ind: bihar urban development investment program ... of the subproject in bhagalpur shows that...
TRANSCRIPT
Resettlement Plan
August 2013
IND: Bihar Urban Development Investment Program—Bhagalpur Water Supply Subproject Prepared by Bihar Urban Infrastructure Development Corporation Limited of the Government of Bihar for the Asian Development Bank. This is an updated version of the draft originally posted in January 2012 available on http://www.adb.org/projects/41603-023/documents.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
Bhagalpur Water Supply Project 1 (BWSP1)
Draft Resettlement Plan (August, 2013)
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
Abbreviations and Definitions
Abbreviation Term or Definition
ADB Asian Development Bank
BRJP Bihar Rajya Jal Parshad
BUIDCo Bihar Urban Infrastructure Development Corporation
CLC
City Level Committee set up to monitor project implementation in
the town and also act as Grievance Redress Committee
CLO Community Liaison Officer of the implementing NGO
DOEF Department of Environment and Forest
DSC Design and Supervision Consultant
DWR Department of Water Resources
EARF Environmental Assessment and Review Framework
EIA Environmental Impact Assessment
EMP Environmental Management Plan
ESMC Environment and Social Management Coordinator at the Project
Management Unit
GRC Grievance Redress Committee set up to resolve grievances in the
town
GRM Grievance Redress Mechanism
IEE Initial Environmental Examination
IPP Indigenous Peoples Plan
IPPF Indigenous Peoples Planning Framework
MOEF Ministry of Environment and Forests
NGO nongovernmental organization
NRRP National Rehabilitation and Resettlement Policy
OHT overhead tank
PIU Project Implementation Unit
PMC Project Management Consultant
PMU Project Management Unit
PSC Project Steering Committee at the state level
UDHD Urban Development and Housing Department
ULB urban local body
WRD Water Resources Department
WTP water treatment plant
Note
"$" refers to US dollars
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
ii
This Resettlement Plan is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB's Board of Directors, Management, or staff, and may be
preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the Asian
Development Bank does not intend to make any judgments as to the legal or other status of any
territory or area.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
CONTENTS
Page
EXECUTIVE SUMMARY i
I. PROJECT DESCRIPTION 1
II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 4
III. SOCIOECONOMIC INFORMATION AND PROFILE 4
IV. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION 6
V. GRIEVANCE REDRESS MECHANISMS 7
A. Common Grievance Redress Mechanism 7 B. Composition of GRC and PSC 9 C. Areas of Jurisdiction 10 D. Consultation Arrangements 10 E. Record-keeping 10 F. Information Dissemination Methods of the GRM 10 G. Periodic Review and Documentation of Lessons Learned 11 H. Costs 11 I. Legal Framework 11
VI. ENTITLEMENTS, ASSISTANCE AND BENEFITS 12
VII. INCOME RESTORATION AND REHABILITATION 14
VIII. RESETTLEMENT BUDGET AND FINANCING PLAN 14
IX. INSTITUTIONAL ARRANGEMENTS 16
A. Implementation Arrangements 16 B. Program Implementation Unit (PIU) 17 C. Implementing NGO 17 D. Institutional Capacity 21 E. Coordination with other Agencies and Organizations 21
X. IMPLEMENTATION SCHEDULE 21
XI. MONITORING AND REPORTING 23
ANNEXES
Annex 1: Methodology for Estimation of Temporary Impacts 23
Annex 2: Summary of Discussions Held with Stakeholders at Subproject Sites 26
Annex 3: Survey Number and Ownership Details of Selected Sites for Subproject Facilities 34
Annex 4: Subproject Sites with Footprints of Proposed Facilities 35
Annex 5: Consultation and Participation Plan 53
Annex 6: Sample Grievance Redress Form 58
Annex 7: Summary Policy Frameworks 59
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
i
EXECUTIVE SUMMARY
1. Project Description. The Bihar Urban Development Investment Program
(BUDIP) aims at infrastructure development in four urban areas of Bihar (Bhagalpur,
Darbhanga, Gaya, and Muzaffarpur), using a multi-tranche financing facility. This
Resettlement Plan is prepared for the Bhagalpur Water Supply Project (BWSP1), to be
implemented under Tranche 1. Subproject components under BWSP1 include
rehabilitation of the Barari Water Works, 16 new overhead tanks (OHTs), rehabilitation
of one OHT, and new distribution mains and metered household connections. Screening
of BWSP1 shows that neither land acquisition nor permanent physical displacement is
required and only temporary impacts are anticipated. It is classified as Category B based
on Asian Development Bank’s (ADB’s) Safeguards Policy Statement, 2009. Measures to
avoid and minimize involuntary resettlement impacts included consideration of viable
alternative sites and/or locations for subproject components, in accordance with
safeguards frameworks to ensure that land acquisition, involuntary resettlement, and
other adverse impacts are avoided or minimized. Overall involuntary resettlement
impacts are to be further minimized during detailed design and subproject
implementation.
2. Scope of Land Acquisition and Resettlement. All land required for subproject
components in Bhagalpur has been identified. No land acquisition is required and no
physical displacement is anticipated. Based on a thorough survey of all possible site
alternatives, subproject components are proposed on government or municipal land,
where available. Three OHTs are proposed on vacant land belonging to a high school, the
Diocesan Centre, and a temple trust, and for each of these a no objection and lease
agreement with the Municipal Corporation, Bhagalpur is required. Anticipated
involuntary resettlement impacts include temporary impacts on non-titled persons such as
hawkers and vendors during construction of pipelines.
3. Socio-economic Information and Profile. Based on transect walks and
confirmation of project engineers, limited impacts are anticipated on permanent
structures. Temporary impacts on 3,704 non-titled persons (vendors with push carts,
baskets and moveable tables, and those with bamboo and tarpaulin repair stands) are
envisaged during construction of distribution pipelines. Transect walks reveal that 20% of
temporarily affected persons are vulnerable affected persons including women, children,
and affected persons with incomes below poverty line.
4. Information Disclosure, Consultation and Participation. Detailed
consultations with potential beneficiaries and affected persons revealed that there is a
great need for the water supply project in Bhagalpur, and consultations helped in
selection and finalization of subproject sites in Bhagalpur. The draft Resettlement
Framework and draft Resettlement Plan in local language were discussed in a city-wide
stakeholder consultation workshop and the documents were disclosed. The Resettlement
Framework and Resettlement Plan provide a strategy for continued consultation at
different stages of Resettlement Plan implementation.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
ii
5. Grievance Redress Mechanism. The Grievance Redress Mechanism provides an
accessible, gender-sensitive and culturally appropriate platform for receiving and
facilitating resolution of affected persons’ grievances related to the project. The Project
Implementation Unit (PIU) and the implementing nongovernmental organization (NGO)
will resolve smaller issues and consult the Environment and Social Management
Coordinator (ESMC) at the Project Management Unit (PMU) regarding resolution of
larger issues. Unresolved grievances will be placed before the City Level Committee
(CLC) cum Grievance Redress Committee (GRC) at the city level, and then the Project
Steering Committee (PSC) at the state level, failing which, the complainant can seek
legal recourse.
6. Legal Framework. The policy framework followed for the Resettlement Plan is
based on the Land Acquisition Act, 1894 (amended in 1984), the National Rehabilitation
and Resettlement Policy, 2007, the Bihar Land Acquisition and Resettlement and
Rehabilitation Policy, 2007, and ADB’s Safeguard Policy Statement, 2009.
7. Entitlements, Assistance and Benefits. The entitlement matrix prepared for the
subproject provides for compensation of land and all assets to be acquired at replacement
value and also recognizes encroachers and squatters as affected persons. Vulnerable
households will be provided additional assistance, priority in employment for subproject
activities, skills and livelihood training, and income generating assets.
8. Income Restoration and Rehabilitation. Affected persons will be provided 30
days advance notice to ensure no or minimal disruption in livelihood. Should
construction activities result in unavoidable livelihood disruption, compensation for lost
income or a transitional allowance for the period of disruption, whichever is greater, will
be provided. Compensation and assistance to affected persons will be made prior to
possession of land and/or assets and prior to the award of civil works contracts.
9. Resettlement Budget and Financing Plan. The resettlement cost for the
subproject is estimated at Rs. 8.900 million.
10. Institutional Arrangements. The ESMC at the PMU within the Urban
Development and Housing Department will have the overall responsibility of overseeing
Resettlement Plan preparation (for future Resettlement Plans of future tranches),
implementation, and monitoring. The resettlement and/or social specialist of the Project
Management Consultant (PMC) will assist the PMU in preparing and/or updating
Resettlement Plan reports. The resettlement officer at the PIU will be responsible for
implementing and monitoring safeguards compliance, gender mainstreaming, and
consultation and participation. The implementing NGO will assist the PIU in
implementing and monitoring Resettlement Plan implementation.
11. Implementation Schedule. The entire process of Resettlement Plan
implementation including institutional arrangements, monitoring and rehabilitation of
temporarily occupied lands is expected to require 24 months.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
iii
12. Monitoring and Reporting. Resettlement Plan implementation will be closely
monitored to provide the PMU with an effective basis for assessing resettlement progress
and identifying potential difficulties and problems. Monitoring will be undertaken by the
PIU (through the implementing NGO) with assistance from the PMU. The Executing
Agency (EA) will submit all monitoring reports to ADB for review.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
1
I. PROJECT DESCRIPTION
1. The Bihar Urban Development Investment Program (BUDIP) is expected to
improve the urban environment and living conditions in targeted urban areas. The project
will be implemented in four urban areas: Bhagalpur, Darbhanga, Gaya, and Muzaffarpur.
The improvement in urban infrastructure will include rehabilitation, improvement, and
expansion of: (i) water supplies, and (ii) sewerage and sanitation.
2. The project will be implemented using a multitranche financing facility. Project 1
funded by Tranche 1 comprises the Bhagalpur Water Supply Project (BWSP1).
Preliminary design has been developed for BWSP1, and on this basis, social assessment
was undertaken.
3. Subproject components for BWSP1 include rehabilitation of the Barari Water
Works, 16 Overhead Tanks (OHTs), rehabilitation of one OHT, and new distribution
mains and metered household connections. Table 1 provides a description of subproject
components in Bhagalpur.
4. Measures to avoid and minimize involuntary resettlement impacts included
consideration of viable alternative sites and/or locations for subproject components, in
accordance with the Resettlement Framework and the Environmental Assessment and
Review Framework (EARF) to ensure that land acquisition and other involuntary
resettlement impacts are avoided or minimized. Based on a thorough survey of all
possible site alternatives, subproject components are proposed on vacant government
land, where available. The overall impacts are to be further minimized during detailed
design and subproject implementation.
5. Screening of the subproject in Bhagalpur shows that neither land acquisition nor
permanent physical displacement is required. On the basis of preliminary design,
anticipated impacts are temporary, and will have impacts on non-titled persons, hawkers
and vendors during laying of networks. This Resettlement Plan is prepared for BWSP1
funded under Tranche 1. It addresses the involuntary resettlement impacts of the
proposed BWSP1 and is consistent with the draft Resettlement Framework for the
project.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
2
Table 1: Water Supply Subproject Components – Bhagalpur
Component Location Function Description Remarks
Rehabilitation of
existing Water
Treatment Plants
( 3 separate
plants)
Barari To treat raw water
drawn from the
Ganga River to
drinking water
standards
The refurbishment includes introduction of (i) alum
and lime dosing systems with necessary chemical
storage and mixing tanks, dosing-pumps, metering
device with 100% standby capacity; (ii) flash mixers
for coagulant rapid mixing; (iii) chlorination system
with necessary dosing mechanism, storage and safety
equipment in all three existing treatment plants; (iv)
electrical actuators for all existing sluice valves in the
Jewel Filter unit; (v) servicing of existing machinery
and equipment, and (vi) painting of various units.
