Increasing Energy Efficiency at the Allegan WWTP

MWEA/AWWA Joint Annual Conference

August 19, 2010

Page 2: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010
Page 3: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Project Background

Current treatment plant built in the early 70’s

Headworks, manual 1 ½” bar screen, grit removal system has not been operation for 25 years.

Freezing at headworks during winter months.

Page 4: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Project Background

Aeration basin 2 inoperable due to failed air header, failing air header and extensive weed growth the in grit and sludge in basin.

Fine bubble diffuser in aeration basins and underground sludge storage tank added in 1992

Aeration basin 3 and clarifier added in 1995 for addition BOD capacity.

Page 5: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Project Background

(3) 150Hp Hoffman blowers for 3 aeration basins.

No auto controls on blowers to track D.O.

Blowers and motors were in needed new bearings.

Aeration basin 3 utilized existing blower designed for basin 1/3 its size.

(2) 75hp centrifugal blowers were used on the aerobic digester, no timer or automated controls.

Page 6: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Project Background

Centrifugal wasting pumps held together with wooden wedges, pumped 50gpm above rated capacity.

Centrifugal sludge transfer pumps were unable to move thickened sludge over 3% solids.

Significant Industrial flow from Perrigo Corporation with no pretreatment other than pH adjustment.

Page 7: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Project Goals/Constraints

Rehabilitate/replace existing process equipment Modify/improve activated sludge process to

improve performance, increase efficiency and add organic treatment capacity for Perrigo

Accomplish improvements on existing site which is surrounded by floodplain, old municipal dump and Rockwell Superfund site (utilize existing tankage or build structures primarily above grade).

Page 8: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Aeration Energy Efficiencies

1. Diffusers Replaced fine bubble

diffusers with new, more efficient diffusers in aeration basins 1 and 2.

Page 9: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Aeration Energy Efficiencies

Energy Savings from Diffuser Replacement

Page 10: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Aeration Energy Efficiencies

Energy Savings from Diffuser Replacement

Page 11: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Aeration Energy Efficiencies

Energy Savings from Diffuser Replacement

Page 12: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Aeration Energy Efficiencies

2. Sensors Dissolved oxygen sensors were installed at the

end of aeration tanks 1 and 2 to provide automatic feedback/control of blower inlet valves based on operator set D.O. control point.

Page 13: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Aeration Energy Efficiencies

Design Point: 114 HP

Operating Point: 70 HP

Energy Savings from Automatic Blower Control Savings of just over $5,000/yr for every 10 HP reduced

Page 14: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Aeration Energy Efficiencies

3. Biological Nitrogen Removal If nitrification is occurring in the aeration basins,

nitrates (NO3) can be returned to the anoxic zone (no or low dissolved oxygen).

Bugs utilize oxygen in nitrates. Nitrogen (N2) is released as a gas and oxygen needs

are reduced in aeration basin.

Page 15: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Aeration Energy Efficiencies

Basin configuration made returning nitrates very simple, and anoxic zone was already in place due to new divider wall.

External carbon source is sometimes required (in addition to raw sewage) for de-nitrification reaction to be optimal.

Page 16: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Aeration Energy Efficiencies

We may not optimize this process, just get some added benefit at a low up-front cost.

After system is more fully loaded will test BNR process to determine if further optimization is desired.

Page 17: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Septage/Treatment Energy Efficiency

Mix septage in aerated tank with waste-activated sludge.

Pump contents to sludge storage tank.

Decant from sludge tank back to liquid end of plant is treated in liquid process.

Load to the aeration system is reduced due to less flow and lower organic loading.

Page 18: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Septage/Treatment Energy Efficiency

Energy Savings from Septage Treatment System Sludge Decant: 140 mg/l CBOD Septage: 4,550 mg/l CBOD Estimated Annual Septage: 3,000,000 gallons

Page 19: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Miscellaneous Efficiencies

Biological phosphorus removal system results in less sludge produced (less chemical deliveries).

Automatic flow control system for high flows routes flows to either the EQ tank or aeration tank 3 (standby tank) to maintain treatment efficiency of main treatment tanks.

Page 20: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Miscellaneous Efficiencies

New Headworks ¼” automatic fine screen Self-cleaning wet well High efficiency grit removal

Page 21: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Miscellaneous Efficiencies

New clarifiers with energy dissipating influent well and stamford baffles

New RAS pumps with VFDs

Page 22: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Miscellaneous Efficiencies

Replaced gaseous chlorine disinfection system with Ultraviolet Disinfection (no more chlorine gas or sodium bisulfite deliveries).

Page 23: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Building Systems Efficiencies

New natural gas fed Pulse Boiler Indoor lighting

Replaced all fluorescent bulbs (T12 to T8) Occupancy sensors installed in new areas of building Option to control multiple bulbs in each fixture

Outdoor lighting Replace mercury vapor lights with 2 stage induction

lighting with motion detector (10 pole mounted fixtures)

Page 24: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Treatment Results

Average effluent results: CBOD: 8 mg/l SS: 17 mg/l T. Phos. .6 mg/l

Septage receiving: 250,000 gallons per month CBOD: 4,500 mg/l SS: 20,000 mg/l

Decant from aerated sludge storage: CBOD: 140 mg/l SS: 218 mg/l

Page 25: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Operational Efficiencies

New SCADA system provides full automation of plant Automatic sludge wasting Automatic sludge pumping PD Sludge Blower control UV control pacing Automated headworks (fine screen control, grit collection, raw

sewage pumps)

Personnel requirements More duties (e.g. septage operation), less personnel 1990’s: total of 5 staff Present: total of 3 (possibly 4) staff

Page 26: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Original POTW Found

The wastewater plant that was built in the 1930’s was located during construction.

It was supposed to have been removed and filled.

Page 27: Increasing Energy Efficiency at the Allegan WWTP MWEA/AWWA Joint Annual Conference August 19, 2010

Increasing Energy Efficiency at the Allegan WWTP

MWEA/AWWA Joint Annual Conference

August 19, 2010