall

New Sitting Arrangement

the work for

widening the

existing pathway

for motor able

with CC road .

5.Harshil:-

Breast wall work

is in progress at

Bagori

6. Mukhwa:

Plastering work

at Bhogshala

work is in

progress.

Page 17: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

15

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Renovation of Existing PanchayatBhawan& Temple Premises

Construction Parking facility

Entrance Gate

Toilet Block -

Directional and Informative Signage

Railing

Kanakchori (Pogatha)

Upgradation of Pedestrian Pathway and Pathway Covering Shelter

Retaining & Breast Wall

Toilet Block - Small

Directional and Informative Signage

Solar Lighting

Sitting Bench

Niti Construction of Community Centre

Renovation of open air theater and compound wall

Construction of Parking facility

Upgradation of gram panchayatbhawan

Directional and Informative Signage

Plastering work

at toilet work in

progress and

parking work in

progress.

Kanakchori

Retaining wall

completed ,

pedestrian

pathway

completed and

solar lights

installation in

progress

Page 18: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

16

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

upgradation of village Pathway with KC drain

Seating Benches

Toilet

Upgradation of existing View Points

Provision of Dust Bins

Solar Light

Erection of Glass House (View points)

Lata No Hardware components proposed

UK/IDIPT/III/BH

T/01 Lot 1

Conservation

of Cultural

Heritage and

urban place

making in

Nainital Lot-1

M/s

Simplex

Project

Limited

407,

Skipper

Corner, 88

Nehru

Place, New

Delhi -

110019,

India

Proposed Scope as per IEE (DPR)

1. Promenade development around Nainital lake

• Mechanical car parking

• Development of Children’s park 2. Enhancement of Nainital Lake

Heritage Precinct

• Restoration of Municipal Corporation, DSA Pavilion, New Club

• Development of Gandhi gram, Takula

• Façade improvement of Dam wall at Mallital,

• Façade restoration and

19.10.2015 18.10.2017 1.Basement Area Side upto to 2nd floor roof casting completed 2. 3rd Floor roof shuttering work in progress 3. Column work upto 2nd & 3rd floor 100 % completed. 4. Brick work- a. Basement area 100 %, b. Ground Floor -90 % , c. 1st Floor 80 % completed. 5.

11.29% Nil Cooperation of

LDA is integral for

fulfillment of

project objectives

Page 19: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

17

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

illumination of Govt. owned heritage buildings (Bishop Shaw, Municipal Library, Catholic church, Methodist Church

• Provision of Public Amenities and facilities at appropriate location in Nainital area precinct

• Integrated signage and interpretation in lake precinct

• Reclamation of public and open spaces in the lake precinct

• Removal and demolition of obsolete, damaged street furniture and structures

• Rickshaw stand

• Integrated stone paved pedestrian access and pathways with adequate plantation

• Street furniture

• Weather shelters

• Heritage type railing and integrated lake edge lighting along lake edge

• Improvement of Heritage Trekking Trail

o Nature Trail 1 - Land's End & Tiffin Top

o Nature Trail 2 - Naina Peak (Trail 1- Tiffin Top – Lands End Trail: Length 4.5 Km From Ayar Jungle Camp to

Non Basement area- All work complete upto plinth level, staircase work (shuttering & casting etc) on progress, column work upto 1st floor complete, all PCC work upto plinth level completed.

DSA flat-Tile work, electrical Work and painting work in progress

Methodist church-Dismantling of inside plaster, making plaster in wall and wooden ceiling work in progress

Catholic Church-

Page 20: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

18

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Lands End + 1.17 Kms from LandsEnd to Barapatthar Trail 2 – TankiNaina Peak: Length 3 Km starting at Tanki)

Repair of damaged pathways Rough stone paving of steep, slushy stretches Provision of railings at outer sides in vulnerable stretches Wayside furniture at pause points Rain shelters at viewing points Camping sites Provision of portable toilets at appropriate points [where water pipeline already available] Signages [informative and regulatory]

Out of above proposed scope in the IEE (based on DPR) only the components listed below are being taken up:

Restoration of

• Catholic Church

• Methodist church

• Bishop Shaw

• Library Building

• Municipality Building

• DSA Flat

• Gandhi Ashram- Takula

GRC cladding work out site, railing work and electrical work in site in progress,

Gandhi Ashram-Stone masonry work in approach road in progress

Page 21: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

19

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

• New Club

• DSB College Chapel

• Treatment of Dam Wall

• Repaving of Upper Mall

• Rickshaw Stand

• Lake Front Development

• Park Development

• Railing & Band Stand

• Construction of Toilets in Nainital- Cheena baba and National Hotel

• Improvement of High mass light Electricity

• Nature Heritage Trail: o Wayside furniture at pause

points o Rain shelters at viewing points o Camping sites o Provision of portable toilets at

appropriate points (water pipeline available)

o Signages (informative &regulatory)

Mechanical car parking component shall

be taken up in separate package

UK/IDIPT/III/BHT/01 Lot 2

UK/IDIPT/III/BH

T/03

Restoration

M/s

Simplex

Project

Scope as per IEE: Restoration of the historic sites: Ram Shila Temple and the MallaMahal or Fort Nanda Devi Complex

19-10-2015 18-10-2017 1.Basement Area

Side upto to 2nd

floor roof casting

34.53% No Change

Page 22: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

20

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

and adaptive

reuse of

Almora Fort

(Rani Mahal)1

The subproject

was bid out in

02 packages

(i) Rani Mahal

UK/IDIPT/III/BH

T/03

(ii)

MallaMahalUK/I

DIPT/III/BHT/06

Limited

407,

Skipper

Corner, 88

Nehru

Place, New

Delhi -

110019,

India

1.Revitalization of the entire precinct as a public space for experiencing regional history and culture, through creation of facilities such as:

• Develop cobblestone-paved courtyard as a performance arena.

• Create a Museum on Kumaon culture in the main building of the MallaMahal

• Create a Himalayan Art Gallery and nature interpretation centre in the Rani Mahal,

• Restoration of the historic site of Ram Shila Temple

• Creation of craft demonstration areas.

• Removal or concealment some buildings through strategic landscaping and foliage coverage of structures

• Create facilities in Almora town to enable it to emerge as a complete destination

• Improve all three access routes that lead up to the fort and temple

• Improve accessibility, especially for the differently-abled through the setting up of elevators leading from bazaar to the site.

• Improve basic tourist and pilgrim facilities and amenities

• Improve vehicular parking facilities for about 100 vehicles in the town.

completed 2. 3rd

Floor roof

shuttering work in

progress 3.

Column work

upto 2nd & 3rd

floor 100 %

completed. 4.

Brick work- a.

Basement area

100 %, b. Ground

Floor -90 % , c.

1st Floor 80 %

completed. 5.

Non Basement

area- All work

complete upto

plinth level,

staircase work

(shuttering &

casting etc) on

progress, column

work upto 1st

floor complete, all

PCC work upto

plinth level

completed."

Page 23: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

21

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

• Improve basic environmental services like solid waste and wastewater management.

• Enforcing strict standards for cleanliness and upkeep. Improving tourist/visitor wayside amenities along approximately 10 km of vehicular access. Improving access to places of tourist/pilgrim attractions by way of 15 km of connectivity improvement inclusive of roadside infrastructure and improved signage.

• Improving about 4 km of pedestrian environment connecting the heritage site with different parts of the town.

• Training and capacity building 2. Construction of District Collectorate office at Porth Free Estate near VikasBhavan. Construction of G + 4 building with office, parking within Govt. land of 2500 sq m

For Almora District Collectorate office, Water supply is planned from municipal water supply and water line will be extended to proposed building.

For waste water – discharge 4 nos. of soak pit and 4 nos. of septic tank will be utilized. In total 64 nos. of toilet, 32 nos.

Page 24: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

22

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

urinal will be constructed

Solid waste will be stored in bins of adequate capacity from where collection will be done by Almora Nagar Palika

Out of above proposed scope in the IEE (based on DPR) only the components listed below are being taken up:

(i) Rani Mahal package has been awarded and scope is

• Restoration of Rani Mahal

• Restoration of Courtyard+ RamshilaTemple

• Restoration of Craft Centre + Toilet

• Restoration of SDM office

• Restoration of Fort Walls

• Signage Plan

• Civil work of Collectorate building in Almora

• Site Development and Landscaping

• Sanitary&

• Electrical Works

Following works shall be taken up in

Page 25: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

23

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

(ii) Malla Mahal package which is not yet awarded

• Museum on Kumaon culture in MallaMahal and

• Removal or concealment some buildings through strategic landscaping and foliage coverage of structures

UK/IDIPT/III/BH

T/05

Restoration

and adaptive

reuse of

Champawat

Fort (Banasur)

M/s

Simplex

Project

Limited

407,

Skipper

Corner, 88

Nehru

Place, New

Delhi -

110019,

India

1. The scope of this

sub-project includes:

a) Restoration of the historic

sites: Rajbhunga Fort and

Banasur Forts, or collectively

Champawat Forts, Restoration

of GoluDevta temple (3 km

from the Champawat fort) and

Goraknath temple (40 km from

Champawat)

b) Revitalization of the entire

precinct as a public space for

experiencing regional history

and culture, through creation

of facilities.

19.10.15 18.10.17 Tehsil Building-

Earth work &

PCC work of

foundation

work completed

100%, PCC

work upto plinth

level work

completed- 100

%, RR stone

work

completed

20%. 2. Type 2

Building- Earth

work & PCC

work of

foundation

work completed

100 % , RCC

24.00% Components

of GoluDevta

and Guru

Gorakhnath

temple have

been

dropped

Page 26: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

24

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

(i) Rajbhunga Fort:

• Removal of existing and

undesirable structures

• Remodeling and

reconstruction of existing

structures:Old Fort &Tehsil

Office and SDM Office, Durga

Devi Temple, Courtyard and

Ramparts.

• Providing Tourist Facilities and

Amenities at fort like Ticket

Counter, Tourist Interpretation

Centre, Cafe & Shop,

Souvenir Shop, Library, Toilet

Block, Creation of link walk

way & Improving the existing

road and Lanes, 12 Bed Hotel,

with 2 suites, Entrance way &

Reception, Water & Waste

Management, Solar lights.

(ii) GoluDevta Temple:

• Repair of Approach to

GoluDevta Temple

work

froundation to

slab upto 1st

floor, work

completed 100

%. 3. Type 4

Building- Earth

work & PCC

work of

foundation

work completed

100 %, PCC of

foundation &

plinth work

beam

completed-100

% .

Page 27: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

25

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

• Improvement of Worship

Space at GoluDevtaTemple

(iii) Guru Goraknath Temple:

• Shed and Railing at

Gorakhnath Temple

• Restoration of Wall at

Gorakhnath Temple

• Gazebos en route Gorakhnath

(iv) Other scope:

In training and capacity building

Present Scope of works includes

Banasur Fort:

• Removal of existing and

undesired structures and

relocation

• Remodelling and

reconstruction of existing

structures: 03 Gazebos en

route, shed on hilltop for café

Preparation of platform etc. on

site for Adventure Sport

Page 28: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

26

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Construction of new Tehsil building

• G+2 Tehsil building in 1400 m2 out of total land of 5400 m2. (Land to be transfer to Tourism dept. from KNVN)

• 1 number Type II quarter and 1 number Type IV quarter

• Garage facility and car parking

• Litigation room

• Boundary wall for whole area

• Approach road to site

Works in Rajbhunga will commence after construction of Tehsil building

Restoration

and Adaptive

Reuse of

Pithoragarh

Fort Phase II

UK/IDIPT/III/BH

T/07

M/S COX

Infratech

Private

Limited in

JV with

Conaech

Associate

s

• Demolition of Buildings

• Landscaping Works

• Lighting Plan

• Planting Plan

• Restoration of Fort Wall

• Restoration of Tehsil Office

• Restoration of Tehsil Residence

01-07-2015 30-06-2016 Multilevel

Parking near

Dev Singh

Ground

1-Dismantling

of CC Road has

been

completed.

2-Footing for

foundations has

been completed

upto 1 no. grid

(Numbers of 31

27.80% Minor

Change as

per site

requirement

Appropriate

measures

have been

taken for

fulfillment of

the

objectives.

Weather

disturbances due

to heavy rains or

snowfall may dlay

the project

Page 29: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

27

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

• Restoration of SDM Camp Office

• Restoration of Record Rooms

• Signage and Waste bins

grids). Tie

beam columns

has been

completed upto

1 to 31 no grid.

3-Steel box

column

erection 31 to 6

grid. (Numbers

of 25 grid)

4-ISMB beam

and floor work

of first, second

and third floor

under progress.

5-Footing for

foundations of

exit ramp under

progress.

Page 30: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

28

Name & No. of

Package

Name of

the

contracto

r

Scope of Works under Package

Starting Date(land

clearance) and schedule

date of completion Type of works

Continued at

Present

Progress

% age

Expected

change

from

Approve

d scope

Fulfillment

of

objective

Type of

remedial

measures

needed

Key assumption and

risk affect

attainment the

objective Starting

date

Date of

Completion

UK/IDIPT-III/KOT/01

Creation of

Pedestrian Route

for Pilgrims and

Tourists in Haridwar

M/s SS

Infratech Jv

, Tikola

Nagar,

Roorkee

a) Development of a pedestrian route or pathway for movement of pilgrims and tourist from near Mayapur Regulator to Bahadarabad Bridge. Total length of pedestrian pathway to be developed is 11.33 km. For a stretch of 5.9 km length (from near Mayapur Regulator to Jathwara bridge) the existing Kanwar Patri ( Route followed by Kanwarias) will be developed to a pedestrian pathway. For a stretch of 5.43 km (from Jathwara Bridge to Bahadarabad Steel Bridge) a pedestrian pathway will be developed on the side of existing motorable road (canal bank road). In this stretch of 5.43 km Kanwar Patri, and proposed pedestrian pathway and existing motor able canal bank road will exist.

b) Landscaping, sitting arrangements, murals, etc. on the proposed pedestrian pathway.

c) Providing lighting or illumination arrangement on the proposed pedestrian pathway of 11.33 km.

d) Providing safety hand railing on the pedestrian pathway on

22/07/2015 21/07/2017 • Footpath work

is in progress

at Sonali Park

• Plaster work

and PCC over

Brick on Guard

wall towards

canal side is in

progress

• Landscaping

work is in

progress along

the pathway

• Plantation

work is in

progress as

part of

landscaping

• Seating

arrangement

along the

pathway is in

progress

• First floor roof

casting is done

32% Foot Over

bridge over

NH-58 at

Manglaur

Crossing

dropped

due to

work done

by NHAI

on the

same

location.

Appropriate

measures

have been

taken for

fulfillment of

the

objectives

In case of any

restrictions by the UP

Irrigation Department

and permissions of Foot

Over Bridge

Construction on NH-58

at Manglaur

Page 31: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

29

canal side. e) Providing solid waste bins on the side of proposed pedestrian pathway.

f) Providing a toilet complex and drinking water facility on side of the proposed pedestrian pathway near Shankaracharya Chowk.

g) At one location near the proposed pedestrian pathway (before Lohe Ka Pul on railway track near Jawalapur) a multi facility complex will be developed which will include a toilet complex, drinking water fountain, bathing and sanitation facilities, rest shelter, food distribution centre, police control room, solid waste bins, compound wall with entrance gate, landscaping, etc.

h) Construction of a foot over bridge over Railway track near Jawalapur. i) Installation of tourist Signages on Kanwar Patri from Har Ki Pauri to Mangalour Cross. Total length of the stretch of Kanwar Patri to be taken up for the signage installation works is 42 km.

at integrated

complex

• Plumbing work

and brick work

is in progress

at Integrated

facility complex

UK/IDIPT-III/KOT/02

Development of

Tourism

Infrastructure in

Sem Mukhem (

Tehri)

M/s

Mangalam

and

Constructio

n Company

in JV with

Sunil Garg

Company

The main sub-project components include the following:

i. Dharamshala/ rest shelter at fair ground.

ii. Toilet complex at fair ground including septic tank with soak pit.

iii. Water supply Arrangement at Fair Ground

23/09/2015 21/09/2017 • For rest

shelter

(including

toilet

complex) all

brick work for

superstructure

completed.

RCC slab

55% Canopy for

a length of

147 m,

component

dropped

Appropriate

measures

have been

taken for

fulfillment of

the

objectives

In case of adverse

weather conditions and

any disagreement with

Mela Committee and

village Panchayat

Page 32: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

30

Meerut iv. Landscaping works at fair ground. Locally available materials shall be used for construction. The landscaping elements shall incorporate local foliages and flora of fairground so that the built environment is in sync with the background

v. Development of pathway from main road to fair ground.

vi. Solar lighting system along with normal outdoor lights is proposed at fair ground. Electricity source for illumination works is from Uttarakhand Power Corporation Limited and the same is reliable

vii. Development of existing small lake near fair ground. The existing small lake covers about 1500 sqm. area, while water spread area is 500 sqm.

viii. Solid waste bins and compost pits at Fair Ground. Solid wastes from Fair ground and Mandir complex will be collected in collection bins and ultimately dumped in to compost pit to be developed in the sub project.

ix. Murals depicting the story of Lord Krishna at 4 locations.

x. Providing solid waste bins and construction of compost pit in Mandir Complex. Solid wastes from Mandir complex will be collected in collection bins and ultimately dumped in to compost pit to be developed in the sub project.

xi. Solar light at the temple complex.

casting work

in progress.

• Pathway at

fair ground

WBM

completed,

CC work

completed

• Pathway for

Mukhem

Village is

completed

• RCC Slab

casting for

Pujari cottage

completed

• Renovation

of Mukhem

village temple

is in progress.

• Silt removal

from Jheel

completed.

Pitching work

is in progress.

Page 33: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

31

xii. Canopy for a length of 147 m on pathway in between fair ground and Nagraj Temple.

xiii. Hand rails and finishing works on pathway between fair ground and temple complex.

xiv. Facilities planned at Mukhem village are: a) Renovation of existing Temple

in Mukhem village. b) Renovation of existing entry

gate of Mukhem village. c) Development of internal roads

in Mukhem village. d) Expansion of existing pipe

water supply network. e) Installation of solar lighting

system, f) Solid waste management with

compost pits in Mukhem village.

• Tourism Signages on the 23Km road from Kodar to Fair Ground.

UKIDIPT/III/ GEN/03

Development of

Traditional Medicine

and Yoga Training

centers

M/s Bansal

Constructio

n,

Muzaffarna

gar

Development of Traditional Medicine Panchkarma and Yoga Centers at 3 TRHs/Resorts operated by GMVN in Garhwal Region (Dhanaulti, Rishikesh, Lansdowne) and at 5 TRHs/ Resorts operated by KMVN (Chiliyanaula, Kausani, Choukori, Naukuchiyatal and Sukhatal). New construction of above facilities is to be carried out only in Naukuchiyatal and Lansdowne, in the other locations facilities are planned within existing resorts by after interior refurbishment and slight alterations.

08/03/2017 07/03/2019 Location wise

Progress

update

TRH

Dhanaulti:

Civil Works in

completed

(Door, window

and glass

works,

Furniture,

fixture and

furnishing/déc

60%

No change Appropriate

measures

have been

taken for

fulfillment of

the

objectives

Only in case of extreme

weather events,

otherwise magnitude of

works is very low and no

risk envisaged

Page 34: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

32

The project progress includes civil component and procurements of equipments in a ratio of 60:40. Dhanault Sukhatal Chiliyanaula Kausani Chaukori Ganga Resort Lansdowne Naukuchiyatal

or items,

electrical, tile

work and

POP and

painting work)

TRH

Sukhatal:

Civil Works

started

09%

Any other information useful for assessing environmental performance of the project:

9. No additional information during this period

Page 35: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

33

2. Compliance Status

10. Status of Compliance with EARF/ADB Procedures is shown in Table 3.

Table 3: Status of Compliance with EARF/ADB Procedures S.No Name & No. of

Package

Environment

Category

Status of preparation of

IEE

Status of Approval

by ADB Date of Approval

Further Action needed For Compliance &

Responsibility

1 UK/IDIPT-III/ DDN/01 B Completed and approved Approved 03.08.2015 Regular monitoring and reporting of EMP

2 UK/IDIPT-III/ DDN/02 B Completed and approved Approved 01.09.2015 Regular monitoring and reporting of EMP

3 UK/IDIPT-III/DDN/03 B Completed and approved Approved 25.05.2016 Regular monitoring and reporting of EMP

4* UK/IDIPT/III/BHT/01Lot1 UK/IDIPT/III/BHT/01Lot2

B Completed and approved Approved 08.09.2015 Regular monitoring and reporting of EMP

5 UK/IDIPT/III/BHT/02 B Design stage

6* UK/IDIPT/III/BHT/03 UK/IDIPT/III/BHT/06

B Completed and approved Approved 09.07.2015 Regular monitoring and reporting of EMP

7* UK/IDIPT/III/BHT/04 UK/IDIPT/III/BHT/05

B Completed and approved Approved 06.08.2015 Regular monitoring and reporting of EMP

8 UK/IDIPT/III/BHT/07 B Completed and approved Approved 25.04.2016 Regular monitoring and reporting of EMP

9 UK/IDIPT-III/KOT/ 01 B Completed and approved Approved 11.05.2015 Regular monitoring and reporting of EMP

10 UK/IDIPT-III/KOT/ 02 B Completed and approved Approved 25.05.2015 Regular monitoring and reporting of EMP

11 UK/IDIPT-III/KOT/ 03 B Completed and approved Approved 28.03.17 Regular monitoring and reporting of EMP

12 UK/IDIPT/III/GEN/01 Goods Package

13 UK/IDIPT/III/GEN/02 B Completed and approved Approved 30.07.2015 Regular monitoring and reporting of EMP

14 UK/IDIPT/III/GEN/03 B Completed and approved Approved 03.03.2017 Regular monitoring and reporting of EMP

*S.no 4, 6 and 7, Project bifurcated into 02 packages

Page 36: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

34

3. Compliance status with National/ State/ Local statutory environmental requirements

11. Status of Compliance with National/ State/ Local statutory environmental requirements is shown in Table 4.

Table 4: Status of Environment, Forest and other Clearance

Work (Package No.) Applicable Legislation/Type of

clearance Clearance Given by

and date Subject/Issue Remarks/Action needed

UK/IDIPT-III/ DDN/01

Development of Tourism Infrastructure in Kartikeya Swami Circuit (Lot-1) (Tungeshwar & Durgadhar Temple)

No environmental and forest clearance required. No requirement of NOC from ASI

Not applicable

UK/IDIPT-III/ DDN/02

Development of Tourism Infrastructure in Kartikeya Swami Circuit (Kartikeya Swami Temple)

Forest clearance required. No requirement of Environmental Clearance or NOC from ASI

Clearance received from MoEF& CC dt. 23.09.16

Kartikeya Swami Temple and pathway are located in Reserve Forest area, for which forest clearance was needed.

Works to be done as per Clearance conditions.

UK/IDIPT-III/DDN/03 Conservation and Development of Rural Tourism in district Rudraprayag, Chamoli and Uttarkashi

No Environmental and forest clearance required. NOC required from Forest Dept. for Tungnath location. No requirement of NOC from ASI.

NOC obtained from Forest Department, GoUkdt. 08/09/14

Out of 9 rural sites, Tungnath lies in buffer zone of Kedarnath Wildlife Sanctuary NOC received from Forest Department

Works to be done as per conditions of NOC given by the Forest department.

UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

No environmental and forest clearance required. No requirement of NOC from ASI.

Not applicable

UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in Sem Mukhem

No Environmental and forest clearance required. (Only a minor canopy component was proposed in reserve forest since trek over which canopy has to be installed, falls in reserve forest). The same has been dropped.

Not required The project is for creation of Tourism Infrastructure in Sem Mukhem. No forest land acquisition involved, so no forest clearance required. The project site is not in ASI regulated Zone.

The canopy component has been dropped

UK/IDIPT-III/BHT/01 Conservation of Cultural Heritage and Urban

NOC from PWD, forest clearance required for pre fab toilets and view

NOC obtained from The project is for conservation of cultural heritage involving mostly repair, restoration

Forest Clearance of Tiffin Top is in process and related works will be

Page 37: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

35

Work (Package No.) Applicable Legislation/Type of

clearance Clearance Given by

and date Subject/Issue Remarks/Action needed

Place making in Nainital Lot 1 points on nature trail (Tiffin top and Tanki China). No requirement of NOC from ASI.

PWD

Forest Clearance for nature trail for Tanki Cheena obtained (Attached annex 3(ii) Forest Clearance for Tiffin Top is in process

works. There are 02 nature trails falling in reserve forest where portable toilet and viewpoints are proposed. So forest clearance required. The project site is not in ASI regulated Zone.

taken up after Clearance is obtained.

UK/IDIPT-III/BHT/03 Conservation and adaptive re-use of Almora Fort (Rani Mahal)

No Environmental and forest clearance required. No requirement of NOC from ASI.

Not applicable

UK/IDIPT-III/BHT/05 Conservation and adaptive re-use of Champawat Fort (Banasur)

No Environmental and forest clearance required.

Requirement of NOC from State ASI for Banasur Fort.

NOC obtained vide letter dt. 5th Dec, 2014.

Banasur Fort is a State Protected Monument and the custodian is State Culture Dept. NOC received from State Culture Dept.

Works as per NOC. Works should not interfere with the original character of the Fort structure.

UK/IDIPT/III/BHT/07

Restoration, Adaptive Reuse and Revitalization of Pithoragarh Fort

No Environmental and forest clearance required.

NOCs from line agencies obtained

NOC from District Administration for shifting Tehsil office NOC from Executive Engineer Nagarpalika Parishad Pithoragarh

NOC from District Sport officer

The project is for conservation of cultural heritage involving mostly repair, restoration works. Tehsil was housed in the Fort campus, which is to be relocated to carry on repair and restoration works in the Fort

Works to be done as per conditions of NOC given by line agencies and in line with their suggestions

UKIDIPT/III/GEN/03

Development of Traditional medicine and Yoga Training Centers

No Environmental and forest clearance required

Not applicable The project involves construction of yoga and panchkarma centres in existing Tourist Rest Houses of Tourism Dept. in 8 locations, wherein modification and refurbishment works are proposed in 06 TRHs while in 02 namely Lansdowne and Naukuchiyatal works will be done on vacant land within premises of the TRHs.

No action needed

Page 38: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

36

4. Compliance status with the environmental covenants as stipulated in the Loan Agreement

12. The status of compliance with environmental loan covenants is presented in Table 5.

Table 5: Status of Compliance with Environmental Loan Covenants S. No Covenants Compliance

1. The Borrower and the States shall ensure that the preparation, design, construction, implementation, operation and

decommissioning of each Subproject and all Project facilities comply with (a) all applicable laws and regulations of the

Borrower and the States relating to environment, health, and safety; (b) the Environment Safeguards; (c) the EAFR; and (d) all

measures and requirements set forth in the respective IEE and EMP, and any corrective or preventative actions set forth in a

Safeguard Monitoring Report.

Compliance of (a) all applicable laws and regulations of the Borrower

and the States relating to environment, health, and safety (b)

Environment Safeguards; (c) the EARF; and (d) EMP is being

ensured during sub projects implementation.

Safeguards – Related Provisions in Bidding Documents and Works Contracts

The States shall ensure that all bidding documents and contracts for Works contain provisions that require contractors to:

(a) Comply with the measures and requirement relevant to the contractor set forth in the IEE, the EMPs, any RO and any

IPP (to the extent they concern impacts on affected people during construction), and any corrective or preventative

actions set out in a Safeguard Monitoring Report;

(b) make available a budget for all such environment and social measures;

© provide the relevant State with a written notice of any unanticipated environmental, resettlement or indigenous peoples

risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the

IEE, the EMP, the or the IPP (if any): and

(d) Fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the

completion of construction.

Full EMP made part of the contract agreements of respective subprojects, thus its provisions being complied with.

Orientation sessions are being carried out in each site for better understanding of Safeguards Compliance by the Contractor Environmental monitoring and mitigation costs allocated/ incorporated in contract agreements. No such environmental impact has been identified so for that was not considered in the IEE and in the EMP. (If any such impact arises in future, will be suitably addressed) All the areas that if disturbed by construction activities will be restored to pre-project condition by the contractors.

Safeguards Monitoring and Reporting

11. The States shall do the following:

(a) Submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to

The fourth semiannual report for Loan No. 3223 IND is submitted herewith. Subsequent reports will be submitted on time.

Page 39: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

37

S. No Covenants Compliance

affected persons promptly upon submission;

(b) if any unanticipated environment and/or social risks and impacts arise during construction, implementation or operation

of the Project that were not considered in the IEE, the EMP, any RP or any IPP, promptly inform ADB of the occurrence

of such risks or impacts, with detailed description of the event and proposed corrective action plan; and Report any

breach of compliance with the measures and requirements set forth in the EMP, any IPP promptly after becoming

aware of the breach.

In case of any unanticipated environmental risks and impacts arise, that shall be immediately informed to ADB with detailed description of the event and proposed corrective action plan. Breach will be reported to ADB immediately after becoming aware of it.

5. Compliance Status with Environment Management and Monitoring Plans as stipulated in the environmental documentation as agreed with ADB.

13. The compliance Status with Environment Management and Monitoring Plan is shown in Table 6.

Table 6: EMP Implementation Status

S.

No Sub Project Name

EMP Part of Contract Documents

(Yes/No)

EMP being Implemented (Yes/ No)

Status of EMP Implementation (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)

Actions Proposed/ Additional Corrective Measures Required

1 UK/IDIPT-III/ DDN/01 Yes Yes Satisfactory DSC Safeguard specialist conducted on-site Training programme on may, 2017.

The Contractor has been instructed to deploy safety officer to look after safety measures

2 UK/IDIPT-III/ DDN/02 Yes Yes Partially Satisfactory In February 2017 training programme was conducted by PMU for all the contractors regarding Contractors obligations wrt EMP implementation at site.

The contractor has been instructed to maintain Grievance register at the site and disclosure signage.

The contractor has been instructed to provide proper hygiene at the temporary labour camp when no. of labour is increased due to certain work for 2-3 days.

Page 40: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

38

S.

No Sub Project Name

EMP Part of Contract Documents

(Yes/No)

EMP being Implemented (Yes/ No)

Status of EMP Implementation (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)

Actions Proposed/ Additional Corrective Measures Required

3 UK/IDIPT-III/ DDN/03 Yes Yes Partially Satisfactory In February 2017 training programme was conducted by PMU for all the contractors regarding Contractors obligations wrt EMP implementation at site.

The Contractor has been instructed to carry out subsequent environment monitoring at the sites.

The Contractor has been instructed to improve condition of temporary labour huts at Mukhwa, Harsil, Kaviltha site.

The Contractor has been instructed to deploy safety officer to look after safety measures and ensure usage of PPEs for labour.

4 UK/IDIPT/III/BHT/01 Conservation of Cultural Heritage and Urban Place making in Nainital Lot 1

Yes Yes Satisfactory 30 local labourers have been deployed for the construction activities. The laborers are staying in a labour camp which having proper sanitation facility. Contractors have provided basic safety equipment like safety Hat, safety Boots & first-aid box at site. On job trading regarding safety measures were imparted to the laborers and contractors supervisors and time to time. Contractor has been instructed for proper stockpiling of raw materials and waste in designated area with demarcation.

5 UK/IDIPT/III/BHT/03 Conservation and adaptive re-use of Almora Fort (Rani Mahal)

Yes Yes Satisfactory 36 (25 male and 11 female) local labourers have been deployed for the construction activities. Contractor will ensure the usage of PPEs.

6 UK/IDIPT/III/BHT/05 Conservation and adaptive re-use of Champawat Fort (Banasur)

Yes Yes Satisfactory Contractor has not carried out ambient air noise water quality test during this reporting period. Contractor has been instructed get ambient air noise water quality test Contractor has been instructed for proper stockpiling with demarcation of raw materials and waste. Contractor was directed to improve housekeeping and clearly demarcate the raw material and waste storage areas. Also instructed to increase the frequency of waste disposal from sites and solid waste management.

Page 41: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

39

S.

No Sub Project Name

EMP Part of Contract Documents

(Yes/No)

EMP being Implemented (Yes/ No)

Status of EMP Implementation (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)

Actions Proposed/ Additional Corrective Measures Required

7 UK/IDIPT/III/BHT/07 Restoration, Adaptive Reuse and Revitalization of Pithoragarh Fort Phase II

Yes Yes Satisfactory On an average 25 male local labourers have been deployed for the construction activities. Contractors have provided basic safety equipment like safety Hat, safety Boots & first-aid box at site. On job trading regarding safety measures were imparted to the laborers and contractors supervisors and time to time. Dust bins provided for collection of solid waste materials. Increased the frequency of waste disposal from sites. Suggested for proper solid waste management Ensuring regular medical checkup of labors after giving instructions to the contracts by DSC/PIU The laborers are staying in a common hall which has been hired by the contractor in Pithoragarh (Hotel Zyonar) on monthly basis. Thus, accommodation for the laborers is not a problem.

8 UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

Yes Yes Satisfactory 1- The contractor has been advised to maintain sanitation facilities at construction camp at integrated facilities complex

2- The contractor has been instructed to maintain bathing place for female workers.

3- The contractor has been sensitized to use personal protective equipment.

4- The contractor has been instructed to carry out environmental monitoring for summer season and submit monitoring report in first week of June 2017.

5- The contractor has been instructed to segregate construction waste scattered at Multi Facility Complex location at one place and enclose it with caution tape to avoid any injury to construction workforce.

6- The contractor has been advised to obtain permission from municipal authorities for planned bore well at multi facility complex.

7- The contractor has been instructed to improve housekeeping at

Page 42: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

40

S.

No Sub Project Name

EMP Part of Contract Documents

(Yes/No)

EMP being Implemented (Yes/ No)

Status of EMP Implementation (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)

Actions Proposed/ Additional Corrective Measures Required

Integrated multi facility site.

9 UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in Sem Mukhem

Yes Yes Satisfactory 1- The contractor has been instructed to carry out environmental monitoring for summer season and to maintain sanitation facilities at construction camp at Mela Ground

2- The contractor has been instructed to store excavated earth from the reservoir properly and use in the filling works of retaining wall of this reservoir.

3- The contractor has been instructed to segregate all construction waste at one location at the Mela ground construction site.

4- The contractor has been instructed to enforce use of PPEs at site.

10 UKIDIPT/III/GEN/03 Development of traditional medicine and Yoga Training centres

Yes Yes Satisfactory Works in the reporting period were carried out only in 03 locations, out of which 02 had just started. Only 10-12 labour were mobilized at site. Contractor was instructed to improve general housekeeping in TRH premises, Dhanaulti and increasing the number of dustbins.

6. Status of Implementation of Environment Management Plan

14. EMP Monitoring status of subprojects is presented in Table 7.

Page 43: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

41

Table 7 (i): EMP Monitoring Status Chart- Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-1) (Tungeshwar&Durgadhar Temple) IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

UK/IDIPT-III/ DDN/01

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC IEE and EMP have been prepared and EMP being complied with. The project planning done in advance and after many stakeholder consultations. Measures for earthquake resistance incorporated in DPR No site of archaeological remains in the vicinity

None

Pre-construction activities by the Contractor

1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC

1 Construction camp established in open land near the project site. It is away from habitation. Sanitation facilities at construction camp have improved. Drinking water facilities available at site. Existing water supply arrangement from natural source is used. 2. No protected area within 200 m of project site 3. No impact on traffic movement due to construction as there is no frequent to and fro transportation of materials The project site is on extreme left edge of NH-58 and construction activities are not interfering with traffic movement and tourist movement. 4. The site clearance activities have been carried out and excavated earth has been kept aside and is being used 5. Potable drinking water is being made available for the construction force through the existing arrangement from natural source. 6. The waste material generated due to clearance and demolition activities is being used for filling and leveling at site only. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. 7. The waste generated during the construction is segregated and stored at the site for possible reuse later. Contractor was instructed to increase the number of dustbins. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU

training program on environmental safeguards has been conducted by the DSC Environmental expert after mobilisation of the contractor

Page 44: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

42

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures

1. The main construction materials at present being used are

bricks, cement, stone, sand and steel rods. These are being

stocked properly. Stockpiles separate and covered

2. The contractor is obtaining sand and sub grade from the

licensed quarries. No borrow pit operations have been carried out

so far.

3. The excavated earth for foundation work of Dharamshala in

Tungeshwar has been kept aside and will be reused for filling.

4. The soil erosion issue is not there as there is no cutting or

steep slope issues involved in the project.

5. The fuel and lubricants are not stored at site as project is small

in nature. These are purchased from market as per need.

6. No water body in the impact area of the subproject.

7. Generation of dust is on account of material handling at site.

Necessary dust suppression measures such as water sprinkling

are followed.

8. The construction vehicles usage is not much in the project. It is

only for the transportation of construction materials and there is a

small concrete mixer at site. The trucks carrying construction

material have pollution under control certificates.

9. In the current project the only noisy equipment used is

concrete mixer and it is operated intermittently. No excess noise

generation is on account of construction activities.

10. The material handling at site is satisfactory as most of the

workers were seen using personal protective equipment.

11. Construction waste generated so far has been stored for

utilization and disposal further at designated location.

12. Toilet block completed and functional

13. Use of PPE’s is satisfactory. Caution tape is provided and

Water and Sanitation issue to be addressed Periodic health check up is necessary for labourer Deployment of safety officer at the site

Proper barricading to be done at the work site Regular health check up and AIDs training needed for the laborers Deployment of regular safety officer by the contractor Regular testing of air and noise in frequent interval

Page 45: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

43

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

14. Risks force majeure 15. Malaria risk

16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds

caution sign board is also put up at site.

14. Risk Force Majeure: situation not occurred so far. Necessary

action will be taken as per contract provisions if such situation

arises

15. Instructions have been given to contractor regarding malaria

risk and prevention measures.

16. Chance Archaeological finds have not been found so far

during the construction works. The contractor has been instructed

to inform to PIU and DSC, if any chance find is found.

17. The project is not impacting any religious structures rather its

meant for maintenance and restoration of religious structures.

18. There is neither any route of migratory birds nor any location

where migratory birds are visiting.

Operation 1. Environmental conditions

2. Uncontrolled tourism

3. Management of the toilet blocks

4. Adequate drainage 5. Unhygienic

condition due to poor maintenance of sanitation facilities and irregular solid waste collection

6. Increased waste

loads onto the

existing waste

disposal facilities

PMU, UTDB The project not yet reached Operation phase Not Applicable Not applicable

Page 46: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

44

Table 7 (ii): EMP Monitoring Status Chart- Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-2) (Kartiekeya Swami Temple)

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

UK/IDIPT-III/ DDN/02

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC IEE and EMP have been prepared and EMP being complied with. The project planning done in advance and after many stakeholder consultations. Measures for earthquake resistance incorporated in DPR No site of archaeological remains in the vicinity

None

Pre-construction activities by the Contractor

1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC

1 Construction workers reside in existing structures. No labour camp established. Temporary camp is established when the no. of labour is increased due to certain works. 2, Work area properly demarcated. 3. Site is far from main road. Traffic interference is not there on account of the construction activities. 4. The site clearance activities have been done and excavated earth has been kept aside and is being used for levelling and filling. 5. Potable drinking water is being made available for the construction force through the existing arrangement from natural source. 6. Disposal site will be identified in consultation with Forest Dept. The waste material generated due to clearance and demolition activities will be used to the extent possible in the project. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. 7. The waste generated during the construction is segregated and stored at the site for possible reuse later. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU

training program on environmental safeguards has been conducted by the DSC Environmental expert after mobilisation of the contractor

Construction 1. Improper stockpiling

1. The main construction materials at present being used are

bricks, cement, stone, sand and steel rods. These are being

Registers and Records to

The contractor has been instructed to maintain

Page 47: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

45

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

2.Quarry/ Borrow pit operations

3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk

16.Chance archaeological finds

stocked properly.

2. The contractor is obtaining sand and sub grade from the licensed quarries. No borrow pit operations have been carried out so far. 3. The excavated earth from pathway work, retaining wall and rest sheds has been kept aside and is being simultaneously reused for filling and leveling. 4. The soil erosion issue is not there as there is no cutting and moreover the area is rocky. 5. The fuel and lubricants are not stored at site as project is small in nature. These are purchased from market as per need. 6. Natural water source but not within the impact zone. 7. Generation of dust is very less. 8. The construction vehicles usage is not much in the project. It is only for the transportation of construction materials and there is a small concrete mixer at site. The trucks carrying construction material have pollution under control certificates. 9. So far no equipment has been used and all activities are manual. 10. The material handling at site is fine as most of the workers were seen using personal protective equipment. 11. Construction waste generated so far has been stored for utilization and disposal further at designated location. 12. The sanitation facilities at construction camp are proper. 13. First aid kits were not found suitably equipped Use of PPE’s is satisfactory. Caution tape is provided and caution sign board is also put up at site. 14. Risk Force Majeure: situation not occurred so far. Necessary action will be taken as per contract provisions if such situation arises 15. Instructions have been given to contractor regarding malaria risk and prevention measures. 16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC, if any chance find is found.

be maintained properly Safety Officer to be deployed

Grievance redressal mechanism at the site

The Contractor has been instructed to deploy safety officer to look after safety measures and ensure usage of PPEs for labour

The contractor has been instructed to provide proper hygiene at the labour camp

Submission of regularly

environmental monitoring report

to PIU

Page 48: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

46

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

17.Religious structures 18. Construction Staff

causing disruption to

migratory birds

17. The project is not impacting any religious structures rather its meant for maintenance and restoration of religious structures. 18. There is neither any route of migratory birds nor any location where migratory birds are visiting.

Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities

PMU, UTDB The project not yet reached Operation phase Not Applicable Not applicable

Table 7 (iii): EMP Monitoring Status Chart- Rural Tourism in District Tehri and Uttarkashi

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

UK/IDIPT-III/ DDN/03

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC IEE and EMP have been prepared and EMP being complied with. The project planning done in advance and after many stakeholder consultations. Measures for earthquake resistance incorporated in DPR No site of archaeological remains in the vicinity

None

Page 49: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

47

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

Pre-construction activities by the Contractor

1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC

Kanakchori 1 No Construction camp. Only local labor involved. 2. Temporary Toilet has been constructed for labour. 3. Drinking water facilities available at site from piped supply line. / Existing water supply arrangement. 2. Located within village boundaries. No impact on traffic movement due to construction as magnitude of work is very less. There is no frequent to and fro transportation of materials Construction activities frequency is less and hence are not interfering with traffic movement and tourist movement. 4. The site clearance activities have been done and excavated earth has been kept aside and is being used for levelling and filling. 5. Potable drinking water is available for the construction force through the existing arrangement from water supply line. 6. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. 7. The waste generated during the construction is segregated and stored at the site for possible reuse later. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU Kabiltha 1. Construction camp established on site Kalidas Smarak. Almost 50% of labour is local. 2. Existing toilet facilities at site is being used for construction camp. Drinking water facilities available at site from natural source. Existing water supply arrangement from natural source is used. 2. Within village boundary. No impact on traffic movement due to construction as there is no frequent to and fro transportation of materials. General vehicle frequency in the area is very less. Construction activities frequency is less and hence are not interfering with traffic movement and tourist movement. 4. The site clearance activities have been done and excavated earth

The contractor has been instructed to maintain all registers and records and project disclosure signages at all working sites. The Contractor has been instructed to deploy safety officer to look after safety measures and ensure usage of PPEs for labour The Contractor has been instructed to carry out subsequent environment monitoring The Contractor has been instructed to improve housekeeping at Mukhwa site. The Contractor has been instructed for proper stockpiling of raw materials at Kaviltha site

All registers and records to be properly maintained.

Page 50: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

48

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

has been kept aside and is being used for levelling and filling. 5. Potable drinking water is being made available for the construction force through the existing arrangement from natural source. 6. The waste material generated due to clearance and demolition activities will be used to the extent possible in the project. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. 7. The waste generated during the construction is segregated and stored at the site for possible reuse later. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU Phalasi 1. No Construction camp established. Skilled labor resides in existing structures and other labour is local. 2. Existing toilet facilities at site is being used for construction labour. Drinking water facilities available at site from natural source and also water supply line 2. Within village boundary. Hence no impact on traffic movement due to construction as there is no frequent to and fro transportation of materials. Vehicle frequency in the area is very less. Construction activities frequency is less and hence is not interfering with traffic movement and tourist movement. 4. The site clearance activities have been done and excavated earth has been kept aside and is being used for levelling and filling. 5. Potable drinking water is being made available for the construction force through the existing arrangement from natural source and water supply line. 6. The waste material generated due to clearance and demolition activities will be used to the extent possible in the project. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. 7. The waste generated during the construction is segregated and stored at the site for possible reuse later. The waste disposal plan will

Page 51: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

49

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU Harshil 1. Local labour hired. No Construction camp established. 2. Existing toilet facilities at site is being used for construction labour. Drinking water facilities available at site from natural source and also water supply line 2. Within village boundary. 3. No impact on traffic movement due to construction as there is no frequent to and fro transportation of materials. Construction vehicle frequency is less and hence are not interfering with traffic movement and tourist movement. 4. The site clearance activities have been done and excavated earth has been kept aside and is being used for levelling and filling. 5. Potable drinking water is being made available for the construction force through the existing arrangement from natural source and water supply line. 6. The waste material generated due to clearance and demolition activities will be used to the extent possible in the project. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. 7. The waste generated during the construction is segregated and stored at the site for possible reuse later. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU Mukhwa 1. No Construction camp established. Local labour employed 2. Existing toilet facilities at site is being used for construction labour. Drinking water facilities available at site from natural source and also water supply line 2. Within village boundary. Hence no impact on traffic movement due to construction as there is no frequent to and fro transportation of materials. Vehicle frequency in the area is very less. Distance from

Page 52: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

50

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

main road at Harshil is 01 km. Construction activities frequency is less and hence is not interfering with traffic movement and tourist movement. 4. The site clearance activities have been done and excavated earth has been kept aside and is being used for levelling and filling. 5. Potable drinking water is being made available for the construction force through the existing arrangement from natural source and water supply line. 6. The waste material generated due to clearance and demolition activities will be used to the extent possible in the project. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. 7. The waste generated during the construction is segregated and stored at the site for possible reuse later. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU

Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust

1. The main construction materials being used at present , at all 04 sites are bricks, cement, stone, sand and steel rods. These are being stocked properly. At Kanakchori site contractor was instructed to properly demarcate and cover stockpiles. 2. The contractor is obtaining sand and sub grade from the licensed quarries. No borrow pit operations have been carried out so far. 3. The excavated earth is being kept aside and is being simultaneously reused for filling and leveling. 4. Minor works. The soil erosion issue is not there as there is no cutting and moreover the area is rocky. 5. The fuel and lubricants are not stored at site as projects are small in nature. These are purchased from market as per need. 6. Natural water source but not within the impact zone. 7. Generation of dust is very less. 8. The construction vehicles usage is not much in the project. It is only for the transportation of construction materials and there is a small concrete mixer at site. The trucks carrying construction material have

To improve hygiene condition of labour hut at Mukhwa, Harsil, Kaviltha site. proper stockpiling of raw materials at Kaviltha site to deploy safety officer to look after safety measures and ensure usage of PPEs for labour Regular environmental monitoring Noise and

Proper barricading is necessary at the work site Regular health check up and AIDs training needed for the laborers Deployment of regular safety officer by the contractor Submission of regularly environmental monitoring report to PIU

Page 53: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

51

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk 16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds

pollution under control certificates. 9. So far no equipment has been used and all activities are manual. 10. The material handling at site is fine as most of the workers were seen using personal protective equipment. 11. Construction waste generated so far has been stored for utilization and disposal further at designated location. 12. The existing sanitation facilities are utilized. 13. Use of PPE’s is satisfactory. Caution tape is provided and caution sign board is also put up at site. 14. Risk Force Majeure: situation not occurred so far. Necessary action will be taken as per contract provisions if such situation arises 15. Instructions have been given to contractor regarding malaria risk and prevention measures. 16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC, if any chance find is found. 17. The project is not impacting any religious structures rather its meant for maintenance and restoration of religious structures. 18. There is neither any route of migratory birds nor any location where migratory birds are visiting.

Air at all the sites

Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities

PMU, UTDB The project not yet reached Operation phase Not Applicable Not applicable

Page 54: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

52

Table 7 (iv): EMP Monitoring Status Chart- Conservation of Cultural Heritage and urban place making in Nainital Lot-1 IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance

issues

Corrective

actions

UK/IDIPT/III/BHT/01

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC 1. Environmental impacts were ascertained and accordingly IEE and EMP have been prepared and EMP being complied with. The project planning done in advance and after many stakeholder consultations

No issue Not Applicable

Pre-construction activities by the Contractor

1.Construction Camps

Contractor & DSC 1 Construction camp established in open land near the Methodist church project site. It is near habitation. Sanitation facilities at construction camp have improved. Drinking water facilities available at site. The source of water is Municipal water supply.

No Issue

2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas.

2. No protected area within 200 m of project site.

No Issue

3. Circulation plan during construction. 3. No impact on traffic movement during construction

No Issue

4. Site clearance activities 4. The site clearance activities have been carried out and excavated earth has been kept aside

No Issue

5.Drinking water availability 5. Potable drinking water is being made available for the construction force through the existing tap water supply

No Issue

6. Identification of disposal sites 6. The waste material generated due to clearance and demolition activities will be used to the extent possible in the project. It is a designated dumping site. However this site has been filled and new site is being identified in consultation with Municipality and DFO.

Contractor and PIU has been instructed to resolve the issue at the earliest.

7. Waste management on site 7. So far the waste generated during the construction is segregated and stored at the site for possible reuse later but not covered adequately. The waste disposal plan will

Stockpiles of waste to be properly covered till probable reuse

Page 55: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

53

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance

issues

Corrective

actions

be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU

in later stages or dispose of at identified disposal sites.

Construction 1. Improper stockpiling Contractor & DSC 1. The main construction materials at present being used are bricks, cement, sand and steel rods. Proper stockpiling was not seen. So instructions were given to the Contractor.

Construction material shall be stored in demarked area with barricades

Contractor has been instructed

2.Quarry/ Borrow pit operations 2. Material is purchased from licensed quarries. No quarrying/ borrow pit operations done so far

No Issue

3.Stripping, stocking & preservation of top soil

3.The top soil generated is being utilized No Issue

4.Soil erosion

4. The soil erosion issue is not there as

there is no cutting or steep slope issues

involved in the project

No Issue

5. Water pollution due to fuel/lubricants

5. The fuel and lubricants are not stored at

site as project is small in nature. These are

purchased from market as per need.

No Issue

6. Siltation of water bodies

6. Silt prevention measures undertaken (silt traps) in Treatment of Dam wall, restoration of Band Stand and Municipal Library

No Issue

7. Generation of dust

7. Generation of dust is on account of

material handling at site. Necessary dust

suppression measures such as water spray

is being followed.

No Issue

8.Emission from construction vehicles

8. The construction vehicles usage is not much in the project. It is only for the transportation of construction materials and a small concrete mixer at site. The trucks carrying construction material have pollution under control certificates

No Issue

9. Noise from construction equipment 9. In the current project the only noisy No Issue

Page 56: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

54

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance

issues

Corrective

actions

equipment used is concrete mixer and it is

operated intermittently.

10. Material handling at site 10. The material handling at site is fine as most of the workers were seen using personal protective equipment.

No Issue

11. Disposal of construction waste/debris

11. Construction waste generated so far has

been stored for utilization and disposal

further at designated location

Contractor shall barricade the waste storage site.

Contractor has

been

instructed for

the same

12. Sanitation facilities at project site 12. Sanitation facilities at site are satisfactory.

Increase the number of dustbins is need at site.

Contractor has

been

instructed for

the same.

13. Safety measures 13. Use of PPE’s is satisfactory. Caution

tape is provided and caution sign board is

also put up at site

Electrical safety to be looked into

Regular

monitoring of the

tools by Safety

Expert should be

done.

Safety Expert to

check all safety

issues

14. Risks force majeure 14. Risk Force Majeure: situation not occurred so far. Necessary action will be taken as per contract provisions if such situation arises

No Issue

15. Malaria risk

15. Instructions have been given to

contractor regarding malaria risk and

prevention measures

No Issue

16.Chance archaeological finds

16. Chance Archaeological finds have not

been found so far during the construction

works. The contractor has been instructed

to inform to PIU and DSC, if any chance find

No Issue

Page 57: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

55

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance

issues

Corrective

actions

is found

17.Religious structures

17. The project is not impacting any religious structures

No Issue

18. Construction Staff causing disruption to migratory birds

18. There is neither any route of migratory

birds nor any location where migratory birds

are visiting

No Issue

Operation 1-Environmental conditions PMU, UTDB The project not yet reached Operation phase

Not Applicable Not applicable

2.Uncontrolled tourism

3. Management of the toilet blocks

4. Adequate drainage

5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection

6. Increased waste loads onto the existing waste disposal facilities

Page 58: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

56

Table 7 (v): EMP Monitoring Status Chart- Restoration and adaptive reuse of Almora Fort (Rani Mahal)

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

UK/IDIPT/III/BHT/03

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC 1. IEE and EMP have been prepared and EMP being complied with. The project planning done in advance and after many stakeholder consultations

No Issue

Pre-construction activities by the Contractor

1.Construction Camps Contractor & DSC 1 Construction camp established in open land near the project site. It is very far from habitation. Sanitation facilities at construction camp are not proper.

No Issue

2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas

2. No protected area within 200 m of project site

No Issue

3. Circulation plan during construction

3. No impact on traffic movement during construction.

No Issue

4. Site clearance activities 4. The site clearance activities have been carried out at excavated earth has been kept aside.

No Issue

5. Drinking water availability 5. Drinking water facilities available at site. The source of water is piped supply from natural source.

No Issue

6. Identification of disposal sites 6. The waste material generated due to clearance and demolition activities has been used to the extent possible in the project. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off.

No issue

7. Waste management on site 7. Presently, the waste generated is Stockpiles of waste to be

Page 59: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

57

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

segregated and stored at the site for possible reuse later. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU.

properly covered till possible reuse in later stages or dispose of at identified disposal sites.

Construction 1. Improper stockpiling

Contractor & DSC 1. The main constructions materials at present being used are bricks, cement, stones, sand and steel rods. These are not stocked properly, for which instructions were given.

Construction material shall be stored in demarked area with barricades. Cover stockpiled material properly. Contractor shall use man at work board and red tape barricades. Construction material and waste shall be stored in demarked area with barricades.

Proper instruction has been given to the contractor.

2.Quarry/ Borrow pit operations

2. Material is being purchased from licensed quarries. No quarrying/borrow pit operations.

No Issue

3.Stripping, stocking & preservation of top soil

3. Top soil generated from foundation work is preserved for reuse.

No Issue

4.Soil erosion

4. The soil erosion issue is not there as there is no cutting or steep slope issues involved in the project.

No Issue

5. Water pollution due to fuel/lubricants

5. The construction vehicles usage is not much in the project. Fuel/ lubricants are not stored in larger quantities and brought as per demand.

No Issue

6. Siltation of water bodies

6. No water body in immediate vicinity No Issue

7. Generation of dust

7. Water sprinkling done. Increase sprinkling frequency

Instructions were given to increase the frequency.

Page 60: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

58

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

8.Emission from construction vehicles

8. Frequency of transportation vehicles is very limited. The trucks carrying construction material have pollution under control certificates

No Issue

9. Noise from construction equipment

9. In the present phase, the only noisy equipment used is concrete mixer and it is operated intermittently.

No Issue

10. Material handling at site

10. Usage of PPE not proper and directions were given.

No Issue

11. Disposal of construction waste/debris

11. Presently stored at site. Construction waste generated so far has been stored for utilization and suitable disposal further at designated location.

12. Sanitation facilities at project site

12. Sanitation facility at site is not proper, for which directions were given.

Sanitation at labour camp was not proper.

Adequate number of dustbins should be kept at site and camp area. Contractor was directed to increase the cleanliness and sanitation arrangements at the site.

13. Safety measures

13. Usage of PPE was not proper. The contractor was instructed to procure first aid kits and to deploy safety officer to look after safety measures

The contractor shall keep one safety officer at site. Maintain adequate supply of PPEs at site. First aid kits have been procured. But First aid training has not been imparted to appropriate number of workers. Signage depicting project details need to be displayed.

The contractor shall keep availability of adequate number of PPEs. Contractor was directed to have a trained first aider and Give first aid training to appropriate number of workers A training program on environmental safeguards has been conducted by the DSC Environmental expert after mobilization of the contractor

14. Risks force majeure 14. Risk Force Majeure situation has not No Issue

Page 61: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

59

IEE/EMP

Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

occurred so far. Necessary action will be taken as per contract provisions

15. Malaria risk

15. Instructions issued regarding malaria risk and prevention were given

No Issue

16.Chance archaeological finds 16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC, if any chance find is found

No Issue

17.Religious structures 17.The project is not impacting any religious structures

No Issue

18. Construction Staff causing disruption to migratory birds

18. There is neither any route of migratory birds nor any location where migratory birds are visiting

No Issue

Operation 1-Environmental conditions

PMU, UTDB The project not yet reached Operation phase

Not Applicable Not Applicable

2.Uncontrolled tourism

3. Management of the toilet blocks

4. Adequate drainage

5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection

6. Increased waste loads onto the existing waste disposal facilities

Page 62: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

60

Table 7 (vi): EMP Monitoring Status Chart- Restoration and adaptive reuse of Champawat Fort (Banasur) IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

UK/IDIPT/III/BHT/03

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC 1. IEE and EMP have been prepared and EMP being complied with. The project planning done in advance and after many stakeholder consultations

No issue

Not applicable

Pre-construction activities by the Contractor

1.Construction Camps

Contractor & DSC 1 Construction camp established in open land near the project site. It is very far from habitation.

No issue

2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas

2. No protected area within 200 m of project site

No issue

3. Circulation plan during construction

3. No impact on traffic movement during construction

No issue

4. Site clearance activities

4. The site clearance activities have been carried out at excavated earth has been kept aside.

No issue

5. Drinking water availability

5. Drinking water facilities available at site. The source of water is piped supply from natural source.

No issue

6. Identification of disposal sites

6. The waste material generated due to clearance and demolition activities will be used to the extent possible in the project. Towards the end of construction phase, the site for disposal of waste material has been identified, keeping in view the quantity to be disposed off.

No issue

7. Waste management on site 7. Presently, the waste generated is segregated and stored at the site for possible reuse later. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the

No issue

Page 63: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

61

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

DSC and will be approved in consultation with PIU

Construction 1. Improper stockpiling

1. The main construction materials at present being used are bricks, cement, stones, sand and steel rods. These are not stocked properly, for which instructions were given.

Cover stockpiled material properly

Contractor has been instructed for proper stocking of construction material.

2.Quarry/ Borrow pit operations

2. Material is being purchased from licensed quarries. No quarrying/borrow pit operations

No issue

3.Stripping, stocking & preservation of top soil

3. Top soil generated from foundation work is preserved for reuse.

No issue

4.Soil erosion

4. The soil erosion issue is not there as there is no cutting or steep slope issues involved in the project.

No issue

5. Water pollution due to fuel/lubricants

5. The construction vehicles usage is not much in the project. Fuel/ lubricants are not stored in larger quantities and brought as per demand.

No issue

Contractor has been instructed to get regular testing of air water and noise as per EMP

6. Siltation of water bodies 6. No water body in immediate vicinity No issue

7. Generation of dust

7. Water sprinkling done. However, instructions were given to increase the frequency.

Increase sprinkling frequency

Contractor has been instructed to get regular testing of air water and noise as per EMP

8.Emission from construction vehicles

8. Frequency of transportation vehicles is very limited. The trucks carrying construction material have pollution under control certificates.

No issue

9. Noise from construction equipment

9. In the present phase, the only noisy equipment used is concrete mixer and it is operated intermittently.

No issue

10. Material handling at site

10. Usage of PPE not proper and directions were given.

No issue

11. Disposal of construction waste/debris

11. Presently stored at site. Construction waste generated so far has been stored for utilization and suitable disposal further at designated location

No issue

12. Sanitation facilities at project site 12. Sanitation facility at site is not proper, for Adequate number of Contractor has been

Page 64: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

62

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

which directions were given. dustbins should be kept at site and camp area

instructed to provide dustbin at site.

13. Safety measures

13. Usage of PPE was not proper. The contractor was instructed to procure first aid kits and to deploy safety officer to look after safety measures

First aid kits have been procured. But First aid training has been imparted to the workers. Other cautionary signage need to be provide

Contractor has been instructed to provide other cautionary signage at Construction Sites

14. Risks force majeure

14. Risk Force Majeure situation has not occurred so far. Necessary action will be taken as per contract provisions

No issue

15. Malaria risk

15. Instructions issued regarding malaria risk and prevention were given.

No issue

16.Chance archaeological finds

16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC, if any chance find is found

No issue

17.Religious structures

17.The project is not impacting any religious structures

No issue

18. Construction Staff causing disruption to migratory birds

18. There is neither any route of migratory birds nor any location where migratory birds are visiting

No issue

Operation 1-Environmental conditions PMU, UTDB The project not yet reached Operation phase Not Applicable Not Applicable

2.Uncontrolled tourism

3. Management of the toilet blocks

4. Adequate drainage

5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection

6. Increased waste loads onto the existing waste disposal facilities

Page 65: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

63

Table 7(vii): EMP Monitoring Status Chart – Restoration and Adaptive Reuse of Pithoragarh Fort, Pithoragarh

IEE/EMP

Components

Environmental Issues Responsibility Action during Reporting period Compliance Issues Corrective Actions

UK/IDIPT/III/BHT/07

Location impacts

Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural character of the surroundings.

PMU & Line Agency The project site is having existing quarter and Parking No issue Not applicable

Design & pre construction impacts

1. Increased storm water runoff from alterations of the site‘s natural drainage patterns due to additional structures in TRH complex and landscaping works in the area and on lake edge.

DSC & PIU Impacts considered and measures integrated in design No issue Not applicable

2. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations

3. Integration of energy efficiency and energy conservation programs in design of subproject components

Pre-construction activities by the contractor

1. Circulation plan during construction in the tourist destinations

Contractor & DSC Circulation plan made No issue Not applicable

2. Site clearance activities, including delineation of construction areas

Site clearance done by contractor

3. Drinking water availability and water arrangement

Municipal water is being used by the labor

4. Identification of sites for disposal of construction and demolition work Construction/demolition waste is being disposed at

designated site identified by PIU

Construction impacts

1. Improper stockpiling of construction materials cause impacts starting from obstruction of drainage, disturbance/safety hazard to tourists, etc.

Contractor 1. Construction Material Properly stockpiled and brought as per demand

No issue

2. Stripping, stocking and preservation of top soil

2. Demolished waste and excavated material from working site and use / disposal of the same as per

No issue

The liter bins needs to dispose at municipal

Page 66: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

64

IEE/EMP

Components

Environmental Issues Responsibility Action during Reporting period Compliance Issues Corrective Actions

Mitigation measures in EMP dumping site frequently.

3. Soil Erosion 3. Construction is being done in place of existing structures as per EMP there is no issue of soil erosion.

No issue

Worker need to use safety shoes

4. Soil and Water Pollution due to fuel and lubricants, construction waste

4. Since no major equipment is being used at site storage is not required. Fuel is being carried as per requirement

Testing of water quality Contractor has been instructed to get regular testing of air water and noise as per EMP

5. Generation of Dust 5. Water sprinkling is being done regularly at construction site and construction material is being carried by covered truck.

Testing of ambient air quality

6.Emission from construction vehicles, equipment and machinery

6. Since no major equipment is being used at site storage of Fuel is not required. Fuel is being carried as per requirement

Testing of ambient air quality

7. Noise from construction equipment 7. Only Vibrators and one concrete mixer is being used. No Major vehicles / equipment’s are present at site.

Testing of ambient noise quality

8. Material Handling at Site 8.Proper Material handling is being done for storage and disposal as per EMP

No issue

19. Disposal of Construction Waste/Debris/Cut Material

9. Demolished waste and excavated material from working site and use / disposal of the same as per Mitigation measures in EMP

No issue

10. Safety Measures During Construction 10. Using Personal Protective Equipment like helmets and shoes are being used by workers

No issue

Contractor has been instructed to provide other cautionary signage at Construction Sites

11. Risk caused by Force Majeure 11. NA

12. Malaria Risk 12. Precaution being taken as per EMP No issue

O & M impacts 1. Environmental Conditions Not Yet Started

2. Adequate drainage of site area

Page 67: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

65

Table 7 (viii) : EMP Monitoring Status Chart- Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

UK/IDIPT-III/KOT/01

Location 1 Siting of facilities 2 Lack of sufficient Planning 3 Impact on archaeological remains 4 Other

PMU & DSC 1 Construction camp established

in open land near multi facility

complex. It is away from habitation.

2. IEE and EMP have been prepared and EMP being complied with. The project planning done in advance and discussed in UTDB during DPR preparation. 3. No site of archaeological remains in the vicinity 4. Upper Ganga canal close to

project influence area

1- Sanitation facilities at construction camp ( Toilets) not being maintained properly and many a times are not operational. 2- Contamination of Upper Ganga canal water with earth and other construction material 3- Bathing facilities for Women workers are not being maintained properly. 4- Construction waste was seen scattered near camp site at Multi facility Center.

1- The contractor has been instructed to maintain sanitation facilities properly. 2- A strict vigil is kept by the DSC staff at site to ensure that no excavated earth or construction materials find their way in the canal. 3- The contractor has been instructed to upgrade bathing facilities for women. 4- The Contractor has been instructed to segregate the construction waste at camp site. 5- The contractor has been instructed to obtain permission for planned bore well(at integrated multi facility complex) from municipal authorities.

Pre-construction activities by

the Contractor

1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction

Contractor & DSC 1 The construction camp established and workers are using this as accommodation. Drinking water facilities available at site. The source of water is existing bore well 2. No protected area within 200 m

No issue as pre construction activities stage in the project is over.

Not Applicable

Page 68: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

66

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

of project site. The construction/ work areas were delineated in the beginning of construction. 3. No impact on traffic movement during construction as there is no frequent to and fro transportation of materials from the construction camp site. The project site is on extreme left edge of NH-58 and construction activities are not interfering with traffic movement and tourist movement. 4. This activity is over in the sub project. 5. Potable drinking water is being made available for the construction force through the existing bore well. 6. The waste material generated due to clearance and demolition activities has been used to the extent possible. Balance has been used in the fill works. 7. The waste generated during the construction is segregated and stored at the site for possible reuse later. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU

Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations

Contractor and DSC 1. The main construction materials

at present being used are bricks,

cement, sand and steel bars. These

1- Based on the instructions the contractor has constructed toilet block. The

1- The contractor has been

advised to keep the toilet

block neat and clean and

Page 69: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

67

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction

vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk 16. Chance archaeological finds 17.Religious structures 18. Construction Staff causing

disruption to migratory birds

are being stocked properly.

2. The contractor is obtaining sand and sub grade from the licensed quarries. No borrow pit operations have been carried out so far. 3- The top soil generated at Integrated facility complex site at Haridwar excavation was kept aside. Later it has been used in landscaping works. Similarly excavated scarified bituminous material at Solani Park has been used in the fill works . 4. The soil erosion issue is not there as there is no cutting or steep slope issues involved in the project. 5. The fuel and lubricants are not stored at site as project is small in nature. These are purchased from market as per needs. There is no maintenance of vehicles at site also. Hence there is no issue of soil and water pollution. 6. The excavated earth was generated at Integrated Multi Facility Complex. This earth was kept aside and is away from Upper Ganga canal. This earth after completion of foundation works has been used in filling. Hence chance of any siltation in Canal

toilet block maintenance and functioning is an issue. 2- Some construction waste was seen scattered near the camp site at multi facility site. 3- The PPE usage by the construction work force is very poor. 4- Bathing facilities for women workers 5- NOC from municipal authorities for planned bore well at multi facility complex.

keep these in operational

conditions.

2- The contractor has

been instructed to

segregate the waste at one

location at integrated

facility complex and

enclose it with caution

tape.

3- The contractor has

been advised to enforce

the usage of PPEs by the

workforce.

4- The contractor has been

advised to improve and

maintain bathing facilities

for women work force.

5- The contractor has been

advised to improve the

housekeeping at Integrated

Multi Facility Complex site.

6- The contractor has been

instructed to obtain NOC for

planned bore well from the

Municipal Authorities at

Haridwar.

Page 70: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

68

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

due to construction activities. 7. Generation of dust is on account of material handling at site. Necessary dust suppression measures such as water spray are taken up. 8. The construction vehicles usage is not much in the project. It is only for the transportation of construction materials and a small concrete mixer at site. The trucks carrying construction material have pollution under control certificates. The mixer small generator and this operates intermittently. 9. In the current project the only noisy equipment used is concrete mixer and it is operated intermittently. No excess noise generation is on account of construction activities. Noise monitoring is being taken up regularly. 10. The material handling at site is not proper as most of the workers were not seen using personal protective equipment during material handling. 11. Brick work of guard wall construction is almost over in about 5.5 km length. Similarly pathway work at Solani Park Roorkee site

Page 71: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

69

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

has also been completed for 1 km length. in these works, there was generation of construction waste. The tile work on Guard Wall is in progress. 12. The construction camp has toilet black. The toilets are not being maintained clean and tidy. 13. The majority of the construction work force is not using personal protective equipment ( PPE) such as hand gloves, shoes, helmets, jackets , etc. The reason given is that they feel uncomfortable. 14. Risk Force Majeure situation has not occurred so far. Necessary action will be taken as per contract provisions 15. The project sites as well as workers' camp are close to Upper Ganga canal. There are chances of mosquito breeding although no water accumulation takes place at construction site. The contractor is instructed to keep good housekeeping at construction workers' camp and DSC staff at site monitors. Malarial risk is not anticipated. 16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC , if any

Page 72: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

70

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

chance find is found. Necessary procedure such informing to state Archeological Department and waiting for their instruction, will be followed. 17. The project is not impacting any religious structures 18 . The project site is located in a urban area and there is neither any route of migratory birds or any location where migratory birds are visiting.

Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto

the existing waste disposal

facilities

PMU, UTDB The project not yet reached

Operation phase

Not Applicable Not applicable

Page 73: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

71

Table 7(ix): EMP Monitoring Status Chart- Development of Tourism Infrastructure in Sem Mukhem

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

UK/IDIPT-III/KOT/02

Location impacts 1. Siting of facilities 2 Lack of sufficient planning 3.Impact on archaeological remains 4. Other

PMU & Line Agency 1. The Development of Tourism Infrastructure at Sem Mukhem has been finalised in consultation with administration and local needs and meets all requirements of local laws. 2. No Action but IEE and EMP have been prepared as part of sub project preparation. The project components have been finalised after detailed review of DPR and local level consultations. 3. No site of archaeological remains in the vicinity, hence no action needed 4. The project being at higher

elevation, accessibility may be

limited during extreme weather

conditions.

No issue related to location finalisation. The sub project components are well defined.

This stage in the sub

project is over .

Design & pre construction

impacts

1. Impact on sensitive areas 2. Slope stability related issues 3. Increased storm water runoff 4. Impact on ground water quality 5. Impact on aesthetic appeal 6. Integration of energy conservation

DSC & PIU 1. No acquisition of any forest ( reserved/protected) area, hence no impacts and no action needed on this account. 2. The sub project construction works on pathway are on slope. The natural slope is maintained in the pathway and other construction works. The side slopes around pathway are compacted. 3. The storm water runoff issue is not be there at rest shelter or at

This stage in the sub project is over. Hence this is not applicable.

None as this is not applicable to reporting period.

Page 74: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

72

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

pathway as these are in hilly terrain having quick natural drainage. No storm water runoff generation seen in Mukhem village. 4. No impact on ground water quality. Water requirement for construction is very less (<4000 liters/day) and is being met from nearby natural reservoir. The minor requirement for construction has no impact on reservoir or surrounding eco system. The waste water generation is well taken care. 5. No impact on aesthetic appeal due to construction works. 6. Integration of Energy conservation measures have been planned in the project design. The project plans to use solar lighting system and LED lighting.

Pre-construction activities by

the Contractor

1.Construction Camp 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC 1. The contractor has hired a house in the vicinity of Mela ground (location of rest shelter) and provided drinking water and sanitation facilities at this house. This house acts as construction camp. 2. The project components are not using any area of forest although forest area is around pathway. The pathway is being constructed on already existing track outside forest area. The works/construction areas

The pre construction

activities are over and

construction works are in

progress at all locations of

sub project. Hence this is

not applicable.

Not applicable for the reporting period.

Page 75: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

73

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

were delineated at the start of construction phase. 3. No impact on traffic movement, due to construction activity, has been noticed as vehicular movement due to traffic is insignificant. The tourist movement to Sem Nagraja temple has also not been affected. 4. The site clearance activities have been completed. No tree cutting was necessary. 5. The drinking water requirements are being met from nearby natural sources. 6. Some waste material is generated rest shelter site due to construction activities. The waste disposal site will be identified in the later phase of construction period depending upon quantity of waste material to be disposed off. Most of the waste will be used in reservoir fill works. 7. The waste material generated is

being collected and stored aside.

The disposal plan will be prepared in

later phase of construction period.

Construction impacts 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion

Contractor and DSC 1. The contractor is using cement, steel, sand and subgrade at pathway sites, temple site and at Mela Ground sites. Storage of construction material is not much as significant construction work has been completed.

1- Environmental

monitoring for winter and

summer season not

submitted.

2- Use of personal

protective equipment at

1- The contractor has not carried out monitoring for winter season. Due to this DSC organised environmental monitoring for winter

Page 76: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

74

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction

vehicles and equipment 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Safety measures 13. Risks force majeure 14. Malaria risk 15. Chance archaeological finds 16.Religious structures 17. Construction Staff causing

disruption to migratory birds

2. The contractor is obtaining sand and subgrade from the licensed quarries and has been instructed to submit copy of license of the quarry. The borrow pits for the projects have not been operated so far. 3. The excavated earth for foundation works of rest shelter has been kept aside and will be reused for filling. The Mela ground is a waste and barren land so top soil is of no importance as it has rocky and non fertile nature. The excavated earth from reservoir deepening near Mela ground has also been kept aside and being used in filling works of retaining wall of this reservoir. 4. So far in the construction works no soil erosion issue has been identified. In the pathway works natural slope is maintained. At reservoir site, side slopes will be compacted and stabilized. 5. The fuel and lubricants are not stored at site and these are purchased on need basis so question of water pollution due to fuel and lubricants is not there. 6. The project involves deepening of reservoir near Mela Ground. The reservoir excavation work has been completed. The excavated earth

temple site to be enforced.

3- Waste material from rest

shelter construction site and

excavated earth from

reservoir site to be stored

and reutilized.

4- Proper storage of

construction material at

Mukhem village temple site

and pathway site at

Mukhem village so that

villagers' movement is not

restricted.

season after taking approval from PMU. 2- The contractor has been advised to enforce use of PPEs during the construction works. 3-The contractor has been instructed to prepare plan for waste disposal from various sub project locations specially the excavated earth from the reservoir site. The earth should be used in fill works of retaining wall of reservoir. 4- The contractor has been instructed to stabilize side slopes of reservoirs through compaction to avoid soil erosion.

Page 77: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

75

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

mainly comprising of silt has been kept aside. The side slopes of reservoir are being stabilised through compaction and pitching. The excavated earth is being used in fill works of retaining wall of this reservoir. 7. The generation of dust is there from construction material handling such as sand, sub grade and cement. Necessary measures for dust suppression are taken at site as per needs. These measures include water spray and keeping sand and cement inside the cover shed. Keeping sand piles in semi wet form through water spray. 8. At project site no construction vehicles are used except trucks bringing construction materials at site. These trucks/tempos have pollution under control certificates. The only construction equipment used at site is currently mixer, which is Diesel Generator operated. This mixer is operating intermittently and as such there is no issue of air emissions. The contractor has been advised to carry out ambient air quality monitoring at project site to check efficacy of mitigation measures. 9. In the current construction phase of project mixer is the only noise

Page 78: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

76

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

generating equipment is in operation. No noise issue has been felt during the site visits. This is operated intermittently. At Mukhem village temple site, and at pathway construction works are not taken up during night time. Noise level monitoring is being taken up regularly as per monitoring plan. 10. The material handling by the workers at site is proper as construction were seen using personal protective equipment such as gloves, shoes, helmets, etc. Some workers were seen not using personal protective equipment at Mukhem village Temple site. The contractor has been instructed to enforce use of personal protective equipment. 11. At present construction waste /debris generation was seen at rest shelter site at Mela Ground. The excavated earth has also been generated at Reservoir site due to deepening. The maximum construction waste will be reutilised. The material which cannot be used will be disposed off. For this a disposal plan will be prepared in later phase of construction period. The contractor has been advised to segregate waste and store at one place at Mela Ground.

Page 79: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

77

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

12. The contractor has procured personal protective equipment such as helmets, gum boots, jackets, gloves, etc. These are being used. Some of the workers were seen not using PPEs particularly at Mukhem village temple site. The contractor has been advised to enforce use of PPEs. The work force of the contractor has been sensitized for use of PPEs by the DSC environmental expert during site visits. 13. So far conditions for Force Majeure have not been faced at the project site. 14. The project site being at an elevated height in a hilly terrain where low temperatures prevail. No mosquito breeding has been felt. However, contractor has been instructed to take necessary measures in consultation with local state health department. 15. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC , if any chance find is found. Necessary procedure such informing to state Archeological Department and waiting for their instruction, will be followed.

Page 80: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

78

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

16. The existing temple at Mukhem village is being renovated so this will have a positive impact. The facilities being created at Mela ground will enhance pilgrimage at Sem Nagraj temple, so project overall will have positive impact on Religious structure. 17. No action needed as the project site is not close any route of migratory birds or any location where migratory birds are visiting.

O & M impacts 1. Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities

PMU,PIU and Contractor (only

during defect liability period)

1-Not Applicable as project not yet completed and reached O&M Phase.

Not Applicable as project

has not yet reached O&M

phase.

Not Applicable

Page 81: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

79

Table 7(x): EMP Monitoring Status Chart- Development of Traditional medicine and Yoga Training Centres IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

UK/IDIPT-III/GEN/03

Location impacts Lack of sufficient planning to

assure long term sustainability of

the facilities and ensure

protection specially from

earthquake and other natural

disasters . Finalization of

locations of project sites

PMU & Line Agency 1. The subproject has been finalised in consultation with GMVN, KMCN and tourist needs in the TRHs. The facilities have been planned in the existing buildings/ premises which have withstood past earthquake events also. IEE and EMP have been prepared as part of sub project preparation. The project components have been finalised after detailed review of DPR and adequate consultations. All the locations of sub-project have been planned within the existing and operating Resorts/TRHs of KMVN and GMVN.

No issue related to location finalisation. The sub project components are well defined.

Pre-construction activities by

the Contractor 1. Layout of components to

avoid impacts on the aesthetics

of the sub-project sites

2. Increased storm water runoff

from alterations of the site’s

natural drainage patterns due to

landscaping, excavation works,

construction of parking lots, and

addition of paved surface at sub-

project sites

Contractor & DSC 1. Works presently are carried out only in 02 Tourist Rest Houses, Dhanaulti and just started in Sukhatal. 2. Works are carried out within existing Tourist Rest House only and no natural drainage patterns are disturbed. No additional parking lots or landscaping planned as part of sub-project.

Construction impacts 1.Construction Camps - Location, Selection, Design and Layout 2.Site clearance activities,

Contractor and DSC 1. Magnitude of works very less. No construction camp required in Dhanaulti and Sukhatal sites.

2. Works carried out within

1. Use of personal

protective equipment at

Sukhatal site to be enforced.

2- The contractor has been advised to enforce use of PPEs during the

Page 82: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

80

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

including delineation of construction areas at sub-project sites 3.Drinking water availability for construction crew 4. Waste disposal 5. Improper stockpiling of Construction Material 6.Soil and Water Pollution due to fuel and lubricants, construction wastes 7.Siltation of water bodies due to spillage of construction wastes 8. Generation of dust 9.Emission from construction vehicles, equipment and machinery 10. Noise pollution 11.Material handling at site 12.Disposal of construction waste/debris 13.Safety measures 14.Clearing of Construction Sites

existing TRHs only. 3. Drinking water is being made

available from existing supply of TRHs.

4. At present magnitude of waste generation is very less. Presently, it is being stored at site, for reuse/ adequate disposal at later stages. The contractor has been advised to segregate waste and store at one place in the TRH.

5. Since in both sites, modification/ refurbishment of existing TRHs is carried out, Storage of construction material is not much which is segregated and stored properly at site.

6. Since in both sites, modification/ refurbishment of existing TRHs is carried out, storage of fuels is not required, and is brought from market as per needs. Construction waste is also not much which is segregated and stored properly at site.

7. Works carried out within existing TRH, no issues of siltation of water bodies

8. The generation of dust is there from construction material handling such as sand, sub grade and cement, though in very less amount presently. Necessary measures for dust suppression are taken at site as per needs. These measures

2. First aid kit suitably

equipped with all required

medicines to be provided at

all sites.

construction works. 3- The contractor has been instructed to provide first aid kits at all sites.

Page 83: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

81

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

include water spray and keeping sand and cement inside the cover shed. Keeping sand piles in semi wet form through water spray.

9. At both project sites, no construction vehicles are used except trucks bringing construction materials at site. The magnitude of works being very less, the frequency of vehicles is very less.

10. In the current construction phase works are carried out only in Dhanaulti TRH and started in Sukhatal. No major noise generating equipment is in operation. No noise issue has been felt during the site visits. works are not taken up during night time. 11. The material handling by the workers at site is proper as construction labour were seen using personal protective equipment such as gloves, shoes, helmets, etc. Some workers were seen not using personal protective equipment at Sukhatal site. The contractor has been instructed to enforce use of personal protective equipment at all sites. 12. The contractor has procured personal protective equipment such as helmets, gum boots, jackets, gloves, etc. These are being used. Some of the workers were seen not

Page 84: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

82

IEE/EMP Component Environmental issues Responsibility Actions during Reporting Period Compliance issues Corrective actions

using PPEs at Sukhatal site. The contractor has been advised to enforce use of PPEs. 13. No action, as works have not completed. 14. Monitoring has not been carried out in the reporting period, since works are carried out only in 02 TRHs out of which, works in Sukhatal TRH have just started.

O & M impacts Waste oil generation on account of Panchkarma facilities and its safe disposal Safety risks Unhygienic conditions due to poor maintenance of sanitation facilities and irregular solid waste collection

PMU,PIU and Contractor (only during defect liability period)

1-Not Applicable as project not yet completed and reached O&M Phase.

Not Applicable as project has not yet reached O&M phase.

Not Applicable

Page 85: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

83

7. Approach & Methodology engaged for environmental monitoring of the project

15. Continuous monitoring of EMP implementation is being carried out by DSC, PIU and PMU.

16. Concerned staff of DSC and PIU visit the construction sites and report to Team Leader DSC and PMC

about issues/ problems related to environmental non-compliance. Necessary directions, in case of non-

compliance are being issued to the contractors on the site and through letters about the procedures to

resolve the problems/issues or requirements. The Safeguards Staff of DSC conduct regular site visits to

monitor the implementation of safeguards measures on sites.

8. Monitoring of environmental receptors/ attributes

Monitoring basis

17. Monitoring for the implementation of Environmental Monitoring Plan/Management Plan is required to be

done to check if any adverse impact is being caused by the construction activities. The monitoring of

these variables is to be carried out in construction sites within 100 m impact zone of the sub project.

18. The monitoring of environmental variables is to be carried out as per the agreed Environmental

Monitoring Plan.

Type of environmental receptor/ attribute to be monitored

19. The environmental attributes to be monitored include the air, noise and water quality parameters at the

construction sites in sub project sites. The air quality parameters monitored include RSPM (PM10),PM2.5

SO2 and NO2. The water quality parameters include temperature, pH, electrical conductivity (EC),

dissolved oxygen (DO), biochemical oxygen demand (BOD), total suspended solids (TSS), total

dissolved solids (TDS) and turbidity. In case of noise the day and night time Leq values are monitored.

Page 86: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

84

Methods of monitoring and equipment used

20. The parameters and standard methodology used for monitoring is given in Table 8.

Table 8: Parameters and Methodology for Environmental Monitoring

Parameter Methodology

(PM10) High Volume Sampler method (attached with cyclone)/Respirable Dust samplers.

(PM2.5) PM2.5 sampler, Gravimetric method

SO2 IS Modified West and Gaeke Method

NO2 Jacob &Hochheiser Modified (Sodium Arsenite) Method.

Noise Level Direct Reading Sound Level Meter.

Temperature Digital/Mercury Thermometer Method.

pH Electrometric Method.

EC Electrometric Method.

DO Winkle’s Method Using Azide Modification

BOD5 Five Days BOD as per APHA 2005

TDS Digital Meter Method.

TSS Gravimetry (Filtration and Drying at 105oc)

Turbidity Nephelo Turbidity Method.

Page 87: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

85

9. Implementation of Environmental Monitoring Plan

21. Implementation of Environmental Monitoring Plan for sub projects is shown in Table 9.

Table 9 (i): Implementation of Environmental Monitoring Plan- For Projects under DSC Kotdwara

Component Periods of

monitoring Parameters/Pollutants Standard

Base

line

status

Monitoring

result

during

project

Implementa

tion

Remarks

UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

Noise Winter

Season

Sound Level Leq. dB(A) Noise

Standards for

55 dB( A)

for Day Time

and 45 dB( A)

for Night

Time

- (i) Integrated

Facility

Complex

Haridwar

1-Leq ( Day)

=53.9.0 dB( A)

v

2- Leq (Night)

= 44.2 dB(A)

v

3-Leq (Min)

=41.6 dB(A)

4- Leq (Max)

=65.5 dB(A)

(ii) Monitoring

was not

carried out at

Solani Park

Roorkee site

as no

construction

work was in

progress at

this site.

The values are well

within the stipulated

limits.

Air Quality Winter

Season

SO2, NOX, CO , PM10 and

PM2.5

Monitoring at at Integrated

Facility Complex site at

Haridwar

NAAQS

Standards

-

Industrial,

Residential,

Rural and other

Areas

All parameters of

ambient air quality are

well within the limits.

Page 88: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

86

Component Periods of

monitoring Parameters/Pollutants Standard

Base

line

status

Monitoring

result

during

project

Implementa

tion

Remarks

Particulate Matter < 10 micron 100

- 99.2 ug/m3

Particulate Matter < 2.5

micron

60µg/m3

- 53.8 site

Sulphur dioxide,(SO2 )

80 µg/m3

11.0

Nitrogen dioxide(NO2) 80 µg/m3

18.1 ug/m3

Carbon Monoxide (CO) 02 mg/m3

for 08 hrs

0.90 mg/m3

Water Quality Winter

Season

1- Drinking Water at camp

and Construction site

(Ground Water)

Drinking

water

standards

specified in

IS: 10500

-

1- Colour-= <1

Hazen Unit

2- Odour=

Agreeable

3-pH= 6.68

4- Total

Hardness as

CaCO3= 176

mg/l

5- TDS= 384

mg/l

6- BOD= no

test done

7- Total

Coliform= Not

detected

8- Iron as Fe

<0.18 mg/l

9- Chloride as

Cl= 80 mg/l

11- Fluoride as

All parameters of

drinking water at

Haridwar Integrated

facility Complex are

well within the limits of

Drinking water specified

in IS: 10500

Page 89: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

87

Component Periods of

monitoring Parameters/Pollutants Standard

Base

line

status

Monitoring

result

during

project

Implementa

tion

Remarks

2- Upper Ganga Canal near

Haridwar Integrated Facility

Complex Site

CPCB

Standards for

Surface

Water Quality

F < 0.20 mg/l

1-PH=7.4

2- Dissolved

Oxygen =6.1

mg/l

3- BOD (3 Days

at 27 oC)=

< 1mg/l

4- COD =

<5mg/l

5-Electrical

Conductivity=

283 mg/l

6- Ammonia=

<10 mg/l

7-Coliform =

Absent

Dissolved Oxygen, pH,

BOD and coliform

bacteria parameters

meet the CPCB norm

for surface water

category A.

UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in Sem Mukhem

Noise Winter

Season

Sound Level Leq. dB(A) Noise

Standards

for 55

dB( A) for

Day Time

and 45 dB(

A) for Night

Time

- Leq ( Day) at

Mela Ground

- 51.0 dB(A)

Leq (Night) at

Mela Ground

=40.6 dB(A)

Leq (Min) at

Mela Ground

=39.6 dB(A)

Leq (Max) at

Mela

Ground=

57.2 dB(A)

The noise levels

are well within limits

during day and night

times.

Page 90: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

88

Component Periods of

monitoring Parameters/Pollutants Standard

Base

line

status

Monitoring

result

during

project

Implementa

tion

Remarks

Air Quality Winter

Season

SO2, NOX, CO , PM10 and

PM2.5

NAAQS

Standards

-

Industrial,

Residential,

Rural and

other Areas

All monitored ambient

air quality parameters

are well within the

stipulated limits at Mela

Ground

Particulate Matter < 10 micron 100

72.3 ug/m3 at

Mela Ground

Particulate Matter < 2.5 micron

Sulphur dioxide,(So2 )

Nitrogen dioxide(NO2)

Carbon Monoxide (CO)

60µg/m3

80 µg/m3

80 µg/m3

02 mg/m3

for 08 hrs

32.8 ug/m3

10.6 ug/m3

17.40 ug/m3

0.2 mg/m3

Page 91: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

89

Component Periods of

monitoring Parameters/Pollutants Standard

Base

line

status

Monitoring

result

during

project

Implementa

tion

Remarks

Water Quality Winter

Season

Parameters specified for

Drinking water in IS: 10500

Drinking

Water

Standards

specified in

IS: 10500

1- Colour = <1

Hazen units

2- Odour

=Agreeable

3- Turbidity =

3.4 NTU

4- pH= 6.62

5- Total

Hardness = 96

mg/l

6- Iron as Fe =

0.16 mg/l

7- Chlorides=

20 mg/l

8- Fluoride <

0.20 mg/l

9- TDS- 132

mg/l

10- Total Coli

form - Not

Detected

All monitoring

parameters are for

drinking water available

at Mela ground where

construction works were

in Progress. The

monitoring parameters

of drinking water are

well within the stipulated

limits of Drinking Water

specified in IS: 10500.

Page 92: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

90

Table 9 (ii): Implementation of Environmental Monitoring Plan- For Projects under DSC Bhimtal

Component Periods of monitoring

Parameters/ Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

Restoration and Adaptive Reuse of Champawat Fort (Banasur)

Noise (near construction site)

02/02/2017 to 03/02/2017

Sound Level Lmax, Lmin. dB(A)

Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Residential Zone)

Lmax -50.8(Day), 42.2 (Night) dB(A)

Lmax -52.8 (Day), 44.8 (Night) dB(A)

Values are well within permissible level

Lmin – 40.3(Day), 34.5 (Night) dB(A)

Lmin – 41.3Day), 33.4 (Night) dB(A)

Leq – 43.2(Day), 35.2 (Night) dB(A)

Leq – 44.7 (Day), 38.9(Night) dB(A)

Air Quality (near construction site)

02/02/2017 to 03/02/2017

SO2, NOX, CO, PM10 and PM2.5

NAAQS Standards Baseline Status Near Construction site,

All parameters of ambient air quality are well within the limits. Particulate Matter < 10

micron 100 µg/m3

60.10 µg/m3 64.20 µg/m3

Particulate Matter < 2.5 micron

60µg/m3

34.10 µg/m3 24.60 µg/m3

Sulphur dioxide,(So2 ) 80 µg/m3 7.10 µg/m3 8.40 µg/m3

Nitrogen dioxide(NO2) 80 µg/m3 19.30 µg/m3 21.30 µg/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.20 mg/m3 0.25 mg/m3

Air Quality (near back side of fort)

02/02/2017 to 03/02/2017

SO2, NOX, CO , PM10 and PM2.5

NAAQS Standards Baseline Status Near Back Side of Fort

All parameters of ambient air quality are well within the limits.

Particulate Matter < 10 micron

100 µg/m3 62.10 µg/m3 66.80 µg/m3

Particulate Matter < 2.5 micron

60µg/m3 30.15 µg/m3 28.15 µg/m3

Sulphur dioxide,(So2 ) 80 µg/m3 7.18µg/m3 8.48 µg/m3

Nitrogen dioxide(NO2) 80 µg/m3 17.10µg/m3 19.50 µg/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.22 mg/m3 0.28 mg/m3

Water Quality Drinking water Village :-(Near Construction Site Champawat)

02/02/2017 pH CPCB Standards for Drinking Water Standards for drinking water specified in IS: 10500

7.20 7.12 All parameters of drinking water are well within the limits of Drinking water specified in IS: 10500

Colour <5 <5

Turbidity(NTU) BDL BDL

Odour Agreeable Agreeable

Taste Agreeable Agreeable

Total Hardness mg/L 189.00 185.00

Calcium as Ca 70.20 74.10

Alkalinity mg/l 138.00 148.00

Chloride mg/l 20.10 22.30

Magnisium and Mg 18.10 20.20

Total Dissolved Solids mg/l

325.24 320.14

Iron mg/l 0.10 0.14

Copper mg/l <0.05 <0.05

Total Coliform 100 ml. at <2/100ml <2/100ml

Page 93: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

91

Component Periods of monitoring

Parameters/ Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

37℃ (MPN)

E-Coli / 100ml(MPN) Absent Absent

Conservation of Cultural Heritage and Urban Place- making in Nanital

Noise (At Near Construction Site Library)

28/01/2017 to 29/01/2017

Sound Level Lmax, Lmin. dB(A)

Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Commercial Zone)

Lmax -52.3(Day),43.1 (Night)dB(A) Lmin – 32.1(Day),35.2 (Night)dB(A) Leq- 44.2, 38.1

Lmax – 51.3(Day), 44.3 (Night)dB(A) Lmin – 37.2(Day), 32.5 (Night)dB(A) Leq- 43.5 (Day) , 39.3 (Night)

Values are well within permissible level

Noise (back site, library)

15.11.2016 Sound Level Lmax, Lmin. dB(A)

Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Commercial Zone)

At Near Back Side Library Lmax -53.7(Day),43.1 (Night)dB(A) Lmin – 38.1(Day),31.8 (Night)dB(A) Leq- 42.0, 37.2

Lmax -53.7 (Day),43.1 (Night)dB(A) Lmin – 38.1 (Day), 31.8 (Night)dB(A) Leq- 42.0 (Day), 45.0 (Night)

Values are well within permissible level

Air Quality (Near construction site, Library)

28/01/2017 to 29/01/2017

SO2, NOX, CO , PM10 and PM2.5

NAAQS Standards Baseline Status Near Construction Site, Library

All monitored ambient air quality parameters are well within the stipulated limits of air quality.

Particulate Matter < 10 micron

100 66.18 ug/m3 63.88 ug/m3

Particulate Matter < 2.5 micron

60µg/m3 35.10 ug/m3 25.30ug/m3

Sulphur dioxide,(So2 ) 80 µg/m3 7.34ug/m3 9.34 ug/m3

Nitrogen dioxide(NO2) 80 µg/m3 18.15ug/m3 22.15 ug/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.20 mg/m3 for 08 hrs

0.24 mg/m3 for 08 hrs

Air Quality (Near back side library)

28/01/2017 to 29/01/2017

SO2, NOX, CO , PM10 and PM2.5

NAAQS Standards Baseline Status Near back side library

Particulate Matter < 10 micron

100

68.15ug/m3 61.15 ug/m3

Particulate Matter < 2.5 micron

60µg/m3 38.12ug/m3 27.32 ug/m3

Sulphur dioxide,(So2 ) 80 µg/m3 9.08 ug/m3 8.28 ug/m3

Nitrogen dioxide(NO2) 80 µg/m3 17.10ug/m3 19.30 ug/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.20 mg/m3 for 08 hrs

0.26 mg/m3 for 08 hrs

Water Quality Drinking water (Tap Water)

28/01/2017

pH- CPCB Standards for Drinking Water Standards for Potable water

7.08 7.08 All parameters of drinking water are well within the limits of

Colour <5 <5

Turbidity –(NTU) BDL BDL

Odour – Agreeable Agreeable

Page 94: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

92

Component Periods of monitoring

Parameters/ Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

Taste – Agreeable Agreeable Drinking water specified in IS: 10500

Total Hardness mg/L - 432 190.15

Calcium as Ca- 168 78.30

Alkalinity mg/l 265 149.00

Chloride- mg/l 15.62 20.20

Magnisium and Mg- 64.42 19.15

Total Dissolved Solids – mg/l

420 308.30

Iron - mg/l 0.02 0.12

Copper mg/l <0.05

Total Coliform 100 ml. at

37℃ (MPN)

Absent <2/100ml

E-Coli / 100ml(MPN) Absent Absent

Water Quality Surface water –Naini lake

28/01/2017

pH- CPCB Standards for Surface water bodies Standards for Potable water

7.80 7.85

Colour <5 <5

Turbidity(NTU) BDL BDL

Total Hardness mg/L - 362.50 352.15

Calcium as Ca - 98.52 102.50

Total Alkalinity mg/l 271.44 253.40

Chloride- mg/l 65.30 64.15

Magnisium Hardness - 36.34 38.30

Sulfate as SO4- 52.30 51.82

Nitrate as NO3 2.44 2.42

Flouride as F 0.8 0.54

Sodium as Na – 19.70 19.32

Potassium as K- 3.70 3.85

TKN as N- 1.40 1.34

Total Phosphorous 0.26 0.22

COD- 4.15 4.10

Phenolic Compound <0.002 <0.002

Iron as Fe mg/l 0.15 0.12

Boron - 0.26 0.24

Sodium Absorption ratio - 2.84 2.72

Free Ammonia as N- 0.82 0.68

Dissolved Oxygen - 7.00 7.00

BOD(3 days at 27) - 10.00 12.00

Zinc as Zn- 0.14 0.12

Arsanic as As -<0.012 <0.012

Mercury as Hg <0.002 <0.002

Total dissolved Solids mg/l

420 375

E-Coli / 100ml(MPN)

Restoration and Adaptive Reuse of Almora Fort (Rani Mahal)

Noise (Near Back Site)

30/01/2017 to 31/01/2017

Sound Level Lmax, Lmin. dB(A)

Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Residential Zone)

Lmax -48.2(Day),40.3 (Night)dB(A) Lmin – 32.1(Day),32.8

Lmax -52.7 (Day), 42.3 (Night)dB(A) Lmin –

Values are well within permissible level

Page 95: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

93

Component Periods of monitoring

Parameters/ Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

(Night)dB(A) Leq – 43.4(Day),38.1 (Night)dB(A)

38.1(Day), 32.8 (Night)dB(A) Leq – 47.8 (Day), 36.2 (Night)dB(A)

Noise (Near Construction Site)

30/01/2017 to 31/01/2017

Sound Level Lmax, Lmin. dB(A)

Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Residential Zone)

Lmax -52.0(Day),42.4 (Night)dB(A) Lmin – 44.1(Day),34.3 (Night)dB(A)

Lmax – 49.9 (Day), 39.8 (Night)dB(A) Lmin – 39.2 (Day), 32.5 (Night)dB(A) Leq – 45.3 (Day), 36.4 (Night)dB(A)

Values are well within permissible level

Air Quality (Near Construction Site)

30/01/2017 to 31/01/2017

SO2, NOX, CO , PM10 and PM2.5

NAAQS Standards

All monitored ambient air quality parameters are well within the stipulated limits of air quality.

Particulate Matter < 10 micron

100 µg/m3

56.20 ug/m3 Near Vikash Bhawan Distt. Almora

61.45 ug/m3 Near Vikash Bhawan Distt. Almora

Particulate Matter < 2.5 micron

60µg/m3

29.33 ug/m3

25.40 ug/m3

Sulphur dioxide, (So2) 80 µg/m3

7.22 ug/m3

8.35 ug/m3

Nitrogen dioxide (NO2) 80 µg/m3

16.43 ug/m3

19.80 ug/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.3 mg/m3 for 08 hrs

0.24 mg/m3 for 08 hrs

Air Quality (Near Back side of Almora fort)

30/01/2017 to 31/01/2017

SO2, NOX, CO , PM10 and PM2.5

NAAQS Standards All monitored ambient air quality parameters are well within the stipulated limits of air quality.

Particulate Matter < 10 micron

100 µg/m3

61.81 ug/m3 63.70ug/m3

Particulate Matter < 2.5 micron

60µg/m3

23.09ug/m3

26.65ug/m3

Sulphur dioxide,(So2) Nitrogen

80 µg/m3

6.50ug/m3

9.42ug/m3

dioxide(NO2) 80 µg/m3 19.22 ug/m3 20.75ug/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.38 mg/m3 for 08 hrs

0.26mg/m3 for 08 hrs

Water Quality Drinking water (Tap Water)

05-08/02/2017

pH- CPCB Standards for Surface water bodies and Drinking Water Standards for Potable

7.22 7.10 All parameters of drinking water are well within the limits of

Colour <5 <5

Turbidity –(NTU) BDL BDL

Odour – Agreeable Agreeable

Page 96: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

94

Component Periods of monitoring

Parameters/ Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

Taste – water Agreeable Agreeable Drinking water specified in IS: 10500

Total Hardness mg/L - 345.0 178.0

Calcium as Ca- 86.55 70.20

Alkalinity mg/l -268.00 142.00

Chloride- mg/l 70.40 21.32

Magnisium and Mg 28.62 19.30

Total Dissolved Solids mg/l

365.00 315.30

Iron as Fe mg/l 0.12 0.13

Copper as Cu mg/l <0.05 <0.05

Total Coliform 100 ml. at

37℃ (MPN)

<2/100ml <2/100ml

E-Coli / 100ml(MPN) Absent Absent

Component Periods of monitoring

Parameters/Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

UK/IDIPT/III/BHT/07 – Pithoragarh Fort

Ambient Noise Level

23-05-2015 Sound Level Leq. dB(A) AAQ Standards for noise (Day time) for silence zones 55 dB(A) For residential -- For commercial –65 dB(A) For Industrial –75 dB(A)

55.74 dB(A) Ambient Noise Level is not monitored during reporting period.

Contractor has been instructed and will be monitored in the coming quarter

Ambient Air Quality

30-05-2015 Concentration in Ambient :Air, as per NAAQS

NAAQS for Ecologically sensitive area as per CPCB notification , 18th Nov, 2009

Ambient Air Quality is not monitored during reporting period.

Contractor has been instructed and Will be monitored in the coming quarter

Particulate Matter <10 micron

100 54.2 µg/m3

Particulate Matter <2.5 micron

60µg/m3 24.5 µg/m3

Sulphur dioxide,(So2 ) 80 µg/m3 14.3 µg/m3

Nitrogen dioxide(NO2) 80 µg/m3 18.4 µg/m3

Carbon Mono-oxide (CO)

2.0 mg/m3 0.03

Drinking Water Quality

30-05-2015 Colour (Hazen) 5 Max <5 Water Quality is not monitored during reporting

Contractor has been instructed and Will be monitored in the coming

Page 97: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

95

Component Periods of monitoring

Parameters/Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

period. quarter

Odour Unobjectionable Unobjectionable

Taste Agreeable Agreeable

Turbidity (NTU) 5 Max <1

pH 6.5 – 8.5 7.12

BOD5 at 200C (mg/l) 2 ---

Total hardness mg/L 300 Max 94.2

Chloride mg/L 250 Max 24.9

Residual Free Chlorine mg/L

0.2

<0.2

Sulphats mg/L 200 max 11.9

Total Alkalinity mg/l 200 147.6

Flouride mg/L 1.0 0.24

Total dissolved solids mg/l

500 289

Iron (mg/l) 0.8 0.3

BACTERIOLOGICAL TESTS

Total Coli form Organisms 100 ml. at

37℃ (MPN)

<10 <2

Feacal Coli form / 100ml

Absent Absent

Page 98: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

96

Institutional Arrangements

Program Management

22. The Government of Uttarakhand through Department of Tourism (DOT) is the Executing Agency (EA).

The EA (i) assumes overall responsibility for the execution of the Project and reporting; (ii) engage

adequate permanent or fixed-term staff to implement the Project; (iii) setup a state-level project

management unit (PMU) and project implementation units (PIU); (iv) provide overall strategic guidance

on technical supervision and project execution; and (v) ensure overall compliance with the loan

covenants.

23. The implementing agency (IA) is the Uttarakhand Tourism Development Board (UTDB). The IA’s

responsibilities include (i) project planning and budgeting; (ii) day-to-day assistance, supervision and

guidance for the project implementation units and their consultants; (iii) review subprojects for due

diligence requirements and approve subproject proposals; (iv) bidding, evaluation and contract award;

(v) managing and disbursing funds; (vi) review compliance with loan covenants, contract specifications,

work plans and quality control; and (vii) consolidate and submit progress reports, finance and

accounting / audit reports, and matters requiring higher level decision to state-level empowered

committee (SLEC) and ADB.

24. A State-level empowered committee (SLEC) has been established in Uttarakhand, chaired by state’s

Chief Secretary, with Principal Secretary/Secretary of the Department of Tourism as member secretary

and comprised of secretaries from relevant line departments. The SLEC have been empowered to take

all decisions on behalf of the State and will (i) act as a policy making body, (ii) provide overall advice

and guidance to the State’s executing agency and PMU, and (iii) accord all approvals under the Project.

25. Dept. of Tourism (DoT) has established a PMU, headed by a full-time program director (PD), and

consisting of personnel drawn from relevant line departments and market. Project Management Unit

(PMU) is established in Dehradun for the overall project management. The PMU is the nodal agency for

overall management of all program activities and will be responsible for: (i) project planning and

budgeting; (ii) providing day-to-day assistance, supervision and guidance for the PIUs and their

consultants; (iii) reviewing subprojects to satisfy ADB’s due diligence requirements and approving

subproject proposals submitted by PIU and line departments; (iv) bidding, evaluation and contract

award; (v) managing and disbursing funds; (vi) reviewing compliance with loan covenants, contract

specifications, work plans and quality control; (vii) consolidating and submitting progress reports,

finance and accounting/audit reports, and matters requiring higher-level decision, to the SLEC and

ADB. The PMU will be supported by a team of consultants.

26. The sub-project is being implemented by the Project Implementation Unit (PIU) of IA, i.e. UTDB,

comprising of personnel drawn from relevant line departments and outside of government and headed

by a Project manager. 03 Project Implementation Units (PIU) have been established for each of the

three circuits namely Bhimtal, Dehradun and Kotdwar. The PIUs are responsible for: (i) prioritizing and

preparing subproject proposals; (ii) providing day-to-day assistance, supervision and guidance to the

design and supervision consultants; (iii) conducting detailed assessments and surveys including public

consultation and input from stakeholders; (iv) preparing detailed designs, specifications, schedule of

quantity, bidding documents, and related documentation; (v) implementing civil works and related

activities; (vi) reporting to PMU; (vii) preparing regular progress reports for the SLEC, the executing

agency and ADB through PMU; and (viii) supervising construction, conducting quality control, approving

Page 99: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

97

progress payments to contractors; and (ix) maintaining records and accounts on an up-to-date basis

and making these available to ADB, its missions, or auditors for inspection.

27. The Project Management Consultant (PMC) has been engaged to provide support to the PMU in overall

planning, risk management, implementation, monitoring and evaluation of projects under the

Investment Program. The PMC also assists the PMU and PIUs in meeting the relevant requirements of

ADB, Government of Uttarakhand, and Government of India for project implementation. The PMC

reports and works under the overall guidance of the PMU. The scope of services of the PMC includes

but not necessarily be limited to: (i) planning, reporting, and communication; (ii) establishment of

procedures and systems; (iii) review and preparation of plans, manuals and reports; (iv) overall

Investment Program management, monitoring and implementation of PPMS; and (v) social,

environmental, archaeological, occupational health and safety, community participation and gender

action compliance monitoring.

28. The Design and Supervision Consultants (DSC) have been engaged to provide all necessary support to

and coordination with the EA, IAs, PMU and any other consultants engaged by the authorities to

achieve the desired outcomes of the Investment Program. The DSC reports to and work under the

overall guidance of the PIUs. The scope of services of the DSC includes but not necessarily be limited

to: (i) surveys, verification of feasibility studies and base maps; (ii) project planning and management

support to the PIU; (iii) finalization of design criteria, preparation of manuals, guidelines and systems;

(iv) preparation of detailed design and bid documents; (v) construction management and contract

administration; (vi) environmental, social, archaeological, cultural heritage, community participation and

gender action compliance monitoring; and (vii) capacity building of the service providers for operational

sustainability.

10.1 Institutional Arrangements For EMP Implementation

29. The institutional arrangements specify the arrangements for the implementation of environmental

provisions of the entire project.

Project Management Unit (PMU)

30. A Safeguards Specialist (SGS) is positioned in the PMU, who is responsible for overall implementation

of the environmental safeguard provisions. To look into the matters of forest coordination, a Forest

Conservation Specialist is also placed in the PMU.

Project Management Consultant (PMC) and Design and Supervision Consultants (DSC)

31. Project Management Consultants (PMC) and Design and Supervision Consultants (DSC) have been

recruited to provide assistance to the PMU and PIUs respectively in project implementation. Within the

PMC team an Environment Safeguards Specialist is positioned to provide overall direction for

management of environmental issues, and technical support to the PMU including implementation of

the environmental requirements according to ADB requirements, and assist in monitoring impacts and

mitigation measures associated with sub-projects. Towards addressing the environmental issues in the

project components during design and implementation, the DSC includes provisions for inputs of

Safeguards Specialist Environment.

32. The Safeguards Specialist of the DSC team is responsible for preparation of the Environmental

Assessment documents in line with the Environment Assessment Review Framework (EARF) and

supervises the implementation of the EMP provisions in the various sub-projects.

Page 100: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

98

33. DSC Safeguard Specialist is placed in each of the three DSCs to support environmental management

functions including updating sub-project IEEs in respect to environmental management plans in

compliance with the ADB Safeguard Policy Statement, national and state level environmental policies,

rules and regulations, assisting in preparing IEEs, and assist in monitoring impacts and mitigation

measures associated with sub-projects. He is required to include mitigation measures in designs where

appropriate, and to specify other measures in construction contracts. In addition to addressing the

issues related to environmental management in the project, the DSC Specialist plays a central role in

ensuring capability building on Environmental Management of the PMU/PIU, Contractor and Line

Departments.

34. Contractors are required by their contracts to implement all specified mitigation, monitoring, and

reporting assigned to contractors as presented in sub-project IEE. Contractors have appointed

Environment and Safety Officers for implementation of environment and occupational safety provisions

at site.

35. Environmental monitoring is being undertaken by the PMU supported by the Safeguards Specialist of

DSCs and PMC

36. Contact Details of Safeguards Team is given below:

Unit Name Mobilized Since Phone E-mail

PMU

Ms. Anjali Semwal

April, 2013 +91-8191995004

[email protected]

PMC Mr. Navin Handa

Mr. Ardhendu Mitra

July 2016 – Till Feb, 2017*

July 2013 – Sep, 2015

*Expert has been demobilized since Feb, 2017. PMC has been requested for replacement of Expert.

+91-9599510994

[email protected]

DSC Dehradun

Mr. Ranjan Mallick

Mr. Abhay Srivastava

January, 2014 – Till date

April, 2013 – June, 2013

+91-94382000113

[email protected]

DSC Kotdwar

Mr. Shreeniwas Verma

October, 2013 – Till date +91 9811224458

[email protected]

DSC Bhimtal

Dr. A.K. Sharma

Dr. Aman Sharma

July -2015 to Till Date

March -2013 to May 2015

+91-09799242184

[email protected]

Page 101: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

99

10. Public Consultation Details

37. Meaningful Public Consultation has been done with the stakeholders and the Community, in all the

project areas. Details of Public Consultation held in the Reporting period are given in Table 10.

Consultation Photographs are provided in Annexure 2.

Table 10(i): Public Consultation Meetings for Tranche III sub-projects Under DSC Dehradun

Kartikeya Swami

Circuit Durgadhar

17.05.2017 Environmental awareness

to labourer and

Community Awareness

about operation and

maintenance

15 .Regarding the Safety Training to

Workers/Labour at Site: Safety issues like

Use of PPEs, and its advantage.

Kartikeya Swami

Circuit Durgadhar

15.06.2017 Community Consultation

about operation and

maintenance

12 Regarding the Operation & maintenance

of the works with the Durgadhar temple

committee

Kartikeya Swami

Circuit Tungeshwar

13.06.2017 Meeting with Tungeshwar

temple committee.

24 Regarding the Operation & maintenance

of the works and for conducting the

plantation event at Tungeshwar temple

Kartikeya Swami

Circuit Durgadhar

9.01.2017 Labour sensitization on

environmental and social

safeguards

20 Regarding the Safety Training to

Workers/Labour at Site

Rural Tourism

meeting Durgadhar

09.01.2017 Meeting with Durgadhar

villagers

22 Regarding the construction activity works

with the Durgadhar village committee.

Kartikeya Swami

Circuit Kartikeya

swami temple

8.01.2017 labour Orientation at

Kartikeya swami temple

site

18 Regarding the Safety Training to

Workers/Labour at Site: Safety issues like

Use of PPEs, and its advantage.

Rural Tourism

meeting

kartikswami

08.01.2017 Meeting with Kartikeya

swami temple committee.

19 Regarding the construction activity of on

going works with the Kartikeya swami

temple committee member.

Rural Tourism

Meeting at Kabiltha

5.01.2017 Meeting with Kabiltha

Kalidas committee and

villagers

31 Meeting with Kabiltha Kalidas committee

and villagers regarding ADB funded project

and give him brief description. And also

discuss about O&M of construction work.

Rural Tourism

Meeting at

Pogtha(Kanakchuri)

07.01.2017 Meeting with Pogtha

villagers

24 Meeting with Pogtha villagers Regarding

the construction activity of on going works.

Rural Tourism

Site visit at Mukku

village

10.01.2017 Meeting with Tungnath

temple committee at makku

village.

10 Meeting with the Tungnath Temple

committee Regarding the construction

activity of the works at makku Village

because Tungnath temple committee

belongs to makku village.

Rural Tourism

Site visit at

Tungeswar

11.01.2017 Meeting with Tungeshwar

villagers

43 Meeting with Pogtha villagers Regarding

the construction activity of the works.

Page 102: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

100

Table 10(ii): Public Consultation Meetings for Tranche III sub-projects Under DSC Kotdwar

Sl. No.

Activity /Event at a glance

Date Total

Participant Male Female Discussion/Suggestions

1 Health Minister, Govt. of Uttarakhand, Office, Kotdwara

03.01.2017 2 2 - Consultation with Health Minister Govt. of Uttarakhand and TL, DSC Regarding Kanvashram Project Under “Rural Tourism Sub-Proejct”. Its implementation, design and environmental measures considered.

2 UTDB Office, Dehardun 20.02.2017 and

21.02.2017

30 5 Workshop on Environment and Social Safeguards Regarding Implementation of Social and Environment Mitigation and Monitoring and Reporting System. In this workshop EMP implementation and lessons learnt were discussed. On social issues Gender Action plan and Resettlement Plan implementation were discussed. The queries of contractors and PIU staff on environmental and social safeguards were also replied.

3. Kuthar Village(Rural Tourism)

04.05.2017 40 35 05 Consultation was organized with community, DSC, PIU and NGO representatives The villagers made following suggestions:

1.The location of infrastructure facilities like lighting etc., to be evolved in consultation with them.

2. Sanitation facilities for tourists to be constructed.

Kanvashram

20/05/2017 20 18 2 A detailed public consultations was at Kanvashram site to generate awareness, consensus and also to get cooperation during implementation process by the local people, government officials etc. The following suggestions were made to incorporate during implementation.

1. There is a need to construct a cremation ground on the right bank of the river. It was

Page 103: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

101

Sl. No.

Activity /Event at a glance

Date Total

Participant Male Female Discussion/Suggestions

discussed in detail regarding the availability of the land. The representative of the Panchayat told that the government land is available to construct such cremation ground. According to them the current cremation ground is located at the proposed site of lake. Hence, it is required to be shifted.

2. For the selection of the trainee from the local youth needs to be done through a committee and the local villager, Panchayat representatives should be the committee members.

3. During construction, priority should be given to local laborers for employment.

4. Small contract like supply of sand, and other construction material should be done through the local contractors.

5. During training for income generation activities, skill development etc., priority should be given to women and gender specific training should be given which will help the empowerment aspects of the local women.

6. Provision of stipend, raw material, gadgets etc, should be provided to the trainees.

7. Necessary sanitation and water supply facilities should be provided at Kanvashram site.

Haridwar 18.05.2017 21 21 - During the consultations the following issues were raised and discussed in detail:

1. Workers safety during construction like using of PPPs and safe handling of construction materials were discussed in detail.

2. The cleanliness, sanitation, drinking water facilities etc., at the construction camp was satisfactory and

Page 104: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

102

Sl. No.

Activity /Event at a glance

Date Total

Participant Male Female Discussion/Suggestions

workforce was happy. 3. During consultation it was

also discussed regarding the wages for categories of labour, it was learned that the laborers are getting wages as per Government Prescribed rates.

4- During this month there was no deployment of women labour while enquiry, it was learned that since it is the season of agriculture harvesting so no women labour is available.

3 GMVN, Guest House, Kanvashram

21.05.2017 3 3 - Consultation with Forest Minister-GoUK , DSC and PIU. Regarding Kanvashram Project The forest officials assured cooperation during project implementation and informed that forest clearance has already been issued under the 'Forest (Conservation) Act', 1980 for Kanvashram site.

4 Nagar Magistrate Office, Devpura, Haridwar

23.05.2017 5 5 Meeting with DM-Haridwar, City Magistrate-Haridwar, DTDO-Haridwar and Exe.Eng-UP Irrigation, TL-DSC, PM-PIU Regarding Progress Review of Kanwar Patri Project.

5 CCR, Rodi Belwala, Haridwara

01.06.2017 6 6 Meeting with Hon’ble CM of Uttarakhand and Govt. Official, PM-PIU, TL-DSC, FE-DSC Regarding Progress Review of Kanwar Patri Project.

6 Collectorate Building, Roshnabad, Haridwar

08.06.2017 5 5 Meeting with DM-Haridwar and Govt. Official and PM-PIU, SE-PIU, TL-DSC, FE-DSC Regarding Progress Review of Kanwar Patri Project.

7 UTDB, Dehradun 19.06.2017 5 5 Meeting with APD-PMU, TM-DSC & Architect –DSC Regarding Rural Tourism Project implementation.

8 Kanvashram/Kotdwara 14.06.2017 7 6 1 Meeting with CDS, PMU, and NGO & TL-DSC Regarding Rural Tourism Project implementation as per project design and implementation of safeguard issues as per IEE report and Social Due Diligence Report.

Page 105: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

103

Sl. No.

Activity /Event at a glance

Date Total

Participant Male Female Discussion/Suggestions

9 Mawakot 14.06.2017 7 6 1 Meeting with CDS, PMU, and NGO & TL-DSC Regarding Rural Tourism Project implementation

Table 10(iii): Public Consultation Meetings for Tranche III sub-projects Under DSC Bhimtal Activity /Event at a glance Date Total

Participant Discussion/ Suggestions

Meeting by District Administration, Pithoragarh

09-02-17 11 Discussion on work progress of Car Parking and Tehsil Building

Meeting & Field visit by Secretary Tourism at Almora site

24-02-17 20 Discussion on the progress Collectorate building at Almora

Meeting with Nagarapalika, Pithoragarh

04-03-17 7 Discussion on handover of Chandak Trek sub project at Pithoragarh

Meeting with Local NGOs at Pithoragarh

10-03-17 20 Discussion for Operation & Maintenance of Almora and Pithoragarh Fort

Meeting with DSC & Contractor at Almora Project site

23-03-17 8 Discussion on work progress and drawing issues

11. Implementation of Grievance Redress Mechanism

38. Grievance Redress Committees at PMU and PIU level have been formed (Office Order Annexure 4). The arrangement for implementation of GRM is that the affected person/aggrieved party can give their grievance verbally or in written to the local grievances committee. Grievances of affected person will first be brought to the attention of the implementing NGO or PIU who can resolve the issue at site level. If the matter is not solved within 7 days period by the NGO or PIUs, it will be brought to the Grievance Redress Committee constituted for the purpose in PIU. This GRC shall discuss the issue in its monthly meeting and resolve the issues within one month of time after receiving the grievance. If the matter is not resolved by GRC at PIU level within stipulated time, it shall be referred to GRC at PMU level by Project Manager of PIU. GRC at PMU shall discuss the issue and try to resolve it and inform the PIU accordingly. If the matter is not resolved by the GRC at PMU level within one month of time, the aggrieved person/party can bring the matter to The Court of Law. The PIU shall keep records of all grievances received including contact details of complainant, date of receiving the complaint, nature of grievance, agreed corrective actions and the date these were affected and final outcome. A complaint register will be maintained at PIU as well as sites of the subproject.

39. No grievance was observed in any sub project during the reporting period.

12. Any other environmental aspects, impacts observed during implementation which were not

covered earlier

40. No such impact observed during the reporting period

Page 106: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

104

13. Details of Complaints received from public and action taken thereof to resolve

41. No complaint received during the reporting period.

14. Follow up actions and Conclusions

42. Site supervision is being regularly carried out to ensure that environmental impacts are being

adequately mitigated and to ensure continuation of compliance with statutory regulations as required by

laws and agreed upon in EMP. The contractors are being regularly guided and instructed to pay

attention to environmental issues and adhere to the provisions of EMP. In this series a 02 day Training

Program on Safeguards Implementation in IDIPT was organized by the PMU for sensitization of the

Contractors, Site Engineers of the DSC, PIU and PMU. Report Attached Annexure 5.

Page 107: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

105

Annexure 1: Photo Illustration

Annexure: 1(i): Photo Illustration of Work Progress- DSC Dehradun

UK/ IDIPT-III/DDN/01

Development of Tourism Infrastructure in Kartikeya Swami Circuit (Durgadhar&Tungeshwar)

Dome shutter work at durgadhar Stone masonry work at Durgadhar

Guest house flooring work, Durgadhar Temple Plantation work at Durgadhar Temple

Page 108: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

106

UK/ IDIPT-III/DDN/01

Development of Tourism Infrastructure in Kartikeya Swami Circuit (Kartikeya Swami)

Special signage at Kartikey Swami Alignment and staircase at Kartikaya swami

Pathway at Kartikeya Swami

Entrance grate Kartikeya swami

Page 109: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

107

Photographs of UK/ IDIPT-III/DDN/03 Conservation and Development of Rural Tourism Infrastructure in District Rudraprayag, Chamoli&Uttarkashi

Pathway at Kaviltha Village Guest House work under progress-Kaviltha

Conservation Experts visit to Tungnath Meeting with Temple committee at Tungnath

Page 110: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

108

Pathway construction at Tungnath Pathway at Kaviltha

Toilet External work at Phalasi Unistone cladding at Phalasi

Pathway at Harsil

Pathway at Mukwa

Page 111: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

109

Entrance gate at Mukwa Meeting with Kabiltha Kalidas committee and villagers

Meeting with Pogtha villagers Meeting with Kartikeya Swami temple committee

Meeting with Durgadhar villagers Meeting with Tungnath temple committee at Makku

village

Page 112: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

110

Meeting with Tungeshwar villagers

Annexure: 1(ii): Photo Illustration of Work Progress- DSC Kotdwar

UK/ IDIPT-III/KOT/01

Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar Project Site

View of Toilet Block under construction at Integrated Multi

facility Center at Haridwar

View of Integrated Multi Facility Center Under

Construction At Haridwar

Page 113: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

111

UK/ IDIPT-III/KOT/02

Development of Tourism Infrastructure in Sem-Mukhem (Tehri) Project Site

Care Taker Room Beside Temple under Construction at Mukhem Village

View of Construction works in Progress at Temple in Mukhem Village

View of Dharamshala Under Construction at Mela Ground at Sem Mukhem

Rest Shed Under Construction at Mela Ground

Page 114: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

112

Annexure: 1(iii): Photo Illustration of Work Progress- DSC Bhimtal UK/ IDIPT-III/BHT/05 Restoration and adaptive reuse of Champawat Fort (Banasur)

Retaining Wall

Pathway Development

View point at site

Entrance Gate to Banasur Fort

Page 115: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

113

UK/IDIPT/III/BHT/01 Conservation of Cultural Heritage and urban place making in Nainital Lot-1

Band Stand Toilet

Retaining Wall Wood Work in Library

Breaking of old plaster Methodist church

DSA flat - ceiling putty work - on going

Page 116: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

114

UK/IDIPT/III/BHT/03 Restoration and adaptive reuse of Almora Fort (Rani Mahal)

Discussion with contractor and consultant at Almora fort

Building View

Discussions with the Laborers at construction site, Almora

Training on Social and Environmental safeguards

measures to the laborers and contractors at construction site, Almora

Page 117: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

115

UK/IDIPT/III/BHT/07

Restoration and Adaptive Reuse of Pithoragarh Fort Phase II

Excavation for foundation of Tehsil Building Column preparation under Multilevel Parking

Page 118: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

Annexure Consultation Records PIU-Dehradun Projects

Meeting held on 09/01/2017 at Bora village about reformation of Temple committee and to discuss the assets constructing by thIDIPT and give brief detail about the proposed software ac

Annexure 2: Consultation Records & Photographs Dehradun Projects

Meeting held on 09/01/2017 at Bora village about reformation of Temple committee and to discuss the assets constructing by thIDIPT and give brief detail about the proposed software activities

116

Meeting held on 09/01/2017 at Bora village about reformation of Temple committee and to discuss the assets constructing by the

Page 119: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

Meeting held on 06/01/2017 at makku village where we discuss the new opportunities of tourism after linking the

Meeting held on 06/01/2017 at makku village where we discuss the new opportunities of tourism after linking the makku village with Tungnath.

117

Meeting held on 06/01/2017 at makku village where we discuss the new opportunities of tourism after linking the

Page 120: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

Meeting held at 14/04/2017 at Durgadhar temple in the presence of temple committee to discuss the temple work and also about

operation and maintenance.

Meeting held at 14/04/2017 at Durgadhar temple in the presence of temple committee to discuss the temple work and also about

118

Meeting held at 14/04/2017 at Durgadhar temple in the presence of temple committee to discuss the temple work and also about his

Page 121: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

Meeting with Kartik swami temple com

committee and his work.

Meeting with Kartik swami temple committee and Pogtha committee for coordination which will help them to organize the

119

mittee and Pogtha committee for coordination which will help them to organize the

Page 122: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

120

Consultation Records PIUKotdwar Projects

Consultation- Kanvashram -Attendance Sheet and Photographs-20/05/2017

Attendance Sheet

Page 123: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

121

Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar(UK/IDIPT- III/KOT/01) Consultations-

18/05/2017

Attendance Sheet

Page 124: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

122

Consultation Photographs

Consultation Photographs PIU- Kotdwar

Labour Orientation at Haridwar

Discussion with Community at Sem Mukhem

Public Disclosure about Upcoming Project Development of Rural Tourism in District Pauri and Tehri

Site Visit of Kanvashram Discussion with Gram Pradhan about Works in Rural Tourism Site Mawakot

Page 125: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

123

Consultation Photographs PIU- Dehradun

Meeting with Kabiltha Kalidas committee and villagers regarding sub project

Meeting with Pogtha villagers regarding the Operation & maintenance of the Assets

Meeting with Kartikeya swami temple committee member regarding the Operation & maintenance

Meeting with Tungeshwar villagers regarding the Operation & maintenance

Page 126: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

Presentation to the DM Rudraparyag about the Kartikeyaswami circuit and Rural Tourism Project

Consultation Photographs PIU- Bhimtal

Signages display and meeting with the contractors representatives at the construction site, Almora

Presentation to the DM Rudraparyag about the Kartikeya swami circuit and Rural Tourism Project

Meeting with Pogtha committee Regarding software activities proposed in Kanakchauri village.

Bhimtal

Signages display and meeting with the contractors truction site, Almora

Discussion with support staff of contractor at DSA Sports

124

Meeting with Pogtha committee Regarding software activities proposed in Kanakchauri village.

Discussion with support staff of contractor at DSA Sports

Page 127: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

125

Discussion with Church Father of St. Francis Catholic Church

Ongoing training to the labours at DSA Sports Pavilion

Page 128: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

126

News Paper Cutting (Meeting with District Magistrate, Haridwar and Govt.

Official Regarding Kanwar Patri Sub-Project) dated _08.06.2017

News Paper Cutting (Regarding Kanvashram Project Under Rural Tourism Sub-

Project) dated _22.05.2017 The disclosure meeting was well attended by the local

people, the information regarding the project was discussed in detail,the honourable

Minister and Member of Legislative Assembly(MLA) as public representative was

present in the consultation.The local people welcomed the project as it will provide

boost to tourism activity in the region. The local youth will get the employment during

construction period and it will provide the opportunity for long term employment in

post project scenario.

Page 129: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

127

Annexure 3: NOCs and Related Correspondence

Annexure 3(i): Site Visit Note of Tungnath Temple by ASI

Page 130: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

128

Page 131: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

129

Page 132: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

130

Page 133: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

131

Page 134: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

132

Annexure 3(ii): Forest Land Clearance for Development of Facilities at Tanki Cheena Trek (.075 hec) under Nainital sub project

Page 135: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

133

Page 136: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

134

Annexure 5: Office Order Of Grievance Redress Committee at PIU and PMU level

Page 137: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

135

Annexure 4: Office Order Of Grievance Redress Committee at PIU and PMU level

Page 138: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive
Page 139: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

137

Annexure 5: Summary of Workshop Organized by PMU

Workshop On Gender Mainstreaming, Social And Environmental Safeguards In IDIPT

Date: 20-21, February, 2017

Venue: Hotel Ananda, Dehradun Introduction

A two day workshop on 20th and 21st February 2017 was organised on Gender mainstreaming, social and environmental

safeguards by IDIPT, Dehradun. All stakeholders – concerned representatives of PMU, PMC, PIU, DSC, NGO and

contractors were present.. Gender expert from ADB Mr. Azizur Rahman was the key speaker to sensitise the audience

towards gender mainstreaming. The workshop was graced by PD Madam, FC and keynote address with welcome speech

was delivered by APD, Mr. R K. Joshi.

Objective

The objective of the programme was to sensitise all stakeholders on gender mainstreaming, social and environment

safeguards. The participants were made to actively get involved in workshop with questions and answers, riddle and

puzzle solving, some exercises to work on and troubleshooting issues to be discussed in open forum. In addition a snake

and ladder game was kept on floor which participants played and got acquainted with various good and bad practises of

safeguard issues in a playful manner. The prime objective of the 2 day workshop was to introduce safeguards to the new

team members of IDIPT and refresh the knowledge of few others who attended workshop earlier.

The contractors who present were the main target audience who were sensitised during the workshop

S.No Name of Sub-project Name of Contractor

1 M/S Dagmo Riba, Itanagar Up-gradation of Tourist Facilities at TRH Parichay

Conservation of Pithoragarh Fort

Hanol

North Entry Kotdwar

Adventure Tourist Centre at Baur

2 Aaradhya Engineers and

Construction Pvt Ltd,Rishikesh

Development of Tourism Infrastructure in Kartikeya Swamy

Circuit(Durgadhar and Tungeshwar

3 Navya associate in JV Conservation and Development of Rural Tourism in Rudraprayag, Chamoli

& Uttarkashi

4 APS structure Pvt Ltd Development of Tourism Infrastructure in Kartikeya Swamy

Circuit(Kartikeya Swamy Temple)

5 S S Infratech,Roorkee Creation of Pedestrian route for pilgrims and Tourist Haridwar

6 Simplex Project Ltd Conservation of Cultural Heritage and Urban place in Nainital.

Restoration and Adaptive reuse of Almora Fort

Restoration and Adaptive reuse of Champawat Fort

Gender

The first speaker was gender expert from ADB, Azizur Rahman who gave the background of gender mainstreaming in ADB

and its policy framework. He also linked gender Action Plan (GAP) with IDIPT output and discussed how to insert gender

component in implementation of projects. It was stressed that GAP is not confined to social sector project or operates on a

standalone mode but rather built into the investment programme as an integral part of it. GAP ensures in increased

participation of women in work, more access to services by women and improved socio economic benefits to women. The

deep rooted value of the difference between male and female in all areas of society has to be bridged and GAP is one such

intervention through which IDIPT aims to address this issue within their limited scope of works.

ADB Expert on Gender continued his input on the second day (21.02.17) explaining the GAP of T2 and T3 monitoring and

reporting formats. The T2 and T3 GAP formats were distributed to all the clusters of participants and were explained the

formats in a nutshell. He tried to get the feedback from the participants through a participatory exercise involving PIU/DSC

and Contractors who were present.

Environment

The environment safeguard presentations were from both PMC and DSC experts which continued on both days.

PMC Environmental Expert Presentation highlighted:-

Page 140: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

138

• Applicable laws in case of EHS along with ADB’s requirement.

• Best practices for EHS applicable to site condition

• Checklist for contractor’s requirement for EHS.

Following recommendations were made:-

• Contractors shall maintain legal register for legal compliance

• Contractors are lacking in documentation as per legal requirement

• Contractors shall provide training for EHS to worker and maintain records

• Contractors shall prepare EHS manual for conformance and shall follow EHS procedure at

site.

• PMU shall include one CCG or contract obligation for Occupational Health and Safety.

DSC Dehradun Expert compared present and past site conditions related to EHS for all the projects under DSC Dehradun.

Also presented some of the best practices for Site in case of Environment Health and safety and presented sample

Environmental Monitoring Reports and checklist for site to address EHS best practices.

DSC Kotdwar Presentation also highlighted Environmental Monitoring data for site and recommended that Contractors shall

carry out environmental monitoring as requisite by DSC and PMU and shall adhere to the recommendations of DSC expert.

DSC Bhimtal Presentation showcased good examples from the site of Naukuchiyatal with pictorial presentation. There were

few overall recommendations from sites like:-

• Provision of toilet for women in Naukuchiatal

• Proactive role of the project implementation Unit (PIU).

• Adequate technical knowledge is required for PIU and Contractors.

• Co-operation among all the agencies involved is required.

• Blame game to be avoided.

• Provision of penalty cause in case of non compliance

Social

PMC Expert Dr. Kakoli Singh outlined the main objective of ADB Safeguard Policy that must be complied mechanisms. She

informed that most of the projects were in C category and DDRs were made and approved by ADB. Resettlement Plans was

made for three packages under both the tranches. It was explained that social safeguard documents were dynamic in nature

and may be updated from time to time as per implementation requirements. Role of different stakeholders like

PMU/PIU,PMC/DSC/NGO, Contractors were discussed and mechanism for disclosure, consultation and participation in

design as well as Implementation stages was deliberated in details Grievances Redress Mechanism under IDIPT-UK was

also explained in detail. It was deliberated that 3 tier structures are constituted for resolving project related Grievances at

early stage. Grievance Action Form should be at site and all grievances to be recorded and well documented.

J.D.Singh DSC Expert of Dehradun in his presentation shared his experiences of Tiger Fall sub-project Under Tranche 2

for which RP was made initially which later was revised for DDR as during implementation, impacts were avoided. This best

practise was showcased in this platform as learning experience.

Dr.K.K.Gaur Social Safeguard Expert of DSC Bhimtal explained status of implementation in all the sub-projects under

PIU Bhimtal which are all ddunder C Category. He shared their field experiences particularly Engagement of Labour at site,

basic provision like drinking water ,sanitation, engagement of female labor etc

NGO

IDS is the implementing NGO for IDIPT. The TL and coordinators of this NGO were present in the workshop who presented

that

• Ensure consultation with women for infrastructure development, action plan and operation and maintenance of the

created infrastructure

• Ensure awareness program/ meetings on gender issues with all project stakeholder such as Village Tourism

Management Committees, contractors, Labour, SHG, village Panchayats etc

• Sensitize Contractors, site engineers, Supervisors etc regarding safety, equal wages, employment and social

safeguard for women at construction sites.

• Ensure participation of women, vulnerable group in enhancement of livelihood through suitable micro enterprises

• Facilitation in implementation of resettlement and rehabilitation plan

Page 141: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

139

• Designing, development and distribution of awareness generation material on gender, social and environmental

safeguard

• Documentation of the gender mainstreaming case studies, process etc and showcasing them as appropriate.

• Dissemination or sharing good practices with other stakeholders

• Facilitation in improvement of basic services at sub project site to cater to the need of the women tourists in

particular

• Ensure participation of women in decision making for conservation and promotion of natural and cultural heritage

of the area

• Document baseline situation for showcasing project intervention

• Facilitation in convergence with other agencies for mainstreaming gender, social and environmental issues

Conclusion :

Analysis of Participants Feed Back Survey

At the end of the workshop, feedback forms were circulated among the participants.

The analysis depicts the following,

• More than half of participants agreed that the programme objective have been achieved

• Majority of participants found the programme was useful.

• In case of practical orientation of programme, most agreed that they were benefited by interaction between all

stake holders of programme in open forum and during presentations.

• All participants were in concurrence that workshop had specific ideas for improvement of work conditions.

• Most of participants have given their suggestion for future workshops. Participants recommended increasing the

frequency of such workshops.

X-----------------------X

Page 142: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

140

Commencement of Workshop ADB Expert Delivering Presentation on Gender Implementation

Orientation on Safeguards Implementation by DSC Expert

Through Snake & Ladder Game Q&A Session

Experience Sharing by the PIU Project Managers Presentation on Social Safeguards by PMC Expert

Page 143: IND: Infrastructure Development Investment …...407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India INR 38.52Crore 24 months 5 UK/IDIPT/III/B HT/03 Restoration and adaptive

141

Challenges in Implementation of Environmental Safeguards by DSC Expert

Briefing on Importance of Safeguards by Program Director

Experience Sharing by Contractors

Program Authorities at PMU Learning Safeguards

Implementation through Snake & Ladder Game Group Photograph