Changes in existing
water treatment
works to improve
treatment efficiency
and output
Mechanical,
Electrical, and
Instrumentation
works
Existing Barari
Water Works
To improve overall
working of all three
water treatment
plants
(i) Installation of 2 nos of centrifugal pumps with
accessories; (ii) replacement of sluice and non-return
valves, pipes and fittings, (iii) air blowers for filters,
(iv) chemical mixing and metering system, flash
mixing system, (v) chlorination system, (vi) electrical
works including 33 kV/0.433 kV substation works, LT
switch gear panels and instrumentation works at
pumping station (vii) electro-magnetic flow meter,
ultrasonic type level indicator, pressure loggers, and
(viii) online residual chlorine monitoring system, and
chlorine leak detection system.
Existing renovation
Distribution
System
Area within the
current municipal
boundary
To improve coverage
and reduce losses and
ensure reliable and
continuous water
supply to consumers
Road cutting and earthwork excavation (concrete road
46,215 m3, asphalt road 10,721 m3, WBM road 13,120
m3 and brick road 1,291 m3), pipelines specials and
appurtenances, pipe jacking, installation of valves and
appurtenances, flow and pressure measurement
devices, installation of service connections,
interconnections, valve chambers, and miscellaneous
civil works.
Works include
laying of new
pipeline and
replacement of
existing ones
depending on study
findings
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
3
Component Location Function Description Remarks
Service
Reservoirs
At 16 different
locations
identified by
Bhagalpur
Municipal
Corporation and
the design team
To supply water to
consumers and to
augment treated
water storage to meet
peak demand needs
Design, setting out, construction, testing and
commissioning of 16 new OHTs and rehabilitation of
one OHT.
New
Metered
Customer House
Service
Connections
In the resident
neighbourhood
Providing water
supply inside the
customer property
and measuring the
supply volume
New connections of approx. 52,000 of improved
materials for pipes and fittings and provision of Class
B consumption meter for measuring the supply volume
including rehabilitation of existing connections.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
4
II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT
6. All land required for subproject components in Bhagalpur has been identified and
as discussed in the previous section, there will be no land acquisition or population
displacement as a result of the subproject. There will be temporary impacts on non-titled
persons, hawkers and vendors during construction of pipelines.
7. The proposed subproject components are presented in Table 1. Subproject design
minimizes land acquisition and resettlement impacts.1 The following works are confined
within the compound of existing facilities and will not have any resettlement impacts: (i)
provision of bulk and consumer meters, (ii) decommissioning of tube wells, (iii)
replacement of pumping machinery and automation, and (iv) leak detection and
rectification. Thirteen of 16 OHTs will be on government land or municipal land. One
OHT will be on vacant land belonging to the Inter-level Muslim High School, one is on
the land of the Diocesan Centre, and one is on land belonging to a temple trust. Work on
distribution mains will not require permanent land acquisition as it will be undertaken
within the rights-of-way (ROW), although it can cause temporary disruptions.
8. Annex 3 presents details available on proposed sites for project facilities (survey
numbers, ownership and area), while Annex 4 presents sketches depicting footprints of
proposed subproject components in each identified land parcel. In two government school
sites, impacts on presently unused sheds at the edges of the sites are envisaged; the sheds
will need to be rebuilt, post OHT construction.
III. SOCIOECONOMIC INFORMATION AND PROFILE
9. To estimate the temporary impacts from an estimated 326 km of distribution
network improvement for the subproject, three transect walks of 300 m each were
conducted in Bhagalpur.2 Other impacts are confined to movable structures placed on
ROWs. Estimated resettlement impacts based on extrapolations from the transect walks
are presented in Table 2.
1 Refer Annex 3 on site selection, which clearly reveals that all facility locations are proposed on government land or
on institutional land which will not require acquisition or displacement. Refer also, details of discussions with
institutional stakeholders in Annex 3; it is evident that there is willingness to permit use of land for OHTs as the
proposed project is perceived as one that is greatly needed and beneficial for all. 2 Transect walks were conducted in three 300-meter sections namely DN Singh Road, Swami Vivekananda Path and
Barari (road in front of Mt. Carmel School) - representing high, medium and low density areas. In the absence of
detailed designs, inputs were obtained from the program preparation engineer to assess the extent of impacts likely
due to the proposed works. Refer to Annex 1 for methodology socio-economic questionnaire used during transect
walks and summary of findings.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
5
Table 2: Summary of Resettlement Impacts
S.
No.
Category Impact
1 Permanent Land Acquisition (Ha.) None
2 Temporary Land Acquisition (Ha) None
3 Temporarily Affected Persons 8145
4 Titled affected persons (temporarily affected) None
5 Non-Titled affected persons (temporarily affected hawkers
and vendors)a
8145
5a Female affected persons (temporarily affected) 408
5b Child affected persons (temporarily affected) 408
5c Indigenous people/scheduled tribe affected persons None
5d Below poverty line affected person (temporarily affected) 816
5e Other (temporarily affected) 8145
6 Non-Titled affected persons (temporarily affected kutcha
residential structures)
4
7 Affected Trees/Crops Land proposed behind
the Muslim High School
OHT 2/3 requires further
investigation
8 Temporarily Affected Land under common use OHT site 3/1
9 Affected Common Structures Temporary shanties,
offices and eating places
10 Average Income of affected persons (per month) Rs. 3,200
11 Income Sources Temporarily Affected Fruit, Vegetable, Tea
sellers, roadside eateries,
etc. a Temporarily affected land under common use.
10. Temporary impacts of distribution network improvement will be on affected
persons who are vendors with push carts, baskets and (moveable) tables (3,848) and those
with repair stands having bamboo and tarpaulin structures (1,079). All such affected
persons have makeshift structures and have squatted on the ROW for commercial
purposes.
11. Affected persons will be assisted in moving to the other side of the road and
returning after construction is completed. Where they are not required to shift, access will
be ensured by the Contractor. The construction period will be minimized and is estimated
to be less than 30 days per section of work. The summary of socio-economic information
based on transect walks presented in Table 2 reveals that 20% of temporarily affected
persons are vulnerable affected persons including women, children and those with
incomes below poverty line. The scope of land acquisition and resettlement identified is
based on preliminary design and will be updated during detailed design. Annex 1
provides the methodology for transect walks and results.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
6
IV. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION
12. The Resettlement Plan was prepared in consultation with stakeholders. Detailed
discussions were held with municipal officials, owners and users of sites where
subproject facilities are proposed, academicians and environmental specialists based in
Bhagalpur University, fishers in Bhagalpur and potentials beneficiaries (residents).
Meetings and individual interviews of stakeholders, particularly potentially temporarily
affected persons, were held, and transect walks and interviews conducted to determine
the potential impacts of subproject construction to prepare the sample subproject
Resettlement Plan. Focus Group Discussions held with residents and/or users in and
around each of the identified OHT sites (refer to summary of discussions held at OHT
locations in Annex 2) revealed that the need for the water supply project in Bhagalpur is
great and people recognize the potential benefits in terms of improved quantity and
quality of water supplied. Even for OHT sites that are part of school compounds (selected
in the absence of any other suitable site in the vicinity), discussions with stakeholders
(school authorities, students and residents of the locality) revealed the acute need for
drinking water supply in the schools, that there is a need for a good water supply system
in recognition of its potential benefits, and that these subsume all other concerns (Annex
2). The consultations with stakeholders helped in selection and finalization of subproject
sites in Bhagalpur.
13. Bhagalpur is located adjacent to an environmentally sensitive area (the
Vikramshila Gangetic Dolphin Sanctuary on the River Ganga). Discussions with fishers
(Mallah community, belonging to Other Backward Castes category) revealed that they
normally fish 5-8 km downstream of the Vikramshila Setu Bridge. The fishermen
indicated the presence of an activist organization—the Jal Shramik Sammelan that aims
to protect fishing rights of fishers (earlier, fishing rights on the Ganga were held by a few
zamindars and/or land owning elite, who would contract out these rights to the Mallah
community and take a share of their daily earnings; this practice is now stopped as a
result of active lobbying through the Ganga Mukti Andolan launched by the Jal Shramik
Sammelan). The broad perception of fishers met was that any effort at dolphin
conservation would be good for the overall ecosystem and would lead to better harvests
(in terms of increased availability of different varieties of fish) as well. The fishers met
appeared to be aware of environmental issues as their livelihood depends on these. It is
expected that conservation actions as part of the subproject will improve fishers’
livelihoods.
14. As part of project preparation, a city wide stakeholder consultation workshop was
held, to provide an overview of the project and subprojects to be undertaken in Bhagalpur
and disclose the draft Resettlement Framework and Resettlement Plan. These two
documents were in local language. These documents were also placed in Municipal
Office, Revenue Department, and Bihar Rajya Jal Parishad (BRJP). These will be also be
placed in the PIU office once established and in public locations.
15. Information continues to be disseminated to affected persons and beneficiaries
through various media. The nongovernmental organization (NGO) engaged to implement
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
7
the Resettlement Plan will undertake consultations, information dissemination, and
disclosure. A strategy for continued consultations and participation is in the Resettlement
Framework. The finalized Resettlement Plan will also be disclosed in websites of the
Asian Development Bank (ADB), state government, local government, PMU, and PIU.
ADB review and approval of the Resettlement Plan is required prior to award of civil
works contracts; and compensation and/or assistance of affected persons is required prior
to commencement of civil works.
16. The consultation and participation plan identifies consultation and disclosure
activities with specific reference to resettlement planning and implementation and
environmental assessment and implementation of the Environmental Management Plan
(EMP) to be followed for each subproject and the institutions responsible, see Annex 5
for details.
V. GRIEVANCE REDRESS MECHANISMS
A. Common Grievance Redress Mechanism
17. A common Grievance Redress Mechanism (GRM) will be in place for social,
environmental or any other project and/or subproject related grievances; each
Resettlement Plan, Indigenous Peoples Plan (IPP), and Initial Environmental
Examination (IEE) and/or Environmental Impact Assessment (EIA) will follow the GRM
described below, which is developed in consultation with stakeholders, including affected
persons and NGOs. The GRM will provide an accessible platform for receiving and
facilitating resolution of affected persons’ grievances related to the project. Grievances
and/or suggestions of affected persons can be dropped in suggestion boxes set up for the
project in key locations including subproject sites, or conveyed through phone or mail.
The Community Liaison Officer (CLO) of the implementing NGO will be responsible for
conducting periodic community meetings with affected communities to understand their
concerns and help them through the process of grievance redressal (including translation
from local language, recording and registering grievances of non-literate affected persons
and explaining the process of grievance redressal).
18. Grievances will first be registered at the complaints cell of the implementing
NGO or PIU, who will resolve smaller issues and in case of larger issues, they will
consult or seek the assistance of the Environment and Social Management Coordinator
(ESMC), PMU.3 Grievances not redressed through this process within one month of
registration will be brought to the notice of the City Level Committees (CLC) set up to
monitor project implementation in each town. As a Grievance Redress Committee
(GRC), the CLC will meet every month (if there are pending, registered grievances),
determine the merit of each grievance, and resolve grievances within a month upon
receiving the complaint—failing which the grievance will be addressed by the state-level
3 The grievance redress process cannot address expropriation related issues. Grievances related to award of
compensation can be addressed by the collector’s office and a court of law.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
8
Project Steering Committee (PSC) . Further grievances will be referred by affected
persons to the appropriate courts of law. The grievance redress process is shown in
Figure 1. The GRCs will continue to function throughout the project duration.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
9
Figure 1: Grievance Redress Process
CLC = City Level Committee, GRC = Grievance Redress Mechanism, NGO = nongovernmental organization, PIU =
Project Implementation Unit, PMU = Project Management Unit, PSC = Project Steering Committee.
Source: ADB. 2008. Project Preparatory Technical Assistance to India for Preparing Bihar Urban Development
Project. Manila.
B. Composition of GRC and PSC
19. The CLC, acting as a GRC will have District Magistrate (Chairperson), Mayor,
Municipal Commissioner, Head, PIU (Convener), city level heads of relevant
departments (such as BRJP, Road Construction Department, Public Health Engineering
Department, Electricity Board, State Pollution Control Board, Police, etc., and
departments such as Forest Department, Railways etc.), Chairpersons of the concerned
Municipal Corporation’s Standing Committee, ULB officials including Municipal
Engineer, Town Planning Officer, Medical and Health Officer, representatives from the
affected village panchayat and/or community, if any, eminent citizens, CBOs and NGOs.
The GRC and/or CLC must have a minimum of two women members. In case of any
indigenous people impacts in future subprojects (not envisaged in case of BWSP1 under
Tranche 1), the GRC and/or CLC must have representation of the affected indigenous
people community, including at least one female indigenous person, the chief of the tribe
or a member of the tribal council as traditional arbitrator (to ensure that traditional
grievance redress systems are integrated) and an NGO working with indigenous people
groups.
20. The PSC shall include, the Minister for Urban Development (Chairperson), State
Chief Secretary (Vice Chairperson), and Ministers, Directors and/or representatives of
other relevant government ministries and departments e.g., Finance, Planning, Public
NGO/PIU/PMU
Not Addressed
Affected Persons
PSC
Grievance
addressed
GRC/CLC
Grievance
addressed
Court of Law
Minor Grievances
Major Grievances
Not addressed
Grievance
addressed Not addressed
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
10
Health Engineering Department, Roads, BRJP, etc., Mayors of respective Municipal
Corporations and the Project Director (Member Secretary and Convener) as members.
C. Areas of Jurisdiction
21. The areas of jurisdiction of the GRC—headed by the District Magistrate, will be
(i) all locations or sites within the district where subproject facilities are proposed, or (ii)
their areas of influence within the district. The PSC shall have jurisdictional authority
across the state (i.e., areas of influence of subproject facilities beyond district boundaries,
if any).
D. Consultation Arrangements
22. This will include (i) group meetings and discussions with affected persons, to be
announced in advance and conducted at the time of day agreed on with affected persons
(based on their availability) and conducted by the CLO of the implementing NGO and
PIU, at least twice during Resettlement Plan preparation, quarterly in the first year and
semi-annually in subsequent years of Resettlement Plan implementation to address
general and/or common grievances; and (ii) availability of CLO, implementing NGO and
Resettlement Officer, PIU on a fixed day of every week and/or fortnight (as required,
based on the number of grievances) for one-to-one consultations. The implementing
NGO will be responsible for ensuring that non-literate affected persons and/or vulnerable
affected persons are assisted to understand the grievance redress process, to register
complaints and with follow-up actions at different stages in the process.
E. Record-keeping
23. Records will be kept by the PIU of all grievances received including contact
details of complainant, date the complaint was received, nature of grievance, agreed
corrective actions and the date these were effected, and final outcome.
F. Information Dissemination Methods of the GRM
24. The implementing NGO will be responsible for information dissemination to
affected persons on grievance redress procedure, who to contact and when, where and
how to register grievance, various stages of grievance redress process, time likely to be
taken for redressal of minor and major grievances, and other key grievance related
information. Grievances received and responses provided will be documented and
reported back to affected persons at their request, at the time of grievance registration
(Annex 6 has the Sample Grievance Registration Form). The number of grievances
recorded and resolved and the outcomes will be displayed and/or disclosed in the offices
of the concerned local panchayat, ULB notice board, and the web.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
11
G. Periodic Review and Documentation of Lessons Learned
25. The implementing NGO and/or PIU shall periodically review the functioning of
the GRM and record information on the effectiveness of the mechanism, especially on the
project’s ability to prevent and address grievances.
H. Costs
26. All costs involved in resolving complaints (meetings, consultations,
communication and reporting and/or information dissemination) will be borne by the
PMU; cost estimates for grievance redress are included in resettlement cost estimates
(Section IX).
I. Legal Framework
27. The policy framework and entitlements for the project are based on: (i)
government policies (Land Acquisition Act, 1894 [amended in 1984]; National
Rehabilitation and Resettlement Policy, 2007; Bihar Land Acquisition and Resettlement
and Rehabilitation Policy, 2007); (ii) ADB’s Safeguards Policy Statement; and (iii) the
agreed Resettlement Framework. Based on these, the following involuntary resettlement
principles applicable are:
(i) land acquisition, and other involuntary resettlement impacts will be
avoided or minimized exploring all viable alternative subproject designs;
(ii) where resettlement is unavoidable, time-bound Resettlement Plans will be
prepared and census and socio-economic surveys of displaced persons will
be conducted;
(iii) improve or at least restore the livelihoods of all displaced persons;
(iv) carry out meaningful consultation with affected persons, host communities
and NGOs to ensure their participation in planning, implementation, and
monitoring of the resettlement program. Provide for social preparation to
ensure meaningful consultation, where required;
(v) vulnerable groups will be provided special assistance;
(vi) land for land compensation if feasible;
(vii) compensation based on replacement cost;
(viii) ensure that displaced persons without titles to land or any recognizable
legal rights to land are eligible for resettlement assistance and
compensation for loss of non-land assets;
(ix) pay compensation and provide other resettlement entitlements before
physical or economic displacement;
(x) provision of relocation assistance;
(xi) conceive and execute involuntary resettlement as part of a development
project or program. Include the full costs of resettlement in the
presentation of project’s costs and benefits;
(xii) establish an appropriate GRM;
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
12
(xiii) disclose the Resettlement Plan, including documentation of the
consultation in an accessible place and a form and language(s)
understandable to affected persons and other stakeholders; and
(xiv) monitor and assess resettlement outcomes, their impacts on the standards
of living of displaced persons.
28. Policy framework and entitlements are further discussed in the Resettlement
Framework. Annex 7 provides a comparison of national, state and ADB policies and
identifies how the Resettlement Framework addresses gaps in present policies.
VI. ENTITLEMENTS, ASSISTANCE AND BENEFITS
29. The Entitlement Matrix in Table 3 summarizes the main types of losses and the
corresponding entitlements in accordance with Government and ADB policies.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
13
Table 2: Entitlement Matrixa
S No. Type of Loss Application Definition of Entitled
Person Compensation Policy Implementation Issues Responsible Agency
1 Temporary disruption
of livelihood
(i) Legal titleholders;
(ii) Tenants, leaseholders;
sharecroppers; and
(iii) Persons with non-
recognizable claims
(encroachers, squatters,
hawkers, vendors, etc.).
(i) 30 days advance notice regarding
construction activities, including
duration and type of disruption.
(ii) Contractor’s actions to ensure there
is no income and/or access loss
consistent with the IEE.b
(iii) Assistance to mobile vendors and/or
hawkers to temporarily shift for
continued economic activity.c
(iv) For construction activities involving
unavoidable livelihood disruption,
compensation for lost income or a
transitional allowance for the period of
disruption whichever is greater.
Identification of
alternative temporary sites
to continue economic
activity.
Valuation Committee will
determine income lost.
Contractors will perform actions to
minimize income and/or access loss.
2 Impacts on
vulnerable affected
persons
All impacts Vulnerable affected persons
Livelihood. Vulnerable households will
be given priority in project construction
employment.d
Vulnerable households
will be identified during
the census.
NGO will verify the extent of
impacts through a 100% surveys of
affected households determine
assistance, verify and identify
vulnerable households and establish
extent of demand and/or
willingness to enrol in literacy
and/or numeracy classes.
3 Any other loss not
identified
(i) Legal titleholders;
(ii) Tenants, leaseholders,
sharecroppers; and
(iii) Persons with non-
recognizable claims
(encroachers, squatters,
hawkers, vendors, etc.).
Unanticipated involuntary impacts will
be documented and mitigated based on
the principles of the Resettlement
Framework.
- NGO will ascertain the nature and
extent of such loss. PMU will
finalize the entitlements in line with
the Resettlement Framework.
IEE = Initial Environmental Examination, NGO = nongovernmental organization, PMU = Project Management Unit. a Entitlements Matrix presented here is for identified and unforeseen impacts. A detailed Entitlement Matrix for different loss categories is given in Resettlement Framework Document. b This includes: (i) leaving spaces for access between mounds of soil; (ii) providing walkways and metal sheets to maintain access across trenches for people and vehicles where required; (iii)
increased workforce to finish work in areas with impacts on access; (iv) timing of works to reduce disruption during business hours; and (v) phased construction schedule and working one
segment at a time and one side of the road at a time.
c For example assistance to shift to the other side of the road where there is no construction.
d Affected children, women, and other vulnerable affected persons to be provided special assistance in the form of literacy and numeracy classes, following a demand survey .
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
14
VII. INCOME RESTORATION AND REHABILITATION
30. Affected persons will be provided 30 days advance notice to ensure no or minimal
disruption in livelihood. If required, they will also be assisted to temporarily shift for
continued economic activity; for example, they will be assisted to shift to the other side
of the road where there is no construction. Ensuring there is no income or access loss
during subproject construction is the responsibility of the Contractor. Consistent with the
environmental assessment, the Contractor will ensure: (i) that space is left for access
between mounds of soil; (ii) walkways and metal sheets provided to maintain access
across trenches for people and vehicles where required; (iii) increased workforce is
available to finish work in areas with impacts on access, and timing of works in such
areas that it reduces disruption during business hours; and (iv) phased construction
schedule is followed and work undertaken on one segment at a time and one side of the
road at a time.
31. Should construction activities result in unavoidable livelihood disruption,
compensation for lost income or a transitional allowance for the period of disruption,
whichever is greater, will be provided. Vulnerable affected persons will be given priority
in project construction employment. Highly vulnerable affected persons such as child
laborers and woman-headed households shall be identified and given the opportunity to
enroll in literacy and/or numeracy camps (14 day camps), following a demand survey by
the implementing NGO to determine the proportion willing to enroll.
32. Compensation and assistance to affected persons must be made prior to
possession of land and/or assets and prior to the award of civil works contracts.
33. For OHT sites proposed within school compounds, care must be taken to ensure
that the present use of the major portion of such land (as playground) is not affected. In
addition, each of the government schools will be provided water connections, and the
primary and middle school presently lacking toilet facilities will be provided toilets for
boys and girls. The Inter-level Muslim High School (the only affected non-government
school) will be provided a water connection and toilet facilities for boys and girls. These
measures will lead to further positive outcomes for the subproject.
VIII. RESETTLEMENT BUDGET AND FINANCING PLAN
34. The resettlement cost estimate for the subproject (Table 4) includes eligible
compensation, resettlement assistance as outlined in the entitlement matrix, and support
cost for the Resettlement Plan. The government will finance resettlement implementation.
The total resettlement cost for the subproject is Rs. 8.900 million.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
15
Table 3: Summary of Resettlement Costs
Tranche 1
Bhagalpur
Water Supply
(INR)
Cost in INR
Resettlement plan preparation
Census/socio-economic survey of affected persons, Inventory of assets, reports
Personnel Costs
Personnel Costs of PMU/PIU/PMC personnela
Resettlement plan Implementation
Administrative and implementation costs : Implementing NGO
NGO engagement (personnel costs, office rental, physical facilities and materials)b 3,300,000
Resettlement Plan updation and/or surveys 270,000
Demand Surveys of Vulnerable affected persons for Literacy/Numeracy workshops 200,000
Internal Monitoring Surveys and/or Reporting 270,000
Assistance/Compensation/Mitigationc
Compensation for loss of landd -
Mitigation measures 1,800,000
Assistance/compensation for loss of non land assets to non-titled persons 270,000
Rebuilding affected structurese 270,000
Grievance Redress
Meetings, Consultations and Reporting 270,000
Contingencies
Price (5%) 350,000
Physical (20%) for unanticipated impacts such as temporary impacts on structures or temporary
loss of land), cost of renting out space and/or hiring labour to move vendors, cost of moving
kiosks, reconstruction of movable structures, if required etc.; or livelihoods training for fishing
community and / or literacy and/or numeracy camps for affected child labour and other highly
vulnerable affected personsf
1,900,000
TOTALg 8,900,000 a Personnel costs for Resettlement/Social Development Specialists in PMU/PIU/PMC and utility shifting costs
included in Detailed Cost Estimates for the investment program, are not presented in the above table. Utility
shifting costs shall be borne by state government of Bihar and/or ULB (as part of their 30% share of project
cost). b The Implementing NGO will be involved in resettlement as well as other activities such as IEC and/or
disclosure, consultation and participation, implementation of components of environmental management plan,
etc., NGO engagement costs indicated above cover all of these aspects. NGO will have to identify vulnerable and
women-headed household in consultation with ULB, to ensure their inclusion in the project its benefits. This is
related to broader project goals and is included in Resettlement Plan implementation costs as it is an activity to
be undertaken by the NGO. c Since transect walks revealed that all affected persons can be assisted to shift to nearby locations and are willing
to do so, no economic impact is anticipated. d Toilet facilities requirement estimation could not be undertaken on the basis of norms due to space restrictions
(inadequate land available for provision of toilets as per norm). Hence, requirement is identified on the basis of
user demand and/or consultations with school authorities. Identified requirements are: for the government
primary (1 unit), Government Middle School (4 units) and Muslim School (7 units). e Temporary shanties, offices and eating places at OHT 3/1. f Estimation of cost of literacy and numeracy camps to be determined based on demand survey. g Cost of consultation, participation and disclosure included in Detailed Cost Estimates of the investment
program (refer Annex 5), are not included in the above table.
Source: ADB. 2008. Project Preparatory Technical Assistance to India for Preparing Bihar Urban Development
Project. Manila.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
16
IX. INSTITUTIONAL ARRANGEMENTS
A. Implementation Arrangements
35. The Urban Development and Housing Department (UDHD) of Government of
Bihar is the Executing Agency (EA) for the project, which will receive strategic
directions from a state-level Steering Committee. The PMU within UDHD will have an
ESMC. Bihar Urban Infrastructure Development Finance Corporation (BUIDCo) will
house the PIU at state-level (Patna). PIU field offices shall be set up in each project town
to manage the implementation of subprojects. In addition, CLCs cum GRC will be set up
in each project town to periodically review subproject progress, facilitate smooth
implementation and finalize proposals for any legal, operational, and financial changes
required, in discussion with the PMU and UDHD.
36. The ESMC, PMU will be assisted by the PMC who will prepare
IEE/EIA/Resettlement Plan/IPP reports and provide advice on policy reforms. The PMU
will endorse subproject IEEs/EIAs and Resettlement Plans/IPPs prepared by the PMCs
and will have financing and monitoring responsibilities. ESMC will co-ordinate with
national and state agencies to resolve inter-departmental issues, if any. ESMC will also
monitor physical and non-physical activities under the investment plan and will monitor
implementation of safeguards plans and guide PIU as and when necessary. The PMU,
with support from PIU/PIU field offices (and implementing NGOs in case of resettlement
and/or indigenous people issues) will ensure mitigation of negative environmental and
social impacts due to the subproject, if any. The ESMC will oversee implementation the
EARF/Resettlement Framework/Indigenous Peoples Planning Framework (IPPF) by the
PIU/implementing NGO.
37. The PMCs will have an Environment Specialist and Resettlement/Social
Development Specialist who will be responsible for the preparation of IEE/EIA and
Resettlement Plan/IPP reports respectively. The Environment Specialist and
Resettlement/Social Development Specialist of PMC will review and finalize all reports
in consultation with the ESMC of PMU. The Environment Specialist and
Resettlement/Social Development Specialist of PMC will submit periodic monitoring and
implementation reports to PMU, who will take follow-up actions, if necessary.
38. The ESMC of PMU will endorse and/or submit periodic monitoring reports
received from PMC to the Program Director, PMU who will then submit these to ADB.
The monitoring report will focus on the progress of implementation of the IEE/EIA and
EARF, Resettlement Plan/Resettlement Framework and IPP/IPPF, issues encountered
and measures adopted, follow-up actions required, if any, as well as the status of
compliance with the subproject selection criteria, and relevant loan covenants. The PMU
will seek state government’s clearance for submission and disclosure of the
environmental and social monitoring report to ADB.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
17
B. Program Implementation Unit (PIU)
39. The PIU at state-level will have an Environment Officer and Resettlement Officer
who will be responsible for implementation of the Environmental Management Plan in
each EIA/IEE and the Resettlement Plan/IPP respectively. Both officers will undertake
surveys and record their observations throughout the construction period to ensure that
safeguards and mitigation measures are provided as intended. The PIU through the
implementing NGO will be responsible for delivery of entitlements to affected persons.
In addition to the Environment Officer and the Resettlement Officer, the PIU will have a
Public Relations Officer. Together, they will be responsible for implementing and
monitoring safeguards compliance activities, public relations activities, gender
mainstreaming activities and community participation activities. It will be responsible for
obtaining statutory clearances and obtaining no objection clearances from government
agencies/other entities and entering into agreements with them for use of their land. It
will also coordinate for obtaining right of way clearances with related State and National
agencies. The PIU field office in Bhagalpur will have a Safeguards Officer who will be
responsible for data collection for IEE/EIA and Resettlement Plan/IPP preparation and
implementation. The PIU field office will obtain rights-of-way clearances and prepare
progress reports with respect to IEE/EIA and Resettlement Plan/IPP implementation.
40. The PIU shall recommend entitlements (finalized by the PIU/Design and
Supervision Consultant (DSC)/NGO in consultation with affected persons), which will be
examined/approved by the PMU, and will release payment. The PIU through the
implementing NGO will be responsible for delivery of entitlements to affected persons.
Organizational procedures/institutional roles and responsibilities for Resettlement Plan
implementation and steps/activities involved in delivery of entitlements are described in
Table 5.
C. Implementing NGO
41. The implementing NGO will assist the PIU in implementing and monitoring the
Resettlement Plan/IPP (duly approved by the PMU and reviewed/cleared by ADB prior
to implementation). The implementing NGO should have prior experience in resettlement
and indigenous people issues, have staff fully conversant with the provisions of the
Resettlement Plan/IPP, and adequate understanding of norms and customs of and respect
for indigenous peoples. NGOs hired for Resettlement Plan/IPP implementation will also
be responsible for addressing HIV/AIDS, and core labor standards. The NGO to be
procured should have experience in addressing such social issues.
42. The role of the NGO in Resettlement Plan implementation will be that of a
facilitator of the resettlement process. The NGO will work as a link between the project
and the affected community. They will educate the affected persons on the need to
implement the project and subprojects, on aspects relating to land acquisition and
resettlement measures and ensure proper utilization of compensation paid to the affected
persons under the entitlement package. After the approval of the micro plans, the NGO
will issue identity cards to the entitled persons. The NGO shall:
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
18
(i) Build a rapport with affected persons/indigenous peoples and PMU/PIU;
(ii) Educate affected persons on their rights, entitlements, and obligations
under the Resettlement Plan/IPP;
(iii) Ensure that affected persons/indigenous peoples including vulnerable
households receive their full entitlements;
(iv) Where options are available, provide advice to affected persons on the
relative benefits of each option;
(v) Assist affected persons on grievance redress through the established
system; and
(vi) Collect data as required to help PMU monitor and assess progress.
43. The responsibilities of NGOs in Resettlement Plan/IPP implementation will
include the following:
(i) Work in close co-ordination with the ESMC (PMU) to implement the IPP;
(ii) Facilitate transparency in process4 and public participation;
(iii) Take the lead in joint verification and identification of affected
persons/indigenous peoples/vulnerable households, enlist affected
persons/indigenous peoples/vulnerable households, undertake counselling
for livelihood restoration, dissemination of project policies, documents,
etc.;
(iv) Identify training needs of CBOs/indigenous peoples/vulnerable groups for
income generation activities/literacy and numeracy and ensure that they
are adequately supported;
(v) Put forth grievances of affected persons/indigenous peoples to the GRC;
(vi) Generate awareness about livelihood restoration/livelihoods skills
development activities and opportunities for employment in project related
activities among affected persons/indigenous peoples/vulnerable groups,
and help them to make informed choices;
(vii) Assist the Safeguards Officer (PIU) in disbursement of checks (monetary
compensation) to affected persons;
(viii) Participate in public meetings and consultations as and when required; and
(ix) Submission of periodic Resettlement Plan/IPP implementation reports to
the ESMC (PMU).
44. The success of NGO inputs will largely depend on their liaison with affected
persons and other concerned government agencies. Arrangements would have to be made
during the first month of project implementation to set up the various committees and
implementation mechanisms required.
45. Figure 2 depicts the investment program’s implementation arrangements for
environmental and social safeguards.
4 The NGO will ensure that due entitlements flow to the affected persons/indigenous peoples/vulnerable households in
the most effective and transparent manner.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
19
Figure 2: Bihar Urban Development Investment Program Environmental and Social
Safeguards Implementation Arrangements
BUIDCo = Bihar Urban Infrastructure Development Corporation, ESMC = Environment and Social Management
Coordinator, NGO = nongovernmental organization, PIU = Project Implementation Unit, PMC = Project
Management Consultant, PMU = Project Management Unit, PRO = Public Relations Officer, UDHD = Urban
Development and Housing Department.
46. Table 4 gives the institutional roles and responsibilities for preparation and
implementation of Resettlement Plan/IPP.
BUIDCO/PIU
State Level
UDHD/ PMU
ESMC
Resettlement Officer Environment Officer PRO
PIU City level
Safeguards Officer
Displaced Persons
Implementing NGO
PMC
Resettlement/Social Specialist
Environmental
Specialist
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
20
Table 4: Organizational Procedures/Institutional Roles and Responsibilities for
Resettlement Plan Implementation
Activities Agency
Responsible
Subproject Initiation Stage
Finalization of sites/alignments for subprojects PMU
Disclosure of proposed subproject details including land acquisition and
proposed entitlements / mitigation measures by issuing Public Notice
Meetings at community/household level with affected persons of
land/property
Disclosure of GRM/process
Formation of Valuation Committees
PMU
NGO/PIU
PMU/PIU/NGO
PMU
Report (IEE/EIA/Resettlement Plan/IPP) Preparation Stage
Conducting census of all affected persons PMU/PIU/NGO
Conducting FGDs/meetings/consultations/workshops during SIA surveys
and IEE/EIA preparation
PMU/PIU/NGO
Computation of replacement values of land/properties proposed for
acquisition and for associated assets
Valuation
Committee/PIU
Categorization of affected persons for finalizing entitlements PIU/PMU
Formulating compensation and rehabilitation measures
Conducting discussions/meetings/workshops with all affected persons and
other stakeholders
PIU/PMU
PIU/NGO
Fixing compensation for land/property in consultation with titleholders Valuation
Committee/PMU
Finalizing entitlements and rehabilitation packages for all affected persons PIU/PMU
Disclosure of final entitlements and rehabilitation packages PIU/NGO
Clearance of IEE/EIA/Resettlement Plan/IPP PMU/ADB
Sale deed execution and clearance/release of payment PMU
Delivery of entitlements PIU/NGO
Taking possession of land PMU
Implementation Stage
Implementation of proposed rehabilitation measures NGO/PIU
Consultations with affected persons during rehabilitation activities NGO/PIU
Grievance redressala NGO/Safeguards
Officer/GRC
Internal monitoring PMU/PIU
External monitoring (in case of Category A subprojects) External Agency FGD=focus group discussions, GRC = Grievance Redress Committee, GRM = Grievance Redress
Mechanism, NGO=nongovernmental organization, PIU = program implementation unit, PMU = program
management unit, SIA = social impact assessment. a The program will have a GRM for redressing the grievances of affected persons, including indigenous
people communities, if any.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
21
D. Institutional Capacity
47. Since no externally-aided urban infrastructure projects requiring capacity for
environmental management planning, resettlement planning, implementation and
monitoring in accordance with internationally accepted guidelines/safeguards
frameworks have been implemented in Bihar, and presently, entities such as BUIDCo and
ULBs do not have environmental/social safeguards personnel, capacity to handle
environmental/involuntary resettlement/indigenous people impacts, gender and
vulnerability issues, etc., needs to be built. The PMCs will be responsible for training of
PMU and PIU staff on aspects such as environmental planning/resettlement
planning/implementation, social protection and gender, including the specific recording,
reporting, and disclosure requirements.
48. Owing to the complexity of projects with indigenous people issues, there will be a
special focus on capacity building of government agencies and PMU/PIU staff on social
(distinct social, economic and cultural traits and traditions of indigenous peoples and the
importance of preserving them, including indigenous knowledge systems, etc.), legal
(traditional rights over land and land tenure issues) and technical aspects in such projects,
with an adequate budgetary provision.
49. The PMC will also be responsible for training the implementing NGO on
provisions of EARF/Resettlement Framework/IPPF. Further, capacity building of
community-based organizations (including indigenous people groups) in the project area
will be undertaken by the implementing NGO to ensure that they are able to represent the
affected groups more effectively. The PMC shall undertake this task with external
resources, e.g., anthropologists and development practitioners with relevant experience,
as required. Additional measures to enhance institutional capacity include exposure visits
of PMU, PIU, and implementing NGO staff to other Indian states that have successfully
implemented ADB funded projects.
E. Coordination with other Agencies and Organizations
50. The PMU will develop lateral linkages to achieve convergence/mobilize resources
to benefit affected persons (e.g. establishing linkages with the government’s livelihoods
programs) and to achieve the desired results expected from IEE/EIA and Resettlement
Plan/IPP implementation.
X. IMPLEMENTATION SCHEDULE
51. The resettlement implementation schedule is given in Table 6 below.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
22
Table 5: Schedule of Resettlement Implementation
Activity Months
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Establishment of PMU (including
ESMC) and PIU
Appointment of SDS / Resettlement
Specialist (PMC)
Appointment of NGOs
Briefing of the CLC on GRC functions
Census and socio-economic surveys
(issuance of ID cards)a
Consultations and disclosure
Confirmation of government land to be
used and transfer from other departments
RP preparationb
RP review and approval (PMU and
ADB)c
Issue notice to affected persons
Compensation and resettlement
assistance
Relocation as required
Skills training as required
Takeover possession of acquired
property
Internal monitoring
Handover land to the Contractor
Start of civil works
Rehabilitation of temporarily occupied
lands Immediately after construction
ADB = Asian Development Bank, ESMC = Environment and Social Management Coordinator, GRC = Grievance Redress Committee, NGO = nongovernmental organization, PIU = Project
Implementation Unit, PMC = Project Management Consultant, PMU = Project Management Unit, SDS = Social Development Specialist. a The census will be the cut-off date for non-titled affected persons. For titled affected persons, the cut-off date is the date of notification. b The Resettlement Plan will be updated based on final detailed design and affected person census and surveys. c Endorsement and disclosure of finalized Resettlement Plans consistent with the Resettlement Framework to be undertaken.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
23
XI. MONITORING AND REPORTING
52. Resettlement Plan implementation will be closely monitored to provide the PMU
with an effective basis for assessing resettlement progress and identifying potential
difficulties and problems. Internal monitoring will be undertaken by the PIU (through the
NGO) with assistance from the PMU. Internal monitoring will involve: (i) administrative
monitoring to ensure that implementation is on schedule and problems are dealt with on a
timely basis; (ii) socio-economic monitoring during and after any resettlement impact
utilizing baseline information established through the socio-economic survey of affected
persons undertaken during project sub-preparation; and (iii) overall monitoring to assess
affected person status. Job charts will be given to the PMU indicating the targets to be
achieved during the month. Monthly progress report will be prepared and submitted to
PMU, reporting actual achievements against the targets fixed in their respective job
charts and reasons for shortfalls, if any. The PIU will be responsible for managing and
maintaining affected person databases, documenting results of affected person census,
and verifying asset and socio-economic survey data which will be used as the baseline for
assessing Resettlement Plan implementation impacts. The EA will submit all semi-annual
monitoring reports to ADB for review (please refer to the Resettlement Framework for
further details).
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
24
Annex 1: Methodology for Estimation of Temporary Impacts
1. Transect walks were undertaken for estimation of temporary impacts in
representative road sections in areas where water supply and sewerage pipelines and slum
improvement is proposed. Transect walks were conducted using a standard format for
recording details at 10 meters intervals and a checklist to gather socio-economic details
on affected persons. Three transect walks were conducted by the survey team along with
project engineers along proposed pipeline lengths; one each in high, medium and low
density areas, covering a length of 300 m in each. Based on the data gathered from
transect walks and confirmation with program preparation engineers and concerned
officials, the extent of temporary impacts were estimated/projected for the entire stretch
of pipeline.
2. The following information was captured through transect walks: number of
temporarily affected persons (titled and non-titled), their livelihoods, whether titled or
non-titled, whether BPL/indigenous people/female-headed household, whether common
structures/trees, etc., affected, whether income sources affected, etc.
CHECKLIST FOR TRANSECT WALKS: SOCIO-ECONOMIC SURVEY OF
AFFECTED PERSONS
City____________________
1. Address/locality:__________________________________________________
2. Name of respondent: _____________________________________________
3. Occupation and Income
Occupation Income (√ per day / per month
/ per year)
a. Primary Occupation
b. Secondary Occupation
4. Other Characteristics (Tick appropriate box):
Below Poverty Line
Household
Scheduled Caste Scheduled Tribe
Woman-headed
Household
Disabled Headed
Household
Child Labour
5. Characteristics of Structure (√)
a. Type Kutcha Semi-pucca Pucca
b. Use Residential Commercial
Residential-commercial /
Other (specify) (√)
c. Status Own Rent/Lease (√) Other
d. Title (for
“Own” structure)
Titled Non-titled
e. Characteristics
e.g. mobile / fixed
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
25
6. No. of occupants/employees ________________
7. If employees, average Wages paid ____________
8. Access to Common Facilities at current location (specify)_________________
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
26
Table A1: Summary of Socio-economic Information from Transect Walks
Category Nos. Backward
Community, if
any
Occupation Daily
Income
Range
Average
Daily
Income
Remarks
High Density – DN Singh Road, Bhagalpur
Temporarily
Affected
Persons
32 (Including
three below
poverty line, of
which 2 were
woman- headed
households and
2 children)
OBC-17, SC-3
and Religious
Minority-2
Fruit, Vegetable,
Tea, Datun (neem
sticks) sellers and
sellers of ceramic
wares, posters,
clothes, building
material (cement,
lime and mud) and a
watch repairer etc.
Rs70 to
Rs500
Rs175 All fruit and vegetable sellers
had baskets or carts with
wheels; tea seller had a table
and tarpaulin cover; watch-
repairer had a table; clothes
seller had a temporary
structure (bamboo and
tarpaulin); poster seller used
the footpath; ceramic wares
seller used a push cart.
Of the 2 children, 1 was a
member of the family (owner
of business) while another was
an employee.
Low Density – Barari, Bhagalpur (road in front of Mount Carmel School and Protected Forest)
Temporarily
Affected
Persons
1
OBC-1- Tea and cigarette
stall-
Rs120-
150-
Rs135- Temporary wooden structure
(moveable)
Medium Density – Swami Vivaekanand Path, Bhagalpur
Temporarily
Affected
Persons
Five
(including one
below poverty
line)a
OBC-2, SC-1 Tea stall, roadside
eatery, two-wheeler
repair mechanic,
clothes ironing stall
etc.
Rs80 to
Rs150
Rs126 Tea stall had a moveable
platform for making tea, a
bench for customers and was
tarpaulin covered;
Roadside eatery had
(moveable) tables and chairs
and a temporary structure
(bamboo and tarpaulin);
Two-wheeler mechanic used
the footpath (no structure);
Clothes ironing stall was a
temporary structure (bamboo
and tarpaulin). a Based Topographic Survey conducted in Bhagalpur, the total road length in the town is 317 km; 74 km will be covered by water
distribution networks under other programs. Of the remaining 243 km of roads, 20% are high density, 30% are medium density and 50%
are low density roads.
Summary of discussions held with persons likely to be temporarily affected:
(i) All hawkers and vendors are willing to shift to the other side of the road or nearby road for a few months during the
construction phase (as they perceived that the water supply project is required in Bhagalpur and would benefit all residents);
(ii) About 20% of the vendors in the High Density Area had employees or dependent relations working with them, who are
paid a fixed rate per day (ranging between Rs50–100 per day) or a share of daily profits (depending on their status); some of
the owners do not hawk wares, but have employees to do so, who report every evening to the owners and hand over the
profits to them; in turn, they are paid fixed daily wages (for a majority, ~Rs50 – 75 per day). Children and elderly women
who are employed by persons other than family are paid the lowest wages (Rs30-50 per day)
(iii) Maximum sale/income in High Density Area is during the festivals (Diwali, Chhat, Id, Dussehra–October to December);
hence it will be good if construction during these months/seasons can be avoided; vendors in other areas reported similar
earnings throughout the year.
(iv) Lowest income in High Density Area is during the rainy season, income losses are highest in these season as buyers are
less.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
27
Annex 2: Summary of Discussions Held with Stakeholders at subproject Sites5
S. No. Proposed
zone /OHT
No.
Location and Site
description
Ownership Present features /
land use
Summary of Discussions with Local
People
Pictorial view of
site/location
1 4/4-1 At Launch Ghat Road
beside BCE Hostel,
Barari
(Changed location wrt
SAR)
Bhagalpur
College of
Engineering,
Education
Department, GoB
Unutilised corner of
playground
Discussions with teachers, students &
residents of the area (Krishna Devi, Lal
Bhadur Singh, Beena Devi, Neelam and
Bulu Devi) revealed acute felt need for
improved water supply and drinking water
facilities in school and surrounding areas.
2 4/4-2 Adjacent (west side) to
Bhagalpur Central Jail,
near Anandanagar
Colony (south west of
Sunderban)
Jawaharlal Nehru
Medical College,
Medical
Department, GoB
Open field, scrub land
high spot
Water pipeline laid in area, but no water
supply at present. Acute need for improved
system.
5 Includes OHTs at 2/1 and 3/3 to be taken up in Tranche 2.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
28
S. No. Proposed
zone /OHT
No.
Location and Site
description
Ownership Present features /
land use
Summary of Discussions with Local
People
Pictorial view of
site/location
3 4/4-4 In front of medical staff
quarter, Surkikal
(New additional OHT
wrt SAR)
Jawaharlal
Medical College,
under Medical
Department, GoB
4 3/3-1 South side open space of
municipality office
building
Kachari Chowk
Bhagalpur
Municipal
Corporation
Temporary shanties,
offices and eating
places
(There are a number of temporary
shanties, offices, and eating places)
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
29
S. No. Proposed
zone /OHT
No.
Location and Site
description
Ownership Present features /
land use
Summary of Discussions with Local
People
Pictorial view of
site/location
5 3/3-2 Within campus of Road
Division, Bhagalpur
(behind the laboratory of
the Rural Development
Department)
Adampur
Executive
Engineer, Road
Division,
Government of
Bihar
Open field, shrub
land
6 3/3-3
(This OHT
is not
included in
BWSP1
under
Tranche 1,
but instead
will be
reviewed by
the
Contractor)
Barahpura Eidgarh in
the land of defunct tube
well of Municipal
Corporation
Sub Divisional
Officer,
Bhagalpur, GoB
Shrub land Surrounding land under Idgah Committee.
Committee members (Md. Soin Ansari and
Md. Ali Shabbir) expressed the need to
address water problems in the locality.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
30
S. No. Proposed
zone /OHT
No.
Location and Site
description
Ownership Present features /
land use
Summary of Discussions with Local
People
Pictorial view of
site/location
7 1/1-1 Corner of University
Campus (opposite to the
office of the Industrial
Department, Deputy
Development Officer)
Bhagalpur
University
(government
university)
Near Mango orchard Mainly institutional stakeholders in area.
Improved water supply system would
benefit staff of these institutions and
people living in the area. Discussion held
with Prof CM Das, Registrar, who agreed
in principle to allow use of the land
required for an overhead storage reservoir.
Bhagalpur managing committee has sent a
formal request to the Registrar for the use
of the land.
8 1/1-2 North side of Constable
Training School
Chairman, Bishop
House, Christ
Church
Compound,
Diocesan Centre,
Bhagalpur
Scrub land,
Vacant,
High spot
Brief discussion with two guards revealed
that the land in question is presently not
used.
9 1/1-3 Mahshay Deodi in
Champanagar
Municipal
corporation
Playground/ open
land; Durga temple in
one corner
Area suffers from acute water problems,
especially in summer.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
31
S. No. Proposed
zone /OHT
No.
Location and Site
description
Ownership Present features /
land use
Summary of Discussions with Local
People
Pictorial view of
site/location
10 1/1-4 Abir Mishra Lane in
Nath nagar
Municipal
corporation
Open land Discussions with residents of nearby area
(Md. Iqram Ansari, Md. Iqbal Khaleel).
Ground water is not potable/usable for
domestic purposes. Cloth dyeing workshop
(Rangi Karkhana) in area led to ground
water pollution.
11 2/2-1
(This OHT
is not
included in
BWSP1
under
Tranche 1,
but instead
will be
reviewed by
the
Contractor)
Government Teacher
Training College near
Ghantagarh Chowk (west
side of open land)
Government
Teacher Training
College,
Bhagalpur, GoB
Existing reservoir
Higher elevation;
hence suitable for
water tank.
Residents and users of site (Alka Yadav,
Amrita, Kallu Yadav) expressed the need
for improved water supply as well as space
to keep cattle. Hence, space below/ around
water tank must be available for cattle-
keeping.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
32
S. No. Proposed
zone /OHT
No.
Location and Site
description
Ownership Present features /
land use
Summary of Discussions with Local
People
Pictorial view of
site/location
12 2/2-2 Jaglal High School
premises at Company
Bagh
District Education
Officer,
Bhagalpur, GoB
Stack of building
waste materials
School authorities would be happy to
provide space for water tank near school
gate. New school building constructed
recently with toilet facilities. Water is a felt
need.
13 2/2-3 Inter-level Muslim High
School
(In the SAR it was at the
front of the School
Building; now it is
shifted to the back of the
main block as discussed
with the Principal on 10
Aug 2013)
Land belonging to
Muslim School
Trust, Bhagalpur.
Vacant Discussions held with Dr. Md. Zahirullah,
Principal and Dr. Farukh Ali, General
Secretary of School Managing Committee.
In principle, both agreed to allow usage of
part of school land for overhead storage
reservoir; subject to approval by the
Managing Committee. Municipal
Corporation, Bhagalpur has sent a formal
letter to the school authorities regarding the
issue.
(Proximity to trees needs to be
investigated)
14 5/5-1 Open land to the north of
the temple, Sarbajanik
Thakurbari, Warsaliganj
(Changed location wrt
SAR)
Trust of Sri Sri
108 Radhakrishna
Sarbajanl]ik
Thakurbari
Samity,
Warsaliganj
(Discussion with
the President of
the Committee
reveals that they
had no objection
One hand tube well Discussion with Mr. Shekhar Kumar
Gupta, School Teacher, students and
residents of nearby areas. At present, no
water supply in school and surrounding
areas; residents face great difficulties
related to water availability in summer;
need improved water supply facilities.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
33
S. No. Proposed
zone /OHT
No.
Location and Site
description
Ownership Present features /
land use
Summary of Discussions with Local
People
Pictorial view of
site/location
to the proposal and
would hand over
the required letter
to BMC)
15 5/5-2 North of Bazar Samity
campus, Agriculture
Market Complex,
Baghbari
Sub Divisional
Officer – cum –
Special Officer,
Krishi Utpadan
Bazar Samity,
Bhagalpur under
the Administrator,
Bihar Raj Krishi
Bipanan Parishad
Shrub land
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
34
S. No. Proposed
zone /OHT
No.
Location and Site
description
Ownership Present features /
land use
Summary of Discussions with Local
People
Pictorial view of
site/location
16 5/5-3 Open land to the west of
the tube well, Aliganj
Kataghat, Hussainabad
Bhagalpur
Municipal
Corporation
Tube well of
corporation
Residents expressed that ever since
tubewell of Corporation became defunct,
they face great difficulty in getting water
for domestic use.
17 5/5-4 Mughalpura Kawali
Maidan, Hussainabad
Government Land
(SDO, Bhagalpur)
Open ground Extreme hardships faced due to water
scarcity; residents are very keen on
overhead storage reservoir being built at
the location.
18 5/5-5 Near Maulana Chowk
Maidan, Maulana Chowk
In Ward 39 on vacant
land where there is a
BSNL tower adjacent to
Badrul Hussain land
(Changed location wrt
SAR)
Bhagalpur
Municipal
Corporation
Open ground
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
35
Annex 3: Survey Number and Ownership Details of Selected Sites for Subproject Facilities6
S.
No.
Location OHT
zone/No.
Ownership Khata
No.
Khasra
No.
Area
(ha)
1 At Launch Ghat Road beside BCE Hostel, Barari 4/4-1 Bhagalpur College of Engineering, Education
Department, GoB
783 1118 0.155
2 Adjacent (west side) to Bhagalpur Central Jail, near Anandanagar
Colony (south west of Sunderban)
4/4-2 Jawaharlal Nehru Medical College, Medical
Department, GoB
97 174 0.196
3 In front of medical staff quarter, Surkikal 4/4-4 Jawaharlal Medical College, under Medical
Department, GoB
- - -
4 South side of municipality office building, Kachari Chowk 3/3-1 Bhagalpur Municipal Corporation 807 158 Kha) 0.065
5 North of Bazar Samity campus, Agriculture Market Complex,
Baghbari
5/5-2 Sub Divisional Officer – cum – Special Officer,
Krishi Utpadan Bazar Samity, Bhagalpur under the
Administrator, Bihar Raj Krishi Bipanan Parishad
1106 1909 3.5835
6 North side of Constable Training School 1/1-2 Chairman, Bishop House, Christ Church Compound,
Diocesan Centre, Bhagalpur
598 819 2.625
Lok Nirman Vibhag, Bhagalpur 598 853 0.0765
7 Abir Mishra Lane in Nath nagar 1/1-4 Municipal corporation 601 755 0.0155
8 Jaglal High School premises at Company Bagh 2/2-2 District Education Officer, Bhagalpur, GoB 907 35 0.353
9 Barahpura Eidgarh in the land of defunct tube well 3/3-3 Sub Divisional Officer, Bhagalpur, GoB 1866 1118 0.155
10 Within campus of Road Division, Bhagalpur (behind the
laboratory of the Rural Development Department), Adampur
3/3-2 Executive Engineer, Road Division, Government of
Bihar
1089 1045 0.049
11 Corner of University Campus (opposite to the office of the
Industrial Department, Deputy Development Officer)
1/1-1 Bhagalpur University (government university) 1463 3391 0.148
12 Mahshay Deodi in Champanagar 1/1-3 Municipal Corporation - - -
13 Government Teacher Training College near Ghantagarh Chowk
(west side of open land)
2/2-1 Government Teacher Training College, Bhagalpur,
GoB
479 325 0.0315
14 Inter-level Muslim School (On high way between Jain Temple--
Railway line)
2/2-3 Muslim School Trust 595 68 0.062
15 Open land to the north of the temple, Sarbajanik Thakurbari,
Warsaliganj
5/5-1 Trust of Sri Sri 108 Radhakrishna Sarbajanl]ik
Thakurbari Samity, Warsaliganj
646 911 0.0865
16 Open land west of the tube well, Aliganj Kataghat, Hussainabad 5/5-3 Bhagalpur Municipal Corporation 1110 865 0.052
17 Mughalpura Kawali Maidan, Hussainabad 5/5-4 Government Land (SDO, Bhagalpur) - - -
18 Near Maulana Chowk Maidan, Maulana Chowk 5/5-5 Bhagalpur Municipal Corporation - - -
Source: Municipal Corporation, Bhagalpur
Note: Bhagalpur Municipal Corporation to provide missing details in above list (extent of land area, survey numbers).
6 Includes OHTs at 2/1 and 3/3 to be taken up in Tranche 2.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
36
Annex 4: Subproject Sites with Footprints of Proposed Facilities
OHT 1
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
54
Annex 5: Consultation and Participation Plan
C&P Activity Target Stakeholders Type of
Participation
Objectives of the C&P
Activity
Responsible
Unit/Persons
Time Frame Cost Estimate
Project orientation
Workshop for
government officials,
officers, and staff on the
Investment program (1
whole day)
50 government officials and
staff per project orientation
workshop consisting of
representatives from the
UDHD, BUIDCo, WDC,
DOEF, BSPCB, WRD, BRJP,
DOF, PDD, ULB officials and
staff, especially the Municipal
Corporations; and private
contractors
Information sharing
Consultation
Shared responsibility
Shared decision-
making
Introduce the project
Demonstrate the link between
improved water supply and
sewerage infrastructure and
good health, women’s
empowerment, and
environmental conservation
(Note: Seminar topics and
contents should be gender-
sensitive, socially inclusive,
and raise environmental
awareness).
Present Safeguards and
Social Frameworks and Plans
and disclosure requirements.
Discuss roles and
accountabilities of various
government units.
Discuss issues related to use
of government lands /
property for the project,
environmental risks.
Mitigate potential problems
e.g., citizens’ use of
government lands and
property that will be lost to
the project such as school
lands, public playgrounds,
environmental risks
especially to dolphins,
Gather and agree on
recommendations
ADB Project
Team, UDHD
Year 1:
Two project orientation
workshops (Patna,
Bhagalpur)
$1,000
4 POS for household 100 community members, Information sharing Introduce the project, PIU, ULB, in Years 1-2: Bhagalpur $ 1000/POS for
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
55
C&P Activity Target Stakeholders Type of
Participation
Objectives of the C&P
Activity
Responsible
Unit/Persons
Time Frame Cost Estimate
heads on the investment
program (half day)
2 POS for women only
on the investment
program (half day)
preferably, household heads,
with at least 30 women
participating per project
orientation seminar
At least 50 women community
members per project
orientation seminar
Consultation
Shared decision-
making
highlighting its importance
and benefits to the
community
Demonstrate the link between
improved water supply and
sewerage infrastructure and
good health, women’s
empowerment, and
environmental conservation.
(Note: Seminar topics and
contents should be gender-
sensitive, socially inclusive,
and raise environmental
awareness).
Present safeguards and social
frameworks and plans.
Gather concerns and views
related to water supply and
sewerage.
Gather recommendations.
cooperation with
the WDC and
NGOs.
household heads
X 4 POS =
$4,000
$ 500 / POS for
women only X 2
POS = $4,000
Total: $8,000
Four FGD, and eight
small group meetings on
resettlement and
compensation issues
(half day)
Affected Persons: Farmers,
titled and non-titled;
landowners, representatives of
affected schools (Bhagalpur
and Muzaffarpur); and
concerned NGOs per FGD
15 affected persons and NGO
representatives per small
group meeting
Information sharing
Consultation
Introduce the project.
Mitigate potential conflict.
Solicit the views of affected
persons on resettlement and
compensation.
Agree on resettlement
processes, location, and
compensation.
PMU, PIU, ULB,
in cooperation with
NGOs
Yrs 1-2:
Two FGDs, two small
group meetings
$ 500/FGD X 1 =
$500
$ 300/small group
meeting X 2 =
$600
Total: $1,100
One consultation
workshop with fishing
communities in
Bhagalpur (half day)
Representatives of fishing
communities in Bhagalpur
Information sharing
Consultation
Introduce the project,
highlighting its importance
and benefits.
Discuss conservation issues
and protection of common
PMU, PIU, in
cooperation with
NGOs
Year 1 Consultation
workshop = $500
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
56
C&P Activity Target Stakeholders Type of
Participation
Objectives of the C&P
Activity
Responsible
Unit/Persons
Time Frame Cost Estimate
sources of livelihood.
Discuss possible roles as
community watchdogs.
Mitigate potential conflict
Explore alternative means of
livelihood.
One Consultation
workshop (half day)
with temporarily
affected persons
50 hawkers/vendors, and small
shopkeepers affected per city
Information sharing
Consultation
Introduce the project.
Demonstrate the link between
improved water supply and
sewerage infrastructure and
good health, women’s
empowerment, and
environmental conservation.
Show possible livelihood/
business opportunities.
(Note: Seminar topics and
contents should be gender-
sensitive, socially inclusive,
and raise environmental
awareness).
Present social and
Resettlement Framework and
draft social and Resettlement
Plans.
Mitigate potential resistance
to the project.
Gather recommendations
Agree on remedial measures.
PMU, PIU in
cooperation with
NGOs
Year 1:
One consultation
workshop
$1,500
One Consultation
workshop with the
academe, NGOs, and
other civil society
organizations (1 whole
day)
50 representatives of the
academe, NGOs, and other
civil society organizations
from Patna and the four
project cities.
Information
sharing/knowledge
generation.
Consultation
Shared responsibility
Introduce the project.
Demonstrate the link between
improved water supply and
sewerage infrastructure and
good health, women’s
empowerment, and
environmental conservation.
PMU, in
cooperation with
the WDC and
NGOs
Year 1:
One consultation
workshop
Consultation
Workshop =
$1,000
Travel of
participants from
out of town =
$500
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
57
C&P Activity Target Stakeholders Type of
Participation
Objectives of the C&P
Activity
Responsible
Unit/Persons
Time Frame Cost Estimate
Show possible livelihood/
business opportunities.
(Note: Seminar topics and
contents should be gender-
sensitive, socially inclusive,
and raise environmental
awareness).
Gather knowledge on
conservation and mitigation
measures.
Mitigate potential resistance
to the project.
Discuss possible roles as
watchdogs of the project’s
implementation.
Gather other relevant
recommendation
Total: $1,500
Strategic and Action
Planning Workshop (1
whole day)
PMU/PIU Monitoring
Meetings (half day)
PSC Meetings (half day)
Town/City Committee
Meetings (half day)
PMU, members of the PSC,
members of the Town/City
Committee, PIU, and private
contractors / implementing
firms from Patna and 4 project
cities
Information sharing
Shared
responsibility.
Shared decision-
making
Control
Develop strategic and action
plans in accordance with the
project road map.
Review compliance with
social safeguards,
environment, and gender
frameworks and plans.
Discuss progress in
implementation, including
problems encountered and
means to mitigate/address
them.
Regularly report on the
progress of implementation.
PMU, PIU, ADB
Project Team
Planning Workshop:
Annually
PMU, PIU Monitoring
Meetings: Quarterly
PSC Meetings: Annually
Town/City Committee
Meetings: Quarterly
Planning
Workshop:
$1,000 X 5 years
= $5,000
PMU/PIU
Monitoring
Meetings: $300 X
4 = $1,200
PSC Meetings:
$300 X 4 years =
$1,200
Town/City
Committee
Meetings: $300 X
4 X 4 years =
$4,800
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
58
C&P Activity Target Stakeholders Type of
Participation
Objectives of the C&P
Activity
Responsible
Unit/Persons
Time Frame Cost Estimate
Participatory
Monitoring Meetings
(half day)
(for community
watchdogs)
20 representatives (50%
women) from the community
and civil society
(representatives of CBOs,
NGOs, ward committees,
fishing communities,
poor/slum communities,
private sector) in each project
city
Information sharing.
Shared responsibility
Surface issues and concerns
during project
implementation.
Discuss and recommend
measures to mitigate/address
the problems.
Monitor progress of project
implementation
ULB, NGO, WDC Participatory Monitoring
Meetings:
Semi-annually
$300 X 2
meetings X 4
years = $2,400
TOTAL COST OF CONSULTATION AND PARTICIPATION $28,200
ADB = Asian Development Bank, BRJP = Bihar Raiya Jal Parshad, BSPCB = Bihar State Pollution Control Board, BUIDCo = Bihar Urban Infrastructure Development Corporation, C&P =
consultation and participation, CBO = community-based organizations, DOEF = Department of Environment and Forests, DOF = Department of Finance, FGD = focus group discussion,
NGO = nongovernmental organization, PDD = Planning and Development Department, PIU = Project Implementation Unit, PMU = Project Management Unit, POS = project orientation
seminar, PSC = Project Steering Committee, UDHD = Urban Development and Housing Department, ULB = urban local body, WDC = Women’s Development Corporation, WRD = Water
Resource Department.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
59
Annex 6: Sample Grievance Redress Form
(To be available in Hindi, Urdu and Other Local Language, if any)
The _____________________________________Project welcomes complaints, suggestions, queries and
comments regarding project implementation. We encourage persons with grievance to provide their name
and contact information to enable us to get in touch with you for clarification and feedback.
Should you choose to include your personal details but want that information to remain confidential,
please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you.
Date Place of registration
Contact Information/Personal Details
Name Gender * Male
* Female
Age
Home Address
Village / Town
District
Phone no.
Complaint/Suggestion/Comment/Question Please provide the details (who, what, where and how) of your grievance below:
If included as attachment/note/letter, please tick here:
How do you want us to reach you for feedback or update on your comment/grievance?
FOR OFFICIAL USE ONLY Registered by: (Name of Official registering grievance)
Mode of communication:
Note/Letter
Verbal/Telephonic
Reviewed by: (Names/Positions of Official(s) reviewing grievance)
Action Taken:
Whether Action Taken Disclosed:
Yes
No
Means of Disclosure:
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
60
Annex 7: Summary Policy Frameworks
The Land Acquisition Act, 1894 and The National Policy for Resettlement and Rehabilitation 2007
provide the overarching framework for land acquisition and resettlement. In Bihar, compensation is
determined based on principles of Bihar Land Acquisition and Resettlement Policy, 2007; for Bihar
Urban Development Investment Program, Asian Development Bank’s Policy Guidelines will also need to
be followed. Table A7 provides a comparison of national, state and Asian Development Bank policies and
indicates how the Resettlement Framework addresses gaps in present policy.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
61
Table A7: Comparison of National, State and ADB involuntary resettlement Policy
Sl.
No. ADB’s SPS (2009)
LAA BLARRP NRRP
Remarks
(Gaps between Government and ADB
policies and Action Taken in the
Resettlement Framework to Bridge
the Gap)
1 Involuntary resettlement
should be avoided
wherever possible;
early screening to
identify involuntary
resettlement impacts and
risks.
Not defined in LAA Not defined in BLARRP NRRP aims to promote ‘non-
displacing or least displacing
alternatives’ but does not clearly
specify the need for early screening.
LAA and BLARRP do not deal with the
minimization of involuntary
resettlement. The Resettlement
Framework requires early screening.
2 Minimize involuntary
resettlement by
exploring project and
design alternatives.
.
Not defined in LAA Not defined in BLARRP NRRP aims to minimize
displacement and requires
exploration of alternatives for the
same.
LAA and BLARRP do not provide for
minimizing resettlement and do not
deal with alternate design.
The Resettlement Framework clearly
defines the procedures to minimize
involuntary resettlement through proper
alternate engineering design and
adequate consultation with stakeholders.
3 Conducting census of
displaced persons and
resettlement planning.
Not considered in LAA Need for surveys of affected
persons or resettlement planning
is not provided for in BLARRP.
However, BLARRP provides for
0.5% of site value upto a
maximum of Rs2 lakhs towards
resettlement costs, if requested
by the landowner.
Defined in NRRP, however, NRRP
is applicable only if 500 or more
people in the plains / 200 or more
ST households are affected.
No project involving displacement
of families beyond the defined
threshold can be undertaken without
a detailed Social Impact Assessment
and resettlement planning.
LAA and BLARRP do not provide for
census surveys of affected persons or
need for resettlement planning. Only
inventories of losses and lists of affected
persons are prepared under these. ADB
policy defines the need for a detailed
census through household surveys of
affected persons in order to assess
vulnerability and other entitlements.
This gap is addressed in the
Resettlement Framework through
incorporating the need for census survey
of affected persons and resettlement
planning in case of permanent or
temporary losses, regardless of scale.
4 Carry out meaningful
consultation with
affected persons, host
communities and NGOs
to ensure their
participation in
LAA notifies titleholders
prior to land acquisition,
but does not provide for
any consultation with
affected persons.
BLARRP does not clearly define
the need/process for
consultation, participation and
disclosure, however, its
provision for higher solatium if
landowner agrees to give land
NRRP provides for consultations
with the affected communities at
each stage, including public
hearings in the affected areas.
LAA and BLARRP do not specify the
need for ‘meaningful consultation’,
project disclosure (purpose of
acquisition, entitlements, compensation
etc.) and participation.
The Resettlement Framework for the
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
62
Sl.
No. ADB’s SPS (2009)
LAA BLARRP NRRP
Remarks
(Gaps between Government and ADB
policies and Action Taken in the
Resettlement Framework to Bridge
the Gap)
planning,
implementation,
and monitoring of
resettlement program.
ADB policy also
provides for ‘social
preparation’ to ensure
meaningful consultation,
where required.
willingly, implies some
consultation with affected
persons.
project advocates a consultation process
which involves all stakeholders
(affected persons, government
department/line agencies, local
community, NGOs, etc.), and the
consultation will be a continuous
process at all stages of the project cycle
such as project formulation, feasibility
study, design stage, implementation and
post implementation phase including
monitoring phase.
5 Establish a GRM. Not defined in LAA Not defined in BLARRP The grievance redressal mechanism
under NRRP includes Standing
(R&R) committees at the district
level, R&R committees at the
project level, and an Ombudsman
duly empowered in this regard.
The Resettlement Framework has
special provisions for grievance redress
procedures which includes formation of
a GRC, complaints cells and requires
the implementing NGO to have a CLO
and disclosure of the scope of
proceedings of meetings and
consultations and their outcomes.
6 Improve or at least
restore the livelihoods
of all displaced persons.
Not defined in LAA BLARRP provides for
livelihoods compensation to
displaced agricultural labourers
working on the affected land for
>3 years through a one-time
payment of two hundred days’
minimum wages. However, it
does provide for livelihoods
restoration; it also does not
consider loss of livelihoods for
any other category of displaced
person (other than agricultural
labor).
NRRP provides for employment
opportunities in the project, training,
scholarships for education; wage
employment in the project to titled
as well as landless affected families.
While BLARRP recognizes livelihoods
losses of non-titled agricultural
labourers, there is no provision for
restoration for lost incomes and
livelihoods. Loss of livelihoods suffered
by other titled/non-titled affected
persons is not considered.
The Resettlement Framework for the
investment program provides for a
census survey which helps create a
database on income and livelihood
losses; and compensation as per the
entitlement matrix for both physically
and economically affected persons.
7 Land based resettlement
strategy.
Not defined in LAA BLARRP provides for land-for-
land compensation only when
homestead land is being
acquired subject to a maximum
of 5 decimals of land.
Not defined for urban infrastructure
projects such as the investment
program (NRRP provides for land
for land option in case of land
development projects,
irrigation/hydel projects and for
Government policy does not adequately
provide for the land for land option.
The entitlement matrix of the
Resettlement Framework provides for
land for land compensation where
feasible. Attempt will be made to find
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
63
Sl.
No. ADB’s SPS (2009)
LAA BLARRP NRRP
Remarks
(Gaps between Government and ADB
policies and Action Taken in the
Resettlement Framework to Bridge
the Gap)
affected schedule tribe/caste
households).
alternate land to compensate for loss of
land if available, taking cognizance of
the concurrence of host community and
land value.
8 Compensation based on
principle of replacement
cost.
Not recognized by LAA BLARRP offers 95% of
guidance value as solatium,
while LAA gives only 30% as
solatium. BLARRP offers 85%
higher cash compensation than
the rate provided for by LAA, if
the affected person willingly
gives the land; however, it does
not provide for compensation at
replacement cost.
NRRP specifies that compensation
award shall take. into account the
market value of
the property being acquired,
including the location-wise
minimum price per unit area fixed
(or to be fixed) by the state
government. It also requires
conversion to the intended category
of use of the land being acquired
(for example, from agricultural to
non-agricultural) to be taken into
account in advance of the
acquisition, and the compensation
award to be determined as per the
intended land use category. (NRRP
explicitly provides for replacement
cost of land only for irrigation/hydel
projects, if suitable land for land
compensation cannot be given.)
Government policy does not provide for
compensation at replacement cost.
Where there are differences in the
valuation of land and prices of affected
assets, ADB prescribes the use of
current market rates in the project area.
The Resettlement Framework addresses
all these issues and spells out a
mechanism to fix the replacement cost
by a Valuation Committee that will be
responsible for deciding the replacement
costs.
9 Provide relocation
assistance to displaced
persons.
Not recognized by LAA BLARRP provides for
transitional assistance in the
form of one-time assistance for
temporary accommodation
(Rs10,000) and one-time
transportation assistance
(Rs5,000) to affected persons
losing homestead land.
BLARRP also provides for 0.5%
of site value up to a maximum of
Rs2 lakhs towards
resettlement/relocation costs, if
requested by the landowner.
NRRP provides for financial
support, transportation costs,
temporary and transitional
accommodation to displaced
persons.
The entitlement matrix in the
investment program’s Resettlement
Framework defines the eligibility and
entitlement for relocation of the affected
persons through relocation assistance
which includes shifting allowances,
right to salvage materials and additional
transitional assistance for the loss of
business and employment.
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
64
Sl.
No. ADB’s SPS (2009)
LAA BLARRP NRRP
Remarks
(Gaps between Government and ADB
policies and Action Taken in the
Resettlement Framework to Bridge
the Gap)
10 Ensure that displaced
persons without titles to
land or any recognizable
legal rights to land are
eligible for resettlement
assistance and
compensation for loss of
non-land assets.
Not defined by LAA. Not defined by BLARRP NRRP recognizes non-titleholders
as eligible affected persons only if
they have been residing or engaged
in any trade, business, occupation or
vocation at the location continuously
for a period of not less than three
years.
This is a drawback of national
law/policy compared to that of ADB.
The process for verification of impacts
and establishing the eligibility of
different categories of affected persons
(including non-titled affected persons) is
outlined in the Resettlement
Framework. The Entitlement Matrix
provides for compensation to all
affected persons whether physically or
economically displaced irrespective of
their legal status. The date of the census
survey will be considered as the cut-off
date and affected persons listed on the
cut-off-date will be eligible for
assistance.
11 Safeguarding needs of
vulnerable groups.
Not defined in LAA Landless agricultural laborer
working for >3 years on an
affected property is the only
category of vulnerability
recognized and provided for
under BLARRP.
NPRR recognizes the need for
protecting the weaker sections of the
society especially members of the
scheduled castes and scheduled
tribes. NPRR gives special provision
for providing life-time monthly
pension to the vulnerable persons. It
also gives preference to schedule
tribes and scheduled castes in land-
for-land compensation.
12 Disclose the
Resettlement Plan,
including
documentation of the
consultation in an
accessible place and a
form and language(s)
understandable to
affected persons and
other stakeholders.
Not defined in LAA Not defined in BLARRP NPRR provides for mandatory
dissemination of information on
displacement, rehabilitation and
resettlement and meaningful
consultations with the affected
communities at each stage,
including public hearings in the
affected areas.
LAA and BLARRP do not provide for
disclosure.
The investment program’s Resettlement
Framework ensures that the
Resettlement Plan along with the
necessary eligibility and entitlement will
be disclosed to the affected persons in
the local language (Hindi/Urdu) in the
relevant project locations and concerned
government offices and the same
Resettlement Plan will also be disclosed
in the websites of the EA and ADB.
13 Conceive and execute No provision for Full involuntary resettlement Addressed in NRRP, however, Though BLARRP and NRRP consider
Section 6.1 – Scope of Services
Annex D – Draft Resettlement Plan
65
Sl.
No. ADB’s SPS (2009)
LAA BLARRP NRRP
Remarks
(Gaps between Government and ADB
policies and Action Taken in the
Resettlement Framework to Bridge
the Gap)
involuntary resettlement
as part of a development
project or program.
Include the full costs of
resettlement in the
presentation of project’s
costs and benefits.
resettlement planning as
part of a development
program or for
involuntary resettlement
costs to be considered.
costs not considered. consideration of “full cost of
resettlement” not specified.
transitional and transport costs etc., they
do not provide for full resettlement costs
to be met.
The Resettlement Framework provides
eligibility to both titleholders and non-
titleholders with compensation and
various kinds of assistance as part of the
resettlement package; the full cost thus
becomes part of the project cost.
14 Pay compensation and
provide other
resettlement
entitlements before
physical or economic
displacement.
Not defined under LAA. Not defined under BLARRP. NRRP specifies that full payment of
compensation as
well as adequate progress in
resettlement shall be ensured in
advance of the actual displacement
of the affected families.
The Resettlement Framework stipulates
that all land acquisition should be
completed before relocation and all land
required is to be handed over free of
encumbrances to the Contractor.
15 Monitor and assess
resettlement outcomes,
their impacts on the
standards of living of
displaced persons.
Not defined under LAA. Not defined under BLARRP. NPRR stipulates the formation of a
National Rehabilitation Commission
to be set up by the Central
Government, to exercise
independent oversight over the
rehabilitation and resettlement of the
affected families.
NPRR has also made provisions for
a National Monitoring Committee, a
National Monitoring Cell and
Oversight Committees in the
ministries/departments concerned
for each major project to monitor
project implementation.
NRRP provides only for monitoring
while the project is being
implemented and not for assessment
of resettlement outcomes.
The Resettlement Framework has
detailed provision for a monitoring
system. The EAthrough the PMU will
be responsible for proper monitoring of
Resettlement Plan implementation and
internal monitoring. Verification by an
external expert is provided for in case of
Category A projects.
The Resettlement Framework details the
process of continuous monitoring and
reporting of Resettlement Plan
activities.
ADB = Asian Development Bank, BLARRP = Bihar Land Acquisition and Resettlement Policy, CLO = Community Liaison Officer, GRM = Grievance Redress Mechanism, LAA =
Land Acquisition Act, NRRP = National Rehabilitation and Resettlement Policy, SPS = Safeguards Policy Statement